control of power systems (1)
TRANSCRIPT
-
8/13/2019 Control of Power Systems (1)
1/43
Control ofPower Systems
Prepared ByA K K Tahira Tasneem
Assistant Professor - EEE
-
8/13/2019 Control of Power Systems (1)
2/43
Outline Review of AGC and reactive power control System operating states by security control
functions Monitoring, evaluation of system state by
contingency analysis Corrective controls (Preventive, emergency and
restorative) Energy control center SCADA system Functions monitoring , Dataacquisition and controls EMS system .
-
8/13/2019 Control of Power Systems (1)
3/43
Review of AGC and reactive
power control Modern implementation of automaticgeneration control (AGC) schemes usuallyconsists of a central location whereinformation pertaining to the system istelemetered.
Control actions are determined in a digital
computer and then transmitted to thegeneration units via the same telemetrychannels.
-
8/13/2019 Control of Power Systems (1)
4/43
To implement an AGC system1. Unit megawatt output for each committed
unit.
2. Megawatt flow over each tie line toneighboring systems.3. System frequency.
-
8/13/2019 Control of Power Systems (1)
5/43
The use of digital telemetry is becomingcommonplace in modern systems whereinsupervisory control.
That is opening and closing substationbreakers, telemetry information and controlinformation (i.e) unit raise/lower is all sent viathe same channels.
-
8/13/2019 Control of Power Systems (1)
6/43
The basic reset control loop for a unit consistsof an integrator with gain K
Basic generation control loop.
-
8/13/2019 Control of Power Systems (1)
7/43
-
8/13/2019 Control of Power Systems (1)
8/43ACE calculation.
-
8/13/2019 Control of Power Systems (1)
9/43Overview of AGC logic.
-
8/13/2019 Control of Power Systems (1)
10/43
AGC Features
Assist action Filtering of ACE Telemetry failure logic Unit control detection Ramp control Rate limiting Unit control modes
-
8/13/2019 Control of Power Systems (1)
11/43
-
8/13/2019 Control of Power Systems (1)
12/43
Normal
EmergencyExtremis
AlertRestorative
Restart
Resynchronisation
Preventive Control
Emergency Control
E,I
,I E,I
E , ,
E Equality Constraint: I Inequality Constraints and - Negation
-
8/13/2019 Control of Power Systems (1)
13/43
Normal State The system is, for most of the time, in its
normal state. Frequency and Voltages are kept at rated or
prescribed values.
Real and Reactive power demanded by theloads match with the output of sources. E Equality
I
Inequality
Loading of generators,transformers or transmission line is with intheir rating or capacity limits.
-
8/13/2019 Control of Power Systems (1)
14/43
Alert State
If the capacity margin below the thresholdvalue or if a disturbance occurs, the securitylevel is reduced and the system enters alertstate.
All equalities and inequalities aremaintained.
The system operates fully synchronized. Preventive control actions need to be
initiated to restore reserve margin.
-
8/13/2019 Control of Power Systems (1)
15/43
Emergency State Second contingency occurs before
preventive action is effected. It may reached directly from normal state,
if the original disturbance is more severe. The generation still tracks the load and the
system remains synchronized. It is most urgent that the system be
returned to a normal or at least alert state.
-
8/13/2019 Control of Power Systems (1)
16/43
-
8/13/2019 Control of Power Systems (1)
17/43
Contingency Analysis To predict the effect of outages, contingency
analysis techniques are used.
Single line failure, multiple equipmentfailure and all possible outages are studied.
-
8/13/2019 Control of Power Systems (1)
18/43
-
8/13/2019 Control of Power Systems (1)
19/43
Energy Control Centers
The energy control center (ECC) hastraditionally been the decision-center for the
electric transmission and generationinterconnected system. Minute-by-minute physical and economic
operation of the power system.
-
8/13/2019 Control of Power Systems (1)
20/43
In the continental U.S., there are only three
interconnected regions:1. Eastern,2. Western, and
3. Texas, But there are many control areas , with each
control area having its own ECC.
-
8/13/2019 Control of Power Systems (1)
21/43
Maintaining integrity and economy of aninter-connected power system requiressignificant coordinated decision-making.
So one of the primary functions of the ECCis to monitor and regulate the physicaloperation of the interconnected grid.
Two-level hierarchy of ECCs Independent System Operator (ISO) - high-
level decision-making. The transmission owner ECC - lower-level
decision-making.
-
8/13/2019 Control of Power Systems (1)
22/43
High-level view of the ECC
27
Substation
Remoteterminalunit
SCADA Master Station
C o m m u n i c a t
i o n
l i n
k
Energy control center with EMS
EMS alarm displayEMS 1-line diagram
ECC C t
-
8/13/2019 Control of Power Systems (1)
23/43
ECC Components
SCADA
Overloads &Voltage Problems
PotentialOverloads &
Voltage Problems
Breaker/Switch StatusIndications
System Model Description
Telemetry &Communications equipment
StateEstimator
NetworkTopology
program
AGC
EconomicDispatch
Calculation
OPF
ContingencySelection
Contingency AnalysisSecurityConstrained OPF
Display Alarms
Updated SystemElectrical Model
Analog Measurements
Display to Operator
Power flows,Voltages etc.,
Display to Operator
Bad MeasurementAlarms
Generator OutputsGenerationRaise/Lower Signals
State EstimatorOutput
SubstationRTUs
-
8/13/2019 Control of Power Systems (1)
24/43
The system control function traditionally used inelectric utility operation consists of three mainintegrated subsystems:
The energy management system (EMS)
The supervisory control and data acquisition(SCADA), and
The communications interconnecting the EMSand the SCADA.
-
8/13/2019 Control of Power Systems (1)
25/43
SCADA system
Supervisory control indicates that theoperator, residing in the energy controlcenter (ECC), has the ability to controlremote equipment.
Data acquisi tion indicates that informationis gathered characterizing the state of the
remote equipment and sent to the ECC formonitoring purposes.
-
8/13/2019 Control of Power Systems (1)
26/43
A SCADA system performs four functions:1. Data acquisition
2. Networked data communication3. Data presentation4. Control
-
8/13/2019 Control of Power Systems (1)
27/43
These functions are performed by four kinds of SCADAcomponents:
1. Sensors (either digital or analogue) and control relays thatdirectly interface with the managed system.
2. Remote telemetry units (RTUs). These are smallcomputerized units deployed in the field at specific sites andlocations. RTUs serve as local collection points for gatheringreports from sensors and delivering commands to controlrelays.
3. SCADA master units. These are larger computer consolesthat serve as the central processor for the SCADA system.Master units provide a human interface to the system andautomatically regulate the managed system in response tosensor inputs.
4. The communications network that connects the SCADAmaster unit to the RTUs in the field.
-
8/13/2019 Control of Power Systems (1)
28/43
The monitoring equipment is normally locatedin the substations and is consolidated in theremote terminal unit (RTU).
The RTUs are equipped with microprocessorshaving memory and logic capability.
Newer RTUs generally have intranet orinternet capability.
Relays located within the RTU, on command
from the ECC, open or close selected controlcircuits to perform a supervisory action.
-
8/13/2019 Control of Power Systems (1)
29/43
-
8/13/2019 Control of Power Systems (1)
30/43
Such supervisory actions are Opening or closing of a circuit breaker or
switch Modifying a transformer tap setting Raising or lowering generator MW output
or terminal voltage Switching in or out a shunt capacitor or
inductor The starting or stopping of a synchronous
condenser.
-
8/13/2019 Control of Power Systems (1)
31/43
Information gathered by the RTU andcommunicated to the ECC includes both analoginformation and status indicators.
Analog information includes Frequency, Voltages, Currents, and Real and Reactive power flows.
Status indicators include Alarm signals (over-temperature, low relay battery
voltage, illegal entry) Whether switches and circuit breakers are open or
closed. Information is provided to the ECC through a
periodic scan of all RTUs.
-
8/13/2019 Control of Power Systems (1)
32/43
Communication technologies
The form of communication required for SCADAis telemetry .
Telemetry may be analog or digital.
In analog telemetry, a voltage, current, orfrequency proportional to the quantity beingmeasured.
In digital telemetry, the quantity being measured
is converted to a code in which the sequence ofpulses transmitted indicates the quantity.
-
8/13/2019 Control of Power Systems (1)
33/43
Block Diagram of Telemetering System
Quantity to be
telemetered
Transducer A/Dconverter
Telemetertransmitter
Telemeterreceiver
Computer
D/Aconverter
Indicatingmeter
Recordingmeter
Signal circuit (wire line,PLC, microwave, etc.)
-
8/13/2019 Control of Power Systems (1)
34/43
Energy Management System (EMS)
The EMS is a software system. Most utility companies purchase their EMS
from one or more EMS vendors.
These EMS vendors are companies specializingin design, development, installation, andmaintenance of EMS within ECCs.
-
8/13/2019 Control of Power Systems (1)
35/43
Industrial for Power EMSElectrical ProcessSystem configurationFunctionality Power EMSReferencesBenefits
-
8/13/2019 Control of Power Systems (1)
36/43
Critical LoadsLimited In-plant GenerationInsufficient reliability of Public Grid
Why Power EMS?
Load Shedding} Several GeneratorsContracted Power Importation Power Control} Different Electrical OperationalConfigurations possible Mode Control} Complex Distribution Networks
Local only Control facilities SCADA
} P EMS S O i
-
8/13/2019 Control of Power Systems (1)
37/43
Fast Functions are performed by Controllers:
Load Shedding / Re-Acceleration / Re-StartingPower Control
Mode Control
MCC
A B B T r a n s m i t OyN e tw o r k P a r tn e r
FEEDER TERMINAL REF541A B B N e t w o r k P a r t n e r
Uaux =80. .. 265Vdc/ acfn =50HzIn =1/ 5A ( I)
1MRS xxxxxx98150Un= 100/ 110V (U)
Uon= 100/ 110V ( Uo)
Ion= 1/ 5A (I o)
9509
A B B T r a n s m i t O yN e tw o r k P a r tn e r
FEEDER TERMINAL REF541A B B N e t w o r k P a r t n e r
Uaux =80. .. 265Vdc/ ac
fn =50HzIn =1/ 5A ( I)
1MRS xxxxxx
98150Un= 100/ 110V (U)Uon= 100/ 110V ( Uo)
Ion= 1/ 5A (I o)
9509
Substation N
S800 I/O
Serial links to AVR
Serial Links to Emergency Diesel GeneratorSerial links to Governor
A B B T r a n s m i t O yN e tw o r k P a r tn e r
FEEDER TERMINAL REF541A B B N e t w o r k P a r t n e r
Uaux = 80. . .265Vdc/ acf n=50HzI n= 1/ 5 A( I )
1MRS xxxxxx98150Un = 100/ 110V ( U)
Uon =100/ 110 V( Uo)
Ion =1/ 5A ( Io)
9509
A B B T r a n s m i t O yN e tw o r k P a r tn e r
FEEDER TERMINAL REF541A B B N e t w o r k P a r t n e r
Uaux = 80. . .265Vdc/ ac
f n=50HzI n= 1/ 5 A( I )
1MRS xxxxxx
98150Un = 100/ 110V ( U)Uon =100/ 110 V( Uo)
Ion =1/ 5A ( Io)
9509
ACS 601
TCP/IP Network
X-terminals(Process DCS)
Power EMS System Overview
Control IT
Substation 2Substation 1 Substation Z
Operate IT Engineering IT
-
8/13/2019 Control of Power Systems (1)
38/43
Functionality Power EMS
Load Shedding Active and Reactive Power Control Supervision, Control and Data Acquisition
(SCADA) Mode Control
Re-Acceleration / Re-Starting Synchronisation
-
8/13/2019 Control of Power Systems (1)
39/43
Load Shedding
Functionality Power EMS
?
Without Load SheddingWith Load Shedding
-
8/13/2019 Control of Power Systems (1)
40/43
Load Shedding: The types
Fast Load Shedding on Loss of PowerResources
Load Shedding on Frequency Drop Slow Load Shedding on Overload Slow Load Shedding for Peak Shaving
Manual Load Shedding
-
8/13/2019 Control of Power Systems (1)
41/43
-
8/13/2019 Control of Power Systems (1)
42/43
-
8/13/2019 Control of Power Systems (1)
43/43
Thank You