cost-21 day 85

Upload: ieltsabadan

Post on 05-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Cost-21 day 85

    1/60

    A Guide Line To Perform

    EPC Project Contract Cost

    EstimationIn the Field of

    Oil, Gas & Petrochemical Industries

    Held by : FARAGOSTARAN

    Present by: Hassan MirzaieDate : 11 January 2007

    Location: Simorgh Hotel

    Tel. & Fax : 021- 8870 29 24 , 8870 45 84

  • 7/31/2019 Cost-21 day 85

    2/60

    No Body Plans to Fail, But

    Fails to Planning!

  • 7/31/2019 Cost-21 day 85

    3/60

    EPC Key Approach

    EPC Project Contract Cost Estimation

    Contractors Know-How For EPC Project Executing

    Project Work Break Down Structure (WBS)

    Identifying and Managing Risks in EPC Projects

    Managing & Control of Project Changes in EPC Projects

    EPC Project Management

    Engineering & Design Phase Documents Flow Diagram

  • 7/31/2019 Cost-21 day 85

    4/60

    A Guide Line To Perform

    EPC Project Contract Cost

    EstimationIn the Field of

    Oil, Gas & Petrochemical Industries

  • 7/31/2019 Cost-21 day 85

    5/60

    Seminar Approach

    1. EPC Project Definition

    2. Functional WBS Code for EPC Project

    3. Methodology and Flow of Cost Estimating

    4. Main Questions to be Asked to Cost Estimate

    5. Why People Get Estimating Wrong

    6. Risk Related Cost Estimating7. Summary

  • 7/31/2019 Cost-21 day 85

    6/60

    1. EPC Project Definition

    Performing of Feasibility Study

    Preparation of Bid Documents

    License Agreement and Engineering Design (Basic,FEED & Detail Activities)

    Procurement

    Construction / Erection and Pre-CommissioningCommissioning and Start-up

    Training

  • 7/31/2019 Cost-21 day 85

    7/60

    DefineScope

    Funding /Budgeting

    Feasibility

    Study

    PlanningPhase

    PMC/Engineer

    Selection

    Process/

    Basic Design

    ITB

    Preparation

    Evaluation

    & Clarification

    ITB

    Bid Evaluation &Clarification

    Bid Negotiation

    Letter of Intend

    Contract Negotiation& Signing

    Marketing/SalesApproach

    Bidding Strategy

    Partnering

    Site Survey &Clarification

    Cost Estimate &

    Bid Submission

    Project DefinitionPhase

    Project Execution

    Engineering

    Design

    Procurement

    /Supply

    Construction

    Implementation Phase

    EPC Project Flow Diagram

  • 7/31/2019 Cost-21 day 85

    8/60

    Typical Weight Percent of An EPC

    Project

    1Logistic and Others7

    1Training6

    2Commissioning and

    Start-up

    5

    20-25Construction Pre-Com450-60Procurement3

    7-10License & Engineering2

    1Feasibility Study1

    % RangeDescriptionItem

  • 7/31/2019 Cost-21 day 85

    9/60

    2. Functional WBS Code for EPC

    Project

    PrefossinalServices Materials Labor Work Transportation

    Direct / IndirectExpenses

    Others

    EPC Project

  • 7/31/2019 Cost-21 day 85

    10/60

    Professional Services

    Professional

    services

    Detail

    Engineering

    Quality MGT

    Procurement

    Const. MGT &

    Supervision

    Project MGTBasic

    Engineering

    Project

    Administration

    Comm. &

    Operation

    Training

    Others

  • 7/31/2019 Cost-21 day 85

    11/60

    Professional Services (1/2)

    Project Management and ControlProject Directing, Organization and Stuffing, Project Planning and Control,

    Project Coordination, Estimating, Management Support

    Basic EngineeringProcess Design, Plant Safety, Instrumentation, General Civil, Plant Layout andPiping Specification

    Detail EngineeringCivil and U/G, Structure, Building, Equipment, Piping, Instrumentation,Electrical, Paint AND Insulation,

    ProcurementProcurement General, Purchasing, Subcontracting, Expediting, Traffic andCustom Clearances

  • 7/31/2019 Cost-21 day 85

    12/60

    Professional Services (2/2)

    Quality ManagementQuality Assurance, Quality Control, Shop Inspection, Field Inspection,

    Maintenance Inspection, Plant Diagnosis

    Construction Management and SupervisionConstruction Management and Super-intendance, Planning,Field Controlling,Field Installation Supervision, Field Technical Support, Field Engineering,Subcontracting Administration

    Commissioning and OperationCommissioning and Operation General, Pre-commissioning, Commissioning,Operation Services

    Project AdministrationAdministration General, Personnel Control, Project Accounting, Communicationand Correspondence, Document Handling, Camp Organization, General Affairs

  • 7/31/2019 Cost-21 day 85

    13/60

    Materials

    Materials

    Spare Parts OthersDirect

    Materials

    Ind. Mat. for

    Tem. Facilities

  • 7/31/2019 Cost-21 day 85

    14/60

    Materials

    Direct Materials

    Civil Materials, Structure Materials, Building Materials, Equipment,Piping and Bulk, Instrumentation, Electrical, Insulation and Painting,FireProofing and Surface Protection, Catalysts, Chemicals, and Utilities

    Indirect MaterialsTemporary Building, Utilities and Telecommunications, HousingEquipment and Furniture, Shop Equipment and Tools,CommonScaffolding, Canteen

    Spare Partsspare Parts for Commissioning and Start-up, Spare Parts for Operation (2Years)

  • 7/31/2019 Cost-21 day 85

    15/60

    Labor Work

    Labor Work

    Indirect Field

    Operation

    Construction

    Equipment

    Supervisory

    Others

    Direct Labor

    Work

    Ind. Lab.

    Work for

    Temp. Work

  • 7/31/2019 Cost-21 day 85

    16/60

    Labor Work (1/2)

    Direct Labor WorkCivil General, Concrete Structure, Steel Structure, Building, Equipment

    Installation, Piping, Instrumentation, Electrical, Insulation and Painting, FireProofing and Surface Protection, Catalysts, Chemicals and Utilities, Othersincluding System Test Preparation

    Indirect Labor Work For Temporary FacilitiesTemporary Building, Utilities and Telecommunications, Housing Equipment andFurniture, Assembling of Shop Equipment and Tools, Installation of CommonScaffolding, Canteen,

    Indirect Field OperationCommissioning and Operation, Project Administration

    Supervisory

    Civil General, Concrete Structure, Steel Structure, Building, EquipmentInstallation, Piping, Instrumentation, Electrical, Insulation and Painting, FireProofing and Surface Protection, Catalysts, Chemicals and Utilities

  • 7/31/2019 Cost-21 day 85

    17/60

    Labor Work (2/2)

    Construction Equipment

    Construction equipment, Operator and Driver

  • 7/31/2019 Cost-21 day 85

    18/60

    Transportation

    Transportation

    Onshore OthersOffshore Ocean Frieght

  • 7/31/2019 Cost-21 day 85

    19/60

    Transportation

    Offshore

    Packing, Handling, Transportation, Shipping and Custom Clearances

    Ocean FreightOcean Freight, Air Freight

    OnshorePacking, Handling, Transportation,

  • 7/31/2019 Cost-21 day 85

    20/60

    Direct and Indirect Expenses

    Financial

    Charge

    Tax and

    Duties

    Insurance

    Licensors

    Charge

    Home and

    Branch Office

    Expences

    Field Office

    Expenses

    Consultant

    Fee

    Third Party

    InspectionCharge

    Agent Fee Others

  • 7/31/2019 Cost-21 day 85

    21/60

    Direct and Indirect Expenses (1/2)

    Home and Branch Office ExpensesTraveling and Traffic Charge, Telecommunication Charge, Office Charge,Social

    Charges, Miscellaneous Charges

    Field Office ExpensesTraveling and Traffic Charge, Telecommunication Charge, Office Charge,SocialCharges, Miscellaneous Charges

    Financial ChargeL/C Charge, Bond Charge, Interest Charge

    InsuranceGovernmental Insurance, Transport Insurance, Travels, Accident Insurance,Social Insurance, Construction Insurance, Provisional Liability Insurance

  • 7/31/2019 Cost-21 day 85

    22/60

    Direct and Indirect Expenses (2/2)

    Tax and Duties

    Import Duties, Corporate Charge

    Licensors ChargeRoyalty, Know-How Fee, Basic Design Fee, Design Checking Fee,

    Operation Charge

    Consultant FeeEngineering Consultant Fee, Training Consultant Fee, Accountant Fee,

    Lawyer Fee

  • 7/31/2019 Cost-21 day 85

    23/60

    Others

    Others

    Rate

    Difference ContingencyGeneral

    Overhead

  • 7/31/2019 Cost-21 day 85

    24/60

    3. Methodology and Flow of Cost

    Estimating3.1 Definition of Cost

    3.2 Type of Costs3.3 Cost Estimation Methodology (Tools and

    Techniques)3.4 Cost Estimation Templates for EPC

    Project

  • 7/31/2019 Cost-21 day 85

    25/60

    3.1 Definition of Cost

    A Resource (People, Equipment, et.) whichForeseen to Achieve a Specific Objective

    Cost Estimating Should be Based on a WBS toImprove Accuracy

    Cost Estimation Includes all the Work Needed to

    Complete the Project Including: Quality Efforts,Risk Efforts, Management Time

    Cost Estimates are Generally Expressed in Units of

    Currency (Dollars, Euro, Rials,etc.,)

  • 7/31/2019 Cost-21 day 85

    26/60

    3.2 Type of Costs (1/2)

    Variable Costs: Any Cost that Changes With the Amount ofProduction or the Amount of Work. Examples Include the

    Cost of Material, Supplies, Labor, etc. Fixed Costs: Costs That Do Not Change as Production

    Changes. Examples Include Set-Up, Rental, etc.

    Direct Costs: Costs That Are Directly Attributable to the Work

    on the Project. Examples are Team Travel, Recognition andRewards, Cost of Materials, Training

    Indirect Costs: Overhead Items or Costs Incurred for theBenefit of More Than on Project. Examples Include Taxes,

    Benefits, Insurances, etc. Opportunity Costs: Net Present Value of a Project. Is Really a

    Choice to Do / Not to Do a Project

  • 7/31/2019 Cost-21 day 85

    27/60

    3.2 Type of Costs (2/2)

    Type of Guest Accuracy Rate Rough Order of Magnitude (ROM) -25% to 75%

    Budgetary -10% to 25%

    Approximate Estimate (Informational) + or 15%

    Definitive (Based on Detailed Information) + or 5%

    3 3 C E i i M h d l

  • 7/31/2019 Cost-21 day 85

    28/60

    3.3 Cost Estimating Methodology

    (Tools and Techniques)3.3.1 Analogous or Top-Down

    3.3.2 Parametric or Bottom-Up3.3.3 Cost Budgeting

    3 3 1 A l T D

  • 7/31/2019 Cost-21 day 85

    29/60

    3.3.1 Analogous or Top-Down

    Estimating (1/2) Uses the Actual Cost of a Previous, Similar Project as the

    Basis for the New Estimate

    Advantages: Quick

    Activities Need not be Identified

    Less Costly to Create

    Disadvantages: Less Accurate

    Estimates are Prepared with a Limited Amount of Detailed Information andUnderstanding of the Project

    Requires Considerable Experience to Do Well

    Extremely Difficult for Project With Uncertainty

    3 3 1 A l T D

  • 7/31/2019 Cost-21 day 85

    30/60

    3.3.1 Analogous or Top-Down

    Estimating (2/2) Examples:

    Estimation of Engineering Man-Hour from Previous Projects

    Weight Of Piping Bulk Materials

    Cost of Temporary Equipment to be Used During Construction

    3 3 2 P t i B tt U

  • 7/31/2019 Cost-21 day 85

    31/60

    3.3.2 Parametric or Bottom-Up

    Estimating (1/2) Estimate Individual Work Items and Sum Them to Get a

    Total Estimate

    Advantages: More Accurate

    Gains Buy-In From Team Because the Team Creates Estimates the CanLive With

    Has Been Prepared Based On a Detailed Analysis of the Project Provides a Basis for Monitoring and Controlling, Performance Measurement

    and Management

    Disadvantages: Takes Time and Expenses

    Tendency for the Team to Pad Estimates Unless Taught About Reserves

    Requires that the Project be Well Understood

    Requires Time to Break the Project Down into Smaller Pieces

    3 3 2 P t i B tt Up

  • 7/31/2019 Cost-21 day 85

    32/60

    3.3.2 Parametric or Bottom-Up

    Estimating (2/2)

    Examples: Detailed Estimation of Cost of Engineering Manpower, Equipment,Materials, Construction Fee Based on Conceptual Design Information

    and Document.

  • 7/31/2019 Cost-21 day 85

    33/60

    3.3.3 Cost Budgeting

  • 7/31/2019 Cost-21 day 85

    34/60

    3.3.3 Cost Budgeting

    A Budget is Merely a Compilation of the IndividualCost Estimates.

    Management Reserves: Extra Amount of Funds tobe Set Aside to Cover Unforeseen Risks or Change inthe Project

    Contingency Reserves: Percentage of the Subtotal ofthe Cost of Project Items, Supplemental Work,Materials and Expenses

  • 7/31/2019 Cost-21 day 85

    35/60

    Report from GG5, Dec. 20, 2005

    General Methodology

    Create Technical

    Requirements Document

    Develop Technical

    Conceptual Design

    Create the WBSEstablish C/S

    Coordinator

    for each WorkPackage

    Establish rules for C/S &

    define assumptions

    Set up tools and

    format for data input

    Develop the RLSand Mgmt Docs

    Estimate Cost &Schedule and

    create the BOE

    ReviewNo

    Yes

    Fund Starts

    C/S = Cost & ScheduleWBS = Work Breakdown StructureBOE = Basis of EstimateRLS = Resource Loaded Schedule

    Interpret this Core

    Cost in each Region

    3 4 Cost Estimation Templates for

  • 7/31/2019 Cost-21 day 85

    36/60

    3.4 Cost Estimation Templates for

    EPC Project (1/2) A Commercial Proposal for an EPC Project Normally

    Includes Following Sections:

    EngineeringMan Power (Basic Engineering, Endorsement, Detail Engineering)

    Consumable

    Office and Furniture

    Management

    Overhead Contingency

    Procurement

    Procurement Engineering and Man Power (Technical Doc. Preparationand Material requisition, Bidder Clarifications, Proposal Evaluation(Technical, Commercial, Expediting and Inspection)

    Equipment (LC Opening, Purchase Order, Manufacturing, Test andInspection)

    Bulk Materials (LC Opening, Purchase Order, Manufacturing, Test andInspection)

    Logistic (Shipment, Custom Clearances and Delivery to Site)

    3.4 Cost Estimation Templates for

  • 7/31/2019 Cost-21 day 85

    37/60

    3.4 Cost Estimation Templates for

    EPC Project (2/2) Insurance

    Provisional Cost

    Overhead and Contingency

    Construction Site Preparation

    Site Establishment Plant Construction

    Safety and Security

    Camping

    Pre-Commissioning Commissioning

    Management Man Power

    Contingency

    Construction Insurance

    EPC Cost Weight Percent

  • 7/31/2019 Cost-21 day 85

    38/60

    gDescription (Sub (Total Remarks

    8.5

    Man Power 66 Engineering TeamConsumable 7.5 Stationary, Doc. / Dwg.

    Office and Furniture 8.5 Soffice Included all Stationary Equipment

    Management 5

    Overhead 8 Taxes, Duties, Social Fees

    Contingency 5

    64Equipment 65 Mechanical, Electrical, Instrument

    Bulk Materials 18.5 Piping, Steel Str., Inst., Ele., Paint, Ins., F&G, Chem.,

    Logestic and Custom Clear 4 Transp, Costum Du, Insp, Load and Unload, Heavy Li

    Man Power 2.8

    Insurance 0.7 Financial and Logestic Insurance

    Overhead and Contingency 0.5 Office Rent, ConsumablesProvisional Cost 8.5 2 Years Spare Part, Duties

    27.5

    Site Preparation 5 Site Preparation and Site Access

    Site Establishment 2 Mobilization / Demobilization, Workshop, Spool Shop

    Plant Construction 70 Civil, Structures, Mechanical, Electrical, Inst. Installat

    Safety and Security 2.5 HSE, Guard Housing, Fire Station, First AidCamping 8.5 Camp, Catering, Transportation

    Pre-Commissioning 2 Mechanical Complition, Test Packages

    Commissioning 2.5 Test Running, Performance Test, Vendor Specialist

    Mangement Man Power 1.5

    Contingency 5

    Construction Insurance 1 Full Risk

    100

    Engineering

    Procurement

    Construction

    Total

    Overall S Curve

  • 7/31/2019 Cost-21 day 85

    39/60

    Overall S Curve

    Finishing

    PeriodMay-2

    00

    5

    Jun-2

    00

    5

    Ju

    ly-2

    005

    Aug-2

    005

    Sep-2

    00

    5

    Oc

    t-200

    5

    Nov-2

    00

    5

    Dec-2

    00

    5

    Jan-2

    00

    6

    Fe

    b-2

    00

    6

    Mar-2

    00

    6

    Apr-2

    00

    6

    May-2

    00

    6

    Jun-2

    00

    6

    Ju

    ly-2

    006

    Aug-2

    006

    Sep-2

    00

    6

    Oc

    t-200

    6

    Early Pla 0 0 1 1 4 11 18 26 37 48.2 59.8 72 83 90.9 96 98 99 100

    Actual

    Cummulative Plan Progress

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    May-2

    005

    Jun-

    2005

    Ju

    ly-2

    005

    Aug-

    2005

    Sep-2

    005

    Oct-2

    005

    Nov-2

    005

    Dec-

    2005

    Jan-

    2006

    Feb-

    2006

    Mar-

    2006

    Apr-2

    006

    May-2

    006

    Jun-

    2006

    Ju

    ly-2

    006

    Aug-

    2006

    Sep-2

    006

    Oct-2

    006

    MONTH

    PR

    OGRE

    S

    Early PlanActual

    Engineering S Curve

  • 7/31/2019 Cost-21 day 85

    40/60

    Engineering S Curve

    Finishing

    Period

    May-2

    005

    Jun-2

    005

    Ju

    ly-2

    005

    Aug-2

    005

    Sep-2

    005

    Oc

    t-2005

    Nov-2

    005

    Dec-2

    005

    Jan-2

    006

    Fe

    b-2

    006

    Mar-2

    006

    Apr-2

    006

    May-2

    006

    Jun-2

    006

    Ju

    ly-2

    006

    Aug-2

    006

    Sep-2

    006

    Oc

    t-2006

    Early Plan 3.40 12.81 24.00 34.00 43.00 51.50 60.00 70.30 78.70 80.01 84.27 88.31 90.40 91.09 91.60 92.05 95.80 100.00

    Actual

    Cummulative Plan Progress

    0.00

    10.00

    20.00

    30.00

    40.00

    50.00

    60.00

    70.00

    80.00

    90.00

    100.00

    May-2

    005

    Jun-2

    005

    July

    -2005

    Aug-2

    005

    Sep-2

    005

    Oct-2005

    Nov-2

    005

    Dec-2

    005

    Jan-2

    006

    Feb

    -2006

    Mar-2006

    Apr-2006

    May-2

    006

    Jun-2

    006

    July

    -2006

    Aug-2

    006

    Sep-2

    006

    Oct-2006

    MONTH

    PROGRESS

    Early PlanActual

    Procurement S Curve

  • 7/31/2019 Cost-21 day 85

    41/60

    Procurement S CurveFinishing

    Period

    May-2

    005

    Jun-

    2005

    July-2

    005

    Aug-2

    005

    Sep-

    2005

    Oct-

    2005

    Nov-2

    005

    Dec-2

    005

    Jan-

    2006

    Feb-

    2006

    Mar-

    2006

    Apr-

    2006

    May-2

    006

    Jun-

    2006

    July-2

    006

    Aug-2

    006

    Early Plan 0.00 0.00 0.00 0.00 1.35 7.95 15.14 22.77 34.54 46.64 59.25 72.14 84.51 94.15 98.58 100

    Actual

    Cummulative Plan Progress

    0.00

    10.00

    20.00

    30.00

    40.00

    50.00

    60.00

    70.00

    80.00

    90.00

    100.00

    May-2

    005

    Jun-2

    005

    Ju

    ly-2

    005

    Aug-2

    005

    Sep-2

    005

    Oc

    t-2005

    Nov-2

    005

    Dec-2

    005

    Jan-2

    006

    Fe

    b-2

    006

    Mar-

    2006

    Apr-

    2006

    May-2

    006

    Jun-2

    006

    Ju

    ly-2

    006

    Aug-2

    006

    MONTH

    PROGRES

    Early Plan

    Actual

    Construction S Curve

  • 7/31/2019 Cost-21 day 85

    42/60

    Construction S Curve

    FinishingPeriod

    May-20

    05

    Jun-2

    0

    05

    July-20

    05

    Aug-20

    05

    Sep-20

    05

    Oct-20

    05

    Nov-20

    05

    Dec-20

    05

    Jan-2

    0

    06

    Feb-20

    06

    Mar-20

    06

    Apr-20

    06

    May-20

    06

    Jun-2

    0

    06

    July-20

    06

    Aug-20

    06

    Sep-20

    06

    Oct-20

    06

    Early 0.00 0.00 0.00 0.35 6.20 12.35 20.11 28.54 37.54 47.04 57.14 67.88 77.48 84.12 89.15 94.16 97.17 100

    Actual

    Cummulative Plan Progress

    0.00

    10.00

    20.00

    30.00

    40.00

    50.00

    60.00

    70.00

    80.00

    90.00

    100.00

    May-2

    005

    Jun-2

    005

    Ju

    ly-2

    005

    Aug-2

    005

    Sep-2

    005

    Oc

    t-2005

    Nov-2

    005

    Dec-2

    005

    Jan-2

    006

    Fe

    b-2

    006

    Mar-

    2006

    Apr-

    2006

    May-2

    006

    Jun-2

    006

    Ju

    ly-2

    006

    Aug-2

    006

    Sep-2

    006

    Oc

    t-2006

    MONTH

    PR

    OGRE

    S

    Early Plan

    Ac tual

  • 7/31/2019 Cost-21 day 85

    43/60

    Engineering Man-Hour EstimationQty

    Size Sheets Eng. Draft. Eng. Draft. Total

    Specifications / Manuals

    Standard DrawingsCalculation Notes

    Drawings

    Data Sheets

    Sketches

    Inspection and Test Plan

    Vendor Document Review Form

    Bid EvaluationVendor Drawing / Document Review

    Construction Tender Documents

    QA DocumentationCoordination Activities

    Man-HourDescription

    Doc / Dwg Unit Man-Hour

    Eq ipment Cost Estimation

  • 7/31/2019 Cost-21 day 85

    44/60

    Equipment Cost Estimation

    Drums

    Columns / Towers

    Reactors

    Exchangers

    Air Coolers

    Tanks

    Filters

    HeatersFurnaces

    Flares

    Ignitor Packages

    Incinerators

    Reformerspumps

    Compressors

    Gas Turbines

    Steam Turbines

    Diesel / Gas Engines

    Packages

    Miscellaneous

    Inter.Com.

    Spa.

    2Y.

    Spa.

    Cost

    Inst.For.

    Mat.

    For. Gr.

    Tot.

    Description

    Tr.

    Wgh.

    Loc. Loc.Qty

    Mat.

    Cod.

    Est.

    Dim.

    Op.

    Wgh.

    B lk M i l C E i i

  • 7/31/2019 Cost-21 day 85

    45/60

    Bulk Material Cost Estimation

    Bulk and Piping Mat.

    Electrical Equipment

    Electrical Bulk

    Instrument Eq.

    Instrument Bulk

    Steel Structures

    SupportsPaint

    Insulation

    Other Coating Mat.

    Fire and Gas

    Fire FightingGeneral Building

    Miscellaneous

    2Y.

    Spa.

    Inst.Description Qty

    Mat.

    Cod.

    Est.

    Dim.

    Est.

    Wgh.

    Tr.

    Wgh.

    Cost

    Loc.Inter.

    Com.

    Spa.

    Loc.

    Fab.

    For.

    Mat.

    For. Gr.

    Tot.

    Ch i l / C l C E i i

  • 7/31/2019 Cost-21 day 85

    46/60

    Chemical / Catalyst Cost Estimation

    Init. F Fir.

    Y.

    Init.

    F.

    Fir.

    Y.

    Chemical

    Catalyst

    Cost

    Loc. Supp.Qty.

    Init. F.

    Qty.

    Fir. Y.

    Init.

    Fill.

    Description

    Aso.

    Pck.

    Eq.Tag.

    No.

    Gr.

    Tot.

    Inst.

    Consumption

    Init.

    Fill.

    First

    Y.

    Transpor

    tation

    First

    Y.

    For. Supp.

    Construction Cost Estimation

  • 7/31/2019 Cost-21 day 85

    47/60

    Excavation and Backfilling M3

    Concrete Works M3

    Reinf. Con. Process Buldg & Fin.

    Protection of Buried Cables / Pipes M3

    Drainage System M3

    Asphalting, Ballasting & Dickes M3

    Underground Piping IDErection of Fixed & Floating Roof Tanks Ton

    Prefab. of Large Bore Piping (2" and Above) ID

    Prefab. And Erection of Pipe Support ID

    Erection of Steel Structure Ton

    Erection of Fixed Equipment and Heat Exch. Ton

    Erction of Large Bore Piping (2" and Above) IDPrefab. And Erction of Small Bore Piping ID

    Erection of Machinery and Packages Ton

    heavy Equipment Erection (90 Tons and Above) Ton

    Erection of Internal Parts of Equipment Ton

    Installation of Earthing System Unit

    Electrical Cables Laying and Connections L.MPlant Lighting System Unit

    Panel Installation inControl Room / Substation Cu.

    Cathodic Prtection L.M

    Electrical / Instrument Cable Tray L.M

    Field Installation of Instrument Unit

    Pneumatic / Electrical Connections Unit

    Painting of Piping, Equipment and Tanks M2

    Insulation of Piping, Equipment and Tanks M2

    P.W (%)Av. Unit Price PriceDescription Unit Qty Man-Hour

    Indirect Machinery DistributionTotalMonthSL

  • 7/31/2019 Cost-21 day 85

    48/60

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    Batching Plant

    Truck MixerLoader

    Truck Mixer

    Excavator

    Roller

    Grader

    Water Tanker

    Btumen Car

    Finisher

    Craner 800 Ton

    Craner 250 Ton

    Craner 100 Ton

    Craner 45 Ton

    Craner 30 Ton

    Craner 20 Ton

    Craner 15 TonTIG Welding Set

    Diesel Welding Machine

    Air Comp.250 (CFM)

    Air Comp.450 (CFM)

    Stress Relieve Set

    Sand Blast Set

    Airless Spray SetTractor With Trailer

    Lift Truck 10 Ton

    Lift Truck 5 Ton

    Trailer

    Diesel Generator 50 KW

    Diesel Generator 150 KW

    Pick Up Van

    PatrolMini Bus

    Bus

    Ambulance

    Total

    M/M

    MonthSL.

    No.Description

    Direct Manpower Distribution

  • 7/31/2019 Cost-21 day 85

    49/60

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    Foreman

    Tank Fabricator

    Code Welder

    S/S WelderSteel Erector

    Burner

    Scaffolder

    Mill Wright

    Machine 1Machine 2

    Helper

    Labour

    Foreman

    Mason

    Carpenter

    Barbender

    S/S Welder

    Blacksmith

    HelperLabour

    Description

    Month Total

    M/MStatic & Rotary Equipment

    Civil, Building and Structure

    Direct Manpower Distribution

  • 7/31/2019 Cost-21 day 85

    50/60

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    Foreman

    S/S Welder

    Scaffolder

    Sand BlasterElectrician 1

    Electrician 2

    Helper

    Labour

    Foreman

    S/S Welder

    Instrument Fitter 1

    Instrument Fitter 2Scaffolder

    Electrician

    Helper

    Labour

    Electrical and Telecommunication

    Instrumentation

    DescriptionMonth Total

    M/M

    Direct Manpower Distribution

  • 7/31/2019 Cost-21 day 85

    51/60

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    Foreman

    TIG Welder

    Code Welder

    S/S Welder

    Steel Erector

    Burnerman

    Pipe Fitter

    Mechanic 1

    Mechanic 2

    Stress Relive Tech.

    Scaffolder

    Blacksmith

    Wrapping ManHelper

    Labour

    Foreman

    Scaffolder

    Insulator

    TIN SmithHelper

    Labour

    Foreman

    Painter

    Scaffolder

    Sand Blaster

    Helper

    Labour

    Piping

    Insulation

    Painting

    DescriptionMonth Total

    M/M

    Indirect Manpower Distribution

  • 7/31/2019 Cost-21 day 85

    52/60

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18Project Director

    Site General Manager

    Secretery

    Contract Administrator

    CoordinatorSenior Safety Engineer

    Plan. & Project Cont.Manager

    Cost Controller

    Planner

    Project ControllerPlanning Reporter

    S/S Superintendent

    S/S Engineer

    S/S Technician

    SurveyourSurveying Worker

    Mechanical Supperintendent

    Mechanical Engineering (Rotary)

    Mechanical Technician (Rotary)

    Mechanical Engineering (Static)Mechanical Technician (Static)

    DescriptionMonth Total

    M/M

    Indirect Manpower DistributionM th T t l

  • 7/31/2019 Cost-21 day 85

    53/60

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    Piping EngineeringPiping Technician

    Electrical Supperintendent

    Electrical Engineering

    Electrical Technician

    Instrument SuperintendentInstrunment Engineering

    Instrument Technecian

    Paint and Insulation Technecian

    QA /QC Supervisor

    QA /QC Staff

    Field Eng. & QC Manager

    Technical Office Staffs

    Draftsman

    Document Center Senior Officer

    Document Center Officer

    Stress Relieve StaffNDT Staff

    NDT Worker

    Precommissioning manger

    Precommissioning Engineer

    Precommissioning Technecians

    Commissioning Manger

    Commissioning Engineer

    Commissioning Technecians

    DescriptionMonth Total

    M/M

    Indirect Manpower Distribution

  • 7/31/2019 Cost-21 day 85

    54/60

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18Training Manger

    Training Engineer

    Training Technecians

    Proc.t & Stores Superintendent

    Store Supervisor

    Store Controller

    Store Worker

    Buyer (Site)

    Buyer (Home Office)

    Adm. & Finance Superintendent

    Administration Staff

    Accounting

    Camp Service Officer

    Site Service Officer

    Nurse

    Watchman

    Teaman

    Cleaner

    Chief Cooker

    Cooker

    Postman

    General Helper

    General Worker

    DescriptionMonth Total

    M/M

    4. Main Questions to be Asked to Cost

  • 7/31/2019 Cost-21 day 85

    55/60

    Estimate Were Historical Data Used?

    Were Inflation Rates Used?

    Were Project Scope Definition Have Been CompletelyUnderstood and Interred in the Cost Estimating Formats?

    Were Geometrical and Site Condition CompletelyUnderstood?

    Were Codes and Standards Have Been Clarified?

    Were Any Regulation to be Followed During Contract HaveBeen Asked From Client?

    Were Training Requirements for Client Personnel HaveCommunicated?

    Is There Any Client Facilities during Contract Execution?

    5 Why People Get Estimating Wrong?

  • 7/31/2019 Cost-21 day 85

    56/60

    5. Why People Get Estimating Wrong?

    Over Optimistic Nothing Will Go Wrong

    Underestimating Things Like Control the Activity, Coaching, Supervision,Project Meeting

    Lack of Understanding of Project Scope Ignoring Reality Assuming Nothing Will Change

    Just Guessing

    Estimating Isnt a Managed Activity!

    Junior People Involvement Cross Section Communication During Estimation Time

    Double Estimating

    Unclear Scope of Supply Between Procurement and Construction

    Department Underestimating Cost of Temporary Facilities, Consumables, Tools, etc.,

    for Construction, Pre-commissioning, etc.

    Lack of Good Relations With Subcontractors (Vendors)

    Giving Gold Plating Instead of Following Scope

    6 Risk Related Cost Estimating

  • 7/31/2019 Cost-21 day 85

    57/60

    6.Risk Related Cost Estimating

    Type / Complexity of Project

    Procurement Restriction and LawClient / Contractor Resources (personnel, etc.,)

    Project Schedule

    Clients / Contractors Ability to Finance Project

    Scope Changes

    Design Criteria

    7.Summary (1/2)

  • 7/31/2019 Cost-21 day 85

    58/60

    7.Summary (1/2)

    Project Cost Management / Estimating is PrimarilyConcerned with the Cost of the Resource Needed to

    Complete a Defined Activity. Project Cost Management Should Also Consider the Effect

    of Project Decisions on the Cost of Using, Maintaining, andSupporting the Product, Service, or Result of the Project.

    Project Cost Estimating Consider the InformationRequirements of the Project Stakeholders. DifferentStakeholders will Measure Project Costs in Different Ways

    and Different Items. On Some Projects, Especially Ones of Smaller Scope, Cost

    Estimating and Cost Budgeting are so Tightly Linked thatare Reviewed as a Process that can be Performed by a

    Single Person.

    7. Summary (2/2)

  • 7/31/2019 Cost-21 day 85

    59/60

    7. Summary (2/2)

    Some Organizations have Predefined Approachedto Cost Estimating. Where these Exist, the ProjectOperates Within the Boundaries Defined by thePolicy

    Cost of Quality Should be Also be Used to Preparethe Schedule Activity Cost Estimate.

  • 7/31/2019 Cost-21 day 85

    60/60

    Thank You