costestimatetemplate(epc)
TRANSCRIPT
-
7/27/2019 CostEstimateTemplate(EPC)
1/19
Cost ID Cost Description Cost Type
M.P Preliminary works Package Materials
M.M Services Package Materials
NL.P Earthwork & Spillway Civil Package Non Labor
NL.PI Powerhouse & Intake Structure Package Non Labor
E.WW Water to Wire Package Expenses
NL.R Reservoir Clearing Package Non Labor
E.IC Indirect Cost Expenses
E.BI Bonds & Insurance Expenses
L.E Engineering Non Labor
L.PM Project Management Labor
NL.OC Owners Costs Non Labor
NL.IH Intake, Headrace, Penstock & Tailrace Non Labor
L.PS2 Preliminary Study Labor
E.E Engineering ExpensesM.LM Line Material Non Labor
M.ET Mat'l & Equip Transportation Materials
L.CL Construction Labour Labor
NL.CE Construction Equipment Non Labor
NL.CC Camps & Catering Non Labor
NL.DM Depots, Mob & De-Mob Non Labor
L.PM2 Project Management Labor
E.M Microwave Communication System Expenses
NL.AC Lake Athabasca Crossing Non Labor
L.PS Preliminary Study Labor
M.E Engineering Materials
M.AS Apparatus & Structures Materials
M.CW Civil Works Materials
L.LE Labour & Equipment Labor
L.CO Commissioning (primarily labour) Labor
E.CO Contractor Overhead & Profit Expenses
-
7/27/2019 CostEstimateTemplate(EPC)
2/19
-
7/27/2019 CostEstimateTemplate(EPC)
3/19
-
7/27/2019 CostEstimateTemplate(EPC)
4/19
-
7/27/2019 CostEstimateTemplate(EPC)
5/19
Total cost Loading
Distribution
shape Min (%) Likely (%) Max (%)
6,574,150 Spread Triangle 90% 100% 110%
137,927,598 Spread Triangle 95% 100% 120%
105,345,010 Spread Triangle 70% 100% 130%
349,452,966 Normal
462,137,420 Spread Triangle 95% 100% 107%
382,979,400 Normal
66,603,951 Spread Triangle 98% 100% 102%
501,266,007 Spread Triangle 80% 100% 130%
417,266,007 Normal
84,000,000 Normal
140,000,000 Spread Triangle 97% 100% 105%
112,000,000 Spread Triangle 95% 100% 105%
28,000,000 Normal
3,249,000 Spread Triangle 95% 100% 110%19,491,000 Normal
160,548,000 Spread Triangle 90% 100% 105%
4,911,000 Normal
155,738,000 Spread Triangle 90% 100% 115%
68,498,000 Normal
68,300,000 Spread Triangle 95% 100% 110%
4,500,000 Normal
97,047,000 Spread Triangle 92% 100% 115%
14,557,050 Spread Triangle 90% 100% 113%
138,057,150 Normal
773,000 Spread Triangle 95% 100% 105%
4,641,000 Spread Triangle 90% 100% 110%
103,003,000 Spread Triangle 80% 100% 120%
15,322,000 Normal
5,424,000 Normal
2,320,000 Spread Triangle 85% 100% 110%
-
7/27/2019 CostEstimateTemplate(EPC)
6/19
-
7/27/2019 CostEstimateTemplate(EPC)
7/19
-
7/27/2019 CostEstimateTemplate(EPC)
8/19
-
7/27/2019 CostEstimateTemplate(EPC)
9/19
Plan: C:\Documents and Settings\swhite\My Documents\PertmasterBeta\Copy of ExampleRegiste
Cost ID M.P
Description Preliminary works Package
Cost 6,574,150.00
0.0%
ID Description Duration Start
A010 Project Start 0 13/10/2005
A020 Pre-Bid & Bid 60 13/10/2005 30.0%A030 Characterisation 10 13/10/2005
A040 Pre design & optioneeri 15 27/10/2005
A050 Feasibility & Design 50 27/10/2005 40.0%
A060 Engineering 225 05/01/2006
A070 Front End Eng Design 40 05/01/2006
A080 Scheme paper 60 02/03/2006
A090 Board approvals 10 02/03/2006
A100 Design development 80 16/03/2006
A110 Contract process 120 16/03/2006
A120 Safety case 54 16/03/2006
A130 External approvals 55 31/08/2006
A140 Procurement 180 16/11/2006
A150 Implementation 80 16/11/2006 20.0%
A160 Site mobilisation 110 16/11/2006
A170 Procure 3rd party contr 30 14/06/2007
A180 Construction 174 08/03/2007
A190 Reduce hazards 35 08/03/2007
A200 Clean strip out 40 19/04/2007
A210 Contaminated strip out 70 26/07/2007
A220 Decontaminate structur 10 04/10/2007
A230 Building demolition 20 18/10/2007
A290 Post Implementation 10 07/11/2007 10.0%
A240 Post Implementation fini 5 07/11/2007
A250 Final report, historic rec 5 14/11/2007
A310 Damages Start 0 09/12/2007
A320 Damages 1 09/12/2007
A011 Project Completion 0 21/11/2007
-
7/27/2019 CostEstimateTemplate(EPC)
10/19
-EPC.plan
M.M NL.P NL.PI
Services Package Earthwork & Spillway Civil Package Powerhouse & Intake Structure Package
137,927,598.00 105,345,010.00 349,452,966.00
0.0% 0.0% 0.0%
10.0% 50.0% 5.0%
5.0%5.0%
10.0% 5.0%
5.0%
5.0%
10.0% 5.0%
5.0%
5.0%
10.0% 5.0%
5.0%
5.0%
10.0% 5.0%
5.0%
50.0% 5.0%
10.0% 5.0%
5.0%
10.0% 5.0%
5.0%
10.0% 5.0%
10.0%
10.0%
-
7/27/2019 CostEstimateTemplate(EPC)
11/19
E.WW NL.R E.IC E.BI L.E
Water to Wire Package Reservoir Clearing Package Indirect Cost Bonds & Insurance Engineering
462,137,420.00 382,979,400.00 66,603,951.0 501,266,007.0 417,266,007.0
0.0% 0.0% 0.0% 0.0% 0.0%
12.0%
5.00% 20.00%30.0% 5.00% 30.00%
5.00% 20.00%
5.00% 20.00%
88.0% 5.00%
5.00%
5.00%
30.0% 5.00%
5.00% 30.00%
5.00%
5.00%
5.00% 40.00%
5.00%
5.00% 20.00%
5.00%
30.0% 5.00%
5.00%
5.00%
5.00%
10.0% 5.00%
20.00%
-
7/27/2019 CostEstimateTemplate(EPC)
12/19
L.PM NL.OC NL.IH L.PS2
Project Management Owners Costs Intake, Headrace, Penstock & Tailrace Preliminary Study
84,000,000.0 140,000,000.0 112,000,000.0 28,000,000.0
0.0% 0.0% 0.0% 0.0%
5.00% 20.00% 30.00%30.00% 5.00%
5.00%
5.00% 20.00% 40.00%
5.00%
5.00%
5.00%
30.00% 5.00%
5.00%
5.00%
5.00% 20.00%
5.00%
5.00%
5.00% 20.00% 20.00%
5.00%
30.00% 5.00%
5.00%
5.00%
5.00%
10.00% 5.00%
20.00% 10.00%
-
7/27/2019 CostEstimateTemplate(EPC)
13/19
E.E M.LM M.ET L.CL NL.CE
Engineering Line Material Mat'l & Equip Transportation Construction Labour Construction Equipment
3,249,000.0 19,491,000.0 160,548,000.0 4,911,000.0 155,738,000.0
0.0% 0.0% 0.0% 0.0% 0.0%
10.00% 50.00% 5.00% 12.00%
5.00%5.00% 30.00%
10.00% 5.00%
5.00%
5.00%
10.00% 5.00%
5.00%
5.00% 30.00%
10.00% 5.00%
5.00%
5.00%
10.00% 5.00%
5.00%
50.00% 5.00%
10.00% 5.00%
5.00% 30.00%
10.00% 5.00%
5.00%
10.00% 5.00%
10.00% 10.00%
10.00%
88.00%
-
7/27/2019 CostEstimateTemplate(EPC)
14/19
NL.CC NL.DM L.PM2 E.M
Camps & Catering Depots, Mob & De-Mob Project Management Microwave Communication System
68,498,000.0 68,300,000.0 4,500,000.0 97,047,000.0
0.0% 0.0% 0.0% 0.0%
5.00% 20.00%5.00% 30.00% 30.00%
5.00% 20.00%
5.00% 20.00%
5.00%
5.00%
5.00%
5.00% 30.00%
5.00% 30.00%
5.00%
5.00%
5.00% 40.00%
5.00%
5.00% 20.00%
5.00%
5.00% 30.00%
5.00%
5.00%
5.00%
5.00% 10.00%
20.00%
-
7/27/2019 CostEstimateTemplate(EPC)
15/19
NL.AC L.PS M.E M.AS M.CW
Lake Athabasca Crossing Preliminary Study Engineering Apparatus & Structures Civil Works
14,557,050.0 138,057,150.0 773,000.0 4,641,000.0 103,003,000.0
0.0% 0.0% 0.0% 0.0% 0.0%
5.00% 20.00% 5.00% 20.00%5.00% 5.00% 30.00%
5.00% 5.00% 20.00%
5.00% 20.00% 5.00% 20.00%
5.00% 5.00%
5.00% 5.00%
5.00% 5.00%
5.00% 5.00%
5.00% 5.00% 30.00%
5.00% 5.00%
5.00% 20.00% 5.00%
5.00% 5.00% 40.00%
5.00% 5.00%
5.00% 20.00% 5.00% 20.00%
5.00% 5.00%
5.00% 5.00%
5.00% 5.00%
5.00% 5.00%
5.00% 5.00%
5.00% 5.00%
20.00% 20.00%
-
7/27/2019 CostEstimateTemplate(EPC)
16/19
L.LE L.CO E.CO
Labour & Equipment Commissioning (primarily labour) Contractor Overhead & Profit
15,322,000.0 5,424,000.0 2,320,000.0
0.0% 0.0% 0.0%
5.00%
5.00% 15.00%30.00% 5.00%
5.00%
5.00% 20.00%
5.00%
5.00%
5.00%
30.00% 5.00%
5.00%
5.00%
5.00% 20.00%
5.00%
5.00%
5.00% 20.00%
5.00%
30.00% 5.00%
5.00%
5.00%
5.00%
10.00% 5.00%
19.00%
1.00%
-
7/27/2019 CostEstimateTemplate(EPC)
17/19
Version:
Created by:
Overview:
Instructions for use:
Create a cost
Add or updat
Load the cost
Pertmaster Cost
-
7/27/2019 CostEstimateTemplate(EPC)
18/19
1.9
Primavera Systems
This cost loading template allows you to add costs easily to tasks in a Pertmaster plan.
loading matrix
will be able to list the costs you want, or edit the ones that are already there. You will also be able to assign them to
the tasks in the plan.
1. Open the Pertmaster plan you will be loading the costs into.
2. Choose Tools | Create Cost-Loading Matrix.
3. The table of costs will appear in Excel.type. ,loading matrix, with the tasks listed on the left hand side. If there are any costs already in the plan they will
be listed across the top, and the matrix will be filled in to reflect which tasks they are assigned to in the
plan.
the costsOnce you have the cost loading matrix you can use it to change the costs and the tasks they are assigned to, before
loading them back into the Pertmaster plan.
4. In the Cost Estimate sheet, fill in your updated costs. You can:
Edit existing costs, types and uncertainty.Add new costs by adding them to the bottom of the sheet, or by inserting rows for them,
5. Press the Update Matrix With Costs button at the top of the sheet.
The matrix will be shown with your new / updated costs across the top.6. On the matrix, fill / update in the allocations of the costs to tasks in particular, allocate any new costs to the
If the tasks themselves have changed since the matrix was built, you need to load the costs backinto the Pertmaster plan, and then create a new cost loading matrix from there. This new cost matrix will
contain the updated tasks.
Note: When you are filling in the matrix, you don't need to assign costs to summary tasks unless you want the cost
directly against the summary.
s into the Pertmaster
Finally, when the cost loading matrix is complete, you can load the costs into the Pertmaster plan.
7. Check that the top of each column in the matrix is showing green, and then press the Load costs into
Pertmaster plan button at the top of the sheet.
8. Switch back to Pertmaster and check that the costs have been loaded correctly.
Loading Spreadsheet
-
7/27/2019 CostEstimateTemplate(EPC)
19/19
`