![Page 1: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/1.jpg)
1 of 28
Feroze Vazifdar, S.E.Vice PresidentLiftech Consultants Inc.www.liftech.net
Crane Useful Life Assessment and MaintenanceTOC Asia 2005
![Page 2: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/2.jpg)
2 of 28
Forestay Failure
![Page 3: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/3.jpg)
3 of 28
Boom Hanger Failure
![Page 4: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/4.jpg)
4 of 28
Trolley Support Failure
![Page 5: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/5.jpg)
5 of 28
Overview
Failures do occur!Fatigue design philosophyUseful life analysis & structural maintenanceRepair examples
![Page 6: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/6.jpg)
6 of 28
Fatigue Design PhilosophySafe Life Design Damage Tolerant Design
Space Station1 in 106
Cranes1 in 50 without inspection1 in 1,000 with inspection
![Page 7: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/7.jpg)
7 of 28
How to Minimize the Effect of Fatigue CracksProper design
Proper material selection
Proper fabrication and quality control
Proper attachments
Structural maintenance program
![Page 8: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/8.jpg)
8 of 28
Fatigue Crack Growth
Stress range
Number of cycles
Detailing
Workmanship andquality control
Crack
Crack growth
Cleavage fracture rather than slip lines.
![Page 9: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/9.jpg)
9 of 28
You Have an Aging Crane:What are Your Options?
Do nothing and ignore risks
Useful structural life assessment
Prolong life with inspection and repair
Reduce use and/or relocate
Dispose
![Page 10: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/10.jpg)
10 of 28
Steps of a Useful Life Analysis
Structural condition survey
Useful life estimate before inspection
Inspection program
Structural inspection
Useful life estimate after inspection
![Page 11: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/11.jpg)
11 of 28
Structural Condition SurveyLook for
DistressSuspect detailsAttachments
Make photo record for the NDT inspection
![Page 12: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/12.jpg)
12 of 28
Useful Life Estimate Before Inspection
Calculate cumulative damage to date
Estimate remaining cumulative damage for expected operation
Convert to useful life
Owner can decide best course of action
![Page 13: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/13.jpg)
13 of 28
Useful Life Analysis: ExampleDescription Design Crane 1 Crane 2 Crane 3Loads tons tons tons tonsTrolley Wt 13.0 13.0 13.0 13.0Head block 3.1 3.1 3.1 3.1Spreader 12.0 12.0 12.0 12.0Rated Load 40.0 40.0 40.0 40.0Design Fatigue Load 30.0 30.0 30.0 30.0Avg Container Wt (root mean cubed) 30.0 30.0 20.0 40.0
Years in operation (Through 2003) 15.0 15.0 15.0 15.0No. of cycles 1,500,000 1,500,000 2,250,000 1,500,000cycles/year 100,000 100,000 150,000 100,000Predicted future usage rate (cycles/year) 100,000 150,000 150,000 100,000Des cycles/yr 100,000 100,000 100,000 100,000
Cumulative DamageR (act) 2.942E+11 2.942E+11 2.504E+11 4.737E+11R(des) 3.922E+11 3.922E+11 3.922E+11 3.922E+11Cumulative damage ratio R 0.750 0.750 0.638 1.208
Predicted No. of fatigue cracks /craneNo. of std deviations below mean 2.554 2.554 2.865 1.636Reliabity 0.9947 0.9947 0.9979 0.9491No. of joints/crane 1500 1500 1500 1500Predicted fatigue cracks/crane 7.9 7.9 3.1 76.4Predicted Fatigue Cracks / Crane 5 to 10 5 to 10 0 to 5 60 to 90
Structural Useful Life in present conditionYears in operation 15.0 15.0 15.0 15.0Remaining structural life = Yearsleft (predicted rate) 5.0 3.3 7.2 -4.2Estimate of remaining useful life 5 3 to 4 7 to 8 zeroprior to NDT inspection
![Page 14: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/14.jpg)
14 of 28
Structural Maintenance & Inspection ProgramInspection manuals
Details to be inspected
Classification: FCM or NFCM
Inspection method: VT, MT, UT, RT
Acceptance criteria
Inspector’s qualifications
Reporting procedures
Inspection frequencies
![Page 15: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/15.jpg)
15 of 28
Inspection Program:Typical General Arrangement
Joint16DH
Joint5BJ
![Page 16: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/16.jpg)
16 of 28
Inspection Program:Typical NDT Manual Pages
16DH5BJ
![Page 17: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/17.jpg)
17 of 28
Inspection Frequency
Not all joints need inspection at the same interval
More frequent inspection:
Fracture critical members (FCMs)
Joints with higher stress ranges
Less frequent inspection:
Non-fracture critical members (NFCMs)
Joints with lower stress ranges
Joints in secondary members
![Page 18: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/18.jpg)
18 of 28
Example Inspection Intervals
Component Fracture Critical?
No. of Moves Interval(Years)
Trolley Girder Hanger
Yes 300,000 3
Forestay Yes 600,000 6
Lower Legs No 1,200,000 12
Portal Beam No 2,400,000 24
This example is not suitable for all cranes.
![Page 19: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/19.jpg)
19 of 28
Structural Inspection
Inspect and compare predictions with findings
Repair procedures
![Page 20: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/20.jpg)
20 of 28
Useful Life Estimate After Inspection
Review inspection reports
Identify fatigue cracks
Compare identified cracks with prediction
Reevaluate the reliability and useful life based on inspection
Owner can decide best course of action
![Page 21: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/21.jpg)
21 of 28
Fatigue Crack RepairsExample: Repair Original Detail
![Page 22: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/22.jpg)
22 of 28
Fatigue Crack RepairsExample: Modify and Repair Detail
![Page 23: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/23.jpg)
23 of 28
Forestay Failure Profile
Crack Initiation Failure Profile
![Page 24: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/24.jpg)
24 of 28
Modified Detail: Plate Flexing
0.5t
AC
TU
AL
(5t
IDE
AL
)
![Page 25: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/25.jpg)
25 of 28
Modified Detail: Stress Analysis
S ee D eta il Be low
S 22 = -15 .1 t/cm 2
S ee D e ta il B e low
S 22 = -10 .6 t/cm 2
Original Modified
![Page 26: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/26.jpg)
26 of 28
Crack Occurrence and Maintenance
Number of Cycles
Num
ber
of C
rack
s
Original CraneWithout Repair
Inspect andRepair(Typical)
"Design Life"
Envelope ofNew CrackFrequency
• Poor initial details repaired
• More attention during repair
• Threshold stress range
![Page 27: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/27.jpg)
27 of 28
Summary
Fatigue cracks will occur and can be catastrophic if not repaired
Cracking can be controlled with proper design, workmanship, quality control, and a proper structural maintenance program
Crack repairs are inexpensive
Useful life analysis can be used to predict future cracking so the owner can decide the best course of action
![Page 28: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/28.jpg)
28 of 28
Feroze Vazifdar, S.E.Vice President
Liftech Consultants Inc.
Crane Useful Life Assessment and Maintenance
TOC Asia 2005
Thank You
This presentation is available for downloadwww.liftech.net
![Page 29: Crane Useful Life Assessment and Maintenance - · PDF file1 of 28 Feroze Vazifdar, S.E. Vice President Liftech Consultants Inc. Crane Useful Life Assessment and Maintenance TOC Asia](https://reader030.vdocuments.site/reader030/viewer/2022012923/5aacb28b7f8b9a2b4c8d8084/html5/thumbnails/29.jpg)
29 of 28
Quality Assurance Review:
Feroze VazifdarPrincipal:
Michael Jordan, Patrick McCarthy, and Yuo-Fong Chang
Editors:
Feroze VazifdarAuthor:
Liftech Consultants Inc. file data:
N:\Papers & Presentations\!Working\TOC 2005_FV & PWM\03-pres pwm 2005-03-28_web version.ppt
Copyright 2005 by Liftech Consultants Inc. All rights reserved.
The information included in this presentation may not be altered, copied, or used without written authorization from Liftech Consultants Inc. Anyone making use of the information assumes all liability arising from such use.