contract: nzta1234 contract documents · 2010-03-01 · schedule of prices 1 contractor's...

210
NZ Transport Agency Somac 2010 Standard Maintenance Contract Contract: NZTA1234 Highway Maintenance Example Contract Documents

Upload: others

Post on 27-Feb-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

NZ Transport Agency Somac 2010 Standard Maintenance Contract

Contract: NZTA1234

Highway Maintenance Example

Contract Documents

Schedule of Prices

Schedule of Prices

Contents

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

The Schedule of Prices includes the following sections:

1 Contractor’s Management 1

2 Level 1 Routine Maintenance 8

3 Tender Summary 9

4 Barrier Repairs 10

5 Repair Size and Annual Quantities 12

6 Important Note for Tenderers about Quantities 13

Schedule of Prices

1 Contractor's Management Item Description Type Unit Quantity Rate Amount ($)

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

SP 1

1 Contractor’s Management

1 Contract Works

1.1 Establishment M LS/mth 36 The maximum tendered rate must be less than or equal to 2% of the Total Tender Sum

1.2 Contract Management Review M ea 2

2 Contractor's Quality Plan

2.1 Preparation and Management M LS 1 CQP

2.2 Quality Control Testing M Included in tendered rates

3 General Requirements M Included in tendered rates

3.1 Forward Work Programme Field Inspections Included in tendered rates

4 Contractor's Programmes M Included in tendered rates

4.1 Programme M ea 36 (The minimum tendered rate is $200.00/Programme. The maximum tendered rate is $300.00/Programme)

5 Contractor's Reports

5.1 Monthly Reports M ea 36 (The minimum tendered rate is $200.00/Report. The maximum tendered rate is $300.00/Report)

5.2 Final and Maintenance Reports M Included in tendered rates

6 Traffic Management

6.1 Preparation of TMP M LS 1

6.2 Management of TMP M Included in tendered rates

6.3 Traffic Control

6.3.1 Level 1 Traffic Management M Included in tendered rates

6.4 Additional Traffic Control

6.4.1 Level 1 Traffic Management

Schedule of Prices

1 Contractor's Management Item Description Type Unit Quantity Rate Amount ($)

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

SP 2

6.4.1.1 Shoulder Closure U Day 20

6.4.1.2 Single Lane Closure U Day 20

7 Environmental Management M Included in tendered rates

8 Unscheduled Works

8.1 Plant and Equipment U

8.1.1 Excavator, 5-9.9t Hr 200

8.1.2 Excavator, 10-14.9t Hr 150

8.1.3 Excavator, 15-20t Hr 50

8.1.4 Loader, 0-1.5m3 Hr 200

8.1.5 Trucks 0-5m3 Hr 200

8.1.6 Trucks, 5.1-8m3 Hr 200

8.1.7 Truck Trailer 0-8m3 Hr 100

8.1.8 Grader, 0-59.9kW Hr 50

8.1.9 Grader, 60-120kW Hr 100

8.1.10 Roller, 0-5t Hr 100

8.1.11 Roller, 5.1-10t Hr 25

8.1.12 Tractor Broom Hr 25

8.1.13 Suction Sweeper Hr 250

8.1.14 Bitumen Distributor, 0-80001 Hr 50

8.1.15 Bitumen Distributor, 0-10001 Hr 50

8.1.16 Water Cart Hr 50

8.1.17 Heavy Plant Transporter Hr 100

8.1.18 Plant Transport Trailer Hr 50

8.1.19 Single Axle Car Trailer Hr 100

8.1.20 Tandem Axle Car Trailer Hr 100

8.1.21 Utility Hr 50

8.1.22 Post Hole Borer Hr 50

Schedule of Prices

1 Contractor's Management Item Description Type Unit Quantity Rate Amount ($)

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

SP 3

8.1.23 Light Vehicle, <2t Hr 100

8.1.24 Light Truck, 2-4t Hr 100

8.1.25 Pneumatic Tyred Roller Hr 50

8.1.26 Truck Trailer Hr 500

8.1.27 Van Hr 300

8.1.28 Hiab, 5t Hr 200

8.1.29 Compressor, 1501/sec Hr 200

8.1.30 Waterblaster Hr 20

8.1.31 Sandblaster Hr 20

8.1.32 Concrete Mixer, 1m3 Hr 200

8.1.33 Mobile Crane, 20t Hr 25

8.1.34 Attenuator Hr 50

8.2 Materials

8.2.1 Materials U PS 1 $120,000.00 $120,000.00

8.2.2 Contractor's On-cost to Materials U % 120000 (The tendered rate must be expressed as a decimal and rounded to two places. The quantity is in dollars ($))

8.3 Labour

8.3.1 Contract Management Personnel U Hr 200

8.3.2 Other Personnel U Hr 1200

8.4 Cost Fluctuations U PS 1 $60,000.00 $60,000.00

Section 1: Total Tender Sum (Transfer to Tender Summary)

Schedule of Prices

2 Level 1 Routine Maintenance Item Description Type Unit Quantity Rate Amount ($)

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

SP 4

9 Incident Response U PS 1 $1,000,000.00 $1,000,000.00

9.1 Emergency Patrols U Hr

10 Winter Maintenance

10.1 Weather Monitoring C LS/mth 36

10.2 Plant

10.2.1 Type 1 (High Speed Light Snow U Hr 50 Removal)

10.2.2 Type 2 (Heavy Snow Removal) U Hr 40

10.2.3 Type 3 (Snow Drift Removal) U Hr 80

10.2.4 Type 4 (Grit Spreading) U Hr 100

10.2.5 Type 5 (Grit Removal) U Hr 30

10.2.6 Type 6 (Solid Chemical Spreader) U Hr 2000

10.2.7 Type 7 (Liquid Chemical Applicator) U Hr 1000

10.3 Materials

10.3.1 Ice Grit U m³ 80000

10.3.2 CMA U Hr 5000

11 Surfacings

11.1 First Coat Sealing U Included in tendered rates

11.2 Second Coat Sealing U m² 500

11.3 Supply of Higher Polished Stone Value (PSV) Aggregate

11.3.1 PSV 51 - 58 U Included in tendered rates

11.3.1.1 PSV 59 - 61 (Over-rate to Schedule) U m² 5000 (Provisional Item)

11.3.1.2 PSV > 61 (Over-rate to Schedule) U m² 5000 (Provisional Item)

11.4 Crack Sealing

Schedule of Prices

2 Level 1 Routine Maintenance Item Description Type Unit Quantity Rate Amount ($)

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

SP 5

11.4.1 Sealing U m² 2000

11.4.2 Additive U m² 170

11.5 Crack Filling U m 1000

11.6 Scabbing and Stripping U m² 1000

11.7 Flushing and Bleeding

11.7.1 Flushing Repairs

11.7.1.1 High Pressure Water Treatment U m2 1000

11.7.1.2 Diluent and Chip U m² 36

11.7.2 Pavement Gritting

11.7.2.1 Weather Observation C LS/mth 200

11.7.2.2 Application U Hr 100

11.7.2.3 Removal U Hr 40000

11.8 Cold Milling

11.8.1 Texturise Surface U m² 1000

11.8.2 Remove Surface Irregularities U m² 40000

11.9 Reduction in Size U $ 1000 (The tendered rate must be expressed as a percentage. The quantity is in dollars ($))

12 Digouts

12.1 Digout Repairs U m² 4000

12.2 Stabilisation Repairs U m² 1000

12.3 Digouts in A/C Pavements

12.3.1 A/C Surfacing Depth = 0 - 60mm U m² 1000

12.3.2 A/C Surfacing Depth = 61 - 150mm U m² 2500

12.4 Miscellaneous

12.4.1 Positive Drainage U m 500

12.4.2 Geotextile U m² 2000

12.4.3 Surface Water Channels U m 1000

Schedule of Prices

2 Level 1 Routine Maintenance Item Description Type Unit Quantity Rate Amount ($)

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

SP 6

12.4.4 Other Treatments U

12.4.4.1 Consultant to Specify U

12.5 Reduction in Size U $ 8000 (The tendered rate must be expressed as a percentage. The quantity is in dollars ($))

13 Depressions

13.1 Rip and Remake

13.1.1 Chip Sealed Surface U m² 8000

13.1.2 Premix Surface U m² 5000

13.2 Premix Reshaping

13.2.1 Chip Sealed Surface U m² 500

13.2.2 Premix Surface U m² 1000

13.3 Cold Mill and Inlay

13.3.1 0 - 30mm Depth U m² 500

13.3.2 31 - 65mm Depth U m² 500

13.4 Reduction in Size U $ 120 (The tendered rate must be expressed as a percentage. The quantity is in dollars ($))

14 Edge Break U m 4000

15 Service Covers

15.1 Service Hole (Manhole) Covers U ea 1000

15.2 Valve Boxes and Hydrant U ea 30 Covers

16 Shoulder Maintenance

16.1 Remove High Shoulder U m 120

16.2 Repair Low Shoulder U m 6000

16.3 Reshape and Compact Shoulder U m 150

Schedule of Prices

2 Level 1 Routine Maintenance Item Description Type Unit Quantity Rate Amount ($)

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

SP 7

17 Barrier Repairs

17.1 Barrier Repairs U LS 1 (Rate transferred from Barrier Repairs Schedule)

18 Abandoned Vehicles U ea 15

19 Potholes

19.1 Repair of Potholes C km.mth 10

19.2 Additional Potholes C /100ea 150

20 Detritus and Slip Removal

20.1 Sealed Surfaces C km.mth 7920

20.2 Lined and Unlined Channels C km.mth 7920

20.3 Slips

20.3.1 Establishment U ea 40

20.3.2 Removal U m3 400

21 Drainage Systems

21.1 Routine Maintenance C km.mth 7920

21.2 Other Drainage Systems C LS/mth 36

22 Unsealed Pavements

22.1 Potholes C km.mth 3400

22.2 Surface and Shape Restoration C km.mth 12000

22.3 Digouts

22.3.1 Digout Repairs U m² 4500

22.3.2 Stabilisation Repairs U m² 3000

22.3.3 Miscellaneous

22.3.3.1 Positive Drainage U m 1200

Schedule of Prices

2 Level 1 Routine Maintenance Item Description Type Unit Quantity Rate Amount ($)

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

SP 8

22.3.3.2 Geotextile U m² 5000

22.3.3.3 Surface Water Channels U m 4500

22.4 Maintenance Aggregate

22.4.1 Maintenance Aggregate U m² 2500

22.4.2 Clay Additive U m² 1200

23 Drainage Improvements

23.1 Side Slope Shape (Cut 1 to 6's) U m 1000

23.2 Clean and Regrade Existing U m 500 Surface Channel

23.3 Clean and Regrade Existing U m 1500 Side Drain

23.4 Subsoil Drain Cleaning U ea 60

23.5 Replace Culvert Marker U ea 50

23.5.1 Remove and Reinstate U m2 2 Level 1 Routine Maintenance

Section 2: Total Tender Sum (Transfer to Tender Summary)

Schedule of Prices

3 Tender Summary

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

SP 9

3 Tender Summary

Section Description Total($)

1 Contractor's Management (from Section 1) _______________________ 2 Level 1 Routine Maintenance (from Section 2) _______________________

Total Tender Sum (All Sections) (Transfer to Tender Form)

$

Tenderer's Signature: ______________________________________________________________

Tenderer's Name: ______________________________________________________________

Contact Person: ______________________________________________________________

Contact Person's Position: ______________________________________________________________

Contact Numbers: Phone __________________ Fax ______________________

Schedule of Prices

4 Barrier Repairs

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

SP 10

4 Barrier Repairs

Tenderers must complete the Barrier Repairs Schedule and transfer the Total to the amount column of Section 2, Schedule Item 17.1. The rates tendered in this schedule will be used to value all work completed under Schedule Item 17.1. To complete this schedule, tenderers must:

a) for each item, enter their tendered rate and determine the amount by multiplying the quantity by the tendered rate

b) sum all amounts to determine the total value and transfer this value to the rate column of Section 2, Schedule Item 17.1.

Level 1 Traffic Management (See Section 2): Barrier Repairs Schedule

Item Description Unit Quantity Rate ($) Amount ($)

17.1.1 Guardrail

17.1.1.1 2.7mm Guardrail (Highway) m Complete 17.1.1.2 3.4mm Guardrail (Bridge) m

17.1.1.3 Timber Post with Blockout ea

17.1.1.4 Steel Post with Blockout ea

17.1.2 Mild Steel Barrier 17.1.2.1 Channel Section m

17.1.2.2 Butt Joint ea

17.1.2.3 Post ea

17.1.3 IBC Steel Median Barrier 17.1.3.1 Standard Panel ea

17.1.3.2 Standard Lid ea

17.1.3.3 Standard Bulkhead ea

17.1.4 MB5 New Jersey Barrier ea

17.1.5 Tric Block Concrete Barrier

17.1.5.1 Standard Unit m

17.1.6 Steel Wire Barrier

17.1.6.1 Post Reflector ea

17.1.6.2 Post ea

17.1.6.3 Post, Pegs, Washer, Reflector and Cap ea

17.1.6.4 Cap and Reflector ea

17.1.6.5 Wire Rope 17.1.6.5.1 Replacement Rope m

17.1.6.5.2 Splices ea

17.1.7 Steel Tube and Post Guardrail

17.1.7.1 Tube m

17.1.7.2 Post ea

17.1.8 End Protection

17.1.8.1 Replacement Units ea

17.1.8.1.1 TNZ M/23 Terminal Fitting ea

17.1.8.1.2 TEA Unit ea

17.1.18.2 Hazard Markers ea

Schedule of Prices

4 Barrier Repairs

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

SP 11

Level 1 Traffic Management (See Section 2): Barrier Repairs Schedule

Item Description Unit Quantity Rate ($) Amount ($)

17.1.9 Steel Drum Cushion

17.1.9.1 Drums ea

17.1.9.2 Mild Steel Handrail m

17.1.9.3 Quadguard Crash Cushion ea

Total Amount (Transfer to Section 2, Schedule Item 17.1) $

Schedule of Prices

5 Repair Size and Annual Quantities

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

SP 12

5 Repair Size and Annual Quantities

The following Schedule sets out the indicative Average Repair Sizes, Depths and Annual Quantities for some Scheduled items and includes the: a) average repair size or b) indicative number or quantity (as appropriate) that can be expected to be completed on an annual basis c) indicative average annual number or quantity of dig out repairs greater than 300mm in depth. These indicative quantities are provided for the tenderer's information and are based on quantities over the last three years. The information provided in no way gives an indication of the final quantities of work.

Level 1 Traffic Management (see Section 2): Repair Size and Annual Quantities

Item Description Average Repair Size Annual Quantity

Consultant to complete

Schedule of Prices

6 Important Note for Tenderers about Quantities

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

SP 13

6 Important Note for Tenderers about Quantities

Tenderers must note:

1. All quantities stated in the Schedule of Prices are for information only. Tenderers:

a) must expect the stated quantities to vary between various sections of the network and throughout the contract period

b) shall allow in the tendered rates for variations such as location, extend and type of work completed under each Unit Rate and Cyclic Maintenance Items.

2. The Contractor is:

a) entitled to payment for the quantity of work completed as provided for in the Basis of Payment

b) is not otherwise entitled to any additional compensation (whether by way of damages or otherwise) for any difference between the actual and scheduled quantities.

Basis of Payment

Basis of Payment

Contents

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

Preamble 1

Payment

1. Contract Works 8

1.1 Establishment 8 1.2 Contract Management Review 8

2. Contractor’s Quality Plan 8

2.1 Preparation and Management of CQP 8 2.2 Quality Control Testing 8

3. General Requirements 9

4. Contractor's Programmes 9

4.1 Programme 9

5. Contractor's Reports 9

5.1 Monthly Reports 9 5.2 Final and Maintenance Reports 9

6. Traffic Management 10

6.1 Preparation of Traffic Management Plan (TMP) 10 6.2 Management of TMP 10 6.3 Traffic Control 10 6.4 Additional Traffic Control 10

7. Environmental Management 10

8. Unscheduled Works 11

8.1 Plant and Equipment 11 8.2 Materials 12 8.3 Labour 12 8.4 Cost Fluctuations 12

9. Incident Response 12

9.1 Emergency Patrols 13

10. Winter Maintenance 13

10.1 Weather Monitoring 13 10.2 Plant 13 10.3 Materials 14

11. Surfacings 14

11.1 First Coat Sealing 14 11.2 Second Coat Sealing 14 11.3 Supply of Higher Polished Stone Value (PSV) Aggregate 15 11.4 Crack Sealing 15 11.5 Crack Filling 15 11.6 Scabbing and Stripping 15

Basis of Payment

Contents

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

11.7 Flushing and Bleeding 16 11.8 Cold Milling 16 11.9 Reduction in Size 17

12. Digouts 17

12.1 Digout Repairs 17 12.2 Stabilisation Repairs 17 12.3 Digouts in A/C Pavements 18 12.4 Miscellaneous 18 12.5 Reduction in Size 19

13. Depressions 19

13.1 Rip and Remake 19 13.2 Premix Reshaping 19 13.3 Reduction in Size 20

14. Edge Break 20

15. Service Covers 20

16. Shoulder Maintenance 20

16.1 Remove High Shoulder 20 16.2 Repair Low Shoulder 21 16.3 Reshape and Compact Unsealed Shoulder 21

17. Barrier Repairs 21

17.1 Barrier Repairs 21

18. Abandoned Vehicles 21

19. Potholes 22

19.1 Repair of Potholes 22 19.2 Additional Potholes 22

20. Detritus and Slip Removal 22

20.1 Sealed Surfaces 22 20.2 Lined and Unlined Channels 23 20.3 Slips 23

21. Drainage Systems 24

21.1 Routine Maintenance 24 21.2 Other Drainage Systems 24

22. Unsealed Pavements 24

22.1 Potholes 24 22.2 Surface and Shape Restoration 25 22.3 Pavement Repairs 25 22.4 Maintenance Aggregate 26

23. Drainage Improvements 26

23.1 Side Slope Shaping (Cut 1 to 6’s) 26

Basis of Payment

Contents

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

23.2 Clean and Regrade Existing Surface Channel 26 23.3 Clean and Regrade Existing Side Drain 27 23.4 Subsoil Drain Cleaning 27 23.5 Replace Culvert Marker 27

Basis of Payment

1 Preamble

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 1

The following Clauses apply to all Items included in the Schedule of Prices. i. Annual Contract Value

The annual contract value is expected to fall between -15% and +0% of the value stated in Request for Tender, Clause 1.13. If the annual value is forecasted to fall more than 15% below the stated value and this is not due to the Contractor’s performance, the Principal will provide top-up work so the annual contract value remains within the specified range.

ii. Abbreviations

Units of measurement shown in the unit column of the Schedule of Prices are abbreviated as follows: % = Percent /100ea = 100 each (per 100 additional potholes) EMP = Edge Marker Post RPM = Raised Pavement Marker Day = Day ea = each Hr = Hour Km = Kilometre Km.mth = Kilometres Monthly l = Litre LS = Lump Sum LS/mth = Lump Sum per Month LS/Remark = Lump Sum per Remark m = Metre m² = Square Metre m3 = Cubic Metre t = Tonne kg = Kilogram PS = Provisional Sum $ = Dollar

iii. Definitions

Task types shown in the Task column of the Schedule of Prices are abbreviated as follows: M = Management Task U = Unit Rate Task C = Cyclic Maintenance Task First Schedule Part B, clause 1.2 defines each task.

Basis of Payment

1 Preamble

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 2

iv. Measurement

Payment for all work completed will be based on the quantities stated on the agreed Programme. No payment will be made for any work completed by the Contractor that was:

a) not agreed with the Engineer

b) not on an agreed Programme

c) deleted by the Engineer from any Programme d) not fully complete at the time of measurement. No additional payment will be made for any increase in the extent of work required to complete Task(s) if this happened only because the Task(s) were not completed by the date shown on the agreed Programme.

v. Engineer's Assessment and Measurement

If the Engineer's reviews and inspections of the Contract Works show:

a) the quality assurance records are incomplete and/or

b) some aspects of the Contract Works are non-complying, the Engineer may:

value the works according to General Conditions, Clause 12.1.3

instruct the Contractor to identify and rectify all non-complying work

arrange for the work to be completed by any such means the Engineer considers appropriate. If time permits, the Contractor will be advised of the Engineer's intentions and given the opportunity to complete the work within the time frame agreed with the Engineer.

All costs of initiating, managing and completing any such work may be deducted from the Contractor's payments. These costs will be based on the rates stated under Conditions of Contract, First Schedule, Clause 6.4.6. If the remedial work is completed, the Engineer may: i) reassess and value the work ii) instruct the Contractor to complete further remedial work. No additional payment will be made for any increase in the extent of work required to complete Task(s) if this happened only because the Task(s) were not completed by the date shown on the agreed Programme.

Basis of Payment

1 Preamble

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 3

v.1 Payment Valuation

Further to General Conditions, Clause 12.1, the Engineer's valuation of the Contractor's claims will be based on the inspection and assessment of: a) a sample or samples of the claimed unit rate tasks to determine unit rate task's compliance b) a sample or samples of at least 10% of the network's length, selected on a random basis, to

determine cyclic maintenance task's compliance. The Engineer will: i) invite the Contractor to participate in the sampling, inspection and assessment of the first

payment claim ii) make available all records and documentation that support each claim's valuation. Any reduction in payment in accordance with these provisions shall be without prejudice to the provisions of Section 14 of the General Conditions.

v.1.1 Sampling

Unit Rate Tasks The unit rate task sample will include: a) all unit rate tasks greater than 20m² in total area or 10m in total length as appropriate b) all unit rate tasks greater than $5,000.00 in value c) a random sample of the remaining unit rate tasks so:

the total sample size is at least 10% of the total number of unit rate tasks claimed and

the total sample value is at least 10% of the total value of unit rate tasks claimed. These inspections will be completed between the date the claim is received and the date the claim is certified for payment. Cyclic Maintenance The assessment of cyclic maintenance task compliance will be based on an inspection and assessment of at least 10% of the total length of highway and/or total number of areas, as appropriate, within the network each month.

Basis of Payment

1 Preamble

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 4

The Engineer will: a) split the network into discrete kilometre sections and/or areas

b) provide a copy of this list to the Contractor at the start of the contract

c) select on a random basis a sample or samples comprising at least 10% of the total number of sections and/or areas each month.

These inspections will be completed at any time during the period the claim applies to.

v.1.2 Sample Assessment

Unit Rate Tasks For each selected task, the Engineer will determine whether it complies with the Contract Documents. The percentage compliance will be: a) calculated using the following formula. If the Engineer includes any other unit rate tasks, not

selected in the original sample, in the assessment, then the sample size used in the calculation will be the total number of unit rate tasks claimed.

b) expressed as a percentage and rounded to the nearest whole number.

The results will be used to help value the Contractor's claim according to General Conditions, Clause 12.1 Contractor's payment claims. Unit Rate Compliance (%) = (Total Number of Tasks Inspected - Number of Non-complying Tasks Identified) Total Number of Tasks Inspected Cyclic Maintenance Tasks For each cyclic maintenance task, the Engineer will: a) inspect each selected section and determine whether it complies with the Contract Documents.

If a defect is identified and a response time is:

stated, the Engineer will re-inspect the section after the specified response time has lapsed. If the defect remains, the section will be non-complying for the month

not stated, the section will be non-complying for the month

b) advise the Contractor of the location of all defects by schedule item, state highway and

reference station within 24 hours of the time each defect is identified. The specific route position of the defect will not be stated

Basis of Payment

1 Preamble

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 5

c) attach a list detailing the specific location of all non-complying defects to the payment certificate.

The percentage compliance will be: i) calculated using the following formula. If the Engineer includes any other sections, not

selected in the original sample, in the assessment, then the sample size used in the calculation will be the total number of sections within the network.

ii) expressed as a percentage, rounded to the nearest whole number. Cyclic Assessment (%) = (Total Number of Sections Inspected - Number of Non-complying Sections Identified) Total Number of Sections Inspected The percentage compliance will be used to value the Contractor's cyclic maintenance claim according to the following table. If the percentage compliance is less than or equal to 29% the work completed by the Contractor during the month is of no value to the Principal and no payment will be made.

Valuation of Contractor’s Monthly Claims

Percentage Compliance Percentage Payment

≥ 90 100

80 to 89 90

60 to 79 70

30 to 59 40

≤ 29 0

v.1.3 Sample Size

The total sample size will be determined by the discretion of the Engineer, subject to the minimum sample size which must be inspected in respect of each claim. If the claim valuation process results in: a) percentage compliance of greater than 95% for 3 or more consecutive months then the

Engineer may, in consultation with the Principal, reduce the minimum total sample size used in the assessment to 5%. If the percentage compliance then drops below 95% then the minimum total sample size will revert to 10%

b) percentage compliance of less than 90% the Engineer may, in consultation with the Principal,

increase the minimum total sample size used in the assessment to a minimum of 20%. If the percentage compliance increases to greater than or equal to 90% for two consecutive months then the minimum total sample size will revert to 10%.

Basis of Payment

1 Preamble

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 6

v.1.4 Defects

The Engineer's discretion inspections may be completed to identify defective work. All defects identified during the payment valuation process and/or identified and/or reported at other times during the month must be rectified within:

a) the specified response time, or

b) one month if no response time is stated. vi. Inspections

The tendered rates must include all the Contractor's costs associated with undertaking and completing all routine and joint inspections.

vii. Stockpile and Disposal Areas

The tendered rates must include all the Contractor's costs associated with the use, management and tidy up of all stockpile and disposal areas (see Maintenance Specification, Section 3 Stockpile and Disposal Areas).

viii. Urgent Work

No additional payment will be made for any work completed as Urgent Work (see Maintenance Specification, Section 4).

ix. Renegotiated Rates

If the number and/or extent of pavement repairs within a 100m treatment length exceed 100m² the Contractor must:

a) complete the work as an area treatment

b) renegotiate the rates for the work to reflect the savings associated with completing larger area treatments rather than smaller individual repairs.

x. Site Investigation and Materials Testing

The tendered rates must include all the Contractor's costs associated with completing site investigations and materials testing.

xi. On-site and Off-site Overheads and Profit

The tendered rates must include all the Contractor's costs associated with all on-site and off-site overheads and profit.

Basis of Payment

1 Preamble

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 7

xii. Scheduled Quantities

The scheduled quantities stated in the Schedule of Prices are for 3 years.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 8

1. Contract Works

1.1 Establishment

Payment will be made as a lump sum per month for each month of the contract period. Payments start from the date of possession of site and end on the Due Date of Practical Completion. The tendered rate: a) covers the Contractor's fixed monthly costs. It will not be changed by any variation affecting

the quantities or quality of materials used, labour expended or plant operated to complete the Contract Works

b) must not be greater than the value stated in the Schedule of Prices. c) excludes costs associated with any Contract Management Review, refer Clause 1.2 below.

1.2 Contract Management Review

Schedule Item 1.1 is a Provisional Item only. Payment will be made for each Contract Management Review undertaken in accordance with Maintenance Specification Section 1. The tendered rate must: a) allow for each review to take 2 days to complete b) fully compensate for completing each review and developing and implementing the Contract

Improvement Plan as specified.

2. Contractor’s Quality Plan

2.1 Preparation and Management of CQP

Payment of the lump sum (LS) will be made as follows: a) 50% when the CQP is agreed

b) Equal proportion of the remaining amount annually, for the duration of the contract. The tendered rate must fully compensate for preparing, accepting, reviewing and updating the CQP in accordance with Maintenance Specification Section 2.

2.2 Quality Control Testing

The tendered rates shall include all the Contractor's costs associated with completing all sampling and testing in accordance with Maintenance Specification Section 2.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 9

3. General Requirements

The tendered rates shall include all the Contractor's costs associated with complying with the Maintenance Specification Section 3.

4. Contractor's Programmes

4.1 Programme Payment will be made for each Programme agreed in accordance with Maintenance Specification Section 4. The tendered rate must: a) fully compensate for preparing, submitting, reviewing, agreeing and implementing each

Programme as specified

b) not be less than nor greater than the values stated in the Schedule of Prices.

5. Contractor's Reports

5.1 Monthly Reports

Payment will be made for each Monthly Report submitted in accordance with Maintenance Specification Section 5. The tendered unit rate must:

a) fully compensate for preparing and submitting each Monthly Report as specified

b) not be less than nor greater than the values stated in the Schedule of Prices. 5.2 Final and Maintenance Reports

The tendered rates must include all the Contractor's costs associated with preparing and submitting the Final and Maintenance Reports in accordance with Maintenance Specification Section 5.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 10

6. Traffic Management

6.1 Preparation of Traffic Management Plan (TMP)

Payment of 100% of the lump sum will be made once the TMP has been agreed.

The tendered rate must fully compensate for:

i) preparing, reviewing, updating and acceptance by the Engineer of the TMP

ii) preparing site specific TMPs which may be required during the contract in accordance with Maintenance Specification Section 6.

6.2 Management of TMP

The tendered rates shall fully compensate for implementing and managing the TMP as specified in the Maintenance Specification Section 6. Tendered rates shall be inclusive of the costs associated with implementation and management of the TMP during any consecutive or concurrent Separable Portions. Where existing TMPs have been approved (unless there are changes to the Code of Practice of Temporary Traffic Manangement (COPTTM) requirements), these approved TMPs may be provided if appropriate for specific circumstances to all tenderers as the basis of pricing e.g. complex temporary traffic management situations. Any changes to the TMP shall be forwarded to the Engineer.

6.3 Traffic Control

The tendered rates must include all the Contractor's costs associated with providing all traffic control in accordance with Maintenance Specification Section 6.

6.4 Additional Traffic Control

This is a Provisional Item and only applies to work completed as Unscheduled Works. Payment will be made for each day additional traffic control is provided in accordance with Maintenance Specification Section 6. The tendered rate must fully compensate for providing all traffic control for each day as specified.

7. Environmental Management

The tendered rates must include all the Contractor's costs associated with developing, implementing, managing and reviewing environmental management measures in accordance with Maintenance Specification Section 7.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 11

8. Unscheduled Works

Schedule Item 8 is a Provisional Item only. In general, payment will be made on a lump sum basis for all Unscheduled Work completed in accordance with Maintenance Specification Section 8. The tendered plant and labour rates must include all costs associated with supplying traffic management which may be required to complete the work. If the work is completed on a dayworks basis, priced Daily Job Records (DJR), refer Appendix 8.1, must be completed to support each claim. The DJR's must accurately reflect the work completed and:

i) include a description of the work completed, including date(s) completed, location and extent

ii) state the type of equipment, total hours, rate and total value of payment claimed for each type of equipment

iii) state the total labour hours, rate and total value of payment claimed. In addition, all invoices for materials used must be available for the Engineer's inspection within one month of the work being completed.

8.1 Plant and Equipment

The tendered hourly rate for plant and equipment including the normal number of operators (plant) will be paid for the number of hours each item of plant is used. If the plant is not used efficiently, the Engineer may reduce the hours paid. The total hours worked is defined when plant:

a) is working with other resources, if appropriate, so the operation is completed with maximum efficiency;

b) is being established or disestablished under its own power to or from the nearest depot, or its previous work site, or the network's boundary, whichever is closer (unless it is cheaper to establish or disestablish the plant by other means);

c) is being loaded on to trucks and transporters whether the operator is assisting or not;

d) in any one hour has idle time of less than 10 minutes. The total hours worked must not include the time when:

e) the plant operator is having breaks or is unavailable;

f) the plant is not working, including periods when the plant is broken down, being serviced, fuelled etc., or transported other than under its own power;

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 12

g) the plant operator is returning to depots at the end of each day without the plant;

h) in any one hour there is idle time in excess of 10 minutes. The tendered hourly rate must fully compensate for the plant operator's wages, the Contractor's profit, on-costs, superintendence, all insurances, levies and holidays with pay and allowances, accommodation and travelling costs, and all clerical, office and all other overhead and incidental costs.

8.2 Materials 8.2.1 Materials

The provisional sum for materials provides for paying the net invoiced cost of all materials, delivered to the site and used for constructing the permanent works by dayworks, as authorised by the Engineer.

8.2.2 Contractor's On-cost to Materials

The percentage on-cost to Schedule Item 8.2.1 applies to the net invoiced cost of materials and must cover all overhead charges and profits.

8.3 Labour

The tendered hourly rate for labour will be paid for the total hours worked. If the labour is not used efficiently the Engineer may reduce the hours paid in direct proportion to the efficiency with which the labour is used. The total hours worked is defined as the hours when the labour is working with other resources, if appropriate, so the operation is completed with maximum efficiency. The tendered hourly rate must fully compensate for:

a) the Contractor's profit, on-cost, superintendence, all insurances, levies and holidays with pay and allowances

b) accommodation and travelling costs, and all clerical, office and all other overhead and incidental costs.

8.4 Cost Fluctuations

The provisional sum allows for the payment of cost fluctuations. Payment will be made according to First Schedule, Clause 12.8.2.

9. Incident Response

Schedule Item 9 is a Provisional Item only.

Payment will be made according to Basis of Payment Clause 8 at the rates tendered under Schedule Item 8.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 13

9.1 Emergency Patrols

Schedule Item 9.1 is a Provisional Item only. Payment for Emergency Patrols will be made according to Basis of Payment Clause 8.1 at the rates tendered under Schedule Item 8.

10. Winter Maintenance

10.1 Weather Monitoring

Payment will be made each month during the winter period for management of a predictive system, to forecast and the pro-active reaction to snow and ice events affecting the highway network, completed in accordance with Maintenance Specification Section 10.

The tendered rate must fully compensate for management of a predictive system, to forecast and the pro-active reaction to snow and ice events including but not limited to:

a) monitoring the system to determine the need to mobilise resources

b) liaison with the Engineer, Police, Automobile Association and Territorial Authorities as required

c) mobilising appropriate resources as required

d) maintaining the road information signs e) the provision of sufficient information to the Network Consultant so the Network Consultant

can update the road information report as specified. Payment for on-site patrolling authorised by the Engineer will be paid for on a Dayworks Basis according to Basis of Payment, Clause 8 at the appropriate tendered rates.

10.2 Plant

Payment for Winter Condition Maintenance Plant will be made according to Basis of Payment, Clause 8 at the rate under Schedule Item 10.2. In addition to Basis of Payment Clause 8.1 the Contractors tendered rate shall allow for all additional costs associated with the initiation, mobilisation and completion of the winter maintenance operations within the stated response times. The rate shall include additional safety personnel and equipment (including pilot vehicles) associated with the winter maintenance operations in addition to normal number of operators for the plant. The cost of supplying and operating grit loading equipment for the loading of the grit ex stockpile is considered to be included in the rate for the Type 4 plant with no additional hours or payment being allowed for such loading plant.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 14

10.3 Materials 10.3.1 Ice Grit

Payment for grit will be made at the rate tendered under Schedule Item 10.3.1 on the loose measure on board the Type 4 plant. The Operator of the plant shall record on a tally docket acceptable to the Engineer the quantity of each load before leaving the grit stockpile area.

10.3.2 CMA

CMA will be supplied by the Principal. Payment for storage and handling (including mixing) of CMA will be made at the rate tendered under Schedule Item 10.3.2 on the measure on board the Type 5 plant. The Operator of the plant shall record on a system or form acceptable to the Engineer the quantity of each load before leaving the CMA loading area.

11. Surfacings

11.1 First Coat Sealing

The tendered rates must include all costs incurred by the Contractor to complete the first coat seals. First coat seals include:

a) single coat first coats and/or two coat first coats and/or premix surfacing

b) if required, temporary or sacrificial seal coats. c) the cost of the correct PSV aggregate for first coat seals which will not be second coat sealed,

in accordance with Maintenance Specification with Section 11. The Contractor will select the sealing technique to address the traffic stresses and price accordingly.

11.2 Second Coat Sealing

Payment will be made for the total area of second coat sealing completed in accordance with Maintenance Specification Section 11. The tendered unit rate must fully compensate for completely constructing the second coat seal and reinstating all pavement markings and raised pavement markers as specified. If the first coat seal is a two coat first coat or premix surfacing and a second coat is not required then no payment will be made.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 15

11.3 Supply of Higher Polished Stone Value (PSV) Aggregate 11.3.1 PSV 51 – 58

The supply of PSV 51- 58 aggregate is deemed to be included in the tendered rates.

11.3.2 PSV 59 – 61 (Over-rate to Schedule) The over-rate shall only be paid on the total area of sealcoat constructed using PSV 59-61 aggregate where this higher PSV chip is required.

11.3.3 PSV > 61 (Over-rate to Schedule) The over-rate shall only be paid on the total area of sealcoat constructed using PSV > 61 aggregate and where this higher PSV chip is required.

11.4 Crack Sealing 11.4.1 Sealing

Payment will be made for the total area of the crack sealing completed in accordance with Maintenance Specification Section 11. The tendered unit rate must fully compensate for completely constructing the crack sealing and reinstating pavement markings and raised pavement markers as specified.

11.4.2 Additive

Payment for Schedule Item 11.4.2 will be in addition to Schedule Item 11.4.1. The tendered unit rate must:

a) be based on the additive specified in the Operational Requirements

b) fully compensate for completely supplying and blending the additive as specified. 11.5 Crack Filling

Payment will be made for the total length of crack filled in accordance with Maintenance Specification Section 11. The tendered unit rate must fully compensate for completely filling each crack as specified.

11.6 Scabbing and Stripping

Payment will be made for the total area of scabbing and/or stripping repairs completed in accordance with Maintenance Specification Section 11.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 16

The tendered unit rate must fully compensate for completely constructing the scabbing and/or stripping repairs and reinstating all pavement markings and raised pavement markers as specified.

11.7 Flushing and Bleeding 11.7.1 Flushing Repairs

Payment will be made for the total area of flushing repairs completed in accordance with Maintenance Specification Section 11. The tendered unit rate must fully compensate for completely constructing the flushing repairs and reinstating all pavement markings and raised pavement markers as specified.

11.7.2 Pavement Gritting

11.7.2.1 Weather Observation Payment will be made for each month over the summer period for all weather observation and associated activities completed in accordance with Maintenance Specification Section 11. The tendered rate must fully compensate for all weather observation and associated activities including but not limited to: a) Monitoring the network to determine the need to mobilise resources b) Liaison with Engineer as required c) Mobilising appropriate resources as required

11.7.2.2 Application Payment will be made according to Basis of Payment, Clause 8 at the rate tendered under Schedule Item 11.7.2.2. The tendered rate must fully compensate for completely supplying and applying the grit as specified.

11.7.2.3 Removal Payment will be made according to Basis of Payment, Clause 8 at the rate tendered under Schedule Item 11.7.2.3. The tendered rate must fully compensate for completely removing the grit as specified.

11.8 Cold Milling

Payment will be made for the total area of cold milling completed in accordance with Maintenance Specification Section 11.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 17

The tendered unit rate must fully compensate for completely constructing the cold milling repairs, protection of all sumps, stormwater outlets and service boxes from damage and contamination with the milled material, removal of all material and reinstating all pavement markings and raised pavement markers as specified.

11.9 Reduction in Size

This is a Provisional Item and will:

a) only apply if the average size of all repairs completed under the Schedule Items for surfacing repairs, where applicable reduces in size by more than 25% from that stated in the Schedule of Indicative Quantities

b) be determined on an annual basis from the date of possession of site. Payment will be made as a lump sum by multiplying the annual value of work completed under the Schedule Items, where applicable by the percentage tendered under various Schedule items in Section 11. The resultant lump sum will fully compensate for all costs associated with the decrease in the average size of repairs completed during the period.

12. Digouts

12.1 Digout Repairs

Payment will be made for the total area of dug out repair completed in accordance with Maintenance Specification Section 12. The tendered unit rate must:

a) include all costs associated with:

reinstating and/or reconstructing the shoulder

constructing the first coat seal, including premix surfacings

if required, a temporary seal coat and reinstating all pavement markings and raised pavement markers

b) fully compensate for completely constructing the digout repair as specified. 12.2 Stabilisation Repairs

Payment will be made for the total area of stabilisation repair completed in accordance with Maintenance Specification Section 12. The tendered unit rate must:

a) include all costs associated with:

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 18

reinstating and/or reconstructing the shoulder

constructing the first coat seal, including premix surfacings

if required, a temporary seal coat and reinstating all pavement markings and raised pavement markers

b) fully compensate for completely constructing the stabilisation repair as specified. 12.3 Digouts in A/C Pavements

This Item applies to completing digout repairs in A/C (asphaltic concrete) pavements only. The Item does not apply to constructing A/C surfaced digouts in chip sealed pavements. Payment will be made for the total area of digout repair completed in accordance with Maintenance Specification Section 12. The tendered unit rate must fully compensate for completely constructing the digout repair and reinstating all pavement markings and raised pavement markers as specified.

12.4 Miscellaneous 12.4.1 Positive Drainage

Payment will be made for the total length of positive drainage constructed in accordance with Maintenance Specification Section 12. The tendered unit rate must fully compensate for completely constructing the positive drainage including reinstatement and resurfacing of the trench as specified.

12.4.2 Geotextile

Payment will be made for the total area of geotextile placed in accordance with Maintenance Specification Section 12. The tendered unit rate must:

a) be based on the geotextile specified in the Operational Requirements

b) fully compensate for completely supplying and placing the geotextile as specified. 12.4.3 Surface Water Channels

This Item:

a) applies to drainage maintenance associated with completing a task or group of tasks

b) does not provide for completing dedicated drainage maintenance works.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 19

Payment will be made for the total length of surface water channel constructed in accordance with Maintenance Specification Section 12. The tendered unit rate must fully compensate for completely constructing the surface water channel, including tying of the new surface water channel into the existing drainage facilities, as specified.

12.4.4 Other Treatments

Payment will be made for the total area or length of repair completed in accordance with Maintenance Specification Section 12. The tendered unit rate must fully compensate for completely constructing the repair as specified.

12.5 Reduction in Size

This is a Provisional Item and will:

a) only apply if the average size of all repairs completed under Schedule Item 12.1, 12.2 and 12.3 reduces in size by more than 25% from that stated in the Schedule of Indicative Quantities

b) be determined on an annual basis from the date of possession of site. Payment will be made as a lump sum, calculated by multiplying the annual value of work completed under Schedule Items 12.1, 12.2 and 12.3 by the percentage tendered under Schedule Item 12.5. The resultant lump sum will fully compensate for all costs associated with the decrease in the average size of repairs completed during the period.

13. Depressions

13.1 Rip and Remake

Payment will be made for the total area of rip and remake completed in accordance with Maintenance Specification Section 13. The tendered unit rate must:

a) include all costs associated with constructing the first coat seal, including premix surfacings, and, if required, a temporary seal coat and reinstating all pavement markings and raised pavement markers

b) fully compensate for completely constructing the rip and remake repair as specified. 13.2 Premix Reshaping

Payment will be made for the total area of premix reshaping completed in accordance with Maintenance Specification Section 13.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 20

The tendered unit rate must:

a) include all costs associated with the cold milling prior to constructing the premix infill and reinstating all pavement markings and raised pavement markers

b) fully compensate for completely constructing the premix shaping repair as specified. 13.3 Reduction in Size

This is a Provisional Item and will:

a) only apply if the average size of all repairs completed under Schedule Item 13 reduces in size by more than 25% from that stated in the Schedule of Indicative Quantities

b) be determined on an annual basis from the date of possession of site. Payment will be made as a lump sum calculated by multiplying the annual value of work completed under Schedule Item 13 by the percentage tendered under Schedule Item 13.3. The resultant lump sum will fully compensate for all costs associated with the decrease in the average size of repairs completed during the period.

14. Edge Break

Payment will be made for the total length of edge break repair completed in accordance with Maintenance Specification Section 14. The tendered unit rate must: a) include constructing the first coat seal, and reinstating all pavement markings b) fully compensate for completely constructing the rip and remake repair as specified..

15. Service Covers

Payment will be made for each service cover adjusted in accordance with Maintenance Specification Section 15. The tendered unit rate must fully compensate for completely adjusting each service cover including constructing the first coat seal and reinstating all pavement markings as specified.

16. Shoulder Maintenance

16.1 Remove High Shoulder

Payment will be made for the total length of high shoulder removed in accordance with Maintenance Specification Section 16.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 21

The tendered unit rate must fully compensate for completely removing the high shoulder including the disposal of all surplus material, sweeping the highway and if required, reinstating all pavement markings and roadside furniture as specified.

16.2 Repair Low Shoulder

Payment will be made for the total length of low shoulder repaired in accordance with Maintenance Specification Section 16. The tendered unit rate must fully compensate for completely repairing the low shoulder including repairing edge rutting, supplying and constructing all makeup material, sweeping the highway and, if required, reinstating all pavement markings and roadside furniture as specified.

16.3 Reshape and Compact Unsealed Shoulder

Payment will be made for the total length of unsealed shoulder reshaped and compacted in accordance with Maintenance Specification Section 16. The tendered unit rate must fully compensate for completely reshaping and compacting the unsealed shoulder, including supplying and constructing all makeup material, sweeping the highway and, if required, reinstating all pavement markings roadside furniture as specified.

17. Barrier Repairs

17.1 Barrier Repairs

Payment will be made for each barrier repair in accordance with Maintenance Specification Section 17.1. The Payment will be based on the rates tendered under Schedule Item 17.1, as detailed in the Schedule of Prices Barrier Repairs Schedule, and the actual quantity of work completed. The tendered rate must: a) include all costs associated with supplying all replacement materials and fabricating each

barrier component if necessary b) fully compensate for completely removing all damaged materials from site and for installation

of the replacement barrier repair, including all components and fixings, as specified.

Any temporary repairs required will be paid for according to Basis of Payment Clause 8 at the rates tendered under Schedule Item 8.

18. Abandoned Vehicles

Payment will made for each abandoned vehicle uplifted, stored and disposed of in accordance with Maintenance Specification Section 18.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 22

The tendered unit rate must fully compensate for uplifting, storage and complete disposal of each vehicle as specified.

19. Potholes

19.1 Repair of Potholes

Payment will be made for each kilometre for each month the network is maintained in accordance with Maintenance Specification Section 19. The tendered unit rate must fully compensate for identifying and completing all permanent repairs as specified for potholes 1m2 or less in area (i.e. excluding practical repairs to individual potholes exceeding 1m2), and not exceeding the quantity stated in the Schedule of Annual Quantities plus 15%. The Engineer will measure compliance and determine the value of the Contractor's payment according to Basis of Payment, Clause (v).

19.2 Additional Potholes

This is a Provisional Item and will:

a) only apply if the number of potholes identified and repaired exceeds the number stated in the Schedule of Indicative Quantities by more than 15%

b) be determined on an annual basis from the date of possession of site. c) payment will be made at the tendered unit rate for each pothole permanently repaired above

the quantity stated in the Schedule of Annual Quantities plus 15%. Payment will be made as a lump sum. This will be calculated by dividing the number of additional potholes by 100, and multiplying this number by the rate tendered under Schedule Item 19.2. The resultant lump sum will fully compensate for all costs associated with identifying and repairing the additional potholes during the period.

20. Detritus and Slip Removal

20.1 Sealed Surfaces

Payment will be made for each kilometre for each month the network is maintained in accordance with Maintenance Specification Section 20. The tendered unit rate must fully compensate for identifying and completely removing all detritus from sealed surfaces as specified. If the Engineer identifies any kilometre or part kilometre that does not comply with the Contract Documents at any time during the month then the:

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 23

a) kilometre will be judged non-complying for the month and b) Contractor's claim for this Schedule Item will be valued according to Basis of Payment, Clause

v).

No additional payment will be made if the quantity of detritus removed exceeds the volume stated in the Schedule of Repair Sizes and Annual Quantities (see Schedule of Prices).

20.2 Lined and Unlined Channels

Payment will be made for each kilometre for each month the network is maintained in accordance with Maintenance Specification Section 20. The tendered unit rate must fully compensate for identifying and completely removing all detritus from lined and unlined channels as specified If the Engineer identifies any kilometre or part kilometre that does not comply with the Contract Documents at any time during the month then the:

a) kilometre will be judged non-complying for the month and

b) Contractor's claim for this Schedule Item will be valued according to Basis of Payment, Clause v).

No additional payment will be made if the quantity of detritus removed exceeds the volume stated in the Schedule of Repair Sizes and Annual Quantities (see Schedule of Prices).

20.3 Slips 20.3.1 Establishment

Payment will be made for establishing all plant at each slip site, or group of slip sites, where the distance between any two adjacent sites is less than 200m apart, or if it is necessary to use transporters to move plant between sites, in accordance with Maintenance Specification Section 20. The tendered unit rate must fully compensate for establishing and dis-establishing all plant as specified.

20.3.2 Removal

Payment will be made for the total volume of slips removed in accordance with Maintenance Specification Section 20 on the loose measure onboard the truck used to cart the material. The operator of the plant shall record on a tally-docket acceptable to the Engineer the quantity of each load removed from the slip site. The tendered unit rate must fully compensate for identifying, completely removing and disposing of all slips as specified.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 24

21. Drainage Systems

21.1 Routine Maintenance

Payment will be made for each kilometre for each month the drainage system is maintained in accordance with Maintenance Specification Section 21. The tender rate must:

a) include all costs associated with drainage fault reporting and preparing, submitting, reviewing and updating the Drainage System Inventory Report

b) fully compensate for completely maintaining the drainage system as specified. The Engineer will measure compliance and determine the value of the Contractor's payment according to Basis of Payment, Clause (v).

21.2 Other Drainage Systems

Payment will be made for each month the specified structures are maintained in accordance with Maintenance Specification Section 21. The tendered unit rate must fully compensate for completing the maintenance as specified. The Engineer will measure compliance and determine the value of the Contractor's payment according to Basis of Payment, Clause (v).

22. Unsealed Pavements

22.1 Potholes

Payment will be made for each kilometre for each month the unsealed pavements are maintained in accordance with Maintenance Specification Section 22. The tendered unit rate shall fully compensate for identifying and completely repairing all potholes in unsealed pavements as specified. If the Engineer identifies any kilometre or part kilometre that does not comply with the Contract Documents at any time during the month then the:

a) kilometre will be judged non-complying for the month

b) Contractor's claim for this Schedule Item for the month will be valued according to Basis of Payment, Clause v).

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 25

22.2 Surface and Shape Restoration

Payment will be made for each kilometre for each month the network is maintained in accordance with Maintenance Specification Section 22. The tendered unit rate shall fully compensate for identifying complete restoring the surface and shape as specified. If the Engineer identifies any kilometre or part kilometre that does not comply with the Contract Documents at any time during the month then the:

a) kilometre will be judged non-complying for the month and

b) Contractor's claim for this Schedule Item for the month will be valued according to Basis of Payment, Clause v).

22.3 Pavement Repairs 22.3.1 Digout Repairs

Payment will be made for the total area of digout repairs completed in accordance with Maintenance Specification Section 22. The tendered unit rate must fully compensate for completely constructing the digout repair, including reinstating the shoulder, as specified.

22.3.2 Stabilisation Repairs

Payment will be made for the total area of stabilisation repairs completed in accordance with Maintenance Specification Section 22. The tendered unit rate shall fully compensate for completely constructing the stabilisation repair, including reinstating the shoulder, as specified.

22.3.3 Miscellaneous 22.3.3.1 Positive Drainage

Payment will be made for the total length of positive drainage constructed in accordance with Maintenance Specification Section 22. The tendered unit rate must fully compensate for completely constructing the positive drainage including reinstatement and resurfacing of the trench as specified.

22.3.3.2 Geotextile

Payment will be made for the total area of geotextile placed in accordance with Maintenance Specification Section 22.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 26

The tendered unit rate must:

a) be based on the geotextile specified in the Operational Requirements

b) fully compensate for the completely supplying and placing the geotextile as specified.

22.3.3.3 Surface Water Channels

This Item:

a) applies to drainage maintenance associated with completing a task or group of tasks

b) does not provide for completing dedicated drainage maintenance works. Payment will be made for the total length of surface water channel constructed in accordance with Maintenance Specification Section 22. The tendered unit rate must fully compensate for completely constructing the surface water channel (including tying of the new surface water channel into the existing drainage facilities) as specified.

22.4 Maintenance Aggregate 22.4.1 Maintenance Aggregate

Payment will be made for the total area of maintenance aggregate constructed in accordance with Maintenance Specification Section 22. The tendered unit rate shall fully compensate for supplying and completely placing the maintenance aggregate as specified.

22.4.2 Clay Additive

Payment will be made for the total area of maintenance aggregate constructed in accordance with Maintenance Specification Section 22. The tendered unit rate shall fully compensate for supplying and completely blending the clay additive with the maintenance aggregate as specified.

23. Drainage Improvements

23.1 Side Slope Shaping (Cut 1 to 6’s) Payment will be made for each lineal metre of side slope shaping completed. This item shall include for grassing, all quality assurance, survey and setout and reinstating all signs, marker posts and culvert markers.

23.2 Clean and Regrade Existing Surface Channel Payment will be made for each lineal metre completed as specified. This item shall include for reinstating all signs, marker posts and culvert markers.

Basis of Payment

2 Payment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

BP 27

23.3 Clean and Regrade Existing Side Drain

Payment will be made for each lineal metre completed as specified. 23.4 Subsoil Drain Cleaning

Payment will be made for each subsoil drain flushed as specified, and shall cover all plant, labour, and transport costs involved in completing the work as specified.

23.5 Replace Culvert Marker Payment will be made for each culvert marker supplied and installed as specified. The tendered rate shall include for numbering of the marker post.

Maintenance Specification

Maintenance Specification

Contents

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

1. Contract Works 1

1.1 Scope 1 1.2 Contract Works' Description 1 1.3 Obligations 3 1.4 Road Classes 5 1.5 Performance Monitoring 5 1.6 Contract Completion 8 1.7 Defects Liability Period 9

2. Contractor's Quality Plan 10

2.1 Scope 10 2.2 Response Times 10 2.3 Contract Quality Plan 10 2.4 Document Procedures 11 2.5 Standards and Materials 13

3. General Requirements 15

3.1 Scope 15 3.2 Response Times 15 3.3 Network Information 16 3.4 Working Hours 16 3.5 Communications 16 3.6 Inspections 18 3.7 Location of Work 19 3.8 Existing Services 19 3.9 Repair of Damage 19 3.10 Reinstatement of Traffic Control Devices 19 3.11 Plant and Equipment 21 3.12 Other Contractors 21 3.13 Publications and Standards 21 3.14 Stockpile and Disposal Areas 22 3.15 Land Entry Agreements 23 3.16 Forward Work Programme Field Inspections 23 3.17 Removal and/or Recycling of Damaged Components 24 3.18 Definitions 24

4. Contractor’s Programmes 36

4.1 Scope 36 4.2 Response Times 36 4.3 Review of Programme 36 4.4 Variation of Method and Dimensions 37 4.5 Preparation of Programmes 37 4.6 Programme Implementation and Management 40

5. Contractor’s Reports 42

5.1 Scope 42 5.2 Response Times 42 5.3 Reports 42

Maintenance Specification

Contents

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

5.4 Monthly Report 42 5.5 Assessment Report 45 5.6 Final Report 45 5.7 Maintenance Report 45 5.8 Work Site Crash/Accident Reports 45

6. Traffic Management 46

6.1 Scope 46 6.2 Response Times 46 6.3 Traffic Management Plan 46

7. Environmental Management 48

7.1 Scope 48 7.2 Response Times 48 7.3 Key Considerations 48 7.4 Resource Consents 49

8. Unscheduled Works 50

8.1 Scope 50 8.2 Response Times 50 8.3 Priced Proposals 50 8.4 Completion 50 8.5 Service Relocation 51

9. Incident Response 52

9.1 Scope 52 9.2 Definitions 52 9.3 Response Times 52 9.4 Specific Requirements 53 9.5 Performance Criteria 56

10. Winter Maintenance 57

10.1 Scope 57 10.2 Definitions 57 10.3 Response Times 57 10.4 Specific Requirements 59 10.5 Treatment 61 10.6 Performance Criteria 65

11. Surfacings 66

11.1 Scope 66 11.2 Definitions 66 11.3 Response Times 66 11.4 Specific Requirements 67 11.5 Treatments 68 11.6 Performance Criteria 71

12. Digouts 73

12.1 Scope 73

Maintenance Specification

Contents

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

12.2 Definitions 73 12.3 Response Times 73 12.4 Specific Requirements 74 12.5 Drainage 77 12.6 Performance Criteria 77

13. Depressions 79

13.1 Scope 79 13.2 Definitions 79 13.3 Response Times 79 13.4 Specific Requirements 80 13.5 Performance Criteria 83

14. Edgebreak 84

14.1 Scope 84 14.2 Definitions 84 14.3 Response Times 84 14.4 Specific Requirements 84 14.5 Performance Criteria 86

15. Service Covers 87

15.1 Scope 87 15.2 Definitions 87 15.3 Response Times 87 15.4 Specific Requirements 87 15.5 Performance Criteria 88

16. Shoulder Maintenance 89

16.1 Scope 89 16.2 Definitions 89 16.3 Response Times 89 16.4 Specific Requirements 89 16.5 Performance Criteria 90

17. Barrier Repairs 91

17.1 Scope 91 17.2 Definitions 91 17.3 Cyclic Inspections 91 17.4 Response Times 91 17.5 Specific Requirements 92 17.6 Materials 94 17.7 Performance Criteria 95

18. Abandoned Vehicles 96

18.1 Scope 96 18.2 Response Times 96 18.3 Specific Requirements 96

19. Potholes 97

Maintenance Specification

Contents

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

19.1 Scope 97 19.2 Definitions 97 19.3 Cyclic Inspections 97 19.4 Response Times 97 19.5 Specific Requirements 98 19.6 Performance Criteria 99

20. Detritus and Slip Removal 100

20.1 Scope 100 20.2 Definitions 100 20.3 Cyclic Inspections 100 20.4 Response Times 100 20.5 Specific Requirements 101 20.6 Performance Criteria 102

21. Drainage Systems 103

21.1 Scope 103 21.2 Definitions 103 21.3 Cyclic Inspections 103 21.4 Response Times 103 21.5 Specific Requirements 104 21.6 Cleaning 105 21.7 Performance Criteria 106

22. Unsealed Pavements 107

22.1 Scope 107 22.2 Definitions 107 22.3 Response Times 107 22.4 Specific Requirements 108 22.5 Performance Criteria 115

23. Drainage Improvements 117

23.1 Scope 117 23.2 Definitions 117 23.3 Response Times 117 23.4 Specific Requirements 117 23.5 Performance Criteria 121

Maintenance Specification

1 Contract Works

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 1

1. Contract Works

1.1 Scope

This Section describes the extent and location of the Contract Works, the Contractor's and Engineer's obligations and describes performance reviews.

1.2 Contract Works' Description

This Contract is for:

a) providing the cost effective road and associated facilities maintenance within a network and the operation of the network. Cost effective maintenance may cause some performance measures, that monitor the network's condition, to deteriorate.

b) providing appropriate resources to respond to incidents (crashes, spills etc.) that may occur within the network

c) providing appropriate resources to respond to incidents (storm damage, emergency events

etc.) that may occur within the network including:

assisting the Engineer to develop appropriate measures and plans to mitigate and manage emergencies, prior to an emergency event occurring.

providing resources and managing the response to incidents and emergency events affecting the safety or integrity of the network.

the reestablishment and/or reinstatement of network access affected by incidents and emergency events at the discretion of the Engineer. The permanent reinstatement of emergency events may be separately contracted.

This Contract is not for upgrading the network to an as new condition. This means it is appropriate for a section of highway:

i) to deteriorate in anticipation of programmed maintenance and/or rehabilitation and/or reconstruction in future years

ii) to have many small repairs rather than single larger repairs that include treatment of sound pavement

The Operational Requirements detail the specific requirements that apply to this Contract.

This contract requires a high degree of co-operation between the Contractor and the Engineer. The detailed investigations carried out by the Contractor to facilitate the design of the works may necessitate review of the outputs of the treatment selection process. In some cases technical reviews may be necessary to resolve the most effective treatment and such reviews may involve the utilisation of external resources. The treatment selection and design processes, and roles and responsibilities relating to these, are described in Transit's State Highway Asset Management Manual.

Maintenance Specification

1 Contract Works

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 2

1.2.1 Extent

The Contract Works (see General Conditions, Clause 1.2) are described in this Maintenance Specification, summarised in the Schedule of Prices and include:

a) implementing a CQP to enable the completion of the Contract Works (see Section 2)

b) providing all labour, plant and materials required to complete the Contract Works.

The Contract Works may exclude:

i) maintaining private accessways and pedestrian facilities located outside the kerb line and/or edge of seal unless specifically provided for in these Contract Documents

ii) maintaining culverts, sumps and associated stormwater structures within urban areas unless specifically provided for in these Contract Documents

iii) drainage maintenance works and major drainage control. These are described in NZTA’s Planning, programming and funding Manual, Section 2.3 under Work Categories 113 and 213

iv) traffic services maintenance

v) pre-surfacing repairs and pre-surfacing treatments

vi) pavement repairs located within sections of pavement that meet the funding criteria for area wide treatment or smoothing projects (see NZTA’s Planning, programming and funding Manual, Sections 2.3, Work Category 111 and Section 2.4, Work Category 214). In general these sections are:

shown in the Ten Year Programme (see Section 4)

are greater than 100m long.

If the maintenance works proceed, they must be completed as an area treatment and revised rates for the work agreed (see Basis of Payment, Clause ix)

vii) Schedule rates do not apply to repairs greater than 100m² in area

viii)Rehabilitation and Construction Works.

The Contractor shall proactively programme Maintenance Area Wide Pavement Treatments (between 100m2 and 800m2), where numerous patch repairs become uneconomic. The Maintenance Intervention Strategy (MIS) details when these Maintenance Area Wide Pavement Treatments are to be programmed. The Contractor and Engineer are to agree that the implementation of repairs will provide for the lowest maintenance cost option before approval. The Contractor shall be responsible for the pavement investigation and design, and shall demonstrate that the required design life is achievable.

Maintenance Specification

1 Contract Works

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 3

If the Engineer requests the Contractor to complete maintenance works described in items vi) and/or viii) above, these works shall be undertaken as a variation in accordance with Section 9 of NZS3910: 2003.

1.2.2 Location

The Contract Works are located within the network described in Operational Requirements, Clause 2. The network includes:

a) all carriageway, bridges and other structures, stormwater structures, roadside furniture and road safety barrier systems, and encompasses the road reserve bound by existing fences or road reserve boundaries

b) all established rest areas and roads, bridges and stormwater structures within these areas.

c) If a local road intersects the state highway at grade, the Contractor must maintain the state highway for a distance of 10 metres from the limit line position or to the end of seal, whichever is the lesser. This maintenance includes:

Pavement maintenance Maintenance of regulatory signs associated with the intersection Maintenance of pavement marking related to traffic control of the intersection where

these are appropriate Maintenance of raised traffic islands related to the traffic control of the intersection

The Contractor will continue to maintain the network through lengths affected by other construction projects, unless directed by the Engineer to stop specific activities.

1.3 Obligations 1.3.1 Contractor's Obligations

The Contractor must:

a) ensure that the proposed treatment is appropriate

b) programme and complete all work in accordance with Section 4. Each Programme must be compiled according to the programming constraints and meet the network's needs

c) establish and maintain appropriate systems to monitor and report against specified performance indicators (see Clause 1.5.3).

d) ensure that sufficient resources are maintained to source the needs of the contract, both for programmed and scheduled works and for unscheduled works and emergency works.

This means the Contractor must:

i) proactively manage this Contract

ii) provide appropriate resources to respond to incidents

Maintenance Specification

1 Contract Works

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 4

iii) intervene so the area and/or type of deterioration does not increase. It is recognised however that the implementation strategies may be necessary, which may result in constraints being placed on maintenance activity and, ultimately, deterioration in the condition of some areas within the network.

iv) programme cost effective repairs. This requires a proactive approach so the first signs of deterioration are addressed. An example of this is completing crack sealing rather than allowing the pavement to fail and completing a digout repair

v) liaise with the other contractors working within the network and in particular the resurfacing and pavement marking contractors.

1.3.1.1. Maintenance on State Highway Benchmark and Calibration Sections

State highway benchmark and calibration sections are listed in the Operational Requirements. The maintenance requirements for these sections are tabulated below:

Table 1.1: Maintenance on State Highway Benchmark Calibration Sections

Section Type

Obtain Approval Prior to

Maintenance work

(Yes / No)

Maintain to Contract Specification

(Yes / No)

Maintenance records provision

Benchmark Section (excluding any calibration length)

No Yes Details entered into RAMM database

Calibration Section (Sterilised)

Yes No

(Hazard Removal Only)

Details entered into RAMM and LTPP Site Maintenance Databases

Calibration Section (Non-Sterilised)

Yes Yes Details entered into RAMM and LTPP Site Maintenance Databases

Note: The completed LTPP site maintenance database for each financial year shall be submitted to the Asset Management Team, NZTA National Office, Wellington annually by the end of July.

Maintenance Specification

1 Contract Works

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 5

1.3.2 Engineer's Obligations

The Engineer will complete routine and specific network inspections and CQP reviews to:

a) assess the Contractor's progress and performance

b) assess the content and appropriateness of all work included in the Contractor's Programmes

c) verify the Contractor's reports

d) certify the Contractor's claims for payment according to the Contract Documents

e) complete performance appraisals. f) updating of the inventories including measures adopted to ensure the accuracy, validity and

completeness of the data presented for updating the Client's databases. 1.4 Road Classes

Table 1.2 Road Classes shows the classification of each highway road within the network.

Table 1.2: Road Classes

Class Type/Volume

M Motorways and Expressways

U Urban State Highways

R1 Greater than or equal to 10,000 vpd

R2 4,000 to 9,999 vpd, Heavy Vehicle and Tourist Routes

R3 1,000 to 3,999 vpd

R4 0 to 999 vpd

1.5 Performance Monitoring

Systems shall be implemented to monitor and report on the performance of the Contract in respect to achievement of performance indicators and compliance with the specified outcomes defined in this contract.

1.5.1 Monitoring by the Engineer

The Principal requires the Engineer to:

a) provide monthly contract progress reports

b) complete performance evaluations:

i) assess the Contractor's overall performance

ii) monitor the performance indicators (see Clause 1.5.3)

iii) assess the culture of the contracted parties and the Engineer's performance

Maintenance Specification

1 Contract Works

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 6

iv) determine the Contractor's overall track record score for the Contract.

All parties will meet with an independent party, if required, and complete each appraisal.

v) If provided for in the Contract Documents, the resulting overall performance appraisal score will be used to determine if the Contract will be extended, see First Schedule, Clause 1.2.

vi) Where provided for in the Contract Documents, any performance appraisal to determine if the Contract shall be extended to the following Separable Portion shall be undertaken by the Engineer 6 months prior to the specified Separable Portion date.

vii) The Engineer shall advise both the Contractor and Principal, in writing, the resulting overall performance appraisal score.

viii) Each evaluation will be completed using the Performance Evaluation Form (PACE), see Appendix 1.2

ix)The evaluation frequency for this contract is to be determined by the Engineer following contract award. General guidelines indicate that evaluation frequencies are set at monthly intervals throughout the contract period, but shall not be at more than 6 monthly intervals throughout the period of the contract.

c) complete a final contract report and determine the Contractors overall track record score. The performance evaluations will be considered in determining the overall track record score.

1.5.1.1. Network Condition Monitoring

The Engineer will provide the Contractor with information on the network (asset) condition on at least a six-monthly basis. This information will be provided in conjunction with the review and acceptance of the Assessment Report (see Clause 5.2). Information will include, where practicable

a) analysis of data collected from network condition monitoring surveys undertaken by or on behalf of the Principal

b) an interpretation of information obtained from joint inspections, Engineer's inspections, and routine surveillance of the network.

The overall assessment will incorporate comments on the Contractors performance (see Clause 1.5.1) and effectiveness of network maintenance and intervention strategies.

1.5.2 Contract Management Review

The purpose of the contract management review (CMR) is to assess the compliance and effectiveness of contract management activities, and the ability of the Contract to achieve specified contract outcomes. The Principal:

a) has developed procedures for the CMR. The CMR will be completed over a two-day period in the Contractor's offices

Maintenance Specification

1 Contract Works

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 7

b) may complete the CMR at least once during the contract period and more frequently if problems are encountered

c) will give 2 weeks notice of the CMR.

The Contractor:

i) must provide a working space and make available contract personnel and records to complete the review

ii) will be provided with a report and, if appropriate, a contract improvement plan. This plan will be used to address areas of non-compliance and to monitor the Contractor's progress and performance.

The results of the review will be included in the Contractors PACE evaluation as well as being included in the assessment of quality (see Clause 1.5.3.3). Evaluations will take into consideration the number and type of non-compliances identified, and the Contractor's ability to meet agreed completion dates in respect to corrective action required in response to the review findings.

1.5.3 Monitoring by the Contractor

Except for the network condition monitoring, which shall be monitored by the Engineer., the Contractor must monitor their own performance and in particular the following performance indicators. The updated Performance Indicators must be included in the Monthly Report (see Section 5).

1.5.3.1. Financial Performance

The following financial performance indicators will be measured:

a) Accrued Value of Work versus Budget and Updated Forecast

b) Value of Monthly Programmes versus Budget, Forecast and the value certified for payment

c) Value of Outstanding Work and Work In Progress.

The financial performance indicators will be measured for each payment schedule item and the Contract Works (see Sections 4 and 5).

1.5.3.2. Achievement

The following achievement indicators will be measured:

a) the number of unit rate tasks completed each month compared to the number of tasks programmed, and if they are included

b) the percentage and/or number of cyclic activities completed compared to the percentage and/or number programmed

c) the number of faults the Engineer identifies that were not rectified within the specified response times

Maintenance Specification

1 Contract Works

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 8

d) the number of outstanding tasks each month compared to the number of tasks programmed. 1.5.3.3. Quality

The following quality indicators will be measured:

a) the number of non-complying tasks compared to the number of tasks programmed. The term 'non-complying tasks' is defined as including; repairs outside specification, failure of repair, and complaints; including those identified both internally and externally (e.g. by the Engineer or Public)

b) samples of the Contractor's records, including minutes of meetings etc., that demonstrates the Contractor's procedures for handling quality issues

c) CQP compliance (see Section 2)

d) the number and/or type of Non-Compliances identified in internal contract systems compliance audits, reviews and/or audits by the Engineer (see Clause 1.5.1) and (where appropriate) contract management reviews (see Clause 1.5.2)

e) any other indicators developed during the contract period. 1.5.3.4. Safety (including Traffic Management)

The following safety indicators will be measured:

a) the number of near misses identified

b) the numbers of work site crash/accidents, observed crashes, and/or crash evidence

c) TMP compliance (see Section 6)

d) samples of the Contractor's records, including minutes of meetings etc., that demonstrates the Contractor's procedures for handling safety issues

e) any other indicators developed during the contract period. 1.6 Contract Completion

Within 7 days of completing each Separable Portion and/or the Contract Works (see First Schedule, Clause 10.2.1), the Contractor must:

a) write advising the Engineer that all works are complete and comply with the Contract Documents

b) request the Certificate of Practical Completion for each Separable Portion and/or the Contract Works.

Maintenance Specification

1 Contract Works

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 9

1.7 Defects Liability Period

A minimum of two weeks before the defects liability period is complete, (see First Schedule, Clause 11.1.1) the Contractor must request the Defects Liability Certificate for each Separable Portion and/or the Contract Works.

The Defects Liability Certificate will not be issued until the Contractor has demonstrated the Contract Works comply with the Contract Documents.

Maintenance Specification

2 Contractor's Quality Plan

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 10

2. Contractor's Quality Plan

2.1 Scope

This Section sets out the minimum requirements for the quality assurance of the Contract Works.

The work required shall be completed in accordance with Section 1, TNZ Q/4 and the following requirements.

2.2 Response Times

Table 2.1 states the response times for preparing, submitting, reviewing, updating and accepting the CQP.

Table 2.1: Contract Quality Plan

Activity Assessment

Draft CQP Within 3 weeks of the Date of Acceptance of Tender

Final CQP Within 1 week of the Engineer’s review of the draft CQP and before the date of possession of site

Pre-commencement Review A minimum of 72 hours following the Engineer’s notification of the review

Surveillance Review A minimum of 24 hours following the Engineer’s notification of the review

Annual CQP Review Within 3 weeks of the anniversary of Acceptance of Tender

2.3 Contract Quality Plan

The Contractor must develop the Contract Quality Plan (CQP), and the contract works must be undertaken in accordance with the CQP. The CQP must be based on the Contractor's quality, health and safety and environmental management systems. Nothing in the CQP will take precedence over the requirements of the Contract Documents. In particular, nothing in the CQP will relieve the Contractor from the performance of the Contractor's obligations under the Contract Documents even though the CQP has been approved by the Principal or the Principal's Agent.

2.3.1 CQP Implementation and Management The CQP must be implemented and managed so: a) the Contract Works are identified, programmed and completed within the response times

specified

b) the Contract Works are completed according to the Contract Documents

c) the Contract Works are completed so that the Contractor's current processes and standards are reflected

d) the contract personnel schedule is up to date.

Maintenance Specification

2 Contractor's Quality Plan

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 11

2.3.2 CQP Acceptance and Reviews

The Contractor is to submit a Contract Quality Plan (CQP) to the Engineer for review. The Engineer will mutually agree to its content and appropriateness with the Contractor. Once finalised, the Engineer will advise the Contractor of formal acceptance of the CQP. The Engineer may, from time to time at their discretion, undertake formal or informal reviews of the CQP or parts of the CQP, associated systems and samples of contract records.

2.4 Document Procedures The CQP must include or reference documented procedures for at least the following:

2.4.1 Contract Quality Plan

Implementing and managing the CQP including: 2.4.1.1. Correspondence

Inwards and outwards correspondence, including the submission of all information to the Engineer. 2.4.1.2. Materials Testing

The Contractor to nominate the type, number and frequency of all the Contractor's proposed testing of the materials to be included in the Contract Works.

2.4.1.3. Measurement and Testing

The selection, inspection, measurement and testing of random samples of Unit Rate Tasks completed during each month (construction review) and during the previous six months (post construction reviews).

The construction review must include a minimum of 10% of the total number of tasks completed during the month.

The post construction review must include a minimum of 5% of the total number of tasks completed during the previous six months.

The procedure must detail the:

a) method for selecting the random samples

b) recording of the results and, if required, initiating remedial works. 2.4.1.4. Contract Records

Records compilation and management that demonstrate the materials, work methods and completed works comply with the Contract Documents.

Maintenance Specification

2 Contractor's Quality Plan

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 12

The Contractors Records shall be any information either required to be submitted by the Contract Documents and/or requested to be submitted by the Engineer.

2.4.1.5. Sub-contractors

Sub-contractors management, including the specific procedures implemented to ensure their compliance with the CQP.

2.4.1.6. Non-complying Work

Identifying, recording and rectifying non-complying work, including procedures for completing remedial work, and reporting to the Engineer (see Clause 1.5.3.3).

2.4.1.7. CQP Auditing

Auditing the CQP, including frequency of each audit. 2.4.2 Health and Safety

Preparing, implementing and managing a health and safety plan. The plan must consider the Health and Safety Compliance Notice (see Appendix 2.1) and the following: a) hazard identification and management

b) informing and training of staff

c) crash/accident recording, reporting and investigation systems

d) monitoring the procedures to ensure their compliance with the system and its performance. 2.4.3 Contractor's Programmes

Preparing, implementing and managing the Contractor's Programmes' (see Section 4), including, but not limited to:

a) identifying and prioritising all faults for both Unit Rate and Cyclic Maintenance Items

b) the selection of cost effective treatment methods

c) intervention strategies for identifying and completing cyclic maintenance works

d) compilation of each Programme, and where required, adjusting the content of the Programme to meet the programming constraints

e) re-prioritising all tasks so the Programme continually addresses the network's needs

f) where appropriate, the design of each task. This procedure must address design and construction factors such as subgrade strength, backfill materials, depth and compaction, stabilisation agent, depth and surfacing.

2.4.4 Contractor's Reports

Preparing and submitting the Contractor's Reports (see Section 5).

Maintenance Specification

2 Contractor's Quality Plan

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 13

2.4.5 Traffic Management Preparing, implementing, reviewing, updating and managing the Contractor's TMP (see Section 6) including, but not limited to: a) training the Traffic and Safety Manager and assistants

b) procedures for assessing TMP compliance, and developing and implementing appropriate corrective actions

2.4.6 Environmental Management

Undertaking Environmental Management, including the systems, work practices and actions the Contractor will take to: a) avoid and mitigate social and environmental effects associated with the contract works in accordance with Section 7 b) ensure that all procedural, monitoring and reporting requirements of resource consents, New Zealand Historic Places Trust, archealogical authorities and the HSNO Act 1996 are complied with.

2.4.7 Completion of Work Completing all work required by these Contract Documents including but not limited to: a) selecting plant and materials

b) implementing appropriate levels of traffic management

c) establishing controls to ensure the completed works conform to the construction tolerances

d) completing the Contract Works.

2.5 Standards and Materials

2.5.1 Relevant Standards and Specifications All sampling and testing must be undertaken according to the relevant standards and specifications as listed in Appendices 3.2, 3.3 and 3.4. All materials used in the Contract Works must comply with their respective standard specifications as listed in Appendices 3.2, 3.3 and 3.4.

Maintenance Specification

2 Contractor's Quality Plan

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 14

2.5.2 Materials

All materials must be sampled and tested by an ISO/IEC 17025 accredited testing laboratory accredited for the relevant test. Sampling may be completed by non-laboratory personnel, provided they are registered samplers operating under the direction of the accredited laboratory completing the testing. All handling of hazardous substances, e.g. herbicides, shall be in accordance with the requirements of the Hazardous Substances and New Organisms (HSNO) Act 1996.

2.5.3 Acceptance Testing

Appendix 2.2 states the minimum frequency of sampling and testing of the Contract Works. 2.5.4 Construction Tolerances

Appendix 2.3 states the construction tolerances for the Contract Works.

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 15

3. General Requirements

3.1 Scope

This Section sets out the general requirements of the Contract Works.

The work required by this Section must be completed in accordance with Sections 1 and 2 and the following requirements.

3.2 Response Times

3.2.1 Contractor's Routine Inspections

The Contractor must complete cyclic and routine inspections, including, if required, night inspections, at intervals so that all faults are identified, programmed and repaired according to the contract documents.

If the Contractor identifies any defect including defective workmanship, which may affect road user safety, the Engineer must be advised within 24 hours.

The Contractor will notify the Engineer immediately of any hazards which may affect road user safety.

3.2.2 Joint Inspections

Joint Inspections will be undertaken within the response times stated in Table 3.1 and in accordance with Section 3.6 Inspections.

Table 3.1: Joint Inspections

Score Assessment

Initial Joint Inspection Within 1 week of the date of possession of site

Routine Joint Inspections At regular intervals, as programmed and agreed with the Engineer

Final Joint Inspection During the last two weeks of the contract and defects liability period

3.2.3 Public Complaints

Any work required to correct a deficiency that has originated from a public complaint to the NZTA will be undertaken within the response time for the task required as specified. This response time will apply whether the work is scheduled or unscheduled and will require the Contractor to adjust their programme to achieve remedial work within the specified response time. Where this will result in significant disruption to the programme, the Engineer may agree to an extension on this time for specific repairs, but in all circumstances the work must be completed within the minimum time reasonably achievable. The number of time extensions is not expected to be more than 12 per year. This work will be paid for at scheduled or unscheduled tendered rates as appropriate.

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 16

3.3 Network Information

Appendix 3.1 lists the Network Information that will be provided to the Contractor at the initial contract meeting.

3.4 Working Hours

The Contract Work may be completed on any Working Day at any time. However, no work affecting the traffic lanes may be completed during periods of peak traffic flow in urban areas unless otherwise agreed with the Engineer. a) where traffic lanes will be affected, during periods of peak traffic flow in urban areas unless

otherwise agreed with the Engineer

b) during times specified in the Operational Requirements.

However the Contractor will be required to respond to any work falling under the Incident Response Section at any time on any day. The obligations in this contract are to maintain the network at all times.

3.5 Communications 3.5.1 Meetings 3.5.1.1. Initial Meeting

Before the date of possession of site, the Contractor must contact the Engineer to arrange the initial contract meeting. The meeting will be held at the Engineer's office at an agreed time.

3.5.1.2. Monthly Meeting

Monthly meetings will be held at an agreed time and venue. 3.5.2 Contractor's Communications

The Contractor must maintain:

a) a staffed telephone or cellular phone during normal business hours (8.00am - 5.00pm Monday to Friday)

b) a facsimile machine

c) after-hours contact numbers for key personnel (including, where approved, a pager or answering service).

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 17

3.5.3 Public Contacts

The Contractor must establish a system for receiving and logging all public contacts. The log must record the substance of the contact, time received and the time and details of actions taken to resolve it as appropriate.

If the Contractor considers that the contact falls outside the scope of this Contract, the matter must be referred to the Engineer within two hours of receiving the contact.

3.5.4 Publicity

The Contractor:

a) may not publish or provide to any third party copies of photographs or other details of the Contract Works without the prior approval of the Engineer

b) must allow access to the site to any person(s) designated by the Engineer to take photographs

c) may display non-illuminated signs attached to their site accommodation giving the name of their firm and contact numbers. No other promotional publicity is permitted.

3.5.5 Network Information Requests

The Contractor must forward all requests for network information, including achievement and condition information, received from third parties to the Engineer for action.

3.5.6 Road Event Information Monitoring and Management

The NZTA operates a 24-hour, 7 day a week, internet based advanced traveller information system for road users designated as the Traffic Road Event Information System (TREIS). The Contractor will monitor and manage the state highway condition information within the TREIS system for the extent of the contract network and be responsible for:

a) Ensuring the delivery of accurate, timely and relevant information about the State

highway conditions within the contract network to enable:

Road users to have knowledge about the current condition of the State highway in the contract area in order to plan their intended travel; and

The manner in which the information is delivered builds confidence in the usefulness of the information and it’s supplier(s); and

b) Ensuring national consistency of information being entered into the TREIS system.

The Contractor shall carry out the above duties by:

a) Instigating regular checks of the TREIS system while an event is underway and updating the TREIS information until such time as the highway section is re-opened;

b) Ensuring that there are routine checks of the TREIS information so that outdated data is not left in the system;

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 18

c) Ensuring that there are routine checks of the TREIS information so that information entered by other parties can be checked and verified; and

d) Ensuring that there are routine checks of the TREIS information so that the quality of the information meets national expectations.

The Client will supply the Contractor with the business rules for the TREIS system including the method and expectations of entering data into the system directly.

3.6 Inspections 3.6.1 Joint Inspections

Joint inspections will be completed at regular intervals during the contract period. The purpose of these inspections is to monitor the:

a) Contractor's progress and performance

b) network's condition while under the Contractor's management.

The Assessment Report will be completed as part of these inspections.

Joint inspections will also be held within two weeks of the end of the contract and defects liability periods. If remedial work is required, this must be completed before the Certificate of Practical Completion and/or Defects Liability Certificate (see Clause 1.6 and 1.7) is issued. A report shall be completed identifying any defect or item requiring attention, noting the agreed action to remedy, with timing. Report to be agreed to and signed by the Contractor and the Engineer.

3.6.2 Engineer's Inspections

The Engineer will complete regular routine inspections of the network (independent of the Contractor). The purpose of the inspections is to monitor the:

a) Contractor's progress and performance

b) network condition.

The Engineer may advise the Contractor of the inspection results.

If the inspection reveals any faults or non-complying tasks, the Contractor must remedy these by the dates agreed with the Engineer so they comply with the Contract Documents.

3.6.3 Handover Inspections

Handover inspections will be held: a) a minimum of two weeks before the date of possession of site

b) within two weeks of the end of the contract period

c) two months before the end of the Period of Defects Liability.

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 19

The inspection will involve the Engineer, Contractor and either the current or new contractor as appropriate. The purpose of the inspections is to determine and agree the extent of work required to be completed before the Contractor takes possession of site and/or hands the site over at the end of the Contract Period. A report shall be completed identifying any defect or item requiring attention, noting the agreed action to remedy, with timing. Report to be agreed to and signed by the Contractor and the Engineer.

If required, all remedial work must be completed within the agreed time frames and before the Certificate of Practical Completion and/or Defects Liability Certificate are issued.

3.7 Location of Work

The Contractor must measure and report the route position of all works in accordance with the Location Referencing Management System Manual (SM051) to an accuracy of +/- 10m when measured from the nearest reference station or ERP sign.

3.8 Existing Services

All damage to existing service(s) caused by the Contractor, including traffic detection hardware, private services e.g. domestic water supply, must be immediately reported to the appropriate service authority. The Contractor must meet all costs associated with the repair of the service(s).

If any service requires relocation and/or protection before completing programmed work, the Contractor must arrange for this in accordance with Section 8.

3.9 Repair of Damage

It shall be the Contractor’s responsibility to protect the road asset, plus drainage features, traffic control devices, roadside furniture and other roading assets during the course of the contract. Any preventable damage, as judged by the Engineer, caused to these facilities by the Contractor shall be made good at the Contractor’s expense unless agreed with the prior approval of the Engineer.

All damage must be repaired to the appropriate Transit/NZTA Standards, the satisfaction of the Engineer, and within 24 hours from the time the damage occurred or within the timeframe agreed with the Engineer and detailed in the Quality Plan.

3.10 Reinstatement of Traffic Control Devices 3.10.1 Pavement Markings and Raised Pavement Markers

When the treatment and/or repair is complete, all pavement markings shall be reinstated in accordance with Specification TNZ P/22 and raised pavement markers shall be reinstated in accordance with TNZ P/14. However, if the marking is less than 150m in length the standards may be relaxed by the following:

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 20

The paint pavement marking equipment does not require a TNZ T/8 Certificate and

requirements for the pavement marking applicator and any attendant vehicles are deleted.

The Contractor may decide that quality assurance is not required for the placement of raised pavement markers or the painted pavement markings.

Deletion of the requirement for a materials diary.

The cost for this reinstatement work shall be covered in Contract rates submitted for all highway operations and maintenance work. Raised pavement markers must not be reinstated on temporary seal coats or first coat seals.

3.10.2 Removal of Existing Pavement Markings Where pavement marking removal is required, the Contractor shall submit to the Engineer for approval the proposed pavement marking removal technique, following the principles outlined in the NZRF Line Removal Guide, Appendix 2 Section 12 NZRF, Health and Environment Guide.

3.10.3 Edge Marker Posts Where edge marker posts require temporary removal in order to facilitate work, edge marker posts shall be reinstated prior to the end of each day and before temporary traffic control signs are removed. Edge marker posts shall be replaced in accordance with TNZ P/16 and materials shall comply with TNZ M/14. Any marker posts damaged by the Contractor’s operations shall be replaced with a new marker posts at the Contractor’s expense, within the timeframe agreed with the Engineer.

3.10.4 Permanent Signs Where permanent signs require temporary removal in order to facilitate work they shall be: replaced with temporary signs prior to removal

reinstated prior to the end of each day or before temporary traffic control signs are removed

replaced to the position where they were originally found. Any permanent sign damaged by the Contractor’s operations shall be replaced with new hardware at the Contractor’s expense in accordance with the requirements of TNZ P/24, MOTSAM, and the Traffic Control Devices Manual, within the timeframe agreed with the Engineer.

3.10.5 Vehicle Detection Loops

All existing inductance loops relating to traffic counting, traffic signal control and speed cameras must be protected at all times. The Contractor must liaise with the person responsible for the inductance loops (Traffic Signal Maintenance Contractor / Traffic Counting Contractor / Speed Camera Contractor), where physical work is likely to affect operation.

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 21

3.11 Plant and Equipment

All plant and equipment must be selected to minimise damage to the pavement, traffic control devices, roadside facilities and surrounding area. The Contractor may be instructed to remove any excessively weighted or sized plant which may adversely affect the condition of the network.

All plant and equipment must be :

a) registered for normal use on the road b) operated on surfaced roads so the turning and/or traction of tyres and/or steel blades and

buckets does not cause displacement of the surfacing materials.

Tracked machinery must not be operated on any surfaced pavement without the Engineer's prior approval.

In addition, the Contractor must ensure

i) the movement of any steel drummed compaction equipment outside the area of the task is minimised

ii) equipment depositing bitumen and emulsion outside the area of the work is removed from site.

If any damage to the network is caused by the Contractor's operation it must be repaired, at the Contractor's cost, to a standard no worse than that existing before the work began.

3.12 Other Contractors

Contractors may be working within the network at various times (see General Conditions, Clause 5.5). This work may include but is not limited to other routine maintenance works, pre-reseal repairs and associated surfacing works, installation of services.

The presence of other contractors does not relieve the Contractor of their obligations to maintain the network according to the Contract Documents, unless the presence of other contractors directly affects the Contract Works.

In this case the Contractor must advise the Engineer within 24 hours.

3.13 Publications and Standards

In addition to this Specification, the following Transit/NZTA publications and standard specifications also form part of but are not reproduced in the Contract Documents. If there is any ambiguity or contradiction between this Specification and any publication or standard specification, this Specification will take precedence.

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 22

Unless otherwise stated:

a) reference to a standard specification refers to the edition listed in Appendix 3.3.

b) it is the Contractor's responsibility to make reference to their own set of these publications.

Revised publications and/or standards may be issued during the contract period. The Engineer reserves the right to negotiate the requirements of these documents as a variation to the Contract.

3.13.1 C Series Specifications

Appendix 3.2 lists the Transit C Series Specifications that apply to this Contract. These are available to download from the NZTA website.

3.13.2 Standard Specifications

Appendix 3.3 lists the Transit/NZTA Standard Specifications that apply to this Contract. 3.13.3 Other Publications

Appendix 3.4 lists the other publications that apply to this Contract. 3.14 Stockpile and Disposal Areas 3.14.1 Principal's Areas

Appendix 3.5 lists the stockpile and disposal areas that may be used by the Contractor. The specific conditions for their use are also referenced.

In general, these areas must be maintained to a condition no worse than that existing at the date of possession of site. Unless otherwise approved by the Engineer, all surplus materials shall be removed from stockpile areas and other areas within the road reserve used for storing materials within one month of construction.

3.14.2 Other Areas

The Contractor:

a) is responsible for locating, gaining legal entry to, gaining resource consents or concessions for establishing, maintaining access and drainage, controlling work and reinstatement of other stockpile and disposal areas, in accordance with local authority and Department of Conservation requirements

b) must notify the Engineer of the location of all disposal sites and, prior to their use, must submit copies of any resource consent(s) or concessions required for these areas (see Section 7)

c) must provide written evidence that the conditions have been fulfilled.

The Defects Liability Certificate will not be issued until this written evidence is received.

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 23

3.14.3 Controlling Areas

Stockpile and disposal areas shall be controlled to prevent the carrying of material onto the seal by vehicle tyres.

3.15 Land Entry Agreements

Appendix 3.6 lists the land entry agreements that have been made for access into adjoining properties to complete routine maintenance work, such as stormwater structure maintenance.

The Contractor must comply with the specific requirements of each agreement.

3.16 Forward Work Programme Field Inspections 3.16.1 Objectives / Requirements

The objectives of involving the Contractor in the Forward Work Programme Field Inspections are as follows:

to increase the awareness of the Contractor concerning the inputs and strategies involved with

the development of the Forward Work Programme (FWP).

to increase the awareness of the Contractor concerning the way the available network information data is used to schedule future treatments.

to increase the understanding of how the actions or inactions of the Contractor can affect the condition of the network, and on the programming of future treatments.

to utilise the Contractor’s network knowledge in any reviews of the FWP.

to ensure that the Contractors knowledge of network performance based on their inputs are taken into account

The Contractor is to make available at least one management staff member to accompany the Engineer during the FWP field inspections required bi-annually each year of the Contract.

It is the NZTA’s expectation that the Contractor’s staff member will be someone who is closely associated with the development of the Contractor’s monthly pavement maintenance programmes, has an in depth understanding of the Maintenance Intervention Strategies that need to be applied, and has a detailed understanding of the network and its characteristics.

The Forward Work Programme (FWP) is a commitment by the NZTA, and therefore can always be used for programming, however it is always subject to change. The risk of change is reduced following the October review one year in advance of when the reseal is due to commence. Pre-reseal repairs should be identified and programmed in the subsequent year reseal lengths as soon as possible following receipt of the October review of the Forward Work Programme.

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 24

3.17 Removal and/or Recycling of Damaged Components

The Contractor is responsible for dismantling and removal from site of all damaged or broken components. However, where possible the Contractor is encouraged to recycle components which may be damaged but provide additional life without compromising the level of service required or standards.

3.18 Definitions In addition to First Schedule, Part B, Clause 1.2 Definitions, see Table 3.2 Definitions below, which are included within the Maintenance Specification and provide clarification. Entries in CAPITALS are defined further as a separate definition entry.

Table 3.2: Definitions

Term Definition

Adjacent Highway Operations and Maintenance Contractor

Generally refers to the maintenance contractor who looks after the next stretch of state highway beyond the contract boundary. However, in Auckland, this could be a Local Authority maintenance contractor. I.e. Greenlane could be deemed a “highway”. Refer to the region’s Emergency Procedures Manual, to clarify.

Agrichemical Any substance whether inorganic or organic, man made or naturally occurring, modified or in its original state, that is used in any agriculture, horticulture or related activity to eradicate, modify or control flora and fauna (NZS 8409 New Zealand Standard Code of Practice for the Management of Agrichemicals).

Anti-Icing The application of a liquid CHEMICAL to trafficked surfaces prior to the formation of ICE to prevent ICE forming or binding to the PAVEMENT. See also DE-ICING.

Archaeological site Archaeological site is defined in section 2 of the Historic Places Act 1993. In terms of this definition a site could include an object or material.

Asphaltic Concrete

A mixture of bituminous binder and aggregate with or without mineral filler produced in a mixing plant. It is delivered, spread and compacted while hot, for use in road construction. See also HOT MIX ASPHALT.

Barrier See ROAD SAFETY BARRIER. Batter The uniform SIDE SLOPE of walls, banks, cuttings, etc. The amount of

such slope or rake, usually expressed as a ratio of horizontal to vertical, distinct from grade. In the context of VEGETATION CONTROL, that portion of road reserve (land) between the SURFACE WATER CHANNEL and the legal road boundary, excluding any SIDE DRAINS; sand inclusive of cuts/fills/embankments or flat/sloping ground. See Diagram 3.1.

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 25

Bleeding The exudation of bituminous binder onto the road surface. Bleeding binder may being picked up on the tyres of passing traffic. It is distinguished from FLUSHING, which is a solid smooth surface caused by binder rise to the extent that the binder is above the surfacing aggregate. Bleeding may occur without the presence of any significant FLUSHING. FLUSHING may be the end result of extensive bleeding.

Bridge A bridge is any structure carrying traffic on, under or over the highway, and includes any CULVERT with a waterway area greater than 3.4m2 It includes but is not limited to CULVERT, stock or traffic underpasses or overbridges and conventional bridges.

Carriageway The portion of a road or BRIDGE devoted particularly to the use of vehicles, inclusive of SHOULDERS and auxiliary lanes. Divided roads are considered to have two carriageways. See also SEALED CARRIAGEWAY, SEALED SHOULDER, UNSEALED SHOULDER.

Chemical In the context of VEGETATION CONTROL, any HERBICIDE. In the context of Winter Maintenance, a solid or liquid CHEMICAL DE-ICING agent added to trafficked surfaces to prevent ICE forming on the road surface or to assist with the removal of snow or ICE once formed.

Chemical Control The control of VEGETATION to the required standard by the use of HERBICIDES.

Cold Milling or Cold Milled

A method of automatically controlled removal of PAVEMENT to a desired depth with uniquely designed equipment. Generally used as part of the process to achieve restoration of a surface to a specified grade or slope, free of high points, ruts and other imperfections. The resulting textured PAVEMENT surface can be used immediately as a driving surface, and is usually then overlaid with a new surfacing.

COPTTM Code of Practice of Temporary Traffic Management. Cracking The appearance in the road surface of small, regular, or irregular shaped

continuous areas with fissures. Examples include: alligator Cracking, also known as chicken wire or crocodile

cracking: semi-regular polygon shaped contiguous areas of cracking, irrespective of the size of the polygon.

block Cracking: a pattern of cracking of a PAVEMENT surface that appears as a series of connected rectangles, irrespective of the size of the rectangle.

reflective Cracking: visible cracks in the PAVEMENT surfacing, caused by propagation of cracks through to the PAVEMENT surface from the underlying PAVEMENT layer.

longitudinal and Transverse Cracking: long cracks that run along or across the road.

shrinkage Cracking: cracks caused by shrinkage of old bituminous surfaces.

slippage Cracks: occur only in thin ASPHALTIC CONCRETE wearing course. They are usually crescent shaped and point in the direction of the thrust of the wheels on the PAVEMENT.

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 26

Culvert One or more adjacent pipes or enclosed CHANNELS for conveying a

watercourse or stream below the formation level of a road up to a maximum size of 3.4 m2 cross sectional area. A CULVERT marker peg marks its position. See also DRAINAGE SYSTEM, ROUTINE DRAINAGE MAINTENANCE and STORMWATER STRUCTURE.

Cyclic Inspection A type of ROUTINE INSPECTION, carried out at the specified inspection frequency.

Damage Any gouging of the PAVEMENT, removal of the seal, removal or harm caused to DRAINAGE FEATURES, TRAFFIC CONTROL DEVICES, ROADSIDE FURNITURE or other road assets so that they no longer meet specification.

Defects Liability Period

The period of a construction contract during which the Contractor is responsible for repairing or rectifying defects that appear in the Works. The period usually commences upon practical completion of the Works and runs for a specified time frame (sometimes also known as the maintenance period.

De-icing The application of a solid CHEMICAL to trafficked surfaces to assist with the removal of snow or ICE once formed. See also ANTI-ICING.

Depression A road defect in which the road surface has sunk. Depressions will vary in shape and can develop either without loss of waterproofing (e.g. wheelpath rutting) or due to loss of waterproofing (e.g. areas where water can pond and may be associated with PAVEMENT settlement). Depressions may be isolated or not, roughly circular in shape or of considerable length along the wheelpaths.

Detritus Any collection of fragments or material on the SEALED CARRIAGEWAY surface or in DRAINAGE FEATURES. Detritus includes loose sealing chip, PAVEMENT aggregate, dead animals, SLIPS, deposits of wind blown sand or GRIT, deposits of loose aggregates, fallen leaves and the result of the build up of minor droppings or spillages created from passing traffic or climatic conditions. See also SLIPS. Detritus in the context of DRAINAGE FEATURES may include wood debris, LITTER, and VEGETATION.

DJR Daily Job Record. A record detailing resource utilisation as illustrated in Appendix 8.1.

Drainage Natural or artificial means for intercepting and removing surface or subsurface water (usually by gravity). See also DRAINAGE SYSTEM.

Drainage Faults For sumps, SERVICE HOLES (MANHOLES), catchpits and other DRAINAGE FEATURES, a fault exists:

(a) if more than 30% of the volume of the structure is filled with debris or the debris is within 200mm of the outlet pipe invert and/or

(b) more than 10% of the outlet pipe entry area is covered with debris.

For CULVERTS, a fault exists when more than 10% of the depth of the CULVERT inlet, outlet or barrel, along its entire length, is filled with

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 27

debris. For SIDE DRAINS, a fault exists if water ponds and/or water does not readily flow to the outlet points. See also ROUTINE DRAINAGE REPAIRS, ROUTINE DRAINAGE SYSTEM MAINTENANCE and Diagram 3.1.

Drainage Feature Any feature that forms part of the DRAINAGE SYSTEM. These include STORMWATER STRUCTURES, SIDE DRAINS, lined and unlined CHANNELS.

Drainage System Includes all STORMWATER STRUCTURES, SURFACE WATER CHANNELS, SIDE DRAINS and other features associated with controlling stormwater and runoff from the NETWORK. This includes BRIDGE deck DRAINAGE including CHANNELS and outlets.

Edge Break Fretting or breaking of the edge of a bituminous surface, such that the loss of surfacing encroaches into the CARRIAGEWAY by more than 100 mm from the nominal seal edge or onto the white edge line.

Edge Rutting A defect where ruts appear at the edge of a bituminous surface, usually in the UNSEALED SHOULDER.

Extreme Snow and Ice Events

Extreme weather events that result in short periods of times when specified winter maintenance levels of service cannot be maintained. See also ANTI-ICING, DE-ICING, ICE, SNOW CLEARANCE and WEATHER MONITORING.

Flushing A flushed surface is one in which the binder is approaching or above the mean level of the top of the surfacing aggregate such that surface texture is lost.

Grit Fine angular mineral aggregate, usually passing a 4.75 mm sieve. Gritting The application of GRIT to trafficked surfaces. Often used where ICE

may create or has created a potential traffic hazard. Herbicide An AGRICHEMICAL that is specifically designed to kill or eradicate

unwanted plants. Hot Mix, Hot Mix Asphalt

Aggregate and bitumen heated and mixed while hot, transported to the site of construction, laid and compacted while hot. See also PREMIX and OTHER PREMIX MATERIALS. Also see ASPHALTIC CONCRETE.

Ice Ice includes frost and can consist of: Thick ice, several layers-thick of ice crystals Thin ice or ice glaze, a one-crystal layer-thick ice that moulds over

the macrotexture of the road Ground icing, e.g. frost or light snow compacted by trafficking.

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 28

Incident Any event that may affect either:

(a) the NETWORK'S safety, use, and integrity and/or

(b) road user’s safety;

and/or

(c) any event that results in a spill or discharge (accidental or intentional), that may require the Contractor’s action;

and the Engineer agrees that it constitutes an incident. Inventory A summary of all the items of a particular asset type (e.g. signs or

DRAINAGE FEATURES) on a NETWORK, including some information about them, e.g. location, age, size, type.

Litter Any single item with a dimension greater than 100mm. For example items such as paper, refuse, rubbish, garbage, tyre parts, drink bottles and cans or any item of a like nature.

LON Length of Need. Maintenance Programme

A PROGRAMME designed to: Improve the existing condition of the road asset, including

PAVEMENTS, surfacings, ROADSIDE FURNITURE Improve the environment for the public living, working or

otherwise using state highways, not only visually, but to make the NETWORK safer.

Meet the above requirements within current financial budgets.

Make Safe 1. Mitigate the effects of a hazard to reduce the risk of harm or damage

to the workers and road users. This may involve the removal of obstructions or the erection of signs and/or BARRIERS.

2. In the context of Winter Maintenance, actions undertaken to ensure that the NETWORK has appropriate signage in accordance with COPTMM, the approved TMP plus any restrictions relating to level of service and where either:

The PAVEMENT surface is either free of ICE or free of settled snow, or ICE is covered with GRIT such that: a vehicle tyre is not in full contact with ICE or snow; and sufficient tyre friction is maintained for traffic to travel without loss of control and that vehicles have the ability to stop without skidding when driving at an appropriate speed for the conditions, or,

The road can be opened with some restrictions being sign posted appropriately e.g. open to non-towing vehicles, open to vehicles with chain or open with speed restriction.

See also ANTI-ICING, DE-ICING, GRITTING, ICE and SNOW

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 29

CLEARANCE. Manhole See SERVICE HOLE. Milling In the context of pavement maintenance, refer to COLD MILLING

In the context of pavement marking, the removal or partial removal of long life markings by mechanical means.

MIS The Maintenance Intervention Strategy (MIS) which:

(a) states the type and extent of work permitted under each maintenance strategy

(b) is dependent on the highway environment.

MOTSAM Transit’s Manual of Traffic Signs and Markings. Network The specific road network, electrical network, DRAINAGE network (or

DRAINAGE SYSTEM) included in the contract area. The road network includes the CARRIAGEWAY and may also include TRAFFIC CONTROL DEVICES, ROADSIDE FACILITIES, VERGES, REST AREAS or other road assets. The network includes all CARRIAGEWAYS encompassing the road reserve, bound by existing fences or road reserve boundaries, and all established REST AREAS and roads within these areas.

Network Monitoring

In the context of Winter Maintenance, the observation of the NETWORK by methods such as WEATHER MONITORING, PATROLLING and other means for the purpose of being proactive in mobilising the appropriate resources as necessary to ensure the specified levels of service are achieved during a winter event, e.g. an EXTREME SNOW AND ICE EVENT. See also PATROLLING and WEATHER MONITORING.

Notification The time the Contractor was advised of the INCIDENT, defect or emergency by the Engineer, the Contractor's personnel, or a third party (e.g. Police, Principal or a member of the public), including observations made during any inspections, or the Contractor becomes, or should have become aware of the INCIDENT through monitoring requirements.

Other Structures Other structures include but are not limited to tunnels, commercial vehicle compliance stations, stock effluent disposal receptors, truck compounds, control rooms, and river or coastal protection works.

Patrol, Patrolling (a) In the context of Winter Maintenance, a regular inspection of the

highway, initiated during periods when a snow or ICE event can be reasonably expected. Patrolling should as far as possible be carried out by a vehicle especially equipped for the purpose, e.g. a vehicle capable of making some immediate response to hazardous situations encountered, such as the capability of spreading GRIT (or DE-ICING CHEMICAL where specified). See also NETWORK MONITORING.

(b) In the context of INCIDENT response proactive mobilisation of the appropriate resources as necessary to ensure the specified levels of

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 30

service are achieved.

Pavement The portion of the road, excluding SHOULDERS, that is placed above the design subgrade level for the support of, and to form a running surface for, vehicular traffic. It is supported by the subgrade. See Diagram 3.1.

Possession of Site In the context of PRE-RESEAL repairs, possession of site is when the Contractor becomes responsible for any outstanding work which has appeared, and any PRE-RESEAL repairs which the maintenance contractor has not completed and all repairs up until sealing for sections scheduled for resealing that year.

Pothole A hole in the PAVEMENT, frequently round in shape, resulting from loss of PAVEMENT material caused by the action of traffic. As a defect, potholes are defined as:

(a) Where surface attrition has occurred in areas of PAVEMENT over an area greater than 70mm in diameter but not exceeding 1m2, and the underlying PAVEMENT is exposed. (This does not include SCABBING and STRIPPING on a chip seal), or,

(b) Where the defect exceeds 50mm depth in ASPHALTIC CONCRETE, including porous asphalt and/or surfacing layers.

Premix Premix includes all bitumen-bound materials, whether hot or cold laid, which have been mixed prior to being placed in the repair area. Premix does not include bitumen-stabilised aggregates. To be classified as premix as opposed to bitumen stabilised aggregate, the mix shall have a binder content greater than 2.5%. See also HOT MIX ASPHALT and OTHER PREMIXED MATERIALS. Premix materials, other than those specified, which are designed to meet the service requirements specified. The Engineer must approve Other Premixed Materials before they are used on the NETWORK.

Pre-reseal Any activity undertaken in the period up to a year before chipsealing, to prepare the surface for the chipseal, e.g. DIGOUT, CRACK filling, lichen removal.

Programme A system of projects or services intended to meet a public need or to treat an asset in order to reach a desired level of service.

Programmed Maintenance

A strategy to intervene with, for example, a bulk replacement to reduce or optimise ROUTINE MAINTENANCE needs, e.g. bulk replacement of edge marker posts, a carriageway lighting replacement PROGRAMME. See also ROUTINE MAINTENANCE.

Rest areas A designated area adjacent to a highway where vehicles can stop temporarily for the rest and relaxation of drivers and passengers.

Road Safety Barrier (a) A physical BARRIER, including guardrails, designed to resist

penetration by and out-of-control vehicle and so far as is practicable, to redirect colliding vehicles back into the travelled path and,

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 31

(b) a BARRIER meeting the specification requirements of TNZ M/23.

Roadside Facilities Roadside facilities include but are not limited to: ROADSIDE FURNITURE ROAD SAFETY BARRIER systems lighting columns fences REST AREA furniture pedestrian refuges pedestrian facilities (e.g. pedestrian lighting, belisha beacons,

pedestrian crossing poles) handrails CULVERTS DRAINAGE SYSTEM BRIDGES OTHER STRUCTURES retaining walls sign support structures WEIGHPITs and weighstations other facilities as specified

Roadside facilities does not include:

toilet facilities. other facilities as specified.

Roadside Furniture

These include, edge marker posts, route position pegs, CULVERT marker pegs, subsoil drain markers, benchmark markers, calibration site markers, sightrails, BRIDGE end and hazard markers and signs as specified.

Routine Inspection An activity carried out as part of ROUTINE MAINTENANCE, e.g. monthly inspection of the NETWORK carried out to create the ROUTINE MAINTENANCE PROGRAMME. See also CYCLIC INSPECTION.

Routine Maintenance

Periodic maintenance as required on an individual item to achieve the service level required, e.g. a dig out in a PAVEMENT, or the replacement of a single light bulb. See also PROGRAMMED MAINTENANCE.

Scabbing The progressive loss of chip from a chipseal, often in patches. Can be exacerbated by cold weather and the action of traffic. See also STRIPPING.

Schedule 1. The Schedule of Prices in a contract document.

2. A section of the “Conditions of Contract” (blue section) of standard SOMAC documents, e.g. the “First Schedule”.

3. A list of areas or assets included in the contract

4. A list of exclusions from the contract area

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 32

5. In the context of a VEGETATION CONTROL contract, the Schedule details the areas, type and control required for the contract.

Sealed Carriageway

That portion of the road PAVEMENT sealed to protect and waterproof the underlying PAVEMENT, (inclusive of SEALED SHOULDERS) and provide a suitable driving surface for vehicles. See Diagram 3.1.

Sealed Shoulder That portion of the SEALED CARRIAGEWAY beyond the traffic lane, located between the traffic lane edge line and the edge of seal, generally flush and contiguous with the SEALED CARRIAGEWAY. See Diagram 3.1.

Second Coat Sealing

A second coat seal is a seal applied on top of a previously applied first coat seal over PAVEMENT repairs to provide both waterproofing and a surface texture consistent with the surrounding PAVEMENT. For a PRE-RESEAL repair a Second Coat Seal is not required.

Service Hole, Service Cover

A shaft with a removable cover that leads down to a sewer, drain or other underground service. Also called a MANHOLE.

SHGDM Transit’s State Highway Geometric Design Manual (DRAFT). Shoulder This term refers to the general area between the edge of seal and a point

500mm beyond the invert of the SURFACE WATER CHANNEL. See also UNSEALED SHOULDER, SEALED SHOULDER and Diagram 3.1.

Shoulder Hinge Point

In the cross-section of a road, the point at which the SIDE SLOPE would intersect with the UNSEALED SHOULDER, or in the absence of an UNSEALED SHOULDER, the SEALED SHOULDER. See Diagram 3.1.

Side Drain A longitudinal surface drain or ditch, usually U-shaped and generally located between the SURFACE WATER CHANNEL and the legal road boundary. While it is intended to carry water from the surrounding land, in some situations the side drain may run immediately adjacent to the road PAVEMENT and collect surface water runoff from the road surface and adjacent land. See Diagram 3.1.

Side Slope That area of road formation, located between the SHOULDER HINGE POINT and the SURFACE WATER CHANNEL, having a gradient steeper than 1:12, but no steeper than 1:5. See Diagram 3.1.

Slips Slips include collapsing banks and frettings from cuttings and:

(a) Are greater than 1m³ in volume.

(b) Encroach on to the surface of the SEALED CARRIAGEWAY and/or affect the effective operation of existing DRAINAGE FEATURES.

Snow Clearance The removal of snow from all trafficked surfaces, including on the surfaces of SEALED CARRIAGEWAYS outside the lead-in lines on the approaches to single lane BRIDGES, when it becomes (or to prevent it becoming) a potential traffic hazard.

Stormwater Structure

Any structure with a maximum waterway not exceeding 3.4m2. It includes, but is not limited to, CULVERTS, SERVICE HOLES (MANHOLES), sumps, slot drains, catch pits, soak pits, flumes, outlets to subsoil drains, stormwater ponds, outlets to bored horizontal drains, and accessway CULVERTS.

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 33

Stripping Stripping is the displacement of binder from the chip, causing chiploss, generally through cold or wet conditions. See also SCABBBING.

Summer Period November to February inclusive, or as otherwise defined within the Operational Requirements

Surface Water Channel

An open drain or ditch formed for the collection and DRAINAGE of water runoff from the road’s surface. The width of the CHANNEL shall be a minimum of 1.0 metre (0.5 metre either side of the invert). Also know as a V-shaped CHANNEL. See also SIDE DRAIN and Diagram 3.1.

Taonga An object that relates to Maori culture, history or society and was, or appears to have been;

Manufactured or modified in New Zealand by Maori Brought in to New Zealand by Maori Used by Maori.

Temporary Traffic Management

The process of managing road users through or past a work site in a safe manner with minimal delay and inconvenience.

TMP Traffic Management Plan Traffic Control Devices

Any sign, signal, PAVEMENT marking or other installation placed or erected for the purpose of regulating, warning or guiding traffic.

Treatment Any activity undertaken on the road, such as resurfacing or ROUTINE MAINTENANCE, with the intention of achieving the desired level of service. In the context of winter maintenance, the work required to deal with snow and ICE hazards on the NETWORK in order to ensure the NETWORK meets the required levels of service.

Trimming In the context of a VEGETATION CONTROL contract, the removal of branches or removal of mature trees, scrub or shrubs with a trunk less than 300 mm diameter. In the context of PAVEMENT maintenance, the removal of excess material to create a straight edge on a digout or repair, prior to filling and/or sealing.

Unscheduled Work

Unscheduled work can be either new or maintenance work required outside standard or programmed activities. See also NEW WORK, URGENT WORK.

Unsealed Shoulder That portion of the CARRIAGEWAY, located between the edge of seal and the SHOULDER HINGE POINT, having a slope generally no steeper than 1:12, except on curves where the superelevation may increase the slope. See Diagram 3.1.

Urgent Work Urgent Work is a subset of UNSCHEDULED WORK. Refer to Urgent Work, Section 4, of the Maintenance Specification.

Vegetation All plant life alive or dead within the NETWORK and including but not limited to grass, weeds, scrub, including PLANT PESTS, shrubs, moss, lichen, trees, overhanging and fallen branches.

Vegetation Control

All work required to control and maintain VEGETATION within the road reserve and other areas specified in the contract documents.

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 34

Verge That area of road reserve located between the SHOULDER HINGE POINT and the legal road boundary. See Diagram 3.1.

Weather Monitoring

Consists of regularly obtaining weather information from forecasts, weather stations and obtaining information from road users and visual monitoring. Once an ICE or snow event is predicted weather monitoring shall be performed at a maximum interval of 2 hours until the end of the event. An event is at an end when the NETWORK is free of any snow or ICE and no further events are predicted for the next 24 hours. See also NETWORK MONITORING and PATROLLING.

Weighpit A slot (pit) on a concrete pad designed to accommodate portable wheel weighing scales that are used to weigh vehicles. The depth of the slot enables the surface of the scales to be at the same level as the surrounding PAVEMENT surface.

Winter Period June to September inclusive, or as otherwise defined within the Operational Requirements.

Maintenance Specification

3 General Requirements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 35

Diagram 3.1 See Definitions in Table 3.2 for the target gradients of Unsealed Shoulder and Side Slope.

Maintenance Specification

4 Contractor's Programmes

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 36

4. Contractor’s Programmes

4.1 Scope

This Section sets out the requirements for preparing, accepting, implementing and managing the Contractor's Programmes.

The work required by this Section must be completed in accordance with Sections 1 to 3 (inclusive) and the following requirements.

4.2 Response Times 4.2.1 Programmes

Table 4.1 lists the response time for submitting and reviewing each Programme.

Table 4.1: Contractor’s Programmes

Activity Response Time

Proposed Programme By the 20th of the month prior

Engineer’s Review of the Proposed Programme

Within 5 days of the date the Proposed Programme is received

Revised Programme Within 3 days of the date of the Engineer’s review of the Proposed Programme is received

Engineer’s Review of the Revised Programme

Within 2 days of the Revised Programme’s receipt

4.2.2 Fault Repair

Table 4.2 states the response times for repairing faults whether or not such day is a working day.

Table 4.2: Fault Repair

Activity Response Time

Priority 1 Tasks By the 15th calendar day of Month 1

Priority 2 Tasks By the last day of Month 1

Priority 3 Tasks By the last day of Month 2

Priority 4 Tasks Within the time frame agreed with the Engineer

4.2.3 Urgent Work

All Urgent Work must commence by 8.00am the day following the time of notification. 4.3 Review of Programme

The Engineer will:

a) review the Programme within the response times set out in Table 4.1 and mutually agree the content and appropriateness of all proposed work

b) usually approve only Month 1 of the Programme. However, in some cases the Engineer may approve both Months 1 and 2 of the Programme.

Maintenance Specification

4 Contractor's Programmes

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 37

4.4 Variation of Method and Dimensions

The Contractor shall advise the Engineer immediately of any variation required to the dimensions or proposed method of undertaking the programmed treatment or repair, if such variations become apparent after excavation has commenced.

4.5 Preparation of Programmes

The Contractor must:

a) complete routine inspections in order to meet the response times and identify, by marking on the road the location and extent of all faults, and prioritise the works

b) determine the most cost effective treatment and/or repair, state the location and proposed method of repair, compile and submit the proposed Programme, giving due consideration to budget and service level needs, to the Engineer. The Engineer shall review the Contractor's schedule of location, methods and programme and adjust for technical and budget restraints if any, agree and return to the Contractor

c) implement and manage the agreed Programme so all work is completed to standards and within the response times stated in the Contract Documents.

d) carry out programmed treatments and/or repairs in accordance with the contract documents and be responsible for subsequent maintenance of repairs during the Contract period.

In addition, the Contractor must advise the Engineer of all work that falls outside the scope of this Contract but may affect the network's safety and integrity. Only work on the agreed programme will be paid for.

The Contractor's Programme must include the:

i) Detailed Programme - this must:

be a rolling three month programme that records and prioritises all faults within the network.

be in the specified format

comply with the programming constraints -- see Clause 4.5.1

ii) Projected Monthly Expenditure -- see Clause 4.5.2

The Programme must be submitted in both hard copy and electronic format. Appendix 4.1 sets out the electronic format. The Contractor may provide partial programme submissions to the Engineer only if prior approval by the Engineer has been sought.

Maintenance Specification

4 Contractor's Programmes

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 38

This would permit the Contractor to submit more than one programme per month covering an agreed portion of the state highway network at a time, rather than a single monthly programme covering the entire network within any monthly cycle. The Engineer's approval for the adoption of partial programme submissions would be subject to the Contractor demonstrating an ability to consistently programme the maintenance work effectively and with an error rate well below the 5% threshold. The Engineer may withdraw approval for the continuance of the partial programme submissions at anytime the Contractor fails to maintain the required programming standard.

4.5.1 Programming Constraints

All Programmes must be prepared so they comply with the following constraints: 4.5.1.1. Ten Year Programme

The Engineer maintains the Ten Year Programme (TYP) for the network. The TYP:

a) details all proposed work, by location and type, to be completed within the network

b) states the maintenance strategy that applies to each section of the network

c) is based on the outputs from the NZ Transport Agency's Annual Roading Programme, the Engineer's and Contractor's inspections and financial constraints

d) is formally updated and issued to the Contractor on a six monthly basis. 4.5.1.2. Maintenance Intervention Strategy

The Maintenance Intervention Strategy (MIS):

a) states the type and extent of work permitted under each maintenance strategy

b) is dependent on the highway environment.

This means in some cases, e.g. sections programmed for rehabilitation or reconstruction holding type repair(s) will be preferred to full cost repairs.

The risks associated with the repairs' performance will be carried by the Principal provided the Contractor can demonstrate the repair was completed according to the Contract Documents.

If the Contractor considers the risk of completing holding repairs is too great, the Contractor must advise the Engineer and propose alternative treatment(s)

The MIS is an evolving document and demands both the Contractor's and Engineer's input for its ongoing development and effective implementation.

4.5.1.3. Extent of Finance

All Programmes must be prepared so the value of the Programme approximately equals the value shown on the Contractor's budget forecast for the relevant period (see Clause 4.5.2).

Maintenance Specification

4 Contractor's Programmes

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 39

4.5.1.4. Other Constraints

The Operational Requirements section details other programming constraints that apply. 4.5.2 Projected Monthly Expenditure 4.5.2.1. Budget Forecast

The Contractor must provide a budget forecast for each payment item number (see Appendix 4.2) and the Contract Works with their initial Programme. The budget forecast must:

a) show the proposed monthly expenditure for each payment item number

b) form the basis of the financial performance indicators, evaluation (see Clause 1.5). 4.5.2.2. Projected Monthly Expenditure

The Contractor must provide the Programmed Monthly Expenditure with each subsequent Programme and Monthly Report. The Programmed Monthly Expenditure:

a) is a financial statement, in accrual terms, of the past, current and projected financial status of the contract for each month of the contract period

b) must state, for each payment item number and the Contract Works, for each month of the financial year:

the value of work certified for payment by the Engineer including all retentions

the value of withheld money that may be returned to the Contractor

any claims the Contractor may submit, including work that has been completed but to date not claimed

the estimated value of work to be completed for each month to the end of the financial year

c) must identify any budget surpluses and/or shortfalls. In these cases the Contractor must recommend appropriate transfers or release of surplus monies.

4.5.3 Detailed Programme

The Detailed Programme must state for each fault, programmed under Unit Rate Items the:

a) fault and activity codes as defined in State Highway Database Operation Manual, SM050, Appendix 4

b) proposed method of treatment and/or repair and description of the work, referenced to the appropriate Item(s) in the Schedule of Prices

c) unique task number. If a proposed task is deleted from the Programme, the task number must not be re assigned to another task

d) task priority (see Clause 4.5.3.1)

e) location of the work by state highway and route position

Maintenance Specification

4 Contractor's Programmes

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 40

f) side of the carriageway, and, in multi-laned areas, the lane (e.g. left, centre, right)

g) extent of the work including length, width and depth (as appropriate)

h) units of measurement

i) total quantity, tendered rate and total value. 4.5.3.1. Task Priority

Each task must be assigned a priority of 1 to 4:

a) Priority 1 Tasks are for fault repairs that are:

not unsafe but may become so if they are not repaired by the 15th calendar day of the month

expected to increase in size and cost if left for longer than two weeks (from the 1st day of the month the Programme applies to).

b) Priority 2 Tasks are for fault repairs that are:

not unsafe but may become so if they are not repaired by the last day of the month

expected to increase in size and cost if left for longer than 4 weeks.

c) Priority 3 Tasks are for fault repairs that are:

not unsafe but may become so if they are not repaired by the last day of the second month

expected to increase in size and cost if left for longer than 8 weeks.

d) Priority 4 Tasks are for fault repairs that:

may increase in size and cost if left for longer than 12 weeks

can be considered desirable, but if not completed will not result in network's deterioration (i.e. they are not necessary to complete within 12 weeks).

4.6 Programme Implementation and Management 4.6.1 Responsibilities 4.6.1.1. Contractor's Responsibilities

When agreed, the Contractor must:

a) provide sufficient resources to complete all works by the dates specified in the Programme

b) with the agreement of the Engineer, adjust the priorities of the work to meet the network's needs. This may mean some tasks included in Months 2 and 3 have to be re-prioritised and accelerated or deferred.

Maintenance Specification

4 Contractor's Programmes

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 41

The Contractor shall advise the Engineer immediately of any variation required to the dimensions or proposed method of undertaking the programmed treatment or repair, if such variations become apparent after excavation has commenced.

4.6.1.2. Engineer's Responsibilities

If the Engineer's reviews and network inspections (see Sections 2 and 3) show the Contractor is not managing the Programme effectively, the Engineer may re-prioritise the Programme and instruct the Contractor accordingly.

4.6.2 Urgent Work

The Engineer may notify the Contractor that a task is to be completed as urgent work if:

a) the safety of the public or private property may be compromised, or

b) it is likely the area of distress may increase or the method of repair change so the cost of the repair increases, or

c) subsequent work may depend on the task's completion, or

d) it originates from a public complaint. 4.6.3 Variation to Method and/or Dimensions of Repair

If variations to the dimensions or proposed method of repair become apparent once the repair is started, the Contractor must:

a) advise the Engineer immediately of the task number and reasons for the variation

b) write, confirming the extent, value and reasons for the additional work. 4.6.4 Outstanding Work, Work in Progress and Non-complying Work

All Outstanding Work, Work in Progress and Non-complying Work, must be re-programmed for completion during the current month (see Clause 4.5).

If the cumulative number of Tasks that have not been started (Outstanding Work) is greater than 10% of the total number of tasks in the current programme, the Engineer reserves the right to have the work completed by another contractor on behalf of and at the cost of the Contractor (see Basis of Payment, Preamble, Clause v).

Maintenance Specification

5 Contractor's Reports

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 42

5. Contractor’s Reports

5.1 Scope

This Section sets out the requirements for preparing, submitting and accepting all Reports.

All work required by this Section must be completed in accordance with Sections 1 to 4 (inclusive) and the following requirements.

5.2 Response Times

Table 5.1 states the response times for preparing, submitting and reviewing the Contractor's Reports.

Table 5.1: Contractor’s Reports

Activity Response Time

Monthly Report 9:00am on the 3rd calendar day of the month following. (if the 3rd calendar day falls on a weekend or public holiday the report must be received by the Engineer on the 1st working day following)

Assessment Report Where a joint inspection identifies any defect or item requiring attention this should be documented with an agreed action and timing

Maintenance Report A minimum of 2 weeks before the due date of the completion of the Period of Defects Liability

Drainage System Inspection Report The Contractor must submit the Drainage System Inspection Report within 2 months of the Date of possession of site and after that at 6 monthly intervals

Engineer’s Review Within two weeks of the date of receipt of the Report

Final Report Within one week of the date of issue of the Certificate of Practical Completion

Work Site Crash/Accident Reports

Report to the Engineer within 24 hours (refer clause 5.7), and follow guidelines as set out in COPTTM and explanatory note.

5.3 Reports

In addition to the Reports specified elsewhere in the Contract Documents, the Contractor must compile and submit the Reports listed in table 5.1 above within the response times specified.

A hard copy of all reports must be kept on file for at least 1 year after contract completion. 5.4 Monthly Report

The Monthly Report:

a) will be used by the Engineer to monitor the Contractor's progress and performance

b) must include the:

Financial Report

Updated Programme

Summary of Work

Maintenance Specification

5 Contractor's Reports

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 43

Summary of all Lane Closures and Temporary Speed Restrictions

Updated Performance Indicators (see Clause 1.5)

if requested, copies of all site investigation and materials testing data.

Any discrepancies noted in the preceding month between the Contractor’s inventory data and the inventory data supplied by the Engineer (including but not limited to Highway Information and Route Data Sheets).

Work Site Crash/Accident Report. 5.4.1 Financial Report

The Financial Report must include: 5.4.1.1. Financial Statement

The financial statement must for each month, state for each payment item and for the Contract Works the:

a) Annual Contract Value. This value will be advised by the Engineer

b) Value of Work Completed and Certified to Date. This is the total value of work completed to date, claimed by the Contractor and certified for payment by the Engineer.

c) Value of Outstanding Work. This is the value of work which was programmed for completion by the end of the month but was not started. This value must include the value of any outstanding work from previous month(s).

d) Value of Work in Progress. This is the total value of work started during the month but either:

incomplete and/or

complete but does not comply with the Contract Documents and/or

complete but not included in the monthly progress claim or certified for payment

This value must also include all monthly progress claims that have been submitted, but have not been certified for payment by the Engineer.

5.4.1.2. Monthly Progress Claim

The Monthly Progress Claim must:

a) be in the format of the Schedule of Prices

b) include and separately show the extent and value of all works completed to date, completed under each Schedule Item, as well as those completed for the month

c) include all amendments, deductions, additions, emergency and unscheduled works as instructed by the Engineer.

Maintenance Specification

5 Contractor's Reports

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 44

The claim shall be submitted in hard copy and electronic form. The electronic form shall be in the format specified in Appendix 5.1.

5.4.1.3. Updated Programmed Monthly Expenditure

In addition to the requirements of Clause 5.4.2, the Programmed Monthly Expenditure must, for each payment item number:

a) be updated to reflect the contract's current financial status

b) include an updated forecast for each month until the end of the financial year.

5.4.1.4. Monthly Management Report

The Contract is required to provide a Monthly Management Report which must: a) be in the format shown in Appendix 5.2

b) include contract specific achievements

c) delivered with the Monthly Report. The report shall be submitted in hard copy form.

5.4.2 Updated Programme

The Updated Programme must:

a) show actual progress in comparison with the programme

b) if progress has fallen behind programme, state the reasons for this and actions taken to make up lost time.

The programme shall be submitted in hard copy and electronic form. The electronic form shall be in the format specified in Appendix 5.1.

5.4.3 Summary of Work

The Summary of Work must state the location (see Clause 3.7) and extent of all work completed under Unit Rate and Cyclic Items each month.

For Cyclic Maintenance, this includes information such as the location reference, the date the work was carried out and:

a) approximate volume and/or area (in m²) of detritus removed

b) number of potholes repaired

c) number of stormwater structures inspected and/or cleaned etc.

This information is also to be collated and reported as a performance indicator (see Clause 1.5.3. 2).

Maintenance Specification

5 Contractor's Reports

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 45

5.4.4 Summary of all Lane Closures and Temporary Speed Restrictions

The Summary of all Lane Closures and Temporary Speed Restrictions must state the location, extent of work, dates, times and temporary speed restriction (if applicable) for any work occurring within the road reserve each month. The format shall be agreed by the Engineer.

5.5 Assessment Report

The Assessment Report will be completed according to Clause 1.5. 5.6 Final Report

The Final Report must be in the same format as the Monthly Report except that:

a) an updated Projected Monthly Expenditure is not required

b) the Contractor must include a brief description and estimated value of all claims that may be submitted with their Final Claim.

5.7 Maintenance Report

The Maintenance Report must be in the same format as the Final Report and state the location and extent of all non-complying tasks, the extent of all remedial works and the date this work was completed.

5.8 Work Site Crash/Accident Reports

In the event that a crash occurs involving a vehicle travelling through a site, notification of the crash is to be given to the Engineer within 24 hours of the crash, in terms set out in COPTTM Section A4.2.3, Introduction and General, Contractor Responsibilities “Crashes at Worksites” and explanatory note. Notification shall include:

Full details of the event

Description of the traffic management operating e.g. Stop/Go, 50km/hr signs.

Confirmation or otherwise that the site complied in all respects with the traffic management plan and any health and safety plan

Contractor’s assessment of whether there is a possibility that traffic control or work site condition deficiencies may have contributed to the crash.

Site conditions (e.g. loose chip)

Any Department of Labour requirements. For an unoccupied site, the Contractor shall supply as much information as is possible from the above list.

Maintenance Specification

6 Traffic Management

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 46

6. Traffic Management

6.1 Scope

This section sets out the minimum requirements for the provision of traffic management. All work required by this Section must be completed in accordance with the Code of Practice for Temporary Traffic Management in New Zealand (COPTTM), and the following requirements.

6.1.1 Type 1

Appendix 6.1 sets out the minimum requirements for Level 1 Traffic Management. 6.2 Response Times

Table 6.1 states the response times for preparing, submitting and reviewing the TMP.

Table 6.1: Traffic Management Plan (TMP)

Activity Response Time

Draft Generic TMP (for approval) Within 3 weeks of the Date of Acceptance of Tender or as agreed with the Engineer

Final Generic TMP Within 3 days of the date of the Engineer’s review of the draft TMP and prior to the date of occupancy of the site

Site Specific TMP In accordance with COPTTM

Engineer’s Review of the TMP In accordance with COPTTM

Annual TMP Review Within 3 weeks of the anniversary of the acceptance of tender

6.3 Traffic Management Plan

6.3.1 Content

The Contractor must develop the TMP. Nothing in the TMP will take precedence over the Contract Documents' requirements.

In particular, nothing in the TMP will relieve the Contractor from the performance of the Contractor's obligations under the Contract Documents even though the TMP has been approved by the Principal or the Principal's Agent.

6.3.2 Implementation and Management of TMP

The Contractor must develop the TMP.

The Contractor must implement and manage the TMP so the Contract Works are completed in accordance with these Contract Documents.

The maximum delay time and queue length permitted is shown in Appendix 6.1

The Contractor shall be responsible for the monitoring of traffic delay.

The Contractor must demonstrate that the capacity of any temporary traffic management configuration can cope with the demand without causing excessive traffic delays.

Maintenance Specification

6 Traffic Management

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 47

If delays of greater than 10 minutes are experienced during temporary traffic management, provisions shall be made to communicate to road users the nature of and the expected length of delay.

In particular, nothing in the TMP will relieve the Contractor from the performance of the Contractor's obligations under the Contract Documents even though the Principal or the Principal's Agent has approved the TMP.

6.3.3 Traffic Management Review

The Engineer may review any aspect of the Contractor's operation relevant to traffic management and the Contract Works.

These audits will be undertaken on a random basis without prior notice.

6.3.4 Unusual Traffic Control

If proposed works require traffic control measures not covered by the above requirements, the Contractor must provide site-specific sign layout diagrams and procedures for the Engineer's review and agreement, in accordance with COPTTM.

The information must be provided a minimum of one week before the programmed start date of the work.

Maintenance Specification

7 Environmental Management

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 48

7. Environmental Management

7.1 Scope

This Section sets out the requirements for avoiding and mitigating any adverse environmental effects associated with the Contract Works.

The work required by this Section must be completed in accordance with Sections 1 to 6 (inclusive) and the following requirements.

7.2 Response Times

The documented procedure for environmental management must be provided with the CQP (see Section 2).

7.3 Key Considerations

The procedure for environmental management must include and/or reference, where appropriate, the systems, work practices and actions the Contractor will take to:

a) manage stockpiled material

b) manage stockpile and disposal areas in accordance with Section 3, Stockpile and Disposal Areas

c) transfer and store fuel, waste, oil and hazardous substances

d) control the drift of chemical sprays and fertilisers and actions taken if drift occurs

e) avoid erosion to the extent reasonable in the circumstances

f) avoid, to the extent reasonable in the circumstances, adverse effects on areas of significant vegetation and indigenous vegetation

g) reduce noise and dust, etc. The Contractor must ensure that no hazard, annoyance or damage is caused to traffic or property owners through dust from the Contract Works (see General Conditions, Clause 5.7)

h) prevent fuel and oil spills including the emergency response and reporting procedures to be taken if a spill occurs. The Contractor must ensure that spill prevention and emergency response procedures avoid, to the extent reasonable in the circumstances, adverse environmental effects.

i) liaise with all affected organisations, residents, property owners etc.

j) control sediment, runoff and silt. The Contractor must control the runoff by surface water, berms, flumes, temporary culverts, early establishment of vegetative cover and constructing of silt retention dams or traps. These structures will require maintenance during the Contract

k) manage and reduce waste in accordance with Transit's Environmental Policy Manual

l) assess all operations to promote energy efficiency in accordance with Transit's Environmental Policy Manual

Maintenance Specification

7 Environmental Management

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 49

m) ensure the finished surface, including asphaltic joints, is flush with existing pavement surfaces and utility covers so as not to create adverse noise and vibration effects

n) report to the Engineer and manage any accidental discovery of material that could be an archaeological site(s), koiwi (human skeletal remains), or Taonga.

7.4 Resource Consents

The Consultant and Contractor shall be responsible for ensuring compliance with all conditions of consents affecting the contract services and meeting all social and environmental requirements. In pursuance of this aim the Consultant shall:

Ensure Clients consent compliance management system (CS VUE) is used to manage consents and monitor consent compliance.

Appendix 7.1 lists the resource consents that apply to this Contract. The Operational Requirements detail the specific requirements of these consents.

Maintenance Specification

8 Unscheduled Works

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 50

8. Unscheduled Works

8.1 Scope

This Section sets out the requirements for completing Unscheduled Works. Unscheduled Works may be carried out when there are no other appropriate Schedule Items.

All Unscheduled Works shall be considered a variation and valued in accordance with Section 8. No work under this clause shall commence until discussed and agreed with the Engineer.

The Contractor must complete all work required by this Section in accordance with Sections 1 to 7 (inclusive) and the following requirements.

8.2 Response Times

The Contractor must complete all work required by this Section by the date agreed with the Engineer.

If the work is completed on a dayworks basis, daily job records (DJR's) for each event shall be provided to the Engineer within 48 hours of completion of the work.

8.3 Priced Proposals

If requested by the Engineer, the Contractor must submit priced proposals to complete work for which there is no applicable Schedule Item or where the extent of the proposed work means that the rates in the Schedule of Prices are not applicable.

The priced proposals must include:

a) a description of the proposed work showing the extent and quantities of the work required

b) the proposed completion date

c) a fixed price quote to complete the works

d) a break down of the fixed price if requested by the Engineer. The value of any priced proposal must be reflected in the updated projected monthly expenditure (see Clause 5.4.1.3 Updated Programmed Monthly Expenditure)

8.4 Completion

Unless otherwise specified all work must be:

a) completed in accordance with the Contract Document's requirements, or

b) if the method is not specified, completed in accordance with accepted industry practices.

If the Contractor's proposal is accepted, the work must be included into the current Programme.

Maintenance Specification

8 Unscheduled Works

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 51

8.5 Service Relocation

The Contractor must liaise with the appropriate service authority and provide the Engineer with the priced proposal for the relocation and/or protection of any service that conflicts with the Contractor's work (see Clause 3.9).

The proposal must be agreed with the Engineer before the relocation work starts.

Maintenance Specification

9 Incident Response

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 52

9. Incident Response

9.1 Scope

This Section sets out the minimum level of service for responding to incidents.

Dealing with live animals will be treated as Incident Response. The Contractor is required to attend to all incidents on the network promptly and establish emergency patrols during periods when damage is expected to facilities or the safety or availability for road users may be compromised, or the integrity of access may be affected, and shall: respond to all incidents within the response times specified, including Winter Maintenance,

Section 10, and Detritus and Slip Removal, Section 20.

protect road users by making the road and adjacent area safe to all road users.

undertake emergency patrols as required and/or in response to a request by the Engineer.

undertake repair work to re-establish safe access for all normal road users to at least single lane status, unless instructed otherwise by the Engineer.

protect the environment from adverse effects of a discharge, spill or spill clean up caused by the Contractor

protect the environment from adverse effects of a discharge, spill or spill clean up where the Contractor is required to cleanup the discharge or spill, and

undertake additional requirements as requested by the Incident Controller.

The Contractor shall advise the Engineer of all incidents within the response times set out in this Contract.

9.2 Definitions

The terms defined in Table 3.2, Definitions, appear in bold. 9.3 Response Times

The Contractor must:

a) respond to all incidents within the response times stated in Table 9.1 from the time of notification.

b) provide completed DJRs for each day of each event and forward these to the Engineer within 24 hours.

Maintenance Specification

9 Incident Response

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 53

Table 9.1: Incident Response

Class Response Time

M Mobilise, establish and start work on Site within ½ hour

U and R1 Mobilise within ½ hour, establish and start work on Site within 1 hour

R2 Mobilise within ½ hour, establish and start work on Site within 2 hours

R3 Mobilise within ½ hour, establish and start work on Site within 2 hours

R4 Mobilise within ½ hour, establish and start work on Site within 2 hours

9.4 Specific Requirements 9.4.1 Level of Service

The Contractor must provide sufficient resources to attend to all incidents within the specified response times and if required:

a) complete emergency patrols at the frequency agreed with the Engineer

b) report regularly to the Engineer.

9.4.2 Supplementary Resources

The Engineer may engage additional resources to supplement those provided by the Contractor if the Contractor is unable to provide adequate resources.

9.4.3 Closures

The Contractor shall provide sufficient personnel and resources equipped with a vehicle and effective means of communication (e.g. cell phone or radio telephone) must attend all road closures.

9.4.4 Incident Response Vehicle

When responding to an incident the response vehicle shall be sufficiently equipped and the personnel adequately trained to deal with the range of incidents likely to be encountered and to provide the agreed level of service. The incident response vehicle will be fully equipped with the following minimum items: signage and cones (spare road flares) capable of providing control of 2 lane sites down to a

single lane or complete closure to the standard required by the COPTTM. Some limited detour signage should also be included, but any extensive detour requirements or control would have to rely on additional signage being requested.

normal array of hand tools, i.e. shovels, brooms, etc suitable for cleaning up debris and detritus.

truck mounted and operated spotlight system.

Maintenance Specification

9 Incident Response

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 54

a minimum of 100m of high visibility plastic netting, steel warratah standards and tow wire.

sufficient oil absorbent material capable of handling at least 50 litres of oil/fuel spills.

normal communications equipment - radio telephone plus cell phone.

a comprehensive first aid kit. 9.4.5 Communications

The Contractor shall provide an adequate communication system (e.g. cell phone or radio telephone) that enables the Engineer, Police or Territorial Authority to contact the Contractor 24 hours a day. The Contractor shall ensure that accurate and current lists of people and contact numbers are maintained at all times. The Contractor shall advise the Engineer as soon as practicable and within one hour of establishing on site: the scale of each incident details of plant and labour despatched, and any potential adverse environmental effects, particularly effects on drinking water.

9.4.6 Retrieval of Temporary Warning Equipment

The Contractor must retrieve his temporary warning equipment when the hazard has been attended to, or when a more permanent warning system has been put in place.

9.4.7 Emergency Procedures Manual

The Emergency Procedures Manual, if available, outlines each party's roles' and lines of communication that must be used while responding to an incident.

9.4.8 Liaison With Adjacent Areas

During periods when conditions are such that the highway may require closing, the Contractor shall establish and maintain a close liaison with the adjacent highway operations and maintenance contractor.

9.4.9 Progress Reports

The Contractor shall have available an adequate communication system (e.g. cell phone or radio telephone) to enable up to date verbal progress reports to be made from the incident site to the Engineer. Progress reports shall be at intervals requested by the Engineer. The Contractor may also be requested by the Engineer to make reports and keep informed those organisations nominated in Operational Requirements of any road closures.

Maintenance Specification

9 Incident Response

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 55

9.4.10 Work Outside the Site Boundaries by the Contractor

In certain circumstances during an incident the Contractor may be required to undertake work in the adjacent network (outside the Site Boundary). In any circumstance where the Contractor is required to undertake work outside of the Site Boundary this will not constitute a breach of this Contract and the Conditions of this Contract apply. If, in response to an incident, the Contractor attends at the scene, which is found to be outside the Site Boundaries, the Contractor shall act in accordance with the following:

a) attend to the incident as if it was within the Site Boundaries until the adjacent highway

operations and maintenance contractorarrives

b) render all reasonable assistance that may be requested by the adjacent highway operations and maintenance contractor

c) communicate promptly with the Engineer and advise that person of the circumstances and the action being taken.

9.4.11 Work Inside the Boundaries by a Neighbouring Contractor

If the adjacent highway operations and maintenance contractor is attending an incident within the Site Boundaries the Contractor shall co-operate fully with the adjacent highway operations and maintenance contractor to ensure the prompt completion of the incident and the orderly taking over of that work by the Contractor.

9.4.12 Live Animal(s)

The Contractor is required to do whatever is necessary during an incident involving live animal(s) to make the road safe for the road users. Where possible the Contractor shall identify and notify the owner of the live animal(s). If the owner cannot be identified, live animal(s) removed must be treated, impounded and disposed of according to the requirements of the Impounding Act 1955 and of each Local Authority.

9.4.13 Environmental Management of Spills and Discharges

The Contractor shall ensure the adverse environmental effects of spills, discharges, and spill clean up are avoided to the extent reasonable in the circumstances. The Contractor shall advise the Engineer of any spill or discharge and the steps taken to avoid and mitigate adverse environmental effects of the spill and the spill clean up, including: stopping the spill source containing the spread of the spill removing the spill and cleanup material disposing of contaminated material to an approved location any additional works needed to restore the site to pre-incident conditions, and a report on any cost recovery data.

Maintenance Specification

9 Incident Response

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 56

If the spill is managed by another agency, the Contractor will discuss with the agency the means of minimising any adverse environmental effects and damage to the network, and advise and inform the Engineer of the situation.

9.5 Performance Criteria

The performance of the Contractor during the Contract period will be measured by the following criteria:

a) that the Contractor always attends to all incidents within the response times specified.

b) inspections are completed on time and inspection records are available when requested by the Engineer.

c) communications are such that the Engineer is always aware of the event and progress being made towards rectifying it.

d) that the requirements of the Emergency Procedures Manual are met.

e) that inconvenience to road users is minimised, that the safety of road users is always assured and that the agreed service level is restored as quickly as possible.

f) that an accurately completed DJR record is always submitted to the Engineer.

g) that the response vehicle shall be sufficiently equipped and the personnel adequately trained to deal with the range of incidents likely to be encountered and to provide the agreed level of service.

Maintenance Specification

10 Winter Maintenance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 57

10. Winter Maintenance

10.1 Scope

This section sets out the requirements for maintenance of a road network that is at risk of snow and ice events to ensure the required road availability and levels of service are achieved during winter. The objective is to pro-actively react to predicted snow and ice events that may affect the highway network in order to keep roads open and maintained in a safe condition for motorists as far as is reasonably possible during winter in terms of the defined levels of service. In the case of Extreme Snow and Ice Events where the required level of service cannot be maintained then the road shall be either closed or temporarily sign posted to restrict vehicle use until the required level of service is returned. The work required by this Section must be completed according to the following requirements.

10.2 Definitions

Terms defined in Table 3.2, Definitions appear in bold.

10.3 Response Times 10.3.1 Mobilisation and Levels of Service

The Contractor shall provide the levels of service required in Table 10.1. Table 10.2 explains the levels of service and states the response times for identifying the need for and establishing resources on site in Extreme Snow and Ice Events. The required levels of service for specific locations are given in Appendix 10.1, and the Operational Requirements.

Maintenance Specification

10 Winter Maintenance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 58

Table 10.1: Pavement Levels of Service

Level of Service Road Availability Service Level Method

Monitoring (see also Cl. 10.4.2) Regime – Leads

to Decision Making

1A Open to all vehicles Treatment 24 hours a day to maintain the road in a safe winter driving condition

Mobilisation to ensure:

all sites undergo treatment before ice forms

snow is continually cleared from the road.

Ice undergoes treatment during an event

Use tools available –

“observations” hourly

supplied tools (e.g. weather monitoring services)

Documented process for decision making

Time of predicted ice/snow

Location of predicted ice/snow

Treatment “Just in time”.

Ongoing treatment

1B Open with some restrictions being sign posted appropriately (some roads only) e.g.

- Open to non-towing vehicles

- Open to vehicles with chains

- Open with speed restriction

1C Closed .

2A Open Treatment to maintain the road in a safe winter driving condition 7 am to 7 pm (minimum) and pro-active treatment before 7 am if an overnight ice or snow event is predicted.

As for Level of Service 1 (above), but Treatment 7 am to 7 pm and pro-active treatment before 7 am if an overnight ice or snow event is predicted.

As for Level of Service 1 (above), but, treatment “Just in time” within specified hours

Review overnight forecast and take appropriate pro-active action by 7am.

2B As for Level of Service 1B (above)

2C Closed

Maintenance Specification

10 Winter Maintenance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 59

Table 10.2 Pavement Levels of Service for Extreme Snow and Ice Events – required for short

periods of times when services levels in Table 10.1 cannot be maintained.

Level of Service (Extreme Snow and Ice Events

only)

Location Service Level

Method Response Times

3A Extreme Snow and Ice Events – Urban (includes Class M and U of table 1.1)

React to Extreme Snow and Ice Events within specified response times.

Close road until

Able to make safe

Mobilise, establish and start work on site within ½ hour, in accordance with this table and the Operational Requirements.

3B Extreme Snow and Ice Events – Rural 1 (includes Class R1 of table 1.1)

React to Extreme Snow and Ice Events within specified response times.

Close road until able to make safe

As per table 9.1, and in accordance with this table and the Operational Requirements.

3C Extreme Snow and Ice Events – Rural 2 (includes Classes R2, R3, R4 of table 1.1)

React to Extreme Snow and Ice Events within specified response times.

Close road until

Able to make safe

As per table 9.1, and in accordance with this table and the Operational Requirements.

Where the weather does not allow the specified levels of service in Table 10.1 to be maintained the road may need to be temporally changed to a lower level of service and in some cases the level of service changed to an Extreme Snow and Ice Event as per Table 10.2. The decision shall be made in accordance with the Operational Requirements. The Engineer shall be notified immediately of any decision to close the road as well as those organisations specified in table 4.2 of the Operational Requirements.

10.4 Specific Requirements

10.4.1 Quality Plan The Contractor shall submit to the Engineer for acceptance a Quality Plan detailing the procedures to be followed to ensure the specified levels of service are obtained. All activities of the Contractor carried out under this specification, including but not limited to network and weather monitoring, patrolling, gritting, chemical application, snow clearance and sweeping, shall be documented at the time of the activity and reported regularly to the Engineer in accordance with the Contractors Quality Plan. All activities carried out under this specification shall be documented on forms whose format is to be agreed between the parties to the contract and included in the Contractors Quality Plan. An example form is included in Appendix 10.3. The Contractor will be required to display the appropriate signage in accordance with COPTTM, the approved TMP and for any restrictions relating to level of service.

Maintenance Specification

10 Winter Maintenance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 60

10.4.2 Event Forecasting (Weather Monitoring)

The Contractor must proactively determine when and where pavement gritting, chemical application and/or snow clearance may be required and place the appropriate resources on stand by. This will be achieved through network monitoring including the following: a) weather monitoring throughout the contract period, including using a weather forecasting

system that provides as a minimum the following information:

i) accurate 24 hour forecast providing written description of forecast and expected temperatures relevant to the network

ii) predicted 2 to 5 day forecast indicating likely conditions (e.g. rain, frost, snow, etc) and confidence levels of condition occurring within the network

b) recording the forecasts, observations and the daily decisions on the agreed form.

c) communicating regularly with the Engineer when there is a risk of frost, ice or snow or adverse weather to ensure, as far as possible, hazards are anticipated.

d) providing a written confirmation of 24 hour forecast, 2 to 5 day forecast and the 24 hour decision by 14:00 of each day during the winter period to the Engineer and when requested by the Engineer.

Event management on the network includes opening and closing the permanent and temporary ice/frost grit warning signs located on the network. Payment for placement and management of signs is included in the gritting rate.

10.4.3 Event Response The Contractor is required to proactively respond to events forecast in accordance with 10.4.2 the Event Forecasting Clause by determining when and where pavement gritting, chemical application and/or snow clearance is required and then: mobilising appropriate resources as required

liaising with the Engineer, Police, 0800 4 Highways /Automobile Association and Territorial Authorities as required in Table 4.2 of the Operational Requirements

maintaining the road information signs including opening and closing the permanent and temporary ice/frost grit warning signs located on the network.

providing sufficient information to the Engineer, as specified, so the Engineer can update the road information report.

It is the Contractor’s responsibility to check and validate that the published road information is current and accurate.

Maintenance Specification

10 Winter Maintenance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 61

Patrolling shall continue until the ice or snow event ends. Patrolling shall also be programmed to check on sites outside those identified for treatment and those areas undergoing treatment during the event to ensure that the network is maintained in a safe condition. Should other previously unidentified areas be found to be affected by ice or snow the areas shall immediately undergo treatment in accordance with the required level of service.

10.4.4 Information Supplied by the Engineer

Appendix 10.1 details the Sites that have historically posed a potential frost, ice or snow problem.

10.5 Treatment 10.5.1 Snow Clearance

Snow shall be cleared as close as possible to the pavement surface without causing damage to the pavement. Snow shall be removed clear of the shoulder and kerb and channels where possible and not left where snowmelt is able to run across trafficked surfaces. As a secondary priority windrowed snow shall not be left where it blocks accessways, sideroads or footpaths. On unsealed roads, windrowed maintenance aggregate resulting from snow clearance shall be evenly re-spread over the trafficked surfaces after the snow in the windrow has thawed.

10.5.2 Pavement Gritting 10.5.2.1. Grit Stockpiles

As a minimum grit stockpiles shall be located at the areas specified in Appendix 3.5 and the Operational Requirements. They are to be located so they do not breach any environmental or statutory requirement nor create a traffic hazard by their location or operation. Stockpiles shall not encroach within 6 metres of a traffic lane. The grit stockpiles shall also be located to minimise the risk of the grit becoming contaminated by over size stone, weed seeds, twigs and branches, silt, clay or similar contaminants. The Contractor is to advise the Engineer which of the NZTA stockpile sites will be used to stockpile grit for winter maintenance operations.

10.5.2.2. Grit Material Properties Grit shall: a) be sharp, angular aggregate.

b) have a crushing resistance of at least 100kN when tested to NZS4407 Test 3.10.

c) have a grading complying with the grading envelopes in Table 10.3 when tested to NZS4407 test 3.8.1 or 3.8.2. the NZTA may approve local variant grading envelopes.

d) be free of seeds, if used in National Parks and Conservation areas. As confirmed by test results from the Agriquality National Seed Laboratory, Palmerston North.

Maintenance Specification

10 Winter Maintenance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 62

Table 10.3 – Grit Grading Sieve Aperture Percentage

Passing

9.5mm 100 4.75 mm 80-100 2.36mm 40-80 1.18mm 25-60 75 µm 0-2

10.5.2.3. Application of Grit

Grit shall be applied evenly across the traffic lanes so that the surface is covered to such an extent that sufficient surface friction is maintained for traffic to travel safely in winter driving conditions.

10.5.2.4. Removal of Grit The grit shall be removed if: a) it obstructs water draining from the road surface

b) build up of grit becomes a traffic hazard

c) it is not required because ice or regular frosting is not occurring and there is no immediate threat of ice.

At the end of the winter season, all grit shall be removed from site, including shoulders, berms and under guardrails, to a disposal area in accordance with Section 3 Stockpile and Disposal Areas.

10.5.2.5. Other Contractors If gritting is applied to a surface resealed under a TNZ P/17 contract, the Maintenance Contractor must advise the TNZ P/17 Contractor within one week of grit application. Refer to Table 4.2 of the Operational Requirements for information on TNZ P/17 contracts.

10.5.3 Chemical Treatment 10.5.3.1. CMA Material Properties

Calcium Magnesium Acetate (CMA) is the approved chemical for use on roads and is subject to Resource Consent requirements. The details of the Resource Consent for CMA, if part of this contract, is listed in Appendix 7.1.

10.5.3.2. CMA Application Where the use of CMA is included in the Operational Requirements then the manufacturer’s recommendations should be followed with a general concentration of 25 percent solution. This mixture is equal to mixing CMA at a rate of 0.38 kg/l of fresh water.

Maintenance Specification

10 Winter Maintenance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 63

In the absence of any other information CMA will be applied at an application rate to achieve 30 grams per square metre of CMA as an initial application and can be ‘topped up’ depending on weather conditions at application rates of between 15 and 20 grams per square metre of CMA.(30 grams per square metre of a 25% solution (providing a density of 1.14 kg/l) requires a spray rate of 0.1litres per square metre).

10.5.3.3. De-icing Where light snow has fallen, or ice has formed, CMA as solid pellets may be applied at 25 to 30 grams per square metre. At times the CMA may be combined with grit helping to improve surface friction and to stop the ice sheets from binding together again.

10.5.3.4. CMA Equipment and Calibration The Contractor is responsible for the application equipment, which must meet the following conditions: calibrated each year

capable of variable application rates which are also speed controlled

able to traverse iced roads safely

provided with suitable communication equipment in case of emergency

All calibration measurements should be recorded along with the name of the person responsible for calibration. Storage and mixing equipment must be operated to ensure that spillages are contained within the site and are environmentally and operationally safe.

10.5.4 Plant Indicative seasonal quantities for snow clearance and ice gritting (and/or chemical de-icing and/or anti-icing) are given in Appendix 10.1 and the Operational Requirements. Minimum requirements for plant to be provided is as specified in Appendix 10.2.

10.5.4.1. Snow Clearance Plant Type 1 Plant (high speed light snow removal plant) shall be capable of moving up to 200 millimetres of snow in a 2.4 metre wide strip at a speed of 60 kilometres per hour on easy curves and grades up to 5%. The equipment must also be capable of moving snow up to 200 millimetres deep on all sections of the network. Type 2 Plant (heavy snow removal plant) must be capable of moving up to 400 millimetres of snow in a 2.4 metre wide strip at a speed of 10 kilometres per hour on easy curves and grades up to

Maintenance Specification

10 Winter Maintenance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 64

5%. The equipment must also be capable of moving snow up to 400 millimetres deep on all sections of the network. Type 3 Plant (snow drift removal plant) must be capable of moving at least 120 cubic metres of snow an hour to 10 metres away from snow drifts or windrows on all sections of the network. The plant must also be able to move between sites at least at 15 kilometres per hour.

10.5.4.2. Gritting Plant Type 4 Plant (grit spreading plant) shall be capable of spreading grit at rates between 1 and 5 cubic metres per lane kilometre. The plant shall be capable of operating on ice affected sections on the network. It shall also be of a configuration that allows loading times together with travel and operating speeds so as it can spread at least 10 cubic metres of grit an hour at various sites ranging up to 10 kilometres from a grit stockpile site. Type 5 Plant (grit removal plant), operated in accordance with clause 10.5.3.4, shall be capable of uplifting for transport all detritus and ice grit from sealed carriageway surfaces at the rate of 100 kilograms of material a minute and from concrete and sealed channels, sumps and catch pits at 80 kilograms per minute. It shall also have the capacity to hold and legally transport on the highways a minimum of 4 tonnes of detritus and ice grit at normal operating road speeds, on straight flat sections of road.

10.5.4.3. Chemical Application Plant Type 6 Plant (solid chemical spreader) shall be a spreader capable of accurately spreading a chemical at a spread rate of between 5 and 100 grams per square metre to a tolerance of + or – 5%, or + or – 1 gram per square metre (whichever is the greater) at speeds of at least 50 kilometres an hour. The plant shall also be capable of measuring and recording the actual spread rates to an accuracy of + or – 1% or, + or – 0.2 grams per square metre (which ever is the greater). Type 7 Plant (liquid chemical applicator) shall be capable of accurately spraying chemical at a rate of between 0.02 and 0.15 litres per square metre to a tolerance of + or – 0.003 litres per square metre (equivalent to + or – 1 gram per square metre of CMA in a 25% solution) at speeds of at least 50 kilometres an hour. The plant shall also be capable of measuring and recording the actual spread rates to an accuracy of + or – 1%.

Maintenance Specification

10 Winter Maintenance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 65

10.6 Performance Criteria

The performance measures applying to this specification are:- a) the road surface is maintained in a safe condition in accordance with Table 10.1, Pavement

Levels of Service.

b) inspections are completed on time and inspection records are available when requested by the Engineer.

c) the success rate in predicting and applying grit or chemical for ice conditions shall be at least 95%.

d) providing a written confirmation of 24 hour forecast, 2 to 5 day forecast and the 24 hour decision by 14:00 of each day during the winter period to the Engineer.

e) completion of forms documenting all monitoring and activities carried out under this contract and delivery of the forms to the Engineer at the agreed timeframes. Details of all monitoring and activities on the network shall be available if requested by the Engineer.

f) the Contractor shall cooperate with the Engineer in supplying data on the prediction success rate and response times. The Contractor shall assist the Engineer in refining the prediction system to improve its performance.

Maintenance Specification

11 Surfacings

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 66

11. Surfacings

11.1 Scope

This Section sets out the requirements for:

a) surfacings of repairs and pre-reseal repairs, including first coat seals, premix surfacings, and where required second coat sealing.

b) repairing surface defects, including but not limited to crack sealing and filling, scabbing, stripping, flushing and bleeding.

11.2 Definitions

Terms defined in Table 3.2, Definitions appear in bold. 11.3 Response Times

The Contractor must complete all work required by this Section by the dates shown on the agreed programme. In addition: a) Table 11.1 states the response time for reinstatement of all pavement markings, raised

pavement markers and removal of all loose chip from site.

b) incidents requiring urgent attention will be managed using Section 9 Incident Response (e.g. bleeding)

c) the Contractor shall monitor the weather throughout the contract period in accordance with the requirement of clause 11.3.1.1 and when bleeding is anticipated, respond in sufficient time.

Table 11.1: Reinstatement of Roadmarkings, Raised Pavement Markers and Removal of

Loose Chip

Response Time Class

Pavement Markings* Raised Pavement Markers

Removal of Loose

Chip*

All Highways Within 48 hours of completing first coat and, where required, second coat seals

Within 72 hours of completing the second

coat seal, or as specified for pre-reseal

repairs

Within 48 hours

* Note: All loose chip must be removed prior to reinstatement of pavement markings. All pavement markings must be reinstated and loose chip must be completely removed from site prior to the removal of temporary traffic control. Where the repair is a pre-reseal repair, a second coat seal is not required.

Maintenance Specification

11 Surfacings

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 67

11.3.1.1. Weather Observation (Monitoring)

The Contractor must determine when and where pavement gritting may be required and place the appropriate resources on stand by. This will be achieved through:

a) monitoring the weather throughout the contract period

b) communicating regularly with the Engineer during periods when there is a risk of bleeding, to ensure, as far as possible, hazards are anticipated.

11.4 Specific Requirements

All pavement repairs must have a sealed surface: a) at the end of each day's work, unless circumstances, e.g. weather, are not suitable for surfacing

(see Section 11.4.2)

b) which is maintained for the duration of all public holidays and the periods specified in First Schedule, Part B, Clause 1.2, Definitions.

11.4.1 Surface Defect Repairs

a) All surface defects must be repaired in accordance with the Operational Requirements, the Maintenance Intervention Strategy and the following requirements, unless otherwise agreed.

b) The PSV of all sealing chip and other surfacing aggregates must comply with TNZ T/10 or as stated in the Operational Requirements, unless otherwise agreed, except for:

first coat seals, which are programmed for a second coat seal within 3 months, and,

pre-reseal repairs.

c) Surface defect repairs and, in particular, texturising must not be used for pre-reseal repairs. In general this work will be completed by the resurfacing contractor.

Much of the repair work associated with highway routine maintenance involves chip sealing the surface of repairs.

11.4.2 Construction of Surface Sealing

The final surfacing shall be of the same type as the surrounding pavement, except for pre-reseal repairs where the texture and hardness of the first coat seal must be consistent with the reseal design, at the intended time of reseal.

If for any reason the seal coat is not achieved on the same day, the Contractor shall take positive steps to ensure that the repair surface does not unravel allowing loose material on the road surface. Should ravelling occur the Contractor shall immediately remove all loose material from the road surface and stabilise the surface of the repair. The Contractor may maintain the integrity of the repair by application of a temporary holding coat providing this is not detrimental to the final seal coat and if a first coat seal cannot be achieved within two days.

Maintenance Specification

11 Surfacings

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 68

All pavement repairs must have a sealed carriageway surface which is maintained for the duration of all public holidays and long weekends specified in First Schedule, Part B, Clause 1.2 Definitions.

Once all surfacing work is complete, the repair must comply with the tolerances stated in Appendix 2.3 so there is a smooth transition from the adjoining pavement on to and off the repair and no ponding of water. That the finished pre-reseal repair, including asphaltic joints, is flush with existing pavement surfaces and utility covers so as not to create adverse noise and vibration effects.

11.5 Treatments

11.5.1 First Coat Sealing

The first coat seal must overlap the area of the repair by 100mm to 150mm and when complete present a tidy appearance of rectangular shape; ragged edges will not be accepted.

If agreed, the Contractor may use alternatives such as two coat sealing, slurry seal or thin asphaltic concrete overlay.

11.5.2 Second Coat Sealing

Unless otherwise agreed or specified in the Contract Documents, all repairs except pre-reseal repairs, must be second coat sealed.

a) The second coat seal must overlap the first coat seal by 100mm to 150mm, and when complete

present a tidy appearance of rectangular shape; ragged edges will not be accepted

b) be constructed such that six months after completion, the texture of the repair shall be consistent with the surrounding pavement surfacing

c) not show evidence of blackening of the surface of the pavement immediately beyond the repair caused directly by excess binder tracked from the repair.

11.5.3 Premix Surfacings

All premix surfacing must be designed and constructed to comply with the requirements of the Definition section and, six months after completion, the texture of the repair shall be consistent with the surrounding pavement surfacing, or in the case of pre-reseal repairs, the texture and hardness of the premix must be consistent with the reseal design, at the intended time of reseal. .

11.5.4 Crack Sealing and Filling

The Contractor shall ensure that cracks are effectively sealed and shall be responsible for the chip size, binder type and quantity proposed for use in the particular repair. Crack filling shall be completed to a sufficient width to ensure that the crack is fully covered with sealing product.

Maintenance Specification

11 Surfacings

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 69

The Contractor shall ensure that the final surface texture matches the existing and that no bleeding or flushing occurs during the Contract period. Cracks requiring filling are covered below.

11.5.4.1. Crack Filling When crack filling either prior to sealing or as a single treatment is specified, it is the Contractor’s responsibility to ensure that areas to be treated are free from excess moisture and prepared by removing any grit, dirt, detritus or other deleterious matter prior to the filling of the cracks with one of the following materials, or an approved alternative material. a) Cracks not wider than 5 mm A bituminous binder. b) Cracks wider than 5 mm but not wider than 20 mm A bituminous binder with filler. A waterproofing seal coat shall be applied following crack sealing. c) Cracks wider than 20 mm A fine premix material. A light tackcoat shall be applied to the sides of the cracks to be filled, and a waterproofing seal coat shall be applied following crack sealing. d) Polymer modified proprietary materials Such materials shall be applied strictly in accordance with the manufacturers' instructions. These may be used for all cracks over 5 mm in width. In asphaltic concrete, polymer modified material shall be applied over all cracks in a 100 mm wide strip as a stress-absorbing bandage.

11.5.4.2. Slippage Cracks

If removal and replacement of the in situ material is required in order to repair a slippage crack, the repair must be completed as a digout repair (see Section 5).

11.5.5 Scabbing and Stripping 11.5.5.1. Extent of Area to be Treated

Only the area of scabbing or stripping shall be treated and this shall be marked on the road surface.

11.5.5.2. Surface Preparation Areas to be treated shall be free from excess moisture and prepared by removing any grit, dirt, detritus or other deleterious matter prior to the application of binder.

Maintenance Specification

11 Surfacings

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 70

11.5.5.3. Alternative Treatment for Stripping

Where the Contractor considers there to be adequate bitumen present, a proposal to liven the binder using diluent may be submitted to the Engineer for approval.

11.5.5.4. Application of Binder Binder shall be applied in a fine mist spray. a) Scabbing Binder shall be applied only to the area of scabbing. Care must be taken to avoid spraying binder on to the surrounding pavement. b) Stripping Binder shall be applied to the width specified by the Engineer.

11.5.6 Flushing and Bleeding

The Contractor must nominate the method to repair bleeding or flushed areas.

11.5.6.1. High Pressure Water Treatment If high pressure water treatment (e.g. waterblasting) is proposed then it must be performed in accordance with Transit Specification TNZ P/26.

11.5.6.2. Diluent and Chip Precoated chip or heated chip shall be produced by a method approved by the Engineer. Sufficient diluent shall be sprayed on the road surface under suitable weather conditions to liven the binder to ensure a satisfactory chip take. The Contract shall select appropriate chip size, diluent and adhesion agent following the principles in Chip Sealing in New Zealand, Chapters 8 and 12. Chip spreading must follow immediately on spraying of the diluent. The Contractor must ensure there is sufficient rolling to bed the chip.

11.5.6.3. Pavement Gritting

Pavement gritting is used for the treatment of bleeding. Gritting must be completed with sealing chips that are no larger than the surrounding surface, but sufficiently large to prevent subsequent flushing through binder rise.

The sealing chip may be hand spread, but care must be taken to avoid over chipping.

Maintenance Specification

11 Surfacings

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 71

All surplus chip must be removed from the traffic lanes at the end of each day and completely removed from the Site once the bleeding is controlled.

11.5.7 Cold Milling

11.5.7.1. Extent of Area to be Treated Only the area marked or defined by the Engineer on the road surface shall be cold milled.

11.5.7.2. Cold Milling Where the cold milled area is to be backfilled, all edges shall be finished vertical. No longitudinal or transverse vertical edges shall be left unprotected and exposed to traffic overnight. All cold milling machines with a drum width of more than 750 mm shall be equipped with a self loading conveyor. All contaminants and milled material shall be intercepted and disposed of at an approved disposal site or stockpiled for future recycling or other reuse in accordance with Section 3 Stockpile and Disposal Areas. All stormwater outlets, sumps, service boxes and manholes shall be protected against damage. All spoil shall be removed from the site.

11.5.7.3. Finished Surface The depth cold milled, after removal of all loose material, shall be –0 mm, + 5 mm of the specified depth. The finished surface shall vary by no more than 5 mm from a 3 m straightedge laid longitudinally or a 1 m straightedge laid transversely, including between adjacent runs.

11.5.8 Other Treatments

The Operational Requirements details the technical requirements and applications of the other treatments.

11.6 Performance Criteria

11.6.1.1. Area of Compliance The performance criteria listed under clause 11.6.1.2 shall apply to the entire surface area of the work, or to any part of it providing the area affected by failure is no less than an area of 0.1m2.

11.6.1.2. Performance Criteria The performance of the Contractor during the Contract period will be measured by the following criteria: a) that all repairs are carried out in accordance with this Specification by the date shown on the

agreed programme, and within the response times stated.

Maintenance Specification

11 Surfacings

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 72

b) inspections are completed on time and inspection records are available when requested by the Engineer.

c) the chip sealing, including first coat seals, second coat seals and repairs of all surface defects:

i) does not flush, bleed or strip before the end of the defects liability period,

ii) there are no loose chips on the road surface on completion of the repair,

iii) the surfacing aggregate remains proud of the binder

iv) the binder is not picked up by tyres

v) the skid resistance shall not deteriorate such that is it significantly lower than that apparent in the same cross section location on the pavement immediately before and after the work.

d) that the sealed carriageway surface of second coat seals and repairs of all surfaces have a consistent texture 6 months after the construction of the second coat seal, except for pre-reseal repairs where the texture and hardness of the first coat seal must be consistent with the reseal design, at the intended time of reseal.

e) that material used for crack filling and sealing shall remain in place, waterproofing the crack, for the length of the defects liability period.

f) that treatment of flushing, scabbing or bleeding leads to an improvement in road condition.

g) repairs shall be constructed to the tolerances in Appendix 2.3.

Maintenance Specification

12 Digouts

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 73

12. Digouts

12.1 Scope

This Section sets out the requirements for digout repairs where a structural pavement repair is needed.

12.2 Definitions

Terms defined in Table 3.2, Definitions appear in bold.

12.3 Response Times

The Contractor must complete all digout repairs, including all surfacing and reinstating pavement marking and raised pavement markers, by the date shown on the agreed programme. In addition:

a) Table 12.1 states the response times for the completion of seal coats following commencement of the repair

b) Table 12.2 states the response time for reinstatement of all pavement markings, raised pavement markers and removal of all loose chip from site.

Table 12.1: Seal Coats

Response Time Class

First Coat Second Coat (where required)

M and U 1 Day 1 Month

R1 1 Day 1 Month

R2 2** Days 1 Month

R3 2** Days 1 Month

R4 2** Days 1 Month

Table 12.2: Reinstatement of Roadmarkings, Raised Pavement Markers and Removal of

Loose Chip

Response Time Class

Pavement Markings* Raised Pavement Markers

Removal of Loose

Chip*

All Highways Within 48 hours of completing first coat and, where required, second coat seals

Within 72 hours of completing the second

coat seal, or as specified for pre-reseal

repairs

Within 48 hours

* Note: All loose chip must be removed prior to reinstatement of pavement markings. All pavement markings must be reinstated and loose chip must be completely removed from site prior to the removal of temporary traffic control. ** Note: That the finished pre-reseal repair, including asphaltic joints, is flush with existing pavement surfaces and utility covers so as not to create adverse noise and vibration effects. Where the repair is a pre-reseal repair, a second coat seal is not required.

Maintenance Specification

12 Digouts

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 74

12.4 Specific Requirements 12.4.1 Repair Treatments

A digout is the repair of the existing pavement where the repair is undertaken by either of the following methods. If required, the work includes reinstating and/or reconstructing of the adjoining shoulder.

12.4.1.1. Digout Repairs

A digout repair includes excavating and replacing the in situ material with:

a) TNZ M/4 basecourse and/or

b) subbase, and/or

c) bitumen bound basecourse, and/or

d) asphaltic concrete, and/or

e) geotextile fabric complying with TNZ F/7, and/or

f) any other method and/or materials agreed with the Engineer

and resurfacing with appropriate seal coats constructed as specified in Section 11.

12.4.1.2. Stabilisation Repairs

A stabilisation repair includes stabilising the in situ material and surfacing constructed as specified in Section 11, together with any make up aggregate if required.

12.4.2 Repair Design

The Contractor must design all digout repairs with a minimum design life of 10 years unless indicated otherwise in the Maintenance Intervention Strategy (MIS).

The Contractor must have a documented procedure for determining design life including

a) inspection

b) investigation, including laboratory and field testing

c) where appropriate, determining the type and quantity of stabilisation agent and any make up aggregated required to restore grading requirements for the basecourse

d) marking on the pavement surface the location and extent of all proposed digout repairs.

If reusing the in situ material is the preferred repair method, the Contractor must demonstrate other lower priced methods are inappropriate.

Maintenance Specification

12 Digouts

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 75

12.4.2.1. Depth of Materials

For backfill of repairs in pavements the depth of materials shall meet the repair design requirements defined in Clause 12.4.2. Where the pavement depths have not been designed the following shall apply: a) For digouts up to 200 mm deep, basecourse specified in Clause 12.4.3.4 shall be used. Where a

thin asphaltic concrete layer is required, the basecourse shall terminate a nominal depth of 20 mm or 2.5 times the maximum asphaltic concrete stone size below the finished pavement surface, whichever is greater.

b) For digouts deeper than 200 mm, backfill of the top 200 mm shall be basecourse material specified in Clause 12.4.3.4. Backfilling below this depth shall meet the requirements for sub-base backfill defined in clause 12.4.3.3. up to the design pavement depth and backfill required below the design pavement depth shall meet the requirements for subgrade material specified in clause 12.4.3.2. Where a thin asphaltic concrete layer is required, the basecourse shall terminate a nominal depth that is 2.5 times the maximum asphaltic concrete stone size below the finished pavement surface.

c) For digouts in structural asphaltic concrete the depth of asphaltic concrete backfill shall match the existing asphaltic concrete depth. The type of AC should have properties which are the same or similar to the surrounding AC.

12.4.3 Materials 12.4.3.1. General

All materials used in the repair shall meet the requirements of the appropriate Transit/NZTA specification, or be approved by the Engineer.

12.4.3.2. Subgrade Backfill Subgrade material used as backfill shall have permeability no higher than subgrade material surrounding the repair area. The material shall have a soaked CBR value of not less than 10 unless a higher value is specified in the contract documents

12.4.3.3. Sub-base Backfill

Unless otherwise agreed, all subbase material must have a:

a) minimum soaked CBR value of 40

b) maximum aggregate size no greater than 0.4 times the compacted layer thickness

c) sand equivalent of greater than 35, or a sand equivalent of less than 35, but shall be well graded with no more than 10% by mass passing the 0.425mm sieve

Maintenance Specification

12 Digouts

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 76

12.4.3.4. Basecourse Backfill

All basecourse aggregate must either comply with TNZ M/4, TNZ M/22 or other materials proven suitable for use as a basecourse subject to the Engineer’s agreement..

12.4.3.5. Asphaltic Concrete

Thin asphaltic concrete shall comply with TNZ M/10 or any other mix approved by the NZTA Manager, Operations. A grade 5 chipseal shall be applied to the repair surface before applying the asphaltic concrete. There shall be no sufficient windows left between the chip to ensure an adequate bond between the asphalt and the binder of the chip seal. Unless required in the contract documents, no diluents shall be used.

Structural asphaltic concrete shall be in accordance with TNZ M/10 or any other mix approved by the NZTA Manager, Operations

12.4.4 Construction 12.4.4.1. Cutting of the Perimeter

The perimeter of repairs shall be cut with suitable cutting equipment before executing the remainder of the work so that the sealed surface outside the perimeter of the repair area is not disturbed to the extent that the bond between the sealed surface and the basecourse is destroyed. Ragged edges will not be permitted.

12.4.4.2. Positive Drainage

Where necessary, positive drainage shall be installed and attention paid to any surface drainage improvements which may be necessary to ensure the design life of the digout. Drainage conduits shall comply with TNZ F/2 and have an internal diameter of not less than 50mm. The cover over drainage conduits shall be not less than 200 mm. The material surrounding the conduit shall be free draining and protect adjacent formations from erosion. Drainage trenches shall be backfilled and compacted to the same standards as the digout repair it drains.

12.4.4.3. Construction of Subgrade Backfill

The backfilling of the repair area, up to the levels of the subgrade adjacent to the repair shall be carried out in layers which will allow compaction to a standard no lower than the adjacent subgrade.

12.4.4.4. Construction of Sub-base and Basecourse Sub-base and basecourse backfill shall be placed in layers of uniform thickness and compacted to provide dense, stable layers which do not weave or creep under the action of compaction equipment or road traffic.

Maintenance Specification

12 Digouts

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 77

12.4.4.5. Stabilisation Repairs

Where stabilisation of the in situ material is required the quantity of stabilising agent(s) shall be thoroughly mixed into the in situ material and compacted to meet the requirements of 12.4.5.2 above. The stabilisation of repairs need not be limited to using cement or lime as the stabilising additive. However, any alternative treatments must be agreed with the Engineer for use in the contract works.

12.4.4.6. Surfacings Surfacings shall be constructed as specified in Section 4.

12.4.5 Removal of Surplus Material and Clean Up All material surplus to requirements shall be removed to approved disposal sites and stockpile areas in accordance with Section 3 Stockpile and Disposal Areas. No stockpile areas shall be permitted on the road reserve without written approval of the Engineer. All repaired areas shall be left clean and tidy on completion of the work including removal of loose chip on the surface or shoulders.

12.5 Drainage

The Contractor must pay specific attention to any necessary routine drainage maintenance to ensure the service life is provided.

12.5.1 Surface Water Channels

If required, existing surface water channels must be either regraded and trimmed or new surface water channels constructed for a length up to 5m either side of the digout. The batter slopes must be generally as shown in Diagram 3.1. The surface water channels must be well graded and shaped so the tie in with the existing drainage features is smooth and continuous and water does not pond.

12.5.2 Other Treatments

The Operational Requirements and the Maintenance Intervention Strategy details the specific technical requirements for the other treatments and/or materials.

12.6 Performance Criteria The performance of the Contractor during the contract period will be measured by the following criteria:

Maintenance Specification

12 Digouts

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 78

a) that all digouts, including all surfacing and reinstating pavement marking and raised pavement markers, are carried out in accordance with this Specification by the date shown on the agreed programme, and within the response times stated.

b) inspections are completed on time and inspection records are available when requested by the Engineer.

d) the repaired digouts maintain a smooth riding surface within the surface deviation tolerances specified for the length of the defects liability period.

e) no flushing, bleeding or scabbing of the sealed surface of the digout repair.

f) there shall be no depressions in the finished surface that will allow water to pond.

g) the surface shape of repairs shall be such that the existing road crossfall is maintained.

h) repairs shall be constructed to the tolerances in Appendix 2.3.

Maintenance Specification

13 Depressions

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 79

13. Depressions

13.1 Scope

This Section sets out the requirements for repairing depressions. This applies to the correction of settlement deformation, including depressions and wheel path rutting and settlement due to surface openings in surfaced roads.

13.2 Definitions

Terms defined in Table 3.2, Definitions appear in bold. 13.3 Response Times

The Contractor must complete all depression repairs, including all surfacing and reinstating pavement marking and raised pavement markers, by the date shown on the agreed Programme. In addition:

a) Table 13.1 states the response times for the completion of seal coats following commencement of the repair

b) Table 13.2 states the response time for reinstatement of all pavement markings, raised pavement markers and removal of all loose chip from site.

Table 13.1: Seal Coats

Response Time Class

First Coat Second Coat (where required)

M and U 1 Days 1 Month

R1 1 Days 1 Month

R2 2** Days 1 Month

R3 2** Days 1 Month

R4 2** Days 1 Month

Table 13.2: Reinstatement of Roadmarkings, Raised Pavement Markers and Removal of

Loose Chip

Response Time Class

Pavement Markings* Raised Pavement Markers

Removal of Loose

Chip*

All Highways Within 48 hours of completing first coat and, where required, second coat seals

Within 72 hours of completing the second

coat seal, or as specified for pre-reseal

repairs

Within 48 hours

* Note: All loose chip must be removed prior to reinstatement of pavement markings. All pavement markings must be reinstated and loose chip must be completely removed from site prior to the removal of temporary traffic control.

Maintenance Specification

13 Depressions

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 80

**Note: That the finished pre-reseal repair, including asphaltic joints, is flush with existing pavement surfaces and utility covers so as not to create adverse noise and vibration effects. Where the repair is a pre-reseal repair, a second coat seal is not required.

13.4 Specific Requirements 13.4.1 Methods of Repair

One of the following methods shall be used for repairs:

a) Premix Reshaping

b) Rip and Remake

c) Cold Mill and Inlay

d) Other, provided the method is approved by the Engineer.

13.4.2 Premix Reshaping Method

Reinstatement of acceptable shape with premix placed and compacted on the existing surface. Where required by the Engineer, and following an agreed curing period, the premix shall be surfaced as specified in Section 4.

13.4.2.1. Design of Premix

Standard premix is to be used for depression repairs. Other premixed materials e.g. OGEM premix must not be used for depression repairs unless approved by the Engineer. Approval will be subject to the Contractor demonstrating that the other premixed materials will not deform or result in subsequent flushing of the pavement surfacing.

13.4.2.2. Extent of Repair

The perimeter of the area within which re-shaping is required shall be determined by the Contractor. The basic area shall be the minimum required with such additional area necessary to establish straight lines to the edge of the repair and shall be clearly marked on the road surface.

13.4.2.3. Preparation of Surface Areas to be treated shall be free from excess moisture and prepared by removing any grit, detritus or other deleterious matter prior to the application of a tack coat.

13.4.2.4. Tack Coat A tack coat of quick breaking emulsion shall be applied prior to placing any premix material. Tack coat shall be applied to a dry surface and shall have "broken" just before premix is placed.

Maintenance Specification

13 Depressions

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 81

13.4.2.5. Construction

Areas where tack coat has not been covered with premix material shall also be treated with sand or grit to prevent pick up. To ensure satisfactory jointing of the new premix layer with the adjacent layer, it will be necessary to remove some of the old surfacing material from around the perimeter of the area to be reshaped. Joints shall be prepared to provide a true line and vertical face by saw cutting the perimeter. Straight line final treatment boundaries shall be established by the Contractor in accordance with clause 13.4.4.1 prior to cutting. The depth of material to be removed shall be such that a finishing layer of the required thickness can be constructed over the entire area of reshaping. A waterproof sealcoat using a grade 5 chip shall be applied before the premix is laid. The premix shall not be less than 15 mm thick and will generally correspond with the thickness of adjacent surfacing.

13.4.3 Rip and Remake Method

The perimeter of repairs shall be cut with suitable cutting equipment before executing the remainder of the work so that the sealed surface outside the perimeter of the repair area is not disturbed to the extent that the bond between the sealed surface and the basecourse is destroyed. Ragged edges will not be permitted. Removal of existing surfacing materials, followed by placement and compaction of unbound basecourse to an acceptable shape, and first coat sealing or premix surfacing where the surrounding road is surfaced with premix. The rip and remake of existing pavements must include:

a) cutting the perimeter of the repair

b) ripping the existing pavement

c) supplying and completely constructing up to 100 mm depth of unbound basecourse so the reshaped surface conforms to the shape and nature of the surrounding pavement

d) surfacing constructed as specified in Section 4.

13.4.3.1. Thickness of Surfacing to be Removed

Generally the thickness of surfacing material to be removed will not exceed 100 mm and in many cases will be less than that, except that when repairing surface openings, material shall be removed to the full depth of the basecourse layer.

When removing the existing seal, care shall be taken to remove the minimum practical amount of underlying pavement material.

Maintenance Specification

13 Depressions

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 82

13.4.3.2. Makeup Material

Basecourse material may need to be imported to replace surfacing and other material removed. All basecourse aggregate must comply with either TNZ M/4, TNZ M/22 or other materials proven suitable for use as a basecourse subject to the Engineer’s agreement.

13.4.3.3. Construction

Material shall be constructed so that upon completion of the work a uniformly dense and stable layer which does not weave or creep under the action of compaction equipment or road traffic is produced. Segregation and resultant hungry and fatty patches will not be acceptable. Compaction equipment employed shall be appropriate for the shape of the surface being corrected. Drum and plate dimensions shall be so chosen that edge compaction is attained without bridging. A temporary holding coat shall be applied if the Contractor cannot complete a first coat seal within two days.

13.4.4 Cold Mill and Inlay Method

Inlay material shall be Asphaltic Concrete to TNZ M/10 or any other mix approved by the NZTA Manager, Operations. The cold milling and inlaying of existing pavements must include:

a) cold milling the existing pavement

b) supplying and completely constructing up to 65mm depth of asphaltic concrete infill so the reshaped surface conforms to the shape of the surrounding pavement.

c) surfacing. constructed as specified in Section 4.

13.4.4.1. Extent of Repair The perimeter of the area within which re-shaping is required shall be established by the Contractor. The basic area shall be the minimum required with such additional area necessary to establish straight lines to the edge of the repair and shall be clearly marked on the road surface.

13.4.4.2. Thickness of Surfacing to be Removed

Generally the thickness of surfacing material to be removed will not exceed 100 mm and in many cases will be less than that, except that when repairing surface openings, material shall be removed to the full depth of the basecourse layer.

When removing the existing seal, care shall be taken to remove the minimum practical amount of underlying pavement material.

Maintenance Specification

13 Depressions

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 83

13.4.5 Other Treatments

Alternative treatments such as granular reshaping, may be agreed. These treatments include, but are not limited to, depressions, wheel track rutting and settlement in surfaced pavements. The Operational Requirements details the technical requirements and applications of the other treatments.

13.4.6 Surfacings

Surfacings shall be constructed as specified in Section 4.

13.4.7 Removal of Surplus Material and Clean Up All material surplus to requirements shall be removed and disposed off site.

13.5 Performance Criteria The performance of the Contractor during the contract period will be measured by the following criteria: a) that all work is carried out in accordance with this Specification by the date shown on the

agreed programme, and within the response times stated.

b) inspections are completed on time and inspection records are available when requested by the Engineer.

c) no flushing, bleeding, cracking or scabbing of the sealed surface of the repair.

d) there shall be no depressions in the finished surface that will allow water to pond.

e) the surface shape of repairs shall be such that the existing road crossfall is maintained.

f) repairs shall be constructed to the tolerances in Appendix 2.3.

Maintenance Specification

14 Edgebreak

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 84

14. Edgebreak

14.1 Scope

This section sets out the requirements for edge break repairs. 14.2 Definitions

Terms defined in Table 3.2, Definitions appear in bold.

14.3 Response Times

The Contractor must complete all edge break repairs, including reinstating pavement markings, by the date shown on the agreed programme. Table 14.1 states the response time for reinstatement of all pavement markings and removal of all loose chip from site.

Table 14.1: Reinstatement of Roadmarkings, and Removal of

Loose Chip

Response Time Class

Pavement Markings* Removal of Loose Chip*

All Highways Within 48 hours of completing first coat and, where required, second

coat seals

Within 48 hours

* Note: All loose chip must be removed prior to reinstatement of pavement markings. All pavement markings must be reinstated and loose chip must be completely removed from site prior to the removal of temporary traffic control. Where the repair is a pre-reseal repair, a second coat seal is not required.

14.4 Specific Requirements

14.4.1 Repair Methods 14.4.1.1. Shoulder Preparation

If shoulder maintenance is required it shall be carried out prior to the edge break repair as specified in Section 6.

14.4.1.2. Preparation of Edge Break Repair Area Before edge break is repaired, firm support shall be provided on each side of the repair area including tapers. A firm foundation and a vertical face of not less than 25 mm where the edge break fill material abuts the existing seal, are required.

14.4.1.3. Construction of Edge Break Fill Material

The edge break fill material shall be either premix or granular.

Maintenance Specification

14 Edgebreak

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 85

14.4.1.4. Construction of Edge Break Fill Material - Premix

When the edge break fill is premix, to ensure bond between existing and fill material including the vertical seal face, a light tackcoat of emulsion shall be applied before any fill material is placed. Upon completion, the outer edge of the repair shall present a uniform line lying between zero and 70 mm outside the nominal edge of the seal being repaired. At the end of the repair proper, any required transition between the existing seal edge and the repair edge shall be effected by a flat taper. Where the edge break repair is a pre-reseal repair, the texture and hardness of the repair must be consistent with the reseal design, at the intended time of reseal.

14.4.1.5. Edge Break Fill Material – Granular material Where edge break repairs are completed using granular material, they shall be surfaced as specified in Section 4 and the following: a) shall have a tidy appearance of rectangular shape without ragged edges.

b) any taper shall be sealed to follow the tapered line to form a tidy triangular shape.

c) the edge break repair area plus an overlap of 70 mm ± 20 mm onto the existing seal shall be sealed.

Maintenance Specification

14 Edgebreak

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 86

14.5 Performance Criteria

The performance of the Contractor during the contract period will be measured by the following criteria: a) that all work is carried out in accordance with this Specification by the date shown on the

agreed programme, and within the response times stated.

b) inspections are completed on time and inspection records are available when requested by the Engineer.

c) edge break repairs shall be carried out so that upon completion of the work a stable repair which does not weave or creep under the action of compaction equipment or road traffic is produced. The finished surface shall be a continuation of the adjacent sealed surface and shall not hold surface water

d) the completed surface shall have no flushing or bleeding

e) that the repair remains an integral part of the pavement structure within the specified tolerance.

f) there is no seal loss encroaching into the seal road surface by more than 100mm.

g) that there is no vegetation growing through the finished repair at time of payment.

h) there shall be no depressions between the repaired area and the existing edge of seal that will allow water to pond.

i) the surface shape of repairs shall be such that the existing road crossfall is maintained.

j) repairs shall be constructed to the tolerances in Appendix 2.3.

Maintenance Specification

15 Service Covers

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 87

15. Service Covers

15.1 Scope This Section sets out the requirements for adjusting of service covers necessary before asphaltic concrete paving, after a pavement reseal, settlement of the pavement adjacent to service covers, or settlement of the covers themselves.

15.2 Definitions

Terms defined in Table 3.2, Definitions appear in bold. 15.3 Response Times

The Contractor must adjust all service covers, including all surfacing and reinstating pavement marking and raised pavement markers, by the date shown on the agreed programme. In addition:

Table 15.1 states the response time for reinstatement of all pavement markings, raised pavement markers, and removal of loose chip.

Table 15.1: Reinstatement of Roadmarkings, Raised Pavement Markers, and Removal of Loose

Chip

Response Time Class

Pavement Markings* Raised Pavement Markers

Removal of Loose

Chip*

All Highways Within 48 hours of completing service

cover repairs

Within 72 hours of completing service

cover repairs

Within 48 hours

* Note: All pavement markings must be reinstated and loose chip must be completely removed from site prior to the removal of temporary traffic control.

15.4 Specific Requirements All work under this section must be completed in accordance with the National Code of Practice for Utilities' Access to the Transport Corridors.

15.4.1 Cutting Pavement Surface The perimeter of the opening shall be cleanly cut so as to maintain the integrity of the adjacent pavement surface. The cut shall be vertical. Straight lines shall not deviate more than 50 mm from a 1 m straight edge aligned between two points.

15.4.2 Installation of Service Covers for Strength and Level Service covers shall be designed and supported within the pavement structure to withstand the applied loadings without undue settlement or rocking. Service covers shall be adjusted to level using risers, adjusting rings, epoxy mortar, concrete, or additional service covers.

Maintenance Specification

15 Service Covers

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 88

All hardware shall be firmly held in place by adequate backfilling and compaction. A sufficient width of pavement around the riser or cover shall be excavated to ensure this. Acceptable widths are: 200 mm for backfill depth less than or equal to 300 mm

500 mm for backfill depth greater than 300 mm An acceptable method for backfilling is compliance with Section 5. Adjusting rings shall be located and fixed in place with a haunched mortar pad.

15.4.3 Surfacing

The reinstated pavement surface around the service cover shall: a) be waterproof including the interface with the service cover.

b) have a smooth surface profile.

c) match the cross-fall of the existing pavement.

15.5 Performance Criteria The performance of the Contractor during the Contract period will be measured by the following criteria: a) that all work is carried out in accordance with this Specification by the date shown on the

agreed programme, and within the response times stated.

b) inspections are completed on time and inspection records are available when requested by the Engineer.

c) no flushing or bleeding of repaired surface

d) that the repair work continues to meet the requirements of this specification for the length of the defects liability period.

e) the top of the service cover shall not exceed + 10 mm or be less than - 0 mm with respect to the surrounding pavement surface.

f) the surrounding material shall be uniformly tapered from the top of the service cover to the existing road surface.

g) that the finished service cover and surrounding surface, including asphaltic joints, are flush with existing pavement surfaces, so as not to create adverse noise and vibration effects..

Maintenance Specification

16 Shoulder Maintenance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 89

16. Shoulder Maintenance

16.1 Scope

This Section sets out the requirements for maintaining unsealed shoulders, side slopes and surface water channels. The work required by this Section does not include:

a) removing detritus from surface water channels

b) vegetation control on grassed shoulders

c) chemical control of side slopes and surface water channels

d) improvements to shoulders and surface water channels

e) shoulder maintenance in urban areas or on unsealed highways

f) maintenance of grassed shoulders and swales.

16.2 Definitions

Terms defined in Table 3.2, Definitions appear in bold. 16.3 Response Times

The Contractor must complete all shoulder maintenance work by the date shown on the agreed programme.

16.4 Specific Requirements

The Contractor shall inspect all road shoulders within the contract, prepare schedules of maintenance including location and priority work in order to meet the response times and submit the schedule to the Engineer.

16.4.1 Extent of Work

Shoulders must be maintained from the existing edge of seal to a line parallel to the edge of seal which is 500 mm beyond the invert of the surface water channels. If there are no surface water channels, the Contractor is responsible for maintaining the unsealed shoulder and side slope from the existing edge of seal to a line parallel to, and 3.0m offset from, the existing edge of seal.

16.4.2 Shoulder Maintenance

The Contractor shall maintain all unsealed shoulders, side slope and surface water channels (gravel and grassed) within the scheduled lengths as follows: a) all material used whether aggregate or topsoil, shall conform to the nominated specification in

the contract documents or shall be an equivalent material.

Maintenance Specification

16 Shoulder Maintenance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 90

b) the existing widths and crossfalls shall be maintained as agreed with the Engineer.

c) material shall not encroach onto the sealed carriageway at any time except during maintenance operations. Prior to completing maintenance activities all loose material must be removed from sealed surfaces.

d) for vegetated areas (e.g. grassed areas) an even and mowable vegetation cover shall be maintained.

e) all maintenance aggregate must be evenly graded aggregate with a maximum size of 20mm. Shoulders shall be maintained as follows: f) shoulder material shall be maintained in an even shape, and where material is added, it shall be

compacted using suitable compaction plant. Depth of loose material shall not exceed 20mm loose depth.

g) shoulders shall be maintained so a build up of material adjacent to the edge of seal that prevent water draining from the sealed surface does not form.

To reduce the long term costs of unsealed shoulder maintenance, the Contractor shall allow vegetation growth on existing shoulders. Existing vegetated shoulders must not be removed except to prevent ponding of water on the sealed surface immediately adjacent to the edge of seal.

16.5 Performance Criteria The performance of the Contractor during the contract period will be measured by the following criteria. a) that all shoulder maintenance work is carried out in accordance with this Specification by the

date shown on the agreed programme.

b) inspections are completed on time and inspection records are available when requested by the Engineer.

c) that the unsealed shoulders, side slopes and surface water channels remain compacted, and shed water from the adjacent sealed carriageway without ponding, channelling of water, or edge rutting.

d) that the unsealed shoulders, side slopes and surface water channels retain their widths and crossfalls.

e) all shoulder maintenance repairs shall have a finished surface such that no water ponds on the sealed carriageway, shoulder or taper edge.

Maintenance Specification

17 Barrier Repairs

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 91

17. Barrier Repairs

17.1 Scope

This Section sets out the requirements for repairing the following:

a) road safety barrier systems, meeting the specification requirements of TNZ M/23, of various types and materials and includes that part of the barrier covering the Length of Need (LON), (as defined in the State Highway Geometric Design Manual (SHGDM)), and the end terminals, and

b) barriers, handrails and rails for the containment of pedestrians and cyclists.

The work required by this Section does not include: a) repairing timber sight rails.

17.2 Definitions

Terms defined in Table 3.2, Definitions appear in bold.

17.3 Cyclic Inspections

All equipment failures due to crash damage or vandalism shall be identified, made safe and reported as specified in Section 9. The Contractor shall inspect all barriers within the Contract area at least at the frequency listed in Table 17.1 and shall repair barriers within the response times listed in sections 17.4.1 and 17.4.2.

Table 17.1: Inspection Frequency

Class Inspection Frequency

M Daily

U and R1 Every 2 Days

R2 Every 3 Days

R3 Weekly

R4 Weekly

The purpose of cyclic inspections is to identify any damaged barriers or barrier systems. Any damage identified must be reported to the Engineer.

17.4 Response Times 17.4.1 Temporary Repairs

All temporary repairs must be completed within 24 hours of notification.

Maintenance Specification

17 Barrier Repairs

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 92

17.4.2 Permanent Repairs

The Contractor shall submit a priced repair proposal to the Engineer, and install all replacement materials and components within the response times listed in table 17.2 and in accordance with the manufacturers instructions and/or specifications (where these are available), and best industry practice.

Table 17.2: Permanent Repair of Barrier Damage

Activity Response Time

Submit priced proposal for Repair of Damage to Barrier

Within 3 days from notification

Completion of Barrier Repair Within 2 weeks of Engineer’s Approval

17.5 Specific Requirements 17.5.1 Stockholding and Barrier Inventory

The Contractor shall provide updates to the inventory of all barriers in the contract area and make this available to the Engineer when requested. The Engineer shall provide the Contractor with the necessary information to initiate the barrier inventory within one month of the commencement of the Contract. Updates to the barrier inventory shall record:

the location of the barrier, (SH route position, and side of the road or median)

length of barrier, and general shape of railing (curve, bend and straight)

type of barrier, and indicate if painted

type of end terminal, includes start type and end type

type of defect (if present) and action determined to remedy the defect

a log of any maintenance work completed and the date of completion

installation date.

Appendix 17.1 lists the minimum stockholding that must be maintained for each barrier system. 17.5.2 Temporary Works prior to completing Permanent Works on Barrier

Where temporary works on guardrails or terminal ends are required, they shall be designed such that road users must be protected from the risks arising from damaged or missing sections of barriers. Notwithstanding the requirements, the Contractor shall ensure that appropriate urgent work, e.g. temporary repairs, are carried out to any damaged barrier or barrier terminal, and if necessary the site secured by implementation of effective Positive Traffic Management in accordance with COPTTM to ensure the affect on the safety of road users is minimised until permanent repairs are completed.

Maintenance Specification

17 Barrier Repairs

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 93

17.5.3 Damage to Barrier Terminal

Any damage to a barrier terminal shall be reported and assessed for appropriate treatment prior to completing permanent repairs. Repairs are to comply with TNZ M/23. Damaged barrier terminals that do not comply with TNZ M/23 shall be replaced with an appropriate compliant barrier terminal or impact attenuator. If the barrier system requires modification to comply with TNZ M/23, and the SHGDM including the LON, the Engineer may direct the Contractor to complete the appropriate permanent remedial works. At the completion of any new installation or permanent repair to a barrier terminal, the Contractor is required to complete the manufacturers installation checklist and provide the completed checklist to the Engineer with the monthly report.

17.5.4 Major Damage to Barrier

Barriers subjected to major damage shall be reported and assessed for appropriate treatment prior to completing permanent repairs. If the barrier system requires modification to comply with TNZ M/23, and the SHGDM including the LON, the Engineer may direct the Contractor to complete the appropriate remedial works.

17.5.5 Minor Damage to Barrier

Minor damage to a barrier of up to three sections of rail or equivalent concrete barrier (excluding the barrier terminal section), shall be reported and assessed for appropriate treatment prior to completing permanent repairs. As a minimum, this would normally require the Contractor to reinstate all damaged barrier elements to the lines and levels that existed prior to the damage occurring. Damaged barriers, which were incorrectly installed, shall be repaired to the correct standard, determined by the Engineer, in accordance with the manufacturer’s specification. If the barrier system requires modification to comply with TNZ M/23, and the SHGDM including the LON, the Engineer may direct the Contractor to complete the appropriate remedial works. If barriers are on a bridge and the bridge structure has been damaged then the Contractor shall report the damage immediately to the Engineer so that bridge can be appraised by a suitably qualified engineer.

17.5.6 Permanent Repairs

a) Road Safety Barriers

The Contractor shall report any barrier damage to the Engineer prior to making permanent repairs. Permanent repairs shall be undertaken after an assessment of the barrier system compliance with TNZ M/23, the SHGDM including a determination of the LON by the Engineer who shall direct the Contractor on the work to be performed.

Barriers incorrectly installed shall be repaired to the correct standard, as and when directed/determined by the Engineer, and in accordance with the manufacturer’s specification. Where a damaged barrier does not comply with TNZ M/23 any replacement parts shall be compliant with TNZ M/23, and be in accordance with the manufacturer’s specification.

Maintenance Specification

17 Barrier Repairs

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 94

b) Barriers, handrails and rails for the containment of pedestrians and cyclists.

The Contractor shall report any barrier damage to the Engineer prior to making permanent repairs. Permanent repairs shall be undertaken after an assessment of the barrier system by the Engineer who shall direct the Contractor on the work to be performed. Barriers incorrectly installed shall be repaired to the correct standard, as and when directed/determined by the Engineer, and in accordance with the manufacturer’s specification.

Damaged barriers shall be repaired to a standard not less than that existing before the damage occurred, or if they were incorrectly installed, they shall be repaired to the correct standard, in compliance with the standard determined by the Engineer, and be in accordance with the manufacturer’s specification.

c) Repairs to Bridge Barriers.

The Contractor shall obtain the agreement of the Engineer to the Contract for repairs to bridge barriers. This includes repairs to road safety barriers and barriers for the containment of pedestrians and cyclists.

17.5.7 Barrier Serviceability

All barriers in the contract area shall be maintained by the Contractor to be in a condition fit for purpose. The Engineer may direct the Contractor to maintain, repair, and replace barrier parts or the whole barrier if it is not fit for purpose. The Contractor shall complete the work in accordance with the manufacturer’s specification.

All barrier terminals fitted with an anchor cable shall be maintained fit for purpose by the Contractor. The Contractor shall ensure that cables are taut and not loose or draped below the W-Beam. The Contractor shall replace Breakaway Cable Terminals (BCT’s) that are deemed to be not fit for purpose and require major repair with terminals and associated barrier in compliance with TNZ M/23 and the SHGDM including satisfying the LON, at the direction of the Engineer.

The Engineer may direct the Contractor to replace lengths of barrier comprising W-Sections or steel rails which are not fit for purpose with W-Beam or other barrier in compliance with TNZ M/23.

17.6 Materials Road Safety Barriers shall comply with TNZ M/23 for general road application, and for bridge side protection Transit’s Bridge Manual, and TNZ M/17P "W"-Section Bridge Guardrails, where applicable. Layout and configuration shall be in accordance with the SHGDM.

Maintenance Specification

17 Barrier Repairs

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 95

17.7 Performance Criteria

The performance of the Contractor will be measured by the following criteria: a) that all guard rails and barriers are maintained in accordance with this Specification by the

date shown on the agreed programme, and defective guardrails and barriers are repaired within the response times stated.

b) inspections are completed on time and inspection records are available when requested by the Engineer.

c) that all repairs, installed guardrails and barriers are in accordance with the manufacturers instructions and/or specifications (where these are available) and best industry practice.

Maintenance Specification

18 Abandoned Vehicles

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 96

18. Abandoned Vehicles

18.1 Scope

This Section sets out the requirements for removing and disposing of abandoned vehicles. 18.2 Response Times

Upon notification from the Engineer, the Contractor must deal with all abandoned vehicles by the date agreed.

18.3 Specific Requirements

The Contractor shall notify the Engineer of any vehicle that appears to be abandoned within the road reserve and indicating to the Engineer whether the vehicle poses a hazard to road users. If immediate action is required, this may be tasked under incident response.

18.3.1 Vehicle Removal and Disposal

The State Highway Control Manual outlines the process to be followed for the management of abandoned vehicles. Generally the Engineer will instruct when a vehicle needs to be removed, however where a vehicle poses a hazard to road users, immediate action by the Contractor may be required. The Contractor must uplift, remove, and store all abandoned vehicles. The vehicles must be stored in a secure area for a minimum period of one calendar month. If the vehicle is left unclaimed, the Contractor must dispose of the vehicle according to the Engineer's instructions.

Maintenance Specification

19 Potholes

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 97

19. Potholes

19.1 Scope

This Section sets out the requirements for repairing potholes in sealed roads.

19.2 Definitions Terms defined in Table 3.2, Definitions, appear in bold.

19.3 Cyclic Inspections

The Contractor shall inspect all roads within the Contract area at least within the frequency listed in Table 19.1. The Contractor shall ensure that all potholes found during these inspections are repaired at the time of inspection.

Table 19.1: Inspection Frequency for Potholes

Class Inspection Frequency

M Daily

U and R1 Every 2 Days

R2 Every 3 Days

R3 Weekly

R4 Weekly

19.4 Response Times

All potholes shall be repaired within the response times detailed in Table 19.2. The response times in Table 19.2 apply from the time of notification.

Table 19.2: Pothole Repairs

Response Time Class

May – September October – April

M 24 Hours 24 Hours

U and R1 24 Hours 48 Hours

R2 24 Hours 3 Days

R3 2 Days 4 Days

R4 3 Days 6 Days

Maintenance Specification

19 Potholes

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 98

19.4.1 Large Potholes

If an individual pothole exceeds 1m2 in area, the Contractor must:

i) within the response times, provide the most practical repair that is reasonably possible given the conditions of the surrounding pavement.

ii) notify the Engineer in writing, within 24 hours of first observing and repairing the pothole, of the location of the area of pavement which is considered to have failed or is unsound, and the proposed method of permanent repair.

iii) programme and complete the permanent repair of the area, as urgent work.

19.4.2 Unstable Pavement

When, in the opinion of the Contractor, the pothole is due to underlying instability of the road pavement, the Contractor shall report such potholes after repair to the Engineer.

19.5 Specific Requirements 19.5.1 Repair Method

The immediate area surrounding the pothole shall be excavated to remove distressed material. Ragged and/or proud edges shall not be permitted and vertical squaring up of the existing edge around the perimeter of the area to be treated is required. In unbound granular materials the sides of the excavation shall be trimmed to a battered slope. The Contractor shall select the repair method most appropriate to correct the defect. The materials used shall comply with TNZ M/10 or any other mix approved by the NZTA Manager, Operations.

19.5.2 Temporary Repair Method

When the weather is unsuitable for a permanent repair, the pothole will be filled with a suitable material to make the area safe until a permanent repair can be effected.

19.5.3 Surfacing

The finished running surface of the repair shall be waterproof, dense and stable and not move under the action of traffic.

Maintenance Specification

19 Potholes

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 99

19.6 Performance Criteria

The performance of the Contractor during the Contract period will be measured by the following criteria: a) the safety of road users is not impaired by potholes that have not been repaired

b) inspections are completed on time and inspection records are available when requested by the Engineer

c) inspections are completed within the specified frequencies

d) potholes are repaired within the response times required

e) the pothole repair remains intact

f) repaired potholes continue to remain waterproof and maintain a smooth riding surface

g) there is no flushing or bleeding of the surface of potholes

h) appropriate notification to the Engineer within the response time required, of individual potholes exceeding 1m2

i) the excavation of the repaired area is carried out in such a manner that the integrity of adjacent sections of pavement is not disturbed

j) repairs shall be constructed to the tolerances in Appendix 2.3.

Maintenance Specification

20 Detritus and Slip Removal

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 100

20. Detritus and Slip Removal

20.1 Scope

This Section sets out the requirements for uplifting and completely removing detritus and slips from the surface of the carriageway, shoulder, drainage features, weighpits, rest areas and including the removal of detritus from sump grates in rural areas. The work required by this section includes removal of detritus:

resulting from the Contractor's operation e.g. pavement gritting, surfacing of repairs

requiring removal to complete a subsequent operation e.g. pavement marking The work required by this Section excludes removing:

a) litter,

b) detritus from kerb and channel and sealed surfaces within urban areas, unless listed in Appendix 20.1 or the Operational Requirements.

Clearance of slips occurring during an event where Section 9 Incident Response provisions are being used will generally be managed under Section 9. Agreement will be reached between the Contractor and the Engineer when clearance of slips will be managed under Section 20 provisions.

20.2 Definitions

Terms defined in Table 3.2, Definitions appear in bold.

20.3 Cyclic Inspections

The Contractor shall inspect all roads within the Contract area at least at the frequency listed in Table 20.1 and shall remove detritus within the response times.

Table 20.1: Inspection Frequency

Class Inspection Frequency

M Daily

U and R1 Every 2 Days

R2 Every 3 Days

R3 Weekly

R4 Weekly

20.4 Response Times 20.4.1 Detritus Removal

Table 20.2 states the response times for removing detritus. The response times apply from the time of notification of the detritus.

Maintenance Specification

20 Detritus and Slip Removal

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 101

Table 20.2: Detritus Removal

Response Time Class

Sealed Surfaces Lined and Unlined Channels

M 24 Hours 24 Hours

U and R1 24 Hours 3 Days

R2 3 Days 4 Days

R3 4 Days 6 Days

R4 6 Days 9 Days

20.4.2 Slips

Slips greater than 1m3 must be removed by the date shown on the agreed programme. Where a slip poses a hazard to road users, immediate action by the Contractor may be required. Slips requiring urgent attention (e.g. where a slip obstructs an adjacent drainage facility and forces water across the carriageway surface) will be managed using Section 9 Incident Response.

20.5 Specific Requirements

20.5.1 Detritus Removal from Site

When undertaking detritus removal, all detritus shall be completely removed from the site of the works and disposed of at an approved disposal site in accordance with Section 3 Stockpile and Disposal Areas.

20.5.2 Detritus Removal Intervention Levels

The Contractor must ensure that all detritus is removed when it exceeds the following intervention levels:

20.5.2.1. Sealed Surface

Detritus is to be removed from any sealed surface where the amount of detritus exceeds 0.2 kg/m2.

20.5.2.2. Lined Drainage Channels Detritus must be removed from lined channels, including kerb and channel, when the maximum depth of ponded water in the channel exceeds 20mm and/or water is diverted to run across the sealed road surface.

20.5.2.3. Unlined Drainage Channels Detritus is to be removed from unlined drainage channels when the detritus material obstructs more than 10% of the cross-sectional area of the waterway.

Maintenance Specification

20 Detritus and Slip Removal

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 102

20.5.2.4. Sump Grates

Detritus is to be removed when it covers more than 10% of the top of a sump grate.

20.5.2.5. Bridges - Deck Joints and Drainage Ports

Detritus is to be removed from bridge deck joints when more than 20% of the length of the joint is full of detritus, and drainage ports are to be cleaned when more than 20% of the surface area of any port or drain outlet is blocked.

20.5.3 Intersections

Intersections with local roads shall be maintained in accordance with clause 1.2.2.

20.5.4 Slip Removal

When undertaking slip removal, all slip material shall be completely removed from the site of the works and disposed of at an approved disposal site in accordance with Section 3 Stockpile and Disposal Areas.

20.6 Performance Criteria

The performance of the Contractor during the Contract period will be measured by the following criteria:

a) inspections are completed within the specified frequencies

b) inspections are completed on time and inspection records are available when requested by the Engineer

c) that all detritus is removed in accordance with this Specification within the response times stated.

d) that all slips greater than 1m3 are removed in accordance with this Specification by the date shown on the agreed programme, and within the response times stated.

e) that the road carriageway shall meet the detritus removal intervention levels required

f) that all drainage channels shall meet the detritus removal intervention levels required

g) there is a maximum of 0.2 kg of detritus (e.g. sealing chip) per square metre of sealed surface

h) there is no section of lined drainage channel with ponding greater than 20mm depth.

i) there are no unlined channels with more than 10% of the cross-sectional area obstructed

j) there is no detritus covering more than 10% of the top of a sump grate.

Maintenance Specification

21 Drainage Systems

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 103

21. Drainage Systems

21.1 Scope

This Section sets out the requirements for maintaining drainage systems. The work required includes the maintenance of all drainage facilities except for the following: a) sump cleaning within urban areas b) the maintenance of culverts, sumps and associated leads, catchpits etc within Urban Areas c) side drain maintenance. d) culverts with a waterway area greater than 3.4 m2.

21.2 Definitions

Terms defined in Table 3.2, Definitions appear in bold. 21.3 Cyclic Inspections

The Contractor must develop and implement an inspection and cleaning programme that: a) minimises the likelihood of faults forming b) ensures all stormwater structures are inspected and, if required, cleaned at least once every

six months.

21.3.1 Inspection Reports The Contractor must submit the Drainage System Inspection Report within 2 months of the Date of possession of site and after that at 6 monthly intervals.

21.4 Response Times

21.4.1 Stormwater Structure Fault Repair

In the event of complete blockage of drainage facilities, Table 21.1 states the response times for clearing stormwater structure blockages. These response times apply from the time of notification of the blockage.

Table 21.1: Stormwater Structures

Class Response Time M and U 3 Days

R1 3 Days R2 3 Days R3 6 Days R4 6 Days

Maintenance Specification

21 Drainage Systems

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 104

For the remaining faults and deficiencies identified during the 6 monthly inspections, the Contractor shall prepare a programmne of work for the Engineer’s approval. The same constraints apply to this programme as is detailed in Section 4.

21.4.2 Other Drainage Systems Other drainage systems included in Appendix 21.1, the Operational Requirements or as agreed with the Engineer, for example cleaning side drains, must be completed within the time frame and to the standard agreed with the Engineer.

21.5 Specific Requirements

21.5.1 Routine Drainage Maintenance Routine drainage system maintenance includes regular inspections, defect reporting, blockage and fault clearing and maintaining, notification of damaged and missing culvert markers and culvert numbers and subsoil drain markers to the Engineer. This work includes identification and maintenance of all drainage features, including fault reporting and drainage features that form part of the drainage system but are not included in the drainage system inventory.

21.5.1.1. Exclusions to Routine Drainage Maintenance The work does not include: a) damage repairs b) emergency works.

21.5.1.2. Other Drainage Systems Appendix 21.1 details the locations of other drainage systems requiring routine drainage maintenance. The Operational Requirements may include details of the extent of this maintenance.

21.5.2 Faults For sumps, and catchpits and like features, a fault exists if the detritus is within 200mm of the outlet pipe invert. For manholes and like features, a fault exists if more than 10% of the outlet pipe entry area is covered with detritus. For culverts, including culverts under accessways, a fault exists when more than 10% of the depth of the culvert inlet, outlet, or barrel along its entire length, is filled with detritus. For side drains, if included in the contract, a fault exists if water ponds and/or water does not readily flow to the outlet points.

Maintenance Specification

21 Drainage Systems

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 105

21.5.3 Fault and Inspection Reporting The Contractor must review, update and submit the Drainage System Inspection Report within the response times stated in Clause 21.3.1. This work includes identifying and reporting drainage features that form part of the drainage system but are not included in the current drainage system inventory. The current report will be provided to the Contractor at the initial meeting. The report must be submitted in both electronic and hard copy format agreed with the Engineer.

21.6 Cleaning

Stormwater structures excluding culverts are deemed to be clean when 90% of the waterway area is clear of detritus throughout the length of the structure, and this standard shall be maintained wherever practicable throughout the Contract. Culverts including accessway culverts are deemed to be clean when less than 10% of the depth of the culvert inlet, outlet or barrel, along it's entire length, is filled with detritus. Stormwater structures shall be cleaned, where possible, in conjunction with each inspection. Detritus shall be removed from stormwater structures so that the normal water flow is maintained. All wood debris jammed within structures must be removed. Care shall be taken so that stormwater structures or their linings are not damaged during cleaning operations. Damage arising from the Contractor's methods of work shall be remedied at the Contractor's expense. The channel area within five metres of culvert inlets and outlets shall be cleaned. Culvert inlet and outlet structures, such as headwalls, and the areas immediately adjacent to these, shall also be cleaned. The inverts of sumps and manholes, their gratings, covers, seatings and outlet pipes (first 150mm) shall be cleaned. Care shall be taken during cleaning not to push any detritus into outlet pipes.

21.6.1 Detritus Removal from Site When undertaking cleaning and maintenance of drainage features, all detritus shall be completely removed from the site of the works and disposed of at an approved disposal site, in accordance with Section 3 Stockpile and Disposal Areas.

Maintenance Specification

21 Drainage Systems

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 106

21.7 Performance Criteria

The performance of the Contractor during the contract period will be measured by the following criteria: a) That all blockages are cleared within the response times in Table 21.1 b) inspections are completed on time and inspection records are available when requested by the

Engineer c) inspections are completed within the specified frequencies d) that all repair of faults are carried out in accordance with this Specification by the date shown

on the agreed programme, within the response times stated and that all stormwater structures remain clean.

e) that no damage to existing stormwater structures or adjacent roading features is caused by

the Contractor's operation. Damage arising from the Contractor's methods of work shall be remedied at the Contractor's expense.

f) that drainage inspections are carried out to the frequency required, and accurate inspection

reports are submitted to the Engineer within the specified timeframes.

Maintenance Specification

22 Unsealed Pavements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 107

22. Unsealed Pavements

22.1 Scope

This Section sets out the requirements for the maintenance of unsealed pavements including running course, shoulders, feathered edges and surface water channels. It also includes supply, cartage and laying of maintenance aggregate for unsealed roads including preparation of the surface prior to laying.

22.2 Definitions

Terms defined in Table 3.2 Definitions appear in bold. 22.3 Response Times

The Contractor must complete all unsealed pavement maintenance work as outlined in the following clauses.

22.3.1 Potholes

Potholes shall be repaired within the response time when the depth exceeds 75mm or the area exceeds 0.07m2 and/or unless otherwise specified. Table 22.1 states the response times for repairing all potholes. The response times apply from the time of notification. The Contractor shall inspect all roads within the Contract area at least at the frequency listed in Table 22.2 and shall repair potholes within the response times.

Table 22.1: Pothole Repairs

Response Time Class

May – September October – April

M and U N/A N/A

R1 N/A N/A

R2 1 Week 2 Weeks

R3 2 Weeks 4 Weeks

R4 4 Weeks 4 Weeks

Table 22.2: Inspection Frequency

Class Inspection Frequency

M N/A

U and R1 N/A

R2 Weekly

R3 Weekly

R4 Weekly

Maintenance Specification

22 Unsealed Pavements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 108

22.3.2 Surface and Shape Restoration

The Contractor must complete all surface and shape restoration work so the network complies with the Surface Condition section (see below) at all times.

22.3.3 Pavement Repairs

The Contractor shall inspect the network and supply a work programme to the Engineer within 2 weeks of acceptance of the contract. The Contractor shall submit monthly to the Engineer the proposed programme of maintenance activities for the following month including the location of all repairs required, indicating priority work, and shall submit the schedule together with the proposed method of repair for agreement by the Engineer. The Contractor shall then complete all work by the agreed completion date.

22.3.4 Maintenance Aggregate

The Contractor must complete the placement of all maintenance aggregate by the date shown on the agreed Programme. Placing of maintenance aggregate shall be carried out as soon as possible following preparation of the road surface but no later than 24 hours following preparation. The Contractor shall notify the Engineer at least 48 hours in advance of the intent to commence carting and placing maintenance aggregate. The loose surface layer of the maintenance aggregate placed shall not exceed 20 mm after a period of 48 hours.

22.4 Specific Requirements 22.4.1 Weather Conditions

Suitable weather conditions shall prevail during surface and shape restoration work and during cartage and placing of maintenance aggregate. Under no circumstances shall work be carried out during heavy rain, dry windy conditions, or snow.

22.4.2 Pavement Repairs

Materials used in the repair of potholes for unsealed roads shall have similar characteristics and properties to the surrounding pavement and sufficient fine material to ensure that the repair remains in place. The finished surface of the repair shall be constructed in accordance with Corrugation and Rutting Repair section (see below).

Maintenance Specification

22 Unsealed Pavements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 109

22.4.3 Surface and Shape Restoration

The Contractor shall maintain the running course, feather edges, tapers and surface water channels and shall ensure that the maintenance aggregate is maintained in a smooth and compacted condition and that the surface water channels are maintained to meet the criteria listed in the Drainage section (see below), to prevent ponding of water, and to maintain the pavement condition by the date shown on the agreed Programme.

22.4.4 Widths and Crossfalls

The existing widths and crossfalls of the running course, feather edges, tapers and surface water channels shall be maintained.

22.4.5 Surface Condition

a) Corrugations Corrugations shall not be permitted to exceed a maximum of 25 mm from crest to trough.

b) Rutting

Shallow surface ruts up to 50 mm deep, shall be removed and the surface restored to the general crossfall of the road.

c) Loose Surface

Depth of loose maintenance gravel on the running course shall not exceed 30 mm loose depth.

d) Transition from Unsealed to Sealed Carriageway Where the unsealed carriageway changes to a sealed carriageway, a smooth transition shall be maintained between the two surfaces over a 20 m section within the unsealed carriageway. The sealed carriageway shall be kept free of all maintenance aggregate during surface and shape restoration.

22.4.6 Maintenance Operation

During any maintenance of the running course the following requirements shall be adhered to: a) The length of road where the running course is being disturbed by grading or other means,

and which produces a windrow of loose material, shall not exceed 1.0 km. b) The height of the windrow of loose material shall not exceed that which will allow an average

vehicle to negotiate and cross over without bottoming.

22.4.7 Corrugation and Rutting Repair

Materials used in the repair of corrugations and rutting for unsealed roads shall have similar characteristics and properties to the surrounding pavement and sufficient fine material to ensure that the repair remains in place. The finished surface of the repair shall be constructed in accordance with the Surface Condition section (see above).

Maintenance Specification

22 Unsealed Pavements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 110

22.4.8 Ponding of Water

The running course, shoulders, featheredges and surface water channels shall be maintained so that no water ponds.

22.4.9 Pavement Repairs

Repairs shall be dense and stable and not move under the action of traffic.

The finished surface of the repair shall be constructed to the same crossfall and gradient as the adjacent pavement. The finished surface shall be such that it does not allow water to pond and there shall be no discernable difference in surface level at the joint between the existing pavement and the completed repair. The Contractor shall carry out pavement repairs in accordance with the contract documents and the adjusted schedule, and be responsible for subsequent maintenance of the repairs during the contract period.

22.4.10 Repair Design

The Contractor must design all digout repairs so a service life similar to that provided by the surrounding pavement can be expected.

The Contractor must:

a) inspect

b) investigate, including laboratory and field testing

c) if appropriate, determine the type and quantity of stabilisation agent

d) mark on the pavement surface the location and extent of all proposed digout repairs.

If the replacement of in situ material is the preferred repair method, the Contractor shall demonstrate that other lower priced methods are inappropriate.

22.4.11 Repair Construction

All repairs must be constructed according to this Section except the top 50mm of the repair must be maintenance aggregate complying with the Materials section (see below). The scope of this section and schedule of rates recognises the following methods:

a) excavation of failed area, backfilling with compaction, and the use of geotextile fabric and/or

installation of drainage if required. b) In-Situ Stabilisation using either cement or lime or a combination of them and replacement of

maintenance aggregate to the existing minimum depth at time of repair.

Maintenance Specification

22 Unsealed Pavements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 111

Alternative methods of repair shall be detailed by the Contractor at time of tender including a suitable schedule item for payment.

22.4.12 Variation to Proposed Method

The Contractor shall immediately advise the Engineer of any variation required to the proposed method of undertaking the digout if such variations become apparent after excavation has commenced. Once the digout is commenced the Contractor shall proceed promptly with the repair. Should any additional work be required due to delay in completion of the digout after commencement, the cost of additional work shall be borne by the Contractor.

22.4.13 Excavation and Drainage

All failed, weak or saturated areas in the existing pavement scheduled on the repair schedule shall be excavated to the dimensions agreed in the programme.

The digout and any drainage trenches shall be excavated with side slopes suitably battered inwards. The base of the excavation shall slope towards the berm at between 4.5% and 6% to match the crossfall of the existing pavement. The base of the excavation shall be thoroughly compacted and contain no hollows which could pond water. Any improvement to drainage proposed within the water tables shall be agreed with the Engineer.

22.4.14 Backfilling

The backfilling shall comprise thoroughly compacted basecourse overlaid with a compacted depth of maintenance gravel to the existing minimum depth at time of repair. All basecourse and maintenance aggregate shall conform to the Materials section (see below).

22.4.15 Compaction

Compaction of the backfilled material shall produce a digout repair that is uniformly dense and stable and will not move under the action of traffic.

22.4.16 Finished Surface

The finished surface of the repair shall be constructed in accordance with the Surface and Shape Restoration and Surface Condition section (see above).

22.4.17 In-Situ Stabilisation Repairs

A stabilisation repair requires the stabilising of in situ material.

Maintenance Specification

22 Unsealed Pavements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 112

When the Contractor wishes to carry out in-situ stabilisation, full details of the method proposed shall be submitted to the Engineer.

22.4.18 Maintenance Aggregate 22.4.18.1. Preparation of Carriageway prior to Placement of Maintenance Aggregate

Sections of State Highway scheduled to have maintenance aggregate placed shall be prepared by removing all corrugations, rutting and potholes and by restoring the road widths and crossfalls, all in accordance with this specification. Preparation shall include the running course, featheredges, tapers and surface water channels. Prior to placing of maintenance aggregate, loose depth of existing maintenance aggregate on the surface shall not exceed 20 mm. Compaction may be required to achieve this. Placing of maintenance aggregate shall be carried out as soon as possible following preparation of the road surface but no later than 24 hours following preparation. The Contractor shall notify the Engineer at least 48 hours in advance of the intent to commence carting and placing maintenance aggregate.

22.4.18.2. Carting and Placing

Maintenance aggregate shall be placed to the required depth, true to grade and crossfall of the existing pavement without segregating. The placed maintenance aggregate shall be compacted throughout the layer with equipment appropriate to the depths placed. The finished surface shall be dense and trafficable. The finished surface shall retain its shape and grade. The loose surface layer of the maintenance aggregate placed shall not exceed 20 mm after a period of 48 hours.

22.4.19 Removal and Reinstatement of Existing Edge Marker Posts

Where edge marker posts require temporary removal in order to facilitate work, edge marker posts shall be reinstated prior to the end of each day and before temporary traffic control signs are removed. Edge marker posts shall be replaced in accordance with TNZ P/16 and materials shall comply with TNZ M/14. Any marker posts damaged by the Contractor’s operations shall be replaced with a new marker posts at the Contractor’s expense.

Maintenance Specification

22 Unsealed Pavements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 113

22.4.20 Drainage 22.4.20.1. General

The Contractor must pay specific attention to any drainage works that may be necessary to ensure the service life is provided.

Maintenance Specification

22 Unsealed Pavements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 114

22.4.20.2. Surface Water Channels

If required, existing surface water channels must be either regraded and trimmed or new surface water channels constructed. The side slope and batter slopes forming the surface water channel must be according to SOMAC Definitions diagram 3.1.

The surface water channels must be graded and shaped so the tie-in with the existing drainage facilities is smooth and continuous so water does not pond.

22.4.21 Materials 22.4.21.1. Maintenance Aggregate

All maintenance aggregate must comply with:

a) the grading for Type 1 or Type 2 Maintenance Aggregate specified in Table 22.3 and the requirements of this clause, or

b) the grading specified in the Operational Requirements.

Table 22.3: Maintenance Aggregate

Aggregate Grading % Passing Sieve Size (mm)

Type 1 Type 2

37.5 - 100

19 100 70 -80

9.5 45 – 75 50 – 60

4.75 25 – 55 35 – 50

2.36 15 – 35 25 – 40

1.18 2 – 35 20 – 35

0.75 8 Max 8 Max

To reduce the loss of fines from the Type 1 aggregate, the Type 1 aggregate must, with the Engineer's approval, be blended with a cohesive clay fraction, up to 15% by volume. The actual quantity of clay blended with the aggregate must be varied so the desired result is achieved.

The clay fraction must:

a) be free of all organic, vegetable or other deleterious material

b) pass the 4.75mm sieve

c) be blended so the blended aggregate has a uniform texture with no segregation of fine and coarse material.

The blended aggregate must have a:

i) plasticity index of less than or equal to 6. The testing frequency shall be 1 test per 2,000m2 of maintenance aggregate constructed

Maintenance Specification

22 Unsealed Pavements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 115

ii) laboratory 4 day soaked CBR of greater than 60, unsurcharged. The testing frequency shall be 1 test per 5,000m2 of maintenance aggregate constructed.

22.4.21.2. Repair Aggregate

Materials used in the repair of potholes for unsealed roads shall have similar characteristics and properties to the surrounding pavement and sufficient fine material to ensure that the repair remains in place.

22.5 Performance Criteria

The performance of the Contractor during the Contract Period will be measured by the following criteria:

a) that all activities are carried out within the timeframes in the agreed monthly programme of

maintenance activities.

b) the Contractor's demonstrated ability to identify and schedule repair work in a competent manner.

c) that all potholes are repaired in accordance with this specification within the response times stated.

d) that the material used to repair potholes remains in place for the duration of the Contract

e) that all digouts placement of maintenance aggregate and drainage treatments are repaired in accordance with this specification within the response times stated.

f) that repaired digouts maintain a smooth riding surface for the duration of the contract of no lesser quality than the balance of the road.

g) that the loose depth of maintenance aggregate does not exceed 20 mm, 48 hours following placing of aggregate

h) that roadside furniture damaged by the Contractor is either replaced or repaired promptly.

i) that no reasonable complaints are received by the Engineer on the Contractors operation or condition of the road during and after grading

j) that separate contractors shall at all times co-ordinate and co-operate with each other to ensure standards are meet.

k) that there are no corrugations exceeding a maximum of 25 mm from crest to trough.

l) that there are no shallow surface ruts deeper than 50 mm deep, and that in repairing rutting the surface is restored to the general crossfall of the road.

m) that the depth of loose maintenance gravel on the running course does not exceed 30 mm loose depth.

Maintenance Specification

22 Unsealed Pavements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 116

n) that where the unsealed carriageway changes to a sealed carriageway, a smooth transition is maintained between the two surfaces over a 20 m section within the unsealed carriageway. The sealed carriageway shall be kept free of all maintenance aggregate during surface and shape restoration.

Maintenance Specification

23 Drainage Improvements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 117

23. Drainage Improvements

23.1 Scope

This section sets out the requirement for improving the existing drainage facilities. 23.2 Definitions

Terms defined in Table 3.2, Definitions appear in bold.

23.3 Response Times The Contractor must complete all work required by this Section by the dates shown on the agreed programme.

23.4 Specific Requirements

23.4.1 Extent of Work

The extent of work is as follows: i) shaping of side slopes

ii) cleaning and/or regarding of surface water channels and side drains

iii) disposal of surplus material

iv) provision of traffic control, and quality control testing required to facilitate the work

v) temporary removal and permanent replacement of existing edge marker posts, culvert marker posts, and permanent signs, that are affected by the work

vi) grassing of side slopes.

The intention of the works contained within this contract is to ensure that runoff water from the highway can be readily conveyed through the drainage network, to avoid excessive penetration into the road shoulder. As such the Contractor shall ensure that the required crossfalls and drainage paths are suitably constructed.

The work is not to extend beyond a point 0.5m from existing fence lines, except for ‘drainage cut out’ work. Excavation into banks or batter slopes above 1.5m in height is not required.

23.4.2 Monthly Programming

Further to Section 4 of the maintenance specification, the Contractor shall identify and programme the following: i) side slope shaping sites (cut 1:6)

ii) surface water channels that require cleaning and/or regrading

iii) side drains that require cleaning and/or regrading

iv) subsoil drains that require flushing

Maintenance Specification

23 Drainage Improvements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 118

Unless the drainage deficiency is a safety issue or hazardous to motorists, all drainage work covered by this section of the contract may be programmed with a priority 3 or 4 to allow the Contractor better efficiencies in completing the work. The programme shall be agreed with the Engineer prior to any work commencing on site.

The Contractor shall also identify drainage system deficiencies that arise beyond the boundary of the road reserve. These sites shall be identified as part of the monthly programme and shall include the following:

i) location (i.e. RS, RP, and side of road)

ii) nature of the defect (e.g. blockage)

iii) remedy required (e.g. clean and regrade drain for 20m) 23.4.3 Disposal of Material

No spreading of material within the State Highway road reserve is permitted. All trimmed or excavated material shall be removed from site.

23.4.4 Plant

No tracked construction plant shall be used in the contract works. Construction plant and methodology shall be chosen to enable the following requirements to be met.

i) disruption to traffic flow shall be the minimum possible

ii) surplus material is to be removed within the area of excavation and shall not be dragged or placed onto the seal.

In wet or unstable ground (e.g.. in situ gravel), once the required edge shape has been achieved, construction plant shall not disturb the finished surface.

23.4.5 Cleaning of Sealed Surfaces

Any detritus spilled onto the road as a result of the Contractor’s operations shall be totally removed from the sealed surface as part of the Contractor’s daily operation and before work ceases on site for the day. In wet weather and in circumstances beyond the control of the Contractor which prevent complete removal of all detritus before work ceases on site for the day, the Contractor shall, with the agreement of the Engineer, employ a temporary holding strategy. The temporary holding strategy shall ensure traffic is not exposed to detritus or a greasy sealed carriageway surface during periods of inclement weather, and ensure that the surface remains in a safe and trafficable condition throughout the period of the cleaning operation. If the sealed carriageway surface becomes unsafe, which in this context includes consideration of skid resistance, texture, roughness and detritus, the Contractor shall immediately remove all detritus from the road surface. The

Maintenance Specification

23 Drainage Improvements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 119

Contractor shall ensure that the temporary holding strategy used is not detrimental to the sealed carriageway surface.

23.4.6 Side Slope Shaping (Cut1:6’s)

23.4.6.1. Quality Control Testing The Contractor will be expected to carry out (and may be required to provide to the Engineer records of these) measurements at 20m intervals which confirm that the dimensions and side slope gradient comply with the contract requirements, including:

i) width between edgeline and cut away point

ii) width between cut away point and the outer extremity of the side slope

iii) gradient of the shaped side slope

iv) confirmation that the check with a two metre long straight edge reveals no gaps greater than 25mm on each shaped batter.

23.4.6.2. Location of Sites and Setting Out

The lateral dimension of the cut away point shall commence at a nominal distance of 100mm from the edge of seal. This will be true for all 1:6 sites completed under this contract unless specifically stated otherwise.

23.4.6.3. General Cross Section

The objective is to shape the verges to provide a nominal 1:6 side slope over a minimum of 2.5 metres from the outside edge of the 100mm unsealed shoulder to the invert of the surface water channel. At locations where the shaping of the side slopes creates a high verge beyond the surface water channel, the cut batter sloping away from the channel shall be constructed with a backslope of 1 to 2. However, where there is a side drain or ground shape that is lower than the new surface water channel and within 2 metres of it, then the verge shall be further excavated, shaped and trimmed to provide a crossfall beyond the surface water channel of 1 :12 to shed the runoff into the lower side drain or onto the lower ground. The tolerance for the side slope shall be no steeper than 1:5.75 and no flatter than 1:6.25. However, the Contractor shall undertake additional excavation as necessary to ensure that a positive crossfall of at least 1:12 exists between the edge of seal and the cutaway point at any particular cross section.

23.4.6.4. Special Cross Section At locations where vehicles frequently pull onto or off the carriageway, such as at side roads, entranceways, scenic spots and rest areas which do not have specifically formed or defined access

Maintenance Specification

23 Drainage Improvements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 120

points, the side slopes shall be no steeper than 1:7 and no flatter than 1:9 extending over a minimum width of 3.0 metres at this slope. If there is any uncertainty about the shaping of side slopes at entranceways, the Engineer is to be consulted before construction takes place. Opposite private entranceways where sealed carriageway width is less than 6.2 metres and existing shoulder is within the slope parameters referred to in the paragraph above, then a 10m length of shoulder on the approach side of the entranceway shall be retained. At locations where the side slopes are intercepted by side roads the slope shall be transitioned to the side road over a distance of 30m and at property entranceways over a distance of 5 metres as shown in Appendix 1.4.

23.4.6.5. General Requirements All work shall be carried out to provide adequate disposal of water from the newly formed drainage channels. Ponding of water will not be acceptable. Wherever practicable watertables shall have cut outs at not more than 50 metre intervals and at low points so that water drains away from the pavement. The cut outs shall be sites to avoid risk of damage to roadside structures from washout. Care shall be exercised to avoid damage to the seal edge. The Contractor shall have available on site at all times suitable equipment for ensuring the correct side slopes are achieved and side drains are graded adequately. The shaped and trimmed surfaces shall be even and consistent. For inspection purposes, the surface shall be unacceptable if gaps in excess of 25mm and evident beneath a 2 metre long straight edge placed anywhere on the batter. The finished surface shall be dense and consolidated, and free of large clods of earth or vegetation and large stones which could damage the mowers. Final trimming may not be required provided the surface is not undercut and is left tight and compacted. If the surface is undercut in error beyond the design limits, then the shortfall is to be remade with TNZ M/4 basecourse and shaped and compacted by rolling at the Contractor’s expense.

23.4.6.6. Grass Seeding All areas of the shaped side slopes and verges shall be grassed by spreading seed on the finished surfaces. The seed mix shall be spread at a rate of 12.0g/m2. The seed mix ratio shall be: one third Brown Top (Agrostis Capillaris)

one third White Clover (Trifolium repens)

one third Sheep’s Burnet (Sanguisorba minor spp Muricata)

Maintenance Specification

23 Drainage Improvements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

MS 121

23.4.6.7. Replace Culvert Marker

The Contractor shall replace damaged or missing culvert and subsoil marker posts as approved by the Engineer. The marker posts shall be installed on the left hand side of the highway and shall be clearly visible from the highway. Where practical culvert marker posts shall be between 2m and 6m from the edge of seal and perpendicular to where the culvert inlet or outlet or flushing eye is situated. Culvert marker posts shall have the culvert number printed on the top of the marker post in black and subsoil marker posts shall have the letters SS are to be printed in the top of the marker post. The marker shall be a plastic flexi post and the colour of the marker shall be olive green.

23.5 Performance Criteria The performance of the Contractor during the Contract Period will be measured by the following criteria: a) that all activities are carried out within the timeframes in the agreed monthly programme of

maintenance activities.

Appendices

Appendices

Contents

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

1. Contract Works 1

1.1 Location of Network 1 1.2 Performance Evaluation of Contractor (PACE) 2 1.3 Visual Assessment Scorecard 3 1.4 Typical Cross Section for Drainage Maintenance 4 1.5 Curve Radius Assessment 5 1.6 Additional Widening Graph 6

2. Contractor’s Quality Plan 7

2.1 Health and Safety Compliance Notice 7 2.2 Schedule of Testing 9 2.3 Construction Tolerances 11

3. General Requirements 12

3.1 Network Information 12 3.2 C Series Specifications 13 3.3 Standard Specifications 14 3.4 Other Publications 15 3.5 Stockpile and Disposal Areas 16 3.6 Land Entry Agreements 17

4. Contractor's Programmes 18

4.1 Electronic Format 18 4.2 Item Numbers and Budgets 19

5. Contractor's Reports 20

5.1 Electronic Format 20 5.2 Monthly Management Report 21

6. Traffic Management 22

6.1 Schedule for Traffic Management & Safety 22

7. Environmental Management 24

7.1 Resource Consents 24

8 Unscheduled Works 25

8.1 Daily Job Record 25

10. Winter Maintenance 26

10.1 Areas of Potential Frost or Snow 26 10.2 Snow Clearance Plant 27 10.3 Ice Gritting and CMA Application Records 28

17. Barrier Repairs 31

17.1 Barrier Stockholding 31

20 Detritus and Slip Removal 32

20.1 Detritus Removal 32

Appendices

Contents

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

21. Drainage System 33

21.1 Specific Maintenance 33

Appendices

1 1.1 Location of Network

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 1

1. Contract Works 1.1 Location of Network

Appendices

1 1.2 Performance Evaluation of Contractor (PACE)

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 2

1.2 Performance Evaluation of Contractor (PACE)

Contract Title: Highway Maintenance Example

Contract Number: NZTA1234 Appraisal Date:

Contract Value: Region Office:

Contractor: Appraisal By:

Contractors Manager:

Work Activity: Work Activity either: Bridge Maintenance, Highway Lighting, Highway Operations and Maintenance, Minor Works, Pavement Marking, Resurfacing, Traffic Services, Vegetation Control

Evaluation Status: Evaluation status either: interim, final or contract extension

Criteria Grade

Weakness Strength Management (20%) Skill level and competency N/A 0 1 2 3 4 5 Risk Management N/A 0 1 2 3 4 5 Responsiveness N/A 0 1 2 3 4 5 Quality Assurance N/A 0 1 2 3 4 5

Production (45%) Contractors Programmes N/A 0 1 2 3 4 5 Ability to meet Programme N/A 0 1 2 3 4 5 Achieves the specified standard N/A 0 2 4 6 8 10 Defect Management System N/A 0 2 4 6 8 10 Achievement N/A 0 2 4 6 8 10 Network Condition N/A 0 1 2 3 4 5

Health and Safety (20%) Safe Work Practices N/A 0 2 4 6 8 10 Traffic management Control N/A 0 2 4 6 8 10

Administration (15%) Financial N/A 0 1 2 3 4 5 Handling of Variations N/A 0 1 2 3 4 5 Reporting N/A 0 1 2 3 4 5 0 20 40 60 80 100

Overall % Ratings Brief Comment: Overall Rating %

(please tick one) Unacceptable Performance <36%

Below Average 36-47%

Average 48-57%

Above Average 58-72%

Good 73-87%

Excellent 88-100%

Signatures:

(NZTA Representative) (Suppliers Representative)

Appendices

1 1.3 Visual Assessment Scorecard

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 3

1.3 Visual Assessment Scorecard

Monthly Visual Assessment Scorecard Consultant Month / Year

Contractor

Visual Comfort Safety

Component Feature Network

% Score Result Feature

Network %

Score Result Feature Network

% Score Result

Rest Area Access Condition 100 Definition 100

Detritus - general 100 Bridges

Deck Joints 100

Barrier Systems Guardrail 100 Guardrail 100

Lined Channels Detritus 100 Blocked Channels 100

Intersections Detritus 100 Crash (2) 100

Water Tables Condition 100

Pavement Surface Condition 100 Ride 100 Texture 100

Shoulders Condition 100 Edge rutting 100

Condition 100 Contractors Pavement Remarking (Maintenance Work) Quality 100

Night/wet (1) 100

Unsealed Pavement SH38 Condition 100 Ride 100 Rideability 100

Loose Chip 100 Loose Chip (2) (3) 100 Resurfacing

Scabbing 100 Scabbing (2) (3) 100

Ride 100 Repairs Outstanding 100 Pavement Condition 100

Potholes Unrepaired 100

Subtotal

Weighting 50 20 30

TOTAL VISUAL SCORE

1 = Poor 2 = Needs Attention 3 = Average 4 = Good 5 = Excellent (1) Sourced from daytime or nighttime survey

(2) Sourced from CAS and Unreported Crash summary deficiencies

(3) Only assessed during Resurfacing Construction season. Otherwise default score 3

Appendices

1 1.4 Typical Cross Section for Drainage Maintenance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 4

1.4 Typical Cross Section for Drainage Maintenance

Appendices

1 1.5 Curve Radius Assessment

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 5

1.5 Curve Radius Assessment

Appendices

1 1.6 Additional Widening Graph

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 6

1.6 Additional Widening Graph

Appendices

2 2.1 Health and Safety Compliance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 7

2. Contractor’s Quality Plan 2.1 Health and Safety Compliance Notice

Health and Safety Compliance Notice 2.1.1. This notice aims to:

foster a responsible attitude towards occupational health and safety on the part of all Contractors (including subcontractors) and their employees (personnel) undertaking work for the Principal (NZTA);

ensure compliance with relevant worksite safety laws especially the Health and Safety

in Employment Act 1992 (as amended from time to time), its regulations and any relevant health and safety codes of practice and guidelines issued by the Department of Labour.

2.1.2 The nature of the work undertaken on behalf of the Principal means that Contractors may

frequently be exposed to hazardous situations which require systems and procedures to eliminate, isolate or minimise the risk of harm to personnel and/or motorists.

2.1.3 All Contractors must observe the provisions of the Health and Safety in Employment Act

1992, its regulations and any relevant codes of practice and guidelines issued by the Department of Labour in accordance with the Act. Contractors must ensure:

a. all practicable steps are taken to provide a safe working environment and facilities for

all personnel (both in terms of the physical work environment and “non-physical” factors such as stress and fatigue);

b. Work procedures do not lead to personnel being exposed to hazards in and around the

place of work; c. procedures are developed for effectively managing emergencies that may arise at the

place of work. This should include both health and safety and environmental contingency plan development;

d. appropriate steps are taken for systematically identifying existing and potential new

hazards and subsequently reassessing those hazards; e. all practicable steps for controlling hazards are taken using the eliminate, isolate and

minimisation hierarchy (including the assessment, control, monitoring and review of existing and any new hazards);

f. adequate information, training, competency and supervision processes are in place to

ensure that personnel are able to work safely – this should include all work process, plant, equipment, and materials and, where appropriate, consideration given to those personnel to whom English is a second language. Training and competency records must be maintained;

g. all workplace accidents and incidents are reported, recorded and investigated to

determine root causes with effective corrective and preventative actions being implemented and monitored;

Appendices

2 2.1 Health and Safety Compliance

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 8

h. all Department of Labour requirements for “serious harm” injuries are reported within

the regulated timeframes – these must also be reported to the Principal’s Contract Representative;

i. the Principal’s Contract Representative is advised of any prohibition, improvement or

infringement notices issued by the Department of Labour. 2.1.4 If it is impracticable to eliminate or isolate significant hazards minimisation controls must

be implemented such as:

protective equipment and clothing safety equipment signage inspections, checks, audits and reviews

2.1.5 Contractors must ensure they comply with the NZTA’s Code of Practice for Temporary

Traffic Management. 2.1.6 Where required by the Principal, the Contractor must develop and submit a Contract

Health & Safety Management Plan, Traffic Management Plan and Environmental Management Plan for the contract / project works.

2.1.7 Further health and safety information is available from:

The Engineer Department of Labour Workplace Health & Safety Division

Appendices

2 2.2 Schedule of Testing

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 9

2.2 Schedule of Testing

Schedule of Testing

Material Testing Suggested Frequency of Testing (per quantity of material constructed)

Size, Shape and Cleanliness 1 test per 500 m3 of sealing chip used.

Crushing

Weathering Resistance

1 test per source per year.

Sealing Chip

Polished Stone Value (PSV) PSV tested and reported as specified in TNZ M/6:2004 Clause 3.5.

Cutback Determination Sampling at a rate of a minimum of 2 samples per bitumen distributor load. The first of the samples shall be taken at the end of the initial spray run and the other immediately before the final spray run, and, testing at a rate of 1 sample test per 2,000m2 of sealing completed. The samples shall be held for six months.

Bitumen

Diluent Dosage Rates Sampling at a rate of a minimum of 2 samples per bitumen distributor load. The first of the samples shall be taken at the end of the initial spray run and the other immediately before the final spray run, and, testing at a rate of 1 sample test per 2,000m2 of sealing completed. The samples shall be held for six months.

Emulsion Bitumen Content As for Bitumen

Asphaltic Concrete Marshall Stability

Binder Content

1 test per 100 tonne of asphaltic concrete constructed.

Grading 1 test per 100 tonne of asphaltic concrete constructed, and 1 test per 500m3 of aggregate used.

Premix Materials Marshall Stability

Binder Content

1 test per 100 tonne of premix concrete constructed.

Grading 1 test per 100 tonne of premix concrete constructed, and 1 test per 500m3 of aggregate used.

Imported Subgrade Californian Bearing Ratio (CBR) (Soaked)

1 test per 1,000m3 constructed

Grading

CBR (Soaked)

0 – 1,000m3 2 tests

1,000 – 3,000m3 3 tests

3,000m3+ 3 tests plus 1 additional test per 2000m3 of subbase constructed.

Sub-base

Construction According to TNZ B/2

Basecourse Grading

SE

% Broken Faces (BF)

0 – 400m3 2 tests

400 – 1,500m3 3 tests

1,500m3- 4,000m³ 4 tests plus 1 additional test per 1,000m3 of basecourse constructed.

Appendices

2 2.2 Schedule of Testing

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 10

Crushing and Weathering Resistance

1 test per source per 2 years unless it is geologically proven site then 4 years

Construction According to TNZ B/2

Californian Bearing Ratio (CBR) (Soaked)

Every 10,000m3

Drainage Aggregate Grading, SE 0 – 500m3 2 tests

500m3+ 2 tests plus 1 test for each additional 500m3 constructed

Stabilisation Reactivity

Design Dosage Rates

1 test per section of the network (with like characteristics) prior to the commencement of any stabilisation works.

For work completed under Section 11, the minimum testing frequency must be according to TNZ P/9 and TNZ P/11 and the following requirements: a) Binder Content and Grading – 1 test for the 50 tonne of mix produced and thereafter 1 test per 100

tonnes batched or part thereof b) Field Permeability- (Porous Asphalt only) – 1 test per 1000m² resurfaced or part thereof c) Surface Texture – 1 test per 1000m² resurfaced or part thereof.

Appendices

2 2.3 Construction Tolerances

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 11

2.3 Construction Tolerances

Pavement Repairs a) Surfacing of Repairs

The surfacing of the completed repairs shall comply with Section 11. b) Surface Shape

The primary requirement is that maintenance activity is carried out without unnecessarily reducing ride comfort or introducing adverse environmental effects of noise and/or vibration.

All pavement repairs shall be constructed so that:

the maximum deviation from a 2m straight edge laid normal to the centreline is less than 10mm the maximum deviation from a 3m straight edge laid parallel to the centreline is less than 10mm there is no ponding of water there is a smooth transition from the adjoining pavement on to and off the completed repair the finished surface, including asphaltic joints, is flush with existing pavement surfaces and utility

covers, so as not to create adverse noise and vibration effects.

Appendices

3 3.1 Network Information

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 12

3. General Requirements 3.1 Network Information

It is the Contractor’s responsibility to ensure the most up to date information is obtained throughout the contract period. The following Network Information will be given to the Contractor at the initial meeting: NZTA's State Highway Traffic Volumes

Appendices

3 3.2 C Series Specifications

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 13

3.2 C Series Specifications

There are no C Series Specifications that apply to this Contract.

Appendices

3 3.3 Standard Specifications

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 14

3.3 Standard Specifications

The following Standard Specifications apply to this Contract: <<<Guidance note: refer to current version on the NZTA website and reference latest version below>>>. TNZ B/2:2005 Construction of Unbound Granular Pavement Layers TNZ F/1:1997 Earthworks Construction TNZ F/2:2000 Pipe Subsoil Drain Construction TNZ F/3:2000 Pipe Culvert Construction TNZ F/5:2000 Corrugated Plastic Pipe Subsoil Drain Construction TNZ F/6:2003 Fabric Wrapped Aggregate Subsoil Drain Construction TNZ M/1:2007 Roading Bitumens TNZ M/4:2006 Basecourse Aggregate TNZ M/6:2004 Sealing Chip TNZ M/7:2006 Roadmarking Paints TNZ M/10:2005 Asphaltic Concrete TNZ M/11:1975 Pre-Coating Sealing Chips TNZ M/12:1998 Raised Pavement Markers TNZ M/13:1989 Adhesion Agents TNZ M/14:2005 Edge Marker Posts TNZ M/15:1986 Lime for use in Soil Stabilisation TNZ M/17P:1989 W-Section Bridge Guardrail TNZ M/20:2003 Long Life Roadmarking Materials TNZ M/23:2006 Road Safety Barrier Systems TNZ P/3:1995 First Coat Sealing TNZ P/4:1995 Resealing TNZ P/9:1975 Construction of Asphaltic Concrete Paving TNZ P/11:2007 Open Graded Porous Asphalt TNZ P/14:1995 Installation of Raised Pavement Markers TNZ P/16:1993 Installation of Edge Marker Posts TNZ P/22:2006 Reflectorised Pavement Marking TNZ P/26:2003 Improvement of Pavement Macrotexture by use of High Pressure Water and

Grooving TNZ Q/1:1995 Chipsealing TNZ Q/2:1995 Hot Mix Asphalt TNZ Q/3:1995 Normal QA Level Contracts TNZ Q/4:1995 High QA Level Contracts TNZ T/3:1981 Measurement of Texture by the Sand Circle Method TNZ T/4:1981 Description of Test Locations on Highways NZTA/NZRF T/8:2006 Roadmarking Paint Applicator Testing TNZ T/10:2002 Skid Resistance Deficiency Investigation and Treatment Selection

Appendices

3 3.4 Other Publications

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 15

3.4 Other Publications

The following publications apply to this Contract: Austroads Pavement Design Manuals BCA E/2 Chipsealing in New Zealand New Zealand Bitumen Contractors' Association (BCA) Safe Handling of Bituminous Materials TNZ / LTSA Manual of Traffic Signs and Markings - Part 1: Traffic Signs (MOTSAM-Part1) TNZ / LTSA Manual of Traffic Signs and Markings - Part 2: Markings (MOTSAM-Part2) TNZ Code of Practice for Temporary Traffic Management (COPTTM) TNZ State Highway Location Referencing Management System (LRMS) Manual, SM051 NZTA State Highway Database Operation Manual, SM050 NZRF Line Removal Guide, Appendix to Section 12 of NZRF Safety, Health and Environment Guide BCA 98-03 Code of Practice: Quality Assurance of Bitumen BCA 98-05 Guidelines: Quality Assurance of Aggregates for Chipseals and Bituminous Mixes Roading New Zealand, 99-04 Code of Practice: The Safe Handling of Bituminous Materials used in

Roading TNZ Environmental Policy Manual SP/M/021 Transit’s Planning Policy Manual Coporate Services Manual, Section 12 Land Transport Rule: Traffic Control Devices 2004

Appendices

3 3.5 Stockpile and Disposal Areas

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 16

3.5 Stockpile and Disposal Areas

Schedule of Stockpile Sites

Location

SH RS RP Side

Name

Schedule of Disposal Areas

Location

SH RS RP Side

Name

Appendices

3 3.6 Land Entry Agreements

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 17

3.6 Land Entry Agreements

Schedule of Land Entry Agreements

Location

SH RS RP Side

Owners Name, Contact Number and Agreement Reference

Appendices

4 4.1 Electronic Format

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 18

4. Contractor's Programmes 4.1 Electronic Format

Contractor’s Programme – Electronic Format Field Name Size Description and Format of Field

The submitted file shall be in DBF format

Appendices

4 4.2 Item Numbers and Budgets

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 19

4.2 Item Numbers and Budgets

The following table states the: Payment Item Number estimated budget. The actual budget will be advised prior to the date of possession of site and update

annually the Scheduled Items that will be coded to each Payment Item Number.

Item Numbers and Budget

Item Number Description Annual Estimated Budget ($)

Schedule Items

1098765 Cyclic Maintenance $300,000.00 10.1 16 18 19 20.1 20.2 21 21 22

1098765 Barrier Repairs $300,000.00 16.2

1098765 Incident Response $30,000.00 0 10.2 10.2.3 20.3

1098765 Management $10,000.00 1 2 3 4 5 6 7

1098765 Minor Bridge Repairs $200,000.00 22

198756441 Miscellaneous Works $50,000.00 8

1098765 Pavement Repairs and Preseal $200,000.00 12 13 14 15

10987566 Surfacing Repairs $20,000.00 11

50658741 Unsealed Roads $10,000.00 22

Appendices

5 5.1 Electronic Format

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 20

5. Contractor's Reports 5.1 Electronic Format

Contractor’s Monthly Claim – Electronic Format

Field Name Size Description and Format of Field

The submitted file shall be in DBF format

Appendices

5 5.2 Monthly Management Report

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 21

5.2 Monthly Management Report

For Month: Contract No.:

Contractor: Completed by: Date:

Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

A. Programme Achievement Total Number of Tasks Programmed Total Number of Tasks Achieved B Contract Specific Achievements Volume of Detritus Removed (m3) Number of EMP’s Replaced Number of RMP’s Replaced Number of Potholes Filled Number of Stormwater Structures Checked Number of Tasks Outstanding (Total) Number of Tasks Not Completed Within Specified Response Times

C Quality Number of Non-Complying Tasks Number of CQP Audits / Reviews Number of Non-Compliances Identified Number of Non-Compliances Outstanding D Financial Refer to Monthly Claim & Financial Report E Safety Number of Workplace Accidents Number of Near Misses Identified Number of TMP Audit Non-Compliances F Network Condition Based on Information Provided by Engineer - Contractor to Comment Notes / Comments: i.e achievements, issues (if any), trends. G. General Comments Activity / Actions Planned for Next Month

Attachments : (List, if any)

Appendices

6 6.1 Schedule for Traffic Management & Safety

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 22

6. Traffic Management 6.1 Schedule for Traffic Management & Safety

Specific Job Requirements for Traffic Management and Safety Contract No: NZTA1234 Contract Name: Highway Maintenance Example (Clause numbers are those from the Specification)

A OPERATIONAL REQUIREMENTS 1. Hours of Work

The Contractor shall programme work such that contract activities affecting traffic flow are not carried out on-site between the hours specified in the Operational Requirements Section. No work other than emergency or maintenance work shall be undertaken on weekends without prior approval of the Engineer.

2. Project Specific Conditions

a) maintain two way traffic at all times on all Class R1 and R2 highways b) advise all affected local authorities of all work programmed within urban areas a minimum of 4

weeks before the programmed date of the resurfacing work. c) not work in urban areas during peak traffic flows.

3. Excessive Traffic Delays

The steps outlined in the Traffic Management Plan to deal with excessive traffic delays shall be implemented once traffic delays exceed: 10 minutes. The Contractor shall be responsible for the monitoring of traffic delay.

4. Road Controlling Authority Approval at Single Lane Operations

Approval of the RCA is required in advance if traffic is restricted to single lane operation. 5. Advice to Other Parties

Public Notification. Waikato times and appropriate local newspapers. Newspapers to advertise in. Required within urban areas. Parties with Access Affected The Contractor must advise all authorities, adjoining businesses and occupants.

6. Condition of Road Surface

Appendices

6 6.1 Schedule for Traffic Management & Safety

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 23

Not Applicable

7. Basis of Payment

Payment shall be in accordance with Basis of Payment, Clause 6. 8. Positive Traffic Management - Specific Requirements

The Contractor must provide positive traffic control according to COPTTM. 9. Pilot Vehicle Exemption

None.

Appendices

7 7.1 Resource Consents

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 24

7. Environmental Management 7.1 Resource Consents

Schedule of Resource Consents

Location

SH From RS From RP To RS To RP Side

Consent Number and Description

Appendices

8 8.1 Daily Job Record

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 25

8 Unscheduled Works 8.1 Daily Job Record

Contract Number: NZTA1234

Contract Name: Maintenance

Daily Job Record (DJR) Location: ______________________________________________________________________

Date: __________________ Start Time: ________________ Finish Time: ________________

Description:

______________________________________________________________________________

______________________________________________________________________________

Item Comments Hours Rate Total

PLANT

Sub Total Plant MATERIALS / SUB-CONTRACTORS

Sub Total Materials / Sub-contractors Materials / Sub-contractors on Cost

LABOUR

Sub Total Labour TOTAL

Appendices

10 10.1 Areas of Potential Frost or Snow

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 26

10. Winter Maintenance 10.1 Areas of Potential Frost or Snow

Schedule of Areas of Potential Frost or Snow

Location

SH From RS From RP To RS To RP Local Name

Hazard Level of Service

Indicative Seasonal Quantities

Appendices

10 10.2 Snow Clearance Plant

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 27

10.2 Snow Clearance Plant

Schedule of Snow Clearance Plant

Location

SH RS RP Local Name

Type of Plant Number

Appendices

10 10.3 Ice Gritting and CMA Application Records

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 28

10.3 Ice Gritting and CMA Application Records

ICE GRITTING RECORD Date: Contract Number: Contract Area: Site Details Inspection 1 Inspection 2 Inspection 3 Inspection 4

From To SH

RS RP RS RP

Description, Grit Application Rate or Quantity.

Tim

e In

spec

ted

(hh:

mm

)

Cle

ar

()

Ice

()

Grit

ted

()

Swep

t (

)

Sign

s O

pen

()

Tim

e In

spec

ted

(hh:

mm

)

Cle

ar (

)

Ice

()

Grit

ted

()

Swep

t (

)

Sign

s O

pen

()

Tim

e In

spec

ted

(hh:

mm

)

Cle

ar (

)

Ice

()

Grit

ted

()

Swep

t (

)

Sign

s O

pen

()

Tim

e In

spec

ted

(hh:

mm

)

Cle

ar (

)

Ice

()

Grit

ted

()

Swep

t (

)

Sign

s O

pen

()

Prepared By:

Fax to:

Attention:

Grit Grading Adopted

C22

Alternative Specification

Other (attach details)

Appendices

10 10.3 Ice Gritting and CMA Application Records

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 29

CMA APPLICATION RECORD (One Form Per Site)

Site Details From To

SH RS RP RS RP

Description Lane Metres (based on

3.4 m wide lanes)

Sampling Site (Y/N)

Date

Measurements, Observations, & Actions

Time 6am Midday 6pm Midnight 6am Midday 6pm Midnight 6am Midday 6pm Midnight 6am Midday 6pm Midnight

Skid

Res

ista

nce

Estimated prior to CMA application and periodically following application. Results in terms of estimated skid co-efficient.

Air Temperature (oC)

Road Temperature (oC)

Clim

atic

C

ondi

tions

Overcast (Ox) 1 = clear, 2 = cloudy, 3 = overcast

Fax to:

Attention:

Contract Number:

Contract Area:

Appendices

10 10.3 Ice Gritting and CMA Application Records

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 30

Rain (Rx) 1 = drizzle, 2 = showers, 3 = torrential rain

Wind (Wx) 1 = no wind, 2 = wind

Snow (Sx) 1 = light, 2 = medium, 3 = heavy

CMA liquid application rate (litres/m2). CMA liquid applied – Total (litres) CMA Granular application rate - /grit mix (grams/m2) C

MA

CMA Granular applied - Total (grams) Grit Grit Applied (lane m)

Com

men

ts

Effectiveness of CMA, observations, etc.

Prepared by: Date:

Appendices

17 17.1 Barrier Stockholding

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 31

17. Barrier Repairs 17.1 Barrier Stockholding

Schedule of Minimum Stockholding Quantities to be Held by the Contractor Item Unit Minimum Quantity

Appendices

20 20.1 Detritus Removal

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 32

20 Detritus and Slip Removal 20.1 Detritus Removal

Schedule of Urban Areas For Detritus

Location

SH From RS From RP To RS To RP Local Name

Notes

Appendices

21 21.1 Schedule of Other Drainage Systems

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 33

21. Drainage System 21.1 Specific Maintenance

Drainage System – Schedule of Other Drainage Systems

Description

SH RS RP Side

Structure Name and Description of Maintenance Work

Appendices

NZTA Somac - 2010 Highway Operations and Maintenance NZTA1234: Highway Maintenance Example

A 34

THE END