crookwell 3 wind farm planning review june 2019 · raised by thepac, which resulted in crookwell...
TRANSCRIPT
/Volumes/Company Share/Mersonn/Projects/2019 Projects/219061 Crookwell Windfarm (appeal)/Planning
Review/Crookwell3Planning review.doc.docx
Crookwel l 3 Wind Farm
Planning Review
June 2019
Mersonn Pty Ltd
6/20 Wylde Street
Potts Point NSW 2011
2
Contents
1.0 Introduct ion 3
2.0 Response to DPE assert ion that the Wind Farm would resul t in
unacceptable impacts on the landscape character and signi f icant
landscape features. 9
3.0 Response to DPE assert ion that the Wind Farm would resul t in
unacceptable direct and cumulat ive visual impacts on residences,
publ ic viewpoints and the surrounding landscape.
17
4.0 Response to DPE assert ion that the Wind Farm is not consistent with the current land use zoning provisions.
22
5.0 Response to DPE assert ion that the major i ty of submissions from
residences in the local area object to the project and Upper Lachlan
Shire Counci l maintains residual concerns about the impacts of the of
the Wind Farm. 28
6.0 Conclusion 30
3
1.0 Introduction
Andrew Darroch, Consultant Planner, has been retained by Crookwel l Developments Pty Ltd, a subsidiary of Global Power Generat ion
Austral ia Pty Ltd (GPG), to review the development appl icat ion for the
Crookwel l 3 Wind Farm current ly before the Independent Planning
Commission ( IPC) with a recommendation by the Department of
Environment and Planning (DPE) for refusal .
My br ief f rom Herbert Smith Freehi l ls Lawyers is to prepare an
independent town planning expert report addressing any town planning issues in connect ion with the proposed Wind Farm for considerat ion.
This report has been prepared in accordance with Division 2 of Pt 31 of
the Uniform Civi l Procedure Rules (UCPR) and the Expert Witness Code
of Conduct in Schedule 7 of the UCPR. I have read the Court ’s
Conference of Expert Witness Pol icy and Joint Expert Report Pol icy
(both commencing on 12 June 2015) and agree to be bound by them. This report has been carr ied out in accordance with the Code of
Conduct and the requirements of Divis ion 2 of Part 31 of the UCPR.
The Expert declares that he has made al l the inquir ies which he
bel ieves are desirable and appropriate (save for any matters ident i f ied
expl ic i t ly in this report) , and that no matters of signi f icance which the
Expert regard as relevant have, to the knowledge of the Expert , been
withheld. The plans and documents rel ied on in the preparat ion of this report are those ident i f ied below:
• Environmental Impact Statement (Mecone) dated July 2012;
• Landscape and Visual Impact Assessment (Green Bean Design)
dated July 2012;
• Visual Amenity Review (O’Hanlon Design) dated August 2013;
• Response to Submissions (Crookwel l Developments) dated
March 2014;
• Recommended Instrument of Consent dated 2015
• Secretary’s Environmental Assessment Report dated February
2015;
4
• Addendum Environmental Impact Statement (Mecone) dated September 2016;
• Addendum Landscape and Visual Impact Assessment (Green
Bean Design) dated June 2016;
• Addendum Response to Submissions (Crookwel l Developments)
dated February 2018;
• Department of Planning and Environment Assessment Report
Apri l 2019;
• Addendum Visual Amenity Review (O’Hanlon Design) dated July
2018;
The proposed Wind Farm is located approximately 17 ki lometres south-
east of Crookwel l and 25 ki lometres north-west of Goulburn, in the
Upper Lachlan Shire Local Government Area.
The Wind Farm would cover approximately 1,500 hectares adjacent to
Global Power Generat ion Austral ia Pty Ltd’s (of which Crookwel l is a
whol ly owned subsidiary) Crookwel l 2 Wind Farm (32 turbines, up to 160m in height) , which is completed and operat ional. The operat ional
Crookwel l 1 Wind Farm (8 turbines, up to 45m in height) and Gul len
Range Wind Farm (73 turbines, up to 135 m in height) are located
approximately 5 ki lometres north-west and 10 ki lometres west
respect ively.
On 17 March 2010, Crookwel l lodged major project appl icat ion 10_0034,
seeking approval under the former Part 3A of the Environmental Planning and Assessment Act 1979 (EP&A Act) to construct and operate
the Wind Farm . A prel iminary environmental assessment dated 12
February 2010 was prepared in connect ion with the Appl icat ion. An
Environmental Impact Statement (EIS) dated July 2012 was also lodged
with the DPE. A visual amenity review was conducted in August 2013.
The Appl icat ion was exhibi ted from November 2012 to February 2013.
Fol lowing exhibi t ion, Crookwel l submit ted i ts response to submissions dated March 2014 which reduced the number of turbines from 30 to 29.
5
The DPE completed i ts assessment of the Appl icat ion in February 2015
and referred the appl icat ion to the then Planning Assessment
Commission (PAC). Fol lowing i ts review of the appl icat ion and a publ ic meet ing on 17 March 2015, the PAC referred the Appl icat ion back to the
DPE for further assessment. The PAC raised a number of issues in
relat ion to the Appl icat ion including visual and noise impacts and lack
of certainty regarding proposed agreements with affected landowners
amongst other things.
The DPE then requested Crookwel l to provide a response to the issues
raised by the PAC, which resul ted in Crookwel l submit t ing an Addendum Environmental Impact Statement (Addendum EIS) dated September
2016. The Addendum EIS reduced the number of turbines from 29 to 23,
increased the maximum turbine envelope and increased the maximum
t ip height f rom 152 metres to 157 metres.
The DPE exhibi ted the Addendum EIS from October to November 2016.
Crookwel l submit ted an addendum response to submissions in February 2018.
On 18 Apri l 2019, the DPE recommended to the Independent Planning
Commission ( IPC) that i t refuse the Appl icat ion. The key reasons for
DPE’s recommendation are summarised below.
(a) The Wind Farm would resul t in unacceptable impacts on the
landscape character and signi f icant landscape features.
The DPE considers that the project would have an unacceptable
impact on the broader landscape due to cumulat ive impacts with
other wind farms and impacts on key landscape features in the
immediate vic ini ty of the Wind Farm. In part icular, the
Appl icat ion involves instal lat ion of turbines in two clusters on
elevated r idges on both sides of the Crookwel l 2 Wind Farm and the main road in Crookwel l f rom Goulburn. Combined with
Crookwel l 2, this would resul t in turbines covering an arc
extending more than 10km along the main r idgel ine on
6
the approaches to Crookwel l . Overal l , the DPE considers the
local landscape has l imited capaci ty to absorb further change
from wind farm projects, and the part icular locat ion and layout of the project would resul t in mater ial impacts on the local
landscape values and features.
(b) The Wind Farm would resul t in unacceptable direct and
cumulat ive visual impacts on residences, publ ic viewpoints and
the surrounding landscape.
The proposed Wind Farm turbines are located in close proximity to resident ial dwel l ings with 17 of the 23 proposed turbines
(represent ing 74%) located within 2.1km of non-associated
residences. The local topography and the proximity of the project
to the Crookwel l 2 Wind Farm also contr ibutes to visual
dominance and cumulat ive visual impacts on nearby residences.
The DPE considers that there would be at least 27 non-associated residences that would experience moderate/high or
high visual impacts as a resul t of the project.
The relat ively short setback of residences from project turbines
(1.1km to 3.4km) is a signi f icant contr ibut ing factor to the
moderate-high and high impact rat ings for 19 of these
residences. Whi le the other 8 residences are further from the
proposed turbines they would be subject to a signi f icant cumulat ive impact, wi th turbines affect ing up to 180 degrees of
the viewshed of these residences.
(c) The Wind Farm is not consistent with the current land use
zoning provisions.
The DPE noted that 70% of the turbines (al l of the eastern cluster) are prohibi ted under the current Local Environmental
Plan as they are located in an E3 Environmental Management
Zone. Whi le i t is st i l l open to the Commission to grant consent,
the Department does not consider that the project is consistent
7
wi th the object ives of the E3- Environmental Management zone
or that the bef i ts of the project are so signi f icant or essent ial to
the State that the consent author i ty should overr ide the current strategic planning intent ions for this port ion of the state.
The DPE also noted that the State Environmental Planning Pol icy
( Infrastructure) 2007 only makes electr ic i ty generat ing works
permissible with consent in prescr ibed rural , industr ial or special
use zones, and does not overr ide local planning controls within
environmental zones.
(d) The major i ty of submissions from residences in the local area
object to the project and Upper Lachlan Shire Counci l maintains
residual concerns about the impacts of the of the Wind Farm.
In addit ion to the above matters, the DPE considered the ful l
range of potent ial impacts associated with the Appl icat ion. The
DPE considers that the major i ty of these matters could be managed or condit ioned should the Appl icat ion be approved.
I inspected the si te on 24 May 2019 with part icular at tent ion to
Crookwel l – Goulburn Road, Woodhouselee Road, St Stephens Road,
Pejar Road, Elmgrove Road, Dawsons Creek Road, Middle Arm Road
and the associated and non-associated dwel l ings. I inspected the State
Heri tage l isted St Stephens Church and Pejar Dam, with part icular
at tent ion to the boat launching ramp and publ ic recreat ion area of the lat ter.
On 4 June 2019, the proponent wrote to the IPC offer ing to delete the
southern cluster of 6 turbines from the proposal in the interest of
addressing the concerns raised by the DPE in i ts report 18 Apri l
2019.(Attachment A) The proponent conf i rmed in i ts correspondence
that whi le reducing the total number of turbines from 23 to 17, i t would not make any “corresponding reduct ion in our commitment to the
community and funding better community outcomes through the
Voluntary Planning Agreement (VPA) already agreed with the Counci l . ”
The proponent wrote to Upper Lachlan Shire Counci l on 27 May 2019
8
out l in ing the delet ion of the southern cluster of 6 turbines and
conf i rming their commitment to the community and funding better
community outcomes through the VPA.(Attachment B)
I t is noted that the delet ion of the southern cluster comprising proposed
turbines A28, A29, A30, A31, A32 and A33 would reduce the visual
extent of the proposed wind farm; el iminate the second cable crossing
of Crookwel l Road; reduce TV and radio interference as this cluster is
in between Crookwel l and Goulburn; el iminate the visual impact to Pejar
Creek Dam recreat ional area and el iminate the visual impact for non-
associated dwel l ings at Narangl (n8) and Wombat Hol low (n19).
The proponent also undertook to cont inue engagements with the
remaining 3 non-associated dwel l ings within 2km of the proposed
turbines; to establ ish neighbour agreements or where they cannot be
entered into, of fer acquisi t ion for fair market value.
The proponent has also conf i rmed through correspondence from energy retai ler that negot iat ions for an off- take agreement are f inal ized. The
remaining eastern cluster of seventeen turbines is cr i t ical to the
economic viabi l i ty of the project. The commercial terms of that
agreement mandate approval of the eastern cluster of turbines. The
qual i ty of the wind resource of the eastern turbines in comparison to the
6 southern turbines, together with the proximity to the exist ing gr id
connect ion infrastructure (33/330kV electr ical substat ion) make them
cr i t ical to the agreement and to del iver ing a renewable energy resource to contr ibute to meet ing the Renewable Energy Target (RET).
9
2.0 Response to DPE assertion that the Wind Farm would result in unacceptable impacts on the landscape character and significant landscape features
2.1 The locality has been identif ied as a desirable area for wind energy generation
The NSW Wind At las incorporated into the Upper Lachlan Val ley
Strategy Vision 2020 at p174 denotes Crookwel l 1 with a “B” and clear ly shows from the colour contours why this local i ty is desirable for wind
farms.
I t is important to consider that the Upper Lachlan Val ley Strategy Vision
2020 states i ts purpose as:
The Upper Lachlan Strategy wi l l be used as the basis for preparat ion of
a comprehensive local environmental plan for Upper Lachlan. The
Strategy wi l l also provide the necessary strategic framework to guide
planning and land use decisions and outcomes to the year 2020. The
future Upper Lachlan Local Environmental Plan wi l l replace the three
current local environmental plans that apply to the Counci l area.1
The Upper Lachlan Val ley Strategy Vision 2020 was adopted by Upper Lachlan Shire Counci l and informed the making of Upper Lachlan Local
Environmental Plan 2010 and Upper Lachlan Development Control Plan
2010.
The Upper Lachlan Val ley Strategy Vision 2020 p174 goes on to note
Few areas across NSW that are located away from the sensitive coastal areas generate similar wind capacity to areas within Upper Lachlan.2
1 Parsons Brinckerhof op. cit. p1 2 Parsons Brinckerhof op. cit. p174
10
NSW Wind At las
Source: Upper Lachlan Val ley Strategy Vision 2009
2.2 Wind turbines have a l imited l i fespan and do not impact permanently on the landscape
The local i ty accommodates Austral ia’s f i rst gr id-connected wind farm,
Crookwel l 1, which commenced operat ion in 1998, over 20 years ago.3
I t is commonly accepted within the Wind Generat ion Industry that the l i fe expectancy of a wind farm is 20 – 25 years.4 Consequent ly, one
must consider that the longevi ty of Crookwel l 1 is l imited. Furthermore,
that wind farms in this landscape are not a stat ic or permanent element
but have a l imited l i fe span and on complet ion of their commercial l i fe
the wi l l be removed and the land rehabi l i tated.
The Upper Lachlan Val ley Strategy Vision 2009 p175 notes,
3 Parsons Brinckerhof Upper Lachlan Valley Strategy Vision 2009 p174 4 Pers. Comm. G. Alonso Crookwell Developments 2019
11
The Crookwel l I I Wind Farm is one of the largest wind farms approved
in NSW to date and is reported to be worth $175 mi l l ion. The proposal
was for 46 wind turbines which would create a total generat ion capaci ty
of 92 MW of clean green power. This would generate enough electr ic i ty
for 40,000 households and would avoid emit t ing 228,000 tonnes of
harmful green house gases. 5
Simi lar ly, whi le Gul len Range is vis ible within the local i ty, at a distance
of approximately 10 ki lometers, i t became ful ly operat ional on 23
December 20146 and is l ikely to have a 20 - 25 year l i fe. The Director-
General ’s Environmental Assessment Report dated March 2009 states
(p 5): “The turbines have an expected economic l i fe of 20-30 years after
which they would be removed from the si te, or recommissioned.”
2.3 The full complement of the approval is often not realised We are now aware that Crookwel l 2 was in fact approved with 32
turbines (a 33% reduct ion) and is operat ional wi th 28 turbines and is
unl ikely to real ize the remaining 4 turbines because of i ts commercial
of f- take agreement. The operator est imates the commercial l i fe of
Crookwel l 2 as 20 – 25 years.
2.4 The technology improvements in newer turbines means they have less visual impact than in older turbines While Crookwel l 2, Gul len Range and the proposal for Crookwel l 3 have
turbine t ip heights in the 135m – 160m range; Crookwel l 1 has a turbine
t ip height of 67m. This di f ference is apparent in viewing the landscape,
part icular ly f rom the Crookwel l Wind Farm Viewing Point just north of Elmgrove Road, where the shorter rotors on the Crookwel l 1 turbines
are perceived as turning much faster and are more l ikely to draw the
eye than the apparent ly slower turning rotors of Crookwel l 2 and Gul len
Range instal lat ions. I t is considered, in my opinion, that these more
recent instal lat ions in Crookwel l 2 and Gul len Range have a more
5 Parsons Brinckerhof op. cit. p175 6 Gullen Range Wind Farm website, https://gullenrangewindfarm.com/the-project/about-the-project/.
12
calming and compatible presentat ion in the landscape.
2.5 Impact on the broader character and the test in Taralga
I t is considered that each of these three considerat ions set out above,
namely:
1. the l imited l i fespan of the windfarms;
2. that the ful l complement of the approval is of ten not real ised;
3. and that the tal ler rotors are perceived as having a slower
motion;
al l require considerat ion and weight in any assessment of the impact
upon the broader landscape and the cumulat ive impacts with other wind
farms in the vicini ty and the capaci ty of the local landscape to absorb
further change. I t must be acknowledged that change must occur in the
short to medium term with Crookwel l 1 reaching the end of i ts l i fe.
Furthermore, considerat ion should be afforded the character of the
local i ty, which must undeniably be character ized as an attract ive rural
landscape with wind turbines fol lowing the r idgel ines. This is apparent
as one travels on the Crookwel l -Goulburn Road and Woodhouselee
Road. The quest ion can no longer be whether the insert ion of
windfarms into a rural landscape involves interrupt ing the rural and
natural cohesion of that landscape or whether or not a f i rst “breach” in
the present general landscape should be permit ted, as considered by the Chief Judge in Taralga Landscape Guardians Inc v Minister for
Planning and RES Southern Cross Pty Ltd [2007] NSWLEC 59
(Taralga).7
Preston CJ cont inues that, once such a breach is permit ted, i t is then
relevant to turn to whether or not the extent of i t should be l imited, as a
general quest ion, and also to turn to the quest ion of the impacts on
individual propert ies.8
7 Taralga Landscape Guardians Inc v Minister for Planning and RES Southern Cross Pty Ltd [2007] NSWLEC 59 para 124 8 Ibid. para 124
13
In making this further assessment Preston CJ observes;
140 Moreover, I do not consider that the presence of turbines on only
one side of Bannaby Road but not the other is just i f iable on visual
impact grounds. There is nothing about their presence on one side of
the road which demands their absence on the other.
141 As earl ier noted, the Minister 's cone of viewing approach lacked
any rat ional just i f icat ion apart f rom having the effect of el iminat ing the
outer edges of the rows of turbines. There would remain, on this
approach, a broad sweep of turbines in the landscape only punctuated
by a minor break to the north of Row 10.
142 Nothing that was said in the visual assessment experts’ evidence
leads me to conclude that such marginal outer edge adjustment to the
proposal achieves any part icular benef i t for the vi l lage and i ts out look.
Whether or not the turbines at the northern or southern end of the
proposal should be deleted because of the impact on speci f ic propert ies
is a separate quest ion dealt wi th elsewhere.9
2.6 Applying the test in Taralga
Whi le the context considered in Taralga was somewhat di f ferent f rom
the current proposal , given the relat ionship of the proposed turbines to
the vi l lage of Taralga and that these were the f i rst insert ions into that landscape, his Honour’s observat ions are none-the- less considered
relevant.
The current proposal (as offered on 4 June 2019) is for the insert ion of
17 addit ional turbines, for a per iod of around 25 years, into a landscape
character ized as an attract ive rural landscape with wind turbines
fol lowing the r idgel ines, where al l of the exist ing turbines in that landscape have a short to medium l i fespan before each of the si tes wi l l
be rehabi l i tated as per their approvals and condit ions of consent.
9 Ibid. para 140-142
14
This considerat ion must then be balanced against the signi f icant publ ic
interest, in general terms, in adopt ion of al ternat ive, more environmental ly f r iendly, energy generat ion sources.
The Federal Government’s Renewable Energy Target (RET) of
33,000GWh by 2020 is ci ted in the Department of Planning and
Environment Assessment (DPE) Report Apri l 2019, where i t is est imated
that 5,400MW of new renewable energy capaci ty wi l l need to be bui l t by
2020 to achieve the RET.10 (The source for this stat ist ic is not
referenced in the report) . However, what the report fai ls to ment ion is that the RET has operated since 2001 and was reviewed by the
government in June 2015 and reduced from 41,000GWh to 33,000GWh
(a reduct ion of almost 20%) and that in 2017 less than hal f the reduced
target had been met.11 The proposal which is able to provide 96MW
would contr ibute 1.8% of the 5,400MW of renewable energy ci ted in
DPE Report as being required to be constructed before 2020 to meet
the RET.12 This must be seen as a substant ial contr ibut ion, part icular ly where the proposal ef f ic ient ly ut i l izes the Crookwel l 2 substat ion and
infrastructure and an off- take arrangement has been made (pending
development consent).13
The DPE Report notes at p17, that there are 15 other wind farms
operat ional and approved within the region (and nominates the region
as extending up to 85km from the si te). I t further notes that 8 are
within 30km, but provides no just i f icat ion for why a 30km radius is used. I t is hard to understand how wind farms at Gunning, Taralaga, Cul ler in
and Col lector have a bearing on those within the local i ty of the subject
proposal. The report goes on to note that 7,000MW of wind energy has
been approved in NSW (but provides no source for this stat ist ic)
The DPE Report acknowledges that there is a competi t ive market for
of f- take agreements into the Nat ional Electr ic i ty Market and there are
10 Depar tmen t o f P lann ing and Env i ronmen t Assessmen t Repor t Ap r i l 2019 p16 11 Clean Energy Council RET Newsletter 2018. 12 Ibid. DEP 2019 p16 13 Pers. Comm. G. Alonso Crookwell Developments 2019
15
emerging constraints on the electr ic i ty t ransmission network and that
many of these projects ( together with approved large scale solar
projects) may not proceed.14 The NSW Renewable Energy Act ion Plan 2013 is referenced and the DPE report suggests that i f al l large-scale
projects ( i t is not clar i f ied whether this is approved and proposed) are
developed there would be up to 16,600MW (7,000MW wind energy and
9,600MW solar) of addi t ional renewable energy generat ion in the NSW
energy system in the next 5 to 10 years.15 However, the DPE report
makes no mention of progress in achieving the 2020 target set in the
NSW Renewable Energy Act ion Plan.
On the basis of this level of demand in the effort to meet the adopted
Targets at State and Commonwealth level , the considerat ion of the
abi l i ty for the exist ing landscape which is already character ized by
windfarms, must be given appropriate weight.
This weight ing should also then be tempered by the three
considerat ions previously raised, namely:
1. the l imited l i fespan of the windfarms;
2. that the ful l complement of the approval is of ten not real ised;
3. and that the tal ler rotors are perceived as having a slower
motion;
This would provide a more dynamic frame of reference from which to
evaluate the acceptabi l i ty of the impacts on the landscape character and signi f icant landscape features of the proposed windfarm, rather
than the very stat ic approach which has been assumed by the DPE
assessment.
14 Ibid. DEP 2019 p17 15 Ibid. DEP 2019 p17
16
2.7 Conclusion as to why Crookwell 3 would not result in unacceptable impacts on the landscape character and significant landscape features
In essence, as one travels through the local i ty or one experiences i t
f rom signi f icant vantage points, the exist ing landscape character is of
at tract ive rural , pr imari ly grazing lands with the elevated r idges
accommodating extensive wind farms.
The Appl icat ion or iginal ly involved instal lat ion of turbines in two
clusters on elevated r idges on both sides of the Crookwel l 2 Wind Farm and the main road in Crookwel l f rom Goulburn and that combined with
Crookwel l 2, this would have resul ted in turbines covering an arc
extending more than 10km along the main r idgel ine on the approaches
to Crookwel l , this was consistent with the exist ing character of the
local i ty .
Whi le i t is acknowledged that to some persons this would be visual ly unattract ive, to others i t is an attract ive and reassuring landscape.
This is addressed by Preston CJ:
1 The insert ion of wind turbines into a non-industr ial landscape is
perceived by many as a radical change which confronts their present
real i ty. However, those percept ions come in di f fer ing hues. To
residents, such as members of Taralga Landscape Guardians Inc ( the
Guardians), the change is stark and negat ive. I t would represent a
bl ight and the confrontat ion is with their enjoyment of their rural sett ing.
2 To others, however, the change is posi t ive. I t would represent an
opportuni ty to shi f t f rom societal dependence on high emission fossi l
fuels to renewable energy sources. For them, the confrontat ion is
benef ic ial – being one much needed step in pol icy sett ings confront ing
carbon emissions and global warming.
3 Resolving this conundrum - the conf l ict between the geographical ly
narrower concerns of the Guardians and the broader publ ic good of
increasing the supply of renewable energy - has not been easy.
17
However, I have concluded that, on balance, the broader publ ic good
must prevai l . The reasons for doing so are set out in the body of this
judgment.16
Clear ly, the quest ion is rel ieved by the existence of wind farms in the
local i ty and their s igni f icant contr ibut ion to the exist ing landscape
character and signi f icant landscape features. I t is di f f icul t to
understand, given the dynamic frame of reference, how the project
would mater ial ly impact the local landscape values and features, when
they are already a signi f icant feature or the character and that their
numbers wax and wane over t ime and have a l imited l i fespan.
Furthermore, the arrangement of the turbines and the fact that views to
the turbines are relat ively contained to a (approximately) 10km sect ion
of the 40km journey between Goulburn and Crookwel l ensures that the
change to character ( t ransformation of pastoral to windfarm pastoral) is
a relat ively br ief experience and does l i t t le to diminish the overal l
character of the region.17
Furthermore, the delet ion of the southern cluster signi f icant ly reduces
the visual experience from Crookwel l Road.
I t is considered that the proposed Wind Farm would not resul t in
unacceptable impacts on the landscape character and signi f icant
landscape features for the reasons out l ined above .
16Taralga Landscape Guardians Inc v Minister for Planning and RES Southern Cross Pty Ltd [2007] NSWLEC 59 para 1-3 17 Pers. Comm. D. Moir, Moir Landscape Architecture 2019
18
3.0 Response to DPE assertion that the Wind Farm would result in unacceptable direct and cumulative visual impacts on residences, public viewpoints and the surrounding landscape.
3.1 Application of LEPs The appl icat ion for the proposed wind farm was lodged in March
2010. The Project is classi f ied as State Signi f icant
Development. As acknowledged in the DPE Report , at the t ime
of lodgment the land was zoned 1(a) General Rural under Crookwel l LEP 1994 and Mulwaree LEP 1995, the proposal is
permissible with development consent under both of these
instruments. Whi le the Upper Lachlan LEP 2010 has since
replaced these instruments, Clause 1.8A of Upper Lachlan LEP
2010 requires:
1.8A Savings provision relat ing to development appl icat ions
I f a development appl icat ion has been made before the
commencement of this Plan in relat ion to land to which
this Plan appl ies and the appl icat ion has not been f inal ly
determined before that commencement, the appl icat ion
must be determined as i f this Plan had not commenced.
Consequent ly, Upper Lachlan LEP 2010 is considered and given
weight as a draft and Crookwel l LEP 1994 and Mulwaree LEP 1995 are the prevai l ing instruments.
Simi lar ly, Upper Lachlan DCP 2010 was not in force at the t ime
of lodgment and as acknowledged by the DPE Report the Upper
Lachlan LEP 2010 does not apply to the development.18
18 Ibid. DEP 2019 p50
19
3.2 Distance from and impact on non-associated residences
I f the Upper Lachlan DCP 2010 were to apply, the DPE Report states that i t would “ include a requirement that no turbine is
located closer than 2km from a non-associated residence.”19 The
DCP requires:
f . Turbines shal l not be located within 2.0 ki lometres of any
dwel l ing not associated with the development or f rom any lot
upon which a dwel l ing may be constructed. The 2.0 ki lometre
setback proposes ut i l is ing a precaut ionary pr inciple in
addressing perceived visual and health concerns;
While this is acknowledged as not applying to the development
appl icat ion, i t is a signi f icant submission by Upper Lachlan
Counci l .
I t is noted that under the Secretary of the Environment Assessment Report 2015, 6 non-associated dwel l ings within 2
ki lometres of the si te where no agreement on mit igat ion could be
agreed the opt ion of land acquisi t ion by the proponent was
required.20
With the reconf igured turbine layout removing the southern
cluster of turbines (proposed 4 June 2019) there are current ly 5 non-associated dwel l ings within 2 ki lometres of a proposed
turbine. One of these dwel l ings (Meadowvale 1135
Woodhouselee Road) is current ly a host landowner for Crookwel l
2 and has been offered an addit ional neighbour agreement for
Crookwel l 3. A second dwel l ing, (Rosedale 3199 Middle Arm
Road) is located between 1.89km and 1.93km from the closest
proposed turbine, but the proponent is prepared to micro si te the
turbines to achieve the 2km separat ion.
19 Ibid. DEP 2019 p50 20 Sec re ta ry o f t he Env i ronmen t Assessmen t Repor t 2015 p46
20
This means that there are only three non-associated dwel l ings
with 2km of a proposed turbine.
Each of these dwel l ings have been offered neighbour agreements,
which have not as yet been accepted, and negot iat ions cont inue. The
proponent has committed to establ ishing neighbour agreements or
where they cannot be entered into, to of fer ing acquisi t ion of the
property for fair market value.
I t was and remains the proponent ’s posi t ion, that on fai lure to reach a
neighbour agreement with any owner of a dwel l ing within 2km of a proposed turbine, the opt ion of land acquisi t ion by the proponent at fair
market value is an acceptable outcome.
Simi lar ly, The Wind Energy: Visual Assessment Bul let in which was
released in 2016 is acknowledged as not apply to the subject
appl icat ion given that the Environmental Assessment requirements for
the project were issued some 5 – 6 years before i ts release. However, i t is noted that the Wind Energy: Visual Assessment Bul let in is relevant
because i t , s imi lar to the DCP also recommends a 2km separat ion
between non-associated dwel lngs and turbines.
However, i f the appl icants posi t ion that on fai lure to reach agreement
with any owner of a dwel l ing within 2km of a proposed turbine the
opt ion of land acquisi t ion by the proponent is an acceptable outcome is
adopted then the high impact rat ings under the Wind Energy: Visual Assessment Bul let in ci ted in the DPE report wi l l be signi f icant ly
reduced.
The DPE considers that there would be at least 27 non-associated
residences that would experience moderate/high or high visual impacts
as a resul t of the project.
The relat ively short setback of residences from project turbines (1.1km
to 3.4km) is a signi f icant contr ibut ing factor to the moderate-high and
high impact rat ings for 19 of these residences. Whi le the other 8
residences are further f rom the proposed turbines they would be subject
21
to a signi f icant cumulat ive impacts, wi th turbines affect ing up to 180
degrees of the viewshed of these residences.
The delet ion of the southern cluster and resolut ion of the non-
associated dwel l ings within 2km signi f icant ly reduces the number of
non-associated dwel l ings and the degree of impact on the dwel l ings.
This is covered in detai l in the Visual Impact Assessment by David Moir
of Moir Landscape Archi tecture.
Moir advises that the direct and cumulat ive impact upon nearby
residences is pr imari ly subject ive outside of the 2km range and to be direct ly discussed with “nearby” residences. The impact is largely
determined by the aspect and arrangement of individual residences,
their arr ival /departure points and key views and mit igat ion measures
and landscaping solut ions can be provided on a case by case basis.21
3.3 Impact on public viewpoints, significant features and the surrounding landscape
I t should be noted that proponent ’s of fer to remove the southern cluster
negates views impacts from Pajar Dam and the St Stephens Church
ent i rely, despi te the level of those impacts being considered
unacceptable.
Mr Moir further advises that whi le the Pejar Dam is a key landscape
feature within the Crookwel l Wind Farm viewshed, i t is a man-made dam commissioned in 1979 as part of Goulburn’s water supply infrastructure.
I t is one of three water storage faci l i t ies servicing the ci ty. The DPE
assessment, on the advice of OHD, refer to the Dam as being of high
scenic qual i ty. This is in contrast to the character assessment by GBD
which determined a “medium sensit iv i ty” rat ing to the Pejar Dam
character uni t . I t is noted that GBD appl ied an accepted methodology of
assessment of landscape character whereas OHD’s rat ing of the Pejar Dam appears to be based pr imari ly on opinion. I t is my opinion that the
assessment by GBD is accurate. Landscape character rat ings, whether
21 Pers. Comm. D. Moir, Moir Landscape Architecture 2019
22
they be based on “qual i ty” or “sensi t iv i ty” , must be appl ied consistent ly
across the country. A landscape feature such as Pejar Dam would be
descr ibed as moderate as, al though large bodies of water are general ly considered to be visual ly appeal ing, i t is not a natural feature, i ts
sett ing is amongst a highly modif ied, though attract ive, landscape, i t is
not part icular ly unique and i t is without signi f icant topographic or
geological features. In contrast, for example, the not too distant
Bungonia Gorge would be considered a High Qual i ty or Highly Sensi t ive
Landscape as i t is natural , unmodif ied, rare and r ich with signi f icant
topographic and geological features. In short , just because Pejar Dam
may be the most visual ly appeal ing element within this visual catchment does not make i t of High Qual i ty or Highly Sensi t ive.22
Furthermore, St Stephens Church is a State Listed Heri tage bui lding. I t
is not part icular ly vis ible as i t is a smal l stone church surrounded by a
very tal l hedge. I t may be a sensi t ive viewpoint considering the her i tage
aspects of the bui lding, i ts history and cul tural value however i t is not a
key landscape feature.23
Furthermore, the E3 Zone is not a landscape feature. The E3 Zone is
not def ined by any visual ly ident i f iable vegetat ion pattern, geological
formation, sett lement pattern or landform. As i t is not vis ibly
discernable the E3 Zone cannot be considered a landscape feature. 24
3.4 Cumulative impacts I refer back to my comments in sect ion 2.0 above, part icular ly,
how the visual impact of the proposed wind farm is rel ieved by the
existence of wind farms in the local i ty and their s igni f icant contr ibut ion
to the exist ing landscape character and signi f icant landscape features
and that their numbers wax and wane over t ime and have a l imited
l i fespan. Furthermore, the arrangement of the turbines and the fact
that views to the turbines are relat ively contained to a (approximately) 10km sect ion of the 40km journey between Goulburn and Crookwel l
22 Pers. Comm. D. Moir, Moir Landscape Architecture 2019 23 Pers. Comm. D. Moir, Moir Landscape Architecture 2019 24 Pers. Comm. D. Moir, Moir Landscape Architecture 2019
23
ensures that the change to character ( t ransformation of pastoral to
windfarm pastoral) is a relat ively br ief experience and does l i t t le to
diminish the overal l character of the region. I t is considered that the proposed Wind Farm would not resul t in unacceptable cumulat ive
impacts on the landscape character and signi f icant landscape features
for the reasons out l ined previously .
3.5 Conclusion as to why Crookwell 3 would not result in unacceptable direct and cumulative visual impacts on residences, public viewpoints and the surrounding landscape I t is considered, for these reasons, that the modif ied 17 turbine wind
farm would not resul t in unacceptable direct and cumulat ive visual
impacts on residences, publ ic viewpoints and the surrounding
landscape.
24
4.0 Response to DPE assertion that the Wind Farm is not consistent with the current land use zoning provisions. 4.1 Application of LEPs
At the t ime of lodgment the land was zoned 1(a) General Rural
under Crookwel l LEP 1994 and Mulwaree LEP 1995, the proposal
is permissible with development consent under both of these
instruments.
Whi le the Upper Lachlan LEP 2010 has since replaced these instruments, i t is considered and given weight as a draft and
Crookwel l LEP 1994 and Mulwaree LEP 1995 are the prevai l ing
instruments.
4.2 E3 Environmental Management Zoning relates only to water catchment and not to any special ecological, scientif ic, cultural or aesthetic values
I t is acknowledged in the DPE report that the zoning of a port ion
of the land as E3 Environmental Management Zone by Upper
Lachlan Counci l as i t relates to i ts locat ion within the catchment
of the Pejar Dam which is a dr inking water catchment dam for the
town of Goulburn.25 This can be seen from the photo below of
the information sign at the recreat ion area of the dam.
25 Ibid. DEP 2019 p50
25
Under the standard instrument, there are l imited opt ions when
deal ing with an exist ing rural area which is developed as grazing
land and exist ing windfarms on which zone to choose to manage
water qual i ty within a dr inking water catchment.
The land zoned E3 Environmental Management Zone closely co-
ordinates with the extent of the dr inking water catchment. This
can be seen from the Upper Lachlan LEP 2010 Zoning Map 5
inserted below. The E3 land is coloured orange and surrounded
26
by the l ighter RU1 land. I t is of s igni f icance that al l of the land
east of Crookwel l - Goulburn Road and extending beyond
Woodhouselee Road is zoned E3 Environmental Management Zone which means that 80% of the exist ing turbines in Crookwel l
2 are located on E3 Environmental Management zoned land.
I f this land were zoned RU1 Primary Product ion i t would permit
Industr ies, Open Cut Mining and other intensive land uses which
would not be compatible with the dr inking water catchment.
Upper Lachlan LEP 2010 Zoning Map 5
The object ives of the E3 Environmental Management Zone are:
1 Object ives of zone
• To protect, manage and restore areas with special ecological ,
scient i f ic, cul tural or aesthet ic values.
• To provide for a l imited range of development that does not
have an adverse effect on those values.
27
• To faci l i tate the management of environmental ly sensi t ive land
and areas of high environmental value to the local
government area.
An examinat ion of the Upper Lachlan Val ley Strategy Vision 2020
which we know informed the Upper Lachlan LEP 2010 makes no
mention and does not ident i fy any special ecological , scient i f ic,
cul tural or aesthet ic values in this land and we are only sure that
i t has been zoned in this way to protect the dr inking water
catchment of the town of Goulburn.
4.3 Wind farms are already accommodated within the E3 zone and water catchment. Potential impacts can be managed through appropriate conditions.
The E3 zone current ly accommodates Crookwel l 2 with 28
operat ional turbines which not only descr ibe the landscape
character in the E3 Environmental Management Zone in this local i ty but demonstrate that they can clear ly exist wi th no
signi f icant impact of the dr inking water catchment but also
contr ibut ing to the character of the local i ty rather than adversely
af fect ing those values.
I t is clear f rom the DPE report that the proposal can manage the
environmental ly sensi t ive land and the areas of high
environmental value to the local government area with a relat ively benign sui te of condit ions when one understands that
the sensi t iv i ty and values ar ise from the sensi t iv i ty and value of
the dr inking water catchment.
4.4 Applying the LEP considering its aims and objectives
In order to best understand an instrument i t needs to be read as a whole. In order to assess the weight to be given to the
object ives of the E3 zone one needs to consider the Aims of the
Plan and the object ives of comparable zones.
28
1.2 Aims of Plan
(1) This Plan aims to make local environmental planning
provisions for land in Upper Lachlan in accordance with the
relevant standard environmental planning instrument under
sect ion 33A of the Act.
(2) The part icular aims of this Plan are as fol lows:
(a) to provide planning controls for Upper Lachlan and to update
and consol idate into one instrument the var ious planning
controls that current ly apply to Upper Lachlan,
(b) to encourage the sustainable management, development and
conservat ion of natural resources,
(c) to promote the use of rural resources for agr icul ture and
pr imary product ion including f ishing, forestry, mining and
related processing, service and value adding industr ies,
(d) to protect and conserve the environmental and cul tural
her i tage of Upper Lachlan,
(e) to encourage new residents to Upper Lachlan by providing a
range of housing opportuni t ies in the main towns and vi l lages,
( f ) to al low development only i f i t occurs in a manner that
minimises r isks due to environmental hazards, and minimises
r isks to important elements of the physical environment,
including water qual i ty,
(g) to promote and coordinate the orderly and economic use and
development of land in Upper Lachlan,
(h) to protect and enhance watercourses, r ipar ian habitats,
wet lands and water qual i ty within Upper Lachlan’s dr inking
water catchments so as to enable the achievement of the
water qual i ty object ives.
The opening aim of the Upper Lachlan LEP 2010 Plan is to
encourage the sustainable management, development and
conservat ion of natural resources. This is the cornerstone of the
project in moving our energy economy from fossi l fuels to renewables.
The second aim is to promote the use of rural resources for
agr icul ture and pr imary product ion including f ishing, forestry,
29
mining and related processing, service and value adding
industr ies. Where we have one of New South Wales most
signi f icant wind resources and establ ished infrastructure this must be considered the most fundamental promotion of pr imary
product ion.
4.5 Conclusion as to why Crookwell 3 is consistent with the current land use zoning provisions (to the extent that they should be given weight as a draft instrument)
Li t t le needs to be said about the benef i ts of renewable energy sources in protect ing and conserving the environment of the
Upper Lachlan.
Simi lar ly, the proposal and the DPE report raises no signi f icant
concerns over the need to minimises r isks due to environmental
hazards, and minimises r isks to important elements of the
physical environment, including water qual i ty.
Where the exist ing wind farms, wind resources and infrastructure
are in place the proposal must be said to promote and
coordinate the orderly and economic use and development of
land in Upper Lachlan.
The DPE reports conf i rms that with a sui table sui te of operat ing
condit ions the proposal wi l l protect and enhance watercourses, r ipar ian habitats, wet lands and water qual i ty within Upper
Lachlan’s dr inking water catchments so as to enable the
achievement of the water qual i ty object ives.
Consequent ly, one must be sat isf ied that the proposal is
consistent with the aims of the Plan and that the aims and
object ives behind the zoning would be met in ful l wi th an appropriate publ ic benef i t and better planning outcome than the
do nothing opt ion.
30
Whi le the eastern turbines would be prohibi ted under the current
Local Environmental Plan as they are located in an E3
Environmental Management Zone i t is considered that the project is consistent with the Aims of the Plan and the object ives of the
E3- Environmental Management zone and that the benef i ts of the
project are so signi f icant and essent ial to the State that the
consent author i ty should support the proposal.
31
5.0 Response to DPE assertion that the majority of submissions from residences in the local area object to the project and Upper Lachlan Shire Council maintains residual concerns about the impacts of the of the Wind Farm.
5.1 Statistics demonstrate that a majority of submissions support Crookwell 3
The DPE report actual ly demonstrates qui te a di f ferent prof i le in
the submissions received. The DPE report states that of the 81
submissions from the general publ ic received, 32 objected to the project and 49 supported the project.26 This means in real terms
that in excess of 60% of the submissions supported the project.
I t cannot be disputed that this is a major i ty in favour of the
project.
Furthermore, in my 30 years of experience, i t is common that
submit ters are more often dr iven to respond when they are adversely af fected rather than when they perceive a more
general greater publ ic benef i t . Concerns over cl imate change
and fossi l fuel consumption within the community are wel l
understood.
I t is of interest that of the 81 submissions only 15 objectors l ived
within a 5km radius of the project. 27 This accounts for a l i t t le
over 18% of the submissions and could qui te l ikely be signi f icant ly reduced through the offer to acquire the propert ies
within 2km of the si te.
5.2 Council ’s residual concerns
The Upper Lachlan Shire Counci l ’s residual concerns about the
impacts of the of the Wind Farm are detai led in the DPE Report as:
26 Ibid. DEP 2019 p27 27 Ibid. DEP 2019 p27
32
· impacts of turbines within 2 km of a non-associated
residence and recommended those turbines be deleted;
· potent ial impacts on the local road network dur ing
construct ion of the project including the need for
signi f icant road upgrades pr ior to commencement of any
heavy vehicle haulage, part icular ly on
Woodhouselee Road;
· number of access points proposed for the eastern cluster
and recommendation that there should be only one
access point;
· number of cable crossings for Crookwel l Road and
recommendation that there should be only one cable
crossing; and
· potent ial for the proposed turbines to interfere with
television services in Crookwel l , impact ing up to 850
residences.28
However, the DPE acknowledges that in terms of the ful l range of potent ial impacts associated with the Appl icat ion, the major i ty of
these matters could be managed or condit ioned should the
Appl icat ion be approved and the appl icant accepts the necessary
condit ions to address each of these matters.
Further, i t is noted that the proponent has addressed these
residual concerns in discussions with the Counci l and resolved
them. (See let ter Attachment B)
28 Ibid. DEP 2019 p27
33
6.0 Conclusion
On 17 March 2010, the proponent lodged major project appl icat ion
10_0034, seeking approval under the former Part 3A of the
Environmental Planning and Assessment Act 1979 (EP&A Act) to
construct and operate the Wind Farm comprising 30 turbines.
The matter was considered by the PAC, which resul ted in Crookwel l
submit t ing an (Addendum EIS dated September 2016 which reduced the number of turbines from 29 to 23.
On 18 Apri l 2019, the DPE recommended to the IPC that i t refuse the
Appl icat ion. The key reasons for DPE’s recommendat ion are
summarised below.
(a) The Wind Farm would resul t in unacceptable impacts on the
landscape character and signi f icant landscape features.
(b) The Wind Farm would resul t in unacceptable direct and
cumulat ive visual impacts on residences, publ ic viewpoints and
the surrounding landscape.
(c) The Wind Farm is not consistent with the current land use
zoning provisions.
(d) The major i ty of submissions from residences in the local area
object to the project and Upper Lachlan Shire Counci l maintains
residual concerns about the impacts of the of the Wind Farm.
On 4 June 2019, the proponent wrote to the IPC offer ing to delete the
southern of addressing the concerns raised by the cluster of 6 turbines from the proposal in the interest of addressing the concerns raised by
the DPE in i ts report 18 Apri l 2019. The proponent conf i rmed in i ts
correspondence that whi le reducing the total number of turbines from
23 to 17, i t would not make any “corresponding reduct ion in our
34
commitment to the community and funding better community outcomes
through the Voluntary Planning Agreement (VPA) already agreed with
the Counci l . ” The proponent wrote to Upper Lachlan Shire Counci l on 27 May 2019 out l ining the delet ion of the southern cluster of 6 turbines
and conf i rming their commitment to the community and funding better
community outcomes through the VPA and resolving Counci l ’s residual
concerns.
I t is noted that the delet ion of the southern cluster comprising proposed
turbines A28, A29, A30, A31, A32 and A33 would reduce the visual
extent of the proposed wind farm; el iminate the second cable crossing of Crookwel l Road; reduce TV and radio interference as this cluster is
in between Crookwel l and Goulburn; el iminate the visual impact to Pejar
Creek Dam recreat ional area and el iminate the visual impact for non-
associated dwel l ings at Narangl (n8) and Wombat Hol low (n19).
The proponent also undertook to cont inue engagements with the
remaining 3 non-associated dwel l ings within 2km of the proposed turbines; to establ ish neighbour agreements or where they cannot be
entered into, of fer acquisi t ion for fair market value.
The proponent has also conf i rmed through correspondence from the
energy retai ler that negot iat ions for an off- take agreement are f inal ized.
The remaining eastern cluster of seventeen turbines are cr i t ical to the
economic viabi l i ty of the project. The commercial terms of that
agreement mandate approval of the 17 eastern turbines. The qual i ty of the wind resource of the eastern cluster of turbines in comparison to
the 6 southern turbines, together with the proximity to the exist ing gr id
connect ion infrastructure (33/330kV electr ical substat ion) make them
cr i t ical to the agreement and to del iver ing a renewable energy resource
to contr ibute to meet ing the Renewable Energy Target (RET).
The visual impact of the proposed wind farm is rel ieved by the existence of wind farms in the local i ty and their s igni f icant contr ibut ion
to the exist ing landscape character and signi f icant landscape features
and that their numbers wax and wane over t ime and have a l imited
l i fespan. Furthermore, the arrangement of the turbines and the fact
35
that views to the turbines are relat ively contained to a (approximately)
10km sect ion of the 40km journey between Goulburn and Crookwel l
ensures that the change to character ( t ransformation of pastoral to windfarm pastoral) is a relat ively br ief experience and does l i t t le to
diminish the overal l character of the region. I t is considered that the
proposed Wind Farm would not resul t in unacceptable impacts on the
landscape character and signi f icant landscape features for the reasons
out l ined above .
I t is considered, that the modif ied 17 turbine wind farm would not resul t
in unacceptable direct and cumulat ive visual impacts on residences, publ ic viewpoints and the surrounding landscape.
Whi le the eastern turbines would be prohibi ted under the current Local
Environmental Plan as they are located in an E3 Environmental
Management Zone, i t should be noted that the 2010 LEP only appl ies to
the assessment of the development appl icat ion as a draft . Al l of the
turbines were permissible with consent under the zoning that appl ied in the instruments that were current at the t ime the appl icat ion was
submit ted. However, even to the extent that the 2010 LEP appl ies, i t is
considered that the project is consistent with the Aims of the Plan and
the object ives of the E3- Environmental Management zone and that the
benef i ts of the project are so signi f icant and essent ial to the State that
the consent author i ty should support the proposal.
The DPE acknowledges that in terms of the ful l range of potent ial impacts associated with the Appl icat ion, the major i ty of these matters
could be managed or condit ioned should the Appl icat ion be approved
and the appl icant accepts the necessary condit ions to address each of
these matters.
For these reasons i t is considered that the proposal should be
supported.
36
Signature: Name: Andrew Darroch
Date: June 2019
37
Attachment A
Global Power Generation Australia
Suite 4, Level 3, 24 Marcus Clarke St.
Canberra ACT 2600
ABN 74 130 542 031
Canberra, 27th May 2019
Upper Lachlan Shire Council
CODE: 20190527-CR3-CDP-ULS-001
SUBJECT: Confirmation of GPG commitment related to Crookwell 3 Wind Farm
Dear Tina Dodson
Firstly, we would like to thank the ULSC for the meeting we held on the 22nd May. After internal discussion
related the ULSC concerns related the construction of Crookwell 3 Wind Farm, GPG is pleased to propose
to the ULSC the following mitigation measures and new commitments with the confidence of your positive
support during this final stage of Planning Permit process.
1) GPG will eliminate the southern cluster of Crookwell 3 Wind Farm
The elimination of this cluster will involve the removal of 6 turbines and will implicate also the elimination
or mitigation of some of the ULSC concerns. GPG also confirms that Voluntary Planning Agreement current
total contribution (23 turbines) will be maintained the same even if there is any reduction in the number of
turbines (a new agreement is being drafted to reflect this, and will be provided shortly).
The elimination of this cluster implicates also the elimination of some of the ULSC concerns;
a) Reduction in the global visual impact of the Wind farm
b) Elimination of second cable crossing across Crookwell Road (section 1 of ULSC letter dated on the
26th April 2016)
c) Removal of the cluster and that mainly could cause TV and Radio interferences, as this cluster is in
the line between Goulburn and Crookwell
Global Power Generation Australia
Suite 4, Level 3, 24 Marcus Clarke St.
Canberra ACT 2600
ABN 74 130 542 031
d) Elimination of visual impact in the Pejar Creek Dam Area, considered as a recreation area
e) Elimination of important visual impact to non-associated Neighbours, specially Narangl (n8) and
Wombat Hollow (n19)
2) GPG will accept the option 1 for the access track to the wind Farm
GPG will use this access during construction and operation for all the transport of material and
staff. GPG cannot assure at this stage the utilization of this access for the transport of the Turbines
components due to the special orography of this access and the necessity of further studies. The
upgrade of Graywood Siding Road, estimated at $800.000, should also be considered as a
Community benefit as the Road is a Public Road.
3) GPG commits a Community engagement for a total amount of the $800.000 AUD during
construction stage;
Our proposal for the expenditure of this amount is, pending of further discussion with the ULSC:
3.1) Mobile Black Spot Program
GPG will contribute with 200.000 AUD to this Government program to improve mobile
phone coverage in rural areas. Alternatively, a targeted local approach could be developed
with consultation.
https://www.communications.gov.au/what-we-do/phone/mobile-services-and-
coverage/mobile-black-spot-program
Global Power Generation Australia
Suite 4, Level 3, 24 Marcus Clarke St.
Canberra ACT 2600
ABN 74 130 542 031
3.2) TV reception Improvement
GPG will conduct an exhaustive Interference Communication Study (once the southern cluster
has been removed) and will implement and improve the signal with a re-transmitter if
required. (estimated value of $350.000 AUD).
This installation should be conditioned to an exhaustive study to be done for GPG in
collaboration with the ULSC. In case there is no need of this new re-transmitter, the allocated
amount for commitment would be allocated in another project in agreement with the ULSC.
3.3) Domestic Solar Program
GPG will contribute with an amount of $200.000 AUD for the installation of photovoltaic
solar panels for in designated buildings in accordance with the ULSC.
3.4) Satellite reception Program
GPG will contribute with $50.000 AUD for the installation of satellite dishes and decoders in
the dwellings where the TV reception is poorest.
4) GPG commits a Community engagement for a total amount of the AUD per year during Wind
Farm Operation (excluded VPA and neighbours Deed)
Besides the committed amount with the Voluntary Planning Agreement for Crookwell 2 and 3 wind
Farms, signed on the 27/7/2017 with the ULSC and the Neighbours Deed Agreements, GPG is
committed to a contribution of $50.000 AUD/year to support the maintenance of re-transmitter
installations or any other funding duly agreed with the ULSC.
5) Exclusion area of 2 Km from any not associated neighbours
GPG is committed to continue to engage with residents within the 2 Km zone to establish
neighbours’ agreements. We will keep you informed of any improvement in the upcoming days.
All these commitments are subject to a positive support and a final IPC approval of the Planning Permit for
Crookwell 3 Wind Farm.
Hoping that these actions and commitments will be allow the ULSC to support Crookwell 3 Wind Farm in
the upcoming weeks.
DAVID SANTO TOMAS
Projects Director
38
Attachment B
David Way Senior Planning Officer Independent Planning Commission of NSW
Peter Duncan AM Panel Chair Independent Planning Commission of NSW
4 June 2019
By email
Dear Mr Way and Mr Duncan
Crookwell 3 Wind Farm (SSD 6695): Further reduction of Project impacts
We refer to the Crookwell 3 Wind Farm (SSD 6695) development application currently before the Independent Planning Commission of NSW (IPC) for final determination (Project).
The Department of Planning and Environment (DPE) Assessment Report and referral letter to the IPC dated 23 April 2019 recommend refusal of the Project on the basis that, in DPE’s assessment, the environmental impacts of the Project outweigh the Project’s benefits.
The proponent does not share the outcomes of the assessment of the Project undertaken by DPE and DPE’s conclusion with regard to the impacts of the Project.
GPG Australia Pty Ltd and its SPV Crookwell Development Pty Ltd are long term participants in the community. Over the long history of the Crookwell 3 application, we have reduced the impacts of the Project in response to community submissions, Upper Lachlan Shire Council (Council) concerns and new guidance material from DPE as it has been introduced. The Project will utilise existing infrastructure (including substation, grid connection and road upgrades) from the Crookwell 2 project and so will have far fewer impacts that a project of a similar scale built in any other location. Further, the Project has the benefit of a fully negotiated off-take agreement with a major Australian energy retailer. The agreement is ready to go, pending development consent for the Project.
Further reduction in the perceived impacts of the Project
Notwithstanding that we disagree with the assessment undertaken and recommendation reached by DPE, in the interests of addressing the concerns raised by DPE in its Report, we would be willing to:
(a) remove the southern cluster of turbines from the Project. That change will involve the removal of six (6) turbines (A28, A29, A30, A31, A32 and A33) (Southern Turbines); and
(b) without making any corresponding reduction in our commitment to the community and funding better community outcomes through the Voluntary Planning Agreement (VPA) already agreed with the Council.
The proponent is prepared to make this change to the Project on the basis that there are no changes to or reduction in the number of the remaining eastern cluster of seventeen (17) turbines (Eastern Turbines), which are critical to the economic viability of the Project.
Enclosed is a letter dated 27 May 2019 which we sent to the Council outlining the proposed change to the Project and our commitment to addressing concerns raised by the Council.
The importance of the Eastern Turbines to the economic viability of the Project
The Eastern Turbines are critical to the economic viability of the Project for the following reasons:
(a) the proponent has finalised the negotiation of an off-take agreement with a tier 1 energy retailer. The commercial terms of that agreement mandate approval of the Eastern Turbines.
(b) the quality of the wind resource in comparison to the Southern Turbines, together with the proximity to the existing grid connection infrastructure (33/330kV electrical substation).
Statement of Project commitments
In the event that the IPC is minded to approve the Project with the removal of the Southern Turbines, the proponent is committed to providing the same community benefits as if the Project were approved with the Southern Turbines (i.e. all 23 turbines within the Eastern and Southern Turbine clusters).
Those commitments include:
(a) existing agreements with host landowners and neighbouring properties to the Project;
78733050 Crookwell 3 page 2
(b) a VPA with the Council. This agreement will involve a yearly contribution of $2,500 per turbineover the lifetime of the project, to be used by Council in community projects, improvement of localinfrastructure, etc. The Proponent confirms its commitment under this VPA to contribute basedon a total of 23 wind turbines, irrespective of 17 of them being finally approved (which isaddressed in the enclosed letter to Council);
(c) community engagement in the amount of $800,000 for mobile black spot program, TV receptionimprovement, domestic solar program and satellite reception program;
(d) a contribution of $50,000 per annum to support the maintenance of re-transmitter installations;
(e) the upgrade of Graywood Siding Road estimated at $800,000;
(f) continued engagements with residents within 2km of the Project (Eastern Turbines) to establishneighbour agreements where possible, or to offer acquisition for fair market value whereneighbour agreements cannot be entered into;
Reduction of issues
The removal of the Southern Turbines addresses the following concerns of DPE and Council:
(a) removal of any visual impacts to the public domain, including the Pejar Creek Dam Area Stateheritage listed St Stephens Church;
(b) removal of visual impact to non-associated neighbours;
(c) elimination of second cable crossing across Crookwell Road;
(d) removal of the turbines that could potentially cause TV and Radio interferences;
No delay to IPC’s final determination
Importantly, given that the proposed change to the Project reduces the overall number of turbines and reduces the impacts of the Project in response to matters raised by DPE and the Council, but does not reduce the benefits of the Project to the community, we do not consider that there is any reason to delay the current process before the IPC and the IPC’s final determination of the Project as a result of the proposed change.
We welcome the opportunity to discuss these matters further with the IPC and to address any concerns you may have. We look forward to providing you with further details prior to our meeting. Do not hesitate to contact me on 0400 403 251.
Yours sincerely
Guillermo Alonso
Crookwell Development Pty Ltd