Contracts Management and Administration
(Based on FIDIC Standard)
PMI, PMP, PMBOK and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
“Outlining the Similarities
and Differences between
FIDIC Red and Green Book
Conditions of Contract”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Differences
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Overview – Scope and Content
Generally speaking –
• Red Book for large Construction Projects
• Green Book for smaller, less complicated
Construction Projects – not necessarily
defined by money value.
• Red Book (1999) contains 20 Clauses and over
166 Sub-Clauses over 62 pages
• Green Book contains only 15 Clauses and
only 52 Sub-Clauses over 10 pages.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Overview – Engineer Duties
• Red Book: “Engineer” empowered to be
“impartial” with regards to making “fair
determinations” between the Contractor and
the Employer.
• Green Book: SC 3.2 - “Engineer” formal
position eliminated; “EmployeesRepresentative” – who COULD BE an Engineer
- acts for and in the interests of the Employer.
There is no dual role or duty to be impartial.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Overview – Risk Ownership
• Green Book: Overall, the risk allocation has
moved slightly in the contractor's favor. The
contractor allowed to recover time and money
for rectifying damage to works, goods and
documents caused by employers risks which
are most of the force majeure list plus use or
occupation and design by the employer. (GBSC
2.3, 7.3, 10.3 and 10.4)
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Overview – Risk Ownership
• Green Book: Inclement weather is NOT provided for
in the Green form, though it is possible for the
parties to insert an express provision, allocating risk
to one party or the other for such eventuality.
• Since inclement weather is not a risk of the
employer, the contractor is not entitled under 7.3. to
an extension of time.
• Given any unjustified over-run will lead to liquidated
damages, (rate set out in the Appendix under 7.4 up
to a max of 10% of the contract sum) this represents
a considerable shift of liability onto the contractor.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Overview – Risk Ownership
Generally speaking –
• Red Book: Risk is “balanced” between the
Employer and Contractor;
➢ Contractor responsible for execution of all
work prior to the Take-Over Certificate.
➢ Employer is responsible for all designs and
specifications, providing access to the site to
the Contractor.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Overview – Risk Ownership
Generally speaking –
• Red Book: Inclement Weather remains a
legitimate reason for an extension of time
claim under these Conditions of Contract.
➢ SC 19.1, “Definition of Force Majeure” – (v)
“natural catastrophes such as earthquake,hurricane, typhoon or volcanic activity.”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Overview – Design Ownership
Generally speaking –
• Red Book: “The Employer, under the 1999 Red
Book Conditions of Contract – is completely
responsible for the specifications, drawings
and overall design of the project.
• “For Buildings and Engineering works
Designed by the Employer” – Title Page
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Overview – Design Ownership
Generally speaking –
• Green Book: SC 5.2 - “The Contractor shall
remain responsible for his tendered design
and the design under this Clause, both of
which shall be fit for the intended purposes
defined in the Contract and he shall also
remain responsible for any infringement of any
patent or copyright in respect of the same”.• The Employer shall be responsible for the
Specification and Drawings however.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Alternative Dispute Resolution
• Red Book:
• SC 20.4; Obtaining Dispute Adjudication
Boards Decision
• SC 20.5; Amicable Settlement
• SC 20.6; Arbitration
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Alternative Dispute Resolution
• Red Book: SC 20.4; Obtaining Dispute
Adjudication Boards Decision
• If a dispute (of any kind whatsoever) arises between
the Parties in connection with, or arising out of, the
Contract or the execution of the Works, including any
dispute as to any certificate, determination,
instruction, opinion or valuation of the Engineer,
either Party may refer the dispute in writing to the
DAB for its decision, with copies to the other Party
and the Engineer. Such reference shall state that it is
given under this Sub-Clause..
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Alternative Dispute Resolution
• Red Book: SC 20.4; Obtaining Dispute
Adjudication Boards Decision
• Within 84 days after receiving such reference,
or within such other period as may be
proposed by the DAB and approved by both
Parties, the DAB shall give its decision, which
shall be reasoned and shall state that it is
given under this Sub-Clause.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Alternative Dispute Resolution
• Red Book: SC 20.4; Obtaining Dispute
Adjudication Boards Decision
• The decision shall be binding on both Parties,
who shall promptly give effect to it unless and
until it shall be revised in an amicable
settlement or an arbitral award as described
below. Unless the Contract has already been
abandoned, repudiated or terminated, the
Contractor shall continue to proceed with the
Works in accordance with the Contract.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Alternative Dispute Resolution
• Green Book: SC 15.1; Adjudication
• Unless settled amicably, any dispute or difference
which arises between the Contractor and the
Employer out of or in connection with the Contract,
including any valuation or other decision of the
Employer, shall be referred by either Party to
adjudication in accordance with the attached Rules
for Adjudication ("the Rules"). The adjudicator shall
be any person agreed by the Parties. In the event of
disagreement, the adjudicator shall be appointed in
accordance with the Rules.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Alternative Dispute Resolution
• Red Book: SC 20.5; Amicable Decision
• Where notice of dissatisfaction has been given
under Sub-Clause 20.4 above, both Parties shall
attempt to settle the dispute amicably before the
commencement of arbitration. However, unless
both Parties agree otherwise, arbitration may be
commenced on or after the fifty-sixth day after the
day on which notice of dissatisfaction was given,
even if no attempt at amicable settlement has
been made.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Alternative Dispute Resolution
• Green Book: SC 15.2;
“Notice of Dissatisfaction”
• If a Party is dissatisfied with the decision of the
adjudicator or if no decision is given within the
time set out in the Rules, the Party may give
notice of dissatisfaction referring to this Sub-
Clause within 28 days of receipt of the decision or
the expiry of the time for the decision.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Alternative Dispute Resolution
• Green Book: SC 15.2;
“Notice of Dissatisfaction”
• If no notice of dissatisfaction is given within the
specified time, the decision shall be final and
binding on the Parties. If notice of dissatisfaction
is given within the specified time, the decision
shall be binding on the Parties who shall give
effect to it without delay unless and until the
decision of the adjudicator is revised by an
arbitrator.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Alternative Dispute Resolution
• Red Book: SC 20.6; Arbitration
• Unless settled amicably, any dispute in respect of
which the DAB’s decision (if any) has not become
final and binding shall be finally settled by
international arbitration. Unless otherwise agreed
by both Parties:
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Alternative Dispute Resolution
• Red Book: SC 20.6; Arbitration
a) The dispute shall be finally settled under the
Rules of Arbitration of the International Chamber
of Commerce,
b) The dispute shall be settled by three arbitrators
appointed in accordance with these Rules, and
c) The arbitration shall be conducted in the
language for communications defined in Sub-
Clause 1.4 [Law and Language].
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Alternative Dispute Resolution
• Green Book: SC 15.3; Arbitration
• A dispute which has been the subject of a notice
of dissatisfaction shall be finally settled by a
single arbitrator under the rules specified in the
Appendix. In the absence of agreement, the
arbitrator shall be designated by the appointing
authority specified in the Appendix. Any hearing
shall be held at the place specified in the
Appendix and in the language referred to in Sub-
Clause 1.5.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Similarities
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Duty to Report
Generally speaking –
Red Book: SC 1.8;
“Care and Supply of Documents”
• “If a Party becomes aware of an error or
defect of a technical nature in a document
which was prepared for use in executing the
Works, the Party shall promptly give notice to
the other Party of such error or defect.”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Duty to Report
Generally speaking –
Green Book: SC 10.3;
“Early Warning”
• “A Party shall notify the other as soon as he
is aware of any circumstance which may
delay or disrupt the Works, or which may give
rise to a claim for additional payment. The
Contractor shall take all reasonable steps to
minimise these effects.”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Claims – Time Bar
Red Book: SC 20.1;
“Contractors Claims”
• “If the Contractor considers himself to be entitled to
any extension of the Time for Completion and/or any
additional payment, under any Clause of these
Conditions or otherwise…, the Contractor shall give
notice to the Engineer, describing the event or
circumstance giving rise to the claim. The notice shall
be given as soon as practicable, and not later than 28
days after the Contractor became aware, or should
have become aware, of the event or circumstance.”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Claims – Time Bar
Generally speaking –
Green Book: SC 10.3;
“Early Warning”
• “The Contractor shall submit to the Employer an
itemized make-up of the value of Variations and
claims within 28 days of the instruction or of the
event giving rise to the claim. The Employer shall
check and if possible agree the value. In the
absence of agreement, the Employer shall
determine the value.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Claims – Entitlement
Red Book: SC 20.1;
“Contractors Claims”
• “If the Contractor fails to give notice of a claim
within such period of 28 days, the Time for
Completion shall not be extended, the Contractor
shall not be entitled to additional payment, and
the Employer shall be discharged from all liability
in connection with the claim. Otherwise, the
following provisions of this Sub-Clause shall
apply.”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Claims – Entitlement
Generally speaking –
Green Book: SC 10.5;
“Variation and Claim Procedure”
• “The Contractor's entitlement to extension to
the Time for Completion or additional
payment shall be limited to the time and
payment which would have been due if he had
given prompt notice and had taken all
reasonable steps.”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Interim Payment
Red Book: SC 14.3;
“Application to Interim Payment Certificates”
• “The Contractor shall submit a Statement in six
copies to the Engineer after the end of each month,
in a form approved by the Engineer, showing in
detail the amounts to which the Contractor
considers himself to be entitled, together with
supporting documents which shall include the
report on the progress during this month in
accordance with Sub-Clause 4.21 [Progress
Reports].”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Interim Payment
Red Book: SC 14.6;
“Issue of Interim Payment Certificates”
• “…Thereafter, the Engineer shall, within 28 days
after receiving a Statement and supporting
documents, issue to the Employer an Interim
Payment Certificate which shall state the amount
which the Engineer fairly determines to be due,
with supporting particulars.”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Interim Payment
Green Book: SC 11.2;
“Monthly Statements”
• “The Contractor shall submit each month to
the Employer a statement showing the
amounts to which he considers himself
entitled.”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Interim Payment
Green Book: SC 11.3;
“Interim Payments”
• “Within 28 days of delivery of each statement, the
less retention
at the rate stated in the Appendix, and less any
amount for which the Employer has specified his
reasons for disagreement.”
• Also, the Employer shall not be bound by any sum
previously considered by him to be due to the
Contractor.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Final Payment
Red Book:
Applicable Sub-Clauses;
SC 11.9, Performance Certificate
SC 14.10, Statement at Completion
SC 14.11, Application for Final Payment
Certificate
SC 14.12, Discharge
SC 14.13, Issue of Final Payment Certificate
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Interim Payment
Red Book: SC 14.10; “Statement at Completion”
Within 84 days after receiving the Taking-Over
Certificate for the Works, the Contractor shall
submit to the Engineer six copies of a
Statement at completion with supporting
documents, in accordance with Sub-Clause 14.3
[Application for Interim Payment Certificates],
showing:
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Interim Payment
Red Book: SC 14.10; “Statement at Completion”
a) The value of all work done in accordance with
the Contract up to the date stated in the Taking-
Over Certificate for the Works,
b) Any further sums which the Contractor considers
to be due, and
c) An estimate of any other amounts which the
Contractor considers will become due to him
under the Contract. Estimated amounts shall be
shown separately in this Statement at
completion.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Interim Payment
Red Book: SC 14.11;
“Application for Final Payment Certificate”
“Within 56 days after receiving the Performance
Certificate, the Contractor shall submit, to the
Engineer, six copies of a draft final statement
with supporting documents showing in detail in
a form approved by the Engineer:
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Interim Payment
Red Book: SC 14.11;
“Application for Final Payment Certificate”
a)The value of all work done in accordance
with the Contract, and
b)Any further sums which the Contractor
considers to be due to him under the
Contract or otherwise.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Interim Payment
Red Book: SC 14.11;
“Application for Final Payment Certificate”
• “If the Engineer disagrees with or cannot verify
any part of the draft final statement, the
Contractor shall submit such further information
as the Engineer may reasonably require and shall
make such changes in the draft as may be agreed
between them. The Contractor shall then prepare
and submit to the Engineer the final statement as
agreed. This agreed statement is referred to in
these Conditions as the “Final Statement”.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Interim Payment
Red Book: SC 14.12; “Discharge”
• “When submitting the Final Statement, the
Contractor shall submit a written discharge which
confirms that the total of the Final Statement
represents full and final settlement of all moneys
due to the Contractor under or in connection with
the Contract. This discharge may state that it
becomes effective when the Contractor has
received the Performance Security and the
outstanding balance of this total, in which event
the discharge shall be effective on such date.”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
Claims – Final Payment
Red Book: SC 14.13;
“Issuance of Final Payment Certificate”
• “Within 28 days after receiving the Final
Statement and written discharge in
accordance with Sub-Clause 14.11
[Application for Final Payment Certificate]
and Sub-Clause 14.12 [Discharge], the
Engineer shall issue, to the Employer, the
Final Payment Certificate which shall state:
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Final Payment
Red Book: SC 14.13;
“Issuance of Final Payment Certificate”
a)The amount which is finally due, and
b) After giving credit to the Employer for all
amounts previously paid by the Employer and
for all sums to which the Employer is
entitled, the balance (if any) due from the
Employer to the Contractor or from the
Contractor to the Employer, as the case may
be.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Final Payment
Green Book: SC 11.6;
“Final Payment”
1. “Within 42 days of the latest of the events listed in
Sub-Clause 11.5 above, the Contractor shall submit
a final account to the Employer together with any
documentation reasonably required to enable the
Employer to ascertain the final contract value.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Final Payment
Green Book: SC 11.6;
“Final Payment”
2. “Within 28 days after the submission of this final
account, the Employer shall pay to the Contractor
any amount due. If the Employer disagrees with any
part of the Contractor's final account, he shall
specify his reasons for disagreement when making
payment.”
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Delayed Payment
Red Book: SC 14.8;
“Delayed Payment”
• If the Contractor does not receive
payment in accordance with Sub-Clause
14.7 [Payment], the Contractor shall be
entitled to receive financing charges
compounded monthly on the amount
unpaid during the period of delay.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Delayed Payment
Red Book: SC 14.8;
“Delayed Payment”
• This period shall be deemed to
commence on the date for payment
specified in Sub-Clause 14.7 [Payment],
irrespective (in the case of its sub-
paragraph (b)) of the date on which any
Interim Payment Certificate is issued.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Delayed Payment
Red Book: SC 14.8;
“Delayed Payment”
• Unless otherwise stated in the Particular
Conditions, these financing charges shall
be calculated at the annual rate of three
percentage points above the discount rate
of the central bank in the country of the
currency of payment, and shall be paid in
such currency.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Delayed Payment
Green Book: SC 11.8;
“Delayed Payment”
• The Contractor shall be entitled to interest at
the rate stated in the Appendix for each day
the Employer fails to pay beyond the
prescribed payment period.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Care of Works
Red Book: SC 17.2;
“Contractor’s Care of the Works”
• The Contractor shall take full responsibility for
the care of the Works and Goods from the
Commencement Date until the Taking-Over
Certificate is issued (or is deemed to be issued
under Sub-Clause 10.1 [Taking Over of the Works
and Sections]) for the Works, when responsibility
for the care of the Works shall pass to the
Employer.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Delayed Payment
Red Book: SC 17.2;
“Contractor’s Care of the Works”
If a Taking-Over Certificate is issued (or is
so deemed to be issued) for any Section or
part of the Works, responsibility for the
care of the Section or part shall then pass
to the Employer.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Delayed Payment
Green Book: SC 13.1;
“Contractor’s Care of the Works”
The Contractor shall take full responsibility for the
care of the Works from the Commencement Date
until the date of the Employer's notice under Sub-
Clause 8.2. Responsibility shall then pass to the
Employer. If any loss or damage happens to the
Works during the above period, the Contractor shall
rectify such loss or damage so that the Works
conform with the Contract.
© 2016 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . 800 3FOLD
– Delayed Payment
Green Book: SC 13.1;
“Contractor’s Care of the Works”
Unless the loss or damage happens as a result of an
Employer's Liability, the Contractor shall indemnify
the Employer, the Employer's contractors, agents
and employees against all loss or damage
happening to the Works and against all claims or
expense arising out of the Works caused by a
breach of the Contract, by negligence or by other
default of the Contractor, his agents or employees.