cost - supporting infrastructure development and good governance
TRANSCRIPT
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
1/16
The Construction Sector TransparencyInitiative
Petter Matthews
Director, CoST International Secretariat
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
2/16
Structure
International context
Overview of CoST programme
Institutional arrangements
Disclosure
Assurance Process
Multi-Stakeholder Group
Impact examples
Future trends
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
3/16
International Context
Growing global trend towards greater transparency and
accountability. Launch of a range of international initiatives aimed at improving
the quality of governance and obtaining better value from publicinvestment.
Renewed emphasis on investing in infrastructure to promoteeconomic growth and achieve international development goals.
Value of the global construction set to increase to $15 trillionannually by 2025 or 13.5 per cent of global GDP (GlobalConstruction 2025).
Mismanagement, inefficiency and corruption accounts for 10 to30 per cent of a construction project's value (OECD, TI).
Up to $5 trillion of investment could be lost each year by 2025unless something is done.
CoST is a response to this challenge.
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
4/16
Overview
CoST works with governments, industry and civil society todisclose information on public investment in infrastructure.
Promotes disclosure of project information with the aim of reducingmismanagement, inefficiency and corruption and improving
value for money.
CoST pilot project 20082011, full international programme
launched in 2012.
Registered in the UK as a not-for-profit organisation. It has a Boardof Directors and an International Secretariat.
Programmes in Afghanistan, El Salvador, Ethiopia, Guatemala,
Malawi, Philippines, United Kingdom, Vietnam, Tanzania, Uganda,Ukraine and Zambia.
National programmes steered by Multi-Stakeholder Groupscomprising representatives from government, industry and civilsociety.
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
5/16
Overview: Results chain
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
6/16
Institutional arrangements
A Multi-Stakeholder group (MSG), with representativesfrom government, industry and civil society, oversees theprogramme.
A National Secretariat is responsible to run theprogramme on a day-to-day basis.
The National Secretariat is located within a HostOrganisationthat can employ staff and enter intocontracts.
A good relationship between the MSG and the Host
Organisation is critical to the success of the programme. The CoST programme could eventually be established as
an independent legal entity.
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
7/16
Disclosure
Government procuring entities (PEs) are responsible fordisclosing information.
If there is no formal/legal requirement to discloseinformation, an Interim Disclosure Requirement (IDC) isestablished.
Eventually the Government should establish a FormalDisclosure Requirement (FDR).
Information is disclosed proactively(i.e. on a routinebasis) and reactively(i.e. on request).
PEs respond to questions from stakeholders.
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
8/16
Project phase Project information Contract phase Contract information
ProjectIdentification
Project owner
Sector, subsector
Project nameProject Location
Purpose
Project description
Procurement Procuring entity
Procuring entity contact details
Procurement processContract type
Contract status (current)
Number of firms tendering
Cost estimate
Contract administration entity
Contract titleContract firm(s)
Contract price
Contract scope of work
Contract start date and duration
ProjectPreparation
Project Scope (main output)
Environmental impact
Land and settlement impact
Funding sources
Project Budget
Project budget approval date
ProjectCompletion
Project status (current)
Completion cost (projected)
Completion date (projected)
Scope at completion (projected)
Reasons for project changes
Reference to audit and evaluationreports
Implementation Variation to contract price
Escalation of contract price
Variation to contract duration
Variation to contract scope
Reasons for price changes
Reasons for scope and durationchanges
Information for proactive disclosure
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
9/16
Project information Contract information
Identification and Preparation
Multi-year program & Budget
Project brief or Feasibility study
Environmental and social impact assessment
Resettlement and compensation plan
Project officials and roles
Financial agreement
Procurement plan
Project approval decision
Procurement
Contract officials and roles
Procurement method
Tender documents
Tender evaluation results
Project design report
Contract
Contract agreement and conditions
Registration and ownership of firms
Specifications and drawings
CompletionImplementation progress reports
Budget amendment decision
Project completion report
Project evaluation report
Technical audit reportsFinancial audit reports
ImplementationList of variations, changes, amendments
List of escalation approvals
Quality assurance reports
Disbursement records or payment certificates
Contract amendments
Information for reactive disclosure
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
10/16
Assurance Process
An Assurance Team reviews and reports on the
information disclosed to ensure compliance with thedisclosure requirement and highlight issues ofconcern.
The Assurance Team is approved by the MSG and
usually appointed by the Host Organisation. The Assurance Team is likely to be experienced
consultants or in some cases, a government agency.
It is appropriate to use a government agency whenthere is a high level of pubic trust in the agency.
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
11/16
Multi-Stakeholder Group
Brings together representatives from government,
industry and civil society. Usually operates on a voluntary basis to provide
oversight of the national programme.
It also has a crucial role in providing legitimacy to theCoST programme.
Some countries have opted to establish anindependent entity (usually an NGO) to coordinate
functions of the MSG and National Secretariat.
Multi-Stakeholder working has definite advantages,but it can also be time-consuming and difficult.
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
12/16
Impact: Cost savings in Ethiopia
Gindeber to Gobensa Road
Project, 33 km rural road, centralEthiopia
Assurance report identified anunimaginable volume of
excavation at design stage
MSG voiced concerns aboutinvestment be siphoned off
Ethiopian Roads Agencycommissioned alternative design
Original designer debarred for twoyears
Latest estimate is $3.7m costsaving on original price. CoST Ethiopia Team, Addis
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
13/16
Impact: Highlighting irregularities in Guatemala
Rehabilitation of Belize
Bridge, Guatemala City
Assurance processidentified irregularities inprocurement process
Special measuresintended for use duringhumanitarian disasters hadbeen used
MSG concerned that
process was non-competitive
General Directorate forRoads annulled andretendered the project.
Belize Bridge, Guatemala City
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
14/16
Impact: Building capacity in Malawi
Ali Hassan Mwinyi Road, Chichiri
CoST Malawi Baseline Study
identified average costoverruns of 97%
Government undertook areview of infrastructure
procurement Found that many problems
stemmed from poor projectplanning capacity
Separated BuildingsDepartment from Ministry ofPublic Infrastructure and gavepower to outsource criticalfunctions.
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
15/16
Future trends
Growing demand for corporate disclosure
Promotion of transparency in PPPs
Possibility of a construction transparency index
Mechanisms to avoid initiative overload
-
8/10/2019 CoST - Supporting Infrastructure Development and Good Governance
16/16
www.constructiontransparency.org