cost and quantity estimation

Upload: harish4182

Post on 02-Jun-2018

250 views

Category:

Documents


2 download

TRANSCRIPT

  • 8/10/2019 Cost and Quantity Estimation

    1/71

    1

    CHAPTER-1

    INTRODUCTION TO ESTIMATION AND COSTING

    Introduction

    For all engineering works it is required to know beforehand the probable cost of

    construction is known as the Estimated Cost.If the estimated cost is greater than the

    money available, then attempts are made to reduce the cost by reducing the work or by

    changing the specifications. From this the importance of estimate for engineers may be

    understood. In preparing an estimate, the quantities of different items of work are

    calculated by simple mensuration method and from these quantities the cost is calculated.

    The subject of estimating is simple, nothing much to understand, but knowledge ofdrawing is essential. In preparing an estimate one has to go into the details of each item,

    big or small, nothing can be left or missed. Estimating makes one through, superficial

    work does not do, and one has to go deep into details.

    There is no hard and fast rule for finding out the dimensions from the drawings

    (plans, elevations, sections, etc.) but for quick certain principles may be followed. An

    estimator should picture the object (Building, structure, etc.) in his mind from the study

    of drawings and specifications.

    Our building is a G+3 Residential building located at Kukatpally Housing Board

    colony, phase IV, Hyderabad, 500072. Its land area is up to 260.13 sq.m., where it has

    got all the facilities like easy transport and scarce water. It is a place where the promoter

    can make a good amount of profit for his construction of work. The soil strength is good

    enough so that we don't have to go for deep foundations.

    We need to estimate the cost which is going to be incurred while during the

    construction of this building. In order to estimate the cost of a building we need to

    segregate the building into various item of work and to quantify it.

    Objective

    Objective is to quantify and arrive the cost of the project with minimum profit which is

    going to be incurred by the promoter for the construction of G+3 Residential building.

  • 8/10/2019 Cost and Quantity Estimation

    2/71

    2

    1.1 Definition of estimating

    Estimating is the technique of calculating or computing the various quantities and

    the expected Expenditure to be incurred on a particular work or project.

    In case the funds available are less than the estimated cost the work is done in part

    or by reducing it or specifications are altered, the following requirement are necessary for

    preparing an estimate.

    a) Drawings like plan, elevation and sections of important points.

    b) Detailed specifications about workmanship & properties of materials etc.

    c) Standard schedule of rates of the current year.

    1.2 Need for estimation

    1. Estimate gives an idea of the cost of the work and hence its feasibility can be

    determined i.e. whether the project could be taken up with in the funds available or not.

    2. Estimate gives an idea of time required for the completion of the work.

    3. Estimate is required to invite the tenders and Quotations and to arrange contract.

    4. Estimate is also required to control the expenditure during the execution of work.

    5. Estimate decides whether the proposed plan matches the funds available or not.

    1.3 Procedure of estimating or method of estimating.

    Estimating involves the following operations

    1. Preparing detailed Estimate.

    2. Calculating the rate of each unit of work

    3. Preparing abstract of estimate

    1.4 Data required to prepare an estimate

    1. Drawings i.e. plans, elevations, sections etc.

    2. Specifications

    3. Rates

  • 8/10/2019 Cost and Quantity Estimation

    3/71

    3

    1.4.1 Drawings

    If the drawings are not clear and without complete dimensions the preparation of

    estimation become very difficult. So, it is very essential before preparing an estimate.

    1.4.2. Specifications

    a) General Specifications: This gives the nature, quality, class and work and materials in

    general terms to be used in various parts of wok. It helps no form a general idea of

    building.

    b) Detailed Specifications: These gives the detailed description of the various items of

    work laying down the Quantities and qualities of materials, their proportions, the method

    of preparation workmanship and execution of work.

    1.4.3. Rates

    For preparing the estimate the unit rates of each item of work are required.

    1. For arriving at the unit rates of each item.

    2. The rates of various materials to be used in the construction.

    3. The cost of transport materials.

    4. The wages of labour, skilled or unskilled of masons, carpenters, Mazdoor, etc.

    1.5 Lumpsum

    While preparing an estimate, it is not possible to work out in detail in case of

    petty items. Items other than civil engineering such items are called lumpsum items or

    simply L.S.Items.

    The following are some of L.S. Items in the estimate.

    1. Water supply and sanitary arrangements.

    2. Electrical installations like meter, motor, etc.,

    3. Architectural features.

    4. Contingencies and unforeseen items.

  • 8/10/2019 Cost and Quantity Estimation

    4/71

    4

    In general, certain percentage on the cost of estimation is allotted for the above

    L.S.Items Even if sub estimates prepared or at the end of execution of work, the actual

    cost should not exceed the L.S.amounts provided in the main estimate.

    1.6Complete Estimate

    Most of the people think that estimate of a structure includes cost of land, cost of

    materials and labour. But many other direct and indirect costs included and are shown

    below

    The complete estimate

    Cost of land P.S & contingencies at 5% legal expenses cost of structure

    Actual cost Cost of Cost of Brochorage Cost of Cost of Consulting Permit feeof land Surveying verification materials labour Engineers fee for water,

    and execution electricity

    of deeds

    cost for cost for

    preparation of supervision

    plan, estimate anddesign

    Figure 1: Complete Estimate

    1.7 Work charged establishment:

    During the construction of a project considerable number of skilled supervisors,

    work assistance, watch men etc., are employed on temporary basis. The salaries of these

    persons are drawn from the L.S. amount allotted towards the work charged establishment.

    That is, establishment which is charged directly to work. An L.S.amount of 1 to 2% of

    the estimated cost is provided towards the work charged establishment.

  • 8/10/2019 Cost and Quantity Estimation

    5/71

    5

    CHAPTER-2

    MEASUREMENT OF MATERIALS AND WORKS

    2.1 Units of measurements

    The units of measurements are mainly categorized for their nature, shape and size

    and for making payments to the contractor and also. The principle of units of

    measurements normally consists the following:

    a) Single units work like doors, windows, trusses the etc., are expressed in numbers.

    b) Works consists linear measurements involve length like cornice, fencing, hand rail,

    bands of

    specified width etc., are expressed in (RM)

    c) Works consists areal surface measurements involve area like plastering, white

    washing,

    partitions of specified thickness etc., are expressed in square meters (m2)

    d) Works consists cubical contents which involve volume like earthwork, cement

    concrete,

    Masonry etc are expressed in Cubic meters.

  • 8/10/2019 Cost and Quantity Estimation

    6/71

    6

    Table 1: Units of Measurement

    S.No Particulars of items Units of

    measurement

    Units of

    payment

    1

    2

    3

    4

    5

    6

    Earth work:

    1. Earth work in Excavation2. Earthwork in filling in foundation

    trenches

    3. Earth work in filling in plinth

    Concrete:

    1. Lime concrete in foundation

    2. Cement concrete in Lintels3. R.C.C.in slab

    4. C.C. or R.C.C. Chujja, Sunshade

    5. L.C. in roof terracing

    (thickness specified)6. Cement concrete bed

    7. R.C. Sunshade (Specified

    Width & Height)

    Damp Proof Course (D.P.C):(Thickness should be mentioned)

    Brick work:

    1. Brickwork in foundation

    2. Brick work in plinth3. Brick work in super structure

    4. Thin partition walls5. Brick work in arches

    6. Reinforced brick work

    (R.B.Work)

    Stone Work:

    Stone masonry

    Wood work:

    1. Doors and windows framesor chowkhats, rafters & beams

    2. Shutters of doors and windows(thickness specified)

    3. Doors and windows fittings (like hinges,

    tower bolts, sliding bolts, handles)

    cum

    cum

    cum

    cum

    cumcum

    cum

    sqmcum

    cum

    sqm

    cum

    cumcum

    sqmcum

    cum

    cum

    cum

    sqm

    Nos.

    Per%cum

    Per%cum

    Per%cum

    percum

    percumpercum

    percum

    persqmper cum

    1rm

    persqm

    per cum

    per cumper cum

    per cumper cum

    per cum

    per cum

    per cum

    per sqm

    per Nos.

  • 8/10/2019 Cost and Quantity Estimation

    7/71

    7

    7

    8

    9

    10

    11

    12

    13

    14

    Steel work

    1. Steel reinforcement bars etc in R.C.C.and R.B.work.

    2. Bending, binding of steel Reinforcement

    3. Rivets, bolts, & nuts, Anchor bolts, Lewis

    bolts, Holding down bolts.4. Iron hold fasts

    5. Iron railing (height and types specified)6. Iron grills

    Roofing

    1. R.C.C. and R.B.Slab roof(excluding steel)

    2. L.C. roof over and inclusive of tiles or

    brick or stone slab etc (thickness specified)

    3. Centering and shuttering form work

    4. A.C.Sheet roofing

    Plastering, points finishing1. Plastering-Cement or Lime

    Mortar (thickness and proportion specified)

    2. Pointing3. White washing, colour washing, cement

    wash (number of coats specified)

    4. Distempering (number of coats specified)

    5.Painting, varnishing(no of coats specified)

    Flooring:1. 25mm cement concrete over 75mm limeconcrete floor (including L.C.)

    2. 25mm or 40mm C.C. floor

    3. Doors and window sills (C.C. or cement

    mortar plain)

    Rain water pipe /Plain pipe

    Steel wooden trusses

    Glass panels(supply)

    Fixing of glass panels or Cleaning

    Quintal

    Quintal

    QuintalQuintal

    QuintalSqm

    cum

    sqm

    sqm

    sqm

    sqm

    sqm

    sqm

    sqmsqm

    sqm

    sqm

    sqm

    1RM

    1No

    sqm

    Nos.

    per quintal

    per quintal

    per quintalper quintal

    per quintalper sqm

    per cum

    per sqm

    per sqm

    per sqm

    per sqm

    per sqm

    per sqm

    per sqmper sqm

    per sqm

    per sqm

    per sqm

    per RM

    per 1No

    per sqm

    per Nos.

  • 8/10/2019 Cost and Quantity Estimation

    8/71

    8

    2.2 Rules for measurement

    The rules for measurement of each item are invariably described in IS- 1200.

    However some of the general rules are listed below.

    1. Measurement shall be made for finished item of work and description of each item

    shall include materials, transport, labour, fabrication tools and plant and all types of

    overheads for finishing the work in required shape, size and specification.

    2. In booking, the order shall be in sequence of length, breadth and height or thickness.

    3. All works shall be measured subject to the following tolerances.

    i) Linear measurement shall be measured to the nearest 0.01m.

    ii) Areas shall be measured to the nearest 0.01 sq.m

    iii) Cubic contents shall be worked-out to the nearest 0.01 cum

    4. Same type of work under different conditions and nature shall be measured separately

    under separate items.

    5. The bill of quantities shall fully describe the materials, proportions, workmanships and

    accurately represent the work to be executed.

    6. In case of masonry (stone or brick) or structural concrete, the categories shall be

    measured separately and the heights shall be described:

    a) From foundation to plinth level

    b) From plinth level to first floor levelc) From First floor to second floor level and so on.

    2.3Methods of taking out quantities

    The quantities like earth work, foundation concrete, brickwork in plinth and super

    structure etc., can be workout by any of following two methods:

    2.3.1 Long wall - short wall method

    2.3.2 Centre line method.

    2.3.3Partly centre line and short wall method.

    2.3.1 Long wall-short wall method

    In this method, the wall along the length of room is considered to be long wall

    while the wall perpendicular to long wall is said to be short wall. To get the length of

  • 8/10/2019 Cost and Quantity Estimation

    9/71

    9

    long wall or short wall, calculate first the centre line lengths of individual walls. Then the

    length of long wall, (out to out) may be calculated after adding half breadth at each end to

    its centre line length. Thus the length of short wall measured into in and may be found by

    deducting half breadth from its centre line length at each end. The length of long wall

    usually decreases from earth work to brick work in super structure while the short wall

    increases. These lengths are multiplied by breadth and depth to get quantities.

    2.3.2 Centre line method

    This method is suitable for walls of similar cross sections. Here the total centre

    line length is multiplied by breadth and depth of respective item to get the total quantity

    at a time. When cross walls or partitions or verandah walls join with main wall, the centre

    line length gets reduced by half of breadth for each junction. Such junction or joints are

    studied carefully while calculating total centre line length .The estimates prepared by this

    method are most accurate and quick.

    2.3.3 Partly centre line and partly cross wall method

    This method is adopted when external (i.e., all-round the building) wall is of one

    thickness and the internal walls having different thicknesses. In such cases, centre line

    method is applied to external walls and long wall-short wall method is used to internal

    walls. This method suits for different thicknesses walls and different level of foundations.

    Because of this reason, all Engineering departments are practicing this method.

  • 8/10/2019 Cost and Quantity Estimation

    10/71

    10

    CHAPTER-3

    TYPES OF ESTIMATES

    3.1 Detailed estimate

    The preparation of detailed estimate consists of working out quantities of various

    items of work and then determines the cost of each item. This is prepared in two stages.

    i) Details of measurements and calculation of quantities

    The complete work is divided into various items of work such as earthwork

    concreting, brick work, R.C.C. Plastering etc. The details of measurements are taken

    from drawings and entered in respective columns of prescribed Performa. The quantities

    are calculated by multiplying the values that are in numbers Column to Depth column as

    shown below:

    Table 2: Details of measurements form:

    S.No Descriptionof Item

    Nos. Length(L)

    M

    Breadth(B)

    m

    Depth/Height

    (D/H) m

    Quantity ExplanatoryNotes

    ii) Abstract of Estimated Cost

    The cost of each item of work is worked out from the quantities that already

    computed in the details measurement form at workable rate. But the total cost is worked

    out in the prescribed form is known as abstract of estimated form.4%of estimated Cost is

    allowed for Petty Supervision, contingencies and Unforeseen items.

  • 8/10/2019 Cost and Quantity Estimation

    11/71

    11

    Table 3: Abstract Estimate Form:

    Item

    No.

    Description/

    Particulars

    Quantity Unit Rate Per

    (Unit)

    Amount

    The detailed estimate should accompanied with

    i) Report

    ii) Specificationiii) Drawings (plans, elevation, sections)

    iv) Design charts and calculations

    v) Standard schedule of rates.

    3.1.1. Factors to be considered While Preparing Detailed Estimate:

    i) Quantity and transportation of materials: For bigger project, the requirement of

    materials is more. Such bulk volume of materials will be purchased and transported

    definitely at cheaper rate.

    ii) Location of site: The site of work is selected, such that it should reduce damage or in

    transit during loading, unloading, stocking of materials.

    iii) Local labour charges: The skill, suitability and wages of local laborers are

    considered while preparing the detailed estimate.

    3.2 Data

    The process of working out the cost or rate per unit of each item is called as Data.In preparation of Data, the rates of materials and labour are obtained from current

    standard scheduled of rates and while the quantities of materials and labour required for

    one unit of item are taken from Standard Data Book (S.D.B)

  • 8/10/2019 Cost and Quantity Estimation

    12/71

    12

    3.2.1 Fixing of Rate per Unit of an Item:

    The rate per unit of an item includes the following:

    i) Quantity of materials & cost:The requirements of materials are taken strictly in

    accordance with standard data book (S.D.B). The cost of these includes first cost, freight,

    insurance and transportation charges.

    ii) Cost of labour:The exact number of labourers required for unit of work and the

    multiplied by the wages/ day to get of labour for unit item work.

    iii) Cost of equipment (T&P):Some works need special type of equipment, tools and

    plant. In such case, an amount of 1 to 2% of estimated cost is provided.

    iv)Overhead charges: To meet expenses of office rent, depreciation of equipment

    salaries of staff postage, lighting an amount of 4% of estimate cost is allocated.

    3.3 Methods of preparation of approximate estimate

    Preliminary or approximate estimate is required for studies of various aspects of

    work of project and for its administrative approval. It can decide, in case of commercial

    projects, whether the net income earned justifies the amount invested or not. The

    approximate estimate is prepared from the practical knowledge and cost of similar works.

    The estimate is accompanied by a report duly explaining necessity and utility of the

    project and with a site or layout plan. A percentage 5 to 10% is allowed forcontingencies. The following are the methods used for preparation of approximate

    estimates.

    3.3.1 Plinth area method

    3.3.2 Cubical contents methods

    3.3.3 Unit base method.

    3.3.1 Plinth area method:

    The cost of construction is determined by multiplying plinth area with plinth area

    rate. The area is obtained by multiplying length and breadth (outer dimensions of

    building). In fixing the plinth area rate, careful observation and necessary enquiries are

    made in respect of quality and quantity aspect of materials and labour, type of foundation,

    height of building, roof, wood work, fixtures, number of storeys etc.,

  • 8/10/2019 Cost and Quantity Estimation

    13/71

    13

    As per IS 3861-1966, the following areas include while calculating the plinth area of

    building.

    a) Area of walls at floor level.

    b) Internal shafts of sanitary installations not exceeding 2.0m2, lifts, air-conditioning

    ducts etc.,

    c) Area of barsati at terrace level: Barsati means any covered space open on one side

    constructed on one side constructed on terraced roof which is used as shelter during rainy

    season.

    d) Porches of non cantilever type.

    Areas which are not to include

    a) Area of lofts.

    b) Unenclosed balconies.

    c) Architectural bands, cornices etc.,

    d) Domes, towers projecting above terrace level.

    e) Box louvers and vertical sun breakers.

    3.3.2 Cubical Contents Method:

    This method is generally used for multistoried buildings. It is more accurate that

    the other two methods viz., plinth area method and unit base method. The cost of a

    structure is calculated approximately as the total cubical contents (Volume of buildings)

    multiplied by Local Cubic Rate. The volume of building is obtained by Length x breadth

    x depth or height. The length and breadth are measured out to out of walls excluding the

    plinth off set. The cost of string course, cornice, corbelling etc., is neglected.

    The cost of building= volume of buildings x rate/ unit volume.

    3.3.3 Unit Base Method:

    According to this method the cost of structure is determined by multiplying the

    total number of units with unit rate of each item. In case schools and colleges, the unit

    considered to be as 'one student' and in case of hospital, the unit is 'one bed'. the unit rate

    is calculated by dividing the actual expenditure incurred or cost of similar building in the

    nearby locality by the number of units.

  • 8/10/2019 Cost and Quantity Estimation

    14/71

    14

    CHAPTER-4

    MAIN ITEMS OF WORK

    4.1 EarthworkEarthwork in excavation and Earthwork in filling are taken out separately under

    different items, and quantities are calculated in cu m. Foundation trenches are usually dug

    to the exact width of foundation with vertical sides. Earth in excavation in foundation is

    calculated by taking the dimensions of each trench length x breadth x depth. Filling in

    trenches after the construction of masonry is ordinarily neglected. If the trench filling is

    accounted, this may be calculated by deducting the masonry from the excavation.

    Earthwork in plinth filling is calculated by taking by taking the internal

    dimensions in between plinth wall (length x breadth) which are usually less than the

    internal dimensions of the room by two off-sets of plinth wall i.e. 10 cm (4.5) and height

    is taken after deducting the thickness of concrete in floor, usually 7.5cm (3). If sand

    filling is done in plinth, this should be taken separately. The length and breadth for each

    filling may be same as the internal dimensions of the room if there is no off-set in plinth

    wall.

    Excavated earth is used in trench filling and plinth filling and usually not paid for

    separately, but may also be included under a separate item Return fill and ram or

    backfill and paid at a lesser rate .Extra earth if required for filling is brought from

    outside. If there is surplus earth after trench and plinth filling, this may be utilized in

    leveling and dressing of site or carted away and removed.

    4.2 Concrete In Foundation

    The concrete is taken out in cu m by length x breadth x thickness. The length and

    breadth of foundation concrete are usually the same as for excavation, only the depth or

    thickness differs. The thickness of concrete varies from 20 cm to 45 cm, usually 30 cm

    (9 to 18, usually 12). Foundation concrete consists of lime concrete or weak cement

    concrete.

  • 8/10/2019 Cost and Quantity Estimation

    15/71

    15

    PCCPlain Cement Concrete:

    After the process of excavation, laying of plain cement concrete that is PCC is

    done. A layer of 100mm was made in such a manner that it was not mixed with the soil.

    It provides a solid base for the foundation and a mix of 1:4:8 that is, 1 part of cement to 4

    parts of fine aggregates and 8 parts of coarse aggregates by volume were used in it. Plain

    concrete is vibrated to achieve full compaction.

    Concrete placed below ground should be protected from falling earth during and

    after placing.

    Concrete placed in ground containing deleterious substances should be kept free

    from contact with such a ground and with water draining there from during placing and

    for a period of seven days.

    Figure 2: P.C.C

    4.3 SolingWhen the soil is soft or bad, one layer of dry brick or stone soling is applied

    below the foundation concrete. The soling layer is computed in sq m (Length x Breadth)

    specifying the thickness.

    4.4 Damp Proof Course

    D.P.C. usually of 2.5 cm (1) thick rich cement concrete 1:1.5:3 or 2 cm, (3/4)

    thick rich cement mortar 1:2, mixed with standard waterproofing material, is provided atthe plinth level to full width of plinth wall , and the quantities are computed in sq m,

    (Length x Breadth). Usually D.P.C. is not provided at the sills of doors veranda openings,

    for which deductions are made. (One kg of Cem-seal or impermo or other standard

    waterproofing compound per bag of cement is generally used).

  • 8/10/2019 Cost and Quantity Estimation

    16/71

    16

    4.5 Masonry

    Masonry is computed in cu m (Length x Breadth x Height). Foundation and plinth

    masonry is taken under one item, and masonry in superstructure is taken under a separate

    item. In storied building the masonry in each story as ground floor above plinth level,

    first floor, etc. is computed separately. In taking out quantities the walls are measured as

    solid and then deductions are made for openings as doors, windows, etc. and such other

    portions as necessary. Masonry of different types or classes, masonry with different

    mortar, etc. are taken out under separate items.

    4.6 Lintels Over Openings

    Lintels are made of R.C.C or R.B., quantities are calculated in cu.m. Length of the

    lintel is equal to the clear spanplus two bearings. If dimension of bearings are not giventhe bearing may be taken as same as the thickness of lintel with a minimum of 12cm

    (4.5).

    4.7 R.C.C and R.B. work

    R.C.C and R.B work may be in roof or floor slab, in beams, lintels, columns,

    foundations, etc. and the quantities are calculated in cu m. Length, breadth and thickness

    are found correctly from the plan, elevation, and section or from other detailed drawings.

    Bearings are added with the clear span to get the dimensions. The quantities are

    calculated in cu m exclusive of steel reinforcement and its being but inclusive of

    centering and shuttering and fixing and binding reinforcement in position. The

    reinforcement including its taken up separately under steel, if other details are not given.

    The volume of steel is not required to be deducted from the R.C.C. or R.B.

    Columns:

    Columns are the vertical members which are used to transfer the loads from the

    roof beams to the footings. Based on the loads different sizes of columns are designed.

    The various sizes of columns are used in our site those are 750x400, 400x600, 250x900,

    230x300mm etc.

  • 8/10/2019 Cost and Quantity Estimation

    17/71

    17

    Roof Beams:

    Roof beams are horizontal members which transfers the loads from the slab to

    columns. Based on the loads different sizes of roof beams are designed. The various

    sizes of roof beams are used in our site those are 400x600, 400x750, 250x750mm etc.

    Slabs:

    Slab covers over roof beams which can take the live loads and transfers it to the

    roof beams.

    Generally the slabs are divided into two categories. When the ratio of long span

    to short span is greater or equal to 2 then the slab is known as single way slab, when the

    ratio of long span to short span is less than 2 then the slab is known as two way slabs.

    R.C.C and R.B. work may also be estimated inclusive of steel and centering and

    shuttering for the complete works, if specified.

    Centering and shuttering (from work) are usually included in the R.C.C or R.B.

    work, but may also be taken separately in sq m of surface in contact with concrete.

    In R.C.C work plastering is not taken separately, but the exposed surface are

    finished with thin rich cement sand mortar plastering to give smooth and even surface ,

    which usually is not taken into consideration.

    Reinforcement:

    Steel reinforcements are used, generally, in the form of bars of circular cross

    section in concrete structure. They are like a skeleton in human body. Plain concrete

    without steel or any other reinforcement is strong in compression but weak in tension.

    Steel is one of the best forms of reinforcements, to take care of those stresses and to

    strengthen concrete to bear all kinds of loads. Grade Fe 415 is being used most

    commonly nowadays. This has limited the use of plain mild steel bars because of higher

    yield stress and bond strength resulting in saving of steel quantity. Some companies

    have brought Thermo Mechanically Treated (TMT) and Corrosion Resistant Steel (CRS)

    bars with added features. Among these types we used TMT bars in our construction.

  • 8/10/2019 Cost and Quantity Estimation

    18/71

    18

    Figure 3: Slab Reinforcement

    Terms Used In Reinforcement:

    Bar-bending-schedule

    Bar-bending-schedule is the schedule of reinforcement bars prepared in

    advance before cutting and bending of bars. This schedule contains all details of size,

    shape and dimension of bars to be cut.

    Lap length

    Figure 4: Lap Joint

    Lap length is the length overlap of bars tied to extend the reinforcement

    length. Lap length is about 50 times the diameter of the bar is considered safe. Laps of

    neighboring bar lengths should be staggered and should not be provided at one level/line.

  • 8/10/2019 Cost and Quantity Estimation

    19/71

    19

    At one cross section, a maximum of 50% bars should be lapped. In case, required lap

    length is not available at junction because of space and other constraints, bars can be

    joined with couplers or welded (with correct choice of method of welding).

    Anchorage Length

    This is the additional length of steel of one structure required to be inserted

    in other at the junction. For example, main bars of beam in column at beam column

    junction, column bars in footing etc. The length requirement is similar to the lap length

    mentioned in previous question or as per the design instructions

    Figure 5: Anchorage

    Cover Block

    Cover blocks are placed to prevent the steel rods from touching the

    shuttering plates and thereby providing a minimum cover and fix the reinforcements as

    per the design drawings.

    The cover blocks used for different individuals are:

    Footings 40mm

    Columns 40mm

    Slabs 15mm

    Beams 25mm

    Retainingwall 25mm for earth face

    20mm for other face

  • 8/10/2019 Cost and Quantity Estimation

    20/71

    20

    Figure 6: Cover Block

    4.8 Flooring and Roofing

    (i) Ground FloorThe base lime concrete and floor finishing of C.C. or stone or

    Marble or Mosaic, etc. are usually taken as one job or one item (combined in one item)

    and the quantity is calculated in sq m multiplying the length and breadth. The length and

    breadth are measured as inside dimensions of wall to wall of superstructure. Both the

    works of base concrete and floor finishing are paid under one item.

    (ii) First floor, Second floor, etc.Supporting super structure is taken separately

    is cu.m. as R.C.C., R.B. etc.. and the floor finishing is taken separately in sq m as 2.5 cm

    or 4 cm C.C. (Cement Concrete) or marble or Mosaic, etc. if a cushioning layer of lime

    concrete is given in between the slab and the floor, the cushioning concrete may be

    measured with the floor under one item or taken separately.

    (iii) RoofSupporting structure is taken separately in cu.m and the lime concrete

    terracing is computed in sq. M with thickness specified, under a separate item including

    surface rendering smooth. The compacted thickness of lime concrete terracing is 7.5 cm

    to 12 cm. L.C. terracing may also be calculated in cu m with average thickness.

    4.9 Plastering and Pointing

    Plastering usually 12mm (0.5) thick is calculated in sq m. For walls the

    measurements are taken for the whole face of the wall for both sides as solid, and

    deductions for openings are made. Plastering of ceiling of 12mm thick is computed in sq

  • 8/10/2019 Cost and Quantity Estimation

    21/71

    21

    m under a separate head as this work is done with rich cement mortar. For R.C.C work

    usually no plastering is allowed but for fair finish a thin plaster of rich cement mortar

    may be allowed which should not be taken in the measurement separately.

    Pointing Pointing in walls is calculated in sq m for whole surface and deductions

    similar to plastering are made.

    4.10 Columns

    Columns are the vertical members which are used to transfer the loads from the

    roof beams to the footings. Based on the loads different sizes of columns are designed.

    The various sizes of columns are used in our site those are 750x400, 400x600, 250x900,

    230x300mm etc.

    4.11 Doors and WindowsWood Work- Chowkhat or Frame

    Door and window frames or Chowkhats are computed in cu.m. Length is obtained

    by adding all the members of the chowkhat, top and two verticals if there is no sill

    member, and adding bottom also if there is sill, and the length is multiplied by the two

    dimensions of the cross section of the member.

    4.12 White washing or Colour Washing or Distempering and Painting

    The quantities are computed in sq m and are usually same as for plastering. The

    inside is usually white washed or distempered and this item will be same as for inside

    plaster. The outside is colour washed and the quantities of colour washing will be same as

    for the outside plaster. Number of coats of white washing or colour washing is taken as

    one job or work and the rates cover for number of coats which should not be multiplying

    factor. The number of coats should be mentioned in the item. Deductions are dealt in the

    same manner as for plastering.

    Painting or Varnishing of doors and windows are computed in sq m, the

    dimensions should be taken for outer dimensions of the chowkhat i.e., outer dimensions

    of doors and windows. The area is measure flat. No separate measurement is taken for the

    chowkhat, the area is same as the area of opening.

  • 8/10/2019 Cost and Quantity Estimation

    22/71

    22

    The methods of measurement of white washing, colour washing, distempering

    and painting of building surfaces in civil engineering works.

    The following rules are to be followed:

    1 Clubbing of Items

    Items may be clubbed together provided these are on the basis of detailed

    description of item, stated in this standard.

    2 Booking of Dimensions

    In booking of dimensions the order shall be consistent and generally in the

    sequence of length, breadth or width and height.

    3 Descriptions of Items

    Description of each item shall unless otherwise stated, be held to include, where

    necessary, conveyance; delivery; handling; unloading; storing; waste; return of packings;

    necessary scaffolding; protective cover; and cleaning stains from floors, walls, glass

    panes, etc.

    4 Bills of Quantities

    Item of work shall fully describe materials and workmanship, and accurately

    represent the work to be executed.

    5 Numbers of CoatsDecorative treatment shall be fully described stating the number of coats in each

    case.

    6 Preparatory Works

    Preparatory work, such as brooming down, steel wire brushing, scrapping

    washing and rubbing down, shall be described and included in the main item. Preparatory

    work on new surfaces and primary coats, if any, shall be described and included in the

    main item.

    7 Classifications

    Various decorative treatments shall be measured separately under the various

    classifications as given below and materials and type of surfaces to be treated shall be

    fully described:

  • 8/10/2019 Cost and Quantity Estimation

    23/71

    23

    a) Whitewash, colour wash, etc;

    b) Non-washable distemper;

    c) Washable distemper;

    d) Waterproof paint (colour/colourless);

    e) Chalk whiting to cloth or hessian surface;

    f) Linseed oil and cement to steel and iron work; and

    g) Cement slurry wash.

    Priming and alkali neutralizing treatments, scrapping of surface, washing surfaces

    spoilt by smoke soot, removal of oil and grease spots, treatment for disinfection with

    efflorescence, moulds moss, fungi, algae and kitchen shall be measured separately and

    materials described.

    8 Walls, Ceilings, etc.

    Work on walls, ceilings and sloping roofs shall each be measured separately.

    9 Old Treated Surfaces

    Work on old treated surfaces shall be measured separately and so described.

    4.13 Lump-sum Item

    Sometimes a lump-sum rate is provided for certain small items for which detailed

    quantities cannot be taken out easily or it takes sufficient time to find the detail, as front

    architectural or decoration work of a building, fire-place, site cleaning and dressing etc.

    4.14 Electrification, Sanitary and Water supply Works

    For Sanitary and Water supply works 8% and for electrification 8% of the

    estimated cost of the building works are usually provided in estimate.

  • 8/10/2019 Cost and Quantity Estimation

    24/71

    24

    CHAPTER-5

    RATE ANALYSIS

    5.1 Definition

    In order to determine the rate of a particular item, the factors affecting the rate of

    that item are studied carefully and then finally, a rate is decided for that item.This process

    of determining the rate of an item is termed as the analysis of rate or rate analysis.

    5.2 Purposes of rate analysis

    Following are the two main purposes of carrying out the rate analysis of an item :

    1. To determine the actual cost per unit of item ; and

    2. To examine the item for economic processes and economic uses of materials

    involved in making the item.

    5.3 Factors affecting Rate Analysis

    The factors which affect the rare analysis of an item can broadly be divided into the

    following two categories.

    1. Major factors

    2. Minor factors

    1. Major factors : There are mainly two factors on which the rate of an item

    depends namely.

    i) Materials

    ii)

    Labour

    Hence, in ordinary procedure of rate analysis, only these two forces are taken into

    account and the rate of an item is derived. The points to be remembered for these two

    factors will now be briefly mentioned.

  • 8/10/2019 Cost and Quantity Estimation

    25/71

    25

    Materials :The quantities of various materials required for the construction of an item

    can be easily worked out by knowing the specification of that item.The prices of various

    materials required are fixed. But their prices are variable from place to place and from

    time to time as they depend on the prevailing market conditions. Hence, before starting

    the rate analysis of an item, it is essential to collect the prices of such materials from the

    market at that instant.

    It is the duty of the person framing the rate analysis to see that the materials available in

    the market are in accordance with the specification of the item. It is also necessary to

    include a certain percentage for waste of all materials to cover breakages, losses, cutting

    waste, etc .However , the average percentage to be adopted for wastage will vary for

    different trades and operations. With the help of the quantities of various materials and

    prices of the materials, the cost of materials for a particular item can be calculated.

    Labour: The labour force will be necessary to arrange the materials in a proper way so

    that the item can be completed. For instance, heaps of bricks, cement and sand cannot be

    used in the construction of brickwall, unless some masons, coolies and bhisties are

    available. The amount of labour force required to carry out a unit of a particular item is

    decided from the past experience or in case of a complicated item, it is decided by

    carrying out a sample of that item. In any case , it is quite clear that the labour force

    required will depend on the efficiency of the labourers and hence, this force will be

    variable from place to place also, the price or wage of labour is a variable factor and will

    vary from place to place, person to person and time to time.Hence the efficiency of the

    labourer and the wage of the labourer should be properly studied before starting the rate

    analysis for a particular item, By knowing the amount of labour force and the wage of

    labourer, the cost of labour of a particular item is calculated.

    2) Minor factors: These are the factors which come into force under special

    circumstances and should, therefore, be given proper weight, when such conditions are to

    exist following are some of such factors.

  • 8/10/2019 Cost and Quantity Estimation

    26/71

    26

    i) Special equipment : If the execution of an item requires the use of some special

    equipment or plant, the cost of using such special equipment on the rental basis should be

    included in the rate analysis of that item.

    ii) Place of work :The site of work will also have some effect on the rate of an item

    under certain conditions. If it is too far, more amount will have to be spent on carting

    similarly, if it is situated in a highly congested area, it will not be possible to take the

    materials directly to the site. The materials will have to be stacked on the main road and

    then they will have to be taken in hand lorries. This will increase the cost of transport of

    the materials and consequently, the rates of the items are to be modified.

    iii) Nature of work :If the work consist of large quantities of the items , the rates may be

    less and vice versa.

    iv) Conditions of contract : If the conditions of contract are very stiff, the rates of the

    various items will be high and vice versa.

    v) Profit of the contractor :The usual percentage of the profit of the contractor is ten.

    But if it is more or less, the rate of the item will be correspondingly affected. The profit

    of the contractor will includes his overhead charges also. These overhead charges are to

    be reasonably ascertained and suitably allocated to various jobs carried out concurrently

    by the contractor. The overhead expences can broadly be divided into two categories.

    a) Expenses relating to the works such as expenses incurred for tools, testing , supervision ,

    insurance , amenities at site, power, plant , stores , etc.

    b) Expenses relating to the office establishment such as expenses incurred for postage , rent

    , travelling, satisfactory, taxes, telephone, etc.

    vi) Specifications :If the specifications of work provide for rigid type tolerances and

    superior quality turn out, the rates will be on the higher side.

    vii) Site conditions :If the site conditions are such that difficulties will be experienced

    during execution of work, such as foundations involving water troubles, the rates will be

    on the higher side, on the other hand, if site conditions are ideally suited for the

    construction activities, the contractor may quote slightly lower rates .

  • 8/10/2019 Cost and Quantity Estimation

    27/71

    27

    viii) Miscellaneous :The other remaining miscellaneous factors affecting rates of items

    include time of completion of the project, climatic conditions , reproduction of the

    contracting firm, discipline of the organization , etc.

    From the above discussion, it is clear that the accuracy of rate analysis will depend on the

    skill, knowledge, experience, precision and judgement of the person entrusted with the

    work of rate analysis.

    5.4 Importance of Rate Analysis

    The process of rate analysis gives a clear picture of various forces acting behind

    the performance of a particular item. It should be remembered that the rate analysis of

    any item is never complete, for instance, in the rate analysis of brickwork, a definite ratefor bricks is assumed. But this rate for bricks is derived by the manufacturer of bricks by

    his own rate analysis for preparing bricks. Thus, theoretically, the rate analysis of an item

    is incomplete, but in practice, it serves as a useful guide to arrive at a reasonable rate for

    a particular item.

    5.5 Essentials of Rate Analysis

    For arriving t the correct rate analysis of a particular item, the following essentials arenecessary for the person carrying out the rate analysis.

    1) Good knowledge of construction work and familiarity with the trade.

    2) Information regarding costs of materials, labour and equipment and

    3) Output of labourer i.e. task works per day for various trades.

    5.6 Schedule of Rates

    A schedule or list of rates of various items is prepared after the analysis of rates of

    these items. Such a document is known as the schedule of rates or S.O.R. It is prepared

    by large concerns or public bodies. It becomes very useful, especially deciding the rate

    of an extra item, carried out by the contractor.

  • 8/10/2019 Cost and Quantity Estimation

    28/71

    28

    Normally, a clause in the conditions of contract is inserted, stating that , any extra

    item that might occur during the execution of the work shall be paid as per rate in the

    schedule of rates.

    In some cases, the contractor may be asked to submit his tender by simply quoting

    the percentage above or below the S.O.R for carrying out the construction work.

    The schedule of rates consists of groups of items such as demolishing items,

    excavation items, concrete items, brickwork items, etc. and also information, regarding

    the present wages of labour and prices of different items , is given in it.

    As the rates of items mentioned in the schedule of rates are likely to vary, the

    schedule of rates is periodically revised, usually after three years.

    The Central Public Works Department ( CPWD ) if the premier construction

    organisation of the Govt.of India and it has been responsible for the planning and design,

    construction and maintenance of a variety of building projects like mass housing

    complexes, hospitals, educational institutions , sport complexes, highways, airports,

    industrial buildings, bridges, etc. Hence, the schedule of rates serves as an important

    document for the CPWD.

    The CPWD schedule of rates contains the basic rates of materials, labour,

    Carriage etc. of about 2500 items and the finished rates of about 3000 items of work

    covered under different subheads like building work, road work, water supply and

    drainage items etc. The rates of the finished items are worked out by the analysis of rates

    with the standard requirements of material, labour and necessary sundries like water

    charges, contractors profit, etc.

    Due to continuous changes in the market rates of materials, wages of labour, cost

    of carriage ,etc. the schedule of rates document requires revision frequently. The updating

    of this document manually proved to be extremely difficult task, as it involved careful

    analysis and thorough checking of several of items in the schedule. The use of computers

    was found to be an ideal solution in the preparation and quick updating of this document

    in minimum possible time without any chance of human errors.

  • 8/10/2019 Cost and Quantity Estimation

    29/71

    29

    The CPWD has evolved the coding procedure and file organization of the

    computer programme for the schedule of rates document. This is an important step in the

    modernisation of the public work system and perhaps, the CPWD is the first

    organization to take this measure in the country. It is likely that in future, an integrated

    package of an easily updatable all India schedule of rates can be developed and it will

    serve as an important national document useful for all the construction agencies in the

    country.

  • 8/10/2019 Cost and Quantity Estimation

    30/71

    30

    CHAPTER-6

    ANALYSIS

    PLANS

    &DRAWINGS

  • 8/10/2019 Cost and Quantity Estimation

    31/71

    31

  • 8/10/2019 Cost and Quantity Estimation

    32/71

    32

  • 8/10/2019 Cost and Quantity Estimation

    33/71

    33

  • 8/10/2019 Cost and Quantity Estimation

    34/71

    34

  • 8/10/2019 Cost and Quantity Estimation

    35/71

    35

    QUANTITY ESTIMATION

    6.2.1. Foundations

    a)Footing1:

    Details of the Foundation 1:

    Footing Size: 5'6"X 5' X 12"

    Total Number: 4

    Note: As per IS1200, Any footing must have a buffer of 600mm extra on either side from

    the face of the footing.

    Table 6.2.1.1detailed estimation of foundation 1

    S.No. ItemDescription

    Length

    (m)

    Breadth

    (m)

    HeightOr

    Thickness(m)

    Quantity

    (m)

    Remarks

    1 EarthworkExcavation

    5'6"+2(0.6)

    =2.88

    5'+2(0.6)=2.72

    5'0"=1.52

    11.91

    2 P.C.C

    (1:4:8)

    6'0"

    = 1.83

    5'6"

    = 1.68

    6"

    = 0.15

    0.46

    3 R.C.C work

    a)In Footing1

    b)In

    Column1

    Until ground

    surface

    5'6"

    = 1.68

    21"

    = 0.53

    5'

    = 1.52

    9"

    = 0.23

    12"

    = 0.3

    3'6"

    = 1.07

    0.77

    0.13

    H= 5'-6"-12"= 3'6"

    Total R.C.C. 0.90

    Earth work refilling= Earth work excavation-(R.C.C+P.C.C)

    =11.91-0.90-0.46

    =10.55m

  • 8/10/2019 Cost and Quantity Estimation

    36/71

    36

    In Footing1:

    Table 6.2.1.2final quantities of foundation 1

    Item For 1 unit Total No. Total Quantity

    Earthwork

    Excavation

    11.91 m

    4 47.64 m

    P.C.C (1:4:8) 0.46 m

    4 1.84 m

    R.C.C Work

    -In Footing

    -In Column (UntilG.S)

    0.77 m3

    0.13 m3

    4

    4

    3.08 m3

    0.52 m3

    Total R.C.C 0.90 m

    4 3.6m

    Earthwork Refilling 10.55 m

    4 42.2 m

    Steel 31.10Kg 4 124.40 Kg.

    b) Footing2:

    Details of the Footing2:

    Footing Size: 6'X 5'6"X 12"

    Total Number: 8

    Note: As per IS1200, Any footing must have a buffer of 600mm extra on either side from

    the face of the footing.

    Table 6.2.1.3detailed estimation of foundation 2

    S.No. ItemDescription

    Length

    (m)

    Breadth

    (m)

    HeightOr

    Thickness(m)

    Quantity

    (m)

    Remarks

    1 EarthworkExcavation

    6'+2(0.6)=3.03

    5'6"+2(0.6)=2.88

    5'0"=1.52

    13.26

    2 P.C.C(1:4:8)

    6'6"=1.98

    6'=1.83

    6"=0.15

    0.54

    3 R.C.C

    Work

    a) In

    Footing 1

    b) InColumn1

    Until

    groundsurface

    6'

    =1.83

    24"

    =0.61

    5'6"

    =1.68

    9"

    =0.23

    12"

    =0.3

    3'6"

    =1.07

    0.92

    0.15

    H=5'-6"-12"=3'6"

    Total R.C.C. 1.07

  • 8/10/2019 Cost and Quantity Estimation

    37/71

    37

    Earth work refilling= Earth work excavation-(R.C.C+P.C.C)

    =13.26-1.07-0.54

    =11.65m

    In Foundation 2:

    Table 6.2.1.4final quantities of foundation 2

    Item For 1 unit Total No. Total Quantity

    EarthworkExcavation

    13.26 m

    8 106.08 m

    P.C.C (1:4:8) 0.54 m

    8 4.32 m

    R.C.C Work

    -In Footing-In Column (Until

    G.S)

    0.92m3

    0.15 m3

    88

    7.36 m3

    1.2 m3

    Total R.C.C 1.07 m

    8 8.56 m

    Earthwork Refilling 11.65 m

    8 93.2 m

    Steel 38.22Kg. 8 305.76Kg.

    Reinforcement for footing :footing dimensions 5'6'' X 5'

    As per standards end cover for

    footing = 2

    Length of steel along longer

    span= length of footing -2 x end

    cover + 2 x hooks

    L1= 56-2x2+2x9x0.012

    = 1.79m

    Figure 7: Footing Plan

    N0.0f bars = {(length of footingend cover) /centre to centre distance }+1

    = (56-2x2)/6 +1 = 11.33 = 12

  • 8/10/2019 Cost and Quantity Estimation

    38/71

    38

    Total length of bar = no. of bars x length of one steel bar =21.48 m

    Unit weight of steel = 7850 kg/m

    Diameter of the bar = 12mm

    Total weight of steel = unit weight of steel x area of the bar x length of the bar

    = 7850 x (/4 x 0.012) x 21.48

    =19.07 kg

    Cost of steel = Rs 40/kg

    Total cost of steel in footings = 40 x 19.07

    = Rs 768.80

    Similar calculations are made for footings in shorter span direction.

    Table 6.2.1.5barbending schedule of footings

    S.NO Descriptionof item

    Shape Diameter( mm)

    No Length( m)

    Totallength

    (m)

    Unitweight

    (kg/m)

    Totalweight

    (kg)

    1 Column

    C1-4 nos

    a) longer

    direction

    b) shorterdirection

    12

    12

    40

    44

    1.8

    1.54

    72

    67.76

    0.89

    0.89

    64.08

    60.30

    2 ColumnC2-8 nos

    a)longer

    direction

    b)shorter

    Direction

    12

    12

    88

    96

    1.94

    1.8

    170.72

    172.8

    0.89

    0.89

    151.94

    153.79

    Total 430.16

    Total quantities in foundation:

    Total earthwork excavation = 47.64+106.08

  • 8/10/2019 Cost and Quantity Estimation

    39/71

    39

    = 153.72 m3

    Total quantity of p.c.c (1:4:8) =1.84+4.32

    = 6.16 m3

    Total Quantity Of R.C.C. = 3.6+8.56

    = 12.16 m3

    Total Earthwork Refilling = 42.2+93.2

    = 135.4 m3

    Total Steel Quantity In Footings = 430.16kgs(Excluding Column part)

  • 8/10/2019 Cost and Quantity Estimation

    40/71

    40

    6.2.2Plinth Beams R.C.C Work ( Table -6.2.2.1)

    S.No. Description

    of item

    No. Length

    (m)

    Width

    (m)

    Depth

    OrHeight

    (m)

    Quantity

    (m)

    Total

    quantity

    (m)

    1 Beam 1

    Beam 2

    2

    6

    55'6''=16.92

    26'6''=8.08

    9''=0.23

    9''=0.23

    12''=0.3

    12''=0.3

    2.33

    3.35

    2 Deductions

    at junctions

    of beam1&2

    At column1

    At column 2

    4

    8

    21''

    =0.53

    24''

    =0.61

    9''

    =0.23

    9''

    =0.23

    12''

    =0.3

    12''

    =0.3

    -0.15

    - 0.34

    Total 5.19

    3 Filling inside

    plinth beams

    40mm HBGMetal &

    earth filling 1 15.54 7.62 0.8 94.73

    Total 94.73

    Reinforcement in Plinth Beams (Table6.2.2.2)

    S.NO. Description

    of item

    Shape Diameter N0. Length Total

    length

    Unit

    weight

    Total

    quantity

    1 Beam 1

    Main bar

    Extra bar

    Beam 2

    Main bar

    Extra bar

    Stirrups

    16

    16

    16

    16

    8

    8

    4

    24

    12

    456

    17.16

    10.71

    8.32

    7.51

    1.11

    137.28

    42.84

    199.68

    90.12

    506.16

    1.58

    1.58

    1.58

    1.58

    0.39

    216.9

    67.68

    315.5

    142.39

    197.4

    Total 939.87

  • 8/10/2019 Cost and Quantity Estimation

    41/71

    41

    6.2.3 Compound Wall Table6.2.3.1

    S.NO. Description

    of item

    NO. Length

    (m)

    Breadth

    (m)

    Height

    Or depth

    (m)

    Quantity

    (m)

    Total

    quantity

    (m)1 Earth work

    excavation

    Long wall

    Short wall

    2

    2

    21.34

    10.6

    0.8

    0.8

    0.5

    0.5

    17.07

    8.48

    Total 25.55

    2 R.Rmasonry

    Long wall

    Short wall

    2

    2

    20.94

    11

    0.4

    0.4

    0.5

    0.5

    8.38

    4.4

    Total 12.78

    3 Earth workrefilling

    Long wall

    Short wall

    2

    2

    21.34

    10.6

    0.4

    0.4

    0.5

    0.5

    8.54

    4.24

    Total 12.78

    4 Brick work

    Long wall

    Short wall

    2

    2

    20.77

    10.83

    0.23

    0.23

    1.5

    1.5

    14.33

    7.47

    Deductionof gate 1 4 0.23 1.5 -1.38

    Total 20.42

    6 Plastering

    (C.M 1:4)

    External

    Internal

    1

    1

    64.34

    62.96

    1.5

    1.5

    96.51

    94.44

    Total 190.95m

  • 8/10/2019 Cost and Quantity Estimation

    42/71

    42

    6.2.4 Columns:

    a)In columns above ground surface :

    Total Height of Column = (No. of Floors * Floor Height) - (No. of beams on column

    *beam Thickness)

    = (4*3m) - (3*18'')

    = 10.63m

    From N.G.L. to Plinth top, Height = 12''

    Therefore Total Height of Column above G.S or G.L = 10.63+ 12'' =10.93 m

    (G.S = Ground Surface)

    Table 6.2.4.1C.C. work in columns

    ColumnNo.

    Specification Length

    (m)

    Breadth

    (m)

    Height

    (m)

    Quantity

    (m3)

    TotalNo.

    TotalQuantity

    (m3)

    C1 9 X 21 9=0.23m 21=0.53m 10.93m 1.33 4 5.32

    C2 9 X 24 9=0.23m 24=0.61m 10.93m 1.53 8 12.24

    Total 17.56

    Therefore, Total Column Concrete Quantity above G.S = 17.56 m3

  • 8/10/2019 Cost and Quantity Estimation

    43/71

    43

    b) Reinforcement for columns : ( Table -6.2.4.2 )

    S.No. Description

    Of item

    Shape Diameter

    (mm)

    Nos. Length

    (m)

    Total

    Length(m)

    Unit

    Weight(kg/m)

    Total

    Weight(kg)

    1 Main bars

    upto plinthlevel for

    a)ColumnC1-4 nos

    b)Column

    C2-8 nos

    20

    16

    25

    20

    24

    16

    32

    48

    2.28

    2.13

    2.36

    2.28

    54.72

    34.08

    75.52

    109.44

    2.46

    1.58

    3.85

    2.47

    134.61

    53.84

    290.75

    270.31

    3 Stirrups

    upto plinthlevel for

    a)columnc1-4 nos

    b)column

    c2-8 nos

    8

    8

    40

    80

    2.288

    2.3

    91.52

    184

    0.39

    0.39

    35.7

    71.76

    4 Main bars

    from plinthlevel to

    G+3 for

    a)ColumnC1-4 nos

    b)Column

    C2-8 nos

    20

    16

    25

    20

    24

    16

    32

    48

    14.01

    14.01

    14.01

    14.01

    336.24

    224.16

    448.32

    672.48

    2.47

    1.58

    3.85

    2.47

    830.51

    354.17

    1726

    1661

    5 Stirrups

    from plinth

    level to

    G+3 for

    columnC1-4 nos

    column

    C2-8 nos

    12

    12

    352

    352

    2.432

    2.432

    856

    856

    0.89

    0.89

    761.84

    761.84

  • 8/10/2019 Cost and Quantity Estimation

    44/71

    44

    6.2.5 Beams

    Table6.2.5.1 C.C. work in roof beams

    S.NO. Description

    of item

    NO. Length Breadth Height Quantity Total

    quantity

    1 Beam 1

    Beam 2

    Small beam1

    (b/w 5&6)

    Small beam1

    (b/w 1&2)

    3

    6

    1

    1

    51'=15.55

    34'

    =10.36

    10'3''

    =3.12

    11'6''

    =3.51

    9''=0.23

    9''

    =0.23

    9''

    =0.23

    9''

    =0.23

    12''=0.30

    12''

    =0.30

    12''

    =0.30

    12''

    =0.3

    3.21

    4.29

    0.22

    0.24

    Total 7.96

    C.C work in roof beams for single floor = 7.96 m

    for total building = no. of floors X C.C work in single floor

    = 4 X 7.96

    = 31.84 m

  • 8/10/2019 Cost and Quantity Estimation

    45/71

    45

    d) Beam Reinforcement Calculation:

    Figure 8: Beam Reinforcement

    Beam dimension = 139 x 9 x 12

    Length of main bar in beam = total length of beam 2* end

    cover + 2* hooks

    = 139 2*1+ 2* 9* 0.016

    =4.43 m

    We have 4 bars of this type in one beam so ,

    Total length of main bar = 4* 4.43

    =17.72 m

    Extra bars at ends, length of extra bar

    =

    = 2*( 13/4 + 9 -1 + 2*9* 0.016)

    = 2.96 m

    We have 2 extra bars for this beam so,

    Total length of extra bars in this beam = 2* 2.96

    = 5.92 m

    Total length 16 mm dia bars in this beam = length of main bar +length of extra bars

    = 17.72+5.92

    = 23.64 m

  • 8/10/2019 Cost and Quantity Estimation

    46/71

    46

    Unit weight of steel = 7850 kg/m

    Area of bar = /4 * 0.016

    Total weight of bars = unit weight * area* total length

    = 7850 * /4 * 0.016 * 23.64

    = 37.31kg

    Dimension of stirrup = 20.5 X 7

    Total Length of one stirrup = 2*( L+B + hooks )

    = 2*(20.5+7-9*0.008)

    =1.25m

    No. of stirrups = ( length of beam2*end cover)/center to center distance of stirrups + 1

    = ( 139- 2* 1)/ 7 +1

    = 24.28

    = 25

    Total length of all stirrups = no. of stirrups * length of single stirrup = 25 *1.25

    =31.25

    Unit weight of steel = 7850 kg/m

    Area of bar = /4 * 0.008

    Weight of stirrups = unit weight * area * total length of stirrups

    = 7850 * /4 * 0.008*31.25

    =12.33 kg

  • 8/10/2019 Cost and Quantity Estimation

    47/71

    47

    Beam Reinforcement Details

    Table 6.2.5.2bar bending schedule of roof beams

    S.No

    .

    Description of

    item

    Shape Diameter

    (mm)

    No Length

    (m)

    Total

    length

    (m)

    Unit

    weight

    (kg/m)

    Total

    weight

    (kg)1 BEAM 1

    Main bars

    Extra bars

    SMALL

    BEAM 1(b/w 6&5)

    Main bar

    Extra bar

    SMALLBEAM 1

    (b/w 1&2)

    Main bar

    Extra bar

    STIRRUPS

    Beam1

    Small beam1b/w 6&5

    Small beam1

    b/w 1&2

    16

    16

    16

    16

    16

    16

    8

    8

    8

    12

    6

    4

    2

    4

    2

    288

    21

    23

    17.92

    10.71

    3.82

    2.55

    3.97

    2.74

    1.2236

    1.236

    1.236

    215.04

    64.26

    15.28

    5.1

    15.88

    5.48

    355.97

    25.96

    28.43

    1.58

    1.58

    1.58

    1.58

    1.58

    1.58

    0.39

    0.39

    0.39

    339.76

    101.53

    24.14

    8.06

    25.09

    8.66

    138.83

    10.12

    11.09

    2 BEAM 2

    Main bar

    Extra bar

    STIRRUPS

    20

    20

    24

    12

    10.6

    10.16

    254.4

    121.92

    2.47

    2.47

    628.37

    301.14

  • 8/10/2019 Cost and Quantity Estimation

    48/71

    48

    8mm@6''c/c

    8mm@7''c/c

    8

    8

    8

    8

    264

    264

    138

    138

    1.54

    0.32

    1.54

    0.32

    406.56

    84.48

    212.52

    44.16

    0.39

    0.39

    0.39

    0.39

    158.56

    32.95

    82.88

    17.22

    Total 1888.4

    Total steel required in all beams in single floor = 1888.4 kg

    total steel required for beams in building = no. of floors X steel required in each floor

    = 4 X 1888.4

    =7553.6 kg

  • 8/10/2019 Cost and Quantity Estimation

    49/71

    49

    6.2.6 Slabs

    In Ground Floor:

    slab dimensions :

    Length= 55'6''

    Breadth=34'

    slab area = total slab area - openings of lift -opening of stair case

    total Slab Area =55'6'' X 34' = 175.29 m2

    Lift dimensions :

    L = 6'

    B = 4'6''

    Lift Area = 6' X 4'6'' = 2.51 m2

    Stair case dimensions

    L = 12'6''

    B = 6'

    Staircase area = 12'6'' X 6' = 6.97 m2

    Slab area = 175.29- 2.51 - 6.97 = 165.81

    Thickness of the Slab = 4.5

    Slab Quantity = 165.81X 4.5 = 18.95 m3

    Therefore Ground Floor Slab Quantity = 18.95 m3

    For all the floors, Slab Properties are the same and henceforth same quantity

    Total Slab Concrete Quantity = 75.8 m3

  • 8/10/2019 Cost and Quantity Estimation

    50/71

    50

    Slab Reinforcement Sample Calculations:

    Sample slab dimensions 20 X 11

    End cover for slabs 20mm

    Along long span

    Length of straight bar =length of slab(2* end cover)+ 2*hooks

    = 20-(2*0.02)+(2*9*0.008)

    =6.2 mLength of cranked bar= length of straight bar +( 0.42*d)* no. ofcranks

    = 6.2+( 0.42*0.008*2)

    = 6.21 m

    No. of bars = (length of slab- 2*end cover )/spacing of bars +1

    = (20- 2*0.02)/ 6 +1

    = 40.73=41 numbers

    Unit weight of steel = 7850 kg/m

    Area of bar = /4 *0.008

    Total weight of steel = unit weight *area*length

    =7850* /4 *0.008 *254.4=100.4kg

  • 8/10/2019 Cost and Quantity Estimation

    51/71

    51

    i) Slabs Reinforcement Details

    table 6.2.6.1bar bending schedule of slabs

    S.No Description

    of item

    Shape Diameter

    (mm)

    No. Length

    (m)

    Total

    length

    (m)

    Unit

    weight

    (kg/m)

    Total

    Weight

    (kg)1 Along

    shorter span

    1)b/w 1&2

    a) straight

    bar

    b) cranckedbar

    2) b/w 2&3

    a) straight

    bar

    b) cranckedbar

    3) b/w 3&4

    a) straight

    bar

    b) cranckedbar

    4) b/w 4&5

    a) straight

    barb) crancked

    bar

    5) b/w 5&6

    a) straight

    bar

    b) cranckedbar

    16

    16

    16

    16

    16

    16

    16

    16

    16

    16

    13

    13

    13

    12

    7

    6

    14

    14

    12

    12

    10.46

    10.48

    10.46

    10.47

    5.05

    5.06

    10.46

    10.47

    10.46

    10.448

    135.98

    136.24

    135.98

    125.64

    35.35

    30.36

    146.44

    146.58

    125.52

    125.76

    1.58

    1.58

    1.58

    1.58

    1.58

    1.58

    1.58

    1.58

    1.58

    1.58

    214.85

    215.26

    214.84

    198.51

    55.85

    47.97

    231.38

    231.6

    198.32

    198.7

  • 8/10/2019 Cost and Quantity Estimation

    52/71

    52

    Alonglonger span

    1) b/w

    staircase &lift

    a) straight

    barb) crancked

    bar

    2) side oflift

    a) straight

    bar

    b) cranckedbar

    3) side of

    staircase

    a) straight

    barb) crancked

    bar

    8

    8

    8

    8

    8

    8

    17

    17

    12

    12

    26

    26

    17.4

    17.44

    7.65

    7.67

    7.65

    7.67

    295.8

    296.48

    91.8

    92.04

    198.9

    199.42

    0.39

    0.39

    0.39

    0.39

    0.39

    0.39

    115.36

    115.63

    35.8

    35.9

    77.57

    77.77

    Total 2265.11

    Total weight of steel in slab for one floor = 2265.11 kg

    Total weight of steel required for building in slabs = number of slabs X total weight of

    steel in single slab

    = 4 X 2265.11

    = 9060.44 kg

  • 8/10/2019 Cost and Quantity Estimation

    53/71

    53

    6.2.7 BRICK WORK

    Table 6.2.7 - Brick work

    S.no. Description of

    item

    Nos. Length

    (m)

    Breadth

    (m)

    Height

    Or

    depth(m)

    Quantity

    (m)

    Total

    quantity

    (m)

    1 External walls(9")

    a) long wall

    (along beamB1)

    b)short wall

    (along beam

    B2)

    2

    4

    55'6''=16.92

    32'6''

    =9.91

    9''=0.23

    9''

    =0.23

    2.7

    2.6

    21

    23.7

    2 Internal walls

    (4'')a)main bed

    room

    1)long wall

    2)short wall

    b)kitchen

    1)long wall

    2) short wall

    c)Toilet wall

    d) Balcony wall

    e) C.Bed Room

    1)long wall

    2) short wall

    2

    2

    2

    4

    4

    2

    1

    1

    12'10''

    =3.91

    11'

    =3.35

    12'10''

    =3.91

    7'10.5''=2.4

    4'=1.22

    10'=3.05

    12'7''

    =3.81

    10'

    =3.05

    4"

    =0.1

    4''

    =0.1

    4''

    =0.1

    4''=0.1

    4''=0.1

    4''=0.1

    4''

    =0.1

    4''

    =0.1

    2.7

    2.6

    2.6

    2.7

    2.7

    3

    2.7

    2.6

    2.1

    1.74

    2.03

    2.6

    1.32

    1.83

    1.03

    0.8

  • 8/10/2019 Cost and Quantity Estimation

    54/71

    54

    f) C.Bed Room1) long wall

    2)short wall

    1

    1

    11'4''

    =3.45

    10'=3.05

    4''

    =0.1

    4''=0.1

    2.7

    2.6

    0.93

    0.8

    Total 59.88

    = 60

    DEDUCTIONS

    3 DOORS

    a) main door

    b) door (D)

    C) door (D1)

    2

    4

    8

    3'6''

    =1

    3'

    =0.91

    2'6''=0.76

    9"

    =0.23

    4''

    =0.1

    4''=0.1

    6'9''

    =2

    6'9''

    =2

    6'9''=2

    -0.92

    -0.73

    -1.22

    4 WINDOWS

    a) window (W)

    b)window (W1)

    c)window(W2)

    d) kitchen

    window (K/W)

    2

    9

    1

    2

    6'

    =1.8

    4'

    =1.2

    3'=0.9

    2'

    =0.6

    9''

    =0.23

    4''

    =0.1

    4''=0.1

    4''

    =0.1

    4'

    =1.2

    4'

    =1.2

    4'=1.2

    1'6''

    =0.45

    -1

    -1.3

    -0.11

    -0.05

    5 VENTILATOR

    (V)

    2 2'

    =0.6

    4''

    =0.1

    1'6''

    =0.45 -0.05

    6 COLUMNS

    a) column (C1)

    b) column (C2)

    4

    8

    21''

    =0.53

    29''

    =0.74

    9''

    =0.23

    9''

    =0.23

    2.6

    2.6

    -1.27

    -3.5

  • 8/10/2019 Cost and Quantity Estimation

    55/71

    55

    7 BALCONYa)Wide balcony

    b)kitchenbalcony

    c) staircase

    landing

    2

    2

    1

    10'

    =3.05

    7'9''

    =2.36

    6'

    =1.83

    9''

    =0.23

    9''

    =0.23

    9''

    =0.23

    1.68

    1.83

    1.83

    -3

    -2

    -0.77

    Total

    deduction

    -15.92

    =(-)16

    Total quantity of brick for one floor = total brick work + deductions

    = 60-16

    = 44 m

    total quantity of brick work in building = no.of floors X single floor brick work

    = 3 X 44

    =132 m

    total no.of bricks =

    brick size = 0.19 X 0.09 X 0.09 m

    brick size along with cement mortor = 0.2 X 0.1 X 0.1 m

    total no. of bricks =

    = 66000

  • 8/10/2019 Cost and Quantity Estimation

    56/71

    56

    6.2.8 PLASTERING

    Table 6.2.8.1plastering work

    S.no. Decsription of

    item

    Nos. Length

    (m)

    Breadth

    (m)

    Height

    or

    depth(m)

    Quantity

    (m)

    Total

    quantity

    (m)

    18mm cement

    plastering 1:4

    in walls

    1 Main bed rooma) long wall

    b) short wall

    c) slab

    d) column

    4

    4

    2

    4

    12'6''

    =3.81

    11'

    =3.35

    12'6''=3.81

    4'5''=1.35

    11'=3.35

    10'

    =3.05

    10'

    =3.05

    8'6''=2.59

    46.48

    40.87

    25.53

    14

    2 Kitchen rooma)long wall

    b)short wall

    c)slab

    4

    4

    2

    9'

    =2.74

    7'10.5''=2.4

    9'=2.74

    7'10.5''=2.4

    10'

    =3.05

    10'=3.05

    33.43

    29.28

    13.15

    3 Toilets(6' X 4')

    a) long wall

    b)short wall

    c) slab

    4

    4

    2

    6'

    =1.83

    4'

    =1.22

    6'

    =1.83

    4'

    =1.22

    10'

    =3.05

    10'

    =3.05

    22.33

    14.88

    4.47

  • 8/10/2019 Cost and Quantity Estimation

    57/71

  • 8/10/2019 Cost and Quantity Estimation

    58/71

    58

    b) short wall

    c) slab

    2

    1

    11'

    =3.35

    20'4.5''=6.21

    11'=3.35

    10'

    =3.05 20.44

    20.8

    8 C.BED ROOM(11' X 10')

    a) short wall

    b) short wall

    c) slab

    d)columns

    C.BED ROOM(12'3'' X 10')

    a)long wall

    b) short wall

    c)slab

    d) column

    2

    2

    1

    4

    2

    2

    1

    4

    11'

    =3.3510'

    =3.05

    10'=3.05

    4.5''

    =0.11

    12'3''

    =3.73

    10'

    =3.05

    10'

    =3.05

    4.5''=0.11

    11'=3.35

    12'3''

    =3.73

    10'

    =3.0510'

    =3.05

    8'6''

    =3

    10'

    =3.05

    10'

    =3.05

    8'6''=3

    20.44

    18.61

    10.22

    1.32

    22.75

    18.61

    11.38

    1.32

    9 Lift

    a) long wall

    b) short wall

    2

    2

    6'

    =1.83

    4'6''

    =1.37

    10'4.5''

    =3.16

    10'4.5''

    =3.16

    11.57

    8.66

    10 Wide corridora) long wall

    b) short wall

    2

    1

    16'6.5''

    =5.04

    6'

    =1.83

    10'

    =3.05

    10'

    =3.05

    30.74

    5.58

  • 8/10/2019 Cost and Quantity Estimation

    59/71

    59

    c) slab 1 16'6.5''

    =5.04

    10'

    =3.05 15.37

    11 WIDE

    BALOCNY

    a) long wall

    b) short wall

    c) slab

    d) short long

    wall

    e) short longwall top

    2

    4

    2

    2

    2

    10'

    =3.05

    3'

    =0.91

    10'

    =3.05

    10'=3.05

    10'

    =3.05

    3'

    =0.91

    9''

    =0.23

    10'

    =3.05

    10'

    =3.05

    3'=0.91

    18.61

    11.10

    5.55

    5.55

    1.4

    12 Kitchen wash

    a) long wall

    b) short wall

    c) slab

    d) short long

    wall

    e) short longwall top

    2

    4

    2

    2

    2

    8'1''

    =2.46

    3'6''

    =1.07

    8'1''

    =2.46

    8'1''

    =2.46

    8'1''=2.46

    3'6''

    =1.07

    9''=0.23

    10'

    =3.05

    10'

    =3.05

    3'

    =0.91

    15

    13.05

    5.26

    4.48

    1.13

    13 Out side

    a) long wall

    b) short wall

    2

    2

    55'6''

    =16.92

    34'

    =10.36

    10'4.5''

    =3.16

    10'4.5''

    =3.16

    106.93

    65.48Total 910.72

  • 8/10/2019 Cost and Quantity Estimation

    60/71

    60

    Deductions

    DOORS

    1) M.D

    2)D

    3)D1

    WINDOWS

    1) W

    2)W1

    3)W2

    4) K/W

    5) V

    OUT SIDE

    OPENINGS

    a) widebalcony

    b) kitchen

    wash

    4

    8

    16

    4

    18

    2

    4

    4

    2

    2

    3'6''=1.07

    3'

    =0.91

    2'6''

    =0.76

    6'

    =1.83

    4'

    =1.22

    4'

    =1.22

    3'

    =0.91

    2'

    =0.61

    10'=3.05

    7'10.5''=2.4

    6'9''=2.06

    6'9''

    =2.06

    6'9''

    =2.06

    4'

    =1.22

    4'

    =1.22

    3'

    =0.91

    2'6''

    =0.76

    1'6''

    =0.46

    7'=2.13

    7'=2.13

    -8.82

    -15

    -25.05

    -8.93

    -26.8

    -2.22

    -2.77

    -1.12

    -13

    -10.22

    Total

    deducti

    on -113.91

    Painting is similar to plastering .

  • 8/10/2019 Cost and Quantity Estimation

    61/71

    61

    6.2.9 Stair case

    Table 6.2.9.1C.C. work in stair case

    S.NO Description of

    item

    No Length

    (m)

    Breadth

    (m)

    Height

    (m)

    Quantity

    (m)

    Total

    quantity

    (m)

    Remarks

    1 Stair case

    R.c.c bed

    Landing area

    2

    1

    3.09

    6'1.83

    3'

    0.91

    3'6''1.07

    5''

    0.127

    5''0.127

    0.71

    0.25

    Total 0.96

    Reinforcement in staircase

    Table 6.2.9.2bar bending schedule of stair case

    S.NO. Description

    of item

    shape diameter NO. Length Total

    length

    Unit

    weight

    Total

    quantity

    1 Main

    reinforcement

    Distribution

    reinforcement

    12

    8

    14

    32

    3.68

    0.86

    51.52

    27.53

    0.89

    0.39

    45.85

    10.73

    Total 56.58

    reinforcement in staircase for single floor = 56.58 kg

    reinforcement in total staircase = no. of floors X reinforcement in single floor

    = 4 X 56.58

    = 226.32 kg

  • 8/10/2019 Cost and Quantity Estimation

    62/71

    62

    6.2.10 LINTELS

    Table 6.2.10.1C.C. work in lintels

    S. NO Descriptionof item

    NO. Length

    (m)

    Breadth

    (m)

    HeightOr depth

    (m)

    Quantity

    (m)

    Totalquantity

    (m)

    1 Over

    M.D

    DD1

    W

    W1

    W2

    K/WV

    2

    48

    2

    9

    1

    22

    1.37

    1.221.07

    2.13

    1.52

    1.22

    1.221.07

    0.23

    0.10.1

    0.23

    0.23

    0.1

    0.10.23

    0.1

    0.10.1

    0.1

    0.1

    0.1

    0.10.1

    0.06

    0.050.09

    0.1

    0.31

    0.01

    0.020.05

    TOTAL 0.69

    For three floors = 3 X 0.69

    = 2.07 m

    6.2.11 SKIRTING

    Table 6.2.11.1 - skirting

    S.NO. Description

    of item

    NO. Length

    (RM)

    Breadth

    (m)

    Height

    (m)

    Quantity

    (RM)

    Total

    quantity(RM)

    1 M.BED

    C.BED

    Living,dining hall

    Kitchen

    Wide

    balconyK/wash

    Toilets

    2

    2

    2

    2

    22

    4

    14.32

    13.56

    25.11

    10.29

    7.927.06

    6.1

    28.64

    27.12

    50.22

    20.58

    15.8414.12

    24.4

    Total 180.92

  • 8/10/2019 Cost and Quantity Estimation

    63/71

    63

    6.2.12 AREA UNDER TILES ( table 6.2.12.1)

    S.NO. Description of

    item

    N0. Length

    (m)

    Breadth

    (m)

    Depth

    Or height(m)

    Quantity

    (m)

    Total

    quantity(m)

    1

    Common bedroom

    (12'3'' X 10')

    Dining hall

    (10' X 9'7.5'')

    Living hall

    (20'4.5'' X

    11')

    Wide balcony

    Kitchen

    Kitchen wash

    area

    Toilets(6' X 4')

    Toilets(6'2'' X 4')

    Living hall(20'4.5'' X

    12'3'')

    Dining hall

    (10' X 8'4.5'')

    Common bedroom

    (11' X 10')

    Wide corridor(16'6.5'' X 6')

    1

    1

    1

    2

    2

    2

    2

    2

    1

    1

    1

    1

    12'3''=3.73

    10'

    =3.05

    20'4.5''

    =6.21

    10'

    =3.05

    9'=2.74

    7'10.5''=2.4

    6'

    =1.83

    6'2''=1.88

    20'4.5''

    =6.21

    10'

    =3.05

    11'

    =3.35

    16'6.5''

    =5.04

    10'=3.05

    9'7.5''

    =2.93

    11'

    =3.35

    3'

    =0.91

    7'10.5''=2.4

    3'6''=1.07

    4'

    =1.22

    4'=1.22

    12'3''

    =3.73

    8'4.5''

    =2.55

    10'

    =3.05

    6'

    =1.83

    11.38

    8.94

    20.8

    5.55

    13.15

    5.13

    4.47

    4.47

    23.16

    7.78

    10.22

    9.22

    Total 124.27

  • 8/10/2019 Cost and Quantity Estimation

    64/71

    64

  • 8/10/2019 Cost and Quantity Estimation

    65/71

    65

  • 8/10/2019 Cost and Quantity Estimation

    66/71

    66

  • 8/10/2019 Cost and Quantity Estimation

    67/71

    67

  • 8/10/2019 Cost and Quantity Estimation

    68/71

    68

  • 8/10/2019 Cost and Quantity Estimation

    69/71

    69

    RESULTS

    Table 7.1.1

    S.No Description of item Quantity

    1 Earth work excavation 179.27 m

    2 P.C.C bed concrete quantity 6.16 m

    3 Total R.C.C work 148.48 m

    4 Total Cement mortar

    a) for bricksb) plastering

    c) under tiles

    36.02 m15.96 m

    7.88 m

    5 Total bricks 78130

    6 Steel

    8mm dia bars

    12mm dia bars

    16mm dia bars 20mm dia bars

    25mm dia bars

    3986.5kg2137.24kg

    10408.56 kg6614.47 kg2106.75 kg

    Total Steel 25,251kgs

    7 Total cement bags ( 50kg / bag) 1045 bags

    8 Fine aggregates (sand ) in tones 150 tonnes

    9 Coarse aggregates in tones 122 tonnes

    1m 20mm aggregate = 1.43 metric tonnes

    1m of cement = 1440 kg

    1m of sand = 1602 kg

    Land cost per sq. yard = 42, 000

    Total area = (40' X 70')

    = 311.11 sq. yards

    Total cost of land = Rs 1,30,66,667/-

    Total construction cost = Rs 65,92,902/-

    Total cost = cost of land + cost of construction

    = 1,30,66,667 + 65,92,902

    =Rs1,96,59,569/-

  • 8/10/2019 Cost and Quantity Estimation

    70/71

    70

    CONCLUSION

    The estimate also gives an idea of the time required for the completion of the

    work, i.e. the probable time of completion can also be calculated. Also before the start of

    any work, at least probable cost has to be found out, here estimation and costing plays an

    important role. The estimate is also required for inviting tenders and to arrange contract

    and to control the expenditure during execution.

    The primary object of an estimate is to enable one to know, beforehand, the cost

    of work. The actual cost is known only after the completion of the work from the account

    of completed work. The estimate may be prepared approximately as a preliminary

    estimate by various methods without going into the details of different items of work, to

    know the approximate cost or rough cost.

    Estimation and Analysis of Rates of various Items of Building are calculated and

    presented in this documentation. All the calculations are based on the Design Drawings

    provided, Standard Schedule of Rates, Andhra Pradesh, 2013-14 and Standard Data

    Book. Reading the drawings, which is the essential feature of a Civil Engineer, has been

    learned all through this project.

  • 8/10/2019 Cost and Quantity Estimation

    71/71

    REFERENCES

    [1] IS: 1200Hand Book of Method of Measurement of Building Works

    [2] SP-34Hand book on Concrete Reinforcement and Detailing

    [3] Estimating and Costing in Civil Engineering by B.N. Dutta, 26th

    revised

    Edition, UBS Publishers Distributors pvt. Ltd. , 2007, pages 1, 4-11, 13-20, 213-214,

    448-449, 472-517, 564.

    [4] Standard Schedule of Rates (SSR), Andhra Pradesh, 2013-14

    [5] Standard Data BookFor Material and Labour Constants