cost-21 day 85
TRANSCRIPT
-
7/31/2019 Cost-21 day 85
1/60
A Guide Line To Perform
EPC Project Contract Cost
EstimationIn the Field of
Oil, Gas & Petrochemical Industries
Held by : FARAGOSTARAN
Present by: Hassan MirzaieDate : 11 January 2007
Location: Simorgh Hotel
Tel. & Fax : 021- 8870 29 24 , 8870 45 84
-
7/31/2019 Cost-21 day 85
2/60
No Body Plans to Fail, But
Fails to Planning!
-
7/31/2019 Cost-21 day 85
3/60
EPC Key Approach
EPC Project Contract Cost Estimation
Contractors Know-How For EPC Project Executing
Project Work Break Down Structure (WBS)
Identifying and Managing Risks in EPC Projects
Managing & Control of Project Changes in EPC Projects
EPC Project Management
Engineering & Design Phase Documents Flow Diagram
-
7/31/2019 Cost-21 day 85
4/60
A Guide Line To Perform
EPC Project Contract Cost
EstimationIn the Field of
Oil, Gas & Petrochemical Industries
-
7/31/2019 Cost-21 day 85
5/60
Seminar Approach
1. EPC Project Definition
2. Functional WBS Code for EPC Project
3. Methodology and Flow of Cost Estimating
4. Main Questions to be Asked to Cost Estimate
5. Why People Get Estimating Wrong
6. Risk Related Cost Estimating7. Summary
-
7/31/2019 Cost-21 day 85
6/60
1. EPC Project Definition
Performing of Feasibility Study
Preparation of Bid Documents
License Agreement and Engineering Design (Basic,FEED & Detail Activities)
Procurement
Construction / Erection and Pre-CommissioningCommissioning and Start-up
Training
-
7/31/2019 Cost-21 day 85
7/60
DefineScope
Funding /Budgeting
Feasibility
Study
PlanningPhase
PMC/Engineer
Selection
Process/
Basic Design
ITB
Preparation
Evaluation
& Clarification
ITB
Bid Evaluation &Clarification
Bid Negotiation
Letter of Intend
Contract Negotiation& Signing
Marketing/SalesApproach
Bidding Strategy
Partnering
Site Survey &Clarification
Cost Estimate &
Bid Submission
Project DefinitionPhase
Project Execution
Engineering
Design
Procurement
/Supply
Construction
Implementation Phase
EPC Project Flow Diagram
-
7/31/2019 Cost-21 day 85
8/60
Typical Weight Percent of An EPC
Project
1Logistic and Others7
1Training6
2Commissioning and
Start-up
5
20-25Construction Pre-Com450-60Procurement3
7-10License & Engineering2
1Feasibility Study1
% RangeDescriptionItem
-
7/31/2019 Cost-21 day 85
9/60
2. Functional WBS Code for EPC
Project
PrefossinalServices Materials Labor Work Transportation
Direct / IndirectExpenses
Others
EPC Project
-
7/31/2019 Cost-21 day 85
10/60
Professional Services
Professional
services
Detail
Engineering
Quality MGT
Procurement
Const. MGT &
Supervision
Project MGTBasic
Engineering
Project
Administration
Comm. &
Operation
Training
Others
-
7/31/2019 Cost-21 day 85
11/60
Professional Services (1/2)
Project Management and ControlProject Directing, Organization and Stuffing, Project Planning and Control,
Project Coordination, Estimating, Management Support
Basic EngineeringProcess Design, Plant Safety, Instrumentation, General Civil, Plant Layout andPiping Specification
Detail EngineeringCivil and U/G, Structure, Building, Equipment, Piping, Instrumentation,Electrical, Paint AND Insulation,
ProcurementProcurement General, Purchasing, Subcontracting, Expediting, Traffic andCustom Clearances
-
7/31/2019 Cost-21 day 85
12/60
Professional Services (2/2)
Quality ManagementQuality Assurance, Quality Control, Shop Inspection, Field Inspection,
Maintenance Inspection, Plant Diagnosis
Construction Management and SupervisionConstruction Management and Super-intendance, Planning,Field Controlling,Field Installation Supervision, Field Technical Support, Field Engineering,Subcontracting Administration
Commissioning and OperationCommissioning and Operation General, Pre-commissioning, Commissioning,Operation Services
Project AdministrationAdministration General, Personnel Control, Project Accounting, Communicationand Correspondence, Document Handling, Camp Organization, General Affairs
-
7/31/2019 Cost-21 day 85
13/60
Materials
Materials
Spare Parts OthersDirect
Materials
Ind. Mat. for
Tem. Facilities
-
7/31/2019 Cost-21 day 85
14/60
Materials
Direct Materials
Civil Materials, Structure Materials, Building Materials, Equipment,Piping and Bulk, Instrumentation, Electrical, Insulation and Painting,FireProofing and Surface Protection, Catalysts, Chemicals, and Utilities
Indirect MaterialsTemporary Building, Utilities and Telecommunications, HousingEquipment and Furniture, Shop Equipment and Tools,CommonScaffolding, Canteen
Spare Partsspare Parts for Commissioning and Start-up, Spare Parts for Operation (2Years)
-
7/31/2019 Cost-21 day 85
15/60
Labor Work
Labor Work
Indirect Field
Operation
Construction
Equipment
Supervisory
Others
Direct Labor
Work
Ind. Lab.
Work for
Temp. Work
-
7/31/2019 Cost-21 day 85
16/60
Labor Work (1/2)
Direct Labor WorkCivil General, Concrete Structure, Steel Structure, Building, Equipment
Installation, Piping, Instrumentation, Electrical, Insulation and Painting, FireProofing and Surface Protection, Catalysts, Chemicals and Utilities, Othersincluding System Test Preparation
Indirect Labor Work For Temporary FacilitiesTemporary Building, Utilities and Telecommunications, Housing Equipment andFurniture, Assembling of Shop Equipment and Tools, Installation of CommonScaffolding, Canteen,
Indirect Field OperationCommissioning and Operation, Project Administration
Supervisory
Civil General, Concrete Structure, Steel Structure, Building, EquipmentInstallation, Piping, Instrumentation, Electrical, Insulation and Painting, FireProofing and Surface Protection, Catalysts, Chemicals and Utilities
-
7/31/2019 Cost-21 day 85
17/60
Labor Work (2/2)
Construction Equipment
Construction equipment, Operator and Driver
-
7/31/2019 Cost-21 day 85
18/60
Transportation
Transportation
Onshore OthersOffshore Ocean Frieght
-
7/31/2019 Cost-21 day 85
19/60
Transportation
Offshore
Packing, Handling, Transportation, Shipping and Custom Clearances
Ocean FreightOcean Freight, Air Freight
OnshorePacking, Handling, Transportation,
-
7/31/2019 Cost-21 day 85
20/60
Direct and Indirect Expenses
Financial
Charge
Tax and
Duties
Insurance
Licensors
Charge
Home and
Branch Office
Expences
Field Office
Expenses
Consultant
Fee
Third Party
InspectionCharge
Agent Fee Others
-
7/31/2019 Cost-21 day 85
21/60
Direct and Indirect Expenses (1/2)
Home and Branch Office ExpensesTraveling and Traffic Charge, Telecommunication Charge, Office Charge,Social
Charges, Miscellaneous Charges
Field Office ExpensesTraveling and Traffic Charge, Telecommunication Charge, Office Charge,SocialCharges, Miscellaneous Charges
Financial ChargeL/C Charge, Bond Charge, Interest Charge
InsuranceGovernmental Insurance, Transport Insurance, Travels, Accident Insurance,Social Insurance, Construction Insurance, Provisional Liability Insurance
-
7/31/2019 Cost-21 day 85
22/60
Direct and Indirect Expenses (2/2)
Tax and Duties
Import Duties, Corporate Charge
Licensors ChargeRoyalty, Know-How Fee, Basic Design Fee, Design Checking Fee,
Operation Charge
Consultant FeeEngineering Consultant Fee, Training Consultant Fee, Accountant Fee,
Lawyer Fee
-
7/31/2019 Cost-21 day 85
23/60
Others
Others
Rate
Difference ContingencyGeneral
Overhead
-
7/31/2019 Cost-21 day 85
24/60
3. Methodology and Flow of Cost
Estimating3.1 Definition of Cost
3.2 Type of Costs3.3 Cost Estimation Methodology (Tools and
Techniques)3.4 Cost Estimation Templates for EPC
Project
-
7/31/2019 Cost-21 day 85
25/60
3.1 Definition of Cost
A Resource (People, Equipment, et.) whichForeseen to Achieve a Specific Objective
Cost Estimating Should be Based on a WBS toImprove Accuracy
Cost Estimation Includes all the Work Needed to
Complete the Project Including: Quality Efforts,Risk Efforts, Management Time
Cost Estimates are Generally Expressed in Units of
Currency (Dollars, Euro, Rials,etc.,)
-
7/31/2019 Cost-21 day 85
26/60
3.2 Type of Costs (1/2)
Variable Costs: Any Cost that Changes With the Amount ofProduction or the Amount of Work. Examples Include the
Cost of Material, Supplies, Labor, etc. Fixed Costs: Costs That Do Not Change as Production
Changes. Examples Include Set-Up, Rental, etc.
Direct Costs: Costs That Are Directly Attributable to the Work
on the Project. Examples are Team Travel, Recognition andRewards, Cost of Materials, Training
Indirect Costs: Overhead Items or Costs Incurred for theBenefit of More Than on Project. Examples Include Taxes,
Benefits, Insurances, etc. Opportunity Costs: Net Present Value of a Project. Is Really a
Choice to Do / Not to Do a Project
-
7/31/2019 Cost-21 day 85
27/60
3.2 Type of Costs (2/2)
Type of Guest Accuracy Rate Rough Order of Magnitude (ROM) -25% to 75%
Budgetary -10% to 25%
Approximate Estimate (Informational) + or 15%
Definitive (Based on Detailed Information) + or 5%
3 3 C E i i M h d l
-
7/31/2019 Cost-21 day 85
28/60
3.3 Cost Estimating Methodology
(Tools and Techniques)3.3.1 Analogous or Top-Down
3.3.2 Parametric or Bottom-Up3.3.3 Cost Budgeting
3 3 1 A l T D
-
7/31/2019 Cost-21 day 85
29/60
3.3.1 Analogous or Top-Down
Estimating (1/2) Uses the Actual Cost of a Previous, Similar Project as the
Basis for the New Estimate
Advantages: Quick
Activities Need not be Identified
Less Costly to Create
Disadvantages: Less Accurate
Estimates are Prepared with a Limited Amount of Detailed Information andUnderstanding of the Project
Requires Considerable Experience to Do Well
Extremely Difficult for Project With Uncertainty
3 3 1 A l T D
-
7/31/2019 Cost-21 day 85
30/60
3.3.1 Analogous or Top-Down
Estimating (2/2) Examples:
Estimation of Engineering Man-Hour from Previous Projects
Weight Of Piping Bulk Materials
Cost of Temporary Equipment to be Used During Construction
3 3 2 P t i B tt U
-
7/31/2019 Cost-21 day 85
31/60
3.3.2 Parametric or Bottom-Up
Estimating (1/2) Estimate Individual Work Items and Sum Them to Get a
Total Estimate
Advantages: More Accurate
Gains Buy-In From Team Because the Team Creates Estimates the CanLive With
Has Been Prepared Based On a Detailed Analysis of the Project Provides a Basis for Monitoring and Controlling, Performance Measurement
and Management
Disadvantages: Takes Time and Expenses
Tendency for the Team to Pad Estimates Unless Taught About Reserves
Requires that the Project be Well Understood
Requires Time to Break the Project Down into Smaller Pieces
3 3 2 P t i B tt Up
-
7/31/2019 Cost-21 day 85
32/60
3.3.2 Parametric or Bottom-Up
Estimating (2/2)
Examples: Detailed Estimation of Cost of Engineering Manpower, Equipment,Materials, Construction Fee Based on Conceptual Design Information
and Document.
-
7/31/2019 Cost-21 day 85
33/60
3.3.3 Cost Budgeting
-
7/31/2019 Cost-21 day 85
34/60
3.3.3 Cost Budgeting
A Budget is Merely a Compilation of the IndividualCost Estimates.
Management Reserves: Extra Amount of Funds tobe Set Aside to Cover Unforeseen Risks or Change inthe Project
Contingency Reserves: Percentage of the Subtotal ofthe Cost of Project Items, Supplemental Work,Materials and Expenses
-
7/31/2019 Cost-21 day 85
35/60
Report from GG5, Dec. 20, 2005
General Methodology
Create Technical
Requirements Document
Develop Technical
Conceptual Design
Create the WBSEstablish C/S
Coordinator
for each WorkPackage
Establish rules for C/S &
define assumptions
Set up tools and
format for data input
Develop the RLSand Mgmt Docs
Estimate Cost &Schedule and
create the BOE
ReviewNo
Yes
Fund Starts
C/S = Cost & ScheduleWBS = Work Breakdown StructureBOE = Basis of EstimateRLS = Resource Loaded Schedule
Interpret this Core
Cost in each Region
3 4 Cost Estimation Templates for
-
7/31/2019 Cost-21 day 85
36/60
3.4 Cost Estimation Templates for
EPC Project (1/2) A Commercial Proposal for an EPC Project Normally
Includes Following Sections:
EngineeringMan Power (Basic Engineering, Endorsement, Detail Engineering)
Consumable
Office and Furniture
Management
Overhead Contingency
Procurement
Procurement Engineering and Man Power (Technical Doc. Preparationand Material requisition, Bidder Clarifications, Proposal Evaluation(Technical, Commercial, Expediting and Inspection)
Equipment (LC Opening, Purchase Order, Manufacturing, Test andInspection)
Bulk Materials (LC Opening, Purchase Order, Manufacturing, Test andInspection)
Logistic (Shipment, Custom Clearances and Delivery to Site)
3.4 Cost Estimation Templates for
-
7/31/2019 Cost-21 day 85
37/60
3.4 Cost Estimation Templates for
EPC Project (2/2) Insurance
Provisional Cost
Overhead and Contingency
Construction Site Preparation
Site Establishment Plant Construction
Safety and Security
Camping
Pre-Commissioning Commissioning
Management Man Power
Contingency
Construction Insurance
EPC Cost Weight Percent
-
7/31/2019 Cost-21 day 85
38/60
gDescription (Sub (Total Remarks
8.5
Man Power 66 Engineering TeamConsumable 7.5 Stationary, Doc. / Dwg.
Office and Furniture 8.5 Soffice Included all Stationary Equipment
Management 5
Overhead 8 Taxes, Duties, Social Fees
Contingency 5
64Equipment 65 Mechanical, Electrical, Instrument
Bulk Materials 18.5 Piping, Steel Str., Inst., Ele., Paint, Ins., F&G, Chem.,
Logestic and Custom Clear 4 Transp, Costum Du, Insp, Load and Unload, Heavy Li
Man Power 2.8
Insurance 0.7 Financial and Logestic Insurance
Overhead and Contingency 0.5 Office Rent, ConsumablesProvisional Cost 8.5 2 Years Spare Part, Duties
27.5
Site Preparation 5 Site Preparation and Site Access
Site Establishment 2 Mobilization / Demobilization, Workshop, Spool Shop
Plant Construction 70 Civil, Structures, Mechanical, Electrical, Inst. Installat
Safety and Security 2.5 HSE, Guard Housing, Fire Station, First AidCamping 8.5 Camp, Catering, Transportation
Pre-Commissioning 2 Mechanical Complition, Test Packages
Commissioning 2.5 Test Running, Performance Test, Vendor Specialist
Mangement Man Power 1.5
Contingency 5
Construction Insurance 1 Full Risk
100
Engineering
Procurement
Construction
Total
Overall S Curve
-
7/31/2019 Cost-21 day 85
39/60
Overall S Curve
Finishing
PeriodMay-2
00
5
Jun-2
00
5
Ju
ly-2
005
Aug-2
005
Sep-2
00
5
Oc
t-200
5
Nov-2
00
5
Dec-2
00
5
Jan-2
00
6
Fe
b-2
00
6
Mar-2
00
6
Apr-2
00
6
May-2
00
6
Jun-2
00
6
Ju
ly-2
006
Aug-2
006
Sep-2
00
6
Oc
t-200
6
Early Pla 0 0 1 1 4 11 18 26 37 48.2 59.8 72 83 90.9 96 98 99 100
Actual
Cummulative Plan Progress
0
10
20
30
40
50
60
70
80
90
100
May-2
005
Jun-
2005
Ju
ly-2
005
Aug-
2005
Sep-2
005
Oct-2
005
Nov-2
005
Dec-
2005
Jan-
2006
Feb-
2006
Mar-
2006
Apr-2
006
May-2
006
Jun-
2006
Ju
ly-2
006
Aug-
2006
Sep-2
006
Oct-2
006
MONTH
PR
OGRE
S
Early PlanActual
Engineering S Curve
-
7/31/2019 Cost-21 day 85
40/60
Engineering S Curve
Finishing
Period
May-2
005
Jun-2
005
Ju
ly-2
005
Aug-2
005
Sep-2
005
Oc
t-2005
Nov-2
005
Dec-2
005
Jan-2
006
Fe
b-2
006
Mar-2
006
Apr-2
006
May-2
006
Jun-2
006
Ju
ly-2
006
Aug-2
006
Sep-2
006
Oc
t-2006
Early Plan 3.40 12.81 24.00 34.00 43.00 51.50 60.00 70.30 78.70 80.01 84.27 88.31 90.40 91.09 91.60 92.05 95.80 100.00
Actual
Cummulative Plan Progress
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
May-2
005
Jun-2
005
July
-2005
Aug-2
005
Sep-2
005
Oct-2005
Nov-2
005
Dec-2
005
Jan-2
006
Feb
-2006
Mar-2006
Apr-2006
May-2
006
Jun-2
006
July
-2006
Aug-2
006
Sep-2
006
Oct-2006
MONTH
PROGRESS
Early PlanActual
Procurement S Curve
-
7/31/2019 Cost-21 day 85
41/60
Procurement S CurveFinishing
Period
May-2
005
Jun-
2005
July-2
005
Aug-2
005
Sep-
2005
Oct-
2005
Nov-2
005
Dec-2
005
Jan-
2006
Feb-
2006
Mar-
2006
Apr-
2006
May-2
006
Jun-
2006
July-2
006
Aug-2
006
Early Plan 0.00 0.00 0.00 0.00 1.35 7.95 15.14 22.77 34.54 46.64 59.25 72.14 84.51 94.15 98.58 100
Actual
Cummulative Plan Progress
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
May-2
005
Jun-2
005
Ju
ly-2
005
Aug-2
005
Sep-2
005
Oc
t-2005
Nov-2
005
Dec-2
005
Jan-2
006
Fe
b-2
006
Mar-
2006
Apr-
2006
May-2
006
Jun-2
006
Ju
ly-2
006
Aug-2
006
MONTH
PROGRES
Early Plan
Actual
Construction S Curve
-
7/31/2019 Cost-21 day 85
42/60
Construction S Curve
FinishingPeriod
May-20
05
Jun-2
0
05
July-20
05
Aug-20
05
Sep-20
05
Oct-20
05
Nov-20
05
Dec-20
05
Jan-2
0
06
Feb-20
06
Mar-20
06
Apr-20
06
May-20
06
Jun-2
0
06
July-20
06
Aug-20
06
Sep-20
06
Oct-20
06
Early 0.00 0.00 0.00 0.35 6.20 12.35 20.11 28.54 37.54 47.04 57.14 67.88 77.48 84.12 89.15 94.16 97.17 100
Actual
Cummulative Plan Progress
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
May-2
005
Jun-2
005
Ju
ly-2
005
Aug-2
005
Sep-2
005
Oc
t-2005
Nov-2
005
Dec-2
005
Jan-2
006
Fe
b-2
006
Mar-
2006
Apr-
2006
May-2
006
Jun-2
006
Ju
ly-2
006
Aug-2
006
Sep-2
006
Oc
t-2006
MONTH
PR
OGRE
S
Early Plan
Ac tual
-
7/31/2019 Cost-21 day 85
43/60
Engineering Man-Hour EstimationQty
Size Sheets Eng. Draft. Eng. Draft. Total
Specifications / Manuals
Standard DrawingsCalculation Notes
Drawings
Data Sheets
Sketches
Inspection and Test Plan
Vendor Document Review Form
Bid EvaluationVendor Drawing / Document Review
Construction Tender Documents
QA DocumentationCoordination Activities
Man-HourDescription
Doc / Dwg Unit Man-Hour
Eq ipment Cost Estimation
-
7/31/2019 Cost-21 day 85
44/60
Equipment Cost Estimation
Drums
Columns / Towers
Reactors
Exchangers
Air Coolers
Tanks
Filters
HeatersFurnaces
Flares
Ignitor Packages
Incinerators
Reformerspumps
Compressors
Gas Turbines
Steam Turbines
Diesel / Gas Engines
Packages
Miscellaneous
Inter.Com.
Spa.
2Y.
Spa.
Cost
Inst.For.
Mat.
For. Gr.
Tot.
Description
Tr.
Wgh.
Loc. Loc.Qty
Mat.
Cod.
Est.
Dim.
Op.
Wgh.
B lk M i l C E i i
-
7/31/2019 Cost-21 day 85
45/60
Bulk Material Cost Estimation
Bulk and Piping Mat.
Electrical Equipment
Electrical Bulk
Instrument Eq.
Instrument Bulk
Steel Structures
SupportsPaint
Insulation
Other Coating Mat.
Fire and Gas
Fire FightingGeneral Building
Miscellaneous
2Y.
Spa.
Inst.Description Qty
Mat.
Cod.
Est.
Dim.
Est.
Wgh.
Tr.
Wgh.
Cost
Loc.Inter.
Com.
Spa.
Loc.
Fab.
For.
Mat.
For. Gr.
Tot.
Ch i l / C l C E i i
-
7/31/2019 Cost-21 day 85
46/60
Chemical / Catalyst Cost Estimation
Init. F Fir.
Y.
Init.
F.
Fir.
Y.
Chemical
Catalyst
Cost
Loc. Supp.Qty.
Init. F.
Qty.
Fir. Y.
Init.
Fill.
Description
Aso.
Pck.
Eq.Tag.
No.
Gr.
Tot.
Inst.
Consumption
Init.
Fill.
First
Y.
Transpor
tation
First
Y.
For. Supp.
Construction Cost Estimation
-
7/31/2019 Cost-21 day 85
47/60
Excavation and Backfilling M3
Concrete Works M3
Reinf. Con. Process Buldg & Fin.
Protection of Buried Cables / Pipes M3
Drainage System M3
Asphalting, Ballasting & Dickes M3
Underground Piping IDErection of Fixed & Floating Roof Tanks Ton
Prefab. of Large Bore Piping (2" and Above) ID
Prefab. And Erection of Pipe Support ID
Erection of Steel Structure Ton
Erection of Fixed Equipment and Heat Exch. Ton
Erction of Large Bore Piping (2" and Above) IDPrefab. And Erction of Small Bore Piping ID
Erection of Machinery and Packages Ton
heavy Equipment Erection (90 Tons and Above) Ton
Erection of Internal Parts of Equipment Ton
Installation of Earthing System Unit
Electrical Cables Laying and Connections L.MPlant Lighting System Unit
Panel Installation inControl Room / Substation Cu.
Cathodic Prtection L.M
Electrical / Instrument Cable Tray L.M
Field Installation of Instrument Unit
Pneumatic / Electrical Connections Unit
Painting of Piping, Equipment and Tanks M2
Insulation of Piping, Equipment and Tanks M2
P.W (%)Av. Unit Price PriceDescription Unit Qty Man-Hour
Indirect Machinery DistributionTotalMonthSL
-
7/31/2019 Cost-21 day 85
48/60
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Batching Plant
Truck MixerLoader
Truck Mixer
Excavator
Roller
Grader
Water Tanker
Btumen Car
Finisher
Craner 800 Ton
Craner 250 Ton
Craner 100 Ton
Craner 45 Ton
Craner 30 Ton
Craner 20 Ton
Craner 15 TonTIG Welding Set
Diesel Welding Machine
Air Comp.250 (CFM)
Air Comp.450 (CFM)
Stress Relieve Set
Sand Blast Set
Airless Spray SetTractor With Trailer
Lift Truck 10 Ton
Lift Truck 5 Ton
Trailer
Diesel Generator 50 KW
Diesel Generator 150 KW
Pick Up Van
PatrolMini Bus
Bus
Ambulance
Total
M/M
MonthSL.
No.Description
Direct Manpower Distribution
-
7/31/2019 Cost-21 day 85
49/60
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Foreman
Tank Fabricator
Code Welder
S/S WelderSteel Erector
Burner
Scaffolder
Mill Wright
Machine 1Machine 2
Helper
Labour
Foreman
Mason
Carpenter
Barbender
S/S Welder
Blacksmith
HelperLabour
Description
Month Total
M/MStatic & Rotary Equipment
Civil, Building and Structure
Direct Manpower Distribution
-
7/31/2019 Cost-21 day 85
50/60
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Foreman
S/S Welder
Scaffolder
Sand BlasterElectrician 1
Electrician 2
Helper
Labour
Foreman
S/S Welder
Instrument Fitter 1
Instrument Fitter 2Scaffolder
Electrician
Helper
Labour
Electrical and Telecommunication
Instrumentation
DescriptionMonth Total
M/M
Direct Manpower Distribution
-
7/31/2019 Cost-21 day 85
51/60
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Foreman
TIG Welder
Code Welder
S/S Welder
Steel Erector
Burnerman
Pipe Fitter
Mechanic 1
Mechanic 2
Stress Relive Tech.
Scaffolder
Blacksmith
Wrapping ManHelper
Labour
Foreman
Scaffolder
Insulator
TIN SmithHelper
Labour
Foreman
Painter
Scaffolder
Sand Blaster
Helper
Labour
Piping
Insulation
Painting
DescriptionMonth Total
M/M
Indirect Manpower Distribution
-
7/31/2019 Cost-21 day 85
52/60
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18Project Director
Site General Manager
Secretery
Contract Administrator
CoordinatorSenior Safety Engineer
Plan. & Project Cont.Manager
Cost Controller
Planner
Project ControllerPlanning Reporter
S/S Superintendent
S/S Engineer
S/S Technician
SurveyourSurveying Worker
Mechanical Supperintendent
Mechanical Engineering (Rotary)
Mechanical Technician (Rotary)
Mechanical Engineering (Static)Mechanical Technician (Static)
DescriptionMonth Total
M/M
Indirect Manpower DistributionM th T t l
-
7/31/2019 Cost-21 day 85
53/60
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Piping EngineeringPiping Technician
Electrical Supperintendent
Electrical Engineering
Electrical Technician
Instrument SuperintendentInstrunment Engineering
Instrument Technecian
Paint and Insulation Technecian
QA /QC Supervisor
QA /QC Staff
Field Eng. & QC Manager
Technical Office Staffs
Draftsman
Document Center Senior Officer
Document Center Officer
Stress Relieve StaffNDT Staff
NDT Worker
Precommissioning manger
Precommissioning Engineer
Precommissioning Technecians
Commissioning Manger
Commissioning Engineer
Commissioning Technecians
DescriptionMonth Total
M/M
Indirect Manpower Distribution
-
7/31/2019 Cost-21 day 85
54/60
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18Training Manger
Training Engineer
Training Technecians
Proc.t & Stores Superintendent
Store Supervisor
Store Controller
Store Worker
Buyer (Site)
Buyer (Home Office)
Adm. & Finance Superintendent
Administration Staff
Accounting
Camp Service Officer
Site Service Officer
Nurse
Watchman
Teaman
Cleaner
Chief Cooker
Cooker
Postman
General Helper
General Worker
DescriptionMonth Total
M/M
4. Main Questions to be Asked to Cost
-
7/31/2019 Cost-21 day 85
55/60
Estimate Were Historical Data Used?
Were Inflation Rates Used?
Were Project Scope Definition Have Been CompletelyUnderstood and Interred in the Cost Estimating Formats?
Were Geometrical and Site Condition CompletelyUnderstood?
Were Codes and Standards Have Been Clarified?
Were Any Regulation to be Followed During Contract HaveBeen Asked From Client?
Were Training Requirements for Client Personnel HaveCommunicated?
Is There Any Client Facilities during Contract Execution?
5 Why People Get Estimating Wrong?
-
7/31/2019 Cost-21 day 85
56/60
5. Why People Get Estimating Wrong?
Over Optimistic Nothing Will Go Wrong
Underestimating Things Like Control the Activity, Coaching, Supervision,Project Meeting
Lack of Understanding of Project Scope Ignoring Reality Assuming Nothing Will Change
Just Guessing
Estimating Isnt a Managed Activity!
Junior People Involvement Cross Section Communication During Estimation Time
Double Estimating
Unclear Scope of Supply Between Procurement and Construction
Department Underestimating Cost of Temporary Facilities, Consumables, Tools, etc.,
for Construction, Pre-commissioning, etc.
Lack of Good Relations With Subcontractors (Vendors)
Giving Gold Plating Instead of Following Scope
6 Risk Related Cost Estimating
-
7/31/2019 Cost-21 day 85
57/60
6.Risk Related Cost Estimating
Type / Complexity of Project
Procurement Restriction and LawClient / Contractor Resources (personnel, etc.,)
Project Schedule
Clients / Contractors Ability to Finance Project
Scope Changes
Design Criteria
7.Summary (1/2)
-
7/31/2019 Cost-21 day 85
58/60
7.Summary (1/2)
Project Cost Management / Estimating is PrimarilyConcerned with the Cost of the Resource Needed to
Complete a Defined Activity. Project Cost Management Should Also Consider the Effect
of Project Decisions on the Cost of Using, Maintaining, andSupporting the Product, Service, or Result of the Project.
Project Cost Estimating Consider the InformationRequirements of the Project Stakeholders. DifferentStakeholders will Measure Project Costs in Different Ways
and Different Items. On Some Projects, Especially Ones of Smaller Scope, Cost
Estimating and Cost Budgeting are so Tightly Linked thatare Reviewed as a Process that can be Performed by a
Single Person.
7. Summary (2/2)
-
7/31/2019 Cost-21 day 85
59/60
7. Summary (2/2)
Some Organizations have Predefined Approachedto Cost Estimating. Where these Exist, the ProjectOperates Within the Boundaries Defined by thePolicy
Cost of Quality Should be Also be Used to Preparethe Schedule Activity Cost Estimate.
-
7/31/2019 Cost-21 day 85
60/60
Thank You