cpc 02.14.2014 agenda item #14
TRANSCRIPT
El Paso Water UtilitiesEl Paso Water Utilities
Agenda
• Service Areas• Capital Improvement Plan• Update to Impact Fees
El Paso Water UtilitiesEl Paso Water Utilities
What is an Impact Fee?
A one-time fee paid by new or expanding development that represents the cost of the capacity needed to
serve that new development.
El Paso Water Utilities
Capital Improvement Plan
Water CIP ($ millions) Wastewater CIP ($ millions)
Service
Area 2009 CIP
Addition of JRWTP
Expansion 2014 CIP 2009 CIP Change 2014 CIP
Northeast $46.50 $15.00 $61.50 $13.55 $ - $13.55
Westside $40.22 $ - $40.22 $17.95 $ - $17.95
Eastside $23.45 $19.40 $42.85 $84.15 $ - $84.15
El Paso Water Utilities
Significant Update
• Expansion to Jonathan Rogers Water Treatment Plant− Northeast Service Area
» $15,000,000» 7.0 MGD
− Eastside Service Area» $19,400,000» 9.0 MGD
El Paso Water Utilities
2009 Impact Fees
Water Wastewater
Service Area
2009 Calculated Impact Fee
2009 Adopted Impact Fee
2009 Calculated Impact Fee
2009 Adopted Impact Fee
Northeast $1,570 $1,178 $388 $291
Westside $879 $659 $1,236 $927
Eastside $929 $697 $1,227 $920
El Paso Water Utilities
2014 Calculated Impact Fees
Water Wastewater
2014 Calculated Impact Fee 2014 Calculated Impact Fee Total
Service
Area
Maximum Impact
Fee
Impact Fee Credit
(11.7%)
Net Impact
Fee
Maximum Impact
Fee
Impact Fee Credit
(20.3%)
Net Impact
Fee
Net Impact
Fee
Northeast $3,561 ($416) $3,145 $538 ($109) $429 $3,574
Westside $1,044 ($122) $922 $1,711 ($347) $1,364 $2,286
Eastside $2,809 ($328) $2,481 $1,698 ($344) $1,354 $3,835
El Paso Water Utilities
2009 Adopted and 2014 Calculated Impact Fees
Water Wastewater
Service Area
2009 Adopted Impact Fee
2014 Calculated Impact Fee
2009 Adopted Impact Fee
2014 Calculated Impact Fee
Northeast $1,178 $3,145 $291 $429
Westside $659 $922 $927 $1,364
Eastside $697 $2,481 $920 $1,354