CONTROL OF CHLORINATED ORGANICS Doris B. Grego

Upload: others

Post on 23-Sep-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain

CONTROL OF CHLORINATED ORGANICS

Doris B. Grego

Page 2: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain

OVERVIEW

Chlorinated Organics

Control Devices

MACT Monitoring and Measurement Requirements

Alternatives for MACT Requirements

Recordkeeping

Page 3: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain

Chloroprene Unit

(HON)

Neoprene Unit

(P&R I)

HCl Recovery Unit

(BIF)

Chlorine

Wastes

Wastes

HCl for neutralization

Butadiene

Chloroprene Neoprene

DuPont Performance Elastomers

Pontchartrain Site

Wastes

WWT

Mississippi

River

Wells

Sanitary

Page 4: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 5: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 6: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 7: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain

WHAT IS A CHLORINATED ORGANIC?

Compounds that contain

– Carbon, Hydrogen and Chlorine Atoms

Examples

– Dioxins

– PCBs

– Carbon Tetrachloride

– Vinyl Chloride

– Chloroprene

Page 8: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 9: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 10: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain

MACT EMISSIONS CONTROL

Flare

– Halogenated vent streams can’t be flared

– Corrosion, acid formation

Incinerator/Boilers

– Need a scrubber

Condenser

– Cooling Media

– Recovery Device

– Save Money

Page 11: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain

TUBE HEAT EXCHANGER

Page 12: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 13: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 14: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 15: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 16: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain

MONITORING REQUIREMENTS

Under the MACT (MON, HON, P&R, etc.)

– Group 1 and Group 2 Vents

Group 1 – 98% reduction

Group 2 – maintain TRE 1 to 4

– Use recovery device

– Continuous monitoring of specific parameters

Page 17: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 18: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 19: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain

TRACKED PARAMETERS

Inlet temperature of brine

Valve position on the brine lines (open/closed)

Discharge pressure of brine pump

Check on visible emissions

Page 20: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 21: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 22: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 23: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain
Page 24: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain

SUMMARY

Condensers

Monitoring Alternatives

Electronic Records

Page 25: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain

QUESTIONS?

Page 26: CONTROL OF CHLORINATED ORGANICS · 6/2/2011  · MONITORING REQUIREMENTS Under the MACT (MON, HON, P&R, etc.) –Group 1 and Group 2 Vents Group 1 – 98% reduction Group 2 – maintain

THAK YOU!!

Doris B. Grego