cost and time case study on grade plant feed conveyor ......wea have decided to use chute 2278 - on...
TRANSCRIPT
COST AND TIME CASE STUDY
ON GRADE PLANT FEED
CONVEYOR HEAD CHUTE –
CHUTE # 2278
TABLE OF CONTENTS
Contents
Introduction ______________________________________________________________________________________________ 1
Chute Details ______________________________________________________________________________________________________1
Analysis ___________________________________________________________________________________________________ 2
Solution ___________________________________________________________________________________________________ 3
Data Synopsis ____________________________________________________________________________________________ 4
Wear pattern ______________________________________________________________________________________________________4
Replacement frequency ___________________________________________________________________________________________8
Cost comparison ________________________________________________________________________________________ 11
Time saving ______________________________________________________________________________________________ 12
Company Information __________________________________________________________________________________ 14
INTRODUCTION
Page 1
Introduction
WEBA South Africa have supplied over 260 chutes at Khumani Iron Ore in the past ten years. 77 of
which have been fully or partially converted to Quick Release lips.
WEBA have decided to use chute 2278 - On Grade Plant Feed Conveyor Head Chute to conduct a case
study proving the cost and time saving when converting to Quick Release Lips.
CHUTE DETAILS
Chute #: 2278 Installation Date: 07th March 2011
Conveyor: PB 03CV75 – On Grade Plant Feed Conveyor
QRL Installation Date:
February 2016
Belt size: 1530mm Tonnes received since installation of QRL
1 243 088.38
Belt speed: 3.12m/s
Max Lump size: 150mm
Tonnes per hour 3600
ANALYSIS
Page 2
Analysis
WEBA identified some concern with the standard conventional lip. Through research and development, we have improved the Quick release lips system.
Problem
Conventional Lip
- It is necessary to replace the full lip segment when it is only partially worn
- Skilled Artisan required to replace lip
- Laborious and time consuming to remove and install the conventional lips
- Specialised tools to be used to remove lip
- Only 4 – 10 lips could be changed in a maintenance shift
- Safety Requirements
- Hot works permit required
Figure 1: WEBA Conventional Lip
Showing all four segments requires replacement even though only a small part of segments “A” and “D” are worn
SOLUTION
Page 3
Solution
Solution
Quick Release Lip
- Only replace the worn lips
- No skilled Artisan required to replace lip
- Quicker to install
- No specialised tools to be used to remove lip
- Reduced risk
- Interchangeable
- Cost reduction
Figure 2: WEBA QR Lips
Showing only the worn lips need replacement
DATA SYNOPSIS
Page 4
Data Synopsis
WEAR PATTERN
The wear pattern was established and the wear on each lip or segment documented. Leg “A”
and leg “B” will see 50% each of 1,243,088.38 tonnes over a period of 3 (three) months.
Figure 3: Sectioned Internal ISO View
Showing internal wear pattern
Legend
< 10%
< 20%
< 30%
Leg A
Leg B
DATA SYNOPSIS
Page 5
Wear Pattern Established Derived from Site Inspection
Legend
< 10%
< 20%
< 30%
Figure 4: Sectioned ISO View Showing internal wear pattern
DATA SYNOPSIS
Page 6
Ore Flow through the Chute
Figure 5
DATA SYNOPSIS
Page 7
Table 1 – Tonnes per month for both legs – received from Khumani Control Room
Mass Flow Column Labels
Row Labels
[31] On Grade W&S Fresh Feed
[32] On Grade W&S Total Feed
[130] Total On Grade Reclaimed from On/Off
[187] Total On W&S Feed
P 2016_02 75856 193428 52983.33 128839.33
P 2016_03 246742 451162 40379.53 287121.53
P 2016_04 482856 780523 1999.2 484855.2
P 2016_05 341856 598289 416.32 342272.32
Grand Total 1147310 2023402 95778.38 1243088.38
DATA SYNOPSIS
Page 8
REPLACEMENT FREQUENCY
The replacement frequency was determined by the wear pattern, derived from the inspection
report and the average % when new lips should be ordered and when they should be
replaced.
WEBA recommend New QRL’s must be ordered once the lips is 60% worn.
DATA SYNOPSIS
Page 9
Table 2 – Showing the current % wear of the QRL and replacement frequency in months
LIP
QT
Y. Q
R1
00
-25
QT
Y W
orn
% W
orn
Repla
cem
ent
Fre
quency (
mo
nth
s)
QT
Y. Q
RR
400
-25
QT
Y W
orn
% W
orn
Repla
cem
ent
Fre
quency (
mo
nth
s)
QT
Y. Q
RR
450
-25
QT
Y W
orn
% W
orn
Repla
cem
ent
Fre
quency (
mo
nth
s)
Section C
CDB1 17 3 10 23 12 0 0 0
Section D
DR4 (N/S) 8 8 15 14
DR4 (F/S) 8 8 15 14
DR5 (N/S) 8 8 15 14
DR5 (F/S) 8 8 15 14
Section E
E1DB2 13 1 10 23 12 6 10 23
E1DB3 11 1 10 23 12 6 10 23
Section F
F1DB2 11 7 10 23 12 12 10 23
F1DB3 11 7 10 23 12 12 10 23
F1DB4 11 7 10 23 12 12 10 23
F1DB5 11 7 10 23 12 12 10 23
Section G
G1R1 (N/S) 12 8 20 11.5
G1R1 (F/S) 12 8 20 11.5
G1R2 (N/S) 12 8 20 11.5
G1R2 (F/S) 12 8 20 11.5
G1DB2 12 1 10 23 10 10 10 23
DATA SYNOPSIS
Page 10
Table 3 – Section H - Showing the current % wear of the QRL and replacement frequency in
months
LIP
QT
Y. Q
R1
00
-25
QT
Y W
orn
% W
orn
Repla
cem
ent
Fre
quency
(month
s)
QT
Y. Q
RR
300
-25
QT
Y W
orn
% W
orn
Repla
cem
ent
Fre
quency
(month
s)
QT
Y. N
ON
ST
D
QR
-LIP
S
QT
Y. N
ON
ST
D
QT
Y W
orn
% W
orn
Repla
cem
ent
Fre
quency
(month
s)
Section H
H1DB2 14 14 10 23 8 8 10 23 2278-QR2-
25 1 1 10 23
H1DB3 12 6 30 7 8 4 30 7 2278-QR3-
25 1 1 15 14
6 15 14 8 4 15 14
H1DB4 12 12 30 7 8 8 30 7 2278-QR4-
25 1 1 30 7
H1DB5 12 6 20 11.5 8 4 20 11.5 2278-QR5-
25 1 1 20 11.5
H1DB6 14 7 15 14 8 4 10 23 2278-QR6-
25 1 1 10 23
COST COMPARISON
Page 11
Cost comparison
Cost of Replacing Wear Components
Year Conventional Lips Quick Release Lips
% Cost Saving
Year 1 R44 340.00 R35 982.00 18%
Year 2 R190 351.52 R59 740.00 68%
Year 3 R44 340.00 R35 982.00 18%
*Costs determine at 2016 steel prices and does not include inflation
Price for
Full Set Conventional Lips
R230 873.05
Initial Price to
Convert to Quick Release Lips
R284 482.40
TIME SAVING
Page 12
Time saving
Removing and replacing a conventional lip is time consuming. The area around the lip needs
to be cleaned and the bolts removed before the new lip can be installed.
Removal of a conventional lip:
Material first needs to be
cleared on the top and bottom
of the base plate, then the nuts
need to be removed by means
of a cutting torch
TIME SAVING
Page 13
COMPANY INFORMATION
Quick Release Lips:
The removal procedure is
conducive to self-cleaning.
CONVENTIONAL LIP REPLACEMENT TIME
20 minutes per running meter
QUICK RELEASE LIP REPLACEMENT TIME
6.33 minutes per running meter
66% Time Saving
COMPANY INFORMATION
Page 14
Company Information
ALWIN NIENABER
TECHNICAL DIRECTOR
TED CRUICKSHANK PROJECT MANAGER
Tel +2711 827 9372
Fax +2711 827 6132
Mobile +27 82 779 0156
Email [email protected]
Tel +2711 827 9372
Fax +2711 827 6132
Mobile +27 82 334 9878
Email [email protected]
WEBA South Africa (Pty) Ltd
99 Nagington Road, Wadeville, Germiston, 1422
Tel 011 827 9372
Fax 011 827 6132
www.webachutes.com