Construction Cost Estimating
Presented By:
This manual was created for online viewing. State specific information in this manual is used for illustration and is an example only.
mail: P.O. Box 509 Eau Claire, WI 54702-0509 • telephone: 866-352-9539 • fax: 715-802-1131email: [email protected] • website: www.lorman.com • seminar id: 406307
Saleh Mubarak, Saleh A. Mubarak, Ph.D.
Take advantage of this special offer for $50 off of a Lorman
live webinar!
C O N V E N I E N T:Lorman offers a wide variety of live webinars covering current issues affecting numerous industries. Learn the latest on legal compliance, cost savings and strategies, and business trends.
E X P E R I E N C E D :Learn about today’s hot topics presented by our expert speakers who represent prominent firms and have years of industry experience and knowledge.
C U R R E N T :In today’s business world, staying current of the ever-changing regulations is absolutely necessary in order to advance in your field. Earn continuing education credits, educate your entire team and ask questions of the speakers. For a complete listing of upcoming live webinars visit www.lorman.com.
SPECIAL OFFER
$50 OFFYOUR NEXT Discount Code Y1719669This offer can not be used in combination with other discounts.
LIVE WEBINAR
Construction Cost Estimating
©2019 Lorman Education Services. All Rights Reserved.
All Rights Reserved. Lorman programs are copyrighted and may not be recorded or transcribed in whole or part without its express prior written permission. Your attendance at a Lorman seminar constitutes your agreement not to record or transcribe all or any part of it.
Full terms and conditions available at www.lorman.com/terms.php.
This publication is designed to provide general information on the topic presented. It is sold with the understanding that the publisher is not engaged in rendering any legal or professional services. The opinions or viewpoints expressed by faculty members do not necessarily reflect those of Lorman Education Services. These materials were
prepared by the faculty who are solely responsible for the correctness and appropriateness of the content. Although this manual is prepared by professionals, the content and information provided should not be used as a substitute for professional services, and such content and information does not constitute legal or other professional
advice. If legal or other professional advice is required, the services of a professional should be sought. Lorman Education Services is in no way responsible or liable for any advice or information provided by the faculty.
This disclosure may be required by the Circular 230 regulations of the U.S. Treasury and the Internal Revenue Service. We inform you that any federal tax advice contained in this written communication (including any attachments) is not intended to be used, and cannot be used, for the purpose of (i) avoiding federal tax penalties imposed by
the federal government or (ii) promoting, marketing or recommending to another party any tax related matters addressed herein.
mail: P.O. Box 509 Eau Claire, WI 54702-0509 • telephone: 866-352-9539 • fax: 715-802-1131email: [email protected] • website: www.lorman.com • seminar id: 406307
Prepared By:Saleh Mubarak, Saleh A. Mubarak, Ph.D.
Learn What You Want, When You Want From Our Entire
Course Library
UNLIMITED ACCESS
ON-THE-GO LEARNING
We Offer Accredited Training Including CLE, CPE, HRCI, ENG and Many More
A L L - A C C E S S P A S SLORMAN EDUCATION SERVICES
Learn at Your Own Pace From Your Computer,
Tablet or Mobile Device
lorman.com/pass
GET CERTIFIED
Want to learn more? Contact a Lorman
All-Access Pass Specialist:
[email protected] or call 1-877-296-2169
CONSTRUCTION COST ESTIMATINGBy: Saleh Mubarak, Ph.D.
Lorman Education Services
1
2
3
© 2019 Lorman Education Services. All Rights Reserved.Lorman programs are copyrighted and may not be recorded or transcribed in whole or part without its express prior written permission. Your attendance at a Lorman program constitutes your agreement not to record or transcribe all or any part of it. This publication is designed to provide general information on the topic presented. It is sold with the understanding that the publisher is not engaged in rendering any legal or professional services. Although this manual is prepared by professionals, it should not be used as a substitute for professional services. If legal or other professional advice is required, the services of a professional should be sought.
This disclosure may be required by the Circular 230 regulations of the United States Treasury and the Internal Revenue Service. We inform you that any federal tax advice contained in this written communication (including any attachments) is not intended to be used, and cannot be used, for the purpose of (i) avoiding federal tax penaltiesimposed by the federal government or (ii) promoting, marketing or recommending to another party any tax related matters addressed herein.
The opinions or viewpoints expressed by the faculty members do not necessarily reflect those of Lorman Education Services. These materials were prepared by the faculty members who are solely responsible for their correctness and appropriateness.
Learn Effective Cost Estimating Techniques and Best Practices.
Cost estimating is one part of the total construction project management team effort. It impacts many other departments such as procurement, scheduling, accounting & finance, and other. Although cost estimators may need to know all the in’s and out’s in the process of cost estimating, everyone involved in the management of the construction project needs to be familiar with the cost estimate and the cost management process. Cost estimating is an important subject to those in the legal field because disputes arise typically in almost every construction project, with the cost as the core issue in the dispute. Also, this topic is recommended for architects and engineers who are involved in the design of construction projects as well as owners of such projects.
CourseDescription
4
LearningObjectives
At the end of the this course, participants will be able to:
1. You will be able to discuss the importance of construction cost estimating and the qualifications of
the estimator.
2. You will be able to review the definitions and concept of construction cost estimating including the
major cost categories.
3. You will be able to recognize the methodologies of both approximate and detailed estimates.
4. You will be able to describe how cost estimates must be adjusted for project conditions.
Course Outlines
• The mathematical intuition
• Introduction to Cost Estimating• Definitions and concepts
• Types of estimates and their uses
• Work Breakdown Structure (WBS) and the CSI MasterFormat,
• Direct versus indirect cost
• Estimating indirect cost• Bonds and insurance
• Risk Allocation
• Cash-flow diagrams
• Construction Cost Estimating• Estimating labor and equipment
• Cost estimating database/sources of pricing
• Cost of materials
• Approximate estimates
• Tips on quantity take offs and cost estimating
• A quick look at RSMeans online estimating
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 7
5
Mathematical Intuition
• The Mathematical Intuition is the ability to:
1. Instantly / quickly perform mathematical operations and obtain reasonable and relatively accurate (approximate) results
2. Make a good common sense judgement on answers, produced by self or others, and tell if the number is too low, too high, or about right.
• How does this apply to a construction cost estimator?
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 8
Impact of New Technology
• Replacement of human skills• Pros & cons
• How to deal with it?
• All physical and mental skills: use it or lose it!• Can you test yourself
occasionally?
• How can you maintain / improve your mental skills?
• 𝐴 3 2 5
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 9
6
Approximate Math
• Approximate math: • Why and when
• Rules, short-cuts, and tricks
• Approximate estimating:• Comparison to a known amount
• Using a Multiplier / proportions• Sacks of cement / concrete
https://www.quikrete.com/calculator/main.asp
• Dangers of relying completely on such tables
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 10
Approximate Math
• Use in order:1. Mental math
2. Pencil & paper
3. Calculator or computer
• Primary and secondary tools (check!)
• Apply common sense judgment
• Practice…
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 11
7
Wood Joists
Girder
Joist, spaced @ 16” o.c.
60 ft
26 ft
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 12
Proportions - Multiplier
How many stories in this building? How high is this pile (in
feet and meters)?
6 floors
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 13
8
How many windows are there in this building?
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 14
How Many Bricks in a Palette?
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 15
9
How Many Bricks in all Palettes?
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 16
Areas: The Dividing Method
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 17
Area
What is the total shaded area?
10
Areas: The Dividing Method
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 18
Area
AB A
B B
A
Area = A + B Area = A + B Area = A - B
Areas: The Dividing Method
• Total Area =
B * C + ½ * C * (A – B)
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 19
A
CB
11
Areas: The Strip
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 20
Method 1:Total Area = 40 * 24 – 34 * 18 = 348 FT2
16 * 10
24’18’
40’
3’
34’
Areas: The Strip
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 21
= ( 40’ + 18’ ) * 2 each
Method 2Total Area = 2 * (40 + 18) * 3 = 348 FT2
3’
24’18’
12
Math Intuition: One Last Thing
• Remember that a cost estimator’s “math intuition” proficiency depends not only on relative accuracy, but also on speed of processing!• Especially when you don’t have your tools!
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 22
Cost and Value
• Cost is the amount measured in money, cash expended or liability incurred, in consideration of goods and/or services received• From a total cost management perspective, cost may include any
investment of resources in strategic assets including time, monetary, human, and physical resources.
Definitions in this and the next two slides are from the AACE International Recommended Practice No. 10S-90
• Cost versus value• Value = Perceived benefits received / Perceived price paid
• Cost of a commodity is the same for all customers but its value differs depending on the individual’s need to this commodity
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 23
13
Definitions
• Cost Estimating is the determination of quantity and the predicting or forecasting, within a defined scope, of the costs required to construct and equip a facility, to manufacture goods, or to furnish a service.• Cost estimating is the process used to quantify, cost, and price the
resources required by the scope of an investment option or a project.
• Quantity Estimating is the process of measuring the work of the project in the form of a series of quantified work items.• The four measures (length, area, volume, each)
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 24
Definitions
• Total Cost Management (TCM) is the effective application of professional and technical expertise to plan and control resources, costs, profitability and risks
• As a predictive process, estimating must address risks and uncertainties. The outputs of estimating are used primarily as inputs for budgeting, cost or value analysis, decision making in business, asset and project planning, or for project cost and schedule control processesAACE® International Recommended Practice No. 10S-90, Rev. November 14, 2014
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 25
14
Definitions-2• Baseline Budget: The approved cost estimate of the project
including approved changes. It represents the price tag the contractor puts on the project and the owner approves
• Cost Control: The continuous practice of:1. Tracking actual cost
2. Comparing actual cost to the baseline budget, and finding / calculating cost variances
3. Analyzing cost variances to find the causes of any problems
4. Taking corrective action whenever and wherever needed
• Cost Monitoring / Cost Tracking
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 26
Definitions-3
• Schedule of Values: A listing of elements, systems, items, or other subdivisions of the work, establishing a value for each, the total of which equals the contract sum. The schedule of values is used for establishing the cash flow of a project and serves as the basis for payments requests
• In its simplest form (spreadsheet), it has the item code, description, quantity, unit, unit price, total cost (quantity x unit price)• The summation of all items total cost = contract sum
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 27
15
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 28
CONTRACT
LINE ITEM
NUMBER
(CLIN)
CONTRACT LINE ITEM (CLI) TITLE QUANTITY UNIT OF
MEASUREUNIT PRICE TOTAL PRICE
1 (CLI Title) $0.00
2 (CLI Title) ‐
$0.00
3 OPTION A, (CLI Title) $0.00
4 OPTION B, (CLI Title) ‐
5 OPTION C, (CLI Title) ‐
6 OPTION D, (CLI Title) ‐
7 OPTION E, (CLI Title) ‐
8 OPTION F, (CLI Title) ‐
9 OPTION G, (CLI Title) ‐
10 OPTION H, (CLI Title) ‐
$0.00
$0.00
TOTAL PRICE FOR ALL OPTIONS (Contract Line Item Numbers 3 through XX) ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
TOTAL PROPOSED PRICE ‐ BASE PLUS ALL OPTIONS (Contract Line Item Numbers 1 through XX) ‐‐‐‐‐‐‐‐‐‐‐
TOTAL BASE PRICE (Contract Line Item Number 1 through X) ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 29
APPLICATION NO:APPLICATION DATE:
PERIOD TO:PERCENT COMPLETE TO DATE:
A B C D E F G H I J
ITEM DESCRIPTIO N O F WO RK SCHEDULED MATERIALS TO TAL % BALANCE RETAINAGE
NO. VALUE FRO M PREVIO US THIS PERIO D PRESENTLY CO MPLETED (G ÷ C) TO FINISH (IF VARIABLE
APPLICATIO N STO RED AND STO RED (C - G) RAT E)
(D + E) (NOT IN TO DATE
D OR E) (D+E+F)
(Fill in & break down contract values)
(Add any change order(s) descriptions)
GRAND TOTALS 0 0 0 0 0 0 0 0
Contract Manager: Minimum performance requirements successfully completed and approved by: _____________________________________________ Date: ____/_____/_____
Schedule of Contract Values (This form must be completed by the Contractor for the Project.)
PROJECT NAME:
PROJECT #:
CONTRACTOR:
WO RK CO MPLETED
16
Cost Estimating
• Cost Estimating: From Whose Perspective?• Owner
• Contractor / Subcontractor
• Designer (engineer / architect)
• Financier
• Government (not as an owner)
• Investor / share holders
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 30
The “Balancing Errors” Rule
• While the price of one item may be too high or too low, the overall estimate should be pretty accurate
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 31
17
Time and Cost Management
Design
Preliminary Cost Estimate
Summary Schedule
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 32
Time and Cost Management
Design
Preliminary Cost Estimate
Summary Schedule
Bas
elin
e B
udge
tB
asel
ine
Sch
edul
e
Bidding / Negot
Det
aile
d E
stim
ate
Det
aile
d S
ched
ule
Contract
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 33
18
Time and Cost Management
Project Controls
Design Construction
Preliminary Cost Estimate
Summary Schedule
Bas
elin
e B
udge
tB
asel
ine
Sch
edul
e
Cost Control
Schedule Control
Bidding / Negot
Det
aile
d E
stim
ate
Det
aile
d S
ched
ule
Contract
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 34
The Golden Triangle
Cost
Scope
Quality
Schedule
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 35
19
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 36
Quality Time
Cost
Scope
The Golden Triangle: Another Perspective
Cost Estimate
Schedule
Procurement
Budgeting
Accounting
Project Control
Cost Estimating and Project Management
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 37
20
Project Costs to an Owner
1. Lost opportunity cost
2. Land, right-of-way (access), easements
3. Financing
4. Design fees
5. Permits and licenses
6. Construction
7. Project / Construction Management Services
8. Furniture and
Equipment
9. Start-up/Commissioning
10. Warranty
11. Operating and
maintenance
12. Rehabilitation/upgrading
13. Disposal
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 38
Types of Cost Estimates
• Approximate Estimates: Comparing to area unit (SF, M2) or functional unit price (MGD, $/key) obtained from previous similar projects1. Feasibility studies
2. Compare alternative projects / designs
3. Make initial financial arrangements
4. Provide a guaranteed maximum price (GMP) in cost-plus-fee contracts
• Definitive (Detailed) Estimates: based on take-offs from design documents1. Bidding on a project
2. Project control
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 39
21
Source: AACE International Recommended Practice No. 17R-97
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 40
Des
ign
Dev
elop
men
t
Source: Document Project Readiness by Estimate Class Using PDRI, by Syed H. Zaheer, and Craig Fallows
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 41
22
How Much Accuracy is Needed?
• How Much Accuracy is Needed?
• Accuracy versus effort / time required
• Is it worth it?
Approximate Estimates
Detailed Estimates
Preparation Effort
Expected Accuracy
≈ 70%
100%
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 42
To Bid or not to Bid?
• Factors influencing the contractor’s decision to bid or not to bid a project
1. Risk involved:a) Strength and stability of the companyb) Type of construction involved compared to the contractor's area of
expertisec) Location of the projectd) Size of the projecte) Type / complexity of the project
2. The project’s owner and architect/engineer, previous experience
3. The amount of work currently on hand / Bonding capacity4. The equipment and qualified personnel available5. Prevailing economic conditions / other bidders
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 43
23
Types of Contract Award Methods
1. Competitive Bidding• Pre- or post-qualification
2. Selective Bidding
3. Direct award
• Public versus private projects
• When Time Matters…
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 44
Types of Contract Agreements
• Fixed price contracts• Lump-sum
• Unit price
• Cost-plus-fee:• Cost plus a fixed (lump-sum) fee
• Cost plus a percentage fee
• Cost plus a sliding-scale fee
• Cost plus a fixed fee with a bonus / penalty
• Cost plus fee with a guaranteed maximum price (GMP)
• When do you recommend each type?
• Contract Templates: AIA, AGC, FIDIC, NEC
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 45
24
Project Delivery Methods
• Design-Bid-Build (also called traditional method) Method
• Design-Build (also called Design-Construct) Method• turnkey projects
• Construction Management Method• CM-at-risk
• Pure agency construction management (also called CM-for-fee or CM Agency)
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 46
Direct Versus Indirect Expenses
• How do you differentiate between a direct and indirect expense?
• Types of direct expenses:• Labor
• Materials
• Equipment
• Other (government fees, lab tests, etc.)
• Subcontracts
• Construction versus installed materials and equipment• The diesel generator example
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 47
25
Types of Indirect Expenses
• Types of Indirect Expenses:
1. Job (project) overhead
2. General (main office) overhead
3. Contingency
4. Profit: Related to risk taken and competition
5. Inflation and Escalation
• Managing risk in estimating contingency, profit, inflation, and
escalation
• Factors involved in calculating / estimating profit
• Allocating indirect expenses
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 48
Indirect Expenses AllocationUnallocated Total Partial
Allocation Allocation
Labor $375,211 $487,105 $456,564
Materials $422,735 $548,801 $514,392
Equipment $55,000 $71,402 $66,925
Subcontractor $165,000 $214,206 $200,775
Subtotal $1,017,946 $1,321,513 $1,238,657
Performance Bond $11,600 $0 $11,600
Insurance $30,538 $0 $30,538
Job overhead $55,987 $0 $0
General Overhead $50,897 $0 $0
Inflation / escalation $40,718 $0 $40,718
Contingency $50,897 $0 $0
Profit $62,929 $0 $0
Grand total $1,321,513 $1,321,513 $1,321,513
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 49
26
Risk Allocation
• The guidelines of the Construction Management Association of America:
1. Risk should be assigned to the party who can best control it
2. Risk should be assigned to the party who can bear the risk at the lowest cost
3. Risk should be assigned to the Owner when no other party can control the risk or bear the loss
4. Assumption of risk by the other parties to the construction process results in increases in cost (visible or hidden) to the Owner”
Capstone: The History of Construction Management Practice and Procedures, 2003 Edition, Construction Management Association of America, Inc. (CMAA)
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 50
Labor Analysis
• Labor source / pool: Union versus open-shop
• Labor Unit Price
• While crew cost may be constant, crew production fluctuates
based on many factors… so does the unit price!
• Factors influencing labor productivity
• Job conditions: Weather, site congestion, management type
• Crew conditions: Level of skill, equipment type and condition, overtime
• Design complexity and QA/QC requirements
• Productivity adjustment
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 51
27
Adjusting Estimates
1. Weather / climate
2. Labor skill level
3. Crew composition
4. Design complexity
5. Local regulations
6. Location
7. Season
8. Project size
9. Resources availability
10. Inflation / escalation
11. Expectations for world events
12. Prevailing economic conditions, risk taken, and expected profit
13. Other factors
• Note that some factors have to do with productivity while others don’t
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 52
Labor Productivity Examples
• Example: A crew of three brick layers and two helpers laid 1,200 bricks in 6 hours. What is the daily output and the Man-Hours/M Bricks
• Solution:• Hourly output = 1200 bricks/6 hours= 200 bricks/hour
• Daily output = 200 bricks/hour * 8 hours =1600 Bricks = 1.6 M Bricks
• Crew labor hours = 5 workers * 8 hours/day = 40 man-hours
• Labor-Hours = 40 man-hours / 1.6 M Bricks = 25 man-hours/M Bricks
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 53
28
Labor Productivity Examples
• Assume brick layer is paid $36/hour and helper is paid $30/hour• Crew daily cost = (3 x 36 + 2 x 30) x 8 = $1,344
• Cost per M Bricks = $1,344 / 1.6 = $840 (labor only)
• If productivity decreases by 20%:• Crew daily production = 1.6 *(100% – 20%) = 1.28 M Bricks
• Cost per M Bricks = $1,344 / 1.28 = $1,050 (labor only)
• Or, Cost per M Bricks = $840 / (1 – 20%) = $1,050 (labor only)
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 54
Labor Analysis
• Labor Wage Add-ons1. Workers’ Compensation (W.C.) Insurance: Differs among states
and depends on contractor’s Experience Modification Rate (EMR) rating• EMR depends on the contractor’s safety record for the past 3 years
• The average EMR is 1.00. The lower the EMR, the lower the insurance premium for the contractor
2. Government taxes• In the US: FICA (6.2%) + FICA medical (1.45%) = 7.65% taken from
the employee paycheck and matched by the employer, up to $132,900 of wages
3. Unemployment insurance: Differs among states
4. Any other applicable taxes
5. Employer provided benefits
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 55
29
Equipment Expenses
• Equipment Expenses:1. Depreciation
2. Maintenance
3. Investment (interest)
4. Taxes, insurance, and storage
5. Operating expenses (fuel, lubrication, tires, blade, etc.)
• Keep in mind that maintenance is both ownership and operation expense
• Equipment Rental
Ownership expenses
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 56
Bonds & Insurance
• Types of bonds:• Bid bond
• Performance bond
• Payment bond
• Who ultimately pays for all “assurances”?
• Most common types of insurance• Workers’ Compensation (W.C.)
• Builder's Risk
• Public liability
• Cost-trust relationship between owner and contractor
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 57
30
Performance Bond for Building Construction
Contract Amount Performance Bond for Building Construction
up to $100,000 2.50%
$100,001 - 500,000 $2,500 + 1.5% of amount over $100,000
$500,001 - 2,500,000 $8,500 + 1% of amount over $500,000
$2,500,001 - 5,000,000 $28,500 + 0.75% of amount over $2,500,000
$5,000,001 - 7,500,000 $47,250 + 0.7% of amount over $5,000,000
over $7,500,000 $64,750 + 0.6% of amount over $7,500,000
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 58
Organizing the Estimate
• Prior to 1995, there was no “industry standard” for how to organize different cost items
• Mostly, it was organized by type of materials• However, there were many challenges, such as:
• Members made of more than one material such as reinforced concrete
• Same material, wood for example, used in different ways: concrete formwork, framing, kitchen cabinets
• Electrical work that belong to mechanical (HVAC) work
• New and unique materials
• Until the Construction Specifications Institute, CSI, came up with a “MasterFormat” in 1995
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 59
31
First CSI MasterFormat, 1995
1.General Requirements
2.Site
3.Concrete
4.Masonry
5.Metals
6.Wood & Plastic
7.Thermal & Moisture Protection
8.Doors & Windows
9. Finishes
10. Specialties
11. Equipment
12. Furnishings
13. Special Construction
14. Conveying Systems
15. Mechanical
16. Electrical
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 60
The CSI MasterFormat 2004 - 2016
• Division 00 Procurement and Contracting Requirements
• Division 01 General Requirements• Division 02 Existing Conditions• Division 03 Concrete• Division 04 Masonry• Division 05 Metals• Division 06 Wood, Plastics, and Composites• Division 07 Thermal and Moisture Protection• Division 08 Openings• Division 09 Finishes• Division 10 Specialties• Division 11 Equipment• Division 12 Furnishings• Division 13 Special Construction• Division 14 Conveying Equipment• Division 21 Fire Suppression• Division 22 Plumbing• Division 23 Heating, Ventilating, and Air
Conditioning (HVAC)• Division 25 Integrated Automation
• Division 26 Electrical• Division 27 Communications• Division 28 Electronic Safety and Security• Division 31 Earthwork• Division 32 Exterior Improvements• Division 33 Utilities• Division 34 Transportation• Division 35 Waterway and Marine
Construction• Division 40 Process Integration• Division 41 Material Processing and Handling
Equipment• Division 42 Process Heating, Cooling, and
Drying Equipment• Division 43 Process Gas and Liquid Handling,
Purification, and Storage Equipment• Division 44 Pollution and Waste Control
Equipment• Division 45 Industry-Specific Manufacturing
Equipment• Division 46 Water and Wastewater Equipment• Division 48 Electrical Power Generation15 Divisions reserved for future expansion
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 61
32
CSI UniFormat
• UniFormat is a method of arranging construction information based on functional elements, or parts of a facility characterized by their functions, without regard to the materials and methods used to accomplish them. These elements are often referred to as systems or assemblies.
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 62
CSI UniFormat 2010
• Element A: Substructure
• Element B: Shell
• Element C: Interiors
• Element D: Services
• Element E: Equipment and Furnishings
• Element F: Special Construction and Demolition
• Element G: Site work
• Element Z: General
• It almost follows the construction chronological order
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 63
33
160000
100000
Tam
pa
Off
ice
Bld
g
110000
Foun
dat
ion/
Su
bstr
uct
ure
120000
Bui
ldin
g sh
ell
130000
Ext
erio
r cl
osur
e
140000
Inte
rior
fi
nish
es
150000
Mec
hani
cal
/ E
lect
rica
l
Site
Wor
k
121000
Col
umns
122000
Shea
r W
alls
123000
Ele
vate
d
Slab
s
124000
Bea
ms/
G
ird
ers
125000
CIP
Sta
irs
123100
Pos
t-te
nsio
ned
Sl
abs
123200
Flat
Sla
bs
123300
Waf
fle
Slab
s
123400
One
-way
Sl
ab a
nd
beam
123110
Fals
ewor
k
123120
Reb
ar
123130P
ost-
tens
ion
cabl
e
123140
Con
cret
e
123111
Soff
it a
nd
edge
s
123112
Scaf
fold
(t
able
s)
123113
Shor
es
123114
Res
hore
s
Level 0
Level 1
Level 2
Level 3
Level 4
Level 5
Work Breakdown Structure, WBS
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 64
The CSI Masterformat in WBS Format
Title Level
03 00 00 Concrete 103 10 00 Concrete Forming and Accessories 2
03 11 00 Concrete Forming 303 11 13 Structural Cast-in-Place Concrete Forming 4
03 11 13.13 Concrete Slip Forming 503 11 13.16 Concrete Shoring 503 11 13.19 Falsework 5
03 11 16 Architectural Cast-in Place Concrete Forming 403 11 16.13 Concrete Form Liners 5
03 11 19 Insulating Concrete Forming 403 11 23 Permanent Stair Forming 4
• Don’t forget level 0!
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 65
34
Project Breakdown: The Estimator vs. the Scheduler!• Estimators and schedulers could not agree on a
methodology to breaking down the project• For the estimator, the type of material is what matters, regardless to
where or when in the project it is installed
• For the scheduler, when and where matter more than the type of materials
• For example:• Suspended slabs must be separated by floor / location for the scheduler
but can be all combined for the estimator
• Reinforced concrete member can be considered one activity to the scheduler while the estimator has to separate the formwork, the rebar, and the concrete mix
• Now, BIM offers new method for the project breakdown that encompasses the estimator, the scheduler, and everyone else.
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 66
Model Estimating
• Model estimating is a concept that was developed and enabled with the computer technology.
• It’s concept is to provide a detailed take-off and costing to a known project. Later on, this estimate can be the base for estimating similar projects based with proper adjustments (for new project numbers and specs, location, and other items).• The user can also replace items / elements with other available via
a pull-down menu to suit the new project or the client’s demands
• Model estimating allowed the quick preparation of “semi-detailed” estimate with reasonable accuracy.• This accuracy depends on the accuracy of the original estimate and
comparison assumptions
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 67
35
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 68
Change Orders
• A change order is a formal written document, signed by the owner, directing the contractor to make changes from the original contract. After its approval (by the owner) it becomes a part of the contract’s legal documents. A change order can be used for adding, deleting, or substituting work items
• Number and amount of change order reflects one of the measures of the project’s success
• Why is a change order bad for the owner?
• Estimating change orders. Impact on schedule.
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 69
36
Cost of Changes
Time
$
Ability to influence design
Cost of change
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 70
Quantity Takeoffs
• The four basic measuring modes:• Count (each, dozen, etc.)
• Linear / lineal (meter, etc.)
• Area (square meter, etc.)
• Volume (cubic meters, etc.)
• Tools of takeoffs:• Manual / mechanical
• Semi-electronic
• Digitizers
• Directly from CAD or BIM
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 71
37
Tips on Takeoffs
• Rounding: Be reasonable
• Don’t depend completely on the automated process; apply common-sense judgment
• Eliminate / minimize the possibility of missing / duplicating an item
• Be well-organized. Make it easy for you or someone else to track / audit your trail
• Specify your source of information
• Missing or unclear information?
• Add reasonable allowance for waste
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 72
Timing of Project
• Effect of timing on estimate:• Prevailing economic conditions, demand and supply
• Trends, cycles, and future expectations
• Seasonal / after a disaster
• Availability of funds, interest rate
• Availability of resources
• Re-pricing estimates
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 73
38
Do My Numbers Change with Time?
• Yes: Prices of all resources
• Little: Productivity, insurance, overhead
• No: Quantities
• Other: Subjective terms such as profit,
contingency
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 74
Cost Estimating Databases
• Contractor’s own
• Software databases
• 3rd party databases
• Quotations from vendors• Document all info
• Expiration date
• Online databases updates
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 75
39
Pitfalls in Estimating1. Lack of accuracy in estimating quantities / missing an item
2. Lack of accuracy in estimating unit prices, especially major ones
3. Mathematical errors, too much dependency on computers and lack of mathematical intuition / common sense
4. Insufficient risk assessment of impact on cost:• Not accounting for inflation / escalation
• Not accounting for or insufficiently estimating contingency
• Over or underestimating the appropriate profit percentage
5. Not being familiar enough with location
6. Failing to read the contract or at least the relevant parts
7. Not accounting for waste (order quantity versus installed quantity)
8. Wrong or irrelevant comparison to another item
9. It didn’t cost me anything! I used my own equipment
10. For owners: Wrong type of contract
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 76
Are you Paying Attention to the Overall Picture?• It is true you must focus on “major items”, but you need to
be careful from:• Tendency to focus on the construction cost only (for owners)
• Tendency to focus on the immediate cost only
• Tendency to focus on “favorite” items
• Tendency to ignore time-value of the money and/or inflation
• Tendency to be a “perfectionist” and focus too much on small stuff
• The “emotional” factor
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 77
40
Cash Flow Analysis
• What are the types of cash flow diagrams?
• From whose point of view?
• Importance of cash flow analysis
• What is needed for preparing cash flow diagrams?• The CPM schedule tells us when activities are planned, and
• The cost estimate gives us the cost of these activities• the cost may not necessarily be distributed linearly over the duration of
the activity
• So the result is a prediction of spending amount by time period
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 78
Contractor’s Cash Flow Example• A contractor anticipates his
spending to be as shown in the 7-months project.
• Owner’s reimbursement lags by a month and owner retains 10% till the final and satisfactory completion of the project.
• Borrowing money cost the contractor 1% per month.
• Draw the cash flow diagrams and calculate the cost of borrowing money and maximum debt
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 79
Month Spending1 $175,0002 $210,0003 $265,0004 $272,0005 $207,0006 $155,0007 $93,000
Total $1,377,000
41
Contractor’s Cash Flow
Spending
Time
$
Reimbursement
Profit
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 80
Month Spending Reibursement Net Cash flowCumulative Cash flow Future Value *
1 ($175,000) 0 ($175,000) ($175,000) ($187,623.69)2 ($210,000) $157,500.0 ($52,500) ($227,500) ($55,729.81)3 ($265,000) $189,000.0 ($76,000) ($303,500) ($79,876.76)4 ($272,000) $238,500.0 ($33,500) ($337,000) ($34,860.23)5 ($207,000) $244,800.0 $37,800 ($299,200) $38,945.386 ($155,000) $186,300.0 $31,300 ($267,900) $31,929.137 ($93,000) $139,500.0 $46,500 ($221,400) $46,965.00
$221,400.0 $221,400 $0 $221,400.00Total ($1,377,000) $1,377,000 $0 $0 ($18,850.98)
Maximum amount of debt (required line of credit) = $337,000Total bid:
Total cost 1,377,000$ Profit @ 5% 68,850$ Cost of borrowing money 18,851$ Total bid = 1,464,701$ Say $1,465 k
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 81
42
Cash Flow Diagram
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 82
Net Cash Flow Diagram
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 83
43
Cumulative Cash Flow Diagram
5 September 2019 Construction Cost Estimating - Dr. Saleh Mubarak 84
Owner’s Cash Flow
5 September 2019
Construction Cost Estimating - Dr. Saleh Mubarak Slide No. 85
Time
$
44