DBM/BM
Thickness
(mm)
BC
Thickness
(mm)
Total
Thickness
(mm)
1 06.09.2013CH: 0+410RHS ( 30 cm From the
Edge )40mm 30mm 70mm
2 06.09.2013CH: 0+630 LHS ( 30 cm From the
Edge)15mm 30mm 45mm
3 06.09.2013CH: 1+000 RHS ( 50 cm From the
Edge)35mm 37mm 72mm
4 06.09.2013CH: 1+500 LHS (40 cm From the
Edge)31mm 40mm 71mm
5 06.09.2013CH: 2+000 RHS ( 60 cm From the
Edge)38mm 38mm 76mm
6 06.09.2013CH: 2+510 LHS ( 80 cm From the
Edge)30mm 25mm 55mm
7 06.09.2013CH: 3+000 RHS ( 80 cm From the
Edge)50mm 25mm 75mm
8 06.09.2013CH: 3+600 LHS ( 80 cm From the
Edge)54mm 26mm 80mm
9 06.09.2013CH: 4+000 RHS ( 40 cm From the
Edge)50mm 25mm 75mm
10 09.09.2013CH: 4+500 LHS ( 40 cm From the
Edge)40mm 45mm 85mm
11 09.09.2013CH: 5+000 RHS ( 33 cm From the
Edge)30mm 34mm 64mm
12 09.09.2013CH: 5+500 LHS ( 52 cm From the
Edge)52mm 28mm 80mm
13 09.09.2013CH: 6+000 RHS ( 35 cm From the
Edge)47mm 23mm 70mm
KERALA STATE TRANSPORT PROJECT PHASE II
Up Gradation of the Road from Pillathara (Km o+ooo) to Pappinissery (Km 20+900) of SH-67
Detail of cores from the existing Road
Description
Sl.No Date Location
Contractor's Representative Consultant's Representative
Having More Voids
Having More Voids
DBM Disturbed and having
more voids
DBM Disturbed and having
more voids
DBM Disturbed and having
more voids
DBM Disturbed and having
more voids
DBM Disturbed and having
more voids
DBM Disturbed and having
more voids
DBM Disturbed and having
more voids
Having More Voids
Having More Voids
Having More Voids
Having More Voids
KERALA STATE TRANSPORT PROJECT PHASE II
Up Gradation of the Road from Pillathara (Km o+ooo) to Pappinissery (Km 20+900) of SH-67
Detail of cores from the existing Road
Remarks
Contractor's Representative Consultant's Representative
DBM/BM
Thickness
(mm)
BC
Thickness
(mm)
Total
Thickness
(mm)
1 10.09.2013CH: 6+500 LHS ( 60 cm From
the Edge )25mm 40mm 65mm
2 10.09.2013CH: 7+020 RHS ( 45 cm From
the Edge)35mm 40mm 75mm
3 10.09.2013CH: 7+500 LHS ( 39 cm From
the Edge)60mm 25mm 85mm
4 10.09.2013CH: 8+000 RHS (35 cm From
the Edge)30mm 40mm 70mm
5 10.09.2013CH: 8+500 LHS ( 33 cm From
the Edge)30mm 40mm 70mm
6 10.09.2013CH: 9+000 RHS ( 34 cm From
the Edge)35mm 35mm 72mm
7 10.09.2013CH: 9+500 LHS ( 40 cm From
the Edge)35mm 37mm 90mm
8 10.09.2013CH: 10+000 RHS ( 40 cm From
the Edge)50mm 40mm 90mm
9 11.09.2013CH: 10+500 LHS ( 39 cm From
the Edge)50mm 40mm 90mm
KERALA STATE TRANSPORT PROJECT PHASE II
Up Gradation of the Road from Pillathara (Km o+ooo) to Pappinissery (Km 20+900) of SH-67
Detail of cores from the existing Road
Sl.No Date Location
Description
Contractor's Representative Consultant's Representative
Having More Voids
Having More Voids
Having More Voids
Having More Voids
DBM Disturbed
DBM Disturbed
DBM Disturbed
Having More Voids
Having More Voids
KERALA STATE TRANSPORT PROJECT PHASE II
Up Gradation of the Road from Pillathara (Km o+ooo) to Pappinissery (Km 20+900) of SH-67
Detail of cores from the existing Road
Remarks
Contractor's Representative Consultant's Representative
DBM/BM Thickness
(mm)
BC Thickness
(mm)
Total Thickness
(mm)
1 12.09.2013CH: 11+000 RHS ( 45 cm From the Edge )
45mm 33mm 78mm Having More Voids
2 12.09.2013CH: 11+500 LHS ( 34 cm From the Edge)
42mm 28mm 70mm DBM Disturbed
3 12.09.2013CH: 12+000 RHS ( 45 cm From the Edge)
33mm 47mm 80mm DBM Disturbed
4 12.09.2013CH: 12+500 LHS ( 36 cm From the Edge)
31mm 34mm 65mm Having More Voids
5 12.09.2013CH: 13+045 RHS ( 40 cm From the Edge)
48mm 32mm 80mmDBM Disturbed and having
more voids
6 12.09.2013CH: 13+500 LHS ( 40 cm From the Edge)
37mm 33mm 70mmDBM Disturbed and having
more voids
7 12.09.2013CH: 14+000 RHS ( 44 cm From the Edge)
38mm 52mm 90mmDBM Disturbed and having
more voids
8 13.09.2013CH: 14+500 LHS ( 55 cm From the Edge)
30mm 40mm 70mmDBM Disturbed and having
more voids
9 13.09.2013CH: 15+030 RHS ( 80 cm From the Edge)
55mm 35mm 90mm Having More Voids
10 13.09.2013CH: 15+500 LHS ( 45 cm From the Edge)
41mm 34mm 75mmDBM Disturbed and having
more voids
11 13.09.2013CH: 16+000 RHS ( 40 cm From the Edge)
44mm 26mm 70mmDBM Disturbed and having
more voids
12 13.09.2013CH: 16+500 LHS ( 40 cm From the Edge)
60mm 30mm 90mmDBM Disturbed and having
more voids
13 14.09.2013CH: 17+030 RHS ( 50 cm From the Edge)
50mm 30mm 80mm DBM Disturbed
14 14.09.2013CH: 17+500 LHS ( 35 cm From the Edge)
45mm 30mm 75mmDBM Disturbed and having
more voids
15 14.09.2013CH: 18+010 RHS ( 50 cm From the Edge)
42mm 33mm 75mm DBM Disturbed
16 14.09.2013CH: 18+510 LHS ( 50 cm From the Edge)
60mm 35mm 95mm Having More Voids
KERALA STATE TRANSPORT PROJECT PHASE II
Up Gradation of the Road from Pillathara (Km o+ooo) to Pappinissery (Km 20+900) of SH-67
Detail of cores from the existing Road
Sl.No Date Location
Description
Remarks
Contractor's Representative Consultant's Representative
17 14.09.2013CH: 19+000 RHS ( 60 cm From the Edge)
56mm 34mm 90mm Having More Voids
18 14.09.2013CH: 19+530 LHS ( 65 cm From the Edge)
60mm 35mm 95mm Having More Voids
19 14.09.2013CH: 20+070 RHS ( 40 cm From the Edge)
43mm 35mm 78mm DBM Disturbed
20 14.09.2013CH: 20+500 LHS ( 55 cm From the Edge)
37mm 38mm 75mm DBM Disturbed
21 14.09.2013CH: 20+870 RHS ( 36 cm From the Edge)
45mm 40mm 85mm DBM Disturbed
Contractor's Representative Consultant's Representative