CORPORATE ASSET

MANAGEMENT PLAN 2006/07

Page 2: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Corporate Asset Management Plan 2006/07

1.0 Introduction

2.0 Scope of the Plan

3.0 Background to Mendip District Council3.1 The Area3.2 Employment & Economy3.3 The Housing Market3.4 Our Vision and Priorities3.5 Links to Corporate Priorities3.6 Political Decision Making3.7 Management Structure

4.0 The Roles in Asset Management 4.1 Corporate and Strategic Asset Management4.2 Reporting Structure for Asset Management

5.0 Consultation & Links With Others5.1 Consultation5.2 Links to Other Strategies5.3 Partnership Working

6.0 Data Management6.1 Asset Register 6.2 Land & Property Audit6.3 Geographical Information System (GIS) 6.4 Asset Management and E-Government

7.0 Programme / Plan Development And Implementation7.1 Strategic Asset Planning7.2 Establishing Asset Needs7.3 Current Asset Needs7.4 Disposal of Surplus Assets 7.5 Asset Acquisitions7.6 Future changes to the Fixed Asset Register7.7 Asset Condition Survey

8.0 Performance Management8.1 Performance in Relation to Asset Management8.2 Comparison of Performance8.3 Progress against Asset Management Projects for 2004/05 8.4 Progress against the Asset Management Improvement Plan 2004/05

9.0 Asset Management Related Projects / Improvements For 2005 /069.1 Current Programme of Asset Management Projects9.2 Improvement Plan 2005/06

Page 3: CORPORATE ASSET MANAGEMENT PLAN 2006/07

1.0 INTRODUCTION

Since 2003/04 when the Council’s Corporate Asset Management Plan & Capital Strategy achieved a “good” accreditation the Council have continued to produce an annual Corporate Asset Management Plan (CAMP), as this is a good tool to measure how it is managing its assets.

The CAMP is agreed by Corporate Management Team, Scrutiny Board and the Council Cabinet. Some information is provided through Service Planning (See Appendix A) and the project and improvement plans are updated regularly by the Asset Management Working Group, this is monitored by the Corporate Asset Management Team, with regular updates going to the various Committees.

2.0 SCOPE OF THE PLANThe Corporate Asset Management Plan details existing asset management arrangements, project plans, changes during the past year and future plans.

3.0 BACKGROUND TO MENDIP DISTRICT COUNCIL

3.1 The Council Mendip lies in the north eastern part of the county of Somerset, to the south of the cities of Bath and Bristol. The district covers an area of some 285 sq. miles and is mainly rural in character, with four market towns – Frome, Glastonbury, Street and Shepton Mallet and the City of Wells, with an estimated population of the district is 103,865 (Office of National Statistics - 2001).

Mendip District Council is classed as a “smaller” authority because its net revenue budget is less than 35m and its asset value is below 25m.

The Council offices are based at the centre of the area it serves, in Shepton Mallet, the offices accommodate the majority of its 200 (approximately) employees with some of our principal partners and contractors. A distinctive feature of the way that the Council provides its services is our innovative approach to working in partnership and contracting. This approach has added to the business expertise available to our customers, whilst at the same time creating efficiency savings across the organisation.

3.2 Employment The total number of employed people in the Mendip district is approx 39,481 (34%) plus a further 8,800 people (14%) who are self employed (Nomis website 2004), with most people employed in Distribution, Hotels and Restaurants with 11,526 people employed in this industry.

Unemployment standing at approx 788 of which is 1.2% (National Unemployment Rate - June 2006) this is compares with the County which stands at 1.2% and the South West region that stands at 1.6%.

In 2004 there were 4375 VAT Registered Companies in the Mendip district.

1

Page 4: CORPORATE ASSET MANAGEMENT PLAN 2006/07

3.3 Housing MarketThere are currently 46086  houses in the Mendip district (Council Tax Register), this has risen from 42881 since the 2001 census. The average house price is £180,526 (Land Registry Website March 2006) , with prices slightly decreasing over the past two years.

 3.4 Our Vision and Priorities

The Council’s Vision:

“To provide freedom and encouragement for individuals to satisfy the aspirations that they have for themselves and their families, within the security and obligations of a stable and law abiding district”

In addition the following Priorities were also approved, for each Priority Area there are a number of objections:

Better Financial Management Safer Cleaner Streets Greater Prosperity

3.5 Links to Corporate Priorities

The current Priorities have effectively embraced the Priorities of the previous administration and are linked to the authority’s asset management processes in the following ways:

The Priorities were agreed following extensive public consultation and an analysis of needs within the District, are listed below and linkages are identified to corporate asset management:

Better Financial Management Direct link in all areas of asset management and management of Capital

Strategy / Capital Programme To be aware of the implications on assets of applying e-government

initiatives to all service areas, and to recognise how the management of assets can contribute to the delivery of Mendip’s target for electronic service delivery.

To recognise and use available assets to assist the effective delivery of community planning across the district.

To be aware of how the management of Mendip’s assets assists in achieving high standards in local governance.

To consider how Mendip’s assets can be used to deliver Best Value and continuous improvement in all service areas including asset management.

2

Page 5: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Safer Cleaner Streets To consider the general use of available assets within Glastonbury and

Frome to assist delivery of the key Glastonbury SRB Project and the SWRDA Partnerships in Frome and at Morlands..

To recognise and use available assets to assist the effective delivery of community planning across the district.

To consider the general use of available assets within Shepton Mallet to assist regeneration issues in the town.

To consider the general use of available assets to assist the review of the Council’s Transport Policy with partners.

To consider how Mendip’s assets can be used to assist delivery of the Community Safety Strategy Action Plan

To consider the use of available assets to assist delivery of the Health Improvement Programme.

Greater Prosperity To recognise and use available assets to assist the effective delivery of

community planning across the district. To consider the use of local goods and services for the maintenance of

assets. To consider the general use of available assets within Glastonbury and

Frome to assist delivery of the key Glastonbury SRB Project and the SWRDA Partnerships in Frome and at Morlands..

To consider the general use of available assets within Shepton Mallet to assist regeneration issues in the town.

To consider the general use of available assets to assist the promotion of local goods and services.

To consider how Mendip’s assets can be used to assist delivery of the Housing Strategy Action Plan

To consider the use of available assets to assist delivery of the Health Improvement Programme.

These Priorities have been translated into SMART (Specific, Measurable, Achievable, Realistic and Timely) outcomes through consultation between the Cabinet and Officers. These are used to inform the Service Planning process. In turn, these outcomes, and indirectly the Priorities, will be monitored by the Corporate Management Team, the Cabinet and the Scrutiny Board.

3.6 Political Decision Making

For approx. 5 years the Council have operated a Cabinet / Scrutiny model of political management. Cabinet members are assigned a Portfolio, and work individually with their appropriate Business Unit Manager, with each Unit being represented by a Portfolio Holder and in some cases deputy Portfolio Holders who are responsible for specific areas. The Leader of the Council does not hold a specific Portfolio, but instead has a “roving” brief. Councillor Paul Treby is the Senior Portfolio Holder for Corporate Finance & Resources Unit, with 2 Portfolio Holders, Councillor Elizabeth John is responsible for Customer Services, Advice & Information & Corporate Support, Strategy & Research. Whilst Councillor John Parham who is responsible for Asset Management on behalf of the Council, where the accountability for strategic asset management lies.

3

Page 6: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Whilst the structure of the scrutiny side has recently been reviewed, the current political structure has now been approved, having been designed to maximise political leadership and citizen empowerment.

The Council has 46 elected Members in 35 Electoral Wards, there have been two bye elections during the Spring of 2006 and the political make-up has changed since last years plan with:

27 Conservatives 15 Liberal Democrats 4 Independents

3.7 Management Structure

As a smaller authority, Mendip has limited capacity to embrace new work without fundamental change. Internally, the Council must continue to ensure that there are sufficient resources available to support service delivery, whilst continuing to meet the expectations and demands of the public and Central Government.

For approx. 3 years the Council have operated a Corporate Management Team this comprises of:

Chief Executive Business Unit Managers (3 No)

Supplemented by:

Corporate Financial Adviser / S151 Officer Personnel Adviser

This structure is designed to focus more clearly on the Council’s new priorities, and seeks to achieve the Council’s identified priorities through effective, efficient and economic cross service working.

The Mission Statement of the Corporate Management Team is as follows:

"To effectively lead and manage Mendip District Council, and in so doing to ensure that resources available to the Council are utilised in the most effective and efficient manner in order to secure the achievement of the Corporate Vision and identified Priorities."

The role of the Corporate Management Team in respect of asset management is as follows:

To ensure that the Asset Management Plan is informed by, and supports, the Service Plans and Strategic Priorities

To ensure a corporate and consistent approach to asset management across all services

Receives reports on performance relating to asset management Considers recommendations for asset strategies Considers Appraisal Reports for capital funding

4

Page 7: CORPORATE ASSET MANAGEMENT PLAN 2006/07

4.0 ROLES IN ASSET MANAGEMENT

4.1 Corporate and Strategic Asset Management

Within the current structure, assets are not managed as a single function. Whilst the strategic and corporate management of the Council’s assets is the responsibility of the Corporate Finance & Resources Business Unit, the day to day operational management of specific assets (e.g. Car Parks, Public Conveniences, etc) is carried out across a range of service areas.

In terms of the operational management of the range of corporate assets, these are as follows:

Business Unit Manager – Corporate Finance & Resources (Stuart Brown)The Council Offices, Sewage Treatment Plants, hard surface areas and miscellaneous land assets remaining in Council ownership following LSVT

Business Unit Manager - Community & Regeneration (Malcolm Williams)Leisure Facilities, Swimming Pools, Car Parks, Part of Morlands site, Glastonbury. (A key strategic development site)

Business Unit Manager – Planning & Environment (Charles Uzzell)Play Areas, Open Spaces, Trees, Cemeteries, Closed Churchyards, Public Conveniences, Bus Shelters, Street Furniture

Corporate Property OfficerIn October 2005 the role of the Corporate Property Officer was transferred to from the Corporate Finance & Resources Business Manager to the Strategic Asset Manager, this job was then renamed to Corporate Property Officer. The Corporate Finance & Resources Business Unit Manager now acts as the strategic asset management champion on CMT, and the Asset Management Portfolio Holder to act as the champion on Cabinet.

The role of Corporate Property Officer includes:

identifying and auditing all Council land and property assets periodic reviews of the property portfolio developing and implementing a range of policies and strategies for

strategic and operational asset management, including disposal and acquisitions.

promoting good asset management practices across the Council leading the Corporate Asset Management Team and Asset Management

Working Group. Ensuring the Asset Management Plan is maintained and updated

Strategic Asset Management TeamThe Corporate Asset Management Group meet on a quarterly basis, it monitors performance against the CAMP project plans and improvement plan

5

Page 8: CORPORATE ASSET MANAGEMENT PLAN 2006/07

and review the work of the Working Group. The membership of the team has been changed slightly and now comprises of the following officers:

Business Unit Manager (Corporate Finance & Resources) - Stuart Brown Service Manager (Community Services) – Stuart Cave Asset Maintenance Officer - Stuart Finney Corporate Property Officer – Andrea Kent Corporate Financial Adviser - Peter McKenzie Financial Services Manager – Tessa Stobbs Service Manager (Street & Landscape Services) - Rob Thurston

The aim of the Corporate Asset Management Team continues to be as follows:

“To monitor the management of the corporate asset portfolio ensuring this is done in an effective, efficient and economic manner that meets both the needs of the local community and the Council where reasonably practicable.”

Underpinning this Aim, the Team is working towards the achievement of the following objectives:

1. To oversee the comprehensive asset portfolio for Mendip District Council2. To monitor the development and implementation of a range of strategies

and policies to support the effective management of corporate assets, including those to address:a) The purchase of assets as investment opportunitiesb) The realisation of asset potential through the sale or lease of assets as

appropriate3. To monitor the development and implementation of an annual Capital

Strategy, taking into account the Medium Term Financial Plan, the Housing Strategy and other relevant Corporate Strategies.

4. To monitor the development and implementation of corporate planned maintenance programmes.

5. To monitor the Project and Improvement Plans identified in CAMP.6. To report to the Corporate Management Team, the Cabinet and Scrutiny

Board on issues relating to Corporate Asset Management, including performance monitoring.

8. If / when the need arises to set tasks for the working group to undertake

Asset Management Working GroupThe Asset Management Working Group meets on a quarterly basis. This group have improved communications between the various officers involved in asset related functions, identified areas of over lap and encouraged more corporate thinking.

Corporate Property Officer – Andrea Kent Team Leader Street Scene Services - Cathy Day Asset Maintenance Officer – Stuart Finney Car Parks Manager – Nicola Keyworth Wright Leisure Officer – Ian Mundy

The aim of the Asset Management Working Group continues to be as follows:

6

Page 9: CORPORATE ASSET MANAGEMENT PLAN 2006/07

“To work together to manage the corporate asset portfolio in an effective, efficient and economic manner that meets both the needs of the local community and the Council where reasonably practicable.”

The objectives of the group are as follows:

1. To work together to oversee the comprehensive maintenance programme for all corporate assets.

2. To develop, implement and monitor operational policies and strategies for all Council assets

3. To undertake tasks set by the Strategic Asset Management Team 4. To work together to solve problems, discuss ideas and generally improve

communication between all officers dealing with the day to day, strategic and maintenance of Council assets

Portfolio Holder At a political level, asset management is the responsibility of the Cabinet and Portfolio Holder Councillor John Parham, decisions are made within the overall policy framework set by the Council. There is however an exception to this whereby the Community Partnerships are able to make ‘executive’ decisions with regard to the sale of assets within their area, where these do not warrant full Cabinet consideration. Under both of these processes, the decision can be “called in” by the Scrutiny Board.

4.2 Reporting Structure for Asset Management

In terms of the reporting relationships, these are as follows:

a) The Corporate Property Officer will provide update reports to the following:

Corporate Management Team on a quarterly basis. Cabinet on a ½ yearly basis Community Partnerships – year end.

During 2005 the Chairman of Scrutiny advised that they no longer wished to receive update reports on Asset Management.

b) Day to day operational issues relating to asset management are the responsibility of the appropriate Service Manager / Portfolio Holder.

c) The Corporate Asset Management Team will report to the Cabinet and Scrutiny Board as appropriate, on issues relating to the monitoring of strategies / policies etc.

d) The Asset Management Working Group will report when necessary to the Corporate Asset Management Team / Cabinet and Scrutiny Board.

e) Strategic Asset Management is an identified function of the Corporate Finance & Resources Business Unit, and as such is incorporated into the annual Service Plan.

7

Page 10: CORPORATE ASSET MANAGEMENT PLAN 2006/07

f) Similarly, specific aspects of operational asset management (e.g. Car Parks, Public Conveniences, and Parks etc) are incorporated into the appropriate Service Plans (e.g. Planning & Environment etc).

5. CONSULTATION & LINKS WITH OTHERS

5.1 Consultation

Mendip continues with a positive approach to consultation across services areas. The Consultation Strategy is currently being reviewed and it’s hoped that this will be adopted by the end of the year.

Following a Communications Audit a draft Communications Strategy has been produced and is currently going through the adoption process.

In last years plan it was identified that the Leisure Contractor in conjunction with the Somerset Activities Sports Partnership planned to undertake a recreational facilities audit which included questions relating to the quality of each facility. This has not yet been completed and may now merge into a Leisure Facilities Review.

During 2005/06 the Street & Landscape Services Section undertook major survey, this covered a number of areas including street cleansing, street furniture grass areas, public toilets and play equipment etc. 2000 questionnaires were sent out to the Mendip residents and 454 to Town and Parish Councillors of these 997 residents responded and 200 Town and Parish Councillors were returned.

Also in January 2006 the Bereavement Officer sent out a satisfaction survey to 131 users of the Cemeteries.  Although not dealing with assets, it did ask people if they were satisfied with the burial service provided (results attached). 69 questionnaires were received, of these 52% of users stated they were satisfied with the service provided.

5.2 Links to Other Strategies

Previous CAMP’s have included a number of important corporate strategies which it recognises links to strategic asset management including Procurement Strategy, Homelessness Strategy etc.

In the 2005/06 CAMP the following emerging strategies were identified for that year, please see below the current position for each:

Play StrategyThe Play Strategy was in its development stages, however, this was put on hold until the lead officer post could be filled. The Council have recently employed a Consultant to assist in the development of the strategy.

Mendip Open Space Strategy

8

Page 11: CORPORATE ASSET MANAGEMENT PLAN 2006/07

The development of the Open Space Strategy is currently on hold, until the lead officer post can be filled, recently the Council have employed a Consultants to assist in the development of the strategy.

A number of other asset related Strategies have been adopted by the Council during 2005./06 including:

Closed Churchyard Walls StrategyA Churchyard Wall Strategy has been developed and adopted by the Street & Landscape Services Section.

Markets StrategyThe Strategy has been developed and adopted by the Street & Landscape Services Section to assist the Council in the future development of stall markets

A number of new asset related Strategies are expected to be developed and adopted during 2006/07 and beyond including:

Cemeteries Strategy A management plan is currently being finalised that looks at a number of issues including provision and capacity within all three cemeteries, this will result in the development and adoption of a Cemeteries Strategy which will look to resolve the issues.

 Street Light StrategyA street lamp survey commenced in April 2006 which will identify all the Council’s lamps. Once this is complete a Strategy will be developed and adopted on how the Council manages and maintains their Street Lights. (2007/08)

Car Parks Strategy A Car Parks Strategy will be developed following on from the Car Park Working Group but no timescale has been agreed.

Major Leisure Facilities Strategy The Council has recently commissioned a Leisure Facilities Review, it is expected this will lead to the development and adoption of a Major Leisure Facilities Strategy (2007/08)

5.3 Partnership Working

Mendip continues to be committed to working with others in order to deliver improved services to local residents through contracts with the private sector and in partnership with other public bodies, and acknowledges the benefits that this has to securing the achievement of its Priorities.

The Council have a number of asset related contracts and partnerships, including the following:

Interpublic Urban Systems UK Ltd., The Council work with Interpublic to provide a beacon public convenience in each of the 5 main towns.

9

Page 12: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Connaught Environmental LtdThis contract delivers the street cleansing across the district and includes street sweeping, litter bin emptying etc. Connaught also work in partnership with the Council to proactively educate the general public though environmental awareness campaigns.

Western Community Leisure The Council work in partnership with the contractor to provide Mendip major leisure facilities

Capita The Council have appointed Capita to work in partnership for a period of 12 years to deliver council services including finance, IT and printing & stationery, this utilises shared office accommodation.  The contract also delivers 65 regeneration jobs which will be a service centre accommodated on the Mendip campus. 

REALMThe Council work in partnership with REALM to provide some of the car parking in Street.

Somerset County Council The Council works with the County Council to provide dual use leisure provision on school sites. The Council is currently assisting the County Council to secure new office accommodation is Shepton Mallet.

Other District Councils The Council is currently working in partnership with South Somerset District Council to procure a new valuation service.

Town Councils / Parish CouncilsThe Council continues to work with Town and Parish Councils, during 2005/06 the transfer of a number of allotment sites and other public open spaces have been completed. The Council have also worked with several of the Town Councils to reopen a number of closed public conveniences.

Somerset Waste Partnership The Council work with the County Council and the 4 other District Borough Councils across Somerset to coordinate  recycling and refuse collections, treatment and disposal.

6.0 DATA MANAGEMENT

6.1 Asset Register

Mendip’s current Asset Portfolio (including categories and values) is held on an Asset Register Database, this includes details of depreciation, leases, remaining life, net book value, etc. A rolling programme of re-valuation has been implemented to ensure that all assets a re re-valued once every five years.

10

Page 13: CORPORATE ASSET MANAGEMENT PLAN 2006/07

The Council undertook a reconciliation between the information held on both the Asset Register and the Geographical Information System in 2004, since then this practice has continued on an annual basis as the Asset Register is integrated with Mendip’s financial information systems through reconciliation with the Balance Sheet. Also a simple system has been put in place to ensure that the Finance Section are made aware of any changes to the Asset Register (i.e. disposals).

The Council currently has 97 assets on its Fixed Asset Register (See Appendix 1 – Summary of Assets)

The Council also own in the region of 2100 other assets including land, footpaths other small buildings.

During 2005/06 the Council spent approx £270,000 on general maintenance of its assets.

6.2 Land & Property Audit

In March 2006 the Corporate Property Officer completed a Land & Property Audit for all the Councils assets across the district. This totals approximately 2000 individual “pockets” of land.

Each asset has been visited, photographed and information has been collected on the land, this includes information on the surface type, street furniture, vehicular accesses, walls, fences, gates and a simple condition study.

The Land & Property Audit has assisted in the collection of information including the location of street furniture, boundary walls and fences, utilities e.g. manhole covers, telegraph poles etc., and there condition, it also records the location of trees on Council land.

6.3 Geographical Information System (GIS)

The Council continues to plot all its land and property assets onto a GIS, each asset is assigned a unique internal reference number. The details collected as part of the Land & Property Audit i.e. surface type, street furniture, vehicular accesses, street furniture etc. information on boundaries and a simple condition study are all recorded on a Access Database which is linked to the GIS system. (See Appendix 2 – For an example of how this information is identified, using GIS).

The GIS information has been shared with Street & Landscape Services and other service areas through Planweb, and the data has been used to load the Staysafe system.

The GIS system is also used to record leases, licences, Land Disposal Applications and land sold and assets sold by the District Council.

Mendip is constantly improving the content of its NLPG (National Land and Property Gazetteer) extract which currently holds property detail only – land parcels will also be required for its effective use in respect of the management of the asset portfolio. The appropriate UPRN from the NLPG will be assigned

11

Page 14: CORPORATE ASSET MANAGEMENT PLAN 2006/07

to all property and land assets once Mendip has completed its migration to OS Mastermap has been completed.

The Corporate Property Officer continues to strive to improve the types and levels of data held by the Council. During 2005 the Council planned to link the GIS system to Staysafe but due to technical problems this did not happen. However, it is envisaged this will take place during 2006/07.

The Corporate Property Officer is a member of the corporate “GIS User’s Group” which was established in 1997 has continued to develop since that time. The purpose of this Group is to review GIS development needs and assess the need for training, either corporately, within specific Service areas or individually.

6.4 Asset Management and E-Government

Mendip continues to recognise the positive impact that the E-Government agenda can have on the improvement of a number of services.

In respect of the asset management service, work has been completed on updating and ensuring of the Asset Register held on the GIS system. This information will be provided online for users to check the ownership of Council land and will be used by Customer Services representatives to deal with complaints from the general public and for members of the public to submit an online complaint or notification regarding some aspect of the service, the Council is now awaiting the for the software to provide this information, this is expected to be delivered, installed and running by the end of March 2007.

7.0 PROGRAMME / PLAN DEVELOPMENT AND IMPLEMENTATION

7.1 Strategic Asset Planning

In common with Mendip’s innovative approach to service delivery, through the positive engagement of a wide range of contractors, partnerships etc, and our asset portfolio has been managed by reference to the same principles.

Mendip is keen to adopt an increasingly strategic view of the management of its asset portfolio, and is confident that it can build upon the successes that it has already had. Its position on the Mendip Strategic Partnership will assist this strategic overview and allow the needs of other agencies to be considered within the overall framework.

During 2005/06 the Council have become members of the National Asset Management Planning Network, keeps the Council up to date with all asset management related issues / polices / advice etc. from Central Government and other bodies.

7.2 Establishing Asset Needs

Historically Mendip has had a policy of disposing of its assets in order to minimise the costs associated with ownership and to reduce potential liabilities.

12

Page 15: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Whilst Mendip therefore holds only a relatively small Asset Portfolio, there are nevertheless pressures applied from service areas and from the corporate perspective that place demands and requirements on the current small Portfolio.

The pressures are identified at two principal levels:

Corporate: via either Corporate Management team or the Corporate Asset Management Team

Service: via the annual Service Planning process

In turn, the Capital Appraisal System provides the process that links individual projects with corporate / service Priorities and outcomes. This enables the Cabinet to be advised accordingly on the relative priority of the schemes, thus informing the process of programme approval. During 2006/07 the current Capital Appraisal System will be reviewed, it is expected that a new system will be adopted which links more directly with the Council’s Objectives.

Historically, Mendip has not carried out planned maintenance of its assets. However, over the past 2 years the Council have started to realise the benefit of planning maintenance programmes and have started development programmes for a number of assets including the Council’s office buildings, closed churchyard walls and footpaths and other hard surfaces.

7.3 Current Asset Needs

During 2005/06, the principle pressures on the asset portfolio are as follows:

Office AccommodationThe Council acknowledges that it has accommodation needs. During 2005/06 the Council appointed Capita Symonds to undertake an Accommodation Review which will look at the Council and its partners need for office accommodation, consider the options and make recommendations,

MorlandsPart of Mendip’s contribution to the Strategic Priority of supporting the SWRDA Partnerships at Morlands, Glastonbury by transferring the land owned by the Council in order to facilitate the development, a small are of land was transferred during 2005/06. The remainder is under option until 6th March 2010 to SWRDA for the possible development of a combined heating and power plant (CHP) for the Morlands site. However, it is anticipated that the CHP will not proceed and the SWRDA will be requesting a release from the option. .

Frome CemeteryThere will be a need to extend the Frome Cemetery into the land adjacent within the next three years as the current cemetery will be full in about four years time.

Shepton Mallet CemeteryThere will be a need to either extend or start to re-use burial sites within Shepton Mallet Cemetery in a few years time.

13

Page 16: CORPORATE ASSET MANAGEMENT PLAN 2006/07

7.4 Disposal of Surplus Assets

a) As identified previously in this Plan, Mendip retained a significant number of “miscellaneous” land assets, most of little if any consequential value, following the transfer of the housing stock.

The Land & Property Audit has indicated that the majority of the land is of little or no use to the Council and are in fact significant liabilities. Since May 2004 the Council have offer approx 135 surplus areas of land in total, from these the Council received 63 “Expressions of Interest”, of which 29 have been completed, the remaining applications are at various stages within the process.

b) The Land & Property Audit has identified opportunities for development which are actively being pursued. During 2004/05 the Council agreed to the disposal of 8 sites in Frome for affordable housing, however, applications on 5 of these sites were refused by the Planning Board in March 2006. During 2005/06 the Council agreed to the disposal of a further 5 sites in Frome and Shepton Mallet.

c) The Audit also identified a number of smaller sites, which may be developed as single building plots or small development plots. The Corporate Property Officer worked with a Development Control Team Leader on two sites, one was written up for refusal by the Planning Officer and withdrawn, the other received outline planning approval and was recently sold on the open market for £170,000.

During 2006/07 a further two to three sites will be considered and their viability tested before a planning application is submitted.

d) The Council have clear procedures for the disposing of assets. There are Application Forms to be completed by all applicants. A stakeholder consultation takes place for all applications before a decision is made. The Corporate Property Officer has the delegated authority to ”agree in principle” to the disposal of all Council owned assets. However, there is a strict ratification process in place once the asset has been valued:

Less than £5000: Corporate Property Officer£5001 - £20 000: Corporate Finance & Resources BU Manager£20 001 - £30 000: Portfolio Holder (Corporate Finance & Resources)Over £30 001: Cabinet / Community Partnerships

7.5 Asset Acquisitions

During 2005/06 the Asset Review Group agreed the following methodology to assist them in considering requests:

Each application is considered on a case by case basis, each area of land within the application site will be viewed individually and given careful consideration by the group.

Is there an existing S106 Agreement which ties the Council into an adoption ?

Does the land meet the minimum standard set out by the Council ?

14

Page 17: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Does the land have any problems etc. which could result in a future liability to the Council i.e. location / ponds / drains / difficult and expensive to maintain areas etc.

Are the Council being asked to adopt things which they have no expertise in managing or maintaining ?

Does the land provide a quality open space / play area and how much value does land provide the local people ?

Is adoption by the Council the only way to preserve the open space or is there an alternative ?

Does the Council wish to enter into a 75 year+ restrictive covenant on this area of land or negotiate a lesser period ?

Does the group wish to add any conditions to the adoption i.e. additional signs, moving of a footpath etc. ?

All senior planners have been issued with a Briefing Note explaining what is expected of them and how the process works.

Over the past year the group have considered a number of requests from developers to adopt land and property though the Section 106 process, several of these have been refused. However, the Council have adopted approx 30 new areas of land during the past financial year due to a number of Section 106s being completed and signed.

7.6 Future Changes to the Fixed Asset Register

The Council have a number of potential changes in it asset holdings during the next few years:

Garsdale / Saxonvale, Frome 

A Planning Brief and Design Codes was adopted by MDC in 2005 to guide the mixed use redevelopment (retail, employment and housing) of 12 hectares of brownfield land extending eastwards from Frome town centre.   The proposed redevelopment area includes 3 Council owned assets – The Slaughterhouse, Merchants Barton Car Park and Public Conveniences.  The Council intends that these landholdings will be developed in accordance with the aims and objectives of the brief.  A comprehensive approach to development is a guiding principle.  It is proposed that new car parking provision provided as part of the comprehensive scheme would be managed by means of a public-private partnership.

 The timescale for redevelopment will be largely private sector / market led as the majority of the area is in mixed private ownerships.  Temporary use of the abattoir site may need to be considered if the abattoir business ceases to operate in the shorter term.

 

15

Page 18: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Prince Road, Wells 

The Council have been contacted by a developer who is interested in the redevelop of the Prince Road area in Wells (approx 3 ha) this site is in mixed ownerships to the south / west of Wells City Centre. The proposed redevelopment area includes 4 Council owned assets - Princes Road Car Park and Public Conveniences, Wells Bus Station and Wells Film Centre. 

The proposed redevelopment is for a mixed use town centre extension re-incorporating many of the existing uses.  It is envisaged that the Council will retain its management of a car parking facility.  The proposals are an early stage of development and a Planning Brief with public consultation is required.

 Commercial Road Car Park, Shepton Mallet

The Council have received several interests looking to develop part of the Council's car park or include the land within part of a wider retail scheme.

A developer has submitted a planning application incorporating 2 Council owned assets – Commercial Road Car Park & Public Conveniences, however, the car park would be retained,  to support a retail development .   Negotiations for the inclusion of these assets into the wider scheme are at an early stage. 

7.7 Asset Condition Survey

During 2005/06 all assets within the Frome area were re-valued (see Appendix 3 - Schedule of Values) and assessed for maintenance requirements (see Appendix 4 – Works Required Table) as part of the 5 year rolling programme. The latter information has assisted the medium term budget planning process, and the development of a rolling planned maintenance programme.

8.0 PERFORMANCE MANAGEMENT

8.1 Performance in Relation to Asset Management

National Performance Indicators

Mendip continues to evaluate its performance against the National Property Performance Indicators (pPI’s). Its performance, in relation to these is as follows, and this will provide a benchmark for future Plans:

16

Page 19: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Indicator Number

DescriptionPerformance

2005/06

1A

Percentage gross internal floor space in Condition categories A to D

A – GoodB - SatisfactoryC - PoorD – Bad

59.57%37.79%0.05%2.59%

1BBacklog of maintenance by cost expressed (i) as total value and (ii) as a percentage of priority levels 1 to 4

i) £ 120,790

1234

Urgent worksEssential worksDesirable worksLong term works

ii) 96% 0% 4% 0%

2A, B and C

Overall average rate of return (IRR) for each of the following portfolios:a) Industrial, b) retail and c) agricultural investment property

NIL

(Note: Mendip has no assets

falling within the definition of this

Indicator.

The performance information provided below is for the Councils main office site only:

Indicator Number

DescriptionPerformance

2004/05Performance

2005/06

3

Total annual management costs per square metre (GIA) for the property portfolio

£10.75 £9.81

4A, B, C and D

A. Repair and maintenance costs per square metre GIA

£38.56 £38.98

B. Energy costs per square metre GIA (gas, electricity, oil, solid fuel)

£9.53 £18.65

C. Water Costs per square metre GIA

£1.09£1.81

17

Page 20: CORPORATE ASSET MANAGEMENT PLAN 2006/07

D. CO2 emissions in tonnes of carbon dioxide per square metre

64.26 56.19

5A and B

A. % of projects where outturn falls within +/- 5% of the estimated outturn, expressed as a percentage of the total number of projects completed in the financial year.

NIL

(Mendip has had no

projects during 2004/05 falling

within the definition of

this Indicator)

NIL

(Mendip has had no

projects during 2005/06 falling

within the definition of

this Indicator)

B. % of projects falling within +5% of the estimated timescale, expressed as a percentage of the total number of projects completed in the financial year.

NIL

(Mendip has had no

projects during 2004/05 falling

within the definition of

this Indicator).

NIL

(Mendip has had no

projects during 2005/06 falling

within the definition of

this Indicator)

During 2005/06 energy prices increased by 95.8%, this accounts for the massive rise in figure 4(B) – Energy Cost per square meter GIA, yet an improvement in CO2 emission..

Over the past 3 years the Council have seen a rise in its energy costs this has led to the Council and other member of the Mendip Strategic Partnership setting up a working group called Mendip Partnership for Energy. This project has recently won government funding for a programme of energy auditing for all its buildings on the Cannard’s Grave Road site, and the energy used in business travel by staff based in those buildings. The Primary Care Trust, Somerset County Council and Avon and Somerset Constabulary are also participating in the project, which will suggest ways in which each organization can use energy more efficiently, saving both carbon and costs. The audit will also suggest ways in which partners can save energy by working together to deliver services and will look at how possible measures fit with the other activities and programmes of the organisations. The audit of buildings at Cannard’s Grave Road will be completed by March 2008.

National IndicatorPerformance

2003/04Performance

2004/05Performance

2005/06

BV 156The % of authority buildingsopen to the public in whichall public areas are suitablefor and accessible todisabled people.

6.3% 8.33%8.33%

18

Page 21: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Local Performance Indicators

The Council have developed two asset related performance indicators:

Asset Disposals

Local IndicatorPerformance

2004/05Performance

2005/06The % of Category A Applications which are “agreed in principle” within 6 weeks from receipt (Target 75%)

95.5% 97%

The total number of expressions of interest received in the financial year

NO DATA AVAILABLE

86

The total number of applications received in the financial year

62 79

The total number of completed assets disposal transactions in the financial year

13 40

The total area in sq m of completed assets disposal transactions in the financial year

2438 m2 31731.39 m2

The total amount of income to the Council for asset disposals in the financial year (This includes completions & deposits)

£ 65,460.00 £364,758.00

Play Areas

Local Indicator Performance 2004/05

Performance 2005/06

The number of playgrounds and play areas provided by the Council per 1000 children under 12

3.6 4.2

8.2 Comparison of Performance

Despite making a number of enquiries, with agencies such as the Government Office South West and the external Auditors, Mendip have still not been able to identify a District Council in a similar position to make any comparative work worthwhile in this respect. During 2005/06 the Corporate Property Officer set up and led a County Asset Management Group this is attended by officers from all the District/Borough Councils and the County Council, the group have agreed there would be benefits in benchmarking against each other but to date no criteria has been set. It has recently been agreed that the County will take over the leadership of the group and it will be expanded to include other public bodies including the police and PCT.

19

Page 22: CORPORATE ASSET MANAGEMENT PLAN 2006/07

The Council have compared its approach to asset management with those in the County group and found that their policies on asset disposal are advanced on the other districts in Somerset.

All energy invoices continue to be processed centrally, within the Corporate Finance & Resources Business Unit, thereby enabling consumption and cost data to be monitored and recorded on Excel spreadsheet.

8.3 Progress against Asset Management Projects for 2005/06

The Corporate Asset Management Plan 2005/06 identified a number of asset management projects for this period, Figure 1 shows the progress made against the identified projects.

8.4 Progress against the Asset Management Improvement Plan 2005/06

Figure 2 indicates the progress made against the Asset Management Improvement Plan for 2004/05.

9.0 ASSET MANAGEMENT RELATED PROJECTS FOR 2006 /07

9.1 Current Programme of Asset Management ProjectsFigure 3 provides a comprehensive list of current / proposed asset management projects for 2006/07.

20

Page 23: CORPORATE ASSET MANAGEMENT PLAN 2006/07

21

Page 24: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Figure 1 PROJECT PLAN UPDATE FOR YR. 2005/06

Action Lead OfficerTarget Date

Progress

Resurface Great Ostry Service Area. Car Parks Manager

September 2005

COMPLETED

Proceed with the disposal of Mendip’s land holding in respect of the Morlands development, working with SWRDA.

Business Unit Manager -

Community & Regeneration

October 2005

Part disposal of the site was completed early in March.

To obtain Planning Permission for new building public convenience at the Cattle Market Car Park, Frome

Asset Maintenance

Officer

November 2005

The Council have amended the plans to take into account the County concerns

Upgrade Cheese and Grain car park area  Car Parks Manager

December 2005

COMPLETED

To complete the transfer of all allotments sites. Strategic Asset Manager

December 2005

A Radon Gas emissions reports has been sent to Frome Town Council – awaiting their response

Ensure compliance with legislation for Disabled access to public buildings:

To produce a costed programme of works for Leisure Centres

Strategic Asset Manager /

Leisure Officer

December 2005

The pool hoists have been fitted at all Leisure facilities.

22

Page 25: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Action Lead OfficerTarget Date

Progress

To continue pursuing the disposal of the Gypsy Lane playing fields.

Leisure Officer / Strategic Asset

Manager

March 2006

Disposal agreed at Cabinet on the 11/6. Awaiting completion.

Replace the Bailey Bridge, Frome Car Parks Manager

March 2006

The Bailey Bridge will be closed at the beginning of July 2006 for Health & Safety reasons. The Council is currently looking at replacement options.

Replace all Pay and Display machines in Street Car Parks Manager

March 2006

A Capital Bid for the replacement of car park ticket machines was approved, therefore the replacement of Street machines will be done at this time. This is now going through the procurement process.

To carry out a planned maintenance survey to develop a costed 10 year maintenance plan relating to MDC’s responsibilities within the Leisure Contract.

Leisure Officer March 2006

This is on hold due to contract arrangement changes

To develop an Accommodation Strategy for the Council to incorporate the needs of Capita Local Government Services.

Corporate Finance & Resources Business Manager

March 2006

Capita Symonds to present to CMT.

To assist in the development of an Asset Management Strategy for the Council’s major assets

Strategic Asset Manager

March 2006

Nothing to report

23

Page 26: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Action Lead OfficerTarget Date

Progress

To investigate the disposal of Park Cottage, Wells in order to facilitate the maintenance of the Bishops Barn & Recreation Ground, Wells

Strategic Asset Manager

April 2007 An update letter has been received from Wells City Council which indicates they are still considering the issues with a view to transferring the properties at the end of March 2007..

Progress the Cabinet's decision regarding the Council's future involvement with The Amulet, with a view to negotiating a surrender of the current full repairing lease.

Corporate Finance & Resources Business Manager

April 2006 COMPLETED – January 2006

Bishops Barn, Wells - To carry out maintenance identified in Historic Building Survey

Leisure Officer April 2007 Awaiting Wells City Council’s decision

Shepton Mallet Leisure Project:The refurbishment (in association with Shepton Mallet Town Council) of Shepton Mallet open air pool.

Leisure Officer September 2006

Progress on course and due for completion by July 2006.

Casual Play / Public Open SpaceTo develop a criteria for casual play and public open space.

Strategic GCDO April 2006The Council have appointed Bakers Associations to assist in the preparation of the Strategies

To assess the condition of the 2 small Sewage Treatment Plants remaining in Mendip’s ownership following LSVT and, if necessary, determine a programme of works.

Business Unit Manager - Corporate Finance & Resources

December 2006

Recommendations have been received from the Consultants, looking at secure capital funding.

24

Page 27: CORPORATE ASSET MANAGEMENT PLAN 2006/07

25

Action Lead OfficerTarget Date

Progress

Tor Leisure, Glastonbury - To produce maintenance programme and delivery within the terms of the lease.

Leisure Officer April 2008 Nothing to report

To continue the Asset Disposal programme Strategic Asset Manager

March 2007

Approx 120 sites have been identified for offer under the surplus land disposals for 2006/07.

To complete the Land & Property Audit and consider options for addressing.

Strategic Asset Manager

April 2006 COMPLETED – February 2006 .

To carry out a condition “fit for purpose” and risk assessments / surveys of major corporate assets

Strategic Asset Manager

March 2007

Nothing to Report

Page 28: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Figure 2 Corporate Asset Management Improvement Plan Update 2005/06

Ref No.

Action Lead Officer OutcomeCompletion

Date

AMP 1

To identify, record and describe a complete portfolio (on both the Asset Register and Geographical Information System) for all assets in Wells and its surrounding area.

Strategic Asset Manager

To complete the Land & Property Audit, enter all data onto the GIS System and make available to all sections of the Council.

COMPLETED

AMP 2

a) To carry out a condition, “fit for purpose” and risk assessments / surveys of major corporate assets

b) To carry out a condition, “fit for purpose” and risk assessments / surveys of all corporate assets

Strategic Asset Manager

A record of the condition of the major corporate assets

A record of the condition of all corporate assets

31/07/06

31/07/06

AMP 3

a) To implement a programme of works to bring the condition of all major assets up to an “acceptable” standard

b) To implement a programme of works to bring the condition of all assets up to an “acceptable” standard

Strategic Asset Manager

All major assets maintained to an “acceptable” identified standard

All assets maintained to an “acceptable” identified standard

Subject to outcome of AMP 2a and 2b, and prioritisation of

works

AMP 4To establish and resource a fully integrated corporate maintenance programme for all assets

Strategic Asset Manager

Corporate assets maintained to an identified standard

Subject to AMP 3 and Risk

Assessment

AMP 5

To develop suitable supporting Strategies and Policies for Corporate Asset Management Strategy to secure the effective, efficient and economic management of the asset portfolio

Strategic Asset Manager

An adopted Corporate Asset Management Strategy and associated supporting policies

This continues to be on going

AMP 6

To develop a programme of Consultation to determine the views of stakeholders in respect of matters relating to Corporate Asset Management

Strategic Asset Manager

An agreed mechanism for ascertaining the views of stakeholders

31/7/06

26

Page 29: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Figure 3 ASSET MANAGEMENT PROJECT PLAN 2006/07

Action Lead OfficerTarget Date

Progress (to be completed by AMWG / AMSG

during the year)MorlandsProceed with the disposal of the remainder of the Councils land holding in respect of the Morlands development, working with SWRDA.

Business Unit Manager -

Community & Regeneration

March 2010

.

Cattle Market Public ConveniencesTo build new public convenience at the Cattle Market Car Park, Frome

Asset Maintenance

Officer

December 2006

Frome AllotmentsTo complete the transfer of all Frome allotments sites.

Corporate Property Officer

December 2006

DDA – Leisure CentresEnsure compliance with legislation for Disabled access to public buildings:

To produce a costed programme of works for Leisure Centres

Strategic Asset Manager /

Leisure Officer

June 2007

Pay & Display Machines Replace all Pay and Display machines in all car parks

Car Parks Manager

March 2007

Leisure – 10 yr Maintenance Plan To carry out a planned maintenance survey to develop a costed 10 year maintenance plan relating to MDC’s responsibilities within the Leisure Contract

Leisure Officer April 2007

27

Page 30: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Action Lead OfficerTarget Date

Progress(to be completed by AMWG / AMSG

during the year)Tor Leisure, Glastonbury To review and agree the maintenance programme, with a view to delivering within the terms of the lease.

Leisure Officer April 2008

Accommodation Strategy To develop an Accommodation Strategy for the Council to incorporate the needs of Capita Local Government Services.

Corporate Finance & Resources Business Manager

March 2007

Asset Management Strategy To assist in the development of an Asset Management Strategy for the Council’s major assets

Corporate Property Officer

October 2007

Wells Recreation GroundTo progress the disposal of Park Cottage, Bishops Barn and Wells Recreation Ground

Corporate Property Officer

March 2007

Chantry Sewage Treatment Plant To progress the consultants recommendations for the Chantry Sewage Treatment Plant.

To be confirmed

March 2008

Batcombe Sewage Treatment PlantTo progress the works at Batcombe Sewage Treatment Plant

To be confirmed

October2007

28

Page 31: CORPORATE ASSET MANAGEMENT PLAN 2006/07

Action Lead OfficerTarget Date

Progress(to be completed by AMWG / AMSG

during the year)Memorial Safety Testing To carry out memorial safety testing in all 3 Cemeteries

Bereavement Officer

March 2007

Nunney ChurchyardTo ensure the repairs to Nunney Churchyard walls are completed

Asset Maintenance

Officer

October 2006

Southside Car Park Public ConveniencesTo obtain Planning Permission for new building public convenience st Southside Car Park in Street

Asset Maintenance

Officer

December 2006

Street Lamp SurveyTo complete a survey of all MDC owned Street Lights

Asset Maintenance

Officer

June 2007

Footpaths & Hard Surface AreaDevelop an inspection programme for all Council owned footpaths and hard surface areas.

Corporate Property Officer

March 2007

Car ParksTo produce a cyclical maintenance programme for car park surfacing and lighting

Car Parks Manager

March 2007

29

Page 32: CORPORATE ASSET MANAGEMENT PLAN 2006/07

30

Action Lead OfficerTarget Date

Progress(to be completed by AMWG / AMSG

during the year)Residential Car Parks To undertake a review of all Council owned residential car parks and produce recommendations for future management

Corporate Property Officer

March 2007