corrosion_prediction_and_risk_assessment_in_oil_fields_dr_turgoose_mses_2012.pdf

Upload: muhammad-awais

Post on 05-Nov-2015

3 views

Category:

Documents


0 download

TRANSCRIPT

  • Corrosion Predictions and Risk Assessment in

    Oilfield Production Systems Steve Turgoose Intertek CAPCIS, Manchester UK

    [email protected]

  • Outline

    Corrosion Prediction Models

    Accuracy

    Limitations

    Application of Models to Risk Assessments

    Materials Selection

    Inhibition System Design

    Effects of Process Changes

    Predictions of Current Condition

    Emphasis on carbon steel in production environments

  • Predictive Models for CO2 corrosion

    Freely available

    Norsok M506 (Norwegian Standard)

    Cassandra (BPs implementation of DeWaard et al. equations)

    Commercial

    ECE (allows for H2S, based on DeWaard equations)

    In house many

    e.g. Hydrocorr (Shell)

  • Inputs

    Temperature

    Partial pressure CO2 (system pressure + mole % CO2)

    pH (water chemistry -TDS and bicarbonate)

    Flow parameters (Oil, water, gas flow rates, pipe diameter)

  • Outputs

    Predicted general sweet corrosion rate of pipeline steel due to CO2

    Many models (including Norsok and Cassandra) do not include effects of:

    Oil wetting

    Top of Line corrosion

    Organic acids

    Sour corrosion rates

    H2S pitting

    Effect of inhibition

  • Accuracy of models

    How accurate are the predicted uninhibited rates?

    NACE Symposium 2005 Predicting Corrosion in Oil and Gas Environments

    Hedges et al paper 05552

    Cassandra +- 25% of calculated rate

    Smith & DeWaard

    ECE 25 % standard deviation

  • Norsok (Olsen et al NACE 05551)

  • Hydrocorr (Pots, NACE paper 05550)

  • Standard test procedures

    Allow similar variations in corrosion rates under identical contions

    E.g. Shell protocols for one particular test

    Baseline corrosion rate should be between 4 and 7 mm/y

    i.e. +- 25%

  • Oil wetting

    At moderate velocity and low water cut surfaces may be oil wet

    Consequent reduction in corrosion rate

    But can we be sure that water drop out will not occur?

    No concensus among operators on this effect.

    Does not apply to light condensates

  • Top of Line Corrosion

    At high condensation rates (>0.25 g/m2/s) may be high corrosion rates in condensing water at the top of the line.

    At lower condensation rates water saturates with iron carbonate and corrosion rate generally taken to be ~ 10 % of bottom of the line

    corrosion rate

    A possible problem with stratified flow.

  • Organic acids

    Recent work has started to quantify this.

    Corrosion rate increases by an amount proportional to undissociated acid concentration (usually mostly acetic acid).

    Not usually a major effect but may be significant in condensing conditions.

  • Sour corrosion

    H2S reduces general corrosion rate

    ECE applies a multiplying function no rigorous basis but seems to reflect what is seen

    H2S may give pitting

    Sweet rate multiplied by a pitting factor often close to 1 but higher at high chloride or if oxygen present

  • Does the accuracy of the uninhibited rate

    matter?

    What are we going to use the results for?

    Can we use C steel without CI? uninhibited rate important

    Can we use C steel with CI? feasibility of inhibition matters

  • Carbon steel without inhibitor?

    At low corrosion rates (maybe < 0.3 mm/y) corrosion inhibitor may not be required.

    Allowable corrosion rate depends on design life and corrosion allowance.

    Inspection can indicate if later inhibition is required.

  • Risks associated with use of carbon steel

    with corrosion inhibitors

    What can we achieve in practice?

    How do we determine and mitigate risks?

  • Availability Approach (conventional)

    Assume a certain corrosion rate when inhibitor added (e.g. 0.1 mm/y).

    The inhibitor concentration for this is determined by testing.

    Assume uninhibited rate when inhibitor not added at or above the required concentration.

  • What is Availability?

    It is a measure of the time that the chemical is present in the pipe at the required concentration

    We measure inhibitor availability by:

    Concentration

    Pump operation time

    Time

    Below target dosage

    Me

    asu

    red

    Con

    ce

    ntr

    atio

    n

    Target dosage level

    %100

    T

    TTA

  • Contributions to lack of availability

    Two types of contribution

    Downtime of inhibitor dosing system (times with no inhibitor dosed)

    Variations in inhibitor dosing with times below target

  • Common Design Assumptions

    0.1 mm/y inhibited corrosion rate

    95 % availability can be increased is appropriate measures taken

    6 mm corrosion allowance up to 8 or 10 mm possible on large (>18 inch) pipes

    Leads to decision on whether carbon steel is technically possible for design life

    Economic factors must be considered

  • What can be achieved with inhibitors

    when present?

    CAPCIS recently reviewed a large set of test data over many years

    And obtained chemical suppliers inputs

    Under what conditions can a rate of < 0.1 mm/y be achieved ?

    Results published in NACE 2011 (Hedges et al, paper 11062)

  • What can be achieved with inhibitors?

    Very limited data

    T > 120 C

    Shear stress > 320 Pa

    Difficult to achieve < 0.1 mm/y if the uninhibited rate is > 35 mm/y

    Also difficult if TDS > 250,000 mg/l

    To inhibit these systems may not be possible or may require very high concentrations of inhibitor.

  • What availability is achievable

    Has to be operator defined

    is largely a corrosion management issue

    System specific e.g. multiple wells vs one trunkline

    For a single pipeline downtime can be reduced to close to zero with sufficient care / expenditure, but there will be times under target.

    For treatment of multiple wells some downtime must be expected and 95 % availability may be difficult.

  • Factors limiting availability?

    Dosing pump failure / injection point blockage

    duplication of equipment and injection points

    Empty dosing tanks

    ensure sufficient stocks

    Leaks, so that inhibitor not going into line

    measurement of inhibitor residuals in the pipeline

  • Uses of predictions

    Design

    Materials selection can we use C steel

    CI regime requirements concentration and availability required

    This should be reviewed in the light of monitoring and inspection data

    System modifications

    Can assess effect of changes in operation

    May lead to further consideration of CI treatment

    Base on present condition from inspection

    Condition assessment

    Failure investigation (root cause)

  • Assessment of present condition -

    example

    An operator had a subsea leak

    Reasons unknown at present

    Review of all other subsea lines in same field

    Without confidence in present condition all lines will be shut in until they can be inspected.

  • Data available?

    No In Line Inspection carried out after 12 years

    No monitoring of corrosion inhibitor levels in the line

    Corrosion coupons and probes show low corrosion rate, but not relied on since the coupons and probes in the failed line also showed low

    corrosion rate

    Only data available is laboratory test data for corrosion inhibitor and inhibitor volumes pumped (+ production data)

  • One year inhibitor records

    0

    50

    100

    150

    200

    250

    300

    14/11/2007 03/01/2008 22/02/2008 12/04/2008 01/06/2008 21/07/2008 09/09/2008 29/10/2008 18/12/2008 06/02/2009

    Date

    Co

    rro

    sio

    n I

    nh

    ibit

    or

    pp

    m

    Target

    Actual

  • If uninhibited when CI below target -

    conventional definition of availability

    Uninhibited rate = 5 mm/y (test data) model said 4.5 mm/y

    Inhibited rate = 0.1 mm/y at 100 ppm

    In one year

    217 days above target

    75 days below target

    ~ 70 days shut down (ignore corrosion in this period low T & P)

    Loss in the year

    = 217 days at 0.1 mm/y + 75 days at 5 mm/y

    = 1.1 mm loss in one year

  • If uninhibited when CI below target -

    conventional definition of availability

    For all twelve years (from similar calculations)

    Loss = 16.5 mm from 18.6 mm nominal wall thickness (MAWT ~ 4mm)

    PIPELINE ALREADY FAILED

    But it has not

    Look at data again?

  • One month data

    0.00

    20.00

    40.00

    60.00

    80.00

    100.00

    120.00

    140.00

    160.00

    16/06/2008 21/06/2008 26/06/2008 01/07/2008 06/07/2008 11/07/2008 16/07/2008 21/07/2008 26/07/2008

    date

    Inh

    ibit

    or

    Co

    nc

    en

    tra

    tio

    n (

    pp

    m)

    inhibitor

    Target

  • Look at specimen one month data

    30 days

    Average daily concentration 105 ppm

    14 days < 100 ppm

    BUT

    Only 1 day < 90 ppm (due to spike in production)

    What is the effect of small variations around the target?

  • Effect of concentration on corrosion rate

    0

    0.05

    0.1

    0.15

    0.2

    0.25

    50 60 70 80 90 100 110 120 130 140 150

    concentration ppm

    Co

    rro

    sio

    n r

    ate

    mm

    /y

    0.122

    0.082

    50% time at 80 ppm, 50 % at 120 ppm

    Average rate = 0.102 mm/y

    Compared to 0.098 mm/y at 100

    ppm

  • Consider unavailability only due to

    downtime (no dosing)

    Assume that system still inhibited when just below target (other days are better inhibited)

    Days with no dosing = 15 days

    Days with dosing = 277 days

    Total loss in year = 0.28 mm

    Total loss to date in 12 years ~ 4 mm

    OK at present?

  • Look at downtime data

    In one year 15 days with no inhibitor (but with production)

    1 period of 5 days

    1 period of 2 days

    8 individual days

    If inhibitor persistent (maintains protection) for one day with no dosing

    Total loss in one year = 0.15 mm

    Total loss to date ~ 2.5 mm

  • Condition

    May have lost

    16 mm

    4 mm or

    2.5 mm

    Depending on assumptions (somewhere between the latter two is likely to be correct)

    There is significant uncertainty, and consequent high risk, due to absence of

    inspection,

    monitoring of inhibitor residuals and corrosion rate

  • Conclusions

    Corrosion predictions can enable assessment of

    whether carbon steel with corrosion inhibition can be used, and

    requirements for control of corrosion inhibition programs.

    Users of the models should be aware of the limitations and accuracy of the models

    A more realistic (less conservative approach to the definition of inhibition availability is required to address risks associated with

    inhibition.

    These risks will never be reduced to low levels unless appropriate inspection and monitoring is carried out.