Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
PROJECT NO.: TCS/00477/09
CEDD CONTRACT NO. ST/2008/02 ROADS, DRAINAGE AND SEWEAGE WORKS AT
WHITEHEAD AND LOK WO SHA, PHASE 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report No.Q1 (October to December 2009)
PREPARED FOR CHINA ROAD & BRIDGE CORPORATION
Quality Index Date Reference No. Prepared By Certified By
22 July 2010 TCS00477/09/600/R0108v2
Nicola Hon
Environmental Consultant T.W. Tam
Environmental Team Leader
Version Date Description 1 20 May 2010 First Submission 2 22 July 2010 Amended against IEC’s comments on 21 July 2010
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Executive Action-United Environmental Services and Consulting
EXECUTIVE SUMMARY ES.01 The China Road & Bridge Corporation (CRBC) has been awarded the Contract ST/2008/02
Ma On Shan Development – Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1 (the Project) by the Civil Engineering & Development Department (CEDD) on 18 June 2009. Total project time is expected to be 23 months. Action-United Environmental Services and Consulting (AUES) have been commissioned by CRBC as the ET to implement the relevant EM&A program.
ES.02 This is the 1st Quarterly EM&A summary report for the Project covering the construction
period from 20 October to 25 December 2009.
ENVIRONMENTAL MONITORING AND AUDIT ACTIVITIES
ES.03 Environmental monitoring activities under the EM&A program in this Reporting Quarter are summarized in the following table.
Issues Environmental Monitoring Parameters / Inspection Occasions 1-hour TSP 36 Air Quality 24-hour TSP 12
Construction Noise Leq (30min) Daytime 13 Water Quality Marine Water Sampling 33
ET Regular Environmental Site Inspection 3 Inspection / Audit IEC Monthly Environmental Site Audit 3
BREACH OF ACTION AND LIMIT (A/L) LEVELS
ES.04 In this reporting quarter, no exceedance of construction noise monitoring was recorded. However, one Acton Level exceedance in 24-hour TSP monitoring and 18 A/L Level exceedances in marine water quality monitoring were reported. The statistics of environmental exceedance, NOE issued and investigation of exceedance are summarized in the following table.
Event & Action Environmental Issues
Monitoring Parameters
Action Level
Limit Level Investigation Corrective Actions
1-hour TSP 0 0 - - Air Quality 24-hour TSP 1 0 Not works related N/A
Construction Noise Leq30min Daytime 0 0 - - DO 0 0 - -
Turbidity 3 5 Not works related N/A Water Quality SS 9 1 Not works related N/A
ENVIRONMENTAL COMPLAINT
ES.05 No environmental complaint was recorded or received in this Reporting Quarter. The statistics of environmental complaint are summarized in the following table.
Environmental Complaint Statistics Reporting Period Frequency Cumulative Complaint Nature
20 October - 25 December 2009 0 0 NA NOTIFICATION OF SUMMONS AND SUCCESSFUL PROSECUTIONS
ES.06 No environmental summons or successful prosecutions were recorded in this Reporting Quarter. The statistics of environmental complaint are summarized in the following tables.
Environmental Summons Statistics Reporting Period Frequency Cumulative Complaint Nature
20 October - 25 December 2009 0 0 NA
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Executive Action-United Environmental Services and Consulting
Environmental Prosecution Statistics Reporting Period Frequency Cumulative Complaint Nature
20 October - 25 December 2009 0 0 NA REPORTING CHANGE
ES.07 There are no reporting changes in this Reporting Quarter. SITE INSPECTION BY EXTERNAL PARTIES
ES.08 In this Reporting quarter, EPD was visited the site on 24 November 2009 to select the treatment facilities as provided by CRBC for the discharge permit application. Apart from EPD, no other external parties i.e. Agriculture, Fisheries and Conservation Department (AFCD) or Leisure and Cultural Services Department (LCSD) paid a visit during the Reporting Period. FUTURE KEY ISSUES
ES.09 As dry season has approached, construction dust has become a key environmental issue. Construction dust suppression measures should therefore be fully implemented. In addition, the implemented construction dust mitigation measures should also be maintained and improved, as necessary, during dusty works including vehicle movement on dry and windy days.
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Table Content Action-United Environmental Services and Consulting
TABLE OF CONTENTS
1 INTRODUCTION 1 1.1 PROJECT BACKGROUND 1 1.2 REPORT STRUCTURE 1
2 PROJECT ORGANIZATION AND CONSTRUCTION PROGRESS 2 2.1 PROJECT ORGANIZATION AND MANAGEMENT STRUCTURE 2 2.2 CONSTRUCTION PROGRESS 2 2.3 SUMMARY OF ENVIRONMENTAL SUBMISSIONS 3
3 SUMMARY OF MONITORING REQUIREMENTS 4 3.1 MONITORING PARAMETERS 4 3.2 MONITORING LOCATIONS 4 3.3 MONITORING FREQUENCY AND PERIOD 5 3.4 METEOROLOGICAL INFORMATION 6 3.5 ENVIRONMENTAL QUALITY CRITERIA 6
4 IMPACT MONITORING RESULTS 7 4.1 RESULTS OF AIR QUALITY MONITORING 7 4.2 RESULTS OF CONSTRUCTION NOISE MONITORING 7 4.3 RESULTS OF MARINE WATER QUALITY OF MONITORING 7
5 WASTE MANAGEMENT 9 5.1 RECORDS OF WASTE QUANTITIES 9
6 SITE INSPECTION 10
7 ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE 11 7.1 ENVIRONMENTAL COMPLAINT, SUMMONS AND PROSECUTION 11
8 IMPLEMENTATION STATUS OF MITIGATION MEASURES 12
9 CONCLUSIONS AND RECOMMENTATIONS 15 9.1 CONCLUSIONS 15 9.2 RECOMMENDATIONS 15
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Table Content Action-United Environmental Services and Consulting
LIST OF ANNEXES Annex A Project Site Layout Plan Annex B Organization Structure and Contact Details of the CRBC and Relevant Parties Annex C Master and Three Months Rolling Construction Programs Annex D Monitoring Locations Designated in the EM&A Manual Annex E Current Impact Monitoring Stations Annex F Graphical Plots of Impact Monitoring – Air, Noise and Marine Water Annex G Meteorological Data of Reporting Month Annex H Monthly Summary Waste Flow Table LIST OF TABLES Table 2-1 Status of Environmental Licenses and Permits Table 3-1 Summary of EM&A Requirements Table 3-2 Location of Air and Noise Quality Noise Monitoring Station Table 3-3 Location of Marine Water Quality Monitoring Stations Table 3-4 Action and Limit Levels for Air Quality Monitoring Table 3-5 Action and Limit Levels for Construction Noise Monitoring Table 3-6 Action and Limit Levels for Water Quality Monitoring Table 3-7 Action Level for Landscape and Visual Impact in Construction Phase Table 4-1 Summary of 24-hour and 1-hour TSP Monitoring Results Table 4-2 Summary of Construction Noise Monitoring Results Table 4-3 Summary of Water Quality Exceedances Table 5-1 Summary of Quantities of Inert C&D Materials Table 5-2 Summary of Quantities of C&D Wastes Table 6-1 Site Observations Table 7-1 Statistical Summary of Environmental Complaints Table 7-2 Statistical Summary of Environmental Summons Table 7-3 Statistical Summary of Environmental Prosecution Table 8-1 Environmental Mitigation Measures
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
1
1 INTRODUCTION 1.1 PROJECT BACKGROUND
The China Road & Bridge Corporation (CRBC) has been awarded the Contract ST/2008/02 Ma On Shan Development – Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1 (the Project) by the Civil Engineering & Development Department (CEDD) on 18 June 2009. Total project time is expected to be 23 months. The Project includes civil engineering infrastructure works for the construction of District Distributors: Road D1(N) & Road D1(W) and Local Road L3 with the associated footpath, cycle tracks, planting areas, drains, sewers, water-mains and landscaping works. There are also one box culvert, one sewage pumping station with pressurized sewers and two site formation works for G/IC and LWS-B areas at Lok Wo Sha to be constructed under the Project. The site layout plan is shown in Annex A. The Project is part of an overall plan approved under a statutory EIA (Register No. AEIAR-068/2002) for a Feasibility Study for Housing Development at Whitehead & Lee On in Man On Shan commissioned by the then Territory Development Department. An Environmental Permit (No. EP-332/2009) for Road D1(N), Road D1(W) and Box Culvert of Whitehead & Lok Wo Sha Phase One Project (EP) has been obtained by the CEDD on 24 March 2009 for the relevant works. According to the Particular Specification (PS) Section 25 and the Environmental Permit No. EP-332/2009, overall scope of environmental monitoring including air quality, construction noise, water quality, and site environmental audit should be undertaken in accordance with the Final Report Environmental Monitoring and Audit Manual [2095/13.3] by an independent Environmental Team (ET). Also, monitoring and audit works for landscaping and visual will be undertaken as part of the EM&A programme. Action-United Environmental Services and Consulting (AUES) has been commissioned by CRBC as the ET to implement the relevant EM&A program. As part of the EM&A program, baseline monitoring is required to determine the ambient environmental conditions. The baseline monitoring program was carried out during the period between 24 August 2009 and 23 September 2009 at the designated monitoring locations by the ET according to the EM&A Manual. The “Baseline Monitoring Report (R0023 Version 2)” had submitted to EPD by the CEDD before commencement of major construction works and approved by the IEC on 5 October 2009. Further to CRBC’s instructions, the EM&A program was commenced on 20 October 2009 and the monitoring schedule had been issued to relevant parties on 17 October 2009. This is the 1st Quarterly EM&A Summary Report (hereinafter “this Report’), covering the first quarter from 20 October to 25 December 2009 (hereinafter “the Reporting Period’).
1.2 REPORT STRUCTURE
The Monthly Environmental Monitoring and Audit (EM&A) Report is structured into the following sections:- SECTION 1 INTRODUCTION SECTION 2 SUMMARY OF IMPACT ENVIRONMENTAL MONITORING AND AUDIT
REQUIREMENTS SECTION 3 MONITORING RESULTS AND BREACHES OF ENVIRONMENTAL QUALITY
CRITERIA SECTION 4 NON-COMPLIANCE, COMPLAINTS, NOTIFICATIONS OF SUMMONS AND
SUCCESSFUL PROSECUTIONS SECTION 5 CONCLUSION
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
2
2 PROJECT ORGANIZATION AND CONSTRUCTION PROGRESS 2.1 PROJECT ORGANIZATION AND MANAGEMENT STRUCTURE
Organization structure and contact details of relevant parties with respect to on-site environmental management are shown in Annex B.
2.2 CONSTRUCTION PROGRESS
The master and three month rolling construction programs are enclosed in Annex C and the major construction activities undertaken in this quarter are listed below:- 20 September to 25 October 2009
Erection of hoarding; Tree transplanting; Excavation for the box culvert and the retaining wall; Erect of formwork; and Concreting
26 October to 25 November 2009
Location Forthcoming Activities Nuisances Mitigation Measures
Erection of hoarding Noise generated from erection work
Carry out work within 07:00-19:00, except public holiday/Sunday
Tree transplanting Noise generated from transplanting work
Carry out work within 07:00-19:00, except public holiday/Sunday Portion 1
Pipe installation
Noise generated from the works are included excavation, formwork, steel fixing and concreting etc.
Carry out work within 07:00-19:00, except public holiday/Sunday
Box Culvert
General Excavation Erect formwork Fix steel reinforcement bars Concreting
Noise generated from the works are included excavation, formwork, steel fixing and concreting etc.
Carry out work within 07:00-19:00, except public holiday/Sunday
Retaining Wall at D1(N) & D1 (W)
General Excavation Erect formwork Fix steel reinforcement bars Concreting
Noise generated from the works are included excavation, formwork, steel fixing and concreting etc.
Carry out work within 07:00-19:00, except public holiday/Sunday
26 November to 25 December 2009
Location Forthcoming Activities Nuisances Mitigation Measures
Erection of hoarding Noise generated from erection work
Carry out work within 07:00-19:00, except public holiday/Sunday
Tree transplanting Noise generated from transplanting work
Carry out work within 07:00-19:00, except public holiday/Sunday
Portion 1
Pipe installation
Noise generated from the works are included excavation, formwork, steel fixing and concreting etc.
Carry out work within 07:00-19:00, except public holiday/Sunday
Box Culvert
General Excavation Erect formwork Fix steel reinforcement bars Concreting
Noise generated from the works are included excavation, formwork, steel fixing and concreting etc.
Carry out work within 07:00-19:00, except public holiday/Sunday
Retaining Wall at D1(N) & D1 (W)
General Excavation Erect formwork Fix steel reinforcement bars Concreting
Noise generated from the works are included excavation, formwork, steel fixing and concreting etc.
Carry out work within 07:00-19:00, except public holiday/Sunday
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
3
2.3 SUMMARY OF ENVIRONMENTAL SUBMISSIONS
Summary of the relevant permits, licences, and/or notifications on environmental protection for this Project in this Reporting Month is presented in Table 2-1. Table 2-1 Status of Environmental Licenses and Permits
Item Description License/Permit Status 1 Air pollution Control (Construction Dust) Notified EPD on 12 June 09 2 Chemical waste Producer Registration (WPN:
5123-757-C3124-31)
Application date: 16/07/2009 Date approved: 20/8/2009
3 Water Pollution Control Ordinance (Discharge License) Application date: 29/10/2009 Status : In progress
4 Billing Account for Disposal of Construction Waste (Account Number: 700892117)
Application no. :RN/00606 Date approved: 22/6/2009
5 Construction Noise permit (PP-RN0006-09) Application date: 16/11/2009 Approved (CNP no. GW-RN0351-09)
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
4
3 SUMMARY OF MONITORING REQUIREMENTS The Environmental Monitoring and Audit requirements are set out in the project EM&A manual. Air quality, construction noise and water quality have been identified to be the key issues during the construction phase of the Project. Also, monitoring and audit works for landscaping and visual will be undertaken as part of the EM&A programme by others during construction period.
3.1 MONITORING PARAMETERS
The EM&A Impact monitoring program covers the following environmental issues: • Air quality; • Construction noise; • Water quality; and • Landscape and visual resources (to be provided by others separately) A summary of the monitoring parameters is presented in Table 3-1 as below. Table 3-1 Summary of EM&A Requirements Environmental Issue Parameters
Air Quality • 1-hour TSP Monitoring by Real-Time Portable Dust Meter; and • 24-hour TSP Monitoring by High Volume Air Sampler.
Noise • Leq(30min) during normal working hours.; and • Leq(15min) during the construction works is undertaken in Restricted Hours.
In-situ Measurements • Dissolved Oxygen Concentration (mg/L); • Dissolved Oxygen Saturation (% ); • Turbidity (NTU); • pH unit; • Salinity (ppt); • Water depth (m); and • Temperature (ºC).
Marine Water Quality*
Laboratory Analysis • Suspended Solids (mg/L)
Landscape and Visual Resources
• Vegetation survey undertaken on an “area” basis to identify representative types and species composition;
• Assessment of landscape character; and • Tree survey report.
* Notes: Since there will be no workshop, vehicle repair area, canteens, workers’ facilities or chemical storage facilities with water discharge points within the site boundaries, no measurements for oil and grease, BOD5 or COD will be necessary based on Section 4.2.2 of the EM&A Manual.
3.2 MONITORING LOCATIONS
Some monitoring locations have been recommended in the EM&A Manual and shown in Annex D. However, as the EM&A Manual was originally approved for a much greater area, some of the monitoring locations have been refined in order to monitor the specific impacts of this Project only. Before the commencement of this EM&A programme, the proposed monitoring locations had been verified by the IEC and endorsed by the EPD. The final Sensitive Receiver where monitoring shall be performed is listed in Table 3-2 and Table 3-3 and shown in Annex E. Table 3-2 Location of Air and Noise Quality Monitoring Station
Env. Aspect Sensitive Receiver Location Air A1 Village house in To Tau near the proposed pumping station
Noise N1 Village house in To Tau near the proposed pumping station
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
5
Table 3-3 Location of Marine Water Quality Monitoring Stations Co-ordnance Sensitive
Receiver Monitoring
Station Status East North
Location/Remarks
C1 Control Station 832992 842208 Upstream of sea body located at
north-west of Whitehead developmentM1
(old W1) Impact Station 832550 842525 Near the shore of Cheung Kang
Village M2
(old W2) Impact Station 832798 842541 The shore of To Tau near the proposed
sewage pumping station M3
(old W3) Impact Station 833091 842654 Close to the new box culvert outfall of
the Project.
The Sea Zone of the Project West and North (Tolo Harbour)
M4 (old W4)
Impact Station 833091 842654 The shore of Wo Kwai Sha Tsoi
C2 Control Station 833106 843846 Upstream of sea body located at
Starfish Bay M5
(old W7) Impact Station 832648 843635 Located offshore near the Tolo
Channel in Starfish Bay M6
(old W5) Impact Station 832580 843494 Located at the natural stream outfall in
Starfish Bay M7
(old W8) Impact Station 832791 843514 Located offshore near the Tolo
Channel in Starfish Bay
The Sea Zone of Starfish Bay
M8 (old W6)
Impact Station 832648 843635 Located at the natural stream outfall in
Starfish Bay 3.3 MONITORING FREQUENCY AND PERIOD
The requirements of impact monitoring are stipulated in Sections 2.7, 3.6, and 4.7 of the EM&A Manual and listed as follows. 1-hour TSP Monitoring Parameters : 1-hour TSP monitoring Frequency : 3 times every six days for 1-hour TSP Duration : Throughout out the construction period
24-hour TSP Monitoring Parameters : 24-hour TSP monitoring Frequency : once every 6 days for 24-hour TSP Duration : Throughout out the construction period
Noise Monitoring Parameters : One set of Leq(30min) as 6 consecutive Leq(5min) between 0700-1900 hours
on normal weekdays Frequency : Once every week Duration : Throughout out the construction period Marine Water Quality Monitoring Parameters : In-situ measurements including water depth, temperature, DO, pH, turbidity
and salinity; and Suspended Solids is analyzed by HOKLAS-accreditedlaboratory.
Frequency : Three days a week, at mid ebb and mid flood tides. The interval between 2 sets of monitoring will be more than 36 hours.
Sampling Depth
: (a) Three depths: 1m below water surface, 1m above sea bottom and at mid-depth when the water depth exceeds 6m.
(b) If the water depth is between 3m and 6m, two depths: 1m below water surface and 1m above sea bottom.
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
6
(c) If the water depth is less than 3m, 1 sample at mid-depth is taken Duration: : (a) Stations C1, M1, M2, M3 and M4 will be carried out during the
construction works is still on-going after stormwater drainage systems are built and operated or marine works undertaken (in accordance with the Section 4.5.4 EM&A Manual).
(b) Station C2, M5, M6, M7 and M7 will be carried out throughout construction period (in accordance with the Section 4.5.3 EM&A Manual).
3.4 METEOROLOGICAL INFORMATION
The meteorological information during the construction phase is obtained from Tai Po and Shatin Stations of the Hong Kong Observatory (HKO). The meteorological data during this quarter are present in Annex G.
3.5 ENVIRONMENTAL QUALITY CRITERIA
According to the Final Report Environmental Monitoring and Audit Manual [2095/13.3], the air quality, construction noise and water quality criteria with Landscape and Visual Impact were set up, namely Action and Limit levels are listed in Tables 3-4, 3-5, 3-6 and 3-7 as below. Table 3-4 Action and Limit Levels for Air Quality Monitoring
Action Level (μg/m3) Limit Level (μg/m3) Monitoring Stations 1-hour 24-hour 1-hour 24-hour
A1 302 172 500 260 Table 3-5 Action and Limit Levels for Construction Noise
Time Period Action Level in dB(A) Limit Level in dB(A)
0700-1900 hours on normal weekdays When one documented complaint is received > 75* dB(A)
Note: * Reduces to 70 dB(A) for schools and 65 dB(A) during the school examination periods. Table 3-6 Action and Limit Levels for Water Quality
DO (mg/L) (Surface & Mid)
DO (mg/L) (Bottom)
Turbidity (NTU) (Depth Averaged)
SS (mg/L) (Depth Averaged) Monitoring
Location Action Level
Limit Level
Action Level
Limit Level
Action Level
Limit Level
Action Level
Limit Level
M1 2.73 1.61 NA NA 5.73 6.44 8.00 8.77 M2 2.85 1.98 NA NA 6.26 6.45 10.40 14.08 M3 2.51 1.62 NA NA 5.10 5.64 4.00 4.00 M4 2.60 1.74 2.57 1.65 5.32 5.83 5.50 6.27 M5 1.94 1.45 NA NA 8.01 8.7 31.55 48.09 M6 2.36 1.38 NA NA 8.47 9.36 12.00 18.93 M7 1.98 1.57 NA NA 7.11 7.24 7.85 10.31 M8 2.67 1.08 NA NA 6.27 7.19 7.00 11.62
Notes: • “Depth-averaged” is calculated by taking the arithmetic means of reading of all three depths; • For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits. • For turbidity and SS, non-compliance of the water quality limits occurs when monitoring result is higher
than the limits. Table 3-7 Action Level for Landscape and Visual Impact in Construction Phase
Parameter Action Level Limit Level Any trespass by the contractor outside the limit of the works, including any damage to existing trees, woodland and vegetation
Non-conformity on one occasion
Repeated non-conformity NA
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
7
4 IMPACT MONITORING RESULTS The environmental monitoring results will be compared against the Action and Limit Levels established based on the baseline monitoring results and statutory criteria. In case the measured data exceed the environmental quality criteria, remedial actions will be triggered according to the Event and Action Plan. In the report quarter, the graphical plots of the trends of monitored parameter over the past four months are presented in Appendix F.
4.1 RESULTS OF AIR QUALITY MONITORING
Results of air quality monitoring at the identified locations during the Reporting Period are summarized in Tables 4-1 below. In this quarter period, 42 events of 1-hour TSP and 12 successful events of 24-hour TSP measurements were conducted at designated Location (A1). It is reported that one Action Level exceedance in 24-hour TSP monitoring was recorded during the reporting quarter. Investigation report has conducted and concluded that the exceedance was not related to the works under the Project.
Table 4-1 Summary of 1-hour and 24-hour TSP result 1-hour TSP 24-hour TSP Station
Max Min Mean Max Min Mean A1 204 22 119 178 54 99
Record Date 2 Dec 09 2 Dec 09 42 events 23 Dec 09 11 Nov 09 12 events
4.2 RESULTS OF CONSTRUCTION NOISE MONITORING
Summary of construction noise monitoring at the identified locations during the Reporting Period are summarized in Table 4-2 below. In this reporting quarter, a total of 13 events of construction noise measurement were conducted while no documented construction complaint was received and all the construction noise results were below the Limit level. No NOE or corrective action was recommended for this parameter. Table 4-2 Summary of Construction Noise Monitoring Results
Leq(30min) Station Max Min N1 62.0 53.7
Record Date 2 Nov 09 8 Dec 09 4.3 RESULTS OF MARINE WATER QUALITY OF MONITORING
In this reporting quarter, a total of 33 days of water quality monitoring were conducted. Breaches of water quality A/L levels and statistics of the compliance status during the Reporting Period are summarized in Table 3-6. A summary of exceedances for the three parameters: dissolved oxygen (DO), turbidity and suspended solids is shown in Table 4-3. Table 4-3 Summary of Water Quality Exceedances
DO (Ave of Top &
mid-depth)
Turbidity (Depth Ave.)
SS (Depth Ave) Total ExceedanceStation
Action Limit Action Limit Action Limit Action Limit November 2009
Mid-Ebb M5 0 0 0 0 0 0 0 0 M6 0 0 0 0 0 0 0 0 M7 0 0 0 0 1 0 1 0 M8 0 0 0 1 2 0 2 1
Mid-Flood M5 0 0 0 0 0 0 0 0
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
8
M6 0 0 0 1 0 0 0 1 M7 0 0 0 1 0 0 0 1 M8 0 0 0 2 1 1 1 3
December 2009
Mid-Ebb M5 0 0 0 0 0 0 0 0 M6 0 0 0 0 0 0 0 0 M7 0 0 2 0 1 0 3 0 M8 0 0 1 0 2 0 3 0
Mid-Flood M5 0 0 0 0 0 0 0 0 M6 0 0 0 0 0 0 0 0 M7 0 0 0 0 0 0 0 0 M8 0 0 0 0 2 0 2 0
No of Exceedance 0 0 3 5 9 1 12 6
During this reporting quarter, no Action/Limit Levels exceedance is recorded in DO, however, 8 Action/ Limit level exceedances are found in Turbidity; also 10 Action/ Limit levels exceedances are indicated at the SS. NOE was issued to notify EPD, IEC, Contractor and RE upon confirmation of the result. Investigation report was conducted which it was concluded that all exceedances in this Reporting Period were unlikely to be due to the Project as marine discharge was not yet started.
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
9
5 WASTE MANAGEMENT Waste management was carried out by an on-site Environmental Officer or an Environmental Supervisor from time to time.
5.1 RECORDS OF WASTE QUANTITIES
All types of waste arising from the construction work are classified into the following:
Construction & Demolition (C&D) Material; Chemical Waste; General Refuse; and Excavated Soil.
The quantities of waste for disposal in this Reporting Period are summarized in Table 5-1 and 5-2 and the Monthly Summary Waste Flow Table is shown in Annex H. Whenever possible, materials were reused on-site as far as practicable.
Table 5-1 Summary of Quantities of Inert C&D Materials
Quantity Type of Waste Oct 09 Nov 09 Dec 09
Disposal Location
C&D Materials (Inert) (m3) 0 0 0 - Reused in this Contract (Inert) (m3) 0 0 0 - Reused in other Projects (Inert) (m3) 0 0 0 - Disposal as Public Fill (Inert) (m3) 0 0 0 -
Table 5-2 Summary of Quantities of C&D Wastes
Quantity Type of Waste Oct 09 Nov 09 Dec 09
Disposal Location
Recycled Metal (kg) 0 0 0 - Recycled Paper / Cardboard Packing (kg) 0 0 0 -
Recycled Plastic (kg) 0 0 0 - Chemical Wastes (kg) 0 0 0 General Refuses (m3) 17.2 6.4 7.72 SENT Landfill
5.01 There was no site effluent discharged but the estimated volume of surface runoff was less than
50m3 in this monthly period.
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
10
6 SITE INSPECTION According to the Final Report Environmental Monitoring and Audit Manual [2095/13.3], the environmental site inspection should been formulation by ET Leader. Regular environmental site inspections had been carried out by the ET to confirm the environmental performance. The site inspection was carried out on 20 October, 4 November and 2 December 2009 with the Representatives of the Engineer and the Contractor to evaluate the site environmental performance in this Reporting quarter. No non-compliance was noted. Observations for the site inspections and monthly audit within this Reporting Month are summarized in Table 6-1. Table 6-1 Site Observations
Date Findings / Deficiencies Follow-Up Status 20 October 2009 N/A N/A
4 November 2009 Dust generation was observed during concrete breaking,
The Contractor is reminded to provide water spraying for dust control.
2 December 2009 The stockpile of construction materials is observed no cover with plastic sheet to prevent dust emission.
The Contractor is reminded to provide water spraying or well compact the surface for dust control
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
11
7 ENVIRONMENTAL COMPLAINT AND NON-COMPLIANCE 7.1 ENVIRONMENTAL COMPLAINT, SUMMONS AND PROSECUTION
No environmental complaint, summons and prosecution was received in this reporting period. The statistical summary table of environmental complaint is presented in Tables 7-1, 7-2 and 7-3.
Table 7-1 Statistical Summary of Environmental Complaints
Environmental Complaint Statistics Reporting Period Frequency Cumulative Complaint Nature
20 October - 25 December 2009 0 0 NA
Table 7-2 Statistical Summary of Environmental Summons Environmental Summons Statistics Reporting Period
Frequency Cumulative Complaint Nature 20 October - 25 December 2009 0 0 NA
Table 7-3 Statistical Summary of Environmental Prosecution
Environmental Prosecution Statistics Reporting Period Frequency Cumulative Complaint Nature
20 October - 25 December 2009 0 0 NA
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
12
8 IMPLEMENTATION STATUS OF MITIGATION MEASURES The environmental mitigation measures that recommended in the Final Report Environmental Monitoring and Audit Manual [2095/13.3] covered the issues of dust, noise and waste and they are summarized as following: Dust Mitigation Measure (a) The contractor shall frequently clean and water the site to minimize fugitive dust
emissions. (b) Effective water sprays shall be used during the delivery ad handling of aggregate, and other
similar materials, when dust is likely to be created and to dampen all sited material during dry and windy weather.
(c) Watering of exposed surfaces shall be exercised as often as possible depending on the circumstance.
(d) Areas within the site where there is regular movement of vehicles must be regularly watered as often as necessary for effective suppression of dust or as often as directed by the Engineer.
(e) Where dusty materials are being discharged to vehicle from a conveying system at a fixed transfer point, a three-sided roofed enclosure with a flexible curtain across the entry shall be provided. Exhausted fans shall be provided for this enclosure and vented to a suitable fabric filer system.
(f) The Contractor shall restrict all motorized vehicles within the site, excluding those on public roads, to a maximum speed of 15km per hour and confine haulage and delivery vehicles to designated roadways inside the site.
(g) Wheel washing facilities shall be installed and used by all vehicles leaving the site. No earth, mud, debris, dust and the like shall be deposited on public roads, water in wheel cleaning facility shall be changed at frequent intervals and sediments shall be removed regularly. The Contractor shall submit detailed proposals for the wheel cleaning facilities to the Engineer prior to construction of the facility. Such wheel washing facilities shall be usable prior to any earthworks excavating activity in the site.
(h) Any material dropped in the roads will need to be cleaned up immediately to prevent dust nuisance.
Noise Mitigation Measure
(a) Noisy equipment and activities should be sited by the Contractor as far from close-proximity sensitive receivers as practical. Prolonged operation of noisy equipment close to dwellings and schools should be avoided.
(b) The Contractor should minimise construction noise exposure to the schools (especially during examination periods) as much as possible. The Contractor should liaise with the school and the Examination Authority to ascertain the exact dates and times of all examination periods during the course of the contract and to avoid noisy activities during these periods.
(c) Noisy plant or processes should be replaced by quieter alternatives where possible. Silenced diesel and gasoline generators and power units, as well as silenced and super-silenced air compressors should be used.
(d) Noisy activities should be scheduled to minimise exposure of nearby sensitive receivers to high levels of construction noise. For example, noisy activities can be scheduled for midday, or at times coinciding with periods of high background noise (such as during peak traffic hours).
(e) Idle equipment should be turned off or throttled down. Noisy equipment should be properly maintained and used no more often than is necessary.
(f) The power units of non-electric stationary plant and earth-moving plant should be quietened by vibration isolation and partial or full acoustic enclosures for individual noise-generating components.
(g) Construction activities should be planned so that parallel operation of several sets of equipment close to a given receiver is avoided, thus reducing the cumulative impacts
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
13
between operations. The numbers of operating items of powered mechanical equipment should be minimised.
(h) Construction plant should be properly maintained (well-greased, damage and worn parts promptly replaced) and operated. Construction equipment often has silencing measures built in or added on, e.g. bulldozer silencers, compressor panels, and mufflers. Silencing measures should be properly maintained and utilised. Where possible, rubber or damping materials should be introduced between metal panels to avoid rattle and reverberation of noise.
(i) Equipment known to emit sound strongly in one direction, should where possible, be oriented so that the noise is directed away from nearby NSRs.
(j) Material stockpiles and other structures (such as site offices) should be effectively utilised, where practicable, to screen noise from on-site construction activities. Alternatively, noise barriers having a surface density of 10 kg/m2 should be used to\ protect nearby NSRs if necessary.
(k) The Contractor should devise, arrange methods of working and carry out the works insuch manner as to minimise noise impacts on the surrounding environment, andshould provide experienced personnel with suitable training to ensure that thesemeasures are implemented properly.
Waste Mitigation Measures
(a) The Contractor shall observe and comply with the Waste Disposal Ordinance (WDO) and its subsidiary regulations.
(b) The Contractor shall submit to the Engineer for approval a Waste Management Plan with appropriate mitigation measures including the allocation of an area for waste segregation and shall ensure that the day-to-day site operations comply with the approved waste management plan.
(c) The Contractor shall minimise the generation of waste from his work. Avoidance and minimisation of waste generation can be achieved through changing or improving design and practices, careful planning and good site management.
(d) The reuse and recycling of waste shall be practised as far as possible. The recycled materials shall include paper/cardboard, timber and metal etc.
(e) The Contractor shall ensure that Construction and Demolition (C&D) materials are sorted into public fill (inert portion) and C&D waste (non-inert portion). The public fill which comprises soil, rock, concrete, brick, cement plaster/mortar, inert building debris, aggregates and asphalt shall be reused in earth filling, reclamation or site formation works. The C&D waste which comprises metal, timber, paper, glass, junk and general garbage shall be reused or recycled where possible and, as the last resort, disposal of at landfills.
(f) The Contractor shall record the amount of wastes generated, recycled and disposed of (including the disposal sites). The Contractor shall use a trip ticket system for the disposal of C&D materials to any designated public filling facility and/or landfill.
(g) In order to avoid dust or odour impacts, any vehicles leaving a works area carrying construction waste or public fill shall have their load covered.
(h) To avoid the excessive use of wood, reusable steel shutters shall be used as a preferred alternative to formwork and falsework where possible.
(i) The Contractor shall observe and comply with the Waste Disposal (Chemical Waste) (General) Regulation. The Contractor shall apply for registration as chemical waste producer under the Waste Disposal (Chemical Waste) (General) Regulation when chemical waste is produced. All chemical waste shall be properly stored, labeled, packaged and collected in accordance with the Regulation.
CRBC had been implementing the required environmental mitigation measures according to the Final Report Environmental Monitoring and Audit Manual [2095/13.3] subject to the site condition. Environmental mitigation measures generally implemented by CRBC in this Reporting Month are summarized in Table 8-1.
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
14
Table 8-1 Environmental Mitigation Measures
Issues Environmental Mitigation Measures Water Quality
• Wastewater were appropriately treated by treatment facilities; • Drainage channels were provided to convey run-off into the treatment facilities; and • Drainage systems were regularly and adequately maintained.
Air Quality • Regular watering to reduce dust emissions from all exposed site surface, particularly during dry weather;
• Frequent watering for particularly dusty construction areas and areas close to air sensitive receivers;• Cover all excavated or stockpile of dusty material by impervious sheeting or sprayed with water to
maintain the entire surface wet; • Public roads around the site entrance/exit had been kept clean and free from dust; and • Tarpaulin covering of any dusty materials on a vehicle leaving the site.
Noise • Good site practices to limit noise emissions at the sources; • Use of quite plant and working methods; • Use of site hoarding or other mass materials as noise barrier to screen noise at ground level of
NSRs; • Use of shrouds/temporary noise barriers to screen noise from relatively static PMEs; • Scheduling of construction works outside school examination period in critical area; and • Alternative use of plant items within one worksite, where practicable.
Waste and Chemical Management
• Excavated material should be reused on site as far as possible to minimize off-site disposal. Scrap metals or abandoned equipment should be recycled if possible;
• Waste arising should be kept to a minimum and be handled, transported and disposed of in a suitable manner;
• The Contractor should adopt a trip ticket system for the disposal of C&D materials to any designed public filling facility and/or landfill; and
• Chemical waste shall be handled in accordance with the Code of Practice on the Packaging, Handling and Storage of Chemical Wastes.
General The site was generally kept tidy and clean.
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Action-United Environmental Services and Consulting
15
9 CONCLUSIONS AND RECOMMENTATIONS 9.1 CONCLUSIONS
This is the 1st Quarterly EM&A summary report for the Project covering the construction period from 20 October to 25 December 2009. No noise complaint (which is an Action Level exceedance) was received and no construction noise measurement results that exceeded the Limit Level were recorded in this Reporting Month. No NOEs or the associated corrective actions were therefore issued. In this reporting quarter, no 1-hour TSP monitoring results that triggered the Action or Limit Levels were recorded but 1 Action Level exceedance in 24-hour TSP monitoring was registered. Investigation report was concluded the exceedance was not related to the works of the Project. For marine water quality, 12 Action and 6 Limit Level exceedances were recorded in this reporting quarter. NOE was issued and investigation concluded that the exceedances were not project related. No documented complaint, notification of summons or successful prosecution was received. Three event of site inspection were carried out by ET in this reporting quarter. No non-compliance was observed during the inspection. In general, it was reminded that good house keeping practice should be maintained. The environmental performance of the Project was therefore considered satisfactory. In this Reporting quarter, EPD visited the site on 24 November 2009 to select the treatment facilities as provided by CRBC for the discharge permit application. No other external parties i.e. Agriculture, Fisheries and Conservation Department (AFCD) or Leisure and Cultural Services Department (LCSD) paid a visit during the Reporting Period.
9.2 RECOMMENDATIONS
As dry season is approaching, special attention should be paid to provide air quality mitigation measures including wheel wash facilities, watering of haul roads and covering of dusty materials with tarpaulin sheet, etc. Moreover, mitigation measures to avoid ingress of surface runoff into nearby water bodies from the construction site should be properly maintained. To control the site performance on waste management, the CRBC shall ensure that all solid and liquid waste management works are fully in compliance with the relevant license/permit requirements, such as the effluent discharge licence and the chemical waste producer registration. CRBC is also reminded to implement the recommended environmental mitigation measures according to the Final Report Environmental Monitoring and Audit Manual [2095/13.3]. Baseline monitoring of air quality, noise and water quality was conducted during typical Hong Kong wet season (April to October). It is important that influence of the seasonal changes is taken into account when interpreting monitoring data of all environmental issues obtained in the coming dry season. Review of the baseline conditions may need to be conducted regularly in particular during times of seasonal changes. If the baseline changes are evident, the environmental performance criteria should be re-established under agreement of the ER and IEC and submitted to the EPD for endorsement.
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Annex A
Project Site Layout Plan
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Annex B
Organization Structure and
Contact Details of the CRBC & Relevant Parties
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Environmental Management Organization
CEDD
Environmental Team (the ET)
Independent Environmental Checker EDMS
Environmental Team Leader AUES
T.W. Tam
Environmental Team Supervisor AUES
Ben Tam
General Public
Environmental Officer CRBC
L. C. Ling
Project Manager CRBC
Raymond Mau
Project Engineer AECOM
Joanna Wong
Environmental Supervisor CRBC T.B.A.
Site Agent CRBC
Felix Chan
Site Foreman & Supervisors CRBC
Cheng Pui Ming
Sub-Contractors’ Project Managers
Sub-Contractors
Site Engineers CRBC
Lam Wai Hong Xia Yu
Ng Ka Ying Environmental Consultant AUES
Ben Tam Nicola Hon
Resident Engineer AECOM
Angus Law
Safety Officer CRBC
John Choi
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Contact Details of Key Personnel
Organization Project Role Name of Key Staff Tel No. Fax No.
CEDD Employer Mr. Dennis Mok 2301 1398 2721 8630
AECOM Engineer’s Representative Mr. Angus Law 2631-7796 2631-7226
EDMS Independent Environmental Checker Mr. James Choi 2869-6018 3007-8556
CRBC Project Director Mr. Wang Yanhua 2283-1688 2283-1689
CRBC Project Manager Mr. Raymond Mau 9048-3669 2631-8993
CRBC Site Agent Mr. Felix Chan 5182-9660 2631-8993
CRBC Site Engineer Mr. Lam Wai Hong 2631-8823 2631-8993
CRBC Site Engineer Mr. Xia Yu 2631-8823 2631-8993
CRBC Site Engineer Ms. Ng Ka Ying 2631-8823 2631-8993
CRBC Environmental Officer Mr. L.C. Ling 9858-1378 2631-8993
CRBC Environmental Supervisor TBA
CRBC Safety Officer Mr. John Choi 2631-8823 2631-8993
AUES Environmental Team Leader Mr. T.W. Tam 2959-6059 2959-6079
AUES Environmental Consultant Mr. Ben Tam 2959-6059 2959-6079
AUES Environmental Consultant Ms. Nicola Hon 2959-6059 2959-6079
AUES Environmental Site Inspector Mr. Ben Tam 2959-6059 2959-6079
Legend: CEDD (Employer) – Civil Engineering and Development Department AECOM (Engineer) – AECOM CRBC (Main Contractor) – China Road and Bridge Corporation EDMS (IEC) – EDMS Consulting Limited AUES (ET) – Action-United Environmental Services & Consulting
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Annex C
Master and Three Months Rolling Construction Programs
Contract No. 5T/2008//02Ma On Shan Development - Road, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Master Programme (Rev. 1.0)
ID læk Name Duration Sta¡t Finish lredecessors 2mslzorolzottlzotza lJunlJul hudseoloctl o llecllan +ú¡rhnl
^ honllothuJs.olo.tl o lo."ll-h.úunlnorl .l¡unl¡ul,q,ods.oloctl o bedJantrbMarlApd a llunllut
cl):02):03)Io: 04 )
?a
I's officeffrce
IUU
,a\
and delivery
's and setting out Site boundæies
on in the vicinity of the Site
M)
rcological survey and approval
Apply License to Excavate and Search for AntiquitiesCarry out archaeological survey
Backfill the confirmatory trial pitSubmission of Draft A¡chaeological survey report for AMO's comn
Submission of Final Archaeological survey report
Envi¡onmental worksSubmit EMP and WMP for approval
Propose website layout for reporting of EM&A information fo¡ app
Propose specialist for baseline monitoring and approval
Propose Methodology of baseline and approval
Carry out baseline monitoringSubmission of Baseline report for ICE s endorsement
Obtain consent from EPD for designated Non Woodland fueaErect hoarding a¡ound the fung shui woodland at DlErection of protective hoæding a¡ound Wu Kai Sha Village Well at
Erection of protective measures around existing grave at Dl(W)Iandscape works
Propose specialist for üee survey and approval
Carry out tree survey
Propose methodology for tree transplanting works for approval
Submission of tree survey report and LMP for IEC's endorsement
Obtain consent from EPD for designaæd Woodland Proþt AreaXP application at Sha On Street
Preparation of planting area for transplanted trees
Ground Investigation WortsProoose soecialist and methodolosv for SI works
1065 days
705 days
700 days
1065 days
700 days
700 days
700 days
1065 days
700 days
256 days
0 days
7 days
14 days
30 days
14 days
7 days
30 days
30 days
20 days
15 days
30 days
90 days
59 days
45 days
7 days
7 days
256 days
30 days
70 days
45 days
7 days
90 days
14 days
162 days
40 days
20 days
l0 days
60 days
30 days
12 days
12 days
14 days
14 days
l0 days
168 days
14 days
60 days
30 days
30 days
60 days
45 days
30 days
Thu 09/6/18
Thu 09/ll8Thu 09/6/18
Thu 09/6/18
Thu 09/6/18
Thu 09/6/18
Thu 09/6/18
Thu 09/6/18
Thu 09/6/18
Thu 09/6/18
Thu 09/6/18
Thu 09/6/18
T\u0916125
Tltuú1719Thu0916125
T\u@1719Thu 09fl16T\u@fi116Sat 09/8/15
Fn0919l4Sat 09/8/15
Sat 09/8/15
T\tt09,ll19T\u@1719
Sun 09/8/23
Sun 09/8/30
Thu 09/6/18
Thu 09/6/18
Sat 09/7/18
Satú19126Tue 09/l 1/10
Tue 09/11/17
Mon 10/2/15
Thu 09/6/18
Thu 09/6/18
TrcC9.Í7128
Thu 09/6/18
Sun 09/6/28
Thu09l8l27SatC!.19126
Thu 09/10/8
Trc09110120
Tue 09/11/3
TueúlllllTThu 09/d18Thu 09/6/18
TltuWl712T\uß1712
Mon 09/8/31
Wed 09/9/30
Sat @/9/19
Tue 09/11/3
Thu 09/d18Thu 09/6/18
T\llAflI1Monlll5l23Wed ll/5/18"Iltu l2l5l17
Wed 1ll5/18Wed 1l/5/18Wed ll/5/18Tltu I2l5ll7wed ll/5/18
Sun 10/2/28
Thu 09/6/18
Wed091612412
Wed 09tl8 13
FtLWlSn AWed 09fll8 13
Wed 09fll15 16
FrrWlSll4lTFri 09/8/14 l8SS
Thu09/9/3 19,18
Fn09l9l1820Sun09/9/13 19
Thu 09/11/12 19
Sat 0919/5
Satú1812214Satú1812925
Sat09.191526
Sun 102/28FnWnln nFnWl9l2529
Mon 09/11/9 30
Mon @/11/16 3lS:u¡,l0l2ll432Sunl0l2l2833
TltuCf.llll26Mon09[71I712Sun @/8/16 36
Satú1612712Wedt9l8l2638
FnWl9l2539WedWlI}n 40
Mon 09/10/19 41
Mon0P.llll242Mon 09/11/16 43
]Jtuú11U2644wdwtvn
WedCF.nllnSun 09/8/30 47
Fnúnß1,47TueC9.1912948
Sat 09/1 1/28 50
Mon09.lIll22lWedWllUz52
Thu 09/1210TueCf.19l1512
176 days
90 davs
)3
4
5
61
8
9
t0ut2r3
I4l5l6t7l8l920
21
22
23
24
25
26
27
28
29
30
31
32
JJ
34
35
36
37
38
39
40
4t42
43
44
45
46
47
48
49
50
5l52
53
54
55
sT/2008/02Task Milestone a Ro[ed Up Critical Tæk Split , , Group By Summary
Critical Tæk Summary Rolled Up Milestone O Exþmal Tæks Deadline {,
Rolled Up Task Rolled Up Prog¡essProgress Proþt Summary
Page 1
Contract No. 5T/2008//02Ma On Shan Development - Road, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Master Programme (Rev. 1.0)
ID tæk Name Duration Staft Finish lPredecessors z(xD I zoto I zott | .2012, h,rnll''l lAuJs lenlocr o Tan Jul o
56 Mobilization of plants and set up
Carry out SI worksADH4ADH5ADH6ADHTADH2ADH3ADHI
Submission of draft and final report
Section I Works (Works at Portion 1)glgrþ ¿¡ esraining Wall no. 6
Tree Transplant - 23nos
Mobilization of plants
Tree - Crown pruning
Tree - Root pruning lst stage - Pruning
Tree - Root pruning lst stage - WaitTree - Root pruning 2nd stage - Pruning
Tre¿ - Root pruning 2nd stage - WaitTree - Transplant
RW6 (CH0.00 - CH104.40 )Bay RW6-3 (CH29.70 - CH65.70)
Bay RW64 (CH65.70 - CH80.70)
Bay RW6-5 (CH80,70 - CH93.40)
Bay RW6-2 (CH14.70 - CH29.70)Bay RW6-6 (CH93.40 - CH104.40)
Bay RW6-l (CHO.ffi - CHl4.70)Works at Box Culvert
Tree Transplant - 20nos
Tree - Crown pruning
Tree - Root pruning lst strge - Pruning
Tree - Root pruning lst stage - WaitTree - Root pruning 2nd stage - Pruning
Tree - Root pruning 2nd stage - WaitTree - Transplant
Slope WorksProvision of temp. access for Lot STI 1033 and 1588
Cut existing road and form proposed slope
Slope inspection and verification works
Construction of æsociate surface drain system, berm and railir
7 days
49 days
7 days
7 days
7 days
7 days
7 days
7 days
7 days
30 days
ó47 days
185 days
101 days
14 days
5 days
5 days
28 days
5 days
28 days
7 days
84 days
20 days
20 days
12 days
12 days
l0 days
l0 days
581 days
71 days
5 days
5 days
28 days
5 days
28 days
5 days
229 days
14 days
180 days
90 days
90 days
5 days
581 days
6 days
40 days
35 days
35 days
35 days
40 days
35 days
35 days
35 days
35 days
35 days
35 days
35 days
Wed 09/9/16
wdúDn3WedWl9l23Wed 09/9/30
Wed 09/10/7
Wed 09/10/14
Wed 09/10/21
Wed 09/10/28
Wed 09/11/4
Wed 09/ll/11Sat 09Æ/15
Mon09/8ßlMon 09/8ß1Mon 09/8/31
Mon 09/9/14
Mon 09/9/14
Sat 09/9/19
Sat 09/10/17
Tttu09ll0l22T1lt09ll2l3
Thu 09/1210Thu 09/12l10
Wed 09/12130
Tue 10/1/19
Sun l0/l/31Fn l0l2ll2
Monl0l2l22Tue 09/10/20Sun 09/1129Sun 09/11/29
Fnæll2l4Fn09lI2l4Fri 10/l/l
Wed 10/l/6Wed,l0l2l3
Mon 10/l/25Mon 10/l/25Mon 10/2/8
Sun 10/5/9
Tue 10/6/8
Mon 10/9/6
Tue 09/1020Tue 09/10/20
Mon 09/10/26
SatúllA5Sat l0/1/9
Sat 10/2/13
Mon09l10126Sarúll2l5Sat 10/l/9
Sat 10/?13Sat 10/3/20
Sa¡1014124
Sarl0l5l29Sat l0f//3
Tueú1912255Tuc 09/ll/10
TueC9.1912956
Tue 09/10/6 58
Tue 09/10/13 59
Tue 09/10/20 60
Tueúll0l27 6ITueúllll362
Tue 09/l l/10 63
Thu 09/12110 64
Mon 11/5/23
Wed 10ßßwedænu9
Sun 09/9/13 49,48
FrA9Mß69Fri 09/9/18 69
Fri 09/10/16 71
Wed,09ll0l2l72wed 09/11/18 73
Wed091121914,53
Wed 10/3/3
Tueú11A2975Mon l0/l/18 77
Sat l0/l/30 78
T1t.t l0l2lIl79Sun 10/2/21 80
Wed 10/3/3 8lMorlll5l23
Sun 10/2/lT\t@ll2l35lTue 09/178 85
Thu09/12131 85
Tue 10/l/5 87
Tuel0l2l288Sun l0/2fl 89,53
Fri 10D/10Sun l0/2fr 90FF
Fri 10/8/6 90,92
Fri 10/8/6 93FS-90 days
Sun 10/9/5 94FS-60 days
Fri 10/9/10 95
Mon 11/5/23
Sun09ll0l25 42
FnWlI2l498Fri l0/l/8 99
Fnl0l2ll2lffiFri 10/3/19 101
Fn09lIA498Fri 10/l/8 103
Fnl0l2lI2lMFri 10/3/19 105
Fri 10/4/23 106
Fri 10/5/28 107
FnrcnDI08Fri 10/8/6 109
Misc. works
Construction of Box CulvertMobilization of plant
Bav 22(CH315.00 - CH330.00)
Bay 23 (CH330.00 - CH345.00)
Bay 24 (CH345.00 - CH360.00)
Bay 25 (CH360.m - CH375.00)
Bav 32(CH465.00 - CH480.00)
Bay 31 (CH450.m - CH465.00)
Bay 30 (CH435.00 - CH450.m)Bav 29 (CH420.00 - CH435.00)
Bay 28 (CH405.00 - CH420.00)
Bay 27 (CH390.m - CH405.00)
Bay 26 (CH375.m - CH390.00)
Bav 2l (CH300.00 - CH315.00)
I
ñ57
58
59
60
6l62
63
64
65
66
67
68
I
!I
69
70
71
72
13
74
15
76
77
78
79
80
81
82
83
84
¡ì-vlì-v
T
It
85
86
87
88
89
90
9t92
93
94
95
96
97
¡L
98
99
100
0l I
!t-02
03
M05 I06
07
108
109
110
sTt2008t02Tæk Milestone O Rolled Up Critic¿l Tæk Split , Group By Summary
Critical Tæk Summary Rolled Up Milestone Ô External Tasks Deadline +
Rolled Up Tæk Rolled Up ProgressProgress Proþt Summary
Page2
Contract No. 5T/2008//02Ma On Shan Development - Road,
Master Programme (Rev. 1.0)Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase I
ID læk Name Duration Staft Finish hedecessors 2ff)g 2010 20t1 2012
a lJunlJul lAudS ieolOc o DeclJan .e 'rh¡"Jnntl t lunllul huJsenloc n ln""llrn h"¡h¡r.lnn.l t lunllut hudseolo.tl o becl¡unF*Mal¡rl a ln¡nll¡lll Bay 20 (CH285.00 - CH300.00) s
Bay l9 (CH270.00 - CH285.00) s
Bay l8 (CH255.00 - CH270.00) s
Bay l7 (CH2,10.00 - CH255.00) s
Bay 16(CH225.00 - CH240.00) s
Bay 15 (CH210.00 - CH225.00) s
Bay 14 (CH195.00 - CH210.00) s
Bay I (CH0.00-CH15.00)
Bay 2 (CH15.00 - CH30.00)
Bay 3 (CH30.00 - CH45.00)
Bay 4 (CH45.00 - CH60.00)
Bay 5 (CH60.00 - CH75.00)
Bay 6 (CH75.00 - CH90.00)
Bay 7 (CH90.00 - CH105.00)
Bay 8 (CH105.00 - CH120.m)Bay 9 (CH120.00 - CH135.00)
Bay 10 (CH135.00 - CH150.00)
Bav ll (CH150.00 - CH165.00)
Bay 12 (CH165.00 - CHl80.m)Bav 13 (CHl80,m - CH195.m)Oufall (CH480.00 - CH493.285)
Completion of Box CulvertRe-alignment of existing road
Tree Transplant - 5nos
Mobilization of plants
Tree - Crown pruning
Tree - Root pruning lst stage - Pruning
Tree - Root pruni¡g lst stage - WaitTree - Root pruning 2nd stage - Pruning
Tree - Root pruning 2nd stage - WaitTree - Transplant
Road WorksUtility coordination meeting
Diversion of existing CLP transformer
Laying of l200dia. Concreæ pþMinor Earthwork for road formationConst¡uction of watermain (beside proposed road)
Construction of proposed concrete road
Implement of TTAConnection of proposed road to existingCuring time for last pour concrete road surface
Open to public
Construction of watermain ( existing road)
Pressure test and swabbing of watermain
Sterlization and water sample
Connection of watermain bv WSDMisc. works
Worls at Dl(N) Road
Tree Transplant - 20nos
Tree - Crown pruning
Tree - Root pruning lst stage - Pruning
Tree - Root pruning lst stage - WaitTree - Root pruning 2nd stage - Pruning
Tree - Root pruning 2nd stage - WaitTree - Transplant
45 days
45 days
40 days
40 days
40 days
40 days
40 days
30 days
30 days
30 days
30 days
30 days
30 days
30 days
30 days
30 days
30 days
30 days
30 days
30 days
40 days
0 days
289 days
101 days
14 days
5 days
5 days
28 days
5 days
28 days
7 days
289 days
45 days
90 days
12 days
35 days
30 days
30 days
3 days
14 days
14 days
3 days
l0 days
7 days
14 days
30 days
7 days
502 days
73 days
5 days
5 days
28 days
5 days
28 days
7 days
Sat l0/8flTue l0l9l2lFri l0/ll/5
Wed l0/lUl5Mo¡ lIlll24
Sat 1l/3/5Thu l1/4/14Sat 10/3/20
Mon 10/4/19
Wed 10/5/19
Fri 10/6/18
Sun 10fll18Tue 10/8/17
Thu 10/9/16
Sat 10/10/16
Mon 10/11/15
Wed l0/12l15Fn lllll14
Sun ll/2/13Tue 1l/3/15Thu ll/4/14Mon lll5l23Sat 09/8/15
Mon 09/8/31
Mon 09/8/31
Mon09l9l14Mon 09/9/14
Sat 09/9/19
Sat 09/10/17
TlttC9.ll0l22TltuúlI2l3Sat 09/8/15Sat 09/8/15
Tue09l9l29Fri 09/l 1/13
Wedúllll25Wed 09/12130
Tue 10/l/19Thu 10/218
Sun 10/2/21
Sun 10/3/7
Sun 10/3/21
Wedl0l3l24Sat 10/4/3
Sat 10/4/10
Sat I0l4l24Monl0l5l24
Tue 09/1020Sun 09/1129Sun 09/l l/29Sun 09/l 1/29
FnWlW4Fri 10/1/1
Wed 10/1/6
WedßU3
Mon 10/920 9l
Thu l0/ll/4 ITue l0ll2ll4l
Sun ll/1/23 IFn lll3l4I
Wed 1l/4/l3lMon 11/5/23 ISun 10/4/18 1l
Tue 10/5/18 IThu 10/6/17 ISat l0r7l17 1l
Mon l0/8/16 llWed 10/9/15 l:Fri 10/10/15 l:
Sun l0/11/14 llTue l0ll2ll4l'Thu ll/1/13 1l
Sat lIl2ll2I'Mon 1l/3/14 llWed 1ll4/13 l:Mon ll/5/23IiMon 1l/5/23 liSun 10/5/30
\rdwlragSun 09i9l13 4'
Fri 09/9/18 l'Fri 09/9/18 l.
Fri 09/10/16 1.
Wed 09/10/21 l.Wed 09/11/18 1,
Wei@ll2l9I'Sun 10/5ß0Mon 09/9/28 1l
SunC'4.ll2l27I'Ttrcúllll242:Tueúll2l29l,Thu 10/1/28 1,
WedI0l2ll7 I'Sarl0l2l20lSat 10/3/6 l,
Sat 10/3/20 1.
Tve l0l3l23l.Fnl0l4l2LFn l0l4l9l.
Ft l0l4l23 L
Sun 10/5/23 1:
Sun 10/5/30 1:
Sat 1lßl5Tuel0l2.ll)
T\uúl|2l35TltuWll2l35
Thu09/12131 ltTue l0/l/5 ltTue l0l2l2ltTue I0l2l9lt
],1 l0I12
t3
t4
r5
t6
)2
t8
t9
¿0
¿1
¿2
,.3
¿4
t5
¿6
t't¿8
z9
l011,1 17
),48
l5l5ttl8l910,53
r3
lt5,14tFS-15 dt6[TFS-10 days,
t8
f9t0ilt2t3
t4t5
r6
It2
t3
A,53
J 5n3
t2r3
t4l5l6r7l819
20
2l22
23
24
25
26
21
28
29
30
3l32
JJ
34
35
36
)t38
39
40
4t42
!
7
k
I
+Tìv]-\I
43
44
45
46
47
r48
r4950
r5l52
153
t54155
56
57
58 I
59
60
6l162
r63T&165
sT/2008/02Tæk Milestone a Roled Up Critical Tæk Split Group By Summary
Critical Task Summary Rolled Up Milestone O External Tasks Deadline O
Rolled Up Tæk Rolled Up Prog¡essProgress ProþtSummary
Page 3
Contract No. 5T/2008//02Ma On Shan Development - Road, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Master Programme (Rev. 1.0)
ID Iæk Name Duration Start Finish ledecessors 2W I 2010 201 I 2Û12
a llunllul lnupls ieoloct o Ian rebh4arlAorl a IunlJul o lo."ll-h.uhr¡.J¡o.l . hunl¡u hodseoloctl o bec[mh*Molen ] a lrunlrult66 RW4 (CH123.00 - CH290.00)
Bay RW4-18 (CH159.00 - CHl7l,00)Bay RW4-19 (CH171.00 - CH183.00)
Bay RW4-22 (CH207.m - CH220.00)
Bay RW4-23 (CH220,00 - CHr2.m)Bay RW4-24 (CH232.N -CH244.m)Bay RW4-25 (CH244.00 - CH256.00)
Bay RW4-20 (CH183.00 - CH195.00) CLPBay RrrlV4-21 (CH195.00 - CH207.00) CLPBay RW4-17 (CH147.00 - CH159.00)
Bay RW4-16 (CH139.00 - CH147.00)
Bay RW4-15 (CH13l.00 - CH139.00)
Bay RW4-14 (CHlæ.m - CH131.00)
Bay RW4-26 (CH256.m - CH266,00)
Bay RW4-27 (CH266.m - CH278.00)
Bay RW4-28 (CH278.00 - CH290,00)
RW2 (CH0.00-CH91.00)
Cofirmation of RW2Bay RW2-l (CH0.00 - CH12.00)
Bay RW2-2 (CH12.00 - CHl7.00)Bay RW2-3 (CH17.00 - CH26.50)
Bay RW2-4 (CH26.50 - CH36.00)
Bay RW2-5 (CH36.m - CH45.00)
Bay R'ü2-6 (CH45.00 - CH54.00)
Bay RW2-7 (CH54.00 - CH63.00)
Bay RW2-8 (CH63.00 - CH71.m)Bay R'ü2-9 (CH?l.m - CH8l.00)Bay RW2-10 (CH81.00 - CH91.00)
Road WortsUtility detection and reporting
Utility coordination and diversion if necessary
Chainage From CH 300 to CH 564
Earthworks
Construction of stormwater drain
Construction of sewerage
Proposed water main layingPressure test and swabbing
Construction of proposed road surface
Public lightineUtilities laying
Gas main
CLP Cable
PCCW
CATVHKBN
Installation of street furmture
Construction of footpath
113 days
15 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
14 days
12 days
12 days
12 days
12 days
1l days
1l days
113 days
53 days
12 days
12 days
12 days
12 days
12 days
12 days
12 days
12 days
12 days
12 days
5û2 days
7 days
50 days
495 days
120 days
120 days
90 days
60 days
14 days
40 days
30 days
115 days
45 days
20 days
40 days
30 days
30 days
15 days
50 days
50 days
10 days
342 days
70 days
Tue 09/10/20Tue 09/10/20
Wed 09/l l/4Wed 09/l l/18wúwn2t2
Wedæll2l16Wed09lW30Wed 10/l/13WedI0lIl2T
Wed 09/11/18
WedWlI2l2MonúlI2l14
SatC9.l12126
Thu l0/1flTue 10/l/19Sat l0/l/30
Tue 09/10/20Tue 09/10/20
Sat09llU12T\u09112124
Tue l0/l/5Sun 10/l/17
Fn l0lll29Sat09lI2l12
Tlttúll2l24Tue l0/l/5
Sun 10/l/17Fn I0lIl29
Tue 09/1020TueC.9.lI0l20
Tue09lI0l27Tveú[email protected]
WedßH24Sat 10/4/10
Wed 10/6/9
Tue 10/5/25
Wed 10/6/9
FNrcNDFnnnlg
Fri 10/8/13
Sat 10/8/28
Fn l0l9lI7Sat 10/10/2
Mon 10/11/lTue 10/11/16
Wed ll/l/5Tltu l1l2l24
we/JL0utoWed 10/2/10
Tue l02DTueúllIl3 42
TueCf.lllll7167Tue 09/1/1 168
Tueúll2ll5169TteúllU29 fiOTae l0llll2lTlTue 1011126172,196
Tue L0l2l9l'13Tue 09/1211 168
Sun 09/12113 175
Fn09ll2l25176Wed,101116l'17
Mon 10/1/18178
Fn l0lll29 179
Tue 10/2/9 180
Tuel0l2l9Fn0gll2lIl42
Wed09ll2l23l83Mon l0/l/4 184
Sat 10/1/16 185
Thu 10/1/28 186
Tue l0l2l9I87WedWllUz3183
Mon l0/l/4 189
Sat 10/l/16 190
Thu 10/l/28 191
Tw I0l2l9l92Sat 1l/3/5
Monú11012642Tue 09/12115 195
Sat ll/3/5Tue 1012123195
Sat l0l4l24 198FS-60 days
Mon l0l 5 124 l99FS-60 days
Tue 10/6/8 200FS45 days
Tue 1016122201
Sat 10frl3 200,119,156
Thu 10fil8 201
Sun 10/10/31
Sunl0l8l222MWed 10/9/1 206FS-10 days
Wed 10/10/6 207FS-5 days
Sat 10/10/16 208FS-20 days
Sun 10/10/31 209FS-15 days
Mon l0/11/15 210
Tue Illll42ILWedlll2l232l2
Sat lll3l5 213
Mon 1l/1/17Tw l0l4l20 165,174,181,188
Construction of surface drain and cycle track
Misc. works
Chainage From CH 100 to CH 300Earthworks
I
!I
I
-
t67
tì.:-v]--r:l!,lLlztrf.Elr
168
69
70
7t72
73
74
75
76
77
78
79
80
8l82
kT¡
I't-!Iì
ùI
Ùì
83
u185
186
187
188
189
90
91
92
93
94
95
¡-!96
9',7
)b
198
t99 v- !!
TTE
2N201 tL202203
2M205
206247
208
2W2t02tr2122t3214
215
2t62t7 Construction ofstormwaterdrain 70 days Sun l0/3r7 Sat 10/5/15 216FS45 days
Constructionof risingmain 4Odays Monl0l4/26 Fri l0/6/42l7FS-20daysPressure test and swabbing 7 days Sat 10/6/5 Fri 10/6/11 218
Proposed water main laying 40 days Mon 1014126 Fn 101614 217FS-20 davs
2182t9220
sT/2008/02Tæk Milestone a Ro[ed Up Critical Task Split ' , Group By Summary
Critical Tæk Summary Rolled Up Milestone O Extemal Tasks Deadline +
Rolled Up Task Rolled Up ProgressProgress Proþt Summa¡y
Page 4
Contract No. 5T/2008//02Ma On Shan Development - Road, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Master Programme (Rev. 1.0)
ID læk Name Duration Start Finish Predecessors 2(X\slZOIOlZOnl20t2, h,tnll'l lAuJs"nlo"r o lD""lJrn ,e fr¡nlnn/ a llonlJul ffi llunl lot lnodsrolo.tl o loæl¡-h¡Mu.l¡p.l u ll*llol
221 Pressure t€st
Construction of proposed road surface
Public lightingUtilities laying
Gæ main
CLP Cable
PCCW
CATVHKBN
Installation of street furnitureConstn¡ction of footpath
Construction of surface drain and cycle track
Misc. works
Access Road to CHEUNG KANGForming Road embedment for access road
Construction of concrete access road
Curing time for læt pour concrete road surface
Misc. works
Open to public
Works at Dl(W) Road
Tree Transplant - Mixed Woodland (37nos)
Tree - Crown pruning
Tree - Root pruning lst stage - Pruning
Tree - Root pruning lst stage - WaitTree - Root Þruning 2nd stage - Pruning
Tree - Root pruning 2nd stage - WaitTree - Transplant
Tree Transplant - Fung Shui Woodland (59noÐ
Tree - Crown pruning
Tree - Root pruning lst stage - Pruning
Tree - Root pruning lst stage - WaitTree - Root pruning 2nd stage - Pruning
Tree - Root pruning 2nd stage - WaitTree - Transplant
Construction of Retaining WallRW4 (CH0.00 - CH123.00)
Site Preparation works and clearance
Bay RW4-l (CH0.00 - CH8,00)
Bay RW4-2 (CH8.00 - CHl6.00)Bay RW4-3 (CH16.00 - CH23.00)
Bay RW44 (CH23.00 - CH3l.00)Bay RW4-5 (CH31.00 - CH41.00)
Bay RW4-13 (CHl15.00 - CHl23.m) TBay RW4-12 (CH107,00 - CHl15.00) TBay RW4-11 (CH95.m - CH107.00) T/æcBay RW4-10 (CH83.00 - CH95.00) T/arcBay RW4-9 (CH?l.m - CH83.00) T/arc
Bay RW4-8 (CH59.00 - CH71.00) TBay RW4-7 (CH51.00 - CH59.m) ABay RW4-6 (CH41.00 - CH5l.00) A
RW2 (CH91.00 - CHl9l.00 )Site Preparation works and clearance
Bay RW2-21 (CHl8l.00 - CHl9l.00)Bay R'ü2-20 (CH171.m - CH181.00)
Bav R'lV2-19 (CH161.00 - CH171.00)
7 days Sat 10/6/5
45 days Sat 10/6/12
20 days Sat 10/6/5
9Odays FnlUff2s35 days Fn 1016125
14 days Fnl0nl2328 days Fri 10/8/6
20 days Tue \0l8l2420 days Fri 10/9/3
30 days T\u l0l9l2340 days Sat 10/10/23
40 days T\u l0ll2l27 days Tue 1l/1/11
168 days Wed 10U1045 days Wed 10/2/10
30 days Sarl}l3l2l14 days Mon1014126
3 days Mon 10/5/10
1 day Tue l0t7l21541 days Sun09/1129
80 days Sun 09/11/297 days Sun 09/ll/297 days Sun 09/11/29
28 days Sun 09/1216
7 days Sun 10/1/3
28 days Sun l0/l/1010 days Sun 10/2fl
91 days Sun09/11/2910 days Sun 09/11/29
l0 days Sun 09/ll/2928 days Wed09ll2l910 days Wed 10/1/6
28 days Sat 10/l/1615 days SarI}l2ll3
269 days Sun 09/1129269 days Sun 09/11/29
10 days Sun 09/11/29
14 days Wed09.ll2l914 days WedúlIA2314 days Wed 10/1/6
14 days Wed 10/l/2014 days Wed 10/2/3
14 days Wed l0l2ll114 days Wed 10/3/3
14 days WeÀ,l0l3ll714 days Wed 10/3/31
14 days Wedl0l4ll414 days Wedl0l4l2814 days Wedrcnl2914 days Wed 10/8/11
269days Sun09/112910 days Sun 09/ll/2914days WdWllUg14 days WedWllU2314 davs V/ed 10/1/6
Fn 1016111220
Mon 10t7126219,221
T\u1016124220wdrcDnzT\ul0fll29223Thu 10/8/5 225FS-7 days
TÏtul0l9l2226Sun 10/9/12 227FS-10 days
W eð, l0l9 122 228FS- l0 days
Frr 10110122229
Wed 10/1211230
Mon ll/l/10231Monllllll7 232
Tue I0l'1127
Ftr 1013126188,193
Sun 1014125235
Sun 10/5/9 236
Wed 1015112231
T ue l0f7 I 27 238,203,222
Monlll5f23Tue I0f2ll6Sat 09/1215 5lSat 09/1215 5 I
Sat |0lll2243Sat 10lll9 244
Sat101216245
Tue 1012116246,53
Sat I0l2I27Tue 09/1218 5lTue 09/1218 5lTue 10/l/5 250
Fn l0l1lI525lFo l0l2lI2252Sat l0l2l2'l 253,53
Tve l0l8l24Tuel0l84¿4Tue 09/1218 51
TueCP.112122257
Tue l0/l/5 258
Tue l0lll19 259
Tue 101212260
Tue10lAß261Tue 101312247,262
Trc 1013116263
Tue 10131302(4,34
Tue 1014113265
Tue l0l4l27 266
Tw l0l5lll267Tue 1018110239,268
Tue 1018124269
Tuel0l8D4Tue 09/lZ8 51
Ttrcú11422272Tue l0lIl5273
Tue 1011119274
222
223
224
225
226227
228
229
230
23r232
233
234
T235
236
237
238
239
2q
a
,
h rtrt
241
242
243
244
245
246
247
248
249
250
25r252253
254
255
256
?-4.
ì
257
258
259
2ñ261
262
263
2g265
26267
268
269
270
27t
h-vlìtvI
272
n3274
275
sT/2008t02Task Milesrone a Ro[ed Up Critical Tæk Split ' , Group By Summa¡y
Critical Task Summa¡y Rolled Up Milestone O Extemal Tasks Deadline i;Rolled Up Task Rolled Up Proefesshogress Proþt Summary
Page 5
Contract No. 5T/2008//02 Master Programme (Rev. 1.0)Ma On Shan Development - Road, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
ID lask Name Duration St¿rt Finish Jredecessors 2UD I 2010 20il I 2012
, hunllul huds ienlchr o lo."lr"n h.l rhr¡rJno.l ^ ll*llot tudseoloc o loer I^n hot#úrtilnJ a Iunl Jur huJs.nlcrtl o loolrunHu[,taJ¿.ml a llunl¡u
276 Bay RW2-18 (CHl54.m - CHl6l.00)Bay RW2-17 (CH147.00 - CH154.00)
Bay RW2-16 (CH137.00 - CH147.00) TBay RW2-15 (CH127.00 - CH137.00) TBay RW2-14 (CHlt9.00 - CH127.00) TBay RW2-13 (CHlll.00 - CHI19,00) TBay RW2-12 (CHl0l.00 - CHll1.00) T/ABay Rrff2-ll (CHgl,m - CHl0l.00) T/A
RWl (CH0.m - CH110.00 )Site Preparation works and clearance
Utility coordination and temp. protection
Modification of Existing Retaining rüall for connection
Bay RWI-Il (CHl02.m - CHl10,00) TBay RWl-10 (CH94.00 - CHI02,00) TBay RWI-9 (CH86.m - CH94.m) TBay RWI-8 (CH78.00 - CH86.00) TBay RWl-7 (CH69.00 - CH78.00) TBay RWI-6 (CH60.m - CH69.00) TBay Rrü1-5 (CH48.00 - CH60.00) TBay RWl4 (CH36.00 - CH48.00) TBay RWl-3 (CH24.00 - CH36.00) TBay RWI-2 (CH12.00 - CH24.00) TBay RWI-l (CH0.00 - CHl2,00) T
RW3 (CH0.00 - CH76.00 )Site Preparation works and cleæance
Bay RW3-7 (CH68.00 - CH76.00) TBay RW3-6 (CH60.00 - CH68.00) TBay RW3-5 (CH48.00 - CH60.00) TBay RW34 (CH36.00 - CH48.00) TBay RW3-3 (CH24.00 - CH36.00) TBay RW3-2 (CH12.00 - CH24.00) TBay RW3-l (CH0.00 - CHl2.m) T
Road ConsEuction
Earthworks
Construction of stormwater drainage works
Construction of rising main
Pressure test of Rising main
Swabbing of Rising MainProposed water main laying
Pressure test of water main
Swabbing of water main
Sterilization of whole water main system
Final connætion by others
Construction of proposed road Dl(W)Installation of Irrigation system and test
Misc. wo¡ks
Public lighting and street furnitureUtilities laying
Gæ main
CLP Cable
PCC'Itr
14 days Wed l0/l/2014 days Wedl0l?314 days WdIjU|T14 days Wed 10/3/3
14 days WeÀ l0l3ll714 days Wed 10/3/31
14 days Wed Ljnnï14days \ryed l0/8/ll
165 days Sun09/11297 days Sun09/11/29
45 days Sun 09/1216
20 days Wed 10/1/20
14 days Sun 10/?2812 days Sun 10/3/14
12 days Ftr 1013126
12 days Wed l0l4n12 days Mon 10/4/19
12 days Sat 10/5/1
12 days Sun 10/3/14
12 days Ftr 1013126
12 days Wed l0l4n12 days Mon 10/4/19
12 days Sat 10/5/1
149 days Sun 09/ll/297 days Sun 09/11/29
16 days Sun 10/2/28
14 days Tue 10/3/16
14 days Tue 10/3/30
14 days Tue t0/4/1314 days Tue 10/3/16
14 days Tue 10/3/30
14 days Tue I0l4l13376 days Thu 10/5/13
120 days Thu 10/5/13
120 days Tae 1016122
60 days Thu 10/9/30
14 days Mon 10/l l/297 days Mon 10/1?13
60 days Thu 10/9/30
14 days Mon 10/l l/297 days Mon 10/lZl3
2l days Monl0ll2l2030 days Mon I l/1/1090 days Mon l0/12l1360 days Sun ll/3/1312 days T\ulll1ll240 days Mon I0llll29
I42days Fnl0lI0ngS0days FnI0ll0l2925 days Mon10112/649 days Sun 10112126
Tue 101212275
Tue 1012116276
Tue 10131227'1,24'7
Tue 1013116278
Tue 1013130279
Tue 10/4/13 280
Tue 10/8/10239,281
Trc1018124282wd l0/5/r2
Sat 09/1215 5 ITue 10/1/19 285
Mon 10/2/8 286
Sat 10/3/13 254,281
Thu 10/3/25 288
Tue 101416289
Sun 10/4/18 290
Ft 1014130291
Wedl0l5l12292Thu 10/3/25 288
Tue 101416294
Sun 10/4/18 295
Fn 1014130296
Wedl0l5l12297Mon1014126
Sat 09/1215 5lMon 10/3/15 300,254
Mon 10/3/29 301
Mon 1014112302
Mon 1014126303
Mon 10/3/29 301
Mon 10/4/12 305
Mon1014126306
Mon 11/5/23
Thu 10/9/9 298,307,2'l 1FF
Tue 10/10/19 309FS-80 days
Sun 10/11/28 3l0FS-20 days
Sun 10/lZl2 3llSun l0/12l19 312
Sun 10/l 1/28 3l0FS-20 days
Sun l0ll2ll23I4Sun l0/12l19 315
Sun 1l/1/9316Tue lll7S3l'lSat lll3ll23I2,3l5
Wed 11/5/11319
Monlll5l23320FnIUn 314
Sat 1ll3/19Fn IÙllAn 3l4FS-31 days
Thu 10/12130 324FS-12 days
Sar Il l2l 12 325FS-5 davs
aì---üa
tI
rt
277
278279
280
281
282283
2U285
286287
288
289
290
29r292293
294
295
296297
298
299
300
301
302303
3U305
306
307
308
30s
J 0
IJ 2
J J
4
J 5
3t63t7318
319
320
32t322
323
324
325
326
327 CATV 35 days Mon lllll24 Sun Ill2l27 326FS-20 days
HKBN 35 days Sun 11/2/13 Sat ll/3/19 327FS-15 days
Construction offootpath 70 days Sun 1l/2/13 SatIll4l23 328FS-35 days,i
Construction of surface drain and cycle track 50 davs Mon lll4l4 Mon Lll5l23 329FS-20 davs
328
329
330
sTt2008t02Tæk Milestone a Rolled Up Critical Tæk Split Group By Summary
Critic¿l Task Summary Rolled Up Milestone O Exæmal Tasks Deadline +
Rolled Up Task Rolled Up ProgressProgress Proþt Summary
Page 6
Contract No. 5T/2008//02 Master Programme (Rev. 1.0)Ma On Shan Development - Road, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
ID Iask Name Du¡ation Start Finish ?redecessors 2.rnslzorolzorrlnt2a llunllu lnuds eoloct o becllanþel iltrJlnt
^ h,,nl]ul hudseoloctl o loecllan rebhMarlAorl a lJunlJul hudSeolOctl o DælJanRlMarlAprl a llunlJul
331 Completion of Section IWorts at Acccss Road o Pump Housc
Laying of sewerage pipe
laying of rising main
Pressure test of rising main along access road
laying of water main
Pressure test and swabbing of water main along access road
Connection water main to Main pipe line along Dl(N)Utility layingConstruction of concrete and græscrete access road to pump house
Misc. works
Construction of sewerage piæ along Sha on SteetApplication of Excavation Permit for gravity sewer pipe at Sha On
lmplement of TTA scheme and trial run
Utility detection and reporting
Construction of gravity sewerage pipe
Reinstatement of existing carriageway
Misc. works
Section IA WorksPossession of Site
Soiling for landscape soft works
Landscape soft work in Portion I (Exclude Section IÐMisc. works
Completion of Section IASection IB Works
Possession of Site
Establishment works in Portion I ( Excluded Section IVA)Completion of Section IB
Section II Works (Portion 2A and Portion 2B)Commencement Date
Works in Portion 24, Site G/ICPossession of Portion 2A & 2B ( Excision No: I )Mobilization of plants and set up
Site cleæance
Site formation wo¡ks
Construction of surface drain
Proposed fence erection
Misc. works
Works in Portion 28, Site LWS-BMobilizatron of plants and set up
Site clearance
Site formation works
Construction of surface drain
Proposed fence erection
Misc. works
Completion of Section IISection Itr Works @ortion 3)
Commencement Date
Possession of Portion 3 ( Excision No:2 )Tree Transplant - L3 (4nos)
Tree - Crown pruning
Tree - Rootpruning lst stage - Pruning
Tree - Root pruning lst søge - WaitTree - Root pruning 2nd stage - Pruning
Tree - Root pruning 2nd staee - Wait
0 days
220 dzys90 days
90 days
14 days
90 days
14 days
5 days
50 days
40 days
10 days
46,1days
180 days
30 days
14 days
180 days
180 days
20 days
700 days
0 days
30 days
30 days
5 days
0 days
1065 days
0 days
365 days
0 days
695 days
0 days
392 days
0 days
7 days
14 days
120 days
90 days
140 days
2l days
395 days
7 days
14 days
120 days
100 days
140 days
14 days
0 days
700 days
0 days
0 days
ó4 days
2 days
2 days
28 days
2 days
28 days
Mon 1l/5/23Sat 10/10/16
Sat 10/10/16
Mon l0/11/15
Sun ll/Zl3Mon l0/ll/15
Sun 1l/213Sun lll2l27Sun 1l/213Mon l1/4/4Sat ll/5/14
Tue 09/10/20Tue 09/10/20
Sun 10/4/18
Tue 10/5/18
Tue 10/6/1
Sun 10/7/11
Fri IIlll7Thu 09/6/18
Thu 09/6/18
Tue lt/3/15T\u 1ll4ll4Sat 11/5/14
tiled I l/5/18Thu 09/6/18
Thu 09/6/18
Thu ll/5/19T\tu l2l5l17Thu 09/6/18
Thu 09/6/18
Tue 10/4/13
Tue l0l4ll3Wed 10/4/14
Wed l0l4l2IWed 10/5/5
Tttu10l9l2Wed 10/12llWedlll4l20wedt0t4tr4Wedl0l4l14Wedl0l4l2lWed 10/5/5
Thul0l9l2Sat l0/12lll
Sat 1l/4/30Fri 11/5/13
Thu 09/6/18
Thu 09/6/18
Tue 10/4/13
wedt0t4n4Wed l0l4ll4Wedl0l4lI4
Fn 1014116
Fri 10/5/14
Sun 10/5/16
Mon I l/5/23 330,321
Mon 1l/5/23ThulIlLlI3124Sat lIl2lI2 333SS+30 days
Sar LI|U26334Sat lll2ll2 333SS+30 days
Sat 1112126336
T\ulll3l3337Sun 1l/4/3 336
Fri 11/5/13 339
Mon I l/5/23 340
wedturn6Satl0l4lI7 42
Mon l0l5l|1 343
Mon 10/5/31 344
Sarl0llrl21345Thu I l/1/6 34655+40 days
WedIlll12634'lWed 1l/5/18Thu 09/6/18
W ed lll4l 13 350,32955+30 c
Fri ll/5/13 351
Wed 1l/5/18 352
Wed I l/5/18 353
T\ttl2l5ll7Thu 09/6/18
Thu l2l5l11 356,353
Tltu l2l5l17 357
Fri l1/5/13Thu 09/6/18
Tue l1/5/10Tue I0l4ll3 36055+300 day
Tue 1014120362
Tue 101514363
Wed 10/9/1 364
Tue 10/l 1/30 365
Tue lIl4ll9 366Tue Ill5ll,0367Fri 11/5/13
Tue 1014120362
Tue 101514370
Wed 10/9/1 371
Fn l0ll2ll0372Fn 1ll4l29 373Fn lll5ll3 374Fri ll/5/13 375,368
Wed ll/5/18Thu 09/6/18
Tue 10/4/13 37833+300 day
wd 10/6/16
Thu 10/4/15 379,51
T\ul0l4l15379Thu 10/5/13 381
Sat 10/5/15 383
Sat10161123M
a 5n3332333
334335
336337
338
339
3N341
342343
3U345
346347
348349
350
351
352
5/18
353
354
35s l-<1.-6118-
J 5n7
356
35',1
358
359
360
361
362
363
3&365
366367
368
369
370371
372
373
374
375
376 t 5/13
377
t3378
379
380
381
382383
3U385
sTt2008102Task Milesrone a Rolled Up Critical Tæk Split ' ' Group By Summary
Critical Task Summary Rolled Up Milestone O External Tasks Deadline {'
Rolled Up Task Rolled Up ProgressProgress Proþt Summary
Page 7
Contract No. 5T/2008//02 Master Programme (Rev. 1.0)Ma On Shan Development - Road, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
ID fask Name Duration Start Finish lredecessors 2CfDlZOIOlZOttl20t2, llunllut hudslenloctl o ln."ll-þ"tlvtJlorl a llunl lut lnudseoloctl o loecllanÞeúr¡arlnorl a lunl Jrl huJseoìcl"tl o lo..lr-heuhvtarlturl a llunl¡ul
386 Tre¿ - Transplant
Road Works ConstructionMobilization of plants and set up
Site clearance
Backfill and compaction works
Construction of storm drain works at Road L3
l¿ying of water main at road L3
Pressure test and swabbing of water main along L3 road
Connection of water main to Main pipe line along Dl(N)Construction of proposed road L3
Erection of proposed fence
Misc. works
Public lighting and street furnitureUtilitiss laying
Gas main
CLP Cable
PCCW
CATVHKBN
Construction of footpath
Completion of Section IIISection W Works (Sewage Pumping Station)
Possession ofPortion IInstruction by the Engineer ( Excision No:3 )E&M design and submission for approval
Order and Delivery of E&M material
Minor Earthwork for pump house ( Below +10.3 mPD )Construction of pump house ( below +10.3 mPD )Backhll and compaction adjacent to pump house
Connection of rising main and sewerage to pump house
Construction of superstructure
Metal work and intemal finishing to pump house
Installation of E&M system
Testing and commission of system
Misc. works and irrigation system at roof of pump house
Construction of boundary wallExternal cladding system and finishing for pump house
Road work inside pump house
I-andscaping works
Misc. works
Completion of Section IVSection IVA Worts (Sewage h¡mping Slation)
Possession of Portion I
Instruction by the Engineer ( Excision No:4 )Establishment works
Completion of Section IVASection V Worls (Presenation and proæction of existing tess)
PossessionofPortion IPropose methodology of tree preservation and protection
Approval of methodology by the ER
Carry out fee preservation and protection within site boundary
Completion of Section V
4 days
400 days
7 days
14 days
120 days
60 days
45 days
2l days
5 days
75 days
40 days
13 days
20 days
79 dzys28 days
15 days
21 days
15 days
15 days
60 days
0 days
700 days
0 days
0 days
180 days
220 days
15 days
70 days
35 days
35 days
75 days
50 days
185 days
31 days
50 days
90 days
70 days
35 days
30 days
20 days
0 days
1065 days
0 days
0 days
365 days
0 days
700 days
0 days
30 days
16 days
580 days
0 davs
Sun 10/6/13
Wd 10/,+/14
Wed 10/4/14
wedl0l4l2lWed 10/5/5
Thu 10/9/2
Mon l0/11/lThu l0/12l16
Thu l1/l/6Tue ll/l/11Sun ll/3/27
Fri 11/5/6
Sat 10/12ll IFrLl0llZ3lFn l\lIU3ISun ll/1i23Monlll2lT
Wedlll2l23Sat 1l/3/5
Sun ll/3/20Wed 1l/5/18Tru 09/6/18
Thu 09/6/18
Wed 09/8/19
wed 09/8/19
Mon 10/2/15
Fn10l2ll2Sat I0l2J27
Sat 10/5/8
Sat 10/5/8
Sat 10/6/12
Thu 10/8/26
Fri 10/10/15
Mon l1/4/18Thu 10/8/26
Thu 10/8/26
Wed l0/11/24WedIll2l2Wed ll/3/9
Fri ll/4/8Wed 1l/5/18Thu 09/6/18
Thu 09/6/18
Wed 09/8/19
Thu ll/5/19T\ul2l5l17Thu 09/6/18
Thu 09/6/18
Mon 09/8/31
Wed 09/9/30
Fri 09/10/16
Wed ll/5/18
Wed 10/6/16 385
Wed 1l/5/18Tae 1014120379
Tue 10/5/4388Wed l0/9/l 389
Sun 10/10/3 1 365,372,390
Wed l0/12l15 391
Wed,lIl115392Mon I l/1/10 393
Sat 1113126394
Thu l1/5/5 395
Wed 11/5/18 396
Thu 10/12130 392FS-5 days
Sat 1lßl19Tltt IIlIl2'1 398
Sun I l/2/6 400FS-5 days
Sw lll2l27 401
Wed I l/3/9 402FS-5 days
Sat 11/3/19 403FS-5 days
Wed 11/5/18 404
Wed ll/5/18 405,397
Wed l1/5/18Thu 09/6/18
Wed 09/8/19 408
Sun 10/2/14,109
Wedl0l9l22410Fn 1012126 409,80
Fnrclsn 412Fri 10/6/11 413
Fn 1016111 413
Wed 10/8/25 415,414
Thu 10/10/14 416
Sun ll/4/17 417,411
Wed l1/5/18 418
Thu 10/10/14416Trc l0llll23 416
Tue lIl2ll421Tue IIl3l8 422
Tltulll4t7 423
Wedlll4l2T 424
Wed 11/5/18 419,425
T\ulAflúThu 09/6/18
Wedú18119428Tlt¡tI2l5lI7 426,429
Thu 12l5ll1 430
Wed 11/5/18
Thu 09/6/18
TueC9.19129 433,48
Thu 09/10/15 434
'üed l115/18 435
Wed l1/5/18 436
€+\
o-6ft$'v
387
388
389
390
391
392393
394
a 5/18
r8
395
396397
398
3W400
40r
N2q3ß4405
406
407
408
4æ4104
4 2
4 )4 44 5
4 6
4 7
4 8
4 9
420
421
422
423
424
425
426
427
428
429
430a 5tr7431
432
a 5/18
433
434
435
436
437
sTt2008t02Tæk Milesrone a Rolled Up Critical Tæk Split , ' Group By Summary
Critical Tæk Summary Rolled Up Milestone O External Tasks Deadline Õ
Rolled Up Task Rolled Up Prog¡essProgress Proþt Summary
Page 8
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Annex D
Monitoring Locations Designated in the EM&A Manual
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Annex E
Current Impact Monitoring Stations
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Annex F
Graphical Plots of Impact Monitoring
1. Air 2. Noise 3. Marine Water
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Air Quality
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Impact Monitoring 1-hour TSP Results at A1
0
100
200
300
400
500
600
16-Oct-09
21-Oct-09
26-Oct-09
31-Oct-09
5-Nov-09
10-Nov-09
15-Nov-09
20-Nov-09
25-Nov-09
30-Nov-09
5-Dec-09
10-Dec-09
15-Dec-09
20-Dec-09
25-Dec-09
Date
TSP (ug/m3)1st hour 2nd hour 3rd hour
Dust Ave. of 3 hours Action Level Limit Level
24-hour TSP Monitoring Results at A1
0
50
100
150
200
250
300
350
16-Oct-09
21-Oct-09
26-Oct-09
31-Oct-09
5-Nov-09
10-Nov-09
15-Nov-09
20-Nov-09
25-Nov-09
30-Nov-09
5-Dec-09
10-Dec-09
15-Dec-09
20-Dec-09
25-Dec-09
Date
24-hour TSP, μg/m3
24-hour TSP Action Limit
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Construction Noise
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Impact Noise Monitoring (N1))
30.0
35.0
40.0
45.0
50.0
55.0
60.0
65.0
70.0
75.0
80.0
85.0
90.0
20-O
ct-0
9
25-O
ct-0
9
30-O
ct-0
9
04-N
ov-0
9
09-N
ov-0
9
14-N
ov-0
9
19-N
ov-0
9
24-N
ov-0
9
29-N
ov-0
9
04-D
ec-0
9
09-D
ec-0
9
14-D
ec-0
9
19-D
ec-0
9
24-D
ec-0
9
Date
Noi
se L
evel
(dB
(A))
Corr. Leq30min Limit Level Leq 30min
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Marine Water
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
DO Conc. (Depth Ave. of Surface and Middle Layer) - Mid-
Ebb
2.00
4.00
6.00
8.00
10.00
12.00
14.00
16.00
18.00
20.00
20-O
ct-0
9
26-O
ct-0
9
1-N
ov-0
9
7-N
ov-0
9
13-N
ov-0
9
19-N
ov-0
9
25-N
ov-0
9
1-D
ec-0
9
7-D
ec-0
9
13-D
ec-0
9
19-D
ec-0
9
25-D
ec-0
9
Date
mg/L
C2 M5 M6 M7 M8
DO Conc. (Dep th Ave. o f Surface and Midd le Layer) -Mid -Flood
2.00
5.00
8.00
11.00
14.00
20-O
ct-0
9
26-O
ct-0
9
1-N
ov-0
9
7-N
ov-0
9
13-N
ov-0
9
19-N
ov-0
9
25-N
ov-0
9
1-D
ec-0
9
7-D
ec-0
9
13-D
ec-0
9
19-D
ec-0
9
25-D
ec-0
9
Date
mg/L
C2 M5 M6 M7 M8
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Turb id ity (Dep th Average) - Mid -Ebb
0.00
3.00
6.00
9.00
12.00
15.00
20-O
ct-0
9
26-O
ct-0
9
1-N
ov-0
9
7-N
ov-0
9
13-N
ov-0
9
19-N
ov-0
9
25-N
ov-0
9
1-D
ec-0
9
7-D
ec-0
9
13-D
ec-0
9
19-D
ec-0
9
25-D
ec-0
9
Date
NTUL
C2 M5 M6 M7 M8
Turb id ity (Dep th Average) - Mid-Flood
0.00
1.50
3.00
4.50
6.00
7.50
9.00
10.50
12.00
13.50
15.00
20-O
ct-0
9
26-O
ct-0
9
1-N
ov-0
9
7-N
ov-0
9
13-N
ov-0
9
19-N
ov-0
9
25-N
ov-0
9
1-D
ec-0
9
7-D
ec-0
9
13-D
ec-0
9
19-D
ec-0
9
25-D
ec-0
9
Date
NTUL
C2 M5 M6 M7 M8
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Suspended So lids (Dep th Average) - Mid-Ebb
0.00
3.00
6.00
9.00
12.00
15.00
18.00
21.00
24.00
27.00
30.00
20-O
ct-0
9
26-O
ct-0
9
1-N
ov-0
9
7-N
ov-0
9
13-N
ov-0
9
19-N
ov-0
9
25-N
ov-0
9
1-D
ec-0
9
7-D
ec-0
9
13-D
ec-0
9
19-D
ec-0
9
25-D
ec-0
9
Date
mg/L
C2 M5 M6 M7 M8
Suspended So lids (Dep th Average) - Mid -Flood
0.00
3.00
6.00
9.00
12.00
15.00
18.00
20-O
ct-0
9
26-O
ct-0
9
1-N
ov-0
9
7-N
ov-0
9
13-N
ov-0
9
19-N
ov-0
9
25-N
ov-0
9
1-D
ec-0
9
7-D
ec-0
9
13-D
ec-0
9
19-D
ec-0
9
25-D
ec-0
9
Date
mg/L
C2 M5 M6 M7 M8
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Annex G
Meteorological Data of Reporting Month
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Meteorological Data – October 2009
Tai Po Wind Speed & Direction use Shatin Station)
Date Weather Total
Rainfall (mm)
Mean Air Temp. (°C)
Wind Speed (km/h)
Mean Relative Humidity (%)
Wind Direction
Mon 19 Cloudy / rain / moderate / fresh 2 25.7 8 74.5 E/SE Tue 20 Cloudy / rain / fresh /strong 0 23.8 10 86.5 E/NE Wed 21 Cloudy / moderate 0 24.7 9.7 78 E/NE Thu 22 Fine / haze/ moderate 0 25.1 7.2 77.5 N/NE Fri 23 Fine / dry / hazy / light winds 0 25.3 6 74 N/NE Sat 24 Fine and dry with some haze. Light winds. Trace 26.5 6 70 E/NE Sun 25 NA 0 25.1 Maintenance
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Meteorological Data – November 2009
Tai Po Wind Speed & Direction use Shatin Station)
Date Weather Total
Rainfall (mm)
Mean Air
Temp. (°C)
Wind Speed (km/h)
Mean Relative
Humidity (%)
Wind Direction
Mon 26-Oct-09 Holiday Tue 27-Oct-09 Mainly fine. Moderate easterly winds, fresh over offshore waters. 0 24.9 10.5 70 E/SE
Wed 28-Oct-09 Mainly fine. Moderate easterly winds, occasionally fresh over offshore waters and on high ground. Trace 24.6 8.5 66.2 E/NE
Thu 29-Oct-09 Mainly fine and dry. Moderate easterly winds. 0 24.9 9 68.5 E/SE
Fri 30-Oct-09 Mainly fine. Some haze tomorrow. Temperatures will range between 23 and 28 degrees. Moderate easterly winds 0 24.8 7.5 74.5 E/SE
Sat 31-Oct-09 Mainly fine and dry. Moderate easterly winds 0 25.9 7.7 70.5 N/NE Sun 1-Nov-09 Fine and dry, Strong northerly winds 0 26.4 13 58 N/NE Mon 2-Nov-09 It will be dry. Mainly fine in the afternoon. Cloudy tonight. Moderate
to fresh north to northeasterly winds 0 22.7 19 36.5 N/NE
Tue 3-Nov-09 It will be dry. Cloudy overnight. Sunny periods tomorrow with a
maximum temperature of around 23 degrees. Moderate to fresh northeasterly winds.
0 17.1 12 47.5 N/NE
Wed 4-Nov-09 Mainly fine and dry. Moderate northeasterly winds, occasionally fresh over offshore waters. 0 19.7 6.7 56 N/NE
Thu 5-Nov-09 Cloudy. Sunny periods in the afternoon. Moderate east to northeasterly winds. 0 22.4 6.5 68.5 N/NE
Fri 6-Nov-09 Mainly fine in the afternoon. Cloudy tonight. Moderate easterly winds 0 23.7 7.5 80.5 E/SE Sat 7-Nov-09 Cloudy overnight. Sunny periods tomorrow. Moderate easterly
winds. 0 25.2 8.2 77.5 E/SE
Sun 8-Nov-09 Mainly cloudy with one or two showers. Moderate east to southeasterly winds. Trace 251 6.2 85.2 E/NE
Mon 9-Nov-09 Mainly cloudy with one or two showers overnight. Moderate southeasterly winds, becoming light winds tomorrow. Trace 25.9 6.2 83.5 E/SE
Tue 10-Nov-09 Mainly fine in the afternoon. Cloudy periods overnight. Light winds. Trace 26.4 8.2 79.5 S/SW Wed 11-Nov-09 Becoming cloudy with a few rain patches. Moderate southeasterly
winds, freshening from the east later. Trace 25.6 11.7 83 E/SE
Thu 12-Nov-09 Cloudy with occasional rain. Appreciably cooler tonight. Moderate to fresh southeasterly winds, becoming fresh northerlies later. 5.2 23.8 9 85.2 S/SE
Fri 13-Nov-09 Sunny periods tomorrow with a maximum temperature of around 21 degrees. Fresh northerly winds, occasionally strong over offshore
waters and on high ground. 0.2 17.4 13.5 76.5 N/NW
Sat 14-Nov-09 Dry with sunny intervals this afternoon. Cloudy tonight. Moderate north to northeasterly winds Trace 14.3 9 73 N
Sun 15-Nov-09 Mainly cloudy with a few rain patches. 20.2 17.4 7.7 86 N Mon 16-Nov-09 Mainly cloudy with a few rain patches overnight. Moderate to fresh
northerly winds. 34.8 14.5 11.5 87.5 N/NW
Tue 17-Nov-09 Cloudy. Dry with sunny intervals in the afternoon. Fresh northerly winds, strong over offshore waters and on high ground at first. 0 10.4 17 68.7 N/NW
Wed 18-Nov-09 Mainly cloudy. Cold in the morning. Dry during the day. Moderate to fresh northerly winds. 0 10.6 14.5 67.2 N/NW
Thu 19-Nov-09 Mainly cloudy and rather cool overnight. Moderate to fresh northerly winds. Trace 14 12 61 N/NW
Fri 20-Nov-09 Fine and dry this afternoon. Cloudy tonight. Fresh northerly winds, occasionally strong over offshore waters and on high ground. 0 14.5 12 56 N/NW
Sat 21-Nov-09 Cloudy and dry with sunny intervals. Fresh northerly winds, occasionally strong over offshore waters and on high ground at first. 0 13.9
Sun 22-Nov-09 Fine apart from some haze at first. Light winds, becoming moderate east to north easterlies tomorrow. 0 15 6.5 56.5 N/NE
Mon 23-Nov-09 Fine. Hazy at first. Light winds, becoming moderate east to north easterlies later. 0 17.4 7 66.5 N/NE
Tue 24-Nov-09 Fine. Hazy at first. Light winds, becoming moderate easterlies later. 0 19.6 6 79 N/NE Wed 25-Nov-09 Sunny periods in the afternoon. Cloudy tonight. Moderate to fresh
easterly winds. 0 20.3 5.5 81.7 N/NE
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Meteorological Data – December 2009
Tai Po Wind Speed & Direction use Shatin Station)
Date Weather Total
Rainfall (mm)
Mean Air
Temp. (°C)
Wind Speed (km/h)
Mean Relative
Humidity (%)
Wind Direction
Thu 26-Nov-09 Sunny periods. Moderate east to northeasterly winds. 0 21.1 7 80.7 E/SE
Fri 27-Nov-09 Sunny periods in the afternoon. Mainly cloudy overnight. Moderate east to northeasterly winds. 0 22.5 6.5 77 N/NE
Sat 28-Nov-09 Mainly fine and dry. Fresh easterly winds, occasionally strong over offshore waters and on high ground 0 21.2 9.5 74.2 E/SE
Sun 29-Nov-09 Fine but hazy. Dry during the day. Moderate northeasterly winds Trace 20.4 7.2 73.5 E/NE
Mon 30-Nov-09 Fine but hazy. Moderate north to northeasterly winds. Trace 19.1 6.7 68.5 NE
Tue 1-Dec-09 Mainly fine but hazy. Moderate northeasterly winds, becoming fresh northerlies tonight. 0 17.8 6.7 72 E/NE
Wed 2-Dec-09 Fine and dry. Moderate to fresh north to northeasterly winds. 0 19.3 6.5 73 N/NE
Thu 3-Dec-09 Fine and dry. Cool in the morning. Moderate to fresh north to northeasterly winds. 0 17.3 16.7 56.5 N/NE
Fri 4-Dec-09 Fine and dry apart from some haze. Cool overnight. Moderate east to northeasterly winds, fresh at times. 0 16.2 7.2 69.7 N/NE
Sat 5-Dec-09 Very dry in the afternoon. Moderate northerly winds, becoming fresh easterlies later. 0 16.4 7 57.5 NE
Sun 6-Dec-09 Cloudy. Fresh easterly winds, occasionally strong over offshore waters. Trace 17.5 82 64.7 N/NE
Mon 7-Dec-09 Mainly cloudy with a few rain patches. Moderate northeasterly winds. 5.5 17.8 8.7 85.7 N
Tue 8-Dec-09 Mainly cloudy with a few rain patches. Moderate north to northeasterly winds. 14.1 18.1 8.2 90 N
Wed 9-Dec-09 Mainly fine apart from relatively low visibility at first. Light to moderate north to northeasterly winds 0.4 18.1 7.2 92.7 N/NE
Thu 10-Dec-09 Mainly fine apart from some haze Trace 20.7 7.5 84.2 E/NE
Fri 11-Dec-09 Sunny periods. Visibility relatively low at first. Light winds, becoming moderate easterlies tonight. Trace 20.7 8.2 84.5 N/NE
Sat 12-Dec-09 Sunny periods. Moderate to fresh easterly winds. Trace 20.6 7 83 E/SE
Sun 13-Dec-09 Cloudy with a few rain patches. Moderate easterly winds, becoming fresh northerlies later in the afternoon. 0 22.1 7.3 75.2 E/NE
Mon 14-Dec-09 Mainly cloudy. Visibility rather low. Moderate to fresh easterly winds. 1 19.7 9.2 85 E
Tue 15-Dec-09 Moderate northerly winds, occasionally fresh over offshore waters. 9.6 17.1 9.5 91 E
Wed 16-Dec-09 Cloudy with a few rain patches at first. It will be cold. Fresh northerly winds. 3.8 13 11.5 79.2 N
Thu 17-Dec-09 Sunny intervals and dry tomorrow with a maximum temperature of around 15 degrees. Trace 11.4 10.4 70.5 N/NW
Fri 18-Dec-09 Mainly cloudy and cold. Dry during the day. Trace 11 10.3 71 N/NWSat 19-Dec-09 Cold and dry. Cloudy at first. Sunny periods during the day. . 0 12.7 10.3 69 NE Sun 20-Dec-09 Mainly cloudy. Very dry with sunny periods in the afternoon. 0 12.9 10.8 42.4 N/NE Mon 21-Dec-09 Cloudy and dry. Sunny periods during the day. 0 14.2 8.5 51 N/NE Tue 22-Dec-09 Sunny periods. Moderate easterly winds. 0 15.9 8.5 70.5 E/SE Wed 23-Dec-09 Cloudy. Sunny periods tomorrow. Moderate easterly winds. 0 18 8.2 72.7 E/NE Thu 24-Dec-09 Mainly fine. Moderate easterly winds. 0 19.7 6.1 84 NE Fri 25-Dec-09 Holiday
Contract No. ST/2008/02 – Ma On Shan Development Roads, Drainage and Sewerage Works at Whitehead and Lok Wo Sha Phase 1
Quarterly Environmental Monitoring and Audit (EM&A) Summary Report Q1 (October to December 2009)
AUES
Z:\Jobs\2009\TCS00477 (ST-2008-02)\600\EM&A Quarterly Report\1st Quarterly Oct-Dec 09\R0108v2.doc Annex Action-United Environmental Services and Consulting
Annex H
Monthly Summary Waste Flow Table
Name of Department: CEDD Contract No. ST/2008/02
Disposed as Public
FillImported Fill
(in '000M3) (in '000M3)
Jan
Feb
Mar
Apr
May
Jun 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Sub-Total 0 0 0 0 0 0 0 0 0 0 0
Jul 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Aug 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.0033
Sep 0.000 0.000 0.000 0.000 0.000 0.106 0.000 0.000 0.000 0.000 0.0022
Oct 0.000 0.000 0.000 0.000 0.000 3.048 0.000 0.000 0.000 0.000 0.0172
Nov 0.000 0.000 0.000 0.000 0.000 3.8205 0.000 0.000 0.000 0.000 0.0064
Dec 0.000 0.000 0.000 0.000 0.000 0.598 0.000 0.000 0.000 0.000 0.00772
Total 0.000 0.000 0.000 0.000 0.000 7.573 0.000 0.000 0.000 0.000 0.037
Total Quantity
Generated
Hard Rock and
Large Broken
Reused in the
Contract
Reused in other
projects
Disposed as
Public FillImported Fill Metals
Paper /
cardboard
Plastics (See
Note 3)Chemical Waste
Others, e.g.
general refuse
(in '000m³) (in '000m³) (in '000m³) (in '000m³) (in '000m³) (in '000m³) (in '000kg) (in '000kg) (in '000kg) (in '000kg) (in '000m³)
0.00 8.00 3.00 5.00 0.00 4.50 2.00 1.00 1.00 0.00 5.00
Notes: (1) The performance targets are given in PS Clause 1.100(14).
(2) The waste flow table shall also include C&D materials that are specified in the Contract to be imported for use at the site.
(3) Plastics refer to plastic bottles / containers, plastic sheets / foam from packaging material.
* (4) The Contractor shall also submit the latest forecast of the total amount of C&D materials expected to be generated from the Works, together with a breakdown of the natrue where the total amoun
C&D materials expected to be generated from the works is equal to or exceeding 50,000m³.
(in '000M3)
MetalsPaper/ Cardboard
packaging
Plastics (see note
3)Chemical Waste
Others, e.g.
General refuse
Monthly Summary Waste Flow Table for December 2009
Month
Actual Quantities of Inert C & D Materials Generated Monthly Actual Quantities of C & D Wastes Generated Monthly
Total Quantitiy
Generated
(in '000KG) (in '000KG) (in '000KG) (in '000KG)
Forecast of Total Quantities of C&D Materials to be Generated from the Contract*
Hard Roack and
Large Broken
Concrete
Reused in the
Contract
Reused in other
Projects
(in '000M3) (in '000M3) (in '000M3) (in '000M3)