crcsd boe presentation 080910
DESCRIPTION
Building Plans for the new Educational Leadership and Support (ELS) Center.TRANSCRIPT
![Page 1: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/1.jpg)
CEDAR RAPIDS COMMUNITY
SCHOOL DISTRICT SERVICES CAMPUS
![Page 2: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/2.jpg)
Site Design & Construction
Buildings Design & Construction
CRCSD FLOOD RECOVERY TIMELINE
CRCSD, State, FEMA Design Reviews and Approvals – Target Dates
Decommissioning ESC @ Kingston
May
27,
201
2
Nov
9, 2
009
2010 2011 2012
JAN
MAR
NO
V
DEC
FEB
APR
MAY
JUN
JUL
AU
G
SEP
OC
T
NO
V
DEC
JAN
MAR
FEB
APR
MAY
JUN
JUL
AU
G
SEP
OC
T
NO
V
DEC
JAN
MAR
FEB
APR
MAY
DESIGN BID CONSTRUCTION
DESIGN BID CONSTRUCTION
DESIGN BID CONSTR
End of Design Development – April 2010
Schedule is contingent on timely governing authority approvals and weather
Completion of Construction Documents – August 2010
Completion of Construction – March 2012
Completion of Project – May 2012
TODAY
Substantial Completion of Construction – January 2012
![Page 3: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/3.jpg)
CRCSD CORE TEAM MEMBERSCRCSDDr. Dave BensonDr. Gary O’MalleyLaurel DaySteve GrahamMarcia HughesDave DvorakTom DayJeff RowrayRuth CallahanLori BruzekDenny SchreckengastMatt DunbarJenna Gardner
SHIVE-HATTERYGeorge KanzMichael GummJim WignallMike HessmanJake HinkleJon FitchTom Bosch
FEMAJim Waller
AIMarty CalabroRobert Wright
IHSEmilie Shipley
CITIZENSMike DawsonLindsay Schumacher
![Page 4: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/4.jpg)
PROJECT STATUSDESIGN IS ON COURSE TO MEETESTABLISHED TIMELINE
BID PACKAGES
DEMOLITION & ROUGH GRADING
F&F, STEEL AND CONCRETE
BUILDING, SITE IMPROVEMENTS, LANDSCAPING
B.O.E. APPROVAL – MAY 2010BIDDING – JUNE 2010CONSTRUCTION – AUGUST 2010
B.O.E. APPROVAL – JUNE 2010BIDDING – AUGUST 2010CONSTRUCTION – SEPTEMBER 2010
B.O.E. APPROVAL – AUGUST 2010BIDDING – SEPTEMBER 2010CONSTRUCTION – OCTOBER 2010
![Page 5: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/5.jpg)
SUSTAINABILITY
ENERGY MODELING – WHOLE BUILDING CONCEPTThe Weidt Group
DESIGN STRATEGIES
GEOTHERMAL HEATING & COOLING
OCCUPANCY SENSORSHIGH PERFORMANCE CURTAINWALL AND WINDOWSR-20 WALL INSULATIONR-30 ROOF INSULATION
WATER USE REDUCTION
DAYLIGHTING
STORMWATER QUALITY CONTROLLIGHT POLLUTION REDUCTION
ENERGY OPTIMIZATION
ENHANCED REFRIGERATION MANAGEMENTRECYCLINGCONSTRUCTION WASTE MANAGEMENTMATERIAL REUSERECYCLED CONTENT IN NEW MATERIALSRAPIDLY RENEWABLE MATERIALSINDOOR AIR QUALITYLOW-EMITTING MATERIALSRAPIDLY RENEWABLE MATERIALS
INDOOR POLLUTANT CONTROLLIGHTING CONTROLS
THERMAL COMFORT CONTROLS
TOTAL HEAT RECOVERY SYSTEMSCO2 SENSORS
VARIABLE FREQUENCY DRIVE PUMPS
HEATING & COOLING ZONES
HVAC COMMISSIONING ENVELOPE COMMISSIONING
GOAL – 50% ENERGY SAVINGS
![Page 6: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/6.jpg)
SUSTAINABILITY
COMPARISON TO LEED CHECKLIST
49 POINTS TARGETED
ACHIEVE GOLD RATING
![Page 7: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/7.jpg)
SITE PLAN
EDGEWOOD RD
ELL
IS R
D
VIS
ITO
R
PA
RK
ING
EMPLOYEE
PARKING
PARKING
PARKING
DISTRICT
VAN
DOCK
PARKING
BUS
BUS DRIVER
![Page 8: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/8.jpg)
EXTERIOR WAYFINDING
![Page 9: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/9.jpg)
EXTERIOR WAYFINDING
![Page 10: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/10.jpg)
EXTERIOR WAYFINDING
![Page 11: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/11.jpg)
EXTERIOR WAYFINDING
![Page 12: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/12.jpg)
PROJECT PLANS
LOWER LEVEL FLOOR PLAN
![Page 13: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/13.jpg)
PROJECT PLANS
FIRST LEVEL FLOOR PLAN
![Page 14: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/14.jpg)
PROJECT PLANS
SECOND LEVEL FLOOR PLAN
![Page 15: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/15.jpg)
INTERIOR WAYFINDING
LOWER LEVEL
MAIN LEVEL
SECOND LEVEL
![Page 16: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/16.jpg)
EXTERIOR ELEVATIONS
![Page 17: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/17.jpg)
EXTERIOR ELEVATIONS
![Page 18: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/18.jpg)
ENTRANCE RENDERING
![Page 19: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/19.jpg)
BUDGET
810,353TRANSPORTATION RELOCATION
CURRENT BUDGET
$915,647
$5,233,818
$29,142,293
$35,897,2524,957,361
2,440,528
$44,500,000
PREVIOUS BUDGET
$915,647BID PACKAGE I
BID PACKAGE 2$5,233,818
BID PACKAGE 3
$28,579,985
FOOTINGS, FOUNDATIONS& STEEL
BUILDING, FF&ESITE LANDSCAPINGAND FINISH GRADING
$35,729,450CONSTRUCTION TOTALA/E FEES 4,957,361
CONTINGENCY 3,002,836
$44,500,000PROJECT TOTAL
810,353
PROJECT SF TOTAL 169,419COST SF (BUILDING) $202.90COST SF (TOTAL PROJECT) $262.66
$1,000,000OFF-SITE IMPROVEMENTS $1,000,000
![Page 20: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/20.jpg)
TRANSPORTATION RELOCATION
CONSTRUCTION
BUS PARKING ATWESTDALE MALL
![Page 21: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/21.jpg)
TRANSPORTATION RELOCATION
CONSTRUCTION
TRANSPORTATIONOFFICES ATWESTDALE MALL
![Page 22: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/22.jpg)
TRANSPORTATION RELOCATION
CONSTRUCTION
BUS REPAIR SHOPAT 27TH AVE SW
![Page 23: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/23.jpg)
ARCHAEOLOGICAL SURVEYS
SURVEY COSTS
PHASE I $21,254PHASE II $49,774
MAY 24 JUNE 3JUNE 7JUNE 18JUNE 25JUNE 29JULY 6JULY 16JULY 22
JULY 28
ALL COSTS ARE REIMBURSED BY FEMA
FEMA NOTIFICATION OF PHASE ICONTRACT OSAOSA BEGINS PHASE IFIELD WORK COMPLETEDFINDINGS BY OSA & SHPOOSA CONTRACT AMENDMENT OSA BEGINS PHASE IIOSA COMPLETES FIELDWORKOSA & SHPO FINDINGSNO SIGNIFICANT IMPACT
FEMA LETTER TO PROCEED
SCHEDULE IMPACT – CONSTRUCTION DELAY OF 2 WEEKS
SHIVE-HATTERY $12,000
![Page 24: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/24.jpg)
CONSTRUCTION - SUSTAINABILITYSALVAGED
BENCHESBUS WASH SYSTEMO.H. DOORS
RECYCLEDTREES & STUMPSFUEL TANKSUSED OIL TANKBATTERIESUSED OIL FILTERSCHAIN LINK FENCINGOH ELECTRICAL WIREHYDRAULIC SYSTEMWIRINGCOPPERCONDUIT
STEELALUMINUMDUCTILE IRONPRECAST WALL PANELSASPHALTCONCRETEBLOCK WALLSSIGNSHAND RAILSLIGHT FIXTURESSAND
![Page 25: Crcsd boe presentation 080910](https://reader036.vdocuments.site/reader036/viewer/2022062514/5597d9dc1a28abb35e8b4703/html5/thumbnails/25.jpg)
QUESTIONSAND
COMMENTS
NEXT REVIEW