Building Rates- 2011- NCP

RATES FOR BUILDING CONSTRUCTIONS 2011

PROVINCIAL ENGINEERING DEPARTMENT NORTH CENTRAL PROVINCE

Page 1

Building Rates- 2011- NCP

PROVINCIAL ENGINEERING DEPARTMENT NORTH CENTRAL PROVINCE

Head Office :Maithreepala Senanayake Mawatha, Anuradhapura. Tel. : 025-2220910, 025-2226157, 025-2225285ax : 025-2220910 F e-mail : [email protected]

Divisional Engineer's Offices :Anuradhapura Kekirawa Mahailluppallama Medawachchiya Polonnaruwa : Tel. : 025 - 2236386 e-mail : [email protected] : Tel. : 025 - 2264286 e-mail : [email protected] : Tel. : 025 - 2249136 e-mail : [email protected] : Tel. : 025 - 2245930 e-mail : [email protected] : Tel. : 027 - 2222406 e-mail : [email protected]

Quality Control laboratory :Maradankadawala Road, Kekirawa Tel. : 025-2263285 e-mail : [email protected]

Page 2

Building Rates- 2011- NCP

Vision :

Being the forerunner in performing Engine activities in the North Central Province qualitatively

Mission :

Our mission is to raise the living standards people with the participation of the community, utilizing resources in an environment-friendly m and preserving the identity and the grandeur of Raj and to ensure optimum management for sustainabi the Engineering activities by using modern techn with an institutional and professional responsibility.

Page 3

Building Rates- 2011- NCP

KEY PERSONS* Eng. C.K.B. Seneviratne C.Eng., MIE(SL), P.G.Dip.(L&W), M-2432 * Eng. (Ms.) K.C.D. Fernando B.Sc. Eng., P.G.Dip.(IWM), C.Eng., MIE(SL), M-5068 * Eng. (Ms.) D.L.B.P. Wijesekara, B.Sc. Eng., M.Sc.(IWRM), C.Eng., MIE(SL), M-4492 * Eng. S.J.K. Alas B.Sc. Eng., AMIE(SL), AM-5978 * Eng. H.M.J. Herath B.Sc. Eng., C.Eng., MIE(SL), M-5822 * Eng.(Ms.) I.K.M.C.K. Illangasinghe B.Sc. Eng., AMIE(SL), AM-4630 * Eng. D.M.U.S.B. Dissanayake B.Sc. Eng., C.Eng., MIE(SL), M-5187 * Eng. (Ms.) M.P.P. Dilhani B.Sc. Eng., C.Eng., MIE(SL), M-5698 * Eng. B.K. Matupala * Eng. W. Jayasundara E.C.(UK), AM-7728 * W.N.P.M.S. Wijithaweera B.Sc. (B.E.) * Eng. S.D.N. Ariyawansha B.Sc. Eng., AMIE(SL), AM-10626 * Eng. B.M.B.S. Bandara B.Sc. Eng., AMIE(SL), AM-10268 * Eng. A.A.D.C.R. Aluthgama B.Sc. Eng., AMIE(SL), AM-10760 * Eng. W.G.S.S. Bandara B.Sc. Eng., AMIE(SL), AM-10614 * Eng. H.M.R.M. Aberathna B.Sc. Eng., AMIE(SL), AM-10023 * Eng. W.H. HapuarachchiPage 4

: : :

Deputy Chief Secretary (Enginee Tel.025-2220910 Director (Buildings), 2226157

Director Designs, (Consultancy & Control), Tel. 025-2

:

Divisional Engineer - Medawach Tel. 025-2245930

: : : : : : : :

Divisional Engineer - Polonnaruw 027-2222406 Divisional Engineer - Kekirawa, Tel. 025-2264286 Engineer - School works, 2222194

T

Divisional Engineer - Mahaillupp Tel. 025-2249136

Divisional Engineer -Anuradhapu 025-2236386

Engineer in charge (Special proje 025-2225285 Architect, Tel. 025-2225285

Engineer in charge (Health depar projects), Tel. 025-222

:

Engineer in charge (Other departm projects), Tel. 025-222 Quality Control Engineer, 2263285

: : : :

T

Additional Engineer - Polonnaruw 027-2222406 Irrigation Engineer, 3779070 Mechanical Engineer , 2225285

T

Building Rates- 2011- NCP

B.Sc. Eng., AMIE(SL), AM-11257

Mechanical Engineer , 2225285

T

Page 5

Building Rates- 2011- NCP

GUIDELINES FOR USERS

* All rates in this book have been prepared by using Anuradhapura district buying committee rates and m of materials in North Central Province.

General Specifications :1.

Specifications for Building Works - Volume I - ICTAD Publication No. SCA/4/I - Revised Edition - July

2.

Specifications for Building Works - Volume II - Sanitary Installations - ICTAD Publication No. SCA/4/ Edition - October 2001

3.

Specifications for Water Supply, Sewerage & Storm Water Drainage Works - ICTAD Publication No Revised Edition - April 2002 Specifications for Electrical & Mechanical works Associated with Building & Civil Engineering Publication No. SCA/8 - Revised Edition - August 2000

4.

*

The Particular Specification shall be read in conjunction with the General Specification where applic event the Particular Specification is in conflict with the General Specification, the Particular Specificat prevail.

*

Particular Specifications for each category are mentioned above. Full description and relevant notes above for each category in the rate book should be given for each item when preparing estimates.

*

In the specifications, if any materials/fittings are described by using a trade name, it is only for the indicating the minimum level of quality and standard required. It may be used any other material/ fitting considered as equivalent in quality and standard to those specified therein subject to the approval of the E

*

Rates can be used as guidance and adjustment could be made to suit the specific site conditions s approval. Overhead and profit applied is 20%. Transport, loading, unloading and material wastage are included in the rates. Prices used are exclusive of VAT.

* * *

Page 6

Building Rates- 2011- NCP

LEDGENDNo. ITEM RATES FOR BUILDING CONSTRUCTIONS A. B. C. D. E. F. G. H. I. J. K. L. M. N. O. P. Q. R. DEMOLISHER EXCAVATION & EARTHWORK MASON CONCRETOR FORMWORK REINFORCEMENT BRICKLAYER PLASTERER PAVIOR ROOFER CARPENTER & JOINER IRONWORK PAINTER & DECORATOR PLUMBER DRAINLAYER ELECTRICAL INSTALLATION MISCELLANEOUS ALUMINIUM WORK UNITS PRICES OF MATERIAL, LABOUR AND PLANT FOR 2011 RATES FOR IRRIGATION CONSTRUCTIONS RATES FOR QUALITY CONTROL TESTS 7-9 10 11 12 - 14 15 16 17 18 - 19 20 - 23 24 - 31 32 - 35 36 - 38 39 - 40 41 - 46 46 - 48 49 - 51 52 53 - 55 56 - 58 60-72 73-75 Page

Page 7

Building Rates- 2011- NCP

Page 8

Building Rates- 2011- NCP

A - DEMOLISHER Rates for Demolisher shall include for: (a) (b) (c) NO. Scaffolding, shoring and shores required.

Protection of site personal, plant and equipment by taking precautions against uncontrolled collaps hazards and fire or explosion risks. Materials arising from the demolition works shall be removed as directed by the Engineer. DESCRIPTION

IMPERIAL UNIT RATE A-1 Brickwork in lime demolished, brick stacked and debris cube 1,483.00 cleared within the site. A-2 Brickwork in cement mortar demolished, brick stacked cube and debris cleared within the site. A-3 Ceiling existing removed, materials stacked and debris cleared within the site sqr. 1,978.00 625.00 8,640.00 18,909.00 711.00

A-4 Cement concrete demolished and debris cleared within the cube site. A-5 Reinforced concrete demolished, reinforcement removed cube and debris cleared within the site. A-6 Corrugated sheets (Iron, asbestos or aluminium) removed from roof or walls and stacked - single storied building A-7 Corrugated sheets (Iron, asbestos or aluminium) removed from roofs or walls and stacked - 2 storied building. A-8 Corrugated sheets (Iron, asbestos or aluminium) removed from roofs or walls and stacked - 3 storied buildings. sqr.

sqr.

772.00

sqr.

834.00

A-9 Door or window with frame size up to 40 sqft. removed from existing walls and stacked. A-10 Door or window with frame size over 40 sqft. removed from existing walls and stacked. A-11 Door or window sash only, up to 40 sqft. removed from existing walls and stacked. A-12 Door or window sash only, over 40 sqft. removed from existing walls and stacked. A-13 Down pipes, old or decayed, removed building and stacked. from existing

no. no. no. no. lft. lft.

960.00 1,440.00 141.00 212.00 10.00 19.00

A-14 Drains demolished and debris cleared within the site.

Page 9

Building Rates- 2011- NCP

A-15 Fence uprooted, barbed wire rolled up and all materials stacked (Length of fencing to be measured)

lft.

40.00

Page 10

Building Rates- 2011- NCP

IMPERIAL UNIT RATE A-16 Floors brick paved, demolished and debris cleared away sqr. 720.00 within the site. A-17 Gate sash removed and stacked after demolishing cement concrete blocks or removing posts and separating pintos (demolishing brickwork where necessary paid for separately) no 960.00

NO.

DESCRIPTION

A-18 Glass panes in doors and windows and fanlights removed and stacked. A-19 Gutter, eaves removed and stacked from roof of single storied building. A-20 Gutter, eaves removed and stacked from roof of 2 storied building A-21 Gutter, eaves removed and stacked from roof of 3 storied building. A-22 Partitions removed and stacked at site, including making good to walls and floors. A-23 Cement, lime plastering chipped and debris cleared away within the site. A-24 Rendering, cement chipped and debris cleared away from brick walls and floors within the site. A-25 Rendering, cement chipped and debris cleared away from cement concrete floors and walls within the site. A-26 Removing of existing roof (tiles, asbestos sheets or GI sheets) with timber frame, stacking usable material and clearing debris in single storied building. A-27 Removing of existing roof (tiles, asbestos sheets or GI sheets) with timber frame, stacking usable material and clearing debris in 2 storied building. A-28 Removing of existing roof (tiles, asbestos sheets or GI sheets) with timber frame stacking usable material and clearing debris in 3 storied and above

sqft. lft. lft. lft. sqft.

41.00 6.00 9.00 12.00 27.00

sqr. sqr.

510.00 1,080.00

sqr.

1,622.00

sqr.

1,410.00

sqr.

1,823.00

sqr.

2,318.00

A-29 Rubble masonry in cement demolished, rubble stacked cube and debris cleared within the site.Page 11

3,090.00

Building Rates- 2011- NCP

A-30 Tiles, glazed demolished and debris cleared within the site.

sqr.

1,920.00

Page 12

Building Rates- 2011- NCP

IMPERIAL UNIT RATE A-31 Tiles Calicut or half round, removed from roof of single sqr. 494.00 storied buildings and stacked at site. A-32 Tiles Calicut or half round removed from roof of storied building and stacked at site. A-33 Tiles Calicut or half round, removed from roofs of storied and above buildings and stacked at site. 2 sqr. 742.00

NO.

DESCRIPTION

3

sqr.

989.00

A-34 Waterproof Treatment of hot bitumen taken off from flat roof and debris cleared away. A-35 Ceiling asbestos removed including timber framework stacking usable materials and debris cleared away in single storied building. A-36 Ceiling asbestos removed including timber frame work, stacking usable materials and debris cleared away in 2 storied building. A-37 Valance/Barge boarding removed, materials stacked and debris cleared away in single storied building. A-38 Valance/Barge board removed, materials stacked and debris cleared away in 2 storied building. A-39 Cement plastering in soffit chipped and debris cleared away. A-40 Roof trusses span up to 30' 0" removed from roof and stacked.

sqr. sqr.

1,920.00 2,348.00

sqr.

2,843.00

lft.

6.00

lft.

9.00

sqr. no.

1,384.00 2,966.00 1,680.00

A-41 Transport of debris to a place where 1-5 km away from the cube site as directed by the Engineer including loading.

A-42 Transport of debris to a place where 5-10 km away from cube the site as directed by the Engineer including loading. A-43 Basin, sink, or urinals including all fittings removed and wall made good A-44 Water Closet or Squatting pan, removed, sewer connection plugged and floor made good no. no.

1,950.00

1,146.00 1,804.00

Page 13

Building Rates- 2011- NCP

B - EXCAVATION & EARTHWORK Rates for Excavation and Earthwork shall include for: (a) (b) (c) (d) (e) (f) NO. Trimming sides, keeping clean, leveling, grading and consolidating bottom of bases and trenches etc.

Leveling and consolidating where required under slabs or sub-floor layers. Back filling and well ramming around foundation. Keeping all excavations free from storm or percolating water to keep excavation dry at all stages of const Any necessary additional excavation for working spaces, planking and strutting etc. Providing shoring work where necessary. DESCRIPTION

IMPERIAL UNIT RATE B-1 Removing top soil to a depth of 150mm and depositing as sqr. 816.00 directed within the site B-2 Excavation for foundation in any material except rock cube requiring blasting, part return fill in and ram, and surplus dispose within the site as directed. B-3 Excavation in any material except rock requiring blasting cube including transporting up to 400m, depositing and leveling. B-4 Excavation in trenches for walls and column pits in soft cube disintegrated rock (not requiring blasting) up to a depth of 1.5m and depositing excavated materials to distance not exceeding 10m. B-5 Excavation in trenches for walls and column pits in hard cube rock requiring blasting up to a depth of 1.5m and depositing excavated materials to distance not exceeding 10m. B-6 Filling under floors with gravel or other approved quality cube of filling, spread, watered and well rammed in 150mm layers (material available at site) B-7 Filling under floors with gravel or other approved quality cube of filling, spread, watered and well rammed in 150mm layers (material not available at site) B-8 Anti termite treatment on excavated foundation and compacted soil under floors (Treatment should be done according to the instructions given by the Engineer) Warranty period 10 years sqr. 1,483.00

1,183.00

2,016.00

5,604.00

1,795.00

3,839.00

3,575.00

Page 14

Building Rates- 2011- NCP

B-9 Drains, earth in any soil except rock requiring blasting cut cube to gradient and shaped as directed, soil deposited within site.

1,291.00

Page 15

Building Rates- 2011- NCP

C - MASON Rates for Masonry work shall include for: (a) (b) (c) All joggles, clamps, dowels, ties, and templates. Rough and fair cutting forming splays. Angles, reveals and returns. Instructions : (a) (b) NO. Rubble Masonry C-1 150-225mm Random Rubble Masonry in cement mortar cube 1:5 above 1 cube C-2 150-225mm Random Rubble Masonry in cement mortar cube 1:5 up to 1 cube Block Masonry C-3 150mm thick Hollow block work in cement and sand mortar 1:5 with 400x200x150mm blocks (Cavities unfilled) C-4 100mm thick Hollow block work in cement and sand mortar 1:5 with 400x200x100mm blocks (Cavities unfilled) C-5 150mm thick solid block work in cement and sand mortar 1:5 with 400x200x150mm blocks C-6 100mm thick solid block work in cement and sand mortar 1:5 with 400x200x100mm blocks sqr. 12,083.00 27,327.00 Cement used should be SLS Certified Products for Masonry work Average crushing strength of 10 blocks shall be not less than 2.8 N/mm2 DESCRIPTION IMPERIAL UNIT RATE

29,830.00

sqr.

8,949.00

sqr.

12,365.00

sqr.

9,090.00

Page 16

Building Rates- 2011- NCP

D - CONCRETOR Grade of concrete used in the construction and recommended mixes as follows. (a) (b) (c) (d) (a) (b) (c) (d) (e) (f) (a) (b) (c) (d) NO. Grade 25 Recommended Mix 1 : 1 : 3 (20mm) Grade 20 Recommended Mix 1 : 2 : 4 (20mm) Grade 15 Recommended Mix 1 : 2 1/2 : 5 (25mm) Grade 10 Recommended Mix 1 : 3: 6 (40mm) Rate shall include, Mixing, hoisting, placing and compacting on the surfaces of any material or on formwork. Forming any construction joint. Vibrating, curing and protecting concrete surfaces from harmful weather conditions. Forming sloping on upper surfaces where required. Grouting the earlier concreted edges. Making good after removal of formwork. Instructions Prior approval for any concrete work should be taken from the Engineer.

Approval for constituent materials and test reports for properties of concrete should be taken from Qua Engineer, Quality Control lab, Kekirawa with contractor's expense. Cement used should be SLS certified products approved for concrete. Reinforcement and formwork paid separately where not mentioned. DESCRIPTION IMPERIAL UNIT RATE cube 33,652.00 cube sqr. 35,902.00 9,915.00

D-1 Cement concrete grade 10 above one cube. D-2 Cement concrete grade 10 up to 1 cube. D-3 75mm thick cement concrete grade 15 in floors using concrete mixer and vibrator including laying of gauge 1000 polythene sheet

D-4 Cement concrete grade 20 in column foundation, column cube shaft and plinth beams using mixer and vibrator - up to first floor level D-5 Cement concrete grade 20 in column shaft using mixer cube and vibrator - up to second floor level D-6 Cement concrete grade 20 in column shaft using mixer cube and vibrator - up to third floor level

43,270.00

45,460.00

48,426.00

Page 17

Building Rates- 2011- NCP

D-7 Cement concrete grade 20 in slab, beams and stair case cube using mixer and vibrator - up to first floor level

44,726.00

Page 18

Building Rates- 2011- NCP

NO.

IMPERIAL UNIT RATE D-8 Cement concrete grade 20 in slab, beams and stair case cube 45,714.00 using mixer and vibrator - up to second floor level

DESCRIPTION

D-9 Cement concrete grade 20 in slab, beams and stair case cube using mixer and vibrator - up to third floor level

47,198.00

D-10 Cement concrete grade 25 in column foundation, column cube shaft and plinth beams using mixer and vibrator - up to first floor level D-11 Cement concrete grade 25 in column shaft using mixer cube and vibrator - up to second floor level D-12 Cement concrete grade 25 in column shaft using mixer cube and vibrator - up to third floor level D-13 Cement concrete grade 25 in slab, beams and stair case using mixer and vibrator - up to first floor level D-14 Cement concrete grade 25 in slab, beams and stair case using mixer and vibrator - up to second floor level cube

46,392.00

48,582.00

51,548.00

48,888.00

cube

49,876.00

D-15 Cement concrete grade 25 in slab, beams and stair case using mixer and vibrator - up to third floor level

cube

51,360.00

D-16 Cement concrete grade 20 in lintels (reinforcement and cube shuttering paid separately) using mixer and vibrator - up to first floor level

39,076.00

D-17 Cement concrete grade 20 in lintels (reinforcement and cube shuttering paid separately) using mixer and vibrator - up to second floor level D-18 Cement concrete grade 20 in lintels (reinforcement and cube shuttering paid separately) using mixer and vibrator - up to third floor level

41,054.00

44,020.00

D-19 Lintel, cement concrete grade 20, 112x150mm with 2 nos. 12 mm dia. tor steel bars and form work - up to first floor levelPage 19

Lft.

323.00

Building Rates- 2011- NCP

NO.

DESCRIPTION lft.

IMPERIAL UNIT RATE 334.00

D-20 Lintel, cement concrete grade 20, 112x150mm with 2 nos. 12 mm dia. tor steel bars and form work - up to second floor level D-21 Lintel, cement concrete grade 20, 112x150mm with 2 nos. 12 mm dia. tor steel bars and form work - up to third floor level D-22 Lintel, cement concrete grade 20, 225x150mm with 2 nos. 12 mm dia. tor steel bars and form work - up to first floor level D-23 Lintel, cement concrete grade 20, 225x150mm with 2 nos. 12 mm dia. tor steel bars and form work - up to second floor level D-24 Lintel, cement concrete grade 20, 225x150mm with 2 nos. 12 mm dia. tor steel bars and form work - up to third floor level D-25 Coble stone in grade 20 cement concrete reinforced with 4 n. of 10mm dia. Tor steel, up to 1 cuft. in volume

lft.

341.00

lft.

384.00

lft.

395.00

lft.

402.00

no.

2,824.00

D-26 75mm thick worktop in grade 20 cement concrete with 10mm tor steel at 150mm c/c both ways including formwork and soffit plastering

sqft.

318.00

D-27 100mm thick copping in grade 20 concrete on 225mm thick walls including 2nos. of 8mm tor steel bars and stirrups with 6mm dia. mild steel including formwork finished smooth with 50mm rendering and red cement floating with throat.

lft.

649.00

D-28 100mm thick copping in grade 20 concrete on 112mm thick walls including 2nos. of 8mm tor steel bars and stirrups with 6mm dia. mild steel including formwork finished smooth with 50mm rendering and red cement floating with throat.

lft.

471.00

Page 20

Building Rates- 2011- NCP

E - FORMWORK Rates for formwork shall include for: (a) (b) (c) (a) NO.

All framing, propping, bracing, cutting angles, bolting, wedging, cleaning, wetting and treating bef concrete. Erecting, Striking off and cleaning of formwork. Rubbing down, filling and making good the surface of concrete after removal of formwork. Instructions All the formwork for slabs should be done in such a way that it is good enough to apply a suitable pillar and painting, without soffit plastering. DESCRIPTION

layer of s

IMPERIAL UNIT RATE E-1 12mm Plywood shuttering for slab, beams and staircase sqr. 11,733.00 including dismantling - up to first floor level E-2 12mm Plywood shuttering for slab, beams and staircase including dismantling - up to second floor level E-3 12mm Plywood shuttering for slab, beams and staircase including dismantling - up to third floor level E-4 12mm Plywood shuttering for column shaft including dismantling - up to first floor level E-5 12mm Plywood shuttering for column shaft including dismantling - up to second floor level E-6 12mm Plywood shuttering for column shaft including dismantling - up to third floor level E-7 Shuttering for plinth beams and lintels including dismantling - up to first floor level E-8 Shuttering for lintels including dismantling - up to second floor level E-9 Shuttering for lintels including dismantling - up to third floor level sqr. 12,363.00

sqr.

12,453.00

sqr.

12,620.00

sqr.

13,040.00

sqr. sqr. sqr. sqr. sqr.

13,320.00 7,654.00 8,974.00 9,094.00 4,647.00

E-10 Class III timber shuttering for small works including dismantling

Page 21

Building Rates- 2011- NCP

F- REINFORCEMENT (a) (b) (c) (d) (e) (f) Rates for Reinforcement shall include for: Rolling margin and waste. Bending, cutting, fabricating, hoisting, and placing in position. Holding and supporting including temporary fixing supports, hangers. Cleaning and wire brushing. All spacing, laps etc. in reinforced steel other than design laps.

Tensile strength of Tor Steel should be not less than 460 N/mm2 and Mild Steel should be not less than 25

(a) (b) (c) (d)

Instructions Inevitable laps should be measured. Unless otherwise specified laps to be 50 times the diameter of the bar. Preparation, supplying & binding of cover blocks such that specified cover is maintained at outer-most ro

Reinforcements should be CN, GTB or LANWA. Tensile strength of reinforcements should be tested i from the institution where specified by the Engineer with contractor's expense.

(e) NO. F-1

Some trade names are used only for the purpose of indicating the minimum level of quality and standards IMPERIAL UNIT RATE Tor steel rods reinforcing in Column foundation and cwt. 9,219.00 plinth beams up to DPC, bent to shape laid in position and tied with G.I. Wire as directed Tor steel rods reinforcing in columns, beams, slabs and lintels up to first floor level bent to shape laid in position and tied with G.I. Wire as directed Tor steel rods reinforcing in columns, beams, slabs and lintels up to second floor level bent to shape laid in position and tied with G.I. Wire as directed Tor steel rods reinforcing in columns, beams, slabs and lintels up to third floor level bent to shape laid in position and tied with G.I. Wire as directed Mild steel rods, shape into stirrups and laid in position and tied with GI wires as directed - up to first floor level Mild steel rods, shape into stirrups and laid in position and tied with GI wires as directed - up to second floor level cwt. 9,561.00 DESCRIPTION

F-2

F-3

cwt.

9,869.00

F-4

cwt.

10,074.00

F-5

cwt.

9,513.00

F-6

cwt.

9,821.00

Page 22

Building Rates- 2011- NCP

F-7

Mild steel rod, shape into stirrups and laid in position and tied with GI wires as directed - up to third floor level

cwt.

10,026.00

Page 23

Building Rates- 2011- NCP

G - BRICK LAYER Rates for Brickwork shall include for: Wetting well all the surfaces of the bricks before using. Plumbing angles. Normal straight cuttings. Ranking of joints for plastering. All the necessary scaffolding. Ranking of joints for plastering. Instructions : (a) (b) NO. Cement used should be SLS Certified Products for Masonry work Average crushing strength of 10 bricks shall be not less than 7.0 N/mm2 DESCRIPTION

(a) (b) (c) (d) (e) (f)

IMPERIAL UNIT RATE G-1 Arch, segmental, brick in cement sand 1:3, including cube 39,017.00 plumbing angles, normal straight cutting, forming rebated reveals and raking of joints for plastering

G-2 225mm thick brick work in cement - sand mortar 1:8 (up cube to first floor level) G-3 225mm thick brick work in cement - sand mortar 1:8 (up cube to second floor level) G-4 225mm thick brick work in cement - sand mortar mortar cube 1:8 (up to third floor level) G-5 Brick 112mm thick in cement - sand mortar 1:5 (up to first floor level) G-6 Brick 112mm thick in cement - sand mortar 1:5 (up to second floor level) G-7 Brick 112mm thick in cement - sand mortar 1:5 (up to third floor level) G-8 Coping, brick in cement - sand mortar 1:5, weathered and throated on 112mm walls, cement rendered with 12mm thick 1:3 mix complete sqr. sqr. sqr. lft.

29,562.00 31,046.00 34,012.00 11,732.00 13,215.00 16,182.00 252.00

G-9 Coping, brick in cement - sand mortar 1:5, weathered and throated on 225mm walls, cement rendered with 12mm thick 1:3 mix complete

lft.

345.00

Page 24

Building Rates- 2011- NCP

G-10 Widening R.C.C Column by placing one brick on both side of column to size 450x225mm

lft.

178.00

Page 25

Building Rates- 2011- NCP

H- PLASTERER (a) (b) (c) (d) (e) (f) (g) (h) NO. Rates for wall finishing shall include for: Temporary rules, screeds, ground etc. Ranking out joints of brickwork and backing concrete surface for forming key. Joints between different surfaces. Forming arises and stopping against joinery work, metal work etc. Making good around pipes, sanitary fittings and fixtures. Straight cutting and raking cutting holes, notching and other sundries Labour of a like nature.

Preparing sample panel of different finishes described below for the approval of the Engineer. Each pa than 0.5 m2 in area. Cement used should be SLS Certified Products for masonry work. DESCRIPTION

IMPERIAL UNIT RATE H-1 D.P.C., 20mm thick, in cement-sand mortar 1:2 finished sqr. 6,980.00 with two coats of hot tar applied at the rate of 0.25 liters per sqm. for each coat H-2 20mm thick plinth plaster in 1:3 cement - sand mortar finished smooth with neat cement floating. H-3 20mm thick plinth plaster in 1:3cement - sand mortar finished smooth with red cement floating. H-4 Cement plastering with 1:5 mix, 15mm thick finished semi rough in external walls - up to first floor level H-5 Cement plastering with 1:5 mix, 15mm thick finished semi rough in external walls - up to second floor level H-6 Cement plastering with 1:5 mix, 15mm thick finished semi rough in external walls - up to third floor level H-7 Cement plaster with 1:5 mix, 15mm thick finished smooth with skim coat in internal walls - up to first floor level H-8 Cement plaster with 1:5 mix, 15mm thick finished smooth with skim coat in internal walls - up to second floor level sqr. 5,617.00

sqr.

5,956.00

sqr.

3,648.00

sqr.

3,987.00

sqr.

4,212.00

sqr.

5,134.00

sqr.

5,660.00

Page 26

Building Rates- 2011- NCP

H-9 Cement plaster with 1:5 mix, 15mm thick finished smooth with skim coat in internal walls - up to third floor level

sqr.

5,953.00

Page 27

Building Rates- 2011- NCP

NO.

DESCRIPTION sqr.

IMPERIAL UNIT RATE 4,923.00

H-10 Cement lime plaster with 1:1:5 mix, 15mm thick finished smooth with lime putty in internal walls - up to first floor level H-11 Cement lime plaster with 1:1:5 mix, 15mm thick finished smooth with lime putty in internal walls - up to second floor level H-12 Cement lime plaster with 1:1:5 mix, 15mm thick finished smooth with lime putty in internal walls - up to third floor level H-13 Reveals or plaster band 150mm wide in walls with cement lime and sand 1:1:5 mix finished to match existing H-14 Finish smooth soffit of slab by applying skim coat - up to first floor level H-15 Finish smooth soffit of slab by applying skim coat - up to second level H-16 Finish smooth soffit of slab by applying skim coat - up to third floor level H-17 15mm thick plaster to R.C.C. columns, beams and soffit of slab in cement - sand 1:3 mix including floating with lime putty - up to first floor level

sqr.

5,399.00

sqr.

5,716.00

lft.

65.00

sqr. sqr.

2,458.00 2,599.00

sqr. sqr.

2,693.00 5,602.00

H-18 15mm thick plaster to R.C.C. columns, beams and soffit of slab in cement - sand 1:3 mix including floating with lime putty - up to second floor level

sqr.

6,236.00

H-19 15mm thick plaster to R.C.C. columns, beams and soffit of slab in cement - sand 1:3 mix including floating with lime putty - up to third floor level

sqr.

6,659.00

H-20 15mm thick plastering to wall in cement- sand 1:3 mix including cement floating H-21 Cracks in walls plastered in cement - sand 1:3 mix after chipping to 50-100mm wide

sqr. lft.

3,833.00 24.00

Page 28

Building Rates- 2011- NCP

I - PAVIOR Rates for paving and tiling shall include for: (a) (b) (c) (d) (e) (f) (g) (h) (i) (j) NO. Preparing surfaces of concrete / brick to receive rendering plaster bedding etc. Joints between different surfaces. Finishing to slopes and cross falls. Straight cutting and waste of tiles and other types of floor finishes. Protecting finished surfaces. For temporary rules, screeds, ground etc. All normal cutting arises, rounded edges, bedding and pointing. Slope should be maintained to a suitable direction to flow the water towards out side. Expansion joints so that no cracks propagated. Tiles should be approved by the Architect DESCRIPTION

IMPERIAL UNIT RATE I -1 Floors, cement concrete 1:2 1/2: 5 (25mm), 75mm thick, sqr. 13,595.00 cement rendered 12mm thick, 1:5 with expansion joints filled with cement and sand (including laying gauge 1000 polythene sheet) I -2 Rendering cement 12mm, in 1:5 cement and sand on existing concrete, finished smooth I -3 Rendering cement 12mm, in 1:5 cement and sand on existing concrete, floating coat using red cement finished smooth I -4 Rendering cement 12mm, in 1:5 cement and sand on existing concrete, finished rough I -5 Tile glazed 200x200mm, Sri Lankan made of approved type and colour, with all specials, supplied and fixed to wall including raking plaster and bedding in cement mortar 1:2, with tile beadings on top and edges - Ground floor I -6 Tile glazed 200x200mm, Sri Lankan made of approved type and colour, with all specials, supplied and fixed to wall including raking plaster and bedding in cement mortar 1:2, with tile beadings on top and edges - First floor sqr. sqr. 3,823.00 5,278.00

sqr.

3,401.00

sqr.

26,458.00

sqr.

26,746.00

Page 29

Building Rates- 2011- NCP

NO.

IMPERIAL UNIT RATE I -7 Tile glazed 200x200mm, Sri Lankan made of approved sqr. 26,938.00 type and colour, with all specials, supplied and fixed to wall including raking plaster and bedding in cement mortar 1:2, with tile beadings on top and edges - Second floor I -8 Tile glazed, 300x200mm, Sri Lankan made of approved type and colour, with all specials, supplied and fixed to wall including raking plaster and bedding in cement mortar 1:2 with tile beadings on top and edges - Ground floor I -9 Tile glazed, 300x200mm, Sri Lankan made of approved type and colour, with all specials, supplied and fixed to wall including raking plaster and bedding in cement mortar 1:2 with tile beadings on top and edges - First floor sqr. 26,689.00

DESCRIPTION

sqr.

26,977.00

I -10 Tile glazed, 300x200mm, Sri Lankan made of approved type and colour, with all specials, supplied and fixed to wall including raking plaster and bedding in cement mortar 1:2 with tile beadings on top and edges - Second floor I -11 Floor tile, 300x300mm, Sri Lankan made, nonskid pattern of approved type and colour supplied and laid including plaster bedding 1:2 with skirting and tile beadings on top - Ground floor

sqr.

27,169.00

sqr.

22,748.00

I -12 Floor tile, 300x300mm, Sri Lankan made, nonskid pattern of approved type and colour supplied and laid including plaster bedding 1:2 with skirting and tile beadings on top - First floor

sqr.

23,036.00

I -13 Floor tile, 300x300mm, Sri Lankan made, nonskid pattern of approved type and colour supplied and laid including plaster bedding 1:2 with skirting and tile beadings on top - Second floor

sqr.

23,228.00

Page 30

Building Rates- 2011- NCP

I -14 Floor tile, 200x200mm, Sri Lankan made, nonskid pattern of approved type and colour supplied and laid including plaster bedding 1:2 with skirting and tile beadings on top - Ground floor

sqr.

26,003.00

Page 31

Building Rates- 2011- NCP

IMPERIAL UNIT RATE I -15 Floor tile, 200x200mm, Sri Lankan made, nonskid sqr. 26,291.00 pattern of approved type and colour supplied and laid including plaster bedding 1:2 with skirting and tile beadings on top - First floor

NO.

DESCRIPTION

I -16 Floor tile, 200x200mm, Sri Lankan made, nonskid pattern of approved type and colour supplied and laid including plaster bedding 1:2 with skirting and tile beadings on top - Second floor

sqr.

26,483.00

I -17 Homogeneous Floor tile, 300x300mm, Sri Lankan made, nonskid pattern of approved type and colour supplied and laid including plaster bedding 1:2 with skirting and tile beadings on top - Ground floor

sqr.

25,184.00

I -18 Homogeneous Floor tile, 300x300mm, Sri Lankan made, nonskid pattern of approved type and colour supplied and laid including plaster bedding 1:2 with skirting and tile beadings on top - First floor

sqr.

25,472.00

I -19 Homogeneous Floor tile, 300x300mm, Sri Lankan made, nonskid pattern of approved type and colour supplied and laid including plaster bedding 1:2 with skirting and tile beadings on top - Second floor

sqr.

25,664.00

I -20 Homogeneous Floor tile, 400x400mm, Sri Lankan made, nonskid pattern of approved type and colour supplied and laid including plaster bedding 1:2 with skirting and tile beadings on top - Ground floor

sqr.

25,428.00

I -21 Homogeneous Floor tile, 400x400mm, Sri Lankan made, nonskid pattern of approved type and colour supplied and laid including plaster bedding 1:2 with skirting and tile beadings on top - First floor

sqr.

25,716.00

I -22 Homogeneous Floor tile, 400x400mm, Sri Lankan made, nonskid pattern of approved type and colour supplied and laid including plaster bedding 1:2 with skirting and tile beadings on top - Second floor

sqr.

25,908.00

Page 32

Building Rates- 2011- NCP

IMPERIAL UNIT RATE I -23 Floor tiles Tera cota of approved type laid on existing sqr. 19,629.00 concrete floor including plaster bed in 1:2 cement and sand

NO.

DESCRIPTION

I -24 Skirting 25x150mm in 1:5, projected or flush with walls and including forming groove I -25 Skirting 25x150mm in 1:5, projected or flush with walls and including forming groove finished with red cement

lft.

79.00

lft.

118.00

I -26 Skirting 25x100mm in 1:5, projected or flush with walls and including forming groove I -27 Skirting 25x100 in 1:5, projected or flush with walls and including forming groove finished with red cement I -28 Floor ramp 75mm thick, 750mm width cement concrete 1:21/2:5(25mm) on gauge 1000 polythene layer and cement rendered, expansion joints filled with 1:2 bitumen sand including filling and compacting gravel on the base and providing 150x225mm curb at the edge finished smooth with red cement floating

lft.

51.00

lft.

76.00

lft.

527.00

I -29 225mm width surface drain joined to the existing ramp with 75mm thick 1:2 1/2:5(25mm) concrete base, side wall of 112mm brick work in 1:5 cement sand rendering in 1:5 match to existing floor/ramp complete with expansion joints and necessary excavation

lft.

393.00

I -30 Laying of inter locking paving blocks on 75mm thick sand bed including site preparation, trimming, leveling and compacting with plate compactor as per instructions

sqr.

27,090.00

Page 33

Building Rates- 2011- NCP

J - ROOFER (a) (b) (c) (d) (a) (b) (c) (d) (e) (a) (b) (c) (d) (e) NO. Rates for Roof work shall include for: Hoisting and placing roofing materials in position. Laps, straight cutting and waste.

Galvanized iron J bolts, nuts, limpets and bituminous felt washers, nails screw clips, rivets straps and t Rafter hooks fixing rafters to the wall. Rates for joinery work shall include for: Framing together all works in accordance with the best practices. Nails Screws, Glue, plugs etc. Priming backs before fixing. Rawl plugs, brass screws etc. Drilling and making goods. Instructions Approval for all sizes of timber should be taken from the Engineer before using. All the timber used to be treated with wood preservative to the specifications. Ceiling sheets to be painted with one coat of acetic filler and two coats of emulsion paints. All the beading to be painted with one coat of wood primer and two coats of enamel paints.

For exposed rafter roofs, timber should be well planed and varnished. Timber sizes indicated in the des the sizes before planning. DESCRIPTION Roof including Timber frame Corrugated asbestos sheet roof (sloping to two directions) including 50x100mm imported treated timber rafters at 900 c/c and 50x50mm imported treated timber bearers with necessary coach screws and limpet washers or hook bolts, prepare and apply one coat of wood preservative (black) to structural timber work, including touching up cut end etc. after fixing (Timber used other than those mentioned above measured separately) IMPERIAL UNIT RATE sqr. 18,473.00

J-1

Page 34

Building Rates- 2011- NCP

J-2

Calicut tile roof (sloping to four directions) on imported treated timber framework including 100x100mm struts, 50x175mm ridge, 50x150mm hip and valley rafters, 100x75mm wall plate, 75x125mm purling, 50x100mm rafters, 50x25mm reapers including nuts and bolts and, prepare and apply one coat of wood preservative (black) to structural timber work (Timber beams measured and paid separately)

sqr.

28,906.00

Page 35

Building Rates- 2011- NCP

NO. J-3

IMPERIAL UNIT RATE Zink Alum sheet -colour- (gauge 0.47 mm, strength sqr. 16,377.00 550Mpa) roof on existing framework including necessary fasteners as per Manufacturer's Specifications

DESCRIPTION

J-4

Zink Alum Non-Colour Roofing on existing framework including necessary fasteners as per Manufacturer's Specifications Asbestos corrugated sheet fixed on existing frame with necessary bolt and nuts (single storied building) Asbestos corrugated sheet fixed on existing roof with necessary bolt and nuts (2 storied building)

sqr.

13,525.00

J-5

sqr.

8,665.00

J-6

sqr.

8,904.00

J-7

Corrugated G.I . Roofing sheet 20 BWG on class 1 timber frame work, including 50x100mm rafters at 900mm c/c and 50x50mm bearers at 900mm c/c complete with G.I. ridging, washers, hook bolts or clips including treating timber with wood preservative (sheets to have 150mm end laps and 1 1/2 corrugation side laps)

sqr.

14,102.00

Ceiling including Timber frame J-8 Asbestos ceiling -to existing rafters Asbestos ceiling fixed to existing rafters, with 50x50mm imported treated timber framework, interior beading 38x12mm and outer molding 38x38mm including prepare and apply one coat of wood preservative to structural timber work and application of one coat of Alkali resistant primer and two coats of Emulsion paint to ceiling sheets including necessary nails and screws. sqr. 18,268.00

Page 36

Building Rates- 2011- NCP

NO. J-9

DESCRIPTION Asbestos ceiling -with rafters Asbestos ceiling with 50x100mm imported timber framework at 1.2m c/c and 50x50mm imported treated timber bearer at 600mm c/c, interior beading 37x12mm and outer molding 37x37mm including prepare and apply one coat of wood preservative to structural timber work and application of one coat of Alkali resistant primer and two coats of emulsion paint to ceiling sheets including necessary nails and screws.

IMPERIAL UNIT RATE sqr. 23,750.00

J-10 Plywood ceiling - with rafters 9mm plywood flat ceiling with 50x100mm imported timber framework at 1200mm c/c and 50x50mm imported treated timber bearer at 600mm c/c, prepare and apply one coat of wood preservative to structural timber work and painting plywood sheets with two coats of varnish including necessary nails and screws.

sqr.

26,855.00

J-11 Lunumidella ceiling - to existing rafters Lunumidella slope ceiling under existing rafters with outer molding to the accepted design (All the beading and Lunumidella planks should be painted with one coat of wood sealer mixing with approved colour die and two coats of varnish) sqr. 15,569.00

J-12 Lunumidella ceiling -With rafters Lunumidella flat ceiling on 50x100mm imported timber framework at 600mm centers, with outer molding to the accepted design (All the beading and Lunumidella planks should be painted with one coat of wood sealer mixing with approved colour die and two coats of varnish)

sqr.

25,785.00

Page 37

Building Rates- 2011- NCP

NO.

DESCRIPTION Exposed rafter roof with ceiling

IMPERIAL UNIT RATE sqr. 36,993.00

J-13 Corrugated asbestos sheet roof with exposed rafter asbestos ceiling on 50x100mm imported treated timber rafters at 600mm centers and 50x50mm imported treated timber bearer and 50x25mm reapers for the joints of ceiling sheets with necessary coach screws and limpet washers, and 25x6mm beading including prepare and apply one coat of wood preservative (clear) and varnish to structural timber work and application of one coat of Alkali resistant primer and two coats of emulsion paint to ceiling sheets including touching up cut end etc. after fixing (Timber used other than those mentioned above measured separately)

J-14 Corrugated asbestos sheet roof with exposed rafter Lunumidella ceiling on 50x100mm imported treated timber rafters at 300mm c/c and 50x50mm imported treated timber bearer, with necessary coach screws and limpet washers, including prepare and apply one coat of wood preservative and varnish to structural timber work, including touching up cut end etc. after fixing Lunumidella planks should be painted with one coat of wood sealer mixing with approved colour die and two coats of varnish (Timber used other than those mentioned above measured separately)

sqr.

37,574.00

J-15 Corrugated asbestos sheet roof with exposed rafter plywood (9mm) ceiling on 2"x4" imported treated timber rafters at 2' c/c and 2"x2" imported treated timber bearer at 2' c/c with necessary coach screws and limpet washers, and 25x6mm beading prepare and apply one coat of wood preservative (clear) to structural timber work and painting plywood sheets with two coats of varnish including touching up cut end etc. after fixing (Timber used other than those mentioned above measured separately)

sqr.

38,429.00

Page 38

Building Rates- 2011- NCP

NO.

IMPERIAL UNIT RATE J-16 Calicut tile roofing (sloping to four directions) on sqr. 40,277.00 imported treated timber framework with exposed rafter asbestos ceiling including 100x100mm struts, 50x175mm ridge, 50x150mm hip and valley rafters, 100x75mm wall plate, 75x125mm purlins, 50x100mm rafters, 50x25mm reapers including nuts and bolts and 25x6mm beading including prepare and apply one coat of wood preservative prepare and apply one coat of wood preservative(clear) and varnish to structural timber work and application of one coat of Alkali resistant primer and two coats of emulsion paint to ceiling sheets (Timber beams measured and paid separately)

DESCRIPTION

Ridging J-17 Ridging, Calicut pattern bedded in cement and sand lime mortar 1:1:4 . Colour to match tiles J-18 Riding G.I. 24 BWG 450mm wide overall fixed complete J-19 Ridging with asbestos bedded in cement and sand mortar 1:4 J-20 Supply and fix Zink Alum ridging (colour) - 0.47 mm thick with necessary bolts and nuts J-21 Supply and fix Zink Alum ridging (non-colour) - 0.47 mm thick with necessary bolts and nuts Gutters & Downpipes J-22 Eaves gutter 150mm, rectangular, PVC fixed with PVC brackets with all necessary specials J-23 Down pipes, PVC fixed with wooden plug to wall including all necessary specials J-24 Supply and fix Zink Alum eave gutter (colour) - size 130x145mm, 0.47 mm thick with necessary bolts and nuts J-25 Supply and fix Zink Alum eave gutter (non-colour) - size 130x145mm, 0.47 mm thick with necessary bolts and nuts

lft.

145.00

lft. lft. lft. lft.

162.00 246.00 409.00 379.00

lft. lft.

154.00 141.00

lft.

414.00

lft.

377.00

Page 39

Building Rates- 2011- NCP

J-26 Supply and fix Zink Alum down pipes (colour) - size 100x100mm, 0.47 mm thick to wall with necessary bracket clips

lft.

339.00

Page 40

Building Rates- 2011- NCP

NO.

IMPERIAL UNIT RATE J-27 Supply and fix Zink Alum down pipes (non-colour) - size lft. 304.00 100x100mm, 0.47 mm thick to wall with necessary bracket clips J-28 Supply and fix standard Zink Alum gutter box - colour (0.47mm thick) J-29 Supply and fix standard Zink Alum gutter box - noncolour - (0.47mm thick) Valley gutter J-30 Supply and fix Aluminium valley gutter, 900mm girth bent with end laps not less than 225mm width including 20mm tongued and grooved planks laid to slope and profile on timber members no. no. 936.00 846.00

DESCRIPTION

lft.

955.00

J-31 Supply and fix Zn-Al valley gutter (Colour), on existing steel members as per Manufacturer's Specifications

lft.

377.00

J-32 Supply and fix Zn-Al valley gutter (non-colour), on existing steel members as per Manufacturer's Specifications Flashing J-33 Supplying and fixing gauge 24 GI wall flashing all complete J-34 Supplying and fixing Zn Alum wall flashing (colour) J-35 Supplying and fixing Zn Alum wall flashing (non-colour) Valance & Barge Board J-36 Barge board, Valance, facia, 20mm thick 225mm high, GINISAPU local timber fixed complete with necessary screws, preparing and painting with one coat of primer and two coats of enamel paint

lft.

348.00

lft. lft. lft.

417.00 384.00 350.00

lft.

236.00

Insulation Foil J-37 Furnishing and laying 3mm thick single side Aluminium foil J-38 Furnishing and laying 3mm thick Double side Aluminium foil J-39 Furnishing and laying gauge 17, 75x75mm Galvanized roof meshPage 41

sqr. sqr. sqr.

1,004.00 1,412.00 2,020.00

Building Rates- 2011- NCP

NO. Roof Timber

DESCRIPTION

IMPERIAL UNIT RATE lft. 304.00

J-40 Furnishing and fixing of 50x150mm Imported treated timber and apply one coat of wood preservative J-41 Furnishing and fixing of 75x100mm Imported treated timber and apply one coat of wood preservative

lft.

291.00

J-42 Furnishing and fixing of 50x100mm Imported treated timber and apply one coat of wood preservative J-43 Furnishing and fixing of 75x125mm Imported treated timber and apply one coat of wood preservative J-44 Furnishing and fixing of 100x150mm Imported treated timber and apply one coat of wood preservative J-45 Furnishing and fixing of 175x50mm Imported treated timber and apply one coat of wood preservative J-46 Furnishing and fixing of 100x200mm Imported treated timber and apply one coat of wood preservative J-47 Furnishing and fixing of 50x50mm Imported treated timber and apply one coat of wood preservative J-48 Furnishing and fixing of 50x25mm Imported treated timber and apply one coat of wood preservative J-49 Supplying and fixing of Coconut rafters 75x50mm J-50 Supplying and fixing of Coconut rafters 100x50mm J-51 Supplying and fixing 38x12mm beadings for ceiling J-52 Supplying and fixing 38x38mm molding for ceiling

lft.

188.00

lft.

388.00

lft.

785.00

lft.

485.00

lft.

968.00

lft.

92.00

lft.

51.00

lft. lft. lft. lft.

68.00 81.00 33.00 48.00

Page 42

Building Rates- 2011- NCP

NO.

DESCRIPTION

IMPERIAL UNIT RATE sqr. 6,252.00

Maintenance J-53 Corrugated G.I. sheet 24 BWG, fixed to roof, walls or fence with necessary cup washers and hook bolts or screws (timber framing paid for separately)

J-54 Leaks (up to 5 in numbers) in roofs of single storied building made good J-55 Leaks (above 5 in numbers) in roof of single storied building made good J-56 Leaks (up to 5 in numbers) in roofs of two or above storied building made good J-57 Leaks (above 5 in numbers) in roof of two or above storied building made good J-58 Leaks in corrugated sheet roof made good with bitumen washers and G.I. bolts and nuts J-59 Ridging, Calicut pattern removed and re-laid in cement mortar 1:1:4 and colour to match tile J-60 Tiles, Calicut pattern, flat supplied and laid up to 25 tiles in single storied building J-61 Tiles, Calicut pattern, flat supplied and laid above 25 tiles and up to 100 in single storied building J-62 Tiles Calicut pattern supplied and laid on roofs - single storied building J-63 Tiles Calicut pattern supplied and laid on roofs - two storied building J-64 Roof covering with Calicut pattern tiles available at site on existing timber frame. J-65 Roof covering with corrugated asbestos sheets available at site on existing timber frame with necessary roofing screws and washers. J-66 Furnishing and fixing of available timber purlins or rafters for the roof including necessary screws and nails and, application of one coat of wood preservative.

no. no. no. no. no. lft. no. no.

160.00 40.00 200.00 80.00 252.00 139.00 45.00 33.00

sqr. sqr. sqr. sqr.

3,635.00 4,115.00 1,140.00 900.00

lft.

27.00

Page 43

Building Rates- 2011- NCP

K - CAPENTER AND JOINER Rates for carpentry work shall include for: (a) (b) (c) (d) (e) (a) (b) (c) (d) (e) (a) (b) (c) NO

All Labour in framing together all work in accordance with the best practices, complete with all nece spikes, screws etc. Hoisting and fixing in position. Drilling and making good. Applying two coats of and approved wood preservative before fixing. Testing to establish properties to conformity to specification. Rates for joinery work shall include for: Framing together all works in accordance with the best practices. Nails Screws, Glue, plugs etc. Priming backs before fixing. Drilling and making goods. Rawtering all squares. Rates for Glazing shall include for: Straight cutting and grinding edges where required. External miters to polishing and leveled edges. Curving edges. DESCRIPTION

IMPERIAL UNIT RATE K-1 Supply and fix Front door, 95x70mm frame in sqft. 1,670.00 MAHOGANI and 28mm thick and sash with designs in TEAK timber (Fit panels) complete with brass furniture, 2 nos. 150mm barrel bolts and 3 nos. hinges including preparation of surface and application of two coats of Varnish

K-2 Supply and fix Front door, 95x70mm frame and 28mm thick sash with designs in MAHOGANI timber (Fit panels) complete with brass furniture, 2 nos. 150mm barrel bolts and 3 nos. hinges including preparation of surface and application of two coats of Varnish

sqft.

925.00

Page 44

Building Rates- 2011- NCP

K-3 Door or Window, ledge braced and battened with grooved and tongued joints, 95x70mm frame and 19mm to 22mm thick sashes in class 1 timber complete with brass furniture 2 nos. 150mm barrel bolts and 3 nos. hinges including preparation of surface and application of two coats of Varnish

sqft.

909.00

Page 45

Building Rates- 2011- NCP

IMPERIAL UNIT RATE K-4 Door or window glazed and / or paneled with 95x70mm sqft. 1,158.00 frame and 28mm thick sash in class 1 timber fixed complete with brass furniture, 2 nos. 150mm barrel bolts and 6 nos. hinges including preparation of surface and application of two coats of Varnish - Double sash

NO

DESCRIPTION

K-5 Supply and fix Plywood door -GINTOTA or equitant with 95x70mm frame and complete with brass furniture, 2 nos. 150mm barrel bolts and 3 nos. hinges including preparation of surface and application of two coats of Varnish

sqft.

754.00

K-6 Supply and fix PVC door with frame complete with 3 hinges and lock/barrel bolt K-7 Door or window glassed with 95x70mm frame comprising 2 no. of openable sashes with100x28mm outer frame and non-openable 125x28mm timber strips area complete with brass mongers including preparation of surface and application of two coats of varnish

sqft. sqft.

388.00 710.00

K-8 Door or windows glazed and / or paneled, sash only 28mm thick in class 1 timber with brass furniture, 2 nos. 150mm barrel bolts and 3 nos. hinges including preparation of surface and application of two coats of Varnish K-9 Supplied and fixed plywood door sash 28mm thick (GINTOTA or equitant) to the existing frame complete with brass furniture 2 nos. 150mm barrel bolts and 3 nos. hinges including preparation of surface and application of two coats of Varnish

sqft.

764.00

sqft.

433.00

K-10 Supply and fix door sash 19 to 22mm thick, ledge braced and battened with grooved and tongued joints in class 1 timber complete with brass furniture 2 nos. 6" barrel bolts and 3 nos. hinges including preparation of surface and application of two coats of Varnish

sqft.

640.00

K-11 Door frame 95x70mm class 1 timber supplied and fixed in position

sqft.

277.00

Page 46

Building Rates- 2011- NCP

K-12 Door or window sash, removing, easing and re-fixing K-13 Door or window sash easing only

no. no.

448.00 173.00

Page 47

Building Rates- 2011- NCP

NO.

DESCRIPTION

IMPERIAL UNIT RATE no. lft. no. lft. lft. sqft. 411.00 226.00 599.00 132.00 201.00 788.00

K-14 Door or window frames renewed in short length with class 1 timber K-15 Door or window, glazing bars renewed in class 1 timber K-16 Door sash, swing, removed and re-fixed in new position K-17 Louver blade 9mm thick in class 1 timber 100mm wide K-18 Louver blade 9mm thick in class 1 timber 150mm wide K-19 Wicket gate at entrance 1050x900mm double hinge fittings to include 2 pairs of 25x63mm butt hinges and 100mm iron barrel bolts post and sash with 40x40x5mm angle iron and 50mm SWG 10 welded mesh complete with 2 coats of anticorrosive paint

K-20 Glass panes 3 mm thick supplied and fixed with class 1 timber beading K-21 Glass panes 5 mm thick supplied and fixed with class 1 timber beading K-22 Beading or filleting for glass panes fixed complete with brass panel pins (with class 1 timber) K-23 Door or window frame altered, existing, rebate fillets using class 1 timber with screws and sash re-hung on opposite side K-24 Supplying and fix mortise lock - Union 678-24-95CH or equivalent, with 5 years guarantee. (guarantee certificate should be submitted with bills)

sqft. sqft. lft.

223.00 328.00 14.00

no.

3,245.00

no.

5,697.00

K-25 Supplying and fix switch lock - Bird or equivalent Iron furniture K-26 Supply and fix barrel bolt 100mm - Iron with brass screws K-27 Supply and fix barrel bolt 75mm - Iron with brass screws K-28 Supply and fix Hasp and staples 100mm - Iron with brass screwsPage 48

no.

2,271.00

no. no. no.

257.00 214.00 194.00

Building Rates- 2011- NCP

K-29 Supply and fix Hasp and staples 150mm - Iron with brass screws

no.

311.00

Page 49

Building Rates- 2011- NCP

NO.

DESCRIPTION with brass heavy

IMPERIAL UNIT RATE no. no. no. no. no. 211.00 280.00 4,866.00 643.00 717.00

K-30 Supply and fix Casement fasteners - Iron screws

K-31 Supply and fix Casement stays, 250mm - Iron quality with brass screws

K-32 Supply and fix door closer approved type with brass screws K-33 Supply and fix Butt Hinge, 100mm - Iron with brass screws K-34 Supply and fix Butt Hinge, 125mm - Iron with brass screws Brass Furniture K-35 Supply and fix Barrel bolts 150mm - brass, heavy quality with brass screws K-36 Supply and fix Casement fasteners -brass with mortise plate, heavy quality with brass screws K-37 Supply and fix Casement stays, 250mm - brass heavy quality with brass screws K-38 Supply and fix Butt Hinge, 100mm - brass heavy quality with brass screws K-39 Bolts, casement fasteners or stays removed and refixed including making good to holes in frames and sashes

no. no.

399.00 387.00

no. no. no.

344.00 601.00 87.00

Page 50

Building Rates- 2011- NCP

L - IRON WORK Rates for Metal work shall include for: To make good ground at balusters on completion. Welding where necessary. Wire brush and clean metal surfaces prior to painting. All fabricating work handling, hosting, fitting and fixing in position. Preparing surfaces and painting as specified or directed. DESCRIPTION IMPERIAL UNIT RATE sqft. 570.00

(a) (b) (c) (d) (e) NO.

L-1 Supply and fix Iron grill with 20x6 mm flat iron outer frame and horizontal bracings at 300 mm intervals complete with 12x6 mm flat iron verticals at 75 mm c/c as per given design including two coats of anticorrosive paint and enamel paint

L-2 Iron grill with 6 mm mild steel rods welded diagonally at 100 mm cts. both way and outer frame with 20x6 mm flat iron fabricated and fixed complete including two coats of anticorrosive paint and enamel paint.

sqft.

471.00

L-3 50x50mm G.I weld mesh fixed to existing frame with staple including painting (Beading paid separately)

sqft.

132.00

L-4 50x50mm G.I weld mesh supplied and fixed to window frame with 50x6mm class 1 timber beadings and, painted weld mesh with 2 coats of anticorrosive paint and beading with primer coat and 2 coats of enamel paint including making opening for bolts and casement stays

sqft.

296.00

L-5 50x50mm G.I weld mesh fixed to 40x40x5mm angle iron frame fabricated and fixed to wall with rawl plugs and screws including painting with enamel paint and anticorrosive paint

sqft.

347.00

Page 51

Building Rates- 2011- NCP

L-6 Supply and fix gate with Zink Alum gate clad sheet (colour) with 30mm heavy duty GI pipe frame work, 20mm heavy duty squire tube bitterns and vertical members at the top, including application of two coats of anticorrosive primer and finishing coat of enamel paint complete with stap hinges, hasp and staples as per given design

sqft.

523.00

Page 52

Building Rates- 2011- NCP

NO.

IMPERIAL UNIT RATE L-7 Supply and place in position steel roof truss (WEB) - span no 41,340.00 4.5-6.0 lm - complete with double member exterior and single member interior, 6mm gusset plate, 16mm dia. rag bolts, 6mm base plate welded and application of two coats of anti-corrosive paint all as per detail drawing given by the Department

DESCRIPTION

L-8 Supply and place in position steel roof truss (WEB) - span 6.5-7.5 lm - complete with double member exterior and single member interior, 6mm gusset plate, 16mm dia. rag bolts, 6mm base plate welded and application of two coats of anti-corrosive paint all as per detail drawing given by the Department

no.

49,019.00

L-9 Supply and place in position steel roof truss (WEB) - span 8.0-9.0 lm - complete with double member exterior and single member interior, 6mm gusset plate, 16mm dia. rag bolts, 6mm base plate welded and application of two coats of anti-corrosive paint all as per detail drawing given by the Department

no.

65,205.00

L-10 Supply and place in position steel roof truss (FLAT) - span 4.5-6.0 lm - complete with double member exterior and single member interior, 6mm gusset plate, 16mm dia. rag bolts, 6mm base plate welded and application of two coats of anti-corrosive paint all as per detail drawing given by the Department

no

47,325.00

L-11 Supply and place in position steel roof truss (FLAT) - span 6.5-7.5 lm - complete with double member exterior and single member interior, 6mm gusset plate, 16mm dia. rag bolts, 6mm base plate welded and application of two coats of anti-corrosive paint all as per detail drawing given by the Department

no.

64,906.00

L-12 Supply and place in position steel roof truss (FLAT) - span 8.0-9.0 lm - complete with double member exterior and single member interior, 6mm gusset plate, 16mm dia. rag bolts, 6mm base plate welded and application of two coats of anti-corrosive paint all as per detail drawing given by the Department

no.

71,663.00

Page 53

Building Rates- 2011- NCP

IMPERIAL UNIT RATE L-13 Supplying and fixing Angle iron purling 40x40x5mm to lft. 197.00 trusses with 10 mm dia. bolts and nuts including application of anticorrosive paint

NO.

DESCRIPTION

L-14 Supplying and fixing Angle iron purling 50x50x5mm to trusses with 10mm dia. bolts and nuts including application of anticorrosive paint

lft.

191.00

L-15 Supplying and fixing Angle iron purling 65x65x5mm to trusses with 10mm dia. bolts and nuts including application of anticorrosive paint

lft.

283.00

L-16 Supplying and fixing End rafters, 50x50x5mm (double) angle iron on gable ends with purling cleats including application of anticorrosive paint L-17 Furnishing and fixing 100x50mm (Thickness-2mm) CPurlins as per Manufacturer's Specifications L-18 Furnishing and fixing 150x65mm (Thickness - 2mm) CPurlins as per Manufacturer's Specifications L-19 Furnishing and fixing 75x38mm (Thickness - 2mm) CPurlins as per Manufacturer's Specifications

lft.

639.00

lft.

311.00

lft.

449.00

lft.

260.00

Page 54

Building Rates- 2011- NCP

M - PAINTER AND DECORATOR Rates for painting shall include for: (a) (b) (c) (d) (e) (f) (g) (h) NO. Preparation of surfaces, cleaning down. Smoothing, knotting, stopping etc. Protecting floors and fittings etc. Removing and replacing doors furniture and cleaning upon completion. Providing samples and specification of all paints to be used in the works. Providing painting to an approved colour scheme design. All the paints are to be done up to the manufacturers specification.

Preparation sample panels of different finishes for the approval of the Engineer. Each panel not less than area. DESCRIPTION

IMPERIAL UNIT RATE M-1 Prepare and apply one coat of Alkali resistant primer and sqr. 2,346.00 two coats of emulsion paint to walls - up to first floor level M-2 Prepare and apply one coat of Alkali resistant primer and two coats of emulsion paint to walls - up to second floor level M-3 Prepare and apply one coat of Alkali resistant primer and two coats of emulsion paint to walls - up to third floor level M-4 Prepare and apply one coat of Alkali resistant primer and two coats of emulsion paint soffit of slabs - up to first floor level M-5 Prepare and apply one coat of Alkali resistant primer and two coats of emulsion paint to soffit of slabs - up to second floor level M-6 Prepare and apply one coat of Alkali resistant primer and two coats of emulsion paint to soffit of slabs - up to third floor level M-7 Prepare and apply one coat of Acrylic wall filler and two coats of weather proof white and colour paint - up to first floor level M-8 Prepare and apply one coat of Acrylic wall filler and two coats of weather proof white and colour paint - up to second floor level sqr. 2,594.00

sqr.

2,841.00

sqr.

2,413.00

sqr.

2,660.00

sqr.

2,884.00

sqr.

2,785.00

sqr.

3,033.00

Page 55

Building Rates- 2011- NCP

M-9 Prepare and apply one coat of Acrylic wall filler and two coats of weather proof white and colour paint - up to third floor level

sqr.

3,280.00

Page 56

Building Rates- 2011- NCP

IMPERIAL UNIT RATE M-10 Prepare and apply one coat of Acrylic wall filler and two sqr. 3,060.00 coats of bathroom paint, white and colour paint - up to first floor level M-11 Prepare and apply one coat of Acrylic wall filler and two coats of bathroom paint, white and colour paint - up to second floor level M-12 Prepare and apply one coat of Acrylic wall filler and two coats of bathroom paint, white and colour paint - up to third floor level M-13 Prepare and apply two coats of floor paint, red, gray or black M-14 Prepare and apply one coat of wood preservative to structural timber work, including touching up cut end etc. after fixing M-15 Varnishing two coats after sand papering of the surface M-16 Preparing and painting wood work with primer and two coats of enamel paint M-17 Painting aluminum paint 1 coat to metal surfaces M-18 Painting steel on new work with 2 coats of anti-corrosive paint M-19 Painting walls with Emulsion paint, 2 coats, including preparation of surface M-20 Painting Ceiling with 2 coats of Emulsion paint to the ceiling sheets and 2 coats of enamal paint to timber beadings including preparation of surface sqr. 3,307.00

NO.

DESCRIPTION

sqr.

3,554.00

sqr. sqr.

2,469.00 2,057.00

sqr. sqr. sqr. sqr. sqr. sqr.

2,289.00 3,229.00 1,217.00 2,078.00 2,198.00 2,364.00

M-21 Painting walls with Weather shield paint, 2 coats, including preparation of surface M-22 Wall, scraped to original plaster, sand papering and lime putting to cracks and defects, applying plaster of Paris and preparing surface for new or similar application of emulsion, snowcem or similar application

sqr.

2,499.00

sqr.

2,046.00

M-23 Preparing and painting wood work with 2 coats of enamel paint. M-24 White or colour washing two coats to walls with SAMARAPage 57

sqr. sqr.

2,580.00 642.00

Building Rates- 2011- NCP

M-25 Water - Proofing of Bathrooms with approved materials as per Instructions

sqr.

3,050.00

Page 58

Building Rates- 2011- NCP

N - PLUMBER Rates for Plumbing shall include for: (a)

Excavation of trenches for services, pipes or drain pipes shall include for deepening and widening as n enable the barrels of pipes, ducts etc. to rest on firm ground and to facilitate jointing . Testing installations on completion. Chasing in brickwork / block work / concrete floor / concrete columns and make good. Fixing pipes to brickwork / block work. Solder rivets, screws, nails, clips, brackets, straps etc. Testing installations on completion. Sterilization, of Drinking water pipes on completion. FIXTURES, APPLIANCES AND EQUIPMENT Rates for sanitary fixtures shall include for:

(b) (c) (d) (e) (f) (g)

(a) (b) (c) (a) (b) (c) (d) NO.

Installation complete with plugs. Grated waste outlets. Brackets and all fixings including jointing to pipes. Instructions Prior approval from the architect should be taken for all the sanitary fittings and accessories.

Guarantee certificates of fittings should be submitted to the Department with the bills. No payment is d bills.

All the UPVC pipes to be SLS certified products. Some trade names are used only for the purpose of indicating the minimum level of quality and standards DESCRIPTION lft. lft. lft. lft. lft. lft. no. IMPERIAL UNIT RATE 26.00 60.00 86.00 96.00 120.00 161.00 921.00

N-1 Supply and lay PVC Pipe 20mm - type 1000 including all necessary fittings N-2 Supply and lay PVC Pipe 25mm - type 1000 including all necessary fittings N-3 Supply and lay PVC Pipe 32mm - type 1000 including all necessary fittings N-4 Supply and lay PVC Pipe 40mm - type 600 including all necessary fittings N-5 Supply and lay PVC Pipe 50mm - type 600 including all necessary fittings N-6 Supply and lay PVC Pipe 63mm - type 400 including all necessary fittings N-7 Supply and fix Ball valve PEGLER or equivalent - for overhead tanks - 20mm - all complete

Page 59

Building Rates- 2011- NCP

NO.

DESCRIPTION no.

IMPERIAL UNIT RATE 1,161.00

N-8 Supply and fix Ball valve PEGLER or equivalent - for overhead tanks - 25mm - all complete N-9 Supply and lay 110mm drainage pipe PVC - special for drainage - with necessary fittings complete N-10 Wash basin, ceramic, with pedestal (Chinese made) with 15 years guarantee complete with mono type, chromium plated basin tap - (Momali, Huai or equivalent) - with 5 years guarantee including all necessary fittings (Guarantee certificates should be submitted with the bill)

lft.

200.00

no.

12,774.00

N-11 Supply and fix closet, closed couple, Chinese made with 15 years guarantee complete with hard seat cover and all necessary fittings.(Guarantee certificate should be submitted with the bill)

no.

17,220.00

N-12 Supply and fix 2 PC set, closed couple with hard seat cover, (Chinese made) with 15 years guarantee complete with mono type, chromium plated basin tap - (Momali, Huai or equivalent) - with 5 years guarantee with all necessary fittings.(Guarantee certificate should be submitted with the bill)

no.

26,874.00

N-13 Supply and fix Closet Squatting type (Indian) with foot rest ceramic, medium, with trap

no.

5,400.00

Page 60

Building Rates- 2011- NCP

NO.

DESCRIPTION

IMPERIAL UNIT RATE no. 8,718.00

N-14 Supply and fix stainless steel kitchen Sink, PRINCE or equivalent - with single bawl, one side drain board including chromium plated long neck type sink tap Momali, Huai or equivalent - with 5 years guarantee complete with all necessary fittings - (overall size 900x450mm) - (Guarantee certificate should be submitted with the bill)

N-15 Supply and fix stainless steel kitchen Sink, PRINCE or equivalent with single bawl, without drain board including chromium plated long neck type sink tap Momali, Huai or equivalent - with 5 years guarantee complete with all necessary fittings (overall size 450x375mm) - (Guarantee certificate should be submitted with the bill)

no.

6,162.00

N-16 Supply and fix Ceramic Sink, 24"x15"x7" complete with mono type, chromium plated long neck type sink tap (Momali, Huai or equivalent) - with 5 years guarantee including all necessary fittings (Guarantee certificates should be submitted with the bill)

no.

8,772.00

N-17 Supply and fix corner wash basin complete with mono type, chromium plated basin tap - (Momali, Huai or equivalent) - with 5 years guarantee including all necessary fittings N-18 Supply and fix bidet spray - (Momali, Huai or equivalent) - with 5 years guarantee with all necessities. (Guarantee certificate should be submitted with the bill)

no.

6,384.00

no.

1,983.00

N-19 Supply and fix Urinal bawl type N-20 Supply and fix bath room accessories set (chromium plated with 5 years guarantee) - 4 pcs. (mirror, mirror shelf, towel bar and soap holder) all complete

no. no.

4,470.00 10,590.00

N-21 Supply and fix bath room accessories set (chromium plated with 5 years guarantee) - 6 pcs. (mirror, mirror shelf, towel bar, soap holder, tooth brush holder and toilet paper holder) all complete

no.

13,890.00

Page 61

Building Rates- 2011- NCP

N-22 Supply and fix Mirror, bathroom type, oval shape, 20" x 16" with plastic back and shelves

no.

2,460.00

Page 62

Building Rates- 2011- NCP

NO.

DESCRIPTION

N-23 Supply and fix Plastic Shower rose, with guarantee N-24 Supply and fix head shower, chromium plated heavy with 5 years guarantee N-25 Supply and fix Telephone shower with bar, chromium plated heavy with 5 years guarantee including flexible cable N-26 Supply and fix Soap tray, chromium plated (Chinese), (Momali, Huai or equivalent) with 5 year guarantee (Guarantee certificate should be submitted with the bill)

IMPERIAL UNIT RATE no. 203.00 no. 2,436.00

no.

5,142.00

no.

2,733.00

N-27 Supply and fix towel bar, chromium plated - (Momali, Huai or equivalent) - with 5 year guarantee (Guarantee certificate should be submitted with the bill)

no.

2,865.00

N-28 Supply and fix concealed stop cock - Mono type (Momali, Huai or equivalent) with 5 years guarantee (Guarantee certificate should be submitted with the bill)

no.

2,181.00

N-29 Supply and fix Angle valve (Momali, Huai or equivalent) with 5 years guarantee (Guarantee certificate should be submitted with the bill) N-30 Supply and fix Long neck type Sink tap, chromium plated - (Momali, Huai or equivalent) - with 5 years guarantee (Guarantee certificate should be submitted with the bill)

no.

1,515.00

no.

2,547.00

N-31 Supply and fix bib tap 20mm dia. - (Momali, Huai or equivalent) - with 5 years guarantee (Guarantee certificate should be submitted with the bill)

no.

1,695.00

N-32 Supply and fix 20mm dia. plastic Bib tap - Water Tec or equivalent - all complete N-33 Supply and fix stop cock/gate valve PVC Water Tec or equitant with SLS standards - 20mm dia.

no. no.

399.00 351.00

Page 63

Building Rates- 2011- NCP

N-34 Supply and fix stop cock/gate valve PVC Water Tec or equitant with SLS standards - 25mm dia.

no.

397.00

Page 64

Building Rates- 2011- NCP

IMPERIAL UNIT RATE N-35 Supply and fix stop cock/gate valve PVC Water Tec or no. 508.00 equitant with SLS standards - 32mm dia. N-36 Supply and fix stop cock/gate valve PVC Water Tec or equivalent with SLS standards - 40mm dia. N-37 Plastic shell water tank with 10 years guarantee of capacity 500 ltr. Including transporting, placing in position and fixing to the accepted Engineering standards N-38 Plastic shell water tank with 10 years guarantee of capacity 1000 ltr. Including transporting, placing in position and fixing to the accepted Engineering standards no. 417.00

NO.

DESCRIPTION

no.

13,920.00

no.

20,040.00

N-39 Plastic shell water tank with 10 years guarantee of capacity 2000 ltr. Including transporting, placing in position and fixing to the accepted Engineering standards N-40 Plastic shell water tank with 10 years guarantee of capacity 5000 ltr. Including transporting, placing in position and fixing to the accepted Engineering standards

no.

31,772.00

no.

66,840.00

N-41 Supply and fix Cover and seat for WC - plastic N-42 Supply and fix Chromium plated flexible cable (Momali, Huai or equivalent) N-43 Flushing cistern, plastic low level, with flush pipe and bracket supplied and fixed complete N-44 Closet, pedestal type, available at site fixed with cement concrete after breaking concrete floor and making good and making connection N-45 Supply and fix PVC specials with SLS standards - 20mm dia. (Elbow, Bend, Socket) N-46 Supply and fix PVC specials with SLS standards - 25mm dia. (Elbow, Bend, Socket) N-47 Supply and fix PVC specials with SLS standards - 32mm dia. (Elbow, Bend, Socket)

no. no. no. no.

1,590.00 906.00 6,660.00 1,835.00

no.

104.00

no.

111.00

no.

127.00

Page 65

Building Rates- 2011- NCP

N-48 Supply and fix PVC specials with SLS standards - 40mm dia. (Elbow, Bend, Socket)

no.

152.00

Page 66

Building Rates- 2011- NCP

IMPERIAL UNIT RATE N-49 Supply and fix PVC specials with SLS standards - 50mm no. 197.00 dia. (Elbow, Bend, Socket) N-50 Supply and fix PVC specials with SLS standards - 63mm dia. (Elbow, Bend, Socket) N-51 Supply and fix PVC specials with SLS standards - 20mm dia. Tees N-52 Supply and fix PVC specials with SLS standards - 25mm dia. Tees N-53 Supply and fix PVC specials with SLS standards - 32mm dia. Tees N-54 Supply and fix PVC specials with SLS standards - 40mm dia. Tees N-55 Supply and fix PVC specials with SLS standards - 50mm dia.Tees N-56 Supply and fix PVC specials with SLS standards - 63mm dia. Tees O - DRAINLAYER Rates for underground drainage shall include for: (a) (b) (c) (d) NO. Short lengths, joints and cutting at Manholes. Cutting and fixing pipe work to fittings. Testing. Grading to slopes and falls. DESCRIPTION IMPERIAL UNIT RATE Item 1,442.00 lft. 476.00 no. 270.00

NO.

DESCRIPTION

no. no. no. no. no. no.

79.00 106.00 126.00 163.00 215.00 298.00

O-1 Connection to existing sewer or manhole O-2 Drainage pipe 110mmdia. (type 400) PVC laid on cement concrete 150mm up to 600mm depth of invert including excavation and cement concrete hunching 1:3:6 (40mm)

O-3 Furnishing and fixing of Multi-floor trap including 150mm plastic grating

no.

1,510.00

Page 67

Building Rates- 2011- NCP

O-4 Gulley pit with internal dimension 300x300x300mm deep, 150mm thick 1:3:6(40mm) concrete foundation, 225mm thick brick work in 1:5 ct. sand, 12mm thick cement sand rendering in 1:2 with forming canals and 75mm thick R.C.C. slab as per Drawings

no.

4,205.00

Page 68

Building Rates- 2011- NCP

NO.

IMPERIAL UNIT RATE O-5 Manhole with internal dimension 450x450x600mm deep, no. 9,400.00 150mm thick 1:3:6(40mm) concrete foundation, 225mm thick brick work in 1:5 ct. sand, 12mm thick cement sand rendering in 1:2 with forming cannels and 75mm thick R.C.C. slab as per Drawings

DESCRIPTION

O-6 Manhole with internal dimension 600x600x600mm deep, 150mm thick 1:3:6(40mm) concrete foundation, 225mm thick brick work in 1:5 ct. sand, 12mm thick cement sand rendering in 1:2 with forming canals and 75mm thick R.C.C. slab as per Drawings

no.

12,474.00

O-7 Manhole with internal dimension 750x750x600mm deep, 150mm thick 1:3:6(40mm) concrete foundation, 225mm thick brick work in 1:5 ct. sand, 12mm thick cement sand rendering in 1:2 with forming canals and steel grating with 16mm dia. MS rod welded at 50mm centers to 25 x 25 x 5 mm angle iron frame including application of anticorrosive paint.

no.

16,837.00

O-8 Septic tank with internal dimensions 2325x900x2100mm, partition with same wall, all complete including excavation, 100mm thick base slab with 1:3:6 (40mm), 225mm brick work, 20mm thick 1:3 cement rendering including 75mm cover slab with 10mm bars at 225mm c/c both way and 63mm vent pipe. (Refer relevant Drawings) - for 30 persons

no.

78,499.00

O-9 Septic tank with internal dimensions 3225x900x2100, partition with same wall, all complete including excavation, 100mm thick Base slab with 1:3:6 (40mm), 225mm brick work, 20mm 1:3 cement rendering including 75mm cover slab with 10mm bars at 225mm c/c both way and 63mm vent pipe. (Refer relevant Drawings) - for 60 persons

no.

97,711.00

Page 69

Building Rates- 2011- NCP

NO.

DESCRIPTION

IMPERIAL UNIT RATE122,592.00

O-10 Septic tank with internal dimensions 4125x1050x2100mm, partition with same wall, all complete including excavation, 100mm thick Base slab with 1:3:6 (40mm), 225mm brick work, 20mm thick 1:3 cement rendering including 75mm cover slab with 10mm bars at 225mm c/c both way and 63mm vent pipe. (Refer relevant Drawings) - for 100 persons

no.

O-11 Soakage pit with internal dia. 1200mm and depth 1500mm, all complete including excavation, ring beam with 4 Nos. 10 mm bars & 6 mm dia. stirrups at 225mm spacing at bottom of wall, 225mm brick work and 75mm thick cover slab with 12mm bars in 150mm c/c both way (as per detail drawing)

no.

74,538.00

O-12 Soakage pit with internal dia. 1200mm and depth 3000mm, all complete including excavation, ring beam with 4 Nos. 10 mm bars & 6 mm dia. stirrups at 225mm spacing at bottom of wall, 225mm brick work and 75mm thick cover slab with 12mm bars in 150mm c/c both way (as per detail drawing)

no.

126,153.00

O-13 Supply and fix 900x2400mm ready made RCC septic tank

no.

31,148.00

Page 70

Building Rates- 2011- NCP

P - ELECTRICAL INSTALLATION Rates for Electrical Installations shall include for: (a) (b) (c) (d) (e) (f) (a) (b) (c) (d) (e) All necessary conduits, cables, fittings, screws, nails clips, brackets straps, and the like. Giving notices, obtaining permits, paying fees etc. Provision of drawings or circuit diagrams etc. Labeling switch and switches or other fittings.

Providing samples of switches or other fittings. Earthening and testing installation as required. Instructions Before conduit pipes are laid on concrete floor slabs, a conduit layout drawing shall be prepared by th for the approval of consultant. All electrical installation shall be for 400 volts / 230 volts 50 Hz. 5 Amp final sub-circuits shall be carried out by the looping-in method. No joints are permitted in the runs of cables. Fixing heights from finished floor level, unless directed otherwise shall be as follows, Main switches (switch fuses) - 1.5 m Lamp fittings - 2.4 m Distribution boards - 1.7 m Ceiling fans - 2.5 m - 0.2 m

(f) (g) (h) (i) NO. P-1

Switches and fan regulators - 1.4 m Socket outlets Current operated ELCBs. Earth resistance shall be less than 5 Ohms, tested on a dry day. All fan regulators to be earthen.

Some trade names are used only for the purpose of indicating the minimum level of quality and standards IMPERIAL UNIT RATE Supply and install Earth electrode G.I. Pipe 50mm Dia. no. 1,737.00 heavy duty, 600mm long fixed on ground with connection Supply and install 65x65x6 mm angle iron, service bracket, D bracket and Insulator with necessary nuts and bolts for main wire fixed to wall or roof frame - Single Phase Supply and install 65x65x6 mm angle iron, service bracket, D bracket and Insulator with necessary nuts and bolts for main wire fixed to wall or roof frame - Three Phase Supply and fix 7/1.35 mm main wire - (Double) no. 3,524.00 DESCRIPTION

P-2

P-3

no.

4,766.00

P-4

lft.

311.00

Page 71

Building Rates- 2011- NCP

P-5

Supply install MCB 6 way, 40A, 2 pole Isolator, 40A ELCB 2-pole and box fixed with 7/1.35mm single core cable - Single Phase

no.

7,800.00

Page 72

Building Rates- 2011- NCP

NO. P-6

IMPERIAL UNIT RATE Supply install MCB 8 way, 40A, 2 pole Isolator, 40A no. 8,673.00 ELCB 2-pole and box fixed with 7/1.35mm single core cable - Single Phase Supply install MCB 10 way, 40A, 2 pole Isolator, 40A ELCB 2-pole and box fixed with 7/1.35mm single core cable - Single Phase Supply install MCB 6 way, 63A, 4 pole Isolator, 63A ELCB 4-pole and box fixed with 7/1.35mm single core cable - Three Phase Supply install MCB 8 way, 63A, 4 pole Isolator, 63A ELCB 4-pole and box fixed with 7/1.35mm single core cable - Three Phase no. 9,606.00

DESCRIPTION

P-7

P-8

no.

22,859.00

P-9

no.

25,478.00

P-10 Supply install MCB 10 way, 63A. 4 pole Isolator, 63A ELCB 4-pole and box fixed with 7/1.35mm single core cable - Three Phase P-11 Supply and install Electric bell and bell push complete with necessary wiring P-12 Supply and install Ceiling fan 56",(230V, 80W) KDK or equivalent with SLS certificate complete with regulator and other fittings P-13 Supply and install Wall fan 16" all complete P-14 Supply and install Exhaust fan all complete P-15 Supply and install Florescent lamp 20W, 600mm single, with plastic cover including switch and necessary wiring P-16 Supply and install Florescent lamp 40W, 1200mm single, with plastic cover including switch and necessary wiring

no.

28,097.00

no. no.

2,935.00 10,801.00

no. no. no.

8,532.00 6,240.00 3,287.00

no.

3,437.00

P-17 Supply and install Florescent lamp 40W, 1200mm, double, with plastic cover including switch and necessary wiring P-18 Supply and install Ceiling lamp barrel type, dia. 150mm - including switch and necessary wiring

no.

4,607.00

no.

4,196.00

Page 73

Building Rates- 2011- NCP

P-19 Supply and install Batten lamp necessary wiring

including switch and

no.

1,962.00

Page 74

Building Rates- 2011- NCP

IMPERIAL UNIT RATE P-20 Supply and install Pendent lamp including switch and no. 2,092.00 necessary wiring P-21 Supply and install CFL bulb - 20w ( spiral or globe) - with guarantee - including switch and necessary wiring P-22 Supply and install Wall lamp bracket type with single glass globe including switch and necessary wiring P-23 Supply and install 5A Switch Socket outlet including necessary wiring P-24 Supply and install 13A Switch Socket outlet including necessary wiring P-25 Supply and install 15A Switch Socket outlet including necessary wiring P-26 Replacing lamp holders P-27 Replacing Florescent lamp 1200mm with shade P-28 Replacing florescent lamp 600mm with plastic shade P-29 Replacing 1/1.13 mm cables P-30 Replacing 7/1.35 mm Cables P-31 Conduit PVC - 3/4" laid in brick or con. Walls AC MACHINES P-32 Supply and install wall mounted AC machine split type 9000 btu - LG or equivalent - with one year guarantee to all and five year guarantee for compressor including free service P-33 Supply and install wall mounted AC machine split type 12000 btu - LG or equivalent - with one year guarantee to all and five year guarantee for compressor including free service P-34 Supply and install wall mounted AC machine split type 18000 btu - LG or equivalent - with one year guarantee to all and five year guarantee for compressor including free service no. 2,576.00

NO.

DESCRIPTION

no.

2,425.00

no. no. no. no. no. no. lft. lft. lft.

3,058.00 3,844.00 4,298.00 71.00 1,211.00 1,091.00 19.00 103.00 76.00

no.

72,490.00

no.

90,090.00

no.

104,390.00

Page 75

Building Rates- 2011- NCP

P-35 Supply and install wall mounted AC machine split type 24000 btu - LG or equivalent - with one year guarantee to all and five year guarantee for compressor including free service

no.

131,890.00

Page 76

Building Rates- 2011- NCP

Q - MISCELLANEOUS Instructions Prior approval for the type of barbed wire should be taken from the Engineer before using. DESCRIPTION

(a) NO.

IMPERIAL UNIT RATE Q-1 Barbed wire fence on concrete posts - (height 1800mm) - lft. 247.00 reinforced with 4 nos. 6mm bars, 2 supports on corner posts, 2 supports for mid of every 6 intervals and 7 nos. wire lines to the accepted Engineering standard. (Posts should be fixed on a concrete pad of 300x300x450mm) Distance between two posts 2400-3000mm

Q-2 Barbed wire fence on concrete posts - (height 2400mm) reinforced with 4 nos. 6mm bars, 2 supports on corner posts, 2 supports for mid of every 6 intervals and 9 nos. wire lines to the accepted Engineering standard. (Posts should be fixed on a concrete pad of 300x300x450mm) Distance between two posts 2400-3000mm

lft.

321.00

Q-3 Furnishing and fixing of fence post - (height 1800 mm, on a concrete pad of 300x300x450mm, including necessary excavation to the accepted Engineering standard

no.

1,153.00

Q-4 Furnishing and fixing of fence post - (height 2400 mm), on a concrete pad of 300x300x450mm including necessary excavation to the accepted Engineering standard

no.

1,531.00

Q-5 Fixing of barbed wire lines to the existing posts with necessary hooks, bolts and nuts Q-6 Furnishing, laying and fixing 300mm dia. RCC Hume pipes with collars Q-7 Furnishing, laying and fixing 450mm dia. RCC Hume pipes with collars Q-8 Furnishing, laying and fixing 600mm dia. RCC Hume pipes with collars

lft. lft. lft. lft.

17.00 900.00 1,365.00 1,868.00

Page 77

Building Rates- 2011- NCP

R - Aluminium Work Specifications(a) All the Aluminium members used for work should have following properties 1. Temper - T