contractual aspects of project management
DESCRIPTION
TRANSCRIPT
Contractual aspects of project
management
Legal pitfalls throughout the life of a contract
Overview
1. Introduction: contractual aspects of project management
2. Pre-contractual phase• (Private sector) tendering
• NDA (pro forma)
• LOI / Authorization letter
3. Contractual phase: • Nature of obligations / liability issues
• Evolution of agreements in function of projects / business decisions
4. Post-contractual phase: hidden obligations
1. Introduction
• PMBOK (Project Procurement
Management Overview)
– Plan Purchases and Acquisitions
– Plan Contracting
– Request Seller Responses
– Select sellers
– Contract administration
– Contract Closure
1. Introduction
• Make/buy analysis
– Contractual issues generally implies “buy”
decision has been made
– Buy decision imposes insourcing
• Ad hoc basis
– Individual agreements for specific contracts / large
projects
• Structured basis
– Standard agreements for “standard procurement”
– Formalized “tendering”
2. Pre-contractual phase
• Negotiation of contracts is subject to obligations
(conduct of parties) and restrictions
– “Good faith conduct” obligation
– Information obligation
• Sanction: pre-contractual liability (“culpa in
contrahendo”)
– Untimely rupture of negotations
– Creating expectations that are not delivered
• Difficult to assess impact and consequences
2. Pre-contractual phase
• Solution: formalize negotiations in a
contractual framework
– RFP/RFQ
– LOI/MoU
– Authorization Letter
• Practical advantage for project manager
– Manageability of procurement process
– May put “commercial pressure” on provider
2. Pre-contractual phase: RFP
• RFP/RFQ– Techical aspects
• Project description (requirements / solutions)
– Legal aspects• Confidentiality
• Non-binding nature (unilateral!)
• Disclaimer
• Model agreement (optional)
– Procedural aspects• Description of selection procedure / time-lines
– Do NOT refer to public sector legislation (unless public sector)
– Do NOT make it too strict (not complying may lead to liability)
• Shortlist / BaFO
2. Pre-contractual phase
• Letter of Intent (LOI) / Memorandum of Understanding (MoU)
• Content
– Preamble
– Purpose of the LOI / intention of the parties
– Binding / non-binding nature (?)
– Subject matter of main agreement
– Commencement and termination date
– Confidentiality and non-disclosure
2. Pre-contractual phase
• Specific case: consortium of companies
participating in a tender
– “Teaming agreement” / “Consortium
agreement” = specific LOI
– Lead contractor / Subcontractor
• Determine engagement of subcontractors (B2B)
• Determine respective obligations
• Project-related exclusivity
2. Pre-contractual phase
• Specific case: time-lines require
performance of agreement prior to the
conclusion thereof
– “Authorization Letter” / “Letter to Proceed” =
special LOI
– Risk: impact on ongoing negotations
• “Point of no return”
3. Contractual phase
• Nature of obligations?
– Obligations of means (middelenverbintenis / obligation de moyens)
• Reasonable efforts to achieve a certain result
• Result is not guaranteed– Not obtaining a result is not per se a breach of contract
– Burden of proof (!)
• Obligations can be reinforced: “best effort”, “effortof a top-tier service provider”, “best efforts in accordance with high industry standards”, description of parties in preamble (!)
2. Contractual phase
• Nature of obligations?
– Obligation to obtain a result
(resultaatsverbintenis / obligation de résultat)
• Result is guaranteed
• No result: breach of contract, unless “force
majeure” (verify definition of force majeure!)
• Burden of evidence (!)
• Qualification of obligations can be
changed by interpretation clauses (!)
3. Contractual phase
• Example:“The Parties acknowledge that their respective obligations shall be, depending on their nature, obligations of means (“middelenverbintenissen” / “obligations de moyen”) or obligations to obtain a result (“resultaatsverbintenissen” / “obligations de résultat”). However, the Parties explicitly agree that any obligation (i) of which the performance can be measured in an objective manner or (ii) which is sanctioned by a service level or a mechanism of liquidated damages or another compensation mechanism, shall be considered an obligation to obtain a result (“resultaatsverbintenis” / “obligation de résultat”).
3. Contractual phase
• Specific problems for long-term and/or
complex projects / agreements
– Agreements are considered as “private laws”
(article 1134 Civil Code)
– Change of agreement requires (in principle)
mutual consent
• May be difficult to obtain
• May be inflexible / formalistic
• May be unpredictable
3. Contractual phase
• Potential problems and solutions– Evolution of price
• Indexation clause
• Hardship / price revision clause
• Benchmarking (price & quality)
• “Most favoured customer” clause
– Quality (pro forma)• Audit
• Service Levels
– Content• Change request clause
– Dispute resolution• Contract management and escalation
3. Contractual phase
• Evolution of price (generally upwards)
– Indexation
• In principle not allowed (exceptions exist)
• Limitation to 80% of real cost increase (limited
“indexation”)
• Price increases are allowed (e.g. annual increase
of 3%)
– Hardship clause
• Fluctuate price (or other modalities) in function of
changing market / technical or other conditions
3. Contractual phase
• Evolution of price (generally downwards)
– Benchmarking• Correction mechanism to ensure “market
compliance”
• Pay attention to criteria to avoid/ensure inapplication or limitation
– “Most favoured customer” clause• Price equivalent of lower to best price offered to
other (comparable) customer
• Dangerous mechanism (management / potential for downward spiral in case of several customers)
3. Contractual phase
• Changes to the contents of an agreement
– In principle: mutual agreement
– Structure negotations by a change request
clause
• Who can request a change? Which information
must be included?
• What must be the reaction of the receiving party
(e.g. service provider must give opinion on
feasibility and pricing impact)
• Deadlines? Good faith negotiations?
3. Contractual phase
• Contract management
– Large project: contract management by
means of a project manager (daily operations)
and contract management committee
(fundamental issues)
– Smaller projects: project manager or contract
manager for informal contacts
3. Contractual phase
• Conflict management
– Disputes (litigation) are time-consuming and costly
– Avoid / manage conflicts where possible
– Escalation clause
• Dispute notification between project managers
• Escalation to contract management committee
• Escalation to management
– Provide sufficient time to resolve conflict, but avoid
lock-in
• Validity has been upheld in court (!)
4. Post-contractual phase
• PMBOK: “Contract Closure”
– Termination of contract ≠ end of all
contractual obligations
• Confidentiality
• Non-competition
• Non-solicitation
• Intellectual Property Rights (indemnification)
– Ensure proper follow-up as part of “contract
closure”
Thank you for your attention.
Questions?Johan Vandendriessche
De Wolf & Partners
Osborne Clarke Alliance
http://www.dewolf-law.be
T. 02/289.29.92