contractor guide - tarmac · is fully compacted to avoid future fretting or surface degradation....

3
November 2015 ULTI DRIVE CONTRACTOR GUIDE

Upload: others

Post on 16-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CONTRACTOR GUIDE - Tarmac · is fully compacted to avoid future fretting or surface degradation. Rolling should be substantially complete before the temperature has fallen below 100°C

November 2015

ULTIDRIVECONTRACTOR GUIDE

Page 2: CONTRACTOR GUIDE - Tarmac · is fully compacted to avoid future fretting or surface degradation. Rolling should be substantially complete before the temperature has fallen below 100°C

TARMAC.COM

CONTRACTOR GUIDE

1. INTRODUCTION

ULTIDRIVE is a proprietary hard wearing surfacing product specifically designed for driveways

and car parks, incorporating a modified binder with enhanced fuel resistance. It offers improved

workability for machine or handlaying to the installer and a long performance life to the client or

customer.

2. WEATHER

Prior to ordering, ensure the following is considered – BS 594987:2015. Laying shall be carried out

with due regard to ambient weather conditions so that materials can be properly compacted.

The asphalt shall not be laid on any surface which is frozen or covered with ice or snow. Laying shall

cease when the air temperature reaches 0°C on a falling thermometer, except in calm dry conditions,

when laying shall cease if the air temperature reaches -3°C on a falling thermometer. Do not lay in

standing water or during periods of heavy rain.

3. DELIVERY

ULTIDRIVE will only be transported in fully insulated vehicles. The truck must remain sheeted at all

times during tipping and chuted vehicles should be encouraged where hand laying is involved.

It is recommended that you have a calibrated digital thermometer to check the material temperature

upon discharging, prior to rolling and monitor throughout the rolling operation.

The minimum discharge temperature should be 150°C. It is recommended that accurate laying records

are kept as this will assist in developing your installation best practice.

4. SITE PREPARATION

Prior to proposing ULTIDRIVE for use, the contractor shall ensure that a site condition survey is carried

out and any potential issues identified.

ULTIDRIVE

TARMAC.COM

Page 3: CONTRACTOR GUIDE - Tarmac · is fully compacted to avoid future fretting or surface degradation. Rolling should be substantially complete before the temperature has fallen below 100°C

TARMAC.COM

The receiving surface should be sound and of suitable regularity to ensure satisfactory surface drainage

and layer thickness of the ULTIDRIVE surfacing.

Assess site access for delivery vehicles to ensure loaded trucks can be accommodated and there are no

obstacles or overhead cables.

Advise the order office of any difficulties that may be experienced at site. Where material has to be

transhipped on site, remember that this will affect the temperature of the product and its’ workability,

which may impact on the installation process.

Should the contractor have any concern regarding product suitability for any specific site, please seek

advice from the Tarmac Technical Team who will be pleased to assist.

5. LAYING AND COMPACTION

6mm ULTIDRIVE is normally laid at a thickness of 25mm, but this can be increased as far as 40mm if

required. The laid thickness at any point should not be less than 20mm. 10mm ULTIDRIVE is normally

laid at a thickness of 30mm, but this can be increased as far as 50mm if required. The laid thickness at

any point should not be less than 25mm.

Before laying any asphalt, it is essential to evenly spray apply a tack coat of bitumen emulsion on to

the receiving course which will bond the surfacing to the substrate and will help prevent undue layer

movement during compaction process ensuring a good surface finish.

End of day joints shall be cut back at least 300mm to a vertical face. It is also recommended to cut

longitudinal joints back by at least 50mm where possible as this will ensure good joint compaction

minimising the risk of water ingress and joint degradation. All joints shall be painted with a compatible

joint paint or hot bitumen.

Compaction shall be carried out in accordance with the general requirements of BS 594987 utilising a

minimum 1.5 tonne tandem roller. Pedestrian guided rollers (single drum) should only be used when

space is too restrictive and ride on rollers should be used wherever possible. For car parks, a minimum

2.5 tonne tandem roller is recommended.

Compaction should commence as soon as possible after spreading the asphalt taking care not to unduly

displace the material. Ensure the ULTIDRIVE is fully compacted to avoid future fretting or surface

degradation. Rolling should be substantially complete before the temperature has fallen below 100°C.

The finished surface should be continuously inspected during laying operations and any defects

immediately rectified before any rolling takes place, thereby avoiding any need for back casting.

To avoid deformation or damage, the surface must not be trafficked until it has been allowed to cool to

near ambient temperature.

TARMAC.COM