cqproject tracker user guide
DESCRIPTION
http://rational-tools.info 'ProjectTracker for MSP Server 2003 & 2007' MS Project and MSP Server and ClearQuest integration module. This tool is registered as the V.A.P-solution in IBM. State-of-art MS Project (Project Server 2003 & 2007) and ClearQuest integration module which allows bidirectional collaboration keeping the full hierarchy, total resources information and all dependencies as well. During planning in MS Project the module allows to import all resources available from the CQ base. It’s irreplaceable tool for excellent project management. CM-Consult ProjectTracker is featured in the IBM Global Solutions Directory ID 38167TRANSCRIPT
MS Project and ClearQuest Integration Module
ProjectTracker
Version 2.5.1
User Guide
LLC CM-Consult
2009
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
2
Contents
1. LIST OF ABBREVIATIONS, CONVENTIONS AND TERMS ........................................................... 4
2. GLOSSARY ........................................................................................................................................... 4
3. INTRODUCTION .................................................................................................................................. 5
3.1 PURPOSE OF THIS DOCUMENT............................................................................................................... 5
3.2 FIELD OF APPLICATION......................................................................................................................... 5
3.3 IMPLEMENTATION ................................................................................................................................ 5
3.4 SYSTEM REQUIREMENTS ...................................................................................................................... 5
4. GENERAL DESCRIPTION .................................................................................................................. 5
4.1 USAGE VARIANTS ................................................................................................................................. 6
5. FUNCTIONALITY .............................................................................................................................. 14
6. DESCRIPTION OF USER INTERFACE FORMS ............................................................................ 14
6.1 AUTHORIZATION ................................................................................................................................ 15
6.2 CONFIGURATION ................................................................................................................................ 15
6.3 SAVING ............................................................................................................................................. 26
6.4 IMPORTING ........................................................................................................................................ 27
6.5 REFRESHING ...................................................................................................................................... 29
7. ADJUSTING MODULE SETTINGS .................................................................................................. 30
7.1 MAIN RECORD SETTINGS .................................................................................................................... 31
7.2 PROJECT RECORD SETTINGS ................................................................................................................ 32
7.3 ADDITIONAL RECORD SETTING............................................................................................................ 33
7.4 ADDITIONAL FIELDS SETTINGS ............................................................................................................ 35
7.5 RESOURCE SETTINGS .......................................................................................................................... 36
7.6 ADDITIONAL SETTINGS ....................................................................................................................... 36
8. USING THE PROGRAM .................................................................................................................... 38
8.1 SAVING TASKS ................................................................................................................................... 38
8.2 CREATING A QUERY FOR IMPORT IN CLEARQUEST .............................................................................. 43
8.3 IMPORTING ........................................................................................................................................ 46
8.4 REFRESHING ...................................................................................................................................... 49
8.5 OPENING A USER INTERFACE FORM OF THE CLEARQUEST REQUEST FROM MS PROJECT ....................... 51
8.6 CREATING A NEW CLEARQUEST REQUEST .......................................................................................... 53
8.7 IMPORTING A LICENSE KEY ................................................................................................................ 55
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
3
LIST OF FIGURES....................................................................................................................................... 58
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
4
1. List of abbreviations, conventions and termsAbbreviation Expansion
ProjectTracker MS Project and ClearQuest Integration Module
MS Microsoft
MPS, MS Project Microsoft Office Project Professional 2003/2007
2. GlossaryTerm Interpretation
ClearQuest Software change management system IMB Rational ClearQuest
ClearQuest
entity type
ClearQuest entity (Defect, Task, etc.)
3. Introduction
3.1 Purpose of This Document
The document provides users with information on functionality of the ProjectTracker
module which allows effectively using MS Project and ClearQuest as a single integrated system.
The document covers the following topics:
· ProjectTracker functionality
· User interface forms
· Module settings
· Using the module
3.2 Field of Application
The document relates to the ProjectTracker module, and is intended for the end user
(project manager) of the change management system.
3.3 Implementation
The module is implemented as an add-on for MS Project, and is integrated into the MS
Project menu. The module represents a COM object implemented in the .NET 2.0 framework.
3.4 System Requirements
· MS Windows 2000/XP/2003
· ClearQuest version 2003.06.00 or later
· MS Project version 2003/2007 (English or Russian edition)
· MS Framework .Net 2.0
4. General DescriptionThe module is intended for integration of ClearQuest and MS Project, and allows
performing tighter integration than the standard IBM Rational module can provide. When
performing integration of the ClearQuest base and the MS Project plan, the module allows
mapping entity properties (synchronized data) using flexible settings. The module supports
hierarchical relations between ClearQuest requests thus it allows keeping several child (nesting)
tasks and subtasks in the plan, which will be synchronized with tasks of the MS Project plan.
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
6
The module allows a manager to plan work of their employees using MS Project directly.
By means of integration, you can open the Clear Quest record forms, and synchronize any fields,
displaying them directly in the MS Project plan.
The main feature of this module that distinguishes it from the standard one is the
possibility to automatically form dependency links between ClearQuest requests. This possibility
allows a manager to plan work in more detail directly in MS Project, which is more handy and
usual for them.
The module performs synchronization of information between the ClearQuest and MSProject systems using the following basic data exchange operations (see Figure 1 – Basicoperations):
· Saving Tasks
· Importing tasks
· Refreshing tasks
Figure 1 – Basic operations
4.1 Usage variants
This section contains information on variants of using hierarchical relations for
integration, and using the fields of ClearQuest requests. For the list of necessary fields, and
details on their use, see the Configuration section.
Project-Request-Task Hierarchy
The Project Tracker module supports various request hierarchies, defined in the task plan,
or the ClearQuest database. The figure below (see Figure 2 – Project-Request-Task relationship)
describes the Project-Request-Task relationship between ClearQuest entities and Ms Project
tasks.
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
7
Ref
eren
ce
BackReference
Figure 2 – Project-Request-Task relationship
Desription of the Project-Request-Task relationship:
1. In this hierarchy type, the following types of ClearQuest entities are used, and
they are associated with the following tasks of the MS Project plan:
1) The Project type of ClearQuest entity – the first nesting level
2) The Request type of ClearQuest entity – the second nesting level
3) The Task type of ClearQuest entity - the thirds and subsequent nesting
levels
2. The ClearQuest entity type used for identification of a project must comply with
the following requirements:
1) Availability of the following fields:
i. Name – mandatory
ii. Description – optional
iii. Owner - optional
iv. Percent complete – optional
v. Plan start date – optional
vi. Plan finish date – optional
vii. Actual start date – optional
viii. Actual finish date – optional
ix. Planned cost – optional
x. Actual cost – optional
xi. Task reference – optional
xii. Request reference – optional
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
8
2) An action available that provides a possibility to edit a record
3. The ClearQuest entity type used for identification of additional requests (defect,
task, etc.) must comply with the following requirements:
1) Availability of the following fields:
i. Headline – mandatory
ii. Description – optional
iii. Plan start date – optional
iv. Plan finish date – optional
v. Child task reference - optional, in case tasks have references to
requests
vi. Project reference – mandatory, in case project does not have
references to requests
2) An action available that provides a possibility to edit a record
4. The ClearQuest entity type used for identification of a task must comply with the
following requirements:
1) Availability of the following fields:
i. Headline – mandatory
ii. Description – optional
iii. Plan start date – mandatory
iv. Plan finish date – mandatory
v. Actual start date – mandatory
vi. Actual finish date – mandatory
vii. Owner – mandatory
viii. Child task reference – mandatory, in case implementation of task
hierarchy is necessary
ix. Parent task reference – mandatory, in case implementation of task
hierarchy is necessary
x. Project reference – mandatory, in case there is no reference to tasks
from the project
xi. Request reference – mandatory, in case there is no reference from
the request to tasks
xii. Predecessors – optional
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
9
xiii. Plan work – optional
xiv. Actual work – optional
2) An action available that provides a possibility to edit a record
Project-Task Hierarchy
The figure below (see Figure 3 – Project-Task relationship) describes the Project-Task
relationship between ClearQuest entities and MS Project tasks.
BackR
eference Ref
eren
ce
Figure 3 – Project-Task relationship
Description of the Project-Task relationship:
1. In this hierarchy type, the following types of ClearQuest entities are used, and
they are associated with the following tasks of the MS Project plan:
1) The Project type of ClearQuest entity – the first nesting level
2) The Task type of ClearQuest entity - the second and subsequent nesting
levels
2. The ClearQuest entity type used for identification of the project must comply with
the following requirements:
1) Availability of the following fields:
i. Name – mandatory
ii. Description – optional
iii. Owner - optional
iv. Percent complete – optional
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
10
v. Plan start date – optional
vi. Plan finish date – optional
vii. Actual start date – optional
viii. Actual finish date – optional
ix. Planned cost – optional
x. Actual cost – optional
xi. Task reference – optional
2) An action available that provides a possibility to edit a record
3. The ClearQuest entity type used for identification of a task must comply with the
following requirements:
1) Availability of the following fields:
i. Headline – mandatory
ii. Description – optional
iii. Plan start date – mandatory
iv. Plan finish date – mandatory
v. Actual start date – mandatory
vi. Actual finish date – mandatory
vii. Owner – mandatory
viii. Child task reference – mandatory, in case implementation of task
hierarchy is necessary
ix. Parent task reference – mandatory, in case implementation of task
hierarchy is necessary
x. Project reference – mandatory, in case there is no reference to tasks
from the project
xi. Predecessors – optional
xii. Plan work – optional
xiii. Actual work – optional
2) An action available that provides a possibility to edit a record
Request-Task Hierarchy
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
11
The figure below (see Figure 4 – Request-Task relationship) describes the Request-Task
relationship between ClearQuest entities and MS Project tasks.
BackR
eference Ref
eren
ce
Figure 4 – Request-Task relationship
Description of the Request-Task relationship:
1. In this hierarchy type, the following types of ClearQuest entities are used, and
they are associated with the following tasks of the MS Project plan:
1) The Request type of ClearQuest entity – the firts nesting level
2) The Task type of ClearQuest entity – the second and subsequent nesting
levels
2. The ClearQuest entity type used for identification of additional requests (Defect,
Enhancement, Request etc.) must comply with the following requirements:
1) Availability of the following fields:
i. Headline – mandatory
ii. Description – optional
iii. Plan start date – optional
iv. Plan finish date – optional
v. Child task reference - optional, in case tasks have references to
requests
2) An action available that provides a possibility to edit a record
3. The ClearQuest entity type used for identification of a task must comply with the
following requirements:
1) Availability of the following fields:
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
12
i. Headline – mandatory
ii. Description – optional
iii. Plan start date – mandatory
iv. Plan finish date – mandatory
v. Actual start date – mandatory
vi. Actual finish date – mandatory
vii. Owner – mandatory
viii. Child task reference – mandatory, in case implementation of task
nesting is necessary
ix. Parent task reference – mandatory, in case implementation of task
nesting is necessary
x. Request reference – mandatory, in case there is no reference from
the request to tasks
xi. Predecessors – optional
xii. Plan work – optional
xiii. Actual work – optional
2) An action available that provides a possibility to edit a record
Task-Task Hierarchy
The figure below (see Figure 5 – Task-Task relationship) describes the Task-Task
relationaship between ClearQuest entities and MS Project tasks.
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
13
Figure 5 – Task-Task relationship
Description of the Task-Task relationship:
1. In this hierarchy type, the following types of ClearQuest entities are used, and
they are associated with the following tasks of the MS Project plan:
1) The Task type of ClearQuest entity - the firtst and subsequent nesting
levels
2. The ClearQuest entity type used for identification of a task must comply with the
following requirements:
1) Availability of the following fields:
i. Headline – mandatory
ii. Description – optional
iii. Plan start date – mandatory
iv. Plan finish date – mandatory
v. Actual start date – mandatory
vi. Actual finish date – mandatory
vii. Owner – mandatory
viii. Child task reference – mandatory
ix. Parent task reference – mandatory
x. Predecessors – optional
xi. Plan work – optional
xii. Actual work – optional
2) An action available that provides a possibility to edit a record
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
14
5. FunctionalityThe ProjectTracker module supports the following functionality:
· Supports hierarchical relations in ClearQuest requests
· Allows importing requests from the ClearQuest database into MS Project plan
with restoration of ClearQuest request hierarchy (the module supports hierarchical
relations not only between requests of the same type, but also between requests of
different types)
· Supports synchronization of any types of fields
· Imports user accounts from the ClearQuest database, and allows using them as
resources in the MS Project plan
· Uses special settings, regulating synchronization priorities
· Does not require installing special packages on records in the ClearQuest scheme
· Integrates into MS Project completely, and allows opening ClearQuest request
forms from the shortcut menu
6. Description of User Interface FormsAfter the installation, the ProjectTracker integrates with MS Project by adding a menu,
and building in the separate toolbar (see Figure 6 – Integrated menu).
Figure 6 – Integrated menu
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
15
The menu and the toolbar provide access to the following functions:
1. Connect – connecting to ClearQuest;
2. New – creating a new ClearQuest request
3. Open CQ Form – opening a form of the selected ClearQuest request;
4. Import to MSP – importing ClearQuest requests into the MS Project plan;
5. Import child records – importing child requests for the selected ClearQuest
request;
6. Save Plan to CQ – saving a whole plan to ClearQuest;
7. Save Selection to CQ – saving the requests selected from the plan to
ClearQuest;
8. Refresh MSP Plan – refreshing a whole MS Project plan from ClearQuest;
9. Refresh MSP Selection – refreshing the selected MS Project plan requests
from ClearQuest;
10. Settings – opening a form for adjusting the module settings;
11. About – opening a window with the module description.
6.1 Authorization
The authorization dialog (see Figure 7 – ClearQuest session authorization window) is the
standard authorization window that appears when the ClearQuest database session is initiated.
Figure 7 – ClearQuest session authorization window
6.2 Configuration
In the Configuration dialog, there are six tabs:
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
16
1. The Main tab – allows adjusting the main request fields necessary for planning
2. The Project tab – allows configuring mapping between the ClearQuest request
and the project, fields of the MS Project plan
3. The Add request tab – allows configuring the ClearQuest additional requests that
should be reflected in the plan
4. The Add fields tab – if necessary, the tab allows configuring the ClearQuest
request’s additional fields that will be included into the plan
5. The Resources tab – allows configuring automatic import of ClearQuest or MS
Project Server users into the plan
6. The Add settings tab – allows adjusting the following parameters: default
request, switching off automatic calculation, etc.
6.2.1 The Main TabThe main request is the ClearQuest request that is used as a task to an end owner, and is
associated with a task in the MS Project plan. In the Main tab, (see Figure 8 – The Main tab) you
can adjust settings of the ClearQuest main request. The tab contains the following properties:
· Record type – the ClearQuest request type intended for associating tasks of the
MS Project plan with it
· Edit – a name of the action that will be used for editing records in ClearQuest
· Assignee action – a name of the action that should be taken to assign an owner
for a task
· Change only plan dates and resources – if this option is selected, only plan
dates and resources will be saved in ClearQuest upon refreshing. Otherwise, all
changed fields of the task will be saved.
· Update plan dates and resources from CQ – select this option, if plan dates and
resources edited in ClearQuest should be updated in the MS Project plan as well
upon the MS Project plan refreshing Otherwise, these changes will be ignored and
rewritten upon saving the plan in ClearQuest.
· Headline – this field contains a brief description of the ClearQuest request, and
will be converted into the Name field of a task in the plan
· Description – this field contains a detailed description of the ClearQuest request,
and will be converted into the Note field of a task in the plan
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
17
· Resources – this field contains a name of an owner in the ClearQuest request
· Plan start date – this field contains a planned date for starting work in the
ClearQuest request
· Plan finish date – this field contains a planned date for finishing work in the
ClearQuest request
· Plan assignment work – this field contains planned effort of an owner in
ClearQuest. The value can be set in percentage, or in hours. If you set the value in
percentage, it will represent a planned owner’s load in percentage relative to a
whole task duration.
· Actual start date – this field contains an actual work start date in the ClearQuest
request
· Actual finish date – this field contains an actual work finish date in the
ClearQuest request
· Actual assignment work – this field contains a value of time spent on a task The
value can be set in percent, or in hours.
· Child record reference – the field that represents a reference to a child request.
The field must refer to the same request type, that is defined in the Record type
configuration field.
· Parent record reference – the field that represents a reference to a parent
request. The field must refer to the same request type, that is defined in the
Record type configuration field.
· Predecessors – this filed contains references to the ClearQuest request (the
references that must precede this request). The field must refer to the same request
type, that is defined in the Record type configuration field, and is responsible for
displaying the sequence in MS Project.
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
18
Figure 8 – The Main tab
6.2.2 The Project Tab
On this tab, you can configure the ClearQuest request that corresponds to the project. The
project in the MS Project plan, if it is configured, can be associated with the first level task only.
The number of projects in a plan is not limited. This tab contains the following fields:
· Record type – the ClearQuest request type that represents a project in the
ClearQuest system
· Edit action – Edit – the action that should be performed to edit a project record
in the ClearQuest system. This action should be defined if it is necessary to
synchronize planned and actual dates, completion rate, project costs in the MS
Project plan with those in the ClearQuest system, and if it is necessary to link
child requests directly from the project entity in ClearQuest.
· Use baseline for planning – select this option, only if it is necessary to edit
planned dates of the ClearQuest project from MS Project. In this case, the baseline
defined in additional settings will be used.
· Headline – the ClearQuest request field that corresponds to the project name
· Description – the ClearQuest request field that contains additional information on
the project
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
19
· Project manager – the ClearQuest request field that contains a project manager
resource
· Plan start – the ClearQuest request field that contains a planned date of starting a
project. You should fill in this field, if the planned date of starting a project will
be set from MS Project.
· Plan finish – the ClearQuest request field that contains a planned date of
finishing a project. You should fill in this field, if the planned date of finishing a
project will be set from MS Project.
· Plan cost – the ClearQuest request field that contains a planned project costs
· Actual start – the ClearQuest request field that contains an actual date of starting
a project. You should fill in this field, if the actual date of starting a project will be
set from MS Project.
· Actual finish – the ClearQuest request field that contains an actual date of
finishing a project. You should fill in this field, if the actual date of finishing a
project will be set from MS Project.
· Actual cost – the ClearQuest request field that contains actual project costs
· Task reference – the ClearQuest request field that contains a list of all project
tasks
· Project reference from main record – the field of the ClearQuest main request
that contains a name of a project corresponding to the main request
· Percent – the ClearQuest request field that contains an actual project completion
rate. If the rate is set, then in the ClearQuest request, there will be set a
completion rate of the task that is associated with this request.
· State – the ClearQuest request field that defines a project state, if a project is
defined using a reference
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
20
Figure 9 – The Project tab
6.2.3 The Add Record Types Tab
Additional requests are requests that initiate a task definition (defect, request from an
interested party, etc.) The distinctive feature of these requests is that you cannot edit any of their
fields in ClearQuest from MS Project. You can only bind child tasks to such requests. To
configure the ClearQuest additional requests, use the Add record types tab.
This tab (see Figure 10 – The Add record types tab) contains the following fields:
· Record type – configurable ClearQuest request type
· Edit – a name of the action that will be used for generating child requests in
ClearQuest;
· Headline – this field contains a brief description of the ClearQuest request
· Description – this field contains a detailed description of the ClearQuest request
· Resource – this field contains a name of an owner in the ClearQuest request
· Plan start date – this field contains a plan date for starting work in the
ClearQuest record;
· Planned finish date – this field contains a plan date for finishing work in the
ClearQuest record;
· Child record reference – the field that represents a reference to a child request.
The field must refer to the same request type, that is defined in the Record type
configuration field on the Main tab
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
21
· Reference from main record – this field contains a reference from the main
request to an additional request
· Project reference – the ClearQuest request field that contains a project name
· Reference from project – the ClearQuest request field that refers to a
configurable additional request
· List with results – this table contains all configured additional requests
· Add – click this button to add new requests to a table
· Delete – click this button to delete any of the configured additional requests from
a table
· Change – click this button to adjust settings of a record selected from the table of
additional requests
Figure 10 – The Add record types tab
6.2.4 The Add Fields Tab
Additional fields are the ClearQuest request fields that should be displayed in the MS
Project plan. Besides, you must have an ability to edit these fields from MS Project. You can
configure the ClearQuest request additional fields on the Add fields tab that is described below.
This tab (see Figure 11 – The Add fields tab) contains the following fields:
· Custom CQ Entity – the entity for which an additional field is configured
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
22
· Name ClearQuest field – the configurable ClearQuest field that should be
displayed in a plan;
· Visible name – a field name that will be displayed in the plan title
· MSProject field – an identifier of the MS Project field, into which the value from
the ClearQuest field will be copied
· Is visible – if you select this option, a configurable field will be added to the plan
as visible. Otherwise, this field will not be displayed in the plan, though values
will be recorder to the field.
· Access – defines a method of using a configured field
o Read/Write – a value in a field will be updated from the ClearQuest
record every time the plan is refreshed from ClearQuest, and a field value
from the MS Project plan will be recorded into the ClearQuest record
every time the plan is saved in ClearQuest
o Read – a field value will only be updated from the ClearQuest request
every time the plan is refreshed from ClearQuest;
o Write – a field value will only be recorded from the MS Project plan into
the ClearQuest request every time the plan is saved in ClearQuest
· List – if you select this option, a configurable field will represent a list
· Reference to – this option allows defining that a field represents a reference to
another ClearQuest entity. There are four fields under this option:
o record type – contains a list of ClearQuest entities From this list, select
the ClearQuest entity that is referenced by this field.
o field – contains a list of fields that are above the selected entity From this
list, select a field name that will be displayed in the MS Project plan
o filter – a list of fields by which you can filter a list
o value – an filtering expression
· Named list – defines a dynamic list that can be associated with a field
· List with results – this table contains all configured additional fields
· Add – click this button to add a new field
· Delete – click this button to delete any of the configured fields from a table
· Change – click this button to adjust settings of a field selected from a table
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
23
Figure 11 – The Add fields tab
6.2.5 The Resources Tab
On the Resources tab (see Figure 12 – The Resources Tab), you can adjust settings for
owners:
· Autoload users to MSProject plan – if you select this option, the integration
module will automatically generate a list of resources If none of the options listed
below is selected, all users defined in the User entity of the ClearQuest will be
downloaded.
· Use non-standard user entity – if you select this option, a non-standard User
entity will be used
o Record type – a name of the User entity
o Resource – the entity field containing an owner ’s name
o Description – a detailed description of a user
o Email – the field containing a user’s e-mail
o Phone – the field containing a users’ phone number
· Use db access for MSProject Server – if you select this option, a list of users
will be downloaded from the MS Project server when importing or refreshing
tasks
o Database server – a name of a database server that hosts the MS Project
Server databases
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
24
o Database name – a name of the MS Project Server database
o User name – a name of a user who have a read access to the MS Project
Server database
o Password – a password of a user defined above
· Use plan assignment in – in this list, you can select a unit of measure for planned
work load (percentage or hours)
· Use actual work in – in this list, you can select a unit of measure for actual work
completion (percentage or hours)
Figure 12 – The Resources Tab
6.2.6 The Add Settings Tab
On this tab (see Figure 13 – The Add settings tab), you can configure additional setings:
· Default query – this field contains a path to a filter query that will be used for
importing the ClearQuest records The entered path will be saved for a project that
is opened during configuration of integration module.
· Every task have ClearQuest record – if you select this option, the Clear Quest
record field will not be used for identification of ClearQuest records
· Autocalculate off – if you select this option, then automatic calculation during
import, refresh and save operations is switched off, that allows speeding up these
operations
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
25
· ClearQuest Record – the system field that is used for identification of the
ClearQuest records
· CQID – the system field that contains the identifier of the ClearQuest record
· Record Type – the system field that contains a name of the ClearQuest record
type
· State – the system field that contains a value of the State field of the ClearQuest
record
· Use baseline for planning – if you select this option, then the set planned dates
will be duplicated into the baseline selected below
· Baseline – in this list, you can select a baseline that will store the planned dates
· Use default CQ values – if you select this option, default values will be saved
during the save operation The entered path will be saved for a project that is
opened during configuration of integration module.
o Field – a name of the ClearQuest main record field that will store default
values
o Value – a default value A default value can be static, or can be equal to
the value of any MS Project field. In the latter case, the field name should
be set in square brackets.
o Update:
§ always – a value will be recorded into the ClearQuest record field
upon every saving of the plan in ClearQuest
§ empty – a value will be recorded into the ClearQuest record field
upon saving of the plan in ClearQuest only if the field is empty
· List with results – this table contains all configured default values
· Add – click this button to add new value to a table
· Delete – click this button to delete any of the configured records from a table
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
26
Figure 13 – The Add settings tab
6.3 Saving
After you have selected the Save Plan to CQ or Save Selection to CQ option from the
menu, the Save dialog opens (see Figure 14 – Launching the Export dialog). The dialog contains
the folowing elements:
· The text box with a log of save operation
· The Start button to launch saving
· The Stop button to stop saving
· The Close button to close the Save dialog
· The Change state if task assigned option – if a resource is assigned for a
task, the ClearQuest request is converted into a next state by the Assignee
action
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
27
Figure 14 – Launching the Export dialog
Export log is displayed in the following format (see Figure 15 – Export log):
Figure 15 – Export log
6.4 Importing
The Import dialog opens when you select the Import to MSP or Import child records
option from the menu (see Figure 16 – Launching the Import dialog). The dialog contains the
following elements:
· The text box with a log of import operation
· The Start button to launch importing
· The Stop button to stop importing
· The Close button to close the Import dialog
· The Use default query option– if this option is selected, the import
operation will be performed using the query defined in the Default query
field on the Add settings tab
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
28
Figure 16 – Launching the Import dialog
If you click Start with the Use default query option not selected, the ClearQuest filter
form will open (see Figure 17 – Selecting requests for importing), otherwise the form will not
open. To procced with imporing, you should select filtered records, and click OK.
Figure 17 – Selecting requests for importing
Import log is displayed in the following format (see Figure 18 – Import log):
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
29
Figure 18 – Import log
6.5 Refreshing
The Refresh dialog opens when you select the Refresh MSP plan or Refresh MSP
selection option from the menu (see Figure 19 – Launching the Synchronization dialog). The
dialog contains the following elements:
· The text box with a log of refresh operation
· The Start button to launch refreshing
· The Stop button to stop refreshing
· The Close button to close the Refresh dialog
Figure 19 – Launching the Synchronization dialog
The refresh log is displayed in the following format (see Figure 20 – Synchronization
log):
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
30
Figure 20 – Synchronization log
7. Adjusting Module SettingsTo open the form for adjusting the module settings, select Settings from the module
menu (see Figure 21 – Adjusting module settings).
Figure 21 – Adjusting module settings
To configure the module, you should fill in all the fields listed below. To save the
adjusted module settings, click Save. To cancel changes, click Cancel.
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
31
7.1 Main record settingsYou should configure the main fields for every request type that should be included into a
plan. The properties of the main fields are described in the Configuration section.
To configure the main fields, follow the steps below:
1. From the Record Type list, select the ClearQuest request type that corresponds to
the main request
2. From the Edit field, select a name of an action that will be used for editing the
ClearQuest records
3. From the Assignee action, select a name of an action that will be used for
converting the ClearQuest request into the next state upon assigning a resource for
a task
4. Select the Change only plan dates and resources option, if only planned dates
and resources should be changed upon saving values into the available ClearQuest
request
5. Select the Update plan dates and resources from CQ option, if changes of
planned dates and resources made in ClearQuest should be applied to
corresponding tasks of the MS Project plan upon refresh operation
6. From the Headline list, select a name of a field that corresponds to the main
ClearQuest request
7. From the Description list, select a name of a field that contains a detailed
description of the main ClearQuest request
8. From the Headline list, select a name of a field that corresponds to the main
ClearQuest request
9. From the Plan start date list, select a name of a field corresponding to a planned
date of starting work in the main ClearQuest request
10. From the Plan finish date list, select a name of a field corresponding to a planned
date of finishing work in the main ClearQuest request
11. From the Plan assignment work list, select a name of a field corresponding to a
planned work load in the main ClearQuest request
12. From the Actual start date list, select a name of a field corresponding to an
actual date of starting work in the main ClearQuest request
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
32
13. From the Actual finish date list, select a name of a field corresponding to an
actual date of finishing work in the main ClearQuest request
14. From the Actual assignment work list, select a name of a field corresponding to
an actual rate of work completion in the main ClearQuest request
15. From the Child record reference list, select a name of a field that represents a
reference to a child main ClearQuest request
16. From the Parent record reference list, select a name of a field that represents a
reference to the parent main ClearQuest request
17. From the Predecessors list, select a name of a field that represents a reference to
the preceding main ClearQuest request
7.2 Project record settings
To configure project request, follow the steps below:
1. From the Record Type list, select a name of a request type
2. From the Edit field, select a name of an action that will be used for generating
child records
3. From the Headline list, select a name of a field that corresponds to the project
ClearQuest request
4. From the Description list, select a name of a field that contains a detailed
description of the project ClearQuest request
5. From the Project managerlist, select a name of a field that corresponds to a
project manager of the project ClearQuest request
6. From the Plan start list, select a name of a field corresponding to a planned date
of starting work in the project ClearQuest request
7. From the Plan finish list, select a name of a field corresponding to a planned date
of finishing work in the project ClearQuest request
8. From the Plan cost list, select a name of a field corresponding to a planned costs
of works in the project ClearQuest request
9. From the Actual start list, select a name of a field corresponding to an actual date
of starting work in the project ClearQuest request
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
33
10. From the Actual finish list, select a name of a field corresponding to an actual
date of finishing work in the project ClearQuest request
11. From the Actual cost list, select a name of a field corresponding to an actual costs
of works in the project ClearQuest request
12. From the Task reference list, select a name of a field that represents a reference
to the main ClearQuest request
13. From the Project reference from main record list, select a name of a field that
represents a reference from the main ClearQuest request to the project ClearQuest
request
14. From the Percent list, select a name of a field corresponding to a work
completion rate in the project ClearQuest request
15. From the Statelist, select a name of a field corresponding to a work completion
rate in the project ClearQuest request
7.3 Additional record setting
Settings of additional requests can be of two types: main settings and relationship
settings. The main settings include a general description of the additional request, and relations
of the additional request to the main request, and a project. Relationship settings define relations
between additional requests.
To configure the main settings, follow the steps below:
1. From the Record Type list, select a name of a record type
2. From the Edit field, select a name of an action that will be used for binding child
requests
3. From the Headline list, select a name of a field that corresponds to the additional
ClearQuest request
4. From the Description list, select a name of a field that contains a detailed
description of the additional ClearQuest request
5. From the Resourcelist, select a name of a field that corresponds to an owner of
the additional ClearQuest request
6. From the Planned start date list, select a name of a field corresponding to a
planned date of starting work in the additional ClearQuest request
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
34
7. From the Planned finish date list, select a name of a field corresponding to a
planned date of starting work in the additional ClearQuest request
8. From the Child record reference list, select a name of a field that represents a
reference to a main ClearQuest request
9. From the Reference to main record list, select a name of a field that represents a
reference from the main ClearQuest request to the additional ClearQuest request
10. From the Project reference list, select a name of a field that represents a
reference to the project ClearQuest request
11. From the Reference from project list, select a name of a field that represents a
reference from the project ClearQuest request to the additional ClearQuest request
12. Click Add
To configure relations between additional requests, follow the steps below:
1. From the Record Type list, select the ClearQuest request type with the main
settings configured
2. From the Reference entity name list, select the name of the field
3. From the Reference field name list, select the name of the field
4. From the BackReference field name list, select the name of the field
5. From the Hard reference list, select the necessary relationship type
6. Click Add
To edit values in the table with results, follow the steps below:
1. In the table, select a line that to be edited
2. Change corresponding values
3. Click Edit
To delete lines from the table with results, follow the steps below:
1. In the table, select a line that to be deleted
2. Click Delete
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
35
7.4 Additional fields settings
To configure the additional fileds, you should add lines to the Add fields table. The
properties of the main fields are described in the Configuration section.
To configure the additional settings, follow the steps below:
1. From the Custom CQ Entity list, select a name of the ClearQuest request type
2. From the Name ClearQuest field list, select the name of the ClearQuest request
field
3. From the MSProject field list, select a name of the MS Project field
4. Select the necessary type of access to a field
5. If the field represents a list in the ClearQuest record, select the List option
a. If the field represents a reference to the record, select the Reference option
i. From the Record type list, select a type of the record that is referenced
by the field
ii. From the Field list, select the field of the record type defined above
(the value in this field is used for the reference)
iii. To create a filter, select the necessary Filter field that will be used for
filtering, and click +. In the Value field, type the value of the filter
after the = sign.
b. If the field represents a dynamic list, select the Named List field, and the list
name from the field that is being activated
6. Click Add
To edit values in the table with results, follow the steps below:
1. In the table, select a line that to be edited
2. Change corresponding values
3. Click Change
To delete lines from the table with results, follow the steps below:
1. In the table, select a line that to be deleted
2. Click Delete
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
36
7.5 Resource settings
To configure the resource settings, follow the steps below:
1. If users should be downloaded automatically into the plan, select the Autoload
users to MSProject plan option
a. If identification of owners should be performed using the ClearQuest entity
different from the Users entity, select the Use non-standard user entity option
i. From the Record Type list, select the necessary entity
ii. Select the Resource field that contains an owner’s name
iii. Select the Description field that contains a detailed description of an
owner
iv. Select the Email field that contains an owner’s e-mail
v. Select the Phone field that contains an owner’s phone number
b. If users should be downloaded from the global pool in MS Project Server, select
the Use db access for MSProject Server option
i. In the Database server field, define a name of server hosting MS Project
Server databases
ii. In the Database name field, define a name of the MS Project Server
database
iii. In the User name field, define a user name for accessing the database
server hosting MS Project Server
iv. In the Password field, define a password of the user defined above
2. From the Use plan assignment in list, select variants of planned workload change
3. From the Use actual work in list, select variants of actual workload change
7.6 Additional settings
To configure additional settings, follow the steps below:
1. Request is configured by default for every new project of MS Project
a. Click Select, and from the opened window, select a record type for whicha request should be selected (see Figure 22 – Choosing a record type forthe request), then click OK
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
37
Figure 22 – Choosing a record type for the request
b. In the opened window, select the necessary request, and click Run or
double-click the request to run it (see Figure 23 – Selecting a request);
then click OK
Figure 23 – Selecting a request
c. To remove association between the project and the request, click Clear
2. If the Every task have ClearQuest record option is selected, the ClearQuest
field in the plan will be ignored, and all tasks in the plan will be processed upon
save, import and refresh operations
3. If the Autocalculate off option is selected, automatic calculation will be switched
off before all operations that significantly increase the module performance when
there is a large number of tasks After the operations are completed, the project is
recalculated, and automatic calculation switches on
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
38
4. Special fields – all system fields necessary for the plan should be filed in System
fields should be used only for synchronization, and should not be changed
needlessly If some fields should not be displayed in the plan, they can be hidden
5. Using default values:
a. From the Field list, select a name of the ClearQuest field
b. In the Value field, enter the default value
c. Select the necessary method of using the field – always or empty
d. Click Add
e. To delete the unnecessary field, click Delete
8. Using the Program
8.1 Saving Tasks
For expoting the exisiting task plan from MS Project into ClearQuest, it is necessary that
the list of tasks have already been generated in MS Project, and properties necessary for
ClearQuest have been already set. The section below provides details on exorting the task plan:
1. Connect to the ClearQuest database (see Figure 24 – Connecting to the ClearQuest
database)
Figure 24 – Connecting to the ClearQuest database
After the connection is established successfully, the additional columns will be added
(see Figure 25 – Additional columns).
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
39
Figure 25 – Additional columns
2. Add new tasks, all necessary fields, and set a value of the ClearQuest field in
CQEntity
Figure 26 – New tasks for saving
3. Save the list of tasks (see Figure 27 – Saving tasks)
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
40
Figure 27 – Saving tasksIf the operation completes successfully, the following log will open (see Figure 28 –
Export log)
Figure 28 – Export log
4. After exporting, in the MS Project plan, system fields will be assigned to tasks (see
Figure 29 – Result of exporting tasks)
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
41
Figure 29 – Result of exporting tasks
5. After saving, in ClearQuest, new tasks will appear (see Figure 30 – New records in
ClearQuest)
Figure 30 – New records in ClearQuest
a. If the Predecessors field is configured in the module settings, then the
preceding records corresponding to tasks in the MS Project plan will be
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
42
automatically added into this field (see Figure 31 – Predecessor records in
ClearQuest)
Figure 31 – Predecessor records in ClearQuest
b. If the Child record reference field is configured in the module settings,
then the child records corresponding to tasks in the MS Project plan will be
automatically added into this field (see Figure 32 – Child records in
ClearQuest)
Figure 32 – Child records in ClearQuest
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
43
8.2 Creating a Query for Import in ClearQuest
The section below describes the steps you need to follow to create a query:
1. start ClearQuest and open the corresponding workspace
2. to create a new query, right-click the folder where the query will be stored, and click
New Query
Figure 33 – Creating a new query
3. In the Choose Record Type window, select a record type that should be
synchronized with the MS Project plan, and click OK
Figure 34 – Record type for query
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
44
4. Enter the query name, and click Enter
Figure 35 – Query name
5. To launch the ClearQuest query wizard, double-click the name of the new query, and
then click Next
Figure 36 – Query wizard – step 1
6. Select the list of fields displayed in the query resulting report , anmd click Next
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
45
Figure 37 – Query wizard – step 2
7. Select a filtering type, if necessary
Figure 38 – Query wizard – step 3
8. After the filter is configured, click Run. The query will be executed, and its result
will be displayed (see Figure 39 – Query result)
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
46
Figure 39 – Query result9. Save the query using the Save command in the File menu
8.3 Importing
To import tasks from ClearQuest, follow the steps below:
1. Connect to ClearQuest (see Figure 40 – Selecting an operation of importing tasks)
2. From the menu of the integration module, select the Import to MSP option (see
Figure 40 – Selecting an operation of importing tasks)
Figure 40 – Selecting an operation of importing tasks
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
47
3. If you want to use the query configured by default, the in the opened window (see
Figure 41 – Launching the Import dialog), select the Use default query option, and
click Start
Figure 41 – Launching the Import dialog
4. If you have not selected the Use default query option, then the window will open,
where you should select a query, run it, and, from the query results, select records that
should be imported into the MS Project plan (see Figure 42 – Selecting tasks for
importing )
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
48
Figure 42 – Selecting tasks for importing
5. In the Import window, in the log field, the list of imported tasks will be displayed
(see Figure 43 –Import log)
Figure 43 –Import log
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
49
6. In the plan, the imported tasks will be displayed (see Figure 44 –Result of importing
tasks)
Figure 44 –Result of importing tasks
8.4 Refreshing
The synchronization mode is necessary for refreshing tasks in the plan. To refresh tasks,
perform the following steps:
1. Open the up-to-date MS Project plan, and establish connection with ClearQuest
2. From the menu of the integration module, select the Refresh MSP plan option (see
Figure 45 – Selecting a synchronization operation)
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
50
Figure 45 – Selecting a synchronization operation
3. In the opened window (see Figure 46 – Launching the Synchronization dialog), click
Start
Figure 46 – Launching the Synchronization dialog
4. The Synchronization log window will open (see Figure 47 –Synchronization log)
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
51
Figure 47 –Synchronization log
8.5 Opening a User Interface Form of the ClearQuest Request from
MS Project
From MS Project, you can open the ClearQuest request form. To open the form, in the
plan, select a task that is associated with the ClearQuest request (for this record, the ClearQuest
identifier is defined); then, from the menu of the integration module, select Open CQ form (see
Figure 48 – Opening a ClearQuest request form). The ClearQuest form of the selected request
will open (see Figure 49 – ClearQuest request opened from MS Project).
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
52
Figure 48 – Opening a ClearQuest request form
Figure 49 – ClearQuest request opened from MS Project
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
53
8.6 Creating a New ClearQuest Request
The integration module supports creation of new ClearQuest request from MS Project. To
create a new request, follow the steps below:
1. From the menu of the integration module, select New
Figure 50 – Creating a new ClearQuest request
2. The dialog window with the list of all ClearQuest requests will open. Select the
necessary ClearQuest request, and click OK
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
54
Figure 51 – Selecting a type of the ClearQuest request
3. In the form of the new ClearQuest request, fill in all the fields, and click OK
Figure 52 – Form of a new ClearQuest request
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
55
8.7 Importing a License Key
Without a license key, the module works in demonstration mode (see Figure 53 –
Demonstration mode). In the demonstration mode, only the following functions are available:
· Importing ClearQuest requests into the MS Project plan
· Creating a new ClearQuest request
· Accessing forms of ClearQuest requests that were imported into the MS Project
plan
Figure 53 – Demonstration mode
To import a license key, follow the steps below:
1. From the menu of the integration module, select About
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
56
Figure 54 – Importing a license key
2. In the opened window, click Import license
Figure 55 – About window
3. select the location of the license key on the local disk
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
57
Figure 56 – Selecting a license key
4. After the license key is imported, restart MS Project to activate the key
Figure 57 – Successful import of the license key
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
58
List of FiguresFigure 1 – Basic operations .............................................................................................. 6
Figure 2 – Project-Request-Task relationship ................................................................... 7
Figure 3 – Project-Task relationship ................................................................................ 9
Figure 4 – Request-Task relationship ............................................................................. 11
Figure 5 – Task-Task relationship .................................................................................. 13
Figure 6 – Integrated menu ............................................................................................ 14
Figure 7 – ClearQuest session authorization window ..................................................... 15
Figure 8 – The Main tab ................................................................................................ 18
Figure 9 – The Project tab .............................................................................................. 20
Figure 10 – The Add record types tab ............................................................................ 21
Figure 11 – The Add fields tab....................................................................................... 23
Figure 12 – The Resources Tab...................................................................................... 24
Figure 13 – The Add settings tab ................................................................................... 26
Figure 14 – Launching the Export dialog ....................................................................... 27
Figure 15 – Export log ................................................................................................... 27
Figure 16 – Launching the Import dialog ....................................................................... 28
Figure 17 – Selecting requests for importing .................................................................. 28
Figure 18 – Import log ................................................................................................... 29
Figure 19 – Launching the Synchronization dialog ........................................................ 29
Figure 20 – Synchronization log .................................................................................... 30
Figure 21 – Adjusting module settings ........................................................................... 30
Figure 22 – Choosing a record type for the request ........................................................ 37
Figure 23 – Selecting a request ...................................................................................... 37
Figure 24 – Connecting to the ClearQuest database ....................................................... 38
Figure 25 – Additional columns ..................................................................................... 39
Figure 26 – New tasks for saving ................................................................................... 39
Figure 27 – Saving tasks ................................................................................................ 40
Figure 28 – Export log ................................................................................................... 40
Figure 29 – Result of exporting tasks ............................................................................. 41
Figure 30 – New records in ClearQuest ......................................................................... 41
CM-Consulthttp://www.rational-tools.com
http://www.cmcons.com/about_us/eng/
59
Figure 31 – Predecessor records in ClearQuest .............................................................. 42
Figure 32 – Child records in ClearQuest ........................................................................ 42
Figure 33 – Creating a new query .................................................................................. 43
Figure 34 – Record type for query ................................................................................. 43
Figure 35 – Query name ................................................................................................ 44
Figure 36 – Query wizard – step 1 ................................................................................. 44
Figure 37 – Query wizard – step 2 ................................................................................. 45
Figure 38 – Query wizard – step 3 ................................................................................. 45
Figure 39 – Query result ................................................................................................ 46
Figure 40 – Selecting an operation of importing tasks .................................................... 46
Figure 41 – Launching the Import dialog ....................................................................... 47
Figure 42 – Selecting tasks for importing ....................................................................... 47
Figure 43 –Import log .................................................................................................... 48
Figure 44 –Result of importing tasks ............................................................................. 48
Figure 45 – Selecting a synchronization operation ......................................................... 49
Figure 46 – Launching the Synchronization dialog ........................................................ 50
Figure 47 –Synchronization log ..................................................................................... 50
Figure 48 – Opening a ClearQuest request form............................................................. 51
Figure 49 – ClearQuest request opened from MS Project ............................................... 52
Figure 50 – Creating a new ClearQuest request .............................................................. 53
Figure 51 – Selecting a type of the ClearQuest request .................................................. 54
Figure 52 – Form of a new ClearQuest request .............................................................. 54
Figure 53 – Demonstration mode ................................................................................... 55
Figure 54 – Importing a license key ............................................................................... 56
Figure 55 – About window ............................................................................................ 56
Figure 56 – Selecting a license key ................................................................................ 57
Figure 57 – Successful import of the license key ............................................................ 57