contents part c3: scope of work - dwaf c3 scope of work addendu… · contents part c3: scope of...
TRANSCRIPT
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
109
Contents PART C3: Scope of Work
C3.1 STANDARD SPECIFICATIONS ............................................................................................. 110 C3.2 PROJECT SPECIFICATIONS ................................................................................................ 111 C3.3 PARTICULAR SPECIFICATIONS .......................................................................................... 121
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
110
C3.1 STANDARD SPECIFICATIONS The standard specifications on which this contract is based are the South African Bureau of Standard
Standardized Specifications for Civil Engineering Construction SABS 1200. (Note to complier “SABS” has
been changed to “SANS”.
SANS 1200 & 0120
The following standardised specifications shall apply to this contract:
SANS 1200 A : General (including AD Small Dams)
SANS 1200 C : Site Clearance
SANS 1200 G : Concrete (Structural)
SANS 1200 HA : Structural Steelwork
SANS 1200 L : Medium Pressure Pipelines
SANS 1200 LC : Cable Ducts
These standardised specifications are not bound into this document nor issued with it. The Contractor may
purchase copies for his own use from SABS, Pretoria
British Standard Code of Practice
B1 - BS 8081 1989 : Ground Anchors
This standard specification is included in Volume 3 (CD inserted in back page pocket of Volume 2).
The Particular Specification constituting additions and amendments to the Standard Specification is included
in C3.3 of this section of the Tender Document, Part C3: Scope of Work.
Other Particular Specifications
B2 – Drilling
B3 – Water Pressure Testing of Boreholes
B4 – Grouting
The above Particular Specifications are included in their entirety in C3.3 of this section of the Tender
Document, Part C3: Scope of Work.
DWA Standard Specifications
B5 – DWS 0750; Water Retaining Concrete
B6 – DWS 9900 Section C6; Corrosion Protection of Platforms, Ladders, Handrails & Flooring
B7 – DWS 9900 Section C1: Corrosion Protection of Steel Pipes and Specials for Pipelines
B8 – DWS 1110; Construction of Pipelines
B9 – DWS 1180: Specialist Services
B10 – DWS 2510: Supply of Valves – Gate Valves
These standard specifications are included in Volume 3 (CD inserted in back page pocket of Volume 2).
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
111
C3.2 PROJECT SPECIFICATIONS
C.3.2.1 Locality and Location Information
a) General
Hazelmere dam is located approximately 5km north of the town of Verulam on the Mdloti River in KwaZulu-
Natal, sited directly 30km due north of Durban and 500km south east of Johannesburg. By road from Durban
the distance is 38.3kms (41 min.) and by road from Johannesburg 617kms (7hrs 7 min.).
b) Accessibility
The locality and location plans are presented in Volume 2: Book of Drawings reproduced at approximate
scales of 1:300,000 and 1:15,000 respectively. As illustrated on the Location Plan access to the dam wall is
gained via the existing gravel road, which runs from the Vincent Dickenson main road turn-off, to the base of
the dam wall a distance of 2.42 km.
The existing gravel access road has the following basic characteristics, relative to 0.0m chainage, located at
the junction with the south channel of Vincent Dickenson Road.
Length (m) Width (m) Length (m) Gradient (m)
0 –320 5.0 – 5.5 0 – 940 1:15 – 1:10 (7%-10%)
320 – 2,420 3.0 – 3.5 940– 2,420 1:30 – 1:25 (3%-4%)
The contractor shall be required to increase the width of the access road wherever he considers such
improvement necessary for the safe operation of two way construction vehicles and shall be required to
maintain the road and side drainage in a safe and workmanlike condition throughout the duration of the
contract. On completion of the works the road must be re-gravelled with Type G5 material to ensure a 200
mm thick running surface and completely re-graded and re-compacted to regular falls.
c) Land for Contractor’s Operations
Three areas have been identified on which the contractor may set up operations and these are indicated on
the Location Plan C41.2/2. The area immediately adjacent to the dam wall, belonging to the Employer, has
been designated the “Working Area” and has an estimated gross area of around 2.4 hectares and a
perimeter of approximately 650 metres. This is considered the primary working area with direct access to the
dam wall for all construction operations. Two hundred metres of the dam wall security fencing lies within this
area. This fencing shall have to be removed to facilitate construction operations and shall be replaced with a
new fence on completion of the works. Additionally, there are around 5 survey beacons within this area that
will require to be fully protected by the contractor throughout the construction period. Any survey beacons
that are destroyed or become displaced as a result of the contractors operations and are thus rendered
unusable shall be reinstated at the expense of the contractor.
The area designated as the “Site of the Works” has been indicated on the Tender Drawing 466 471/12 and
amounts to 14.7 hectares the “Contractors Working Area” is also shown on this drawing and is contained
within the Site of the Works.
The other two areas designated as “Potential Base Camp Accom. & Storage (2.5 ha)” and “Potential
Alternative Base Camp Accom. & Storage” are considered as being potentially suitable for the establishment
of the contractor’s workers accommodation and additional storage of equipment and materials. The first of
these areas is located approximately 420m from the Vincent Dickenson main road turn-off and 2 kms from
the dam wall base camp. This is private land and unfortunately the owner is unknown. Should the contractor
consider this additional area suitable for his operations then he must make his own arrangements for
acquisition or lease.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
112
The second, less desirable and more remote, area is located to the south east of the dam wall, with access
along an informal, low grade access route. The Mdloti River runs along the west flank of the area. Again this
is private land but the owner is known and this information can be made available to the tenderer on request.
Should the contractor consider this additional area suitable for his operations then he must make his own
arrangements for acquisition or lease.
The Contractors construction camp shall be fenced off and shall contain all offices, stores, workshops,
testing laboratories, toilet facilities, etc. The camp shall always be kept in a neat and orderly condition.
The Contractor shall be responsible for providing and maintaining his own security arrangements for the
duration of the Contract.
The Contractor shall not use the area nor allow it to be used for any purposes not directly associated with the
execution of the Contract.
The Contractor shall be responsible for arranging, at his own cost, for the provision of all services he may
require in the area, as well as elsewhere on the Site.
The tendered sums as scheduled by the Contractor, whether grouped or individually, shall include all costs
for the installation, maintenance and removal of the fencing as specified, in addition to all other facilities
specified and as required by the Contractor for his own purposes.
No housing is available nor shall be allowed on the site of the works for the Contractor’s employees. It is the
sole responsibility of the Contractor at his own cost to house his employees and transport them to and from
the site. Only night-watchmen may be on the Site after hours.
C.3.2.2 Project Description
a) General
Hazelmere dam is the responsibility of the Department of Water Affairs (DWA). The Department has in turn
vested the authority for all operation and maintenance aspects in Umgeni Water, who maintain operational
offices at the dam. The offices are located on the north flank of the dam wall as indicated on the Location
Plan included in Volume 2: Book of Drawings, with GPS coordinates 29°35’46.6”S 31°2’29”E
This shall be the meeting point for the site briefing and site inspection scheduled as indicated in the Tender
Notice.
Hazelmere dam is a concrete gravity arched type structure 478m long with a centre line radius of 725m and
incorporates a 103m long ogee spillway situated 60m from the right bank end. The maximum height of the
structure above the lowest foundation level is approximately 47m. The dam was completed in 1976 and was
originally designed and built to accommodate a proposed 7m increase in dam height by means of the
installation of steel gates.
The project now under consideration includes raising the dam’s existing full supply level (FSL) from that of
86.0 m.a.s.l to 93.0 m.a.s.l. The raising thereby increases storage capacity and enables the dam operator,
Umgeni Water, to provide a reliable source of water to meet the demand of the rapidly growing urban and
industrial users within the supply area. In order to prevent critical water shortages in the supply areas the
need to raise the dam has become crucial.
b) Operational Condition
To assist construction operations on the dam wall the Department of Water Affairs have analysed their
historical dam capacity data. From the graph shown below it has been concluded that it will be safe to draw
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
113
down the dam and operate it at 70% of the operating level for the duration of the contract period, implying
that the dam has a small risk of dropping to the 30% level if the abstractions are the same as historic.
However, it must be emphasised that during construction the dam must be regarded as a strategic
operational water supply source and that even with controlled draw down there is a risk of discharge over the
spillway during periods of continuous rainfall or flooding. The contractor must therefore take account of this
risk when planning and implementing construction operations on the spillway and adjacent sections.
In this regard the Contractor’s attention is drawn to Clause 8.8.6 of the Particular Specification
c) Piano Key Weir (PKW)
It has been determined that the most appropriate means of raising the dam is by installation of a reinforced
concrete Piano Key Weir (PKW). This will be constructed atop the existing ogee spillway. A PKW provides a
much extended spillway length, by introducing a hydraulically and geometrically designed (planemetrically)
castellated weir wall. The increased length is evident when the original straight ogee spillway length of 103
metres is compared with the PKW length of 630 metres. This PKW is a first for South Africa and is arguably
the largest of such installations worldwide.
The general dimensions are:
Length (weir top) 630 m
Width 21.6 m
Plan (top) surface area 2,225 m2
The walls vary in height tapering from a minimum of zero to a maximum of 9.0m.
The entire weir structure shall be built to exacting standards and to water retaining structure specifications,
including provision for incorporation of waterproofed expansions joints. The vertical walls have a tapered
profile, ranging from 500mm at the top to 800mm at the bottom, incorporating closely spaced, large diameter
bar reinforcement, all aimed at achieving a design crack width of 0.1mm. As the site will be subject, at times,
to extremes of weather such as high solar radiation, high air temperatures and strong drying winds, then
particular care will be required at all stages of the concreting cycle to ensure that the matrix and final set
concrete is not adversely affected.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
114
d) Grout Curtain
The recent geotechnical investigations at the dam concluded that the grout curtain, especially in the spillway
section, has been compromised. Further investigations indicated that the majority of the pressure relief holes
at the bottom drainage gallery are clogged with material that originated from the mica rich layers in the
substrata of the dam wall foundation and from the dam basin (large organic content). Water pressures of
between 10m and 12 m were measured during the recent drilling of the additional boreholes from the bottom
gallery where artesian water conditions were encountered.
There are also indications that water is flowing through flow paths in the dam foundation which may seriously
damage the foundation in the longer term if not rectified. Restoration of the grout curtain will restrict and
control this flow.
The stability of the present and raised dam structure must be improved and the installation of anchor cables
has been identified as the most acceptable method. In terms of sequence of operations it is essential that the
restoration of the grout curtain be done in advance of the cable installation. Consequently anchoring
conditions in the foundation may well be better understood on completion of the re-grouting operation and
this may well prove beneficial in determining enhancements to the detailed design of the anchors.
e) Ground Anchors
Ground Anchors are to be incorporated to safeguard the stability of the dam wall when raised to the new Full
Supply Level (FSL). A system of vertical anchors through the wall crest as well as inclined anchors through
the downstream face of the dam wall will be installed. In both the Spillway and Auxiliary Spillway sections of
the wall, the heads of the anchors will need to be recessed into the dam wall in order to facilitate the flow of
water over the wall. The installation of the anchors will increase the wall stability against sliding and
overturning.
The specification applies to the supply, installation, stressing and testing of 379 No. post-tensioned anchors,
each with a working load of 3400 kN. Post-tensioned anchors shall be installed in drilled holes expected to
be of the order of 275mm nominal diameter.
The number of anchors has been derived from the basic assumption of a 3400kN working load per anchor.
However, the Contractor shall if he considers it advantageous and with the Engineer’s approval, vary the
anchor capacity taking due account of the geotechnical information and the in-situ concrete core results,
contained in the respective reports available in Volume 3 of the contract documents.
The anchors are to be generally fabricated, installed, stressed and tested in accordance with “BS8081:1989
Ground Anchorages” and any alternate design proposal by the Contractor should also be in accordance with
this British Standard.
It has been deemed beneficial to allow for cutting out existing concrete in the dam wall and installing precast
anchor bearing blocks (complete with water tight sealable lids) underneath the anchor heads where bearing
block dimensions are similar. Where dimensions vary (inclined anchors at the auxiliary spillway downstream
face) it is envisaged that in-situ concrete will need to be used. The Contractor may wish to propose alternate
anchor bearing blocks based on the core results of the in-situ concrete found in Volume 3 of these
specifications.
Furthermore, installation of anchor load monitoring equipment has been included in this contract by way of
hydraulic pressure transducer load cells and associated equipment. Breaking out existing concrete in order
to cast in ducting for read-out lines from the load cells has also been allowed for. In light of the above, the
Contractor may wish to propose alternate performance monitoring equipment to measuring the loads in the
anchors.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
115
C3.2.3 Survey Information
The Department of Water Affairs approved beaconing system relevant to the Hazelmere Dam Raising
contract, consists of eleven permanent beacons all prescribed by the letter “P” they are:
Reference Y (westing) m X (southing) m Elevation m
P03 -4060.169 3275228.241 121.280
P05 -4415.487 3275613.941 73.954
P07 -4344.216 3275646.229 72.613
P08 -4245.744 3275492.391 65.862
P09 -4214.942 3275413.134 74.876
P10 -4157.362 3275338.361 89.144
P108 -4239.661 3275684.93 95.484
P109 -4171.168 3275605.744 95.468
P143 -4054.655 3275380.153 95.473
P214 -4277.174 3275717.118 89.333
P243 -4062.281 3275369.295 91.722
The tabulated coordinate values are all based on the World Geodetic System 1984 ellipsoid, commonly
known as WGS84, with the International Terrestrial Reference Frame 91 (ITRF91, epoch 1994.0)
coordinates of the Hartebeesthoek Radio Astronomy Telescope used as the origin of the system. This
system is known as the Hartebeesthoek94 Datum. At this stage all heights still remain referenced to mean
sea level, as determined in Cape Town and verified at the tide gauges in Port Elizabeth, East London and
Durban.
These principal beacons shall be used for all setting out purposes in relation to the construction works and
the contractor must take great care to ensure that these beacons are protected from damage at all times.
The contractor shall also be responsible for carrying out regular checks on all beacons in this referencing
system to ensure their accuracy remains uncompromised for the duration of the works.
C3.2.4 Engineering Geology and Site Investigation
The geological report for the Hazelmere Dam Raising contract was undertaken by the engineering geological
consultant Knight Hall Hendry and is entitled “ENGINEERING GEOLOGICAL REPORT FOR THE RAISING
OF THE DAM: SITE INVESTIGATIONS” and is referenced KHH1953/3110012907 and dated June 2012.
The report is summarised in its “Section - 7. Conclusions and Recommendations” as follows:
The site is underlain by red brown coarse grained arkosic to subarkosic sandstone; of the Natal Group. The
rock mass behaviour is strongly influenced by the distinct bedding planes, which often contains thick
interbedded micaceous/silty materials. These were mostly not recovered and resulted in core losses.
It can be concluded that the grout curtain has been damaged by (i) movement of the dam as a result of shear
or high tensile stresses below the dam; or (ii) by leaching of the grout by seepage of water from the dam. It
must further be concluded that the existing drainage holes are blocked since they hardly produce any
seepage.
The results of the drilling, water flow, camera survey and pressure measurements paints a rather gloomy
picture of the spillway section with possibly a damaged grout curtain, inoperative drainage system and a
continuous zone of high permeability (and associated uplift pressures) at depths varying between about 2m
and 9m below the concrete/rock interface.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
116
It is recommended that the upper 20m of the grout curtain be reinstated using stable grout injection
processes and the drainage holes be properly cleaned out or redrilled to ensure effective release of pore
pressures.
The results of this investigation confirmed that the shear strength parameters assumed for the foundation
rock mass of c=0 and phi=38° are realistic. Evidence was found that bedding planes are continuous over at
least 7 block widths and contain substantial thickness of interbedded silty/micaceous materials. These
prominent, continuous bedding planes have on average a 5m interval, with numerous bedding planes in
between of limited continuity.
A full copy of this report accompanies and therefore forms an integral part of these tender documents. The
tenderer is required to study the document carefully and to fully acquaint himself with the contents thereof.
C3.2.5 Labour-Enhanced Construction
a) General
It is an objective of the Employer to maximise the labour content of certain operations or portions thereof on this
Contract. In this regard, where the specified work allows for a choice between mechanical or labour-enhanced
means, the former should generally be kept to the practical minimum.
b) Preferential Recruitment Area and Local Labour Composition (% of Total Number of Staff)
Preference will be given to persons from areas closest to the project workplace (Hazelmere Dam). The
following are regarded as communities closest to the workplace in the order of priority as set out below:
i. Persons residing within the municipal areas immediately adjacent to the dam.
ii. Persons residing within the municipal area of the District Municipality
iii. Persons residing within the KZN Province
iv. Persons residing within the rest of the Republic of South Africa.
50% of the labour should thus be recruited from the areas as defined above.
c) Requirements
The Contractor shall take cognisance of these objectives and their contribution to the utilisation of labour when,
at tender stage, he commits on the anticipated labour content required to complete the contract.
It is a requirement that the minimum labour content for this contract will be 20%.
The Contractor is required to supply detailed records of labour content with the monthly payment certificates in
a format approved by the Engineer.
C3.2.6 Affirmative Black Enterprises (ABEs)
It is a requirement of this contract that for the procurement of goods, services (including work carried out by
ABE subcontractors) and materials from affirmative black enterprises (ABEs), an amount of 15% expressed as
a percentage of the contract price (excluding VAT, Contract Price Adjustment (CPA), Contingencies, Variations
on Special Materials, Lump sums and all Provisional and Prime Cost amounts) be achieved.
Preference will be given to the following groups:
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
117
A "black enterprise" (BE) is one that is 50,1% owned by black persons and where there is
substantial management control. Ownership refers to economic interests while management
refers to the membership of any board or similar governing body of the enterprise.
A "black empowered enterprise" (BEE) is one that is 25,1% owned by black persons and where
there is substantial management control. Ownership refers to economic interests. Management
refers to executive directors. This is whether the black enterprise has control or not.
A "small, medium and micro enterprise" (SMME) bears the same meaning assigned to this
expression in the National Small Business Act, 1996 (Act No. 102 of 1996).
Local enterprises within the project area (iLembe Municipality area).
The target value of goods, services and materials (excluding VAT) procured from external sources from the
following designated groups expressed as a percentage of the 15% of the goods, services and materials
required (excluding VAT) shall at least be:
Black enterprises: 15%
Black empowered enterprises: 20%
Local Enterprises 5%
Small, medium and micro enterprises 10%
A record will be kept of percentage value per group. Achievement of targets is to be monitored monthly.
Penalties will be applied at the end of the contract if targets are not met.
C3.2.7 Failure to Comply with Provisions
Failure or refusal on the part of the Contractor to take the necessary steps to ensure that the targeted ABE
content and labour content is met, shall be sufficient cause for the Engineer to deduct penalties as follows:
a) Labour content
Penalty = CP x 3% x (specified labour content % - actual labour content %).
CP is the contract price excluding VAT, Contract Price Adjustment (CPA), Contingencies, Lump
Sums, Variations on Special Materials and all other Provisional and Prime Cost amounts.
b) ABE content
Penalty per group = CP x 0,5% x (specified ABE group content % - actual ABE group content %).
CP is the contract price excluding VAT, Contract Price Adjustment (CPA), Contingencies, Lump
Sums, Variations on Special Materials and all Provisional and Prime Cost amounts.
C3.2.8 HDI Supervisory Staff
If personnel are hourly paid they cannot be classified as supervisory staff, regardless the nature of their duties.
Examples of relevant personnel are, site agent, assistant site agent, senior materials technician, senior
surveyors and clerks.
The minimum value of HDI supervisory staff expressed as a percentage of the total number of supervisory staff
employed on the contract, as proposed by the tenderer shall be 30%.
A historically disadvantaged individual (HDI) means a South African citizen:
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
118
who, due to the Apartheid policy that had been in place, had no franchise in national elections
prior to the introduction of the Constitution of the Republic of South Africa, 1983 (Act No 110 of
1983) or the Constitution of the Republic of South Africa, 1993 (Act No 200 of 1993) ("the interim
Constitution); and/or
who is a female; and/or
who has a disability.
Provided that a person, who obtained South African citizenship on or after the coming to effect of the Interim
Constitution, is deemed not to be an HDI.
C3.2.9 EMP Requirements
The Environmental Management Plan (EMP) is included in Volume 3: Specialist Reports and Standard
Specifications and forms an integral part of these tender documents. It has been developed to mitigate
construction impacts associated with the proposed raising of the Hazelmere Dam. Principles and instructions
contained in this document are to be implemented by the Contractor and his employees.
The EMP has been updated with the conditions of the Record of Decision (ROD).
Non-compliance with the provisions of these documents will thus be regarded as a breach of the construction
contract. Compliance with the EMP will be enforced through monthly audits carried out by the Environmental
Compliance Officer (ECO).
C3.2.10 Quality Assurance, Quality Control and Quality Plan
Within three weeks of the award of the contract the Contractor shall furnish the Engineer with a
comprehensive Quality Assurance and Control plan that incorporates all the requirements of the documents
comprising the contract, for his own quality management as well as describing the Quality Control process
that will provide for regular inspection and signing off of work by the Engineer’s Site Staff. This will
particularly apply to aspects of the work that will be covered such as the checking of rebar and other
embedded items before the placing of concrete. The Quality Plan will provide all forms and documentation to
be signed by inspectors as necessary to generate a complete record of Quality Management.
The Quality Management System shall comply in all respects with the requirements of the ISO 9000-9004
series (as applicable). The Quality System shall take the form of a coordinated and formally documented
statement and shall include quality management objectives, policies, organisation, procedures, and work
instructions that demonstrate the Contractor's implementation of the requirements of ISO 9001 - 2000 Code
for Quality Management Systems.
The Contractor's Project Quality Plan for the Contract shall indicate how the Contractor's Quality System
shall apply to the specific requirements of the Contract. It shall clearly indicate, by way of written description,
schedules, flow diagrams and procedures, compliance with ISO 9001 - 2000 and compliance by Sub-
Contractors to ensure compliance with ISO 9001, 9002 or 9003 - 2000, as appropriate to the classification of
the product or service.
The Project Quality Plan shall identify all documentation concerning implementation of the procedures and
will form part of the demonstration of conformance to requirements for the plant materials and equipment to
be supplied under this Contract.
The Project Quality Plan shall be subject to the Engineer's approval.
The vocabulary used shall comply with the requirements of ISO 8402-1994.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
119
The onus to produce work that conforms in quality and accuracy of detail to the requirements of the
Specifications and Drawings rests with the Contractor, and the Contractor shall, at his own expense, institute
a quality control system and provide experienced engineers, foremen, surveyors, materials technicians, other
technicians and technical staff, together with all transport, instruments and equipment to ensure adequate
supervision and positive control of the Works at all times.
The cost of supervision and process control, including testing carried out by the Contractor, will be deemed
to be included in the rates tendered for the related items of work.
C3.2.11 Existing Services
a) Water, Electricity and Sewerage
The Contractor shall, at his own expenses, be responsible for obtaining and distributing water and electricity
required for construction and domestic use. The distribution of water and electricity shall be carried out in
accordance with the applicable laws and regulations.
No separate payment will be made for obtaining and distributing water and electricity, the cost of which will
be deemed to be included in the tendered rates.
b) Buried Services - General
The record drawings included in Volume 3: Specialist Reports and Standard Specifications provide the best
information available for existing services and the Contractor’s attention is drawn to these drawings.
Before underground or excavation work is carried out, the Contractor shall ascertain the presence and
position of all services likely to be damaged or interfered with by his activities. He shall obtain up-to-date
plans from the Engineer, Employer and local authorities for this purpose, showing the position of services in
the area where he intends to work. As services can often not be reliably located from such plans, the
Contractor shall determine the exact position of such services by means of suitable detecting equipment and
afterwards by careful hand excavation where necessary in order to expose the services at the positions of
possible interference by his activities. This procedure shall also be followed in respect of services not shown
on the plans but believed to be present.
All such services, the positions of which have been located at the critical points, shall be designated as
'known' services and their positions shall be indicated on a separate set of Drawings, a copy of which shall
be furnished to the Engineer.
While he is occupying the Site, the Contractor shall be liable for all damage caused by him to known services
as well as for consequential damage, whether, caused directly by his operations or by the lack of proper
protection.
The Contractor shall exercise all the necessary care to prevent damage to known services during
construction operations. Major excavating equipment and other Plant shall not be operated dangerously
close to these services. Where necessary, excavation in close proximity to these services shall be carefully
carried out with suitable hand tools, excluding picks wherever their use could damage the services.
No additional payment will apply to such more difficult work.
Services left exposed shall be suitably protected from damage.
c) Treatment of existing services
Existing services shall be relocated or removed as indicated on the drawings only at the instruction of the
Engineer.
d) Damage to services
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
120
Damage that occurs to unknown services during construction will be paid by the Employer.
However, all services that have been located and exposed, and are subsequently damaged by the
Contractor or his subcontractor, shall be reinstated to the same state as it was before the damage occurred
at the time and cost of the Contractor.
e) Reinstatement of services and structures damaged during construction
The Contractor shall inform the Engineer immediately when a service or structure is damaged. The extent of
the damage and a proposal how to reinstate the service or structure shall be submitted to the Engineer on a
sketch with dimensions and time frames.
The Contractor shall not be allowed to reinstate any service or structure unless indicated so by the Engineer.
The Contractor shall render all reasonable assistance to the service or structure owner with the
reinstatement of the service or the structure if required.
The Contractor shall be liable to reinstate the service or structure to its original state.
C3.2.12 Recording of Weather
The Contractor shall be responsible for keeping accurate records of weather conditions in the Daily Site
Diary, to use as substantiation of any claim for extension of time..
The Contractor will inform the Engineer when he is unable to proceed with the works in accordance with the
approved contract program. Subject to the approval of the Engineer, the rainfall and other relevant notes will
be noted in the Daily Site Diary for the applicable day/s. After the event the Contractor shall provide a revised
contract program motivating if the delay affects his schedule to the extent that he will need to motivate for an
extension of time in accordance with the Contract.
The Engineer, together with the Employer, shall be responsible for granting the extension of time.
C3.2.13 As-Built Drawings
During the execution of the Works on the Site the Contractor shall, in a manner approved by the Engineer,
record on Working Drawings and Contract Drawings all information necessary for preparing As-built
Drawings of the installed Contract Works. Marked up Drawings and other documents shall be made
available to the Engineer as he may require for inspection and checking.
As-built Drawings may, subject to the approval of the Engineer, include approved Working Drawings
adjusted as a correct record of the installation of the Contract Works.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
121
C3.3 PARTICULAR SPECIFICATIONS
These Particular Specifications constitute additions and amendments applicable to the Standardised
Specifications.
C.3.3.1 Additions and Amendments to SANS 1200
PS A GENERAL
7. TESTING
7.2 APPROVED LABORATORIES
Append sub-clause 7.2 with the following:
The Contractor shall secure the services of an approved laboratory to oversee site activities related
to concrete quality, slump and strength sampling and testing. The method statement and
procedures for the quality control of the concrete are to be approved by the Engineer before
commencement of the work. Should the approved laboratory elect to establish a suitable concrete
testing facility on site, it will be operated by the Contractor with full access permitted to the
Engineer. All work related to sampling and testing, carried out on site, shall be supervised by a
suitably qualified and experienced laboratory technician.
8. MEASUREMENT AND PAYMENT
8.1 MEASUREMENT
8.1.2 Preliminary and General Item or Section
8.1.2.2 Tendered sums
Append sub-clause 8.1.2.2 with the following:
d) All Subcontractors’ direct costs and overhead costs, profit and all other costs for the provision of
the item.
8.3 SCHEDULED FIXED-CHARGE AND VALUE RELATED ITEMS
8.3.2 Establishment of facilities on the Site
8.3.2.1 Facilities for Engineer
The sum tendered shall allow for the Contractor shall provide offices and facilities as specified in
PSAB sub-clause 3.2 and for these offices to be equipped with the following for shared use by the
engineer’s staff:
a wireless network including modem and router;
One multifunction document solution machine with capabilities to copy, scan, email and fax
documents up to A3 in size.
One A1 colour Plotter.
Two 10megapixel, 3x optical zoom digital camera supplied complete with 4mb memory card.
8.3.2.2 Facilities for the Contractor
The rate for all items under this sub-clause must cover the cost of complying with the requirements
of clause 11.1.1 of the EMP in Volume 3 of the Contract Document
c) Laboratories
The sum shall also cover the cost of complying with clause PS A 7.2 above, to which the
Contractor’s attention is drawn.
d) Accommodation
Accommodation will not be permitted on site but the sum tendered shall allow for all costs the
Contractor may incur for accommodation of staff in the area as outlined in the Project
Specifications.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
122
e) Ablution and Latrine facilities
The sum shall also cover the cost of complying with clause 11.1.3 of the EMP in Volume 3 of the
Contract Document, to which the Contractor’s attention is drawn.
i) Access
The sum shall also cover the cost of complying with clause 11.2.2 of the EMP in Volume 3 of the
Contract Document and any improvements to the access in terms of clause C3.2.1b above, to
which the Contractor’s attention is drawn.
j) Plant
The rate shall also cover the cost of complying with clause 11.1.2 of the EMP in Volume 3 of the
Contract Document, to which the Contractor’s attention is drawn.
8.3.3 Other Fixed Charge Obligations
The rate shall also cover for the cost of complying with all fixed charge aspects of the EMP
included in Volume 3 of this Contract Document
8.4 SCHEDULED TIME- RELATED ITEMS
8.4.2 Operation and Maintenance of Facilities on Site, for Duration of Construction, except where
otherwise stated
8.4.2.1 Facilities for Engineer
a) Furnished offices
The Sum tendered shall also allow for the Contractor to service the engineers’ offices on a daily
basis and to maintain the following in working order:
a wireless network including modem and router.
One multifunction document solution machine with capabilities to copy, scan, email and fax
documents up to A3 in size.
One A1 colour Plotter.
b) Telephone
No telephone will be required but the sum tendered shall allow for the Contractor to pay for the
monthly data usage of the Engineer’s Site wireless.
d) Survey assistant and material
The rate shall cover the cost of providing the personnel and equipment listed in PS AB Clause
5.5. On completion of the works, ownership of the survey equipment shall revert to the
Contractor.
New Item:
Append sub-clause 8.4.2 with the following:
e) Accommodation
The Contractor shall pay for the accommodation for the Engineer’s Site Staff as directed by the
Engineer.
f) Transport
The Contractor shall pay for the transport for the Engineer’s Site Staff as directed by the Engineer.
8.4.2.2 Facilities for the Contractor
The sums tendered for all items under this sub-clause must cover the cost of complying with the
requirements of clause 11.1.1 of the EMP in Volume 3 of the Contract Document
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
123
c) Laboratories
The sum shall also cover the cost of complying with clause 7.2 above, to which the Contractor’s
attention is drawn.
d) Accommodation
Accommodation will not be permitted on site but the sum tendered shall allow for all costs the
Contractor may incur for accommodation of staff in the area as outlined in the Project
Specifications.
e) Ablution and Latrine facilities
The sum shall also cover the cost of complying with clause 11.1.3 of the EMP in Volume 3 of the
Contract Document, to which the Contractor’s attention is drawn.
i) Access
The sum shall also cover the cost of complying with clause 11.2.2 of the EMP in Volume 3 of the
Contract Document and any improvements to the access in terms of clause C3.2.1b above, to
which the Contractor’s attention is drawn.
j) Plant
The sum shall also cover the cost of complying with clause 11.1.2 of the EMP in Volume 3 of the
Contract Document, to which the Contractor’s attention is drawn.
8.4.5 Other Time Related Obligations
The sum shall also cover the cost of complying with all time-related aspects of the EMP included in
Volume 3 of this Contract Document
8.6 PRIME COST ITEMS
a) Eel Ladder
In terms of the EIA provision is to be made for the installation of an eel ladder in order to allow
passage of eels to and from the upper reaches of the Mdloti River. In view of the fact that studies in
this regard are not yet conclusive in terms of what is required, a stated sum for the work has been
included in accordance with indications that have been made.
1) Stated sum for study and implementation
The Contractor shall pay for the above as directed by the Engineer.
2) Overheads, charges and profit on (1) above
b) Electrical Installation
The stated sum for this item constitutes provision for the appointment of an electrical contractor to
install cabling and fittings as necessary to reinstate lighting and any other electrical installation
disrupted by the works. The ducting and draw pits required for the installation are measured
elsewhere.
1) Electrical installation as directed.
The Contractor shall pay for the above as directed by the Engineer.
2) Overheads, charges and profit on (1) above.
c) Environmental
The stated sum for this item constitutes provision for carrying out a search to find rare and
endangered flora species in an inundation area in the dam basin and reporting on an action plan to
rescue these species and relocate them to a newly established nursery. It further allows for
actioning the plan in the report and maintaining the nursery on a monthly basis for 12 months. The
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
124
sum also allows for the removal of trees greater than 100mm girth from the dam basin over an area
of approximately 175 Hectares.
1) Stated sum for implementation
2) Overheads, charges and profit on (1) above
8.7 DAYWORKS
Certain routine structural and/or concrete repairs must be carried out on the existing dam wall and
other installations. Where so required the Engineer may use the provisions made under the
Dayworks items in the bill of quantities to attend to such remedial work.
8.8 TEMPORARY WORKS
8.8.6 Special Water Control
The Umgeni Water staff operating the dam will attempt to lower the dam to 70% of its capacity in
order to lower the dam supply level to facilitate construction work. Notwithstanding the
aforementioned steps, these measures will not be able to guarantee control of the supply level.
The contractor shall allow here for the design and construction of a coffer dam or some other
method of protecting the works (or relevant portion thereof) from damage or disruptions resulting
from water levels within the dam rising due to flooding, sudden heavy rainfall or un-seasonally high
rainfall within the dam catchment that prevents dam operating staff from maintaining the lowered
supply levels.
It is envisaged that the protection will be required during the early stages of the construction of
each PKW (Portion of the PKW situated on an individual dam wall monolith) and the lump sum is
for the provision of the number of structures required as well as the consequent movement of a
structure to each position in which it will be required.
In this regard the historical top water level data is provided in C3.2.2b of the Project Specifications
for the Contractors information
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
125
PS AB ENGINEERS OFFICE
1. SCOPE
Append clause 1 with the following:
The location and details of the site office accommodation shall be approved by the Engineer before
construction.
3. MATERIALS
3.2 OFFICE BUILDINGS
Replace sub-clause 3.2 with the following:
The contractor shall provide and furnish offices/rooms for the use of the engineer comprise of the
following:
Resident Engineer’s office – shall consist of one room with a floor area of at least 16m2 and a
ceiling height of 2.5m.
Internal furnishings to include:
a) One trestle table, 2m long x 1m wide x 0.9m high, with a smooth top.
b) Two desks of minimum dimensions 1,5m long x 0,9m wide with four drawers (two lockable).
c) One high stool.
d) One office swivel chair, two visitors’ chairs.
e) A lockable upright steel cabinet with three shelves and a lockable steel filing cabinet with four
drawers.
f) Shoe cleaning mat at entrance.
g) An acceptable blind to each window.
h) A pin board, 3m long x 1,20m high for displaying plans and diagrams.
i) Acceptable lighting.
j) Acceptable air-conditioning unit of minimum 12000BTU output.
k) Two 220V 15A wall socket with computer extension sockets (1 to 4 type).
l) OZA File System or equal approved (12 Clips and 1 Movable holder) for storage of AO size
drawings.
Assistant Resident Engineer’s office – shall consist of one room with a floor area of at least 12m2
and a ceiling height of 2.5m.
Internal furnishings to include:
a) One trestle table, 2m long x 1m wide x 0.9m high, with a smooth top.
b) One desk of minimum dimensions 1,5m long x 0,9m wide with four drawers (two lockable).
c) One high stool.
d) One office swivel chair, one visitor’s chair.
e) A lockable upright steel cabinet with three shelves and a lockable steel filing cabinet with four
drawers.
f) Shoe cleaning mat at entrance.
g) An acceptable blind to each window.
h) A pin board, 3m long x 1,20m high for displaying plans and diagrams.
i) Acceptable lighting.
j) Acceptable air-conditioning unit of minimum 9000BTU output.
k) Two 220V 15A wall socket with computer extension sockets (1 to 4 type).
l) OZA File System or equal approved (12 Clips and 1 Movable holder) for storage of AO size
drawings.
Engineering Technicians’ office – shall consist of one room with a floor area of at least 16m2 and a
ceiling height of 2.5m.
Internal furnishings to include:
a) One trestle table, 2m long x 1m wide x 0.9m high, with a smooth top.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
126
b) Three desks of minimum dimensions 1,5m long x 0,9m wide with four drawers (two lockable).
c) One high stool.
d) Three office swivel chair, one visitor’s chair.
e) A lockable upright steel cabinet with three shelves and a lockable steel filing cabinet with four
drawers.
f) Shoe cleaning mat at entrance.
g) An acceptable blind to each window.
h) A pin board, 3m long x 1,20m high for displaying plans and diagrams.
i) Acceptable lighting.
j) Acceptable air-conditioning unit of minimum 12000BTU output.
k) Two 220V 15A wall socket with computer extension sockets (1 to 4 type).
l) OZA File System or equal approved (12 Clips and 1 Movable holder) for storage of AO size
drawings.
Meeting/boardroom – shall consist of one room with a floor area of at least 24m2 and a ceiling
height of 2.5m.
Internal furnishings to include:
a) One boardroom table, 4m long x 2m wide x 0.9m high, with a smooth top
b) 12 boardroom chairs.
c) Shoe cleaning mat at entrance.
d) An acceptable blind to each window.
e) A white board.
f) Acceptable lighting.
g) Acceptable air-conditioning unit of minimum 18000BTU output.
h) Four 220V 15A wall socket with computer extension sockets (1 to 4 type)
Kitchenette – shall consist of one room with a floor area of at least 9m2 and a ceiling height of
2.5m.
Internal furnishings to include:
a) Cupboard of 3m long x 1m wide x 1.1m high.
b) Crockery and cutlery sufficient for six people.
c) Shoe cleaning mat at entrance.
d) An acceptable blind to each window.
e) Acceptable lighting.
f) Two 220V 15A wall socket with computer extension sockets (1 to 4 type).
g) A 300l fridge.
h) A 20l microwave.
i) A suitable kettle.
j) A sink with cold water tap.
The Contractor shall also supply a toilet for the exclusive use of the Engineer’s Site Staff.
On completion of the works, ownership of the building and their furnishings shall revert to the
Contractor who shall remove them from the Site.
4. PLANT
4.1 TELEPHONE
No telephones shall be supplied by the contractor but the cost of the Engineer’s Site Staff mobile
phone monthly usage shall be paid by the Contractor as Detailed in PSA sub-clause 8.4.2.1 b).
5. CONSTRUCTION
5.5 SURVEY ASSISTANTS
The Contractor shall supply the following certified and calibrated equipment and staff:
Two suitably qualified and experienced survey assistants.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
127
One Engineer’s automatic level, carrying case plus tripod and telescopic levelling staff
(including levelling bubble attachment).
6 ranging staves graduated metrically.
Two plastic coated steel tapes of lengths 30m and 100m.
Levelling and tachometer books as required.
Cover meter capable of measuring within the specified tolerances
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
128
PS C SITE CLEARANCE
5.7 Append sub-clause 5.7 with the following:
During dis-establishment the contractor shall rehabilitate, including reseeding where necessary, the
portions of the works used for offices, laydown yards, laboratories, other works areas, etc.
5.8 Append sub-clause 5.8 with the following:
DEMOLITION OF STRUCTURES
a) Precast concrete barriers
There are two types of concrete barriers (upstream and downstream) shown on the drawings.
These barriers along with the coping will have to be removed.
The weights are as follows:
Coping – 300 kg/m
Upstream – 1 450 kg/m
Downstream – 1 200 kg/m
b) Concrete road screed
There is a concrete screed lightly reinforced (mesh Ref 194) to be removed.
c) Concrete bridge surface slab
The concrete bridge surface is a reinforced concrete structure bonded to the precast I beams.
There are several built in items which must be catered for (vents and shutter-boards).
Volume is 90 m3 (or 230 t)
The stabilising in-situ cross beams must be demolished.
Volume is 12 m3 (or 30 t).
The rubble must be prevented from falling onto the spillway ogee crest or into the lake.
d) Precast prestressed I beams
The precast prestressed I beams spanning the 7 x 13m openings will have have to be removed in
an orderly manner. (Note – The exact fixing to the main concrete lintel beam is unclear possibly
only the concrete bridge slab reinforcing)
No off = 42
Length = 14m (Approximate mass 10 t)
The rubble must be prevented from falling onto the spillway ogee crest or into the lake.
e) Concrete Lintel beam
The lintel beam is envisaged as a heavily reinforced concrete beam cantilevering out from the
abutments and the piers. There are expansion joints at the midpoint of each 13m beam.
The volume of concrete is approximately 750 m3 (or 1 850 t).
The demolition work must follow a strict procedure designed to limit the un-balancing of the
cantilevers and the Contractor will be required to submit a method statement that will indicate, inter
alia, the removal of equal sections alternatively on each side of the pier support.
The rubble must be prevented from falling onto the spillway ogee crest or into the lake.
f) Concrete piers and Abutments
The piers and sections of the abutments (minor) must be removed to top of ogee crest.
The volume of concrete is approximately 1 650 m3 (or 4 050 t).
The rubble must be prevented from falling onto the spillway ogee crest or into the lake.
g) Cut back on ogee spillway
This entails demolition and scabbling of ogee surface to create a suitable key for the PKW base.
The extent of the work is shown on the drawings.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
129
h) Cut trenches in existing dam wall structure
Cut trenches as indicated on drawings for embedment of ducts for electrical and telemetry
installation. These trenches will be either 100x100mm or 225x225mm and will be cut on top of the
dam wall or on the sloping face of the dam wall.
i) Cut pockets for precast anchor heads
These pockets are to receive the anchor live ends as detailed on the drawings.
j) Bore holes through concrete for PKW aeration system
Large diameter holes to be formed in the existing dam to provide aeration ducts for air entrainment
into water spilling over the PKW and new Roberts Splitters as indicated on the drawings.
8. MEASUREMENT AND PAYMENT
8.2 SCHEDULED ITEMS
8.2.8 Demolish and Remove Structures
The rates shall cover all costs to supply, set up and operate specialist equipment as well as any
temporary work to provide platforms from which to operate in order to demolish structures, break
out concrete or bore large diameter holes all described in Clause 5.8 above, with due care and skill
and in strict accordance with a detailed Method Statement to be provided by the Contractor for the
Engineer’s approval before demolition work commences. The rate shall also cover for the
demolition material is to be stockpiled within 1 km of the demolition site for disposal in accordance
with clause 8.2.9 below.
8.2.9 Transport materials and debris to unspecified sites and dump
All surplus material from the work items described in Clause 5.8 stockpiled in accordance with
8.2.8 above, will be sorted and disposed of as follows:
a) The larger portions of the demolished material will have all protruding rebar or other
embedments cut off and disposed of in accordance with the requirements of the EMP.
b) The large size concrete, cleaned of protruding rebar and embedments as described in a) above,
will be disposed of either:
i) At a designated area, within 2 kms of the stockpile, below the new Full Supply Level of the
dam
or
ii) At an approved Waste disposal facility.
c) The smaller particles of size less than 100mm will be separated out and carted to a licensed
dump site.
Application is in progress for a license to dispose of material as outlined in b) above. Should the
application be unsuccessful, all material will have to be removed from site and the quantity for c)
above will increase proportionally.
The rates tendered for the work will include all costs incurred in sorting, cutting, loading,
transporting and dumping and tip fees necessary for the disposal of the demolished material
stockpiled in terms of 8.2.8 above.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
130
PS G CONCRETE (STRUCTURAL)
3. MATERIALS
3.2 CEMENT
3.2.1 Applicable Specifications
Sections of the specifications listed in the Standard Specification have been superseded by new
specifications. The pertinent changes are indicated in the table below. For the superseded sections
of the listed specifications the new specifications will apply:
Description Superseded Code New Code
Cement: OPC, RHC SABS 471 SANS 50197-1
Cement: PBFC SABS 626 SANS 50197-1
Cement: PC15 SABS 831 SANS 50197-1
Cement: GBFS SABS 1491 Part 1 SANS 50197-1
Aggregate SABS 1083 SANS 1083
Drying shrinkage of aggregates SABS method 836 SANS 5836
Drying shrinkage of concrete SABS method 1085 SANS 6085
Aggregate size SABS 1083 SANS 1083
Sulphate content: Aggregates SABS 850 SANS 5850-1
Drilling cores SABS 865 SANS5865
Evaluate cores SABS 0100 Part ii SANS10100 Part 2
Load tests SABS 0100 Part ii SANS10100 Part 2
3.2.2 Alternative Types of Cement
Append sub-clause 3.2.2 with the following:
The blending of fillers (slag and fuel ash) on site will not be allowed unless written approval is
obtained from the engineer.
3.2.3 Storage of Cement
Append sub-clause 3.2.3 with the following:
All cement on the Works shall be fresh and of the best quality and cement which has been
damaged in any way or which has been stored on site for a period exceeding six weeks shall be
condemned and removed from site.
All cement should come from one approved manufacturing source. Cement cannot be supplied
from any different source without the prior approval of the Engineer.
3.4 AGGREGATES
3.4.2 Plums
The use of plums will not be allowed in reinforced concrete.
New item:
3.4.4 Supply of Aggregates
Append sub-clause 3.2.3 with the following:
New item:
3.9 ALKALI-SILICA REACTION
The Contractor is to ensure that the aggregates will not have a detrimental effect on the concrete
used on Site and all aggregate must comply with the requirements of SANS 1083. Certificates
stating the alkali content of each delivery of cement to Site shall be supplied by the Contractor.
4. PLANT
4.5 FORMWORK
4.5.3 Ties
Append sub-clause 4.5.3 with the following:
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
131
The bolt/feral holes shall be placed with regularity and precision and the tie irons must be removed
and calked completely in the case of water retaining areas.
5. CONSTRUCTION
5.1 REINFORCEMENT
5.1.3 Cover
Append sub-clause 5.1.3 with the following:
Fixing/Cover blocks for the attachment of fixtures may be embedded in concrete provided that the
strength is equivalent to the concrete mix being used and any other desirable feature (such as
appearance of the member) is not, in the opinion of the Engineer, impaired thereby.
The contractor must ensure the correct cover as specified is obtained.
5.2 FORMWORK
5.2.1 Classification of Finishes
Replace sub-clause 5.2.1 c) with the following:
c) Special. No special finishes
5.2.5 Removal of Formwork
New item:
5.2.5.6 The use of ‘low heat of hydration’ cements and/or fillers may require special consideration in the
stripping of the formwork and table 2 of SABS 1200G may not be applicable. The Contractor shall
provide a method statement for the removal of formwork prior to placing concrete containing such
cements and/or fillers.
5.5 CONCRETE
5.5.1 Quality
5.5.1.4 Chloride content
The maximum chloride content will be as specified in column 5 of Table 4 for reinforced concrete
exposed to marine environment
5.5.1.5 Durability
The water cement ration will be as per column 5 in Table 5 for moderate section; retaining walls,
piers, beams and exterior portions of mass concrete.
5.5.1.7 Strength Concrete.
Append sub-clause 5.5.1.7 with the following:
The concrete mixes shall be designed for vibration, heat of hydration, shrinkage and expansion
characteristics and the Contractor must demonstrate that the concrete mix design has adequately
addressed these issues.
Surface Bed strength concrete design requires concrete to achieve a minimum concrete strength in
72 hours and a minimum Modulus Ratio at 28 days.
5.5.3 Mixing
5.5.3.2 Ready mix concrete
Append sub-clause 5.5.3.2 with the following:
Should the Contractor propose the use of ready-mixed concrete, a motivation detailing with the
reliability of supply and travel time of the delivery trucks from the supplier’s yard to the Site must be
submitted for approval by the Engineer.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
132
5.5.7 Construction Joints
5.5.7.1 Replace items b) of sub-clause 5.5.7.1 with the following:
Construction joints are to coincide with contraction joints. The contractor must provide a method
statement prior to casting critical elements that includes the following information:
Casting sequences proposed.
Times between major pours.
Volumes of concrete to be poured.
Curing equipment to be used.
Supply of materials.
Means of ensuring that joints are water proof
5.5.7.4 Construction Joint between the Existing Concrete and New Concrete
In addition to the requirements of clause 5.5.7.3c the rate tendered shall allow for the following:
a) Insitu concrete surface is to be scabbled thoroughly to expose uncontaminated concrete
aggregate.
b) The scabbled surface is to be brushed with a wire brush to remove any loose aggregate.
c) The surface is to be thoroughly soaked for 24 hours before pouring of concrete.
d) The mortar applied immediately before placement of concrete must be treated with an approved
latex bonding agent used in accordance with the manufacturers requirements.
5.5.8 Curing and Protection
e) Curing compound shall be a must white resin based compound containing no water and
complying with ASTM C 309 and applied immediately after placing the concrete.
5.5.8.1 PKW Concrete
Replace items a) to e) of subclause 5.5.8 with the following:
The contractor will be required to supply, erect and maintain an approved fog spray irrigation
system to cover the whole structure. The system must have the facility to run on an automatic timer
and be able to provide the correct curing over a 24 hour period.
The system will be required during all the casting stages and must be maintained for a minimum
curing period of 14 days.
The contractor will only be permitted to place concrete once the system is functioning to the
approval of the Engineer.
5.5.11 Watertight Concrete
Append sub-clause 5.5.11 with the following:
The ‘Piano Key Weirs’ are to be considered as water retaining structures and the Contractor will be
responsible for ensuring water tightness in accordance with the requirement of the specification.
Appropriate specifications in DWS 0750: Water Retaining Concrete will also apply.
The works will not be certified complete until the units have been proved by testing to be watertight.
The structure will be considered water tight if there are no leaks or white carbonation marks on the
downstream surface of the structure.
5.5.13 Grouting
Append sub-clause 5.5.11 with the following:
Where grouting in of rebar dowels is specified on the drawings the following additional
requirements shall apply:
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
133
All dowels shall be installed in holes drilled into existing concrete structures in
accordance with the details shown on the drawings and secured by means of the
specified.
The holes should be 1.3 times larger than the prescribed fixing bar detailed for
optimum bonding or as prescribed by the epoxy / adhesive manufacturers
specifications.
The hole is to be cleaned thoroughly of dust and loose aggregate using
compressed air followed by water jetting or in accordance with the adhesive being
used.
The dowel bars must be fixed solid before concrete is cast. They will be tested by
the engineer prior to casting.
The contractor must allow in his tendered rate all wastage, health requirements,
machinery and materials required to mix the epoxy grout to manufacturer’s
requirements.
New Clause
5.5.16 Water Proofing of Joints
All joints formed in the PKW, whether indicated on the drawings or whether agreed to in terms of
the concrete placement method statement, must be water proof and the contractor is to supply
samples of all proposed sealers along with the relevant manufacturer’s details for approval.
Where water proofing by application of special measures is specified on the drawings such as in
the case of the installation of water bar for the expansion joints or where deemed prudent by the
Contractor as a necessary precaution and agreed to by the Engineer, the following will apply:
a) Use of water bar
The water bar must comply with the specifications of DWS 1810 in Volume 3 of this document.
The construction joints (or contraction joints) are shown on our drawings. These joints are
important with respect to the shrinkage of the concrete after casting. The final jointing drawings
with respect to water stops and construction procedures by the contractor must be produced by the
contractor for approval by the engineer. The technical support for the final jointing arrangements
must take into account the concrete design mix proposed, water stop supplier specifications,
standard details, jointing details and technical advice.
The water bar selected must take into consideration the existing water bar in the structure as it
must be bonded to the existing water bar in order to ensure continuous water proofing.
b) Swell-able Water-stops
The use of a swell-able water stop for providing an integral seal between new and old concrete will
be permitted in certain instances where waterproofing by this method is deemed to be appropriate
and as approved by the Engineer. In such applications the manufacturer’s specifications must be
strictly adhered to by the Contractor.
6. TOLERANCES
6.2 PERMISSIBLE DEVIATIONS
6.2.3 Append sub-clause 6.2.3 with the following:
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
134
Levels to top of PKW walls
The top of the end wall of the central inlet key shall be finished to an accuracy of 1mm in 3m of
length and 1mm tolerance with respect to the level specified. All other top levels must be finished to
Degree of Accuracy II but with no negative tolerance.
7. TESTS
7.1 FACILITIES AND FREQUENCY OF TESTS
7.1.2 Frequency of Sampling
7.1.2.2 Replace sub-clause 7.1.2.2 with the following:
At least two sets of samples shall be taken from each day’s casting and from at least every 50m3
of concrete of each grade placed.
The Contractor shall take additional sets of samples, at his own cost, to verify the concrete
strengths for stressing and formwork stripping of concrete pours for critical elements.
8. MEASUREMENT AND PAYMENT
8.4.3 Strength Concrete
a) 40/19 concrete to PKW
The rate must allow for the concrete to comply in all respects with best practice for water retaining
structures, the joint to be treated as specified in clause 5.5.7.4 above and for curing to be done in
accordance with 5.5.8.1 above.
b) 30/19 concrete to Emergency spillway topping slab
The rate must allow for the concrete to comply in all respects with best practice for thin slabs. The
joint between the old and new concrete must be treated as described in 5.5.7.4 above and the
curing must be carried out as specified in 5.5.8e of SANS 1200 G
8.5 JOINTS
Append clause 8.5 with the following
As appropriate the rates tendered will also cover the cost of complying with clauses 5.7, 5.8, 5.11
and 5.16 above.
Where cutting of joints is specified these joints are to be cut as soon as the concrete surface will
permit cutting and the rate will cover the cost of supply, delivery, use and operation of any plant
required, in addition to all other costs incurred for forming the joint.
8.6 MANUFACTURE AND PLACE PRECAST ELEMENTS
Append to Clause 8.6
The rate shall also cover the cost of securing in place and casting into the concrete any anchor
embedment items required (Cost of the embedment item to be included in the supply of the Rock
Anchor under Section GG) as well as the supply and casting in of the structural steel frame and lid
to be provided in accordance with the Drawings.
8.7 GROUTING
In addition to the provisions of Clause 8.7b in the standard Specifications the rate shall allow for the
additional provisions of 5.5.13 above.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
135
PS HA STRUCTURAL STEELWORK (SUNDRY ITEMS)
8. MEASUREMENT AND PAYMENT
8.3 SCHEDULED ITEMS
8.3.6 Replace sub-clause 8.3.6 with the following:
Corrosion Protection
The Rates for all items under Pay Reference 8.3 will include for Heavy Duty Hot Dipped
Galvanizing Corrosion Protection in accordance with the relevant clauses of the DWS 9900 C6
Specification, included in Volume 3 of this document.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
136
PS L PIPELINES
3. Materials
3.4 Steel Pipes, fittings and specials
3.4.3 Pipes of nominal bars over 150mm
Append to Clause 3.4.3
The provisions of specification DWS 1110: Construction of Pipelines will also apply.
The provisions of specification DWS 2510: Supply of Valves will also apply.
3.9 Corrosion protection
3.9.1 Steel Pipes
3.9.2.2 Steel Pipes of nominal bore over 150mm
Append to Clause 3.9.2.2
The provisions of specification DWS 9900: Corrosion Protection of Steel Pipes and Specials for
Pipelines will also apply.
8. Measurement and Payment
8.1 General
8.2 Scheduled Items
8.2.5 The rates tendered for items E1.1 a; b; c; d and e in the Bill of Quantities shall also allow for work to
be performed in accordance with the drawings and with clauses 3.4 and 3.9 above.
The rate tendered for item d) will allow for the supply of gate valves that comply in all respects with
DWS 2510 Supply of Valves - Particular Valve Specification – Gate Valves, included in Volume 3.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
137
C.3.3.2 Additions and Amendments to Standard Specifications Other Than SANS 1200
PS B1 Rock Anchor Specification
General introduction
The specification applies to the supply, installation, stressing and testing of 379 No. post-tensioned anchors
with a working load of 3400 kN.
The anchors are to be generally fabricated, installed, stressed and tested in accordance with BS8081:1989
Ground Anchorages. However, the purpose of this section of the document is to highlight project specific
aspects which shall be implemented by the specialist anchor contractor.
Definitions
Definitions are as defined in Section 2 of BS8081:1989. However, the term anchorage(s) will be referred to
as anchor(s) within this document.
4. RESPONSIBILITIES
Table 1. Recommended design and construction duties
Consultant Contractor
(1) Site investigation data for ground anchorages (1) Anchorage components and details
(borings near fixed anchor locations and outside the (2) Determination of fixed anchor dimensions
site working area if necessary). (3) Meet the requirements of Anchorage
(2) Decision to use ground anchorages, required trials spacing/orientation free anchor length and
and testing and provision of a specification anchorage loads
(3) Overall design of anchored structure, calculations (4) Detailing and performance of the corrosion
of anchorage force required. Definition of safety protection system for anchorage
factors to be employed. (5) Supply and installation of anchorage monitoring
(4) Definition of anchorage life and requirements for system
corrosion protection. (6) Quality control of works
(5) Anchorage spacing and orientation. Free anchor (7) Anchorage maintenance as directed by the designer
length and anchorage load.
(6) Anchorage behaviour monitoring system,
(structure/anchorages) and interpretation of results.
(7) Supervision of the works (inspection by testing and
sampling).
(8) Maintenance specification for anchorages.
(9) Instruction of all contracting parties of key items
within design philosophy to which special attention
should be directed.
In the event of the proving test anchors failing, the Client will not be held liable for costs incurred relating to the
delays while the Contractor redesigns the anchorage system and installs proving test anchors that do pass the
proving tests.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
138
6. DESIGN
6.1 GENERAL
Suitable safety factors are listed in Table 2 under the Anchorage Category of Permanent
Anchorages.
6.2 GROUND/GROUT INTERFACE
All anchorages are subject to a testing procedure as detailed in clause 11. Proving tests shall be
carried out to determine ultimate load holding capacity
8. CORROSION AND CORROSION PROTECTION
8.2 CORROSION PROTECTION
Due to permanent anchorages being installed and a maximum design life of the anchorages
warranted, a minimum of double corrosion protection is required on all anchorages.
Double protection implies the supply of two barriers where the purpose of the outer second barrier
is to protect the inner barrier against the possibility of damage during tendon handling and
placement. The second barrier therefore provides additional insurance, given the distinction
between the degree of protection of the tendon once installed in the ground, and that of the tendon
as supplied.
At the anchor head location, components cannot be wholly prefabricated. Because of the strain in
the tendon associated with prestressing, friction grips for strand and locking nuts on bars cannot fix
the tendon until extension has been achieved.
All existing locking arrangements require bare strand on which to grip and any preformed corrosion
protection of the tendon has to be removed. This leaves two sections of the tendon, above and
below the bearing plate, which require separate protective measures in addition to the protection of
the bearing plate itself.
10. CONSTRUCTION
10.2.4 Hole Geometry
The overall alignment and deviation should not exceed 1:300.
10.4 GROUTING
Provide for all grouting operations to be carried out under the personal direction of one or more
skilled supervisors experienced in similar work. The Designer may direct cessation of grouting at
any time when such supervision is not provided. It is desirable that the supervisor is experienced in
the successful handling of grout mixes with a W/C ratio of about 0.45: I by weight. The Designer will
advise the Contractor of the acceptability, or otherwise of his supervisor(s).
10.4.2 Borehole Testing
On completion of grouting it is necessary to ensure that the loss of grout over the fixed anchor
length is insignificant. This can be achieved by the use of tremie pressure injection techniques
during routine grouting of the anchor or alternatively by pre-testing for and/or providing a grout-tight
borehole over the fixed anchor length.
11. TESTING
11.2 PROVING TESTS
Proving tests will be required to demonstrate or investigate, in advance of the installation of working
anchors, the quality and adequacy of the design in relation to ground conditions and materials used
and the levels of safety that the design provides. The tests may be more rigorous than on-site
suitability tests and the results, therefore, cannot always be directly compared, e.g. where short
fixed anchors of different lengths are installed and tested, ideally to failure. In such cases where the
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
139
ground capacity is being investigated, loads are quoted in terms of characteristic strength of tendon
and the appropriate working load is deduced from the proving test results.
7 No. proving tests shall be carried out on site, in order to demonstrate the suitability of the
materials, components, methods of construction, workmanship and to establish the ultimate in situ
bond stress that can be mobilised in the vicinity of the fixed anchor zones.
1 no. through the spillway crest
1 no. through the emergency spillway crest
1 no. through the spillway downstream face
1 no. through the emergency spillway downstream face
3 no. directly into the underlying rock possibly accessed through the downstream side of the dam
On-site suitability tests are carried out on anchors constructed under identical conditions as the
working anchors and loaded in the same way to the same level. These may be carried out in
advance of the main contract or on selected working anchors during the course of construction. The
period of monitoring should be sufficient to ensure that prestress or creep fluctuations stabilize
within tolerable limits. These tests indicate the results that should be obtained from the working
anchors.
At least the first three anchors should be subjected to suitability tests with further tests for each
category of anchors envisaged in the works. Anchors are categorized by the following:
(a) Geometry, e.g. vertical or inclined;
(b) Ground types, e.g. clay, gravel or rock;
(c) Load capacity.
11.3.2 Proof Loads
The maximum proof load should be 150%Tw for permanent anchorages, where Tw is the working
load of the anchorage.
The maximum proof load shall be 80% of the characteristic strength of the tendon in proving tests
and 150% working load for permanent production anchors.
INFORMATION REQUIRED
The specialist anchor contractor shall provide a Method Statement giving details of the post-
tensioned anchors that are intended to be supplied and installed. Include details of clearances
required around anchor assemblies, grout tube size, experience with and achievability of the
specified grout mix and W/C ratio, details and dimensions of the proposed sheathings and the
tendon installation procedures. Note and outline any necessary changes to concrete and
reinforcement drawings. Provide details of the epoxy mortar for supporting the bearing plates.
Provide details of anchors head for approval. Supply design calculations and all other details
considered necessary by the Designer within 2 weeks of the award of the Contract. Acceptance of
the Method Statement by the Designer is a prerequisite to the start of the works. The Contractor is
also to provide their intended plans for substantial Quality Assurance and Quality Control within 2
weeks of the award of the Contract.
APPROVAL REQUIRED
Unless otherwise advised by the Designer, do not commence fabrication of the cables until
acceptance by the Designer of the Contractor's design calculations and all other important details
are obtained.
LOAD MONITORING
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
140
The DWA will monitor the performance of the anchors on completion of the Contract by periodically
measuring the loads in the anchors. The Contractor shall supply and install suitable load cells (or a
similar approved monitoring system) and associated equipment for this purpose which shall
comprise portable monitoring equipment for periodically checking the loads in selected anchors.
Load monitoring shall consist of a hydraulic pressure transducer load cell and other associated
equipment (or a similar approved monitoring system). The dimensions of the load cell shall be such
that it can be readily and easily moved to the anchor head location and can be accommodated in
the space around all post-tensioning anchor head assembly. The Contractor shall supply the load
cell complete with all necessary adaptor rings and saddles. Submission of details of proposals for
the load monitoring and transport system shall accompany the Tender submission.
The load cell and anchor head assembly so required to be supplied shall enable adjustment of the
anchor head level so that the tendon may be re-stressed by a minimum of 5% of MBL following
completion of the anchor head installation, stressing and trimming of excess strand. The anchor
head assembly arrangement shall provide for re-stressability of individual strands.
Equipment so required to be supplied shall measure the load in the cables to an accuracy of ± 2%
of the actual load. Demonstrate to the satisfaction of the Designer, on an anchor nominated by the
Designer, that the equipment is capable of measuring load to the required accuracy.
12 MEASUREMENT AND PAYMENT
12.1 GENERAL
The rates and pricing assume anchor types and forces as specified in the Drawings and Project
Specifications. The Contractor is at liberty to provide alternative design and stability anchor types
provided that all tests are performed as specified in clause 11 above and the loads specified are
provided in the equivalent position and inclination specified on the drawings.
12.2 SCHEDULED ITEMS
12.2.1 Drilling of 275mm diameter holes for Rock Anchors:
12.2.1.1 Set up at each position
The rate will cover for the design, erection and removal of all scaffolding and support work
necessary to create a platform capable of supporting the drilling rig in position to drill the hole,
crane requirements to place the rig on the platform and remove it afterwards, accurate positioning
of the drill rig and setting up of direction and inclination in order to drill the anchor hole in the
position indicated on the drawings and to the tolerance required..
12.2.1.2 Drilling of holes
The rate will cover drilling operations to drill the hole within the specified tolerances, water testing,
grouting and re-drilling as necessary, until the hole is to the correct depth and tolerance and water
loss under water test is within the specification.
12.2.2 Manufacture and assembly of 3.4 MN Rock Anchors
12.2.2.1 Anchor Heads
The rate will cover for the manufacture, supply and assembly of all components, including the
necessary supply of storage sheds and assembly beds and covering as required.
12.2.2.2 Strand, sheathing, corrosion protection etc for the free length
The rate will cover for the manufacture and supply of strand, fittings, corrosion protection materials
and sheathing, storage and handling on site, measuring and cutting of strand and assembly of all
components including corrosion protection, supply of assembly beds and covering as necessary.
12.2.2.3 Strand, etc, for fixed length
The rate will cover for the manufacture and supply of strand and fittings, storage and handling on
site, measuring and cutting of strand and assembly of all components including corrosion
protection, supply of assembly beds and covering as necessary per anchor.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
141
12.2.3 Transport and install 3.4 MN Rock Anchors
The rate will cover the supply and use of all equipment and plant required to transport the Rock
Anchors from the assembly beds to the position in which the anchor is required as well as inserting
the anchor into the hole already prepared.
12.2.4 Grouting in of fixed length
The rate will cover for the design, erection and removal of all scaffolding and support work
necessary to create a platform capable of supporting the plant and equipment required to perform
the grouting operations, all pipework and fittings to connect to the grout pipe in the anchor
assembly, supply and mixing of grout, pumping of grout, all as required, as well as crane
requirements to place the equipment on the working platform and to remove it afterwards.
12.2.5 Tensioning of Rock Anchors
The rate will cover for the design, erection and removal of all scaffolding and support work
necessary to create a platform capable of supporting the plant and equipment required to perform
the tensioning operations, the supply and operation of the tensioning plant and equipment, the
tensioning and locking off of anchors as required, as well as crane requirements to place the
equipment on the working platform and to remove it afterwards.
12.2.6 Corrosion Protection of Anchor Heads
The rate will cover the supply and application of all corrosion protection methods as specified in
terms of Clause 8 of BS 8081.
12.2.7 Testing of Rock Anchors
The rate will cover the coring of holes, assembly, installation and tensioning of Rock Anchors all as
described in 12.2 1 to 12.2.6 above inclusive of additional tensioning of anchors to test load as
specified in Clauses 10 and 11 of BS 8081 The rate will also cover the cost of making good
afterwards.
12.2.8 Monitoring of Anchors
As indicated in clause C.3.2.2 (d) above, the monitoring of the rock anchors is important throughout
the life of the anchors. The following items are included in the Bill of Quantities (BOQ) to allow for
this process on the basis of either monitoring a sample of anchors and all inaccessible anchors,
OR monitoring all anchors.
12.2.8.1 Anchors
a) The rate will cover the cost of supply, assembly and installation of the measuring and monitoring
equipment for each anchor.
b) The rate will cover the cost of supply, assembly and installation of the measuring and monitoring
equipment for each anchor in the event that it is decided to limit monitoring to a sample of
approximately 100 anchors.
12.2.8.2 Network
a) The rate will cover the cost of supply and installation of all hardware and software required to
provide a continual data record of the load in all the anchors for the lifetime of the anchors. Should
the proposed network be a wireless network, then the trenching in BOQ item B.1.2.8 will not be
required. Should a wired monitoring system be proposed, then the rate will include for the provision
and embedment of all ducting, wiring etc. in the trenches provided.
b) As for a) above in the event that monitoring is limited to a sample of 100 anchors.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
142
C.3.3.3 Other Particular Specifications
PARTICULAR SPECIFICATION B2: DRILLING 1. SCOPE ......................................................................................................................................... 143 2. DEFINITIONS ............................................................................................................................... 143 3. MATERIALS ................................................................................................................................. 143 3.1 General ........................................................................................................................................ 143 3.2 Water ............................................................................................................................................ 143 3.3 Drilling Fluid ................................................................................................................................ 143 3.4 Core Boxes .................................................................................................................................. 143 3.5 Casing Materials ......................................................................................................................... 144 3.5.1 General ........................................................................................................................................ 144 3.5.2 Core Holes ................................................................................................................................... 144 3.5.3 Drainage Holes ............................................................................................................................ 144 3.5.4 Grout Holes ................................................................................................................................. 144 4 PLANT .......................................................................................................................................... 144 4.1 General ......................................................................................................................................... 144 4.2 Rotary Core Drilling Equipment ................................................................................................. 144 4.3 Rotary Percussion (top hammer) Drilling Equipment .............................................................. 144 4.4 Rotary Percussion (bottom hammer) Drilling Equipment ........................................................ 145 5 CONSTRUCTION ......................................................................................................................... 145 5.1 General ......................................................................................................................................... 145 5.2 Drilling Rotary Core Holes .......................................................................................................... 145 5.3 Drilling Grout Holes .................................................................................................................... 145 5.4 Drilling Drainage Holes ............................................................................................................... 146 5.5 Drilling Holes through Concrete ................................................................................................ 146 5.6 Drilling Instrumentation Holes ................................................................................................... 147 5.7 Drilling Holes for Rock Dowels, Rock Bolts and Rock Anchors ............................................. 147 5.8 Storage of Cores ......................................................................................................................... 147 5.9 Handling of Cores ....................................................................................................................... 147 5.10 Marking Exploratory Holes ......................................................................................................... 147 5.11 Plugging of Holes ........................................................................................................................ 147 5.12 Drilling Records .......................................................................................................................... 148 6 TOLERANCES ............................................................................................................................. 148 6.1 General ......................................................................................................................................... 148 7 TESTING ...................................................................................................................................... 148 7.1 Standard Penetration Test ......................................................................................................... 148 8 MEASUREMENT AND PAYMENT .............................................................................................. 149 8.1 General Principles ....................................................................................................................... 149 8.1.1 Rotary Core Drilling .................................................................................................................... 150 8.2 Scheduled Items ......................................................................................................................... 150 8.2.1 Setting up over Holes ................................................................................................................. 150 8.2.2 Drilling .......................................................................................................................................... 150 8.3 Scheduled Items ......................................................................................................................... 151 8.4 Casing .......................................................................................................................................... 151 8.5 Core recovery ............................................................................................................................. 151 8.6 Core boxes .................................................................................................................................. 151 8.7 Standpipes for grout holes ........................................................................................................ 152 8.8 Grouting of holes for stabilization ............................................................................................ 152 8.9 Plugging of holes ....................................................................................................................... 152 8.10 Marking of exploratory holes .................................................................................................... 152 8.11 Standard Penetration Test (SPT) .............................................................................................. 152 8.12 Standby........................................................................................................................................ 152 FIGURES Figure 11.1 : Details of Core Box 125 Figure 11.2 : Labelling of Core Box 126
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
143
1. SCOPE
This specification deals with the drilling of holes for grouting, drainage, instrumentation and rock
support by means of rotary percussion methods and holes for geotechnical exploration by
means of rotary core methods.
The maintenance of accurate drilling records and the disposal of waste, the cleaning up of the
areas upon completion of the work and all other operations that are incidental to performing the
above operation also fall within the scope of this specification.
2. DEFINITIONS
The following definitions shall apply:
“Confined hole” : A hole drilled in any required direction above or below horizontal where an
immovable obstruction such as a wall or rock face would prevent a straight rod of 2,5m length
being inserted into the hole.
“Drainage hole” : A drainage or pressure relief hole is a hole required to relieve hydrostatic
pressure in the rock mass or concrete. It may be drilled from the surface or from a gallery,
through concrete or through a pipe embedded in the concrete for this purpose.
“Exploratory hole” : A hole drilled to obtain information about the ground conditions either by
recovering a cored sample of as much of the material drilled that is feasible and/or to only
recover drill cuttings and to provide access for the purpose of testing.
“Grout hole” : A hole drilled for the purpose of injecting grout into the ground.
“Instrumentation hole” : A hole drilled for the purpose of placing instruments in the structure, soil
or rock.
“Well-screened hole” : A hole, usually of large diameter drilled in soil or unconsolidated gravels
or boulders to be developed with filter gravel and a screened inner casing.
3. MATERIALS 3.1 General
Subject to the Engineer's approval of materials used, the Contractor shall make his own
arrangements for any materials required for the satisfactory completion of the work.
3.2 Water
Water used for drilling shall be clean and free from injurious amounts of acids, alkalis, suspended clay and other substances, which may have a detrimental influence on drilling performance or on the subsequent behaviour of the drilled hole when being tested for water loss or when being grouted.
3.3 Drilling Fluid
Drilling fluid shall only be used where previously agreed to by the Engineer and shall be such that it does not change the properties of the rock or soil or seal the inner wall of the hole. Bentonite and other similar drilling muds shall not be used.
3.4 Core Boxes
All core recovered from all boreholes shall be retained and carefully, neatly and securely packed in the correct sequence in approved core boxes, the design of which is given in Figure 11.1, so as to produce reliable record of the formation drilled. No core box shall contain core of more than one hole. The borehole number, depths of core and the box number shall be marked clearly, neatly and indelibly on boxes as specified in Figure 11A.2.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
144
Core boxes shall be of robust wooden construction to withstand the weight of core and any full boxes which may subsequently be placed upon them and also sufficiently watertight to protect the core from rain on Site or in transit. They shall be made to hold the particular size of core tightly in place in rows separated by securely fitted partitions. Core box lids shall be kept securely fastened to the boxes at all times except when inspected. A sample core box shall be submitted to the Engineer for acceptance prior to manufacture or placing of orders.
3.5 Casing Materials
3.5.1 General
All metal and uPVC pipes and fittings required for casings and standpipes shall be of the size matching the particular size of hole being drilled and shall be furnished, cut, threaded, fabricated and embedded by the Contractor.
3.5.2 Core Holes
Casings to support the sides of holes in caving ground shall be mild steel flush screw jointed tubes conforming to BS1387.
3.5.3 Drainage Holes
Casings to support the sides of holes in caving material shall be steel conforming to BS 1387 or uPVC conforming to SANS 966 and shall be Class 6.
3.5.4 Grout Holes
The casings required for grout holes shall be steel, conforming to BS 1387 or uPVC conforming to SANS 966 and shall be Class 6.
4 PLANT
4.1 General
All equipment shall be of the most modern type in good mechanical condition with adequate capacity and suitable for doing the work. Full details of all drilling equipment shall be submitted to the Engineer for approval before starting any drilling operation.
The Contractor shall provide and maintain all drilling machines and equipment needed for drilling the holes to the sizes and depths shown on the Drawings, in the Schedule of Quantities or in the Specifications.
The Contractor shall provide equipment capable of measuring the slope and direction of holes accurately to within 1 degree.
All drilling equipment shall be capable of drilling holes in compliance with the tolerances set out in Clause 11A.6 of this specification.
4.2 Rotary Core Drilling Equipment
Rotary core drills and associated equipment shall be capable of producing N and H size core from holes drilled in any direction and drilling 150mm diameter cored holes in concrete in any direction. Drills shall be equipped with hydraulic feed control and double tube core barrels. The equipment shall be capable of drilling and recovering core to a depth of 70m. Drilling equipment shall also be available to drill from a gallery with size 2,5m wide by 3m high.
4.3 Rotary Percussion (top hammer) Drilling Equipment
Rotary percussion type drills, using compressed air fed down hollow drill rods for the removal of
drill cuttings shall generally be used for drilling holes from 38mm diameter up to 100mm
diameter. The drills shall be capable of drilling holes at any angle to depths of 60m. Drilling
equipment shall also be available to drill from a gallery with size 2,5m wide by 3m high.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
145
4.4 Rotary Percussion (bottom hammer) Drilling Equipment
Not applicable.
5 CONSTRUCTION
5.1 General
Drilling, sampling and testing shall be performed in a workmanlike manner and only by
competent and experienced workmen. The Contractor shall submit details of the qualifications
and experience of the supervisors and operators he proposes to use to the Engineer for
approval before starting any drilling operation.
The Contractor shall ensure that no pollution of the Site or defacement of structures occurs as a
result of drilling operations.
The positions, directions, depths, sizes and inclinations of holes and the type of drilling equipment to be used shall be as indicated in these specifications, on the Drawings or as
directed by the Engineer. The Contractor shall set out all holes to be drilled.
All holes shall be drilled straight without deflection in the directions and at the inclinations
indicated.
Due allowance shall be made by the Contractor for interrupting the drilling to flush or pressure
wash the boreholes and to perform water pressure tests as specified in Section 11B, to survey
the boreholes if required in terms of the Contract or to rinse, flush or grout sections of boreholes
as specified in Section 11C.
5.2 Drilling Rotary Core Holes
Rotary core drilling may be required for grout holes, piezometers, exploratory work and for RCC
quality testing. Rotary core drilling shall only be performed as directed by the Engineer. The hole
size shall normally be N size (76mm diameter) for grouting and exploratory work, but may be
larger for piezometer installation (100mm diameter) and 150mm for RCC coring. Continuous
core recovery shall be obtained whenever possible in both hard and soft material.
5.3 Drilling Grout Holes
All holes for grouting shall be drilled by rotary percussion drilling methods in the sequence and
at the locations, in the directions, at the inclinations and to the depths and diameters shown on
the Drawings or ordered by the Engineer. Standpipes, nipples or casings set in the concrete or
rock shall generally only be required for grout holes in fractured and/or weak rock, where
surface water or debris can enter the top of the hole or as shown on the Drawings or instructed
by the Engineer.
Grout holes shall be drilled in stages conforming to the specified grouting stages using the split
spacing method. The spacing of the primary holes will depend on conditions encountered and
shall be as indicated on the Drawings or as directed by the Engineer, but in general they shall
be spaced at a distance of 8m for curtain grout holes. Sequential holes shall only be drilled at
the instruction of the Engineer.
The Contractor shall ensure that drill bits used to drill grout holes are in good order so that
excessive wear of bits will not cause wedging if at any time a hole has to be deepened.
Each hole drilled shall be protected from becoming clogged or obstructed by means of a screw
cap on the standpipe or other suitable device. Any hole that becomes clogged or obstructed
before completion of grouting shall be cleaned out in a manner to the satisfaction of the Engineer or another hole provided.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
146
Whenever drill water is lost, or artesian flow is encountered, the drilling operation shall be
stopped and the hole cleaned, pressure tested and grouted in accordance with the relevant
specification and to the instructions of the Engineer before drilling operations are resumed. The
grout so remaining in a partially completed hole shall be removed therefrom by flushing or other
methods before it has set sufficiently to require redrilling.
Where casings are used when drilling in caving ground such casings shall be supplied and installed by the Contractor in such a manner that easy removal of the casings is facilitated. All
casings shall be cleaned thoroughly of all dirt, grease or oil before embedment.
In situations where it proves impossible to install casings in caving ground with conventional
methods due to collapsing of the hole, the Contractor shall, with the approval of the Engineer,
use specialized drilling methods whereby the casing proceeds concurrently with drilling, such as
the "ODEX" method.
Where drilling through concrete placed in the Works is required, the Contractor may substitute
pipes of the appropriate diameter in lieu of such drilling, subject to the approval of the Engineer.
Where required by the Engineer and where conditions dictate, grout holes shall be provided with standpipes at the head of the hole. They shall project approximately 150mm above the rock or
concrete surface and shall be bonded firmly into the surface for a length of not less than
500mm. The bore of the standpipe shall be adequate to accommodate the size of drill bits
required.
All standpipes shall be cleaned thoroughly of all dirt, grease, grout and mortar before being
embedded in the concrete or rock.
The Engineer may order the drilling of a check hole(s) to determine the effectiveness of a
grouted section. Such a check hole shall be drilled as for a grout hole, but comprehensive water
pressure tests shall be performed according to Section 11B.
5.4 Drilling Drainage Holes
Unless otherwise directed, drainage holes shall be drilled by percussion drilling and flushed
clean. The holes shall be drilled to the diameter and in the direction, inclination and location as
indicated in the Drawings or directed by the Engineer.
Drainage holes shall not be drilled until all grouting required within the vicinity has been
completed to the satisfaction of the Engineer.
Drainage holes through concrete and rock shall be lined with an approved slotted PVC sleeve
where shown on the Drawings or directed by the Engineer.
5.5 Drilling Holes through Concrete
Where holes are required through concrete, the Contractor will be permitted to either drill the
holes or where indicated on Drawings or as instructed by the Engineer embed PVC sleeves in
the concrete through which the rock behind or below the concrete can be reached.
No drilling shall be allowed in concrete less than 7 days old.
In the case of reinforced linings, the formwork shall be marked by means of plugs or in some
other way approved by the Engineer to indicate positions where drilling may be carried out
without obstruction by reinforcement.
Should steel reinforcement be encountered during the drilling of any hole into concrete, where
required by the Engineer, drilling shall be discontinued immediately and a new hole shall be
drilled alongside. Such discontinued holes shall be plugged as specified in Section 11C.5.3.1(j).
Sleeves left in the concrete, but which have not been used for drilling holes shall also be
plugged.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
147
Holes of 150mm diameter in RCC as ordered by the Engineer shall also fulfil the requirements
of Section 6, Sub-clause 6.9.1.2 – RCC Coring Programme. 5.6 Drilling Instrumentation Holes
Unless otherwise directed, instrumentation holes shall be drilled by percussion drilling and
flushed clean. The holes shall be drilled to the diameter and in the direction, inclination and
location as indicated on the Drawings or directed by the Engineer.
Instrumentation holes shall not be drilled until all grouting required within 10m from the hole has
been completed to the satisfaction of the Engineer.
5.7 Drilling Holes for Rock Dowels, Rock Bolts and Rock Anchors
Unless otherwise directed, holes for rock dowels, bolts and anchors shall be drilled by
percussion drilling and flushed clean. The holes shall be drilled to the diameter and in the
direction, inclination and location as indicated on the Drawings or directed by the Engineer.
Water pressure tests shall be performed in such holes as directed by the Engineer.
5.8 Storage of Cores
A suitable storage facility for core boxes shall be provided on Site by the Contractor.
.
5.9 Handling of Cores
The core shall be removed from the core barrel by a method designed to produce minimal
disturbance to the core. Extraction under steady carefully applied pressure, the use of split inner
barrels or other method acceptable to the Engineer shall be used. The cores shall not be
extracted by hammering the barrel or by extrusion under high air or water pressure. Where the
core may be prone to slaking, the core shall be sealed in an appropriate plastic sheath.
Core shall be laid in the boxes in correct sequence clearly marked with wooden spacers, giving
the depth at any points of interest and marking all points of core loss.
5.10 Marking Exploratory Holes
When directed by the Engineer, exploratory holes shall be marked by means of a concrete block
and steel peg. The steel peg shall be of 16mm diameter, extend 50mm above the top of the
concrete block and be 300mm long. The concrete block shall be round with 300mm diameter
and 150mm into the ground surface and not protruding above ground surface.
5.11 Plugging of Holes
All exploratory holes drilled prior to construction and holes drilled during the Contract for
exploratory purposes and not used for any other purpose such as for grout or drainage holes,
shall be plugged, unless otherwise ordered by the Engineer. The Engineer shall identify and/or
locate the holes that need to be plugged and such plugging shall be carried out at an early
stage of the Contract, before the standpipes or identification marks are damaged by
construction activities.
All holes that have become clogged shall be cleared before being plugged. Where necessary
to clear the hole, rotary percussion equipment may need to be employed.
After the removal of standpipes or casings the holes shall be backfilled with a 1:1 mixture (by
volume) of cement and water. In dry holes the grout may be poured in from the top, but if the
hole contains standing water the grout shall be fed through a tremie pipe, the outlet of the
tremie pipe being kept submerged in the grout at all times. If running water is encountered in
the hole, the Engineer shall direct what procedure is to be followed.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
148
Grout holes shall be plugged according to Section 11C, Sub-clause 11C.5.3.1(j).
Where the hole, or portion thereof is in a concrete structure, it shall be backfilled with a 1:0,75
grout mixture (by volume) of cement and water upwards from the bottom of the hole so that all
water is replaced by grout.
5.12 Drilling Records
The Contractor shall each day provide the Engineer with an accurate record on forms approved
by the Engineer of all holes drilled on the previous day.
The information provided shall inter alia include the following :
a) The reference number, location of the hole, drilling method and stage of hole (where
applicable).
b) The actual positions of the boreholes recorded to an accuracy of 20mm and the actual
directions and inclinations of the borehole at the borehole collars recorded to within an
accuracy of 1 degree of arc.
c) A non-technical description of all materials encountered, their locations in the holes, the
material recovery for each stratum, changes in the formation (fissures, cavities, seams,
etc.) and any other data which may help in the evaluation of the ground.
d) Size and type of bits used.
e) Levels at which groundwater was encountered and wash-water lost or gained.
f) Drilling pressures and rotation speeds.
g) Any relevant incidents that occurred during the course of the work.
6 TOLERANCES
6.1 General
Unless otherwise indicated on the Drawings or in the Project Specifications, all holes to be
drilled shall be collared to a tolerance of 200mm of the specified position or 25% of the specified
distance between holes, whichever is the lesser. All holes shall be drilled to a tolerance of 3
degrees of the specified inclination and orientation. Where holes are drilled through mass
concrete, such as for grout holes, the holes shall be collared to a tolerance of 50mm of the
specified position and shall be drilled to a tolerance of 3 degrees of the specified inclination and
orientation. Nipples or sleeves set in concrete to act as guides for drilling shall be set in the
concrete to a tolerance of 30mm. The holes shall be drilled to within 0,5m of the specified final
depth.
7 TESTING
7.1 Standard Penetration Test
Standard penetration tests (SPT) shall be carried out in accordance with the international
reference test procedure laid down in the proceedings of the First International Symposium on
Penetration Testing (ISOPT) 1988 except that the number of blows for each 75mm of the total
450mm penetration shall be recorded. Prior to any SPT’s being carried out, the engineer shall
inspect and approve the equipment to be used.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
149
Before commencing the test, the borehole shall be cleaned to the depth where the testing is to
be done. Care must be taken to prevent disturbance of the material to be sampled. The washing
out of the hole by means of side discharge bits is allowable, but not by means of washing
through an open tube. Care shall be taken to ensure that the borehole is cleaned right to the
bottom of the hole in all circumstances. Where casings are used, the bottom end of the casing
shall be no closer than 150mm to the level where the tests are commenced.
When drilling in sand or silt below the water table, the water level in the casing shall always be
kept higher than the ground water level, so that sand and silt is kept from flowing into the
borehole. A valid SPT cannot be executed where an influx of sand or silt has occurred, since
such influx disturbs the materials under the base height of the casing, as well as causing greater
friction against the sample tube. When boring under the said conditions, water shall be
continuously added in order to maintain the water level in the casing level with the top of the
casing. Steady water supply is extremely important during the removal of the drilling rods since
removal is accompanied by a drop in level of the water in the hole. The rods must be removed
slowly and gradually.
Samples recovered from the split barrel sampler shall be sealed in an approved, airtight,
transparent container and placed in the core box at the relevant depth and the blow counts
written onto the sample container.
When it becomes evident that the SPT tests cannot be performed with the standard split barrel
sampler due to gravel or pebble layers, the driving shoe and the standard split barrel sampler
shall be replaced with a 60° cone-end shoe and a normal tube barrel, the overall dimensions of
which correspond to that of the standard split barrel sampler. The outside diameter of the cone-
end shoe shall be 51mm and the total length from tip to base shall be 56mm.
The test with the cone-end shoe shall in all other respects be executed in accordance with
ISOPT standards except that the number of blows for each 75mm of the total 450mm
penetration shall be recorded.
Care shall be taken to ensure that the energy of the hammer is not reduced by friction between
hammer and wall or by any other cause. “Refusal” of the SPT is defined as when the number of
blows necessary to penetrate 75mm exceeds 25. If refusal occurs, the blow counts recorded till
refusal and the actual penetration in mm for the last (refusal) cycle shall be recorded.
8 MEASUREMENT AND PAYMENT
8.1 General Principles
Specific items such as drilling and casings will be measured by length and classified by size,
making provision for various ground conditions. With the exception of casing, payment for
materials used shall be limited to those installed in the Permanent Works, which shall be
classified according to their nature and usage. Measuring of water levels as required from time
to time shall be covered by the various drilling rates.
No measurement for payment shall be made for the redrilling of any drilled hole due to wedging
caused by the excessive wear of drill bits. No measurement for payment shall be made for
providing another hole or for cleaning a drilled hole that becomes clogged or obstructed before
the completion of flushing, pressure washing, water testing, grouting, or borehole surveys.
Redrilling required of grout holes due to the Contractor's failure to clean out a hole before grout
in the hole has set, shall not be measured for payment, except in the case where the Engineer
has instructed the Contractor that the grout be allowed to set.
No measurement for payment shall be made for interrupting the drilling to flush or pressure
wash the boreholes and to perform water pressure tests, to survey the boreholes, or to flush,
rinse and grout sections of boreholes that are being drilled. In the case of grout holes the
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
150
Contractor would be entitled to additional measurement under Clause 11A.8.2.1 if the drilling
equipment has been moved, with the approval of the Engineer, to drill another grout hole while
grouting of the particular hole is in progress.
8.1.1 Rotary Core Drilling
The quantity to be paid for shall be the linear metre actually drilled to the satisfaction of the
Engineer. All measurements of depths drilled shall be measured from the point at which physical
drilling commences.
Consistency and Hardness
For measurement and payment purposes distinction shall be made between the consistency
and hardness of the materials drilled as follows:
Category A : All materials that can be augered.
Category B : Material (rock) that cannot be augered.
Gravel
Gravel shall be defined to be any hard aggregate of average dimension between 10mm and
50mm, with or without a matrix of loose material, and which moves during drilling, resulting in
difficult drilling, and where the hard aggregate occupies more than 30% of the volume of the
hole (measured per individual drill run).
Boulders
The definition shall be as for gravel but the average dimension shall be between 50mm and
300mm.
Inclined drilling
Payment for inclined holes shall be an extra over payment per metre of hole drilled.
Concrete drilling
Any drilling through concrete shall be measured under category B material. Where steel is
encountered in reinforced concrete, this shall be measured and paid for per millimetre
(measured as the diameter of the bar cut). Where a bar is cut more than once, each cut shall be
measured separately.
8.2 Scheduled Items
8.2.1 Setting up over Holes Unit: No
The rates shall cover all costs of setting out the hole position, setting up plant and equipment at
each hole and moving the same to the next hole, including for handling and transporting plant
and equipment, any excavation, or filling necessary for setting up platforms, and cleaning up on
completion of each hole.
Adjustment of the drilling equipment to deal with a number of angled holes at one position shall
not be regarded as separate setups.
Separate items shall be provided for different types of drilling equipment.
For holes to be drilled in stages conforming to the specified grouting stages, setup measurement
shall be made for each setup.
8.2.2 Drilling Unit: metre (m)
Measurement shall be the length of hole drilled as detailed on the Drawings or as instructed by
the Engineer. Distinction shall be made between percussion drilled holes, rotary core drilled
holes and the size of holes drilled.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
151
Separate items will be provided for: i) 0 – 25m depth
ii) 25 – 50m depth
iii) over 50m depth
The tendered rate shall cover the cost for drilling holes inclined at 0° to 30° to the vertrical, but
extra over payment items will be provided for drilling at inclinations to the vertical as follows:
i) 31° – 60°
ii) 61° – 90°
The rate tendered for percussion drilled holes shall cover all variations in strata encountered
(including mass or dental concrete) and the direction and inclination of the hole and include full
compensation for all labour, materials, including drilling fluid and work required to drill the holes
to the required depth.
The rate tendered for rotary core drilled holes shall cover all strata encountered and separate
items shall be specified for Category A and B materials, gravel and boulders. Drilling through
concrete shall be measured as Category B material. The rate tendered shall include the supply
and usage of all labour, materials (including drilling fluid), tools, equipment and plant to drill the
holes to the required depth.
Extra over payment items shall be specified for drilling in confined spaces such as galleries.
8.3 Scheduled Items Unit: metre (m)
Measurement shall be the length of hole redrilled where grout has been allowed to set on
instruction of the Engineer. Grouted holes redrilled on account of the Contractor’s failure to flush
out grout before it has set, shall not be measured. The redrilling shall be percussion drilled.
The tendered rate shall cover the cost for drilling holes inclined at 0° to 30° from the vertical.
Separate extra over items will be provided for drilling at inclinations to the vertical as follows:
i) 31° – 60°
ii) 61° – 90°
The rate shall include full compensation for all work required to redrill grouted holes, irrespective
of the depth of grouted hole.
8.4 Casing Unit: metre (m)
Measurement for payment for casings shall be for any type of drilled holes. No distinction shall
be made between installing casings in vertical or inclined holes. Distinction shall be made for the
drilling method used, size of hole, temporary and permanent casing.
The rates shall cover all costs for the supply and placing of all materials, labour, tools,
equipment and plant necessary to complete the work as specified in this Specification,
regardless of the depth to which casing is installed. No extra measurement for payment shall be
made for the use of drilling fluids or muds for the installation of casing.
8.5 Core recovery Unit: metre (m)
Measurement of core recovery in all types of material will be the length of core recovered from
the core barrel and placed in core boxes. The rates tendered for core recovery shall include full
compensation for special methods adopted during core drilling and core extraction to ensure
recovery of the greatest possible length of complete core and for placing in core boxes.
8.6 Core boxes Unit: No
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
152
Measurement will be by the number of core boxes required. The rate tendered shall include full
compensation for the supply to Site of core boxes, the temporary waterproof storage (if required)
on Site of boxes and cores and transport to permanent storage on site.
8.7 Standpipes for grout holes Unit: No
The number of holes, into which a standpipe is installed, shall be measured. The rate shall cover
all costs incurred in complying with the relevant requirements of Clause 11A.5.3.
8.8 Grouting of holes for stabilization Unit: kg
The weight of cementitious material approved or instructed by the Engineer as being necessary
for grouting of the sections of any hole for the stabilisation of unstable sidewalls shall be
measured. The rate shall include all costs for the supply of all materials, labour, tools, plant and
equipment, preparation and insertion of the grout. Redrilling through set grout shall be measured
in terms of the appropriate clause in this Specification.
8.9 Plugging of holes Unit: metre (m)
The total length of the holes which were plugged as instructed by the Engineer shall be
measured for the different hole sizes. The rate shall cover all costs for the supply of the
materials, labour, plant and equipment as well as the removal of all concrete caps and uPVC
pipes which were inserted in the exploratory holes. No distinction shall be made between
backfilling through a tremie pipe or from the top. Where it is required to redrill exploration holes,
setups and drilling shall be measured in terms of the appropriate clauses in this Specification.
8.10 Marking of exploratory holes Unit: No
The rate shall include all labour, materials, including cement, sand, 16mm steel rod, excavation,
mixing, placing, marking to supply and install the concrete block marker in accordance with
Clause 11A.5.10 of this Specification.
8.11 Standard Penetration Test (SPT) Unit: No
The rate shall cover all the costs to carry out and complete each SPT as ordered by the
Engineer according to Clause 11A.7.1 of this Specification.
8.12 Standby Unit: h
The unit of measurement shall be the time in hours that the different drill rigs or grouting
equipment are on standby as ordered by the Engineer to await the Engineer’s instruction to
complete the drilling/grouting or to be moved. The rate shall cover the cost of keeping the drill
rig, drilling personnel and other equipment and materials on standby. It shall not cover any time
during which plant and labour are standing by while tests or any other operations by the
Contractor that are necessary for the completion of the drilling are being carried out.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
153
Figure 11.1 – Details of Core Box
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
154
Figure 11.2 – Labelling of Core Box
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
155
PARTICULAR SPECIFICATION B3: WATER PRESSURE TESTING OF BOREHOLES
1. SCOPE ......................................................................................................................................... 156 2. DEFINITIONS ............................................................................................................................... 156 3. MATERIALS ................................................................................................................................. 156 3.1 Water ............................................................................................................................................ 156 4. EQUIPMENT ................................................................................................................................ 156 4.1 Water Pumps ............................................................................................................................... 156 4.2 Packers ........................................................................................................................................ 157 4.3 Gauges and Meters .................................................................................................................... 157 5 EXECUTION ................................................................................................................................. 157 5.1 General Procedures for Water Pressure Testing .................................................................... 157 5.2 Comprehensive Water Pressure Tests ...................................................................................... 158 5.3 Abbreviated Water Pressure Tests ............................................................................................ 160 5.4 Water Test Records .................................................................................................................... 160 6 TOLERANCES ............................................................................................................................. 160 7 TESTING ...................................................................................................................................... 160 8 MEASUREMENT AND PAYMENT .............................................................................................. 160 8.1 General Principles ....................................................................................................................... 160 8.2 Scheduled Items .......................................................................................................................... 161 8.2.1 Connections to drilled holes ...................................................................................................... 161 8.2.1.1 Connections for performing comprehensive water pressure tests using a single packer ............... 161 8.2.1.2 Connections for performing comprehensive water pressure tests using double packers ............... 161 8.2.1.3 Connections for performing abbreviated water pressure tests using a single packer .................... 161 8.2.1.4 Connections for performing abbreviated water pressure tests using double packers .................... 161 8.2.2 Comprehensive water pressure tests of 50 minutes duration ........................................................ 161 8.2.3 Comprehensive water pressure tests of 15 minutes duration ........................................................ 161 8.2.4 Extra over Clauses 11B.8.2.2 or 11B.8.2.3 as applicable for measuring the rate of fall of
water levels in boreholes ............................................................................................................... 161 8.2.5 Abbreviated water pressure tests .................................................................................................. 161 8.2.6 Extra over Clause 11B.8.2.5 for pressure washing of holes .......................................................... 161
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
156
1. SCOPE
This specification deals with performing:
a) comprehensive water pressure tests generally conducted in exploratory holes but also in
any other drill holes such as grout holes, and
b) abbreviated water pressure tests usually conducted in grout holes as part of the routine
testing procedures associated with grouting operations.
The disposal of waste water, keeping accurate daily records of all test results, the submission of
the test results to the Engineer on approved forms, the cleaning up of the areas upon
completion of the work and all other work incidental to the performance of the above operations
fall within the scope of this specification.
2. DEFINITIONS
The following definitions shall apply :
“Lugeon unit” : A water take of 1 litre per minute per metre length of hole tested at a pressure of 1MPa. For tests carried out at other pressures:
UL = water taken in pressure test (litre/metre/min) x 1000 P Where
UL = unit water loss in Lugeon units P = gauge pressure at borehole collar in kPa + (10 x ℓ x sin Ø) - pressure loss in drill rods Ø = angle of hole from horizontal ℓ = half length of stage + length of previous stage(s)
“Stage” : The portion of a hole that is to be drilled, water pressure tested and (where applicable)
grouted.
“Flushing” : The cleaning of a borehole by inserting a suitable pipe or tube down to the bottom of
the hole or stage and pumping in a mixture of air and water while moving the pipe up and down
until the wash water runs clear.
“Pressure washing” : The cleaning of seams and crevices containing clay or other materials by
pumping water into a borehole or section of a borehole sealed off by means of a packer(s) while
the water take is recorded at 5-minute intervals. Wash water is allowed to escape from surface
openings or adjacent, interconnecting boreholes and gives an indication whether fracture filling
is being removed.
3. MATERIALS 3.1 Water
Water used for water pressure testing shall be clean and free from injurious amounts of acids,
alkalis, suspended clay and other substances which may have a detrimental influence on the
water pressure test or on subsequent grouting operations.
4. EQUIPMENT 4.1 Water Pumps
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
157
The test pump shall be of the centrifugal type or of the positive displacement type capable of
delivering at least 100 litres of water per minute at a pressure of 1MPa measured at the
borehole collar. Where a positive displacement type pump is used an air vessel shall be fitted to
the pump with a size capable of limiting the range of pressure to 5% of the mean pressure.
4.2 Packers
Single and double packers or obturators at least 500mm long capable of sealing percussion or
rotary core drilled holes of any size between 100mm and 38mm, both sizes inclusive, at a
maximum pressure of 1MPa shall be available so that any section of a hole can be tested at any
stage of the drilling. The packers shall be of the pneumatic or hydraulic type or of soft
expandable rubber capable of sealing tightly against the sides of the hole, particularly when the
material is soft or friable to the extent that enlargement of the hole is unavoidable. The packers
shall be so designed that they can withstand the specified water pressure, to a maximum of
1MPa, without leakage. Mechanically expanded packers may be used at the top of the hole for
single stage testing if approved by the Engineer, but pneumatic or hydraulic packers shall be
used where the hole has to be sealed at depth.
4.3 Gauges and Meters
The water pressure gauges shall be precision instruments of durable construction, graduated to
read in increments of 10kPa and accurate to within 5%. Pressure gauges shall be oil actuated
and shall have a range of approximately twice the expected maximum pressure for the particular
borehole. The pressure gauges shall not be throttled to damp pressure surges and shall be
connected to indicate the water pressure at the borehole collar.
The water meter shall be of the integrator type accurate to within 2% for flows from 1,0 litres per
minute to 100 litres per minute. All water meters and pressure gauges shall be sealed and
calibrated by an approved hydraulics laboratory before use on the Site. If at any time during the
execution of the work the Engineer reasonably suspects that the equipment is defective, the
Contractor shall, if so ordered, have the same tested and recalibrated at an approved laboratory.
When water losses are small, or if the Engineer desires to check the water meter, the flow
recordings are to be supplemented by flow measurements taken from a specially calibrated
suction tank. The suction tank shall be kept on Site at all times.
Calibration of the water testing equipment shall be done whenever ordered by the Engineer by
determining the pressure loss at flows of 20%, 40%, 60%, 80% and 100% of the pump output
for various total rod lengths in increments of 10m up to the maximum depth of hole envisaged.
These calibration tests shall be done with the rods laid horizontally with pressure gauges
installed at both ends. A device for regulating the outflow of the water shall be provided at the
outlet end. The calibration shall be done in the presence of the Engineer, who shall prepare
diagrams of pressure loss versus flow for different rod lengths.
5 EXECUTION 5.1 General Procedures for Water Pressure Testing
(a) Supervision and Responsibility
The Contractor shall continuously supervise water pressure testing operations and measure and
regulate the pressures so that they are at all times in accordance with the Engineer's
requirements. The Contractor shall ensure that there is no damage as a result of performing
water pressure tests. Pressure washing operations shall only be performed in the presence of
the Engineer or his duly authorised representative.
(b) Cleaning Holes before Testing
Any stage or section of any hole to be water tested shall be cleaned immediately prior to water
pressure testing by flushing.
(c) Surface Leaks
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
158
Where surface leaks are excessive the Contractor shall plug such surface leaks as directed by
and subject to the approval of the Engineer, and shall ensure at all times that no rock
movements occur. The points of emergence of any water on the surface shall be noted, their
positions recorded and an estimate of the flow rate made.
5.2 Comprehensive Water Pressure Tests
Comprehensive water pressure tests shall generally only be performed if required by the
Engineer on sections of grout holes. The tests shall be conducted in rock or boulder formations,
provided that a tight packer seal can be achieved. Unless otherwise ordered, downstage testing,
using a single packer, shall be performed in sections of holes between 3m and 6m long and be
conducted after the completion of the drilling of each consecutive test length, and in any event
before correcting any caving. The test section shall be flushed to remove all drill cuttings before
commencing the test. In caving ground the upper portions of the hole shall all have been water
tested to the satisfaction of the Engineer prior to correcting the caving.
Specific sections of a hole shall be tested by using double packers if required by the Engineer.
The test length of such sections can vary depending on the circumstances but would generally
be between 0,5m and 12m long.
Comprehensive water pressure tests shall generally be conducted by performing five
consecutive tests, each of ten minutes duration per single test section so that :
- 1st 10-minute interval is at a low pressure .............................................................. (pressure A)
- 2nd 10-minute interval is at a medium pressure ..................................................... (pressure B)
- 3rd 10-minute interval is at a peak pressure ............................................................ (pressure C)
- 4th 10-minute interval is at a medium pressure ....................................................... (pressure B)
- 5th 10-minute interval is at a low pressure ............................................................... (pressure A)
The pressures to be applied are governed by the depth of the stage under test and by the
competency of the rock to withstand the pressure. Unless otherwise ordered by the Engineer,
the pressures A, B and C shall be as shown in the following schedule:
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
159
SCHEDULE OF TEST PRESSURES
DEPTH* OF (UPPER) PACKER
BELOW SURFACE (m)
SURFACE PRESSURE (kPa)
A B C
1,0
2,0
3,0
4,0
5,0
6,0
9,0
12,0
15,0
18,0
21,0
24,0
27,0
30,0
33,0
36,0
39,0
42,0
45,0
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
2.0
3,0
4,0
5,0
6,0
9,0
12,0
15,0
18,0
21,0
24,0
27,0
30,0
33,0
36,0
39,0
42,0
45,0
60,0
10
20
30
35
45
55
80
110
135
165
195
220
255
280
310
340
350
350
350
15
30
50
65
80
95
140
190
240
285
340
390
440
490
545
595
640
690
700
25
45
70
90
115
135
200
270
340
405
485
555
630
700
780
850
915
985
1 050 (max)
*Depth (D) of packer in inclined holes to be determined by : D = d x sin ø where d = length of borehole at packer position ø = angle of hole from horizontal. The water level within the borehole shall be measured before commencing the test. The Engineer may from time to time require that the borehole above the packer be filled with water during testing to observe if a possible rise of the water level occurs, indicating that the packer has not sealed effectively. If the loss of water due to rock fracturing is such that the required pressure cannot be obtained, the test shall be conducted at the highest pressure that the equipment is capable of producing in that particular test section. The test shall then be performed for 15 minutes while the pressure and water take are recorded at 5-minute intervals. If ordered by the Engineer, the Contractor shall fill the hole with water and observe the rate of fall of water levels as directed by the Engineer. The pressures applied and the sections to be tested are all subject to variation by the Engineer in order to obtain the maximum information from each test. Should any difficulty be experienced with the water pressure testing or any particular section of a hole the Engineer shall be informed immediately in order to decide what action must be taken. In general if a test section cannot be properly sealed the packer(s) shall be moved to the position(s) used for the previous successful test and the two sections tested together at pressures equal to those used in the previous test. The Contractor shall in such instances obtain from the Engineer instructions as to what further testing (if any) must be performed. The accuracy of the individual water pressure tests and of the sealing of the packers shall be checked at regular depth intervals to be decided by the Engineer, but shall generally be conducted by performing check water pressure tests on sections of hole approximately 12m long. The Engineer shall be informed immediately of the results of the check water pressure tests if these differ by more than 10% from the results of the sum of the individual water
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
160
pressure tests. Where the length of hole not yet subjected to a check water pressure test exceeds 3,0m and it becomes necessary to correct caving, a check water pressure test shall be performed before correcting any caving.
5.3 Abbreviated Water Pressure Tests
Unless the Engineer requires that a comprehensive water pressure test be conducted in accordance with this specification, an abbreviated water pressure test, as described hereinafter, shall be conducted on each stage or section of every curtain grout hole immediately prior to grouting that stage or section. If so ordered by the Engineer to establish the effectiveness of the grouting operation, abbreviated water pressure tests of grouted holes shall be performed, but not before at least 6 hours has elapsed after grouting has been completed.
The test section shall be flushed to remove all drill cuttings before commencing the test. Water shall then be pumped into the hole or stage or section of hole ordered by the Engineer until the pressure rises to 100kPa at the collar of the hole. A lower pressure shall be applied if directed by the Engineer in areas of possible rock movement. The pressure shall be maintained constant for 15 minutes and the rate of flow shall be measured and recorded at 5-minute intervals. If the leakage is too great to enable the specified pressure to be attained then the discharge of the pump shall be maintained at a constant rate for 10 minutes at the maximum output of the test pump and be recorded, while the pressure in the hole is measured and recorded at 2-minute intervals.
The unit water loss in Lugeon units shall be calculated and recorded by the Contractor for each time interval of the test.
In the case where increasing water takes for a specific test section are measured, and where connection to adjacent holes has been established, the Contractor shall inform the Engineer or his authorised representative before removing the packer(s). Under such circumstances and if directed by the Engineer the Contractor shall pressure wash the relevant test section. Such pressure washing shall be performed in the presence of the Engineer or his authorised representative, using such pressures and for such durations as may be directed.
5.4 Water Test Records
The Contractor shall each day provide the Engineer with an accurate record of all comprehensive and abbreviated water tests on forms approved by the Engineer. The forms shall inter alia make provision for recording the borehole number, section tested, date and time of test, the duration of the test, test pressures, measured water loss, unit water loss (UL) in Lugeon units, the water level prior to testing and any general remarks. Aspects such as surface leaks, ineffective packer sealing and any sudden changes in pressures and water takes shall also be recorded.
6 TOLERANCES
Not applicable. 7 TESTING
Not applicable. 8 MEASUREMENT AND PAYMENT 8.1 General Principles
Water pressure testing in boreholes shall be measured by the number of tests satisfactorily performed and for which complete records have been produced. The rates for pressure testing shall include for the cleaning up of the areas upon completion of the work, for measuring water levels prior to testing, for flushing the test section prior to testing and shall include for all costs in connection with the keeping of records. The payment for testing and recalibration of equipment shall be determined in accordance with the provisions of the General and Special Conditions of the Contract.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
161
No additional payment for the water used for the execution of water pressure tests shall be made. The Contractor shall be entirely responsible for damage as a result of errors that he may make in performing water pressure tests and shall at his own cost repair such damage.
8.2 Scheduled Items
8.2.1 Connections to drilled holes
The rates for payment shall cover all costs for connections to drilled holes for water pressure testing purposes. Separate items shall be provided for the different types of tests, but no distinction shall be made between different hole diameters.
8.2.1.1 Connections for performing comprehensive water pressure tests using a
single packer Unit: No
The number of connections shall be measured. A connection shall be measured once only for each test section of a borehole regardless of the number of times the packer is adjusted or reseated.
8.2.1.2 Connections for performing comprehensive water pressure tests using
double packers Unit: No
The number of connections shall be measured. A connection shall be measured once only for each test section of a borehole regardless of the number of times the packers are adjusted or reseated.
8.2.1.3 Connections for performing abbreviated water pressure tests using a
single packer Unit: No
The number of connections shall be measured. A connection shall be measured once only for each test section of a borehole regardless of the number of times the packer is adjusted or reseated.
8.2.1.4 Connections for performing abbreviated water pressure tests using double
packers Unit: No
The number of connections shall be measured. A connection shall be measured once only for each test section of a borehole regardless of the number of times the packers are adjusted or reseated.
8.2.2 Comprehensive water pressure tests of 50 minutes duration Unit: No
The number of separate comprehensive water pressure tests of 50 minutes duration which are satisfactorily performed, shall be measured.
8.2.3 Comprehensive water pressure tests of 15 minutes duration Unit: No
The number of separate comprehensive water pressure tests of 15 minutes duration which are satisfactorily performed, shall be measured.
8.2.4 Extra over Clauses 11B.8.2.2 or 11B.8.2.3 as applicable for measuring
the rate of fall of water levels in boreholes
Unit: h
The duration for which the Engineer has ordered the observation and measurement of the rate of fall of the water levels to continue per borehole, shall be measured regardless of the number of measurements.
8.2.5 Abbreviated water pressure tests Unit: No
The number of separate water pressure tests, which are satisfactorily performed, shall be measured. No distinction shall be made between tests of 15 minutes and of 10 minutes duration.
8.2.6 Extra over Clause 11B.8.2.5 for pressure washing of holes Unit: h
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
162
The duration ordered by the Engineer for washing holes under pressure shall be measured regardless the pressures used.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
163
PARTICULAR SPECIFICATION B4: GROUTING
1. SCOPE ......................................................................................................................................... 164 2. DEFINITIONS ............................................................................................................................... 164 3. GROUT ......................................................................................................................................... 165 3.1 General ........................................................................................................................................ 165 3.2 Materials ...................................................................................................................................... 165 3.2.1. Cementitious Materials .............................................................................................................. 165 3.2.2. Water ............................................................................................................................................ 166 3.2.3. Sand ............................................................................................................................................. 166 3.2.4. Chemical Grouts ......................................................................................................................... 166 3.2.5. Bentonite ..................................................................................................................................... 166 3.2.6. Additives and Admixtures ......................................................................................................... 166 3.2.7. Grout Mix ..................................................................................................................................... 166 4. PLANT AND EQUIPMENT .......................................................................................................... 167 4.1. General ........................................................................................................................................ 167 4.2. Grout Pumps ............................................................................................................................... 167 4.3. Mixers .......................................................................................................................................... 167 4.4. Water Storage Tank .................................................................................................................... 167 4.5. Gauges and Meters .................................................................................................................... 168 4.6. Packers ........................................................................................................................................ 168 4.7. Supply and Return Lines and Grouting Pipes, Hoses and Fittings ...................................... 168 4.8. Bentonite Mixers ......................................................................................................................... 168 4.9. Measuring Equipment for Trial Mixes ...................................................................................... 169 5. CONSTRUCTION ......................................................................................................................... 169 5.1. General ........................................................................................................................................ 169 5.2. Drilling Grout Holes .................................................................................................................... 170 5.3. Standard Grouting Methods ...................................................................................................... 170 5.3.1. General Procedure for Grouting ............................................................................................... 170 5.3.2. Specific Procedure for Curtain Grouting ................................................................................. 173 5.3.3. Specific Procedure for Consolidation Grouting ...................................................................... 175 5.4. Specialised Grouting Methods .................................................................................................. 175 5.4.1. General ........................................................................................................................................ 175 5.4.2. Tube-a-manchette (TAM) Grouting Method ............................................................................. 176 6. TOLERANCES ............................................................................................................................. 176 7. TESTING ...................................................................................................................................... 176 7.1. Density (Mud Balance) ............................................................................................................... 176 7.2. Viscosity (Marsh Cone) .............................................................................................................. 177 7.3. Bleeding ....................................................................................................................................... 177 7.4. Test Cubes .................................................................................................................................. 177 8. MEASUREMENT AND PAYMENT .............................................................................................. 178 8.1. General Principles ...................................................................................................................... 178 8.2. Scheduled Items ......................................................................................................................... 178 8.2.1. Grout Connections to Drilled Holes ......................................................................................... 178 8.2.2. Grouting ....................................................................................................................................... 178 8.2.3. Materials used in all Grouting Operations ............................................................................... 178 8.2.3.1. Cementitious material ................................................................................................................ 178 8.2.3.2. Sand ............................................................................................................................................. 179 8.2.3.3. Additives ...................................................................................................................................... 179 8.2.3.4. Chemical grouts ......................................................................................................................... 179 8.2.4. Grout Cap .................................................................................................................................... 179 8.2.5. Rinsing drilled holes .................................................................................................................. 179 8.2.6. Tube-a-manchette (TAM) grouting ............................................................................................ 179 8.2.7. Density (Mud Balance) Test ....................................................................................................... 179 8.2.8. Viscosity (Marsh Cone) Test ..................................................................................................... 179 8.2.9. Bleed Test .................................................................................................................................... 179 8.2.10. Test Cubes .................................................................................................................................. 179
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
164
1. SCOPE
This specification deals with the construction of a grout curtain along lengths of the dam
foundation, performing consolidation grouting of the rock below highly stressed parts of the
foundation and the final plugging of grout holes, in accordance with the Drawings or instructions
of the Engineer.
The work shall consist of flushing grout holes, making grout connections, supplying, mixing and
injecting grout into holes, disposing of waste water and grout, cleaning up of the areas upon
completion of the work and all such other operations as are incidental to grouting.
2. DEFINITIONS
The following shall apply :
“Cavity grouting” : Grouting to fill any voids in rock/concrete or first stage/second stage
concrete interfaces around structures.
“Cement” : All cementitious materials including pozzolans and pseudo pozzolans.
“Consolidation grouting” : Grouting to improve the quality of the rock mass, over an area, by
injecting grout through rows of holes of generally shallow depth. Where the grouting is
performed through concrete, consolidation grouting includes grouting of the contact between the
concrete and the rock mass.
“Contact grouting” : Grouting of embedded steel to fill any voids at steel/concrete interfaces.
“Curtain grouting” : Grouting a row or rows of holes in the rock mass to create a continuous
impervious curtain of grout.
“Depth” : The distance from the mouth of the hole regardless of direction.
“Downstage grouting” : The process of drilling a hole to a limited depth (stage), grouting to
that depth, either washing out the grout hole after the injected grout has attained its initial set or
redrilling through grout in holes that are not flushed after grouting, drilling the hole to a further
depth after the specified length of adjacent grout curtain for the particular stage has been
completed and also after at least 24 hours has elapsed since grouting the previous stage and
then grouting the further depth (next stage). Thus the hole is successively drilled and grouted
until the required depth is completely grouted to the satisfaction of the Engineer.
Downstage grouting can further be subdivided into:
(a) Grouting of each stage with the packer set at the surface. This shall include for a hole
which is completely grouted from bottom to surface in one operation.
(b) Grouting each stage with the packer set at the bottom of the previous stage.
“Grout cap” : A concrete cap constructed along the line of the curtain grout holes and
embedded into the rock, usually in areas where the surface rock is weak or is highly fractured.
“Grout take” : Grout take is the consumption of cement by mass (kilogram) per metre length of
a hole.
“Rinsing” : The circulation of clean water in boreholes to prevent the clogging of such open
boreholes due to the ingress of grout.
“Stable cement grout” : A homogeneous balanced blend of water and cement combined with
selected additives and admixtures to produce a product with minimal bleed, low cohesion and
good resistance to pressure filtration.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
165
“Stage” : A portion of a hole that has been drilled and is to be grouted. The depths of the
grouting stages shall be as indicated on the Drawings, or directed by the Engineer.
“Upstage grouting” : The process of drilling a hole to full depth initially and grouting from the
bottom of the hole upward at different depths by means of a packer set at different depths.
Upstage grouting shall be performed by attaching a packer to the end of the grout supply pipe,
lowering the grout supply pipe into the hole to the top of the lowest section to be grouted,
expanding the packer, grouting at the required pressure, allowing the packer to remain in place
until there is no back pressure, withdrawing the grout supply pipe to the top of the next higher
section to be grouted and thus successively grouting the hole in sections at the specified
pressures until the entire hole is completely grouted.
3. GROUT 3.1 General
Grout shall generally consist of a suitable mixture of a homogeneous balanced blend of cement,
additives, admixtures and water that comply with this specification. No lumps shall be permitted
in the grout mixture. All grout mixtures specified in this specification shall be by volume and shall
be batched by volume unless batching by weight is approved by the Engineer.
Where grout is required to fill large cavities the Contractor shall obtain the Engineer's
instructions regarding the possible use of a filler, such as sand that complies with this
specification. The use of admixtures to control the rate of setting of the grout shall be subject to
the approval or direction of the Engineer. The proportions of cementitious material, water and
sand and any admixtures used shall be as approved or directed by the Engineer and shall be
varied to meet the characteristics of each hole as determined by conditions encountered from
time to time.
Grout that has not been injected within two hours after mixing shall not be used for grouting, and
shall be disposed of as directed.
The method of batching shall be such that the ingredients are proportioned to an accuracy of
within 5%. Where sand is added to the grout, frequent bulking and moisture content
determinations shall be made and the necessary adjustments made to the batching proportions.
Prior to introducing the mixed grout into the grout circuit, it shall be mixed for at least 5 minutes,
as measured from the instant when all the ingredients have been added.
3.2 Materials
3.2.1. Cementitious Materials
Cement shall be either CEM 1 Class 42.5 N Ordinary Portland Cement (OPC) or CEM 1 Class
42,5N Rapid-hardening Cement (RHC) or CEM 1 Class 52,5N (RHC), all complying with the
requirements of SANS 50197-1 and passing a 0,090mm sieve, while not more than 10% shall
be retained on a 0,045mm sieve. The Blaine fineness shall be greater than 440m²/kg. RHC shall
only be used where the Engineer is of the opinion that improved grout injection can be achieved
due to the greater fineness of the cement. In the event that cement is found to contain lumps of
foreign matter of a nature and in amounts which in the opinion of the Engineer may be
deleterious to the grouting operation, screening through a standard No 100 square mesh screen
may be required.
All cementitious materials shall be obtained from approved sources. Bagged cementitious
material shall not be stored for longer than 30 days and shall be delivered in 50kg multi-walled
paper sacks. The volumes of standard 50kg sacks of cementitious materials shall be determined
by the Contractor in the presence of the Engineer for each type of cementitious material.
Separate storage facilities shall be provided on Site for each type of cementitious material used. During transportation, storage and at the place of the grouting activity, all bagged cementitious
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
166
materials shall be kept covered to provide proper protection against moisture and other factors that may promote deterioration of the materials. Sheds for the storage of bagged cementitious materials shall be dry, well ventilated, weatherproof and watertight. The bags shall not be stored or placed in contact with the floor or ground. The Contractor shall provide sufficient storage capacity to cater for at least one week's peak production of grouting.
3.2.2. Water
The water used in the grout and in the work described in this specification shall be fresh, clean and free from suspended matter and injurious amounts of oil, acid, alkali, salts, organic matter
and other substances that may impair the strength and durability of the grout. The Contractor shall provide an adequate water supply, from an approved source, in order that all operations necessary for performing the work described in this specification, such as drilling, pressure washing, rinsing, water pressure testing, flushing and grouting can be performed at the maximum efficiency.
3.2.3. Sand
Sand shall be from a source approved by the Engineer and shall comply with the relevant requirements of SANS 1083 for sand for concrete, shall be washed as necessary and thereafter screened to pass a 300 micron sieve.
3.2.4. Chemical Grouts
In special circumstances the use of proprietary grouts of a non-cementitious nature may be approved or ordered by the Engineer. Such grouts shall be handled, stored, mixed and injected in strict conformity with the manufacturer's instructions.
3.2.5. Bentonite
Bentonite shall be of approved manufacture and shall consist of pulverised natural sodium montmorillonite clay supplied in free-flowing granular form and shall comply with the relevant requirements of API SPEC 13A. The Contractor shall submit the results of tests performed, by a laboratory approved by the Engineer, in accordance with API SPEC 13A on each consignment of bentonite delivered to Site to confirm its compliance with the specified requirements. Peptised or other specially treated bentonite shall not be used.
Bentonite shall be delivered to Site in sacks not exceeding 50kg by mass and shall be stored in a shed that complies with the requirements specified in Clause 11C.3.2 of this specification for cementitious materials.
3.2.6. Additives and Admixtures
Admixtures such as plasticisers, accelerators, retarders, thixatropic agents and anti-washout agents may be used only with the approval of the Engineer. In support of the request to use additives and admixtures, the Contractor shall submit the results of relevant laboratory tests that have been performed on site with the grout materials that will be used to demonstrate the effectiveness and advantages of the product(s). Unless the chemical composition of such products is made known, such products will not be acceptable for use in the grout. Additives and admixtures used shall comply with AST C-494, AASH M-54 or BS 5075.
3.2.7. Grout Mix
The grout mix is specified as the ratio of water : cementitious material by volume. The grout mix design shall ensure that only stable grouts will be used. The permeability of the foundation rock as determined by water pressure tests may require that grouting may be started with a thinner grout mix, which can be thickened as grouting proceeds. Acceptable grout mixes will normally
be allowed to vary between water : cement ratios of 2 : 1 and 0,6 : 1. Other grout mix parameters shall be as follows:
Bleed : <5% at 2 hours
Apparent viscosity : Maximum 60 seconds (Marsh Cone)
Strength : Minimum 25MPa cube strength at 28 days
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
167
The contractor shall perform sufficient laboratory tests on the grout mix proportions for acceptance by the Engineer before any grout operations will be allowed to commence.
4. PLANT AND EQUIPMENT 4.1. General
All grouting equipment shall be of the most modern type with adequate capacity, in good mechanical order and suitable for doing the work. All equipment shall be satisfactorily maintained to ensure continuous and efficient performance during all grouting operations. Any grout hole that is lost or damaged due to mechanical failure of equipment or inadequacy of grout supply shall be replaced by another hole drilled by the Contractor. The equipment available shall be capable of grouting all sizes of hole between 100mm and 38mm, both sizes inclusive. Adequate measures shall be provided to protect the equipment and materials from damage of
whatever nature. The grout lines shall be the shortest practical to prevent wastage of materials, high pressure drops or clogging of the lines. Adequate compressor capacity for the optimal performance of air driven equipment shall be provided. Prior to commencing any grouting, the Contractor shall submit to the Engineer for his approval full details of his proposed plant and equipment and also of the proposed layout of the plant. The Contractor shall at all times during grouting operations have 100% standby equipment of all types available to ensure that grouting operations can be continued without significant interruptions caused by breakdowns of equipment.
4.2. Grout Pumps
Grout pumps shall be of the positive displacement, centrifugal or the helical rotor type. Stand-by
pumps shall be available on Site during grouting operations. Pumps shall be equipped with
quick acting lubricated plug valves, an accurate pressure gauge and a bypass from the pump
discharge to the tank or inlet to the mixer. A screen having square openings of 3mm size shall
be provided at the intake of the pump, and all pumps shall have interconnecting pipes and
valves to permit the immediate transfer, if necessary, to stand-by equipment so that there will be
no interruption in the flow of grout to a hole that is being injected.
Grout pumps shall be capable of injecting grout at a rate of between 50 litres per minute and
100 litres per minute at a pressure of double the grout injection pressure shown on the
Drawings. The rate of pumping shall be readily and accurately adjustable from zero flow to the
maximum capacity, and equipment shall be such that grout consistency can be adjusted without
causing an interruption in the flow, which could result in setting of the grout before pumping is
resumed. Pumps shall be fitted with preset relief valves.
4.3. Mixers
Grout mixers shall be either air or electrically powered, and shall be single or double
compartment high speed (minimum 1200rpm) colloidal mixers that are capable of supplying a
continuous flow of well mixed grouting ingredients. The mixers shall be provided with a device
for accurately measuring the volume of mix water in litres. Where a single compartment mixer is
used, a sump tank equipped with mechanical agitators to keep the cementitious materials in
suspension shall be provided to ensure an uninterrupted supply of well mixed grout to the point
of injection. Mixers shall be of sufficient capacity to ensure that the grout pumps can be supplied
at their maximum pumping capacity.
4.4. Water Storage Tank
A tank of sufficient capacity and adequate bypass pipes and fittings for auxiliary water supply
shall be available to be used for water pressure testing, flushing and pressure washing
operations.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
168
4.5. Gauges and Meters
Pressure gauges shall be installed at the collars of all holes being grouted and at the grout
pump outlet. The pressure gauges shall all be numbered for identification, shall be oil actuated
and shall have a maximum scale deflection not exceeding approximately twice the expected
maximum pressure for the particular stage being grouted. A master pressure gauge, graduated
in divisions of 10kPa and calibrated by a recognised testing authority, shall be kept on Site for
checking and calibrating the working pressure gauges. The master gauge shall not be used for
any other purpose and the metering accuracy shall be 3%.
The working pressure gauges shall be calibrated to read in kPa, and be graduated in divisions
of 10kPa and have an accuracy of 5%.
A flow meter shall be used to accurately measure grout mix water.
Pressure gauges and flow meters shall be calibrated regularly and a 100% replacement stock of
working gauges and meters shall also be on hand at all times. Working gauges shall not be
used for longer than 50 hours of operation after which they shall be cleaned and re-calibrated.
Where ordered by the Engineer, displacement gauges shall be provided to enable any rock
movement during grouting to be measured. A displacement gauge may consist of a screw
adjusted spirit level on a steel straight edge 2m long, or other approved device.
4.6. Packers
Surface packers shall, in general, be used, but packers suitable for isolating a section of a hole
at depth shall also be available on Site.
Generally, packers shall consist of pneumatic or hydraulic tubes, mechanically expanded tubes
or mechanically expanded rings of rubber, leather or other suitable material attached to the end
of the grout injection pipe. The packers shall be so designed that they will seal any size drill
holes between 38mm and 100mm, both sizes inclusive, at the specified level, and then be
capable of withstanding water pressures equal to the maximum grout pressure to be used at
that point without leakage.
Packers shall be suitable for all pressures and rock conditions at the Site and the most
appropriate packers shall be selected. Mechanically expanded packers may be used at the top
of the hole (for downstage grouting) but pneumatic or hydraulic packers shall be used where the
hole has to be sealed at depth.
4.7. Supply and Return Lines and Grouting Pipes, Hoses and Fittings
A single supply line shall be provided between each grout pump and the grout hole. A return line
shall be used for temporary clearing of hoses, for emergency pressure relief and to provide
accurate grout pressure control regardless of how small the grout take may be. Return lines
shall discharge into the mixer only. All supply and return lines shall be the shortest length
practicable for the particular grout hole being grouted.
All grout pipes, hoses and fittings shall be capable of withstanding twice the expected maximum
grouting pressure. All pumps and mixing equipment shall be housed in a central grouting station
that can be moved to another location when necessary and which is located such that the length
of grouting hose from the grout pump to the hole to be grouted does not exceed 300m. Where
the various individual elements of the plant are located in such positions that communication by
normal voice between the hole being injected and the plant is not satisfactory, the Contractor
shall install a means of verbal communication such as a radio, a telephone or a suitable signal
system to the approval of the Engineer.
4.8. Bentonite Mixers
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
169
Where bentonite is incorporated in the grout, separate mixing tanks shall be provided in which
the bentonite/water mix can be prepared and kept agitated until required. Complete hydration of
the bentonite shall be achieved before incorporation in the grout.
4.9. Measuring Equipment for Trial Mixes
The Contractor shall provide adequate scales, balances and measuring flasks for making up
trial grout mixes of the chemical or suspension type.
5. CONSTRUCTION 5.1. General
(a) Supervision and Responsibility
Grouting shall only be performed in a workmanlike manner by competent and
experienced workmen. The Contractor shall submit details of the qualifications and
experience of the supervisors and operators he proposes to use to the Engineer for
approval before starting any grouting operation.
Modifications to the techniques specified in this specification or on the Drawings may
become necessary as work proceeds and as knowledge and experience is gained of the
natural rock and other foundation conditions. The Contractor shall alter or vary his
operations, after approval by the Engineer, or if directed by the Engineer, to suit such
knowledge and experience of the natural rock and other foundation conditions.
Grouting of the first three primary holes and subsequent splitting holes shall be used to
confirm the grout mixes, pressures and proposed grouting procedure.
Seven days before work commences on any grouting the Contractor shall submit to the
Engineer full details of the proposed methods of carrying out the work and also a detailed
programme indicating the proposed order of execution of the work. The approved or
agreed procedures and programme shall be strictly followed, and records shall be
accurately kept.
The Contractor shall take all steps necessary to ensure that no pollution is caused as a
result of drilling and grouting work. Before work commences the Contractor shall submit
details of the methods proposed to be employed to cope with grout spillages, which may
occur as a result of defective equipment, burst pipes or any other reason, for the approval
of the Engineer.
The Contractor shall adequately provide for the disposal of all wash water and waste
grout resulting from all grouting operations. Such water and grout shall not be allowed to
contaminate the Works and shall not be allowed to flow into any watercourse until it has
passed through settlement ponds or tanks approved by the Engineer.
No grouting shall be performed within a distance of 100m from areas where blasting is
still to be performed.
The Contractor shall give all facilities to the Engineer for inspecting the operations at all
times and for checking the results.
Unless otherwise approved all grouting which has been started shall be performed
without interruption until completed.
Regulation measurements and supervision of pressure shall be carried out continuously.
Pressure increases shall be controlled and the Contractor shall take care that the
pressure does not reach too high a value, keeping it within such limits as will ensure that
it does not cause cracking or deformation of rock or concrete. The Contractor shall be
entirely responsible for any damage which may occur due to the use of pressures in
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
170
excess of the maximum allowable pressure for any particular stage as directed by the
Engineer.
Special treatment may be required for faults, seams, fissures or other specified features.
The Engineer shall give the appropriate instructions in each case.
Grout samples shall be taken from time to time as directed by the Engineer for the
purpose of performing density and strength tests.
(b) Records
The Contractor shall provide the Engineer daily, on an approved form, with accurate
records of all water testing and grouting operations performed the previous day.
The information recorded shall inter alia include :
(i) The reference number, location and stage of the hole grouted and grouting
methods employed.
(ii) The results of comprehensive and abbreviated water pressure tests, which shall
include the pressure and water absorption at regular intervals.
(iii) Details of the grout injection giving pressures, mix proportions, grout absorption at
regular intervals to be directed by the Engineer and the time at the start and end of
the grout pumping operating and indicating clearly the duration of stoppages.
(iv) General remarks on grouting processes adopted, surface leaks, interconnections,
refusals and any other phenomena that may have become apparent.
5.2. Drilling Grout Holes Grout holes shall generally be drilled with rotary percussion equipment in accordance with
Section 11A. Where specialised grouting methods are employed, the additional requirements of
Clause 11C.5.4 of this specification shall be complied with.
5.3. Standard Grouting Methods
5.3.1. General Procedure for Grouting
(a) Method
Downstage grouting methods with surface packers shall be used for all stages unless
conditions are such that grouting with the packer set at the bottom of the previous stage is
approved by the Engineer or that another method is approved or ordered by the Engineer.
Each stage of each grout hole shall be grouted only after having been satisfactorily
flushed and water tested in accordance with Section 11B, unless otherwise directed by
the Engineer.
(b) Flushing of Grout Holes
Grout holes shall be cleaned out by flushing before water pressure testing any stage or
section, or after grouting a hole or section of a hole in order to remove partially set grout.
Cleaning of holes after grouting shall not commence before at least 6 hours has elapsed
since the last injection of grout has been completed, or as ordered by the Engineer.
Flushing shall be conducted by inserting a suitable pipe or tube down to the bottom of the
hole and pumping in a mixture of air and water while moving the pipe up and down until
the wash water runs clear.
(c) Rinsing Grout Holes
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
171
If, in the opinion of the Engineer the possibility exists that grout holes adjacent to the one
being grouted could become clogged, the Contractor shall continuously rinse such holes
with clean water while grouting is in progress in the adjacent hole or for such other time
as the Engineer may direct. The Contractor shall rinse all holes that could become
clogged due to the ingress of grout from adjoining holes, as is evidenced by the
emergence of grout or washing water from such holes. In the event of such holes
becoming clogged the Contractor shall clear such holes or replace them with such new
holes as the Engineer may direct.
Rinsing shall be conducted by inserting a suitable pipe or tube down to the bottom of the
hole and pumping in sufficient clean water to produce an upward velocity of the water in
the hole of at least 1m/s.
(d) Protection of Filters and Drains
Unless otherwise authorised by the Engineer, no grouting shall be performed within 50m
of installed perforated pipes or gravel filters. Where permitted in such locations, the
Contractor shall maintain a flow of water through the drains likely to be affected. Where
leakage of grout into drains does occur, the Contractor shall immediately stop the grouting
operations and shall remove all grout from the drains affected by rinsing, to the
satisfaction of the Engineer. Such stoppage of grouting operations and rinsing of drains
shall be repeated as often as required.
(e) Starting Mixes and Thickening
If water pressure tests indicate a tight hole, grouting shall be started with a thin mix. If an
open hole condition exists grouting shall be commenced with a thicker mix with the rate of
grout injection at all times as uniform as is practicable. The water : solids ratio shall be
varied according to the conditions encountered such that the rate of absorption of solids is
a maximum at all times. Periodic applications of water under pressure shall be made only
if necessary to prevent premature stoppage. Under no circumstances shall the pressure
or rate of grout injection be suddenly increased as either may promote stoppage.
Should it prove impossible to attain the required pressure with the approved grout
consistency, the grout shall be gradually thickened up by adding cement while injection
continues at a constant rate until the required maximum pressure is attained.
The Contractor's proposed starting mix and thickening procedure shall be submitted to
the Engineer for his approval for each stage of each hole being grouted.
(f) Abnormal Takes
If a hole absorbs an abnormal amount of grout (more than 100kg of cement per metre
length of hole unless otherwise indicated by the Engineer) without reaching refusal or
without showing any reduction in grout take, the Contractor shall inform the Engineer
immediately to enable him to determine the procedure to be followed in dealing with the
situation. The rate of injection shall be reduced or injection carried out intermittently or
grout thickened or any other procedures ordered by the Engineer shall be adopted.
(g) Pressures
The injection pressure shall be measured and controlled at the collar of each hole with the
return line being used for temporary circulation in the hoses to avoid clogging and for
pressure control as indicated in Clause 11C.4.7 of this specification.
The pressure used for grout injection may vary with the conditions encountered. The
pressures shall be as high as practicable but shall be limited so that grout is not wasted
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
172
by leakage through the rock surface and so as not to cause displacement of the rock or
structure. Grouting pressures shall be as shown on the Drawings or ordered by the
Engineer. Should any movement of the rock or structure be observed during grouting
operations, the pressure in the hole shall immediately be released.
The maximum starting pressure for any new application shall be kept at 50kPa or lower
for at least 5 minutes during which the connections, possible rock movements and leaks
shall be closely observed. Only if no leaks or rock movements are experienced shall the
pressure steadily be increased during the next 25 minutes to the pressures indicated on
the Drawings or ordered by the Engineer.
Grout mix proportions shall be adjusted as necessary and as approved by the Engineer to
prevent any rapid build-up of pressure.
(h) Completion of Grouting
The grouting of any hole or stage of hole shall not be considered complete until that hole
refuses to take any grout whatsoever during a 15-minute interval at the maximum
pressure required for that stage and at the particular water : solids ratio indicated by the
Engineer.
After the grouting of any stage of a hole is complete the pressure shall be maintained by
means of a stopcock or other suitable device until the grout has taken its initial set and
shall be closed for at least 6 hours from the last application of grout in the hole. Unless
otherwise ordered by the Engineer, all the grout shall then be flushed from the hole by
means of a high pressure air and water jet until the wash water runs clear. If any stage of
a hole has to be re-drilled due to failure of the Contractor to remove the partially set grout,
such hole shall be re-drilled by the Contractor at his own expense.
(i) Interruption
If the grouting of any hole is interrupted for any reason, the Contractor shall immediately
clean the hole being grouted and any adjacent holes into which grout has entered by
flushing.
(j) Final Plugging of Grout Holes
Final plugging of grout holes shall generally not be performed until 48 hours after
completion of grouting of the final stage or section of a hole, and not until the approval of
the Engineer has been obtained, upon which the holes shall be filled with cement mortar
consisting of 1 : 0,75 mixture of cement and water or other of approved consistency and
composition from the bottom upwards so that all the water is replaced by grout.
Prior to plugging of grout holes the Contractor shall ensure that no hole becomes blocked
by any cause whatsoever.
(k) Removal of Standpipes and Casings
On completion of all grouting work on a hole, standpipes and casings shall be removed or
cut off at the ground or other surface to the satisfaction of the Engineer. All voids existing
after either procedure shall, as directed by the Engineer, be made good by grouting up
the hole as specified in the foregoing paragraph (j).
Where a portion of a hole is in overburden which may or may not have a casing, that
portion situated in the overburden shall be similarly treated.
(l) Making-good Holes in Finished Concrete Surfaces
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
173
Where grouting is specified to be done from any finished concrete surface with thickness
not exceeding 2m, the holes shall be caulked up on completion of grouting. Where the
concrete thickness exceeds 2m, the holes shall be plugged as specified in the foregoing
paragraph (j).
Permission to caulk the holes shall be obtained from the Engineer before proceeding. The
holes shall be caulked to a minimum depth of 50mm from the surface of the hole. A
method approved by the Engineer shall be employed to caulk the hole, using a very dry
mix comprising 1 part cement and 2½ parts sand measured by weight.
(m) Construction of Grout Caps
Grout caps shall be constructed as shown on the Drawings in those areas directed by the
Engineer. No blasting shall be used for excavating grout caps except if approved by the
Engineer and only under such conditions as he may approve from time to time. Over-
excavation for the grout caps shall be kept to a practical minimum. Weak zones
intersecting the grout cap excavation shall be excavated as directed by the Engineer.
(n) Cleaning Operations
During grouting operations the Contractor shall take all precautions necessary to prevent
drill cuttings, equipment exhaust oil, wash water and grout from defacing or damaging the
permanent structure. The Contractor shall furnish such pumps as may be necessary to
handle waste water and grout from the grouting operations and shall, upon completion of
this portion of the work clean up all waste resulting from his operations, that is unsightly,
that may cause pollution or would interfere with the efficient operation of the Works.
5.3.2. Specific Procedure for Curtain Grouting
The spacing, diameter and depth of the primary holes shall be as shown on the Drawings or
directed by the Engineer.
(a) Downstage Grouting
Unless otherwise directed or approved by the Engineer the procedure for curtain grouting
shall be on the basis of downstage grouting.
Generally a grout curtain shall be formed by drilling primary holes at 8m centres or such
other spacings shown on the Drawings and in stages, as indicated on the Drawings, all of
which shall be flushed and water tested according to Section 11B and then be grouted
using downstage grouting and following the general procedure set out in Clause
11C.5.3.1 of this specification. Unless otherwise directed by the Engineer a secondary
series of holes shall then be drilled along the same line as the primary holes with the
secondary holes placed midway between the primary holes. After the secondary holes
have been drilled, water tested and grouted as necessary for a particular stage, zones
where a third (tertiary) or fourth (quaternary) series of splitting holes may be necessary,
shall be drilled as directed by the Engineer. Generally a splitting hole shall be drilled
where a water loss in excess of 2 Lugeon has been obtained.
The first stage of all grout holes shall generally be drilled to a depth of less than 10m into
the rock foundations, or as directed by the Engineer. The depth of the successive stage
shall be as shown on the drawings, or as directed by the Engineer, but shall generally not
exceed a depth of 18m. In areas where the grout curtain does not exceed a depth of 10m,
grouting shall be performed in a single stage only.
Drilling of a successive stage shall not be commenced until all drilling and grouting of the
upper stage between the primary holes within at least one primary hole spacing adjacent
to the hole to be deepened has been completed to the approval of the Engineer. As a
general rule, it means that drilling/grouting must stay one completed stage behind
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
174
previous holes. All successive stages shall be drilled and grouted in the same order as
the first stage. The number of holes between primary holes shall be determined by the
split spacing method between each pair or primary holes and for each stage being drilled
and grouted.
A curtain grout hole shall not be drilled until all consolidation grout holes within a distance
of 10m from the particular curtain grout hole have been finally grouted.
In general, surface packers, seated into solid rock or concrete, shall be used. However,
where it is found that grout from lower stages "breaks back" through a previously grouted
stage or where there is excessive surface leakage of grout or where it is found impossible
to build up a grout pressure, the Engineer may direct the Contractor to position packers
such that only a specific stage of a hole is grouted separately.
After grouting any stage of any hole it shall be cleaned by flushing as described in Clause
11C.5.3.1 of this specification, except when the Engineer directs that the grout be left
undisturbed to harden before then being re-drilled and flushed. No drilling of a further
stage shall be performed until a period of at least 24 hours has elapsed after grouting the
previous stage. Drilling, flushing, water pressure testing and grouting of successive
stages shall be performed until the specified depth of grout curtain is reached.
All stages of grout holes drilled shall generally be grouted after being water pressure
tested irrespective of the results of the water pressure tests, unless otherwise directed by
the Engineer.
Before drilling the next stage of a particular hole, the Contractor may be instructed to
perform an abbreviated water test on the stage(s) previously grouted. If the water loss of
the particular section exceeds 1 Lugeon (after grouting), such stage(s) shall be regrouted
before commencing drilling of the next stage, unless otherwise directed by the Engineer.
After completion of the final stage the hole shall be flushed in accordance with Clause
11C.5.3.1 of this specification and if ordered by the Engineer, the full length of the hole
shall be subjected to an abbreviated water pressure test conducted prior to finally
plugging the hole. Should the water loss exceed 1 Lugeon the hole shall be regrouted as
directed by the Engineer.
The Engineer may order the drilling of a check hole(s) to determine the effectiveness of a
grouted section. Such check hole shall be drilled and comprehensive water pressure tests
performed according to Sections 11A and 11B. If the water loss in the check hole
exceeds 2 Lugeon, the hole shall be grouted according to Clause 11C.5.3.2(b) and if the
water loss is less than 2 Lugeon, the hole shall be plugged according to Clause
11C.5.3.1.
If during the grouting of a hole, communication is established with a neighbouring hole,
the Engineer may instruct that rinsing of the neighbouring hole be dispensed with and that
the hole be grouted immediately. In such instances the point of entry of grout into the hole
shall immediately be determined by means of a packer. The hole shall then be sealed off
with the packer positioned just above the highest point of entry and grouting of the
adjacent hole shall be continued at such reduced pressure as may be dictated by the
level of the packer closest to the surface. The Contractor shall provide for making
simultaneous grout connections to a series of grout holes if during the pressure testing
operations it becomes evident that a considerable flow of grout would occur between
such holes and if the Engineer directs that such holes be grouted simultaneously.
When grouting holes near the surface of the foundations the Contractor shall, if any
substantial leaks of grout occur through cracks and fissures in the foundations, take
whatever measures that may be necessary, such as caulking, to stem the grout flow and
prevent the loss of grout. The pressures used for grout injection near the surface of the
foundations shall be as indicated on the Drawings or directed by the Engineer, but shall
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
175
be varied to suit the conditions encountered and shall be as directed or approved by the
Engineer. In general the upper stages shall be grouted at a low pressure and the deeper
stages at a higher pressure. The pressure shall generally be as high as possible but shall
be limited so as not to cause displacement of rock or concrete.
(b) Upstage Grouting
Unless otherwise approved by the Engineer, upstage grouting shall generally only be
employed when check holes, which were drilled to examine the effectiveness of the
curtain grouting operations, need to be grouted.
When employing upstage grouting the holes shall be grouted from the bottom up and the
lengths of the sections (stages) to be grouted shall be as approved or directed by the
Engineer. The packer shall be lowered to the top of the section to be grouted and the
Contractor shall take such precautions as may be necessary to ensure an adequate seal
and to prevent grout that may leak past the seal from causing the packer to stick in the
hole.
After the grout has taken its initial set the packer shall be removed and the hole flushed
as described in Clause 11C.5.3.1 of this specification. The packer shall then be inserted
at the next level and then the full length of the hole below the packer shall be grouted.
This procedure shall be continued until the hole has been grouted over its full length.
Immediately prior to the final plugging of a hole grouted by means of upstage grouting,
and if directed by the Engineer, abbreviated water tests using a double packer shall be
conducted on each section of the hole grouted, using a water pressure of 100kPa
measured at the collar of the borehole. If the rate of water loss exceeds 1 Lugeon for any
section tested, the Contractor shall regrout such sections of the hole and at such
pressures as the Engineer may direct.
5.3.3. Specific Procedure for Consolidation Grouting
Consolidation grouting shall be carried out by drilling and grouting groups of holes, at the
spacings and positions within the foundation area of the concrete structure and to the depths
into the rock as shown on the Drawings or as directed by the Engineer. Unless otherwise
directed by the Engineering, all drilling, water pressure testing and grouting shall be performed
in a single stage operation.
The grouting procedures and injection pressures shall in general be as indicated in
Clause 11C.5.3.1 of this specification, unless otherwise directed by the Engineer. Each group of
consolidation grout holes shall be grouted only after being satisfactorily flushed and if directed
by the Engineer, water pressure tested (abbreviated) in accordance with Section 11B.
The sequence of drilling and grouting the consolidation grout holes shall be as shown on the
Drawings or as directed by the Engineer. Grouting shall generally be done from the outer holes
towards the centre of the foundation area to be grouted.
Unless otherwise directed or shown on the Drawings, consolidation grout holes within 10m from
any curtain grout holes to be drilled shall have been completed before drilling the curtain grout
holes.
5.4. Specialised Grouting Methods
5.4.1. General
The Contractor shall use specialised grouting methods such as the Tube-a-manchette (TAM)
grouting method, or other method approved by the Engineer, if directed by the Engineer in areas
where:
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
176
a) the standard grouting procedures specified in Clause 11C.5.3 of this specification prove to
be ineffective, or
b) where joints in the concrete or the concrete/rock contact need to be grouted.
5.4.2. Tube-a-manchette (TAM) Grouting Method
The TAM grouting method comprises a perforated tube which is sealed into the ground with a
relatively weak cement/bentonite sleeve grout. Rubber sleeves covering the perforations shall
be fitted around the outside along the length of the tube. The sleeves shall act as one-way
valves to allow grout to rupture the sleeve grout and enter the ground, but preventing the re-
entry of the grout by closing onto the tube once the injection pressure has dropped.
The Contractor shall submit a detailed proposal concerning the TAM grouting to the Engineer for
prior approval.
Drilling shall be performed according to Section 11A of this specification. Positions of the grout
holes shall be determined by the Engineer.
The sizes of the boreholes shall be as approved by the Engineer and shall be large enough for a
TAM having an inner diameter of approximately 50mm to 70mm to be installed in the borehole
with the annular space sufficiently wide to ensure good embedment of the tube and the sleeves.
The TAM shall be made of uPVC tubing and shall be assembled on Site to the lengths required
for each borehole. The TAM shall be installed in the borehole and the annular space between
the TAM and the ground shall be grouted with a special grout mix consisting of a dense cement
mix containing a small percentage of bentonite to be determined experimentally on Site. If a
casing is present, it shall be pulled out as the sleeve grouting proceeds, leaving the TAM
properly embedded.
After the sheath grout has been allowed to set, grouting of the formation shall be done by using
a double packer at each sleeve. The packers shall be either normal leather cup packers or
inflatable packers.
The sequence of grouting and the pressures used shall be determined by the Contractor on Site
and be to the approval of the Engineer. The grout material and the grout mix proportions shall
be as directed by the Engineer. Cementitious grout shall generally be used for the first
application to fill major voids after which the Engineer may instruct the use of lower viscosity
chemical grouts. Complete records of water acceptances and grout takes shall be kept by the
Contractor, to enable the Engineer to detect where further injections are required.
The tubes shall be cleaned by flushing and shall be capped after completion of the grouting
operation leaving the TAM fully accessible for testing and/or regrouting at a later stage if so
directed.
TAM grouting may also be done from pipes/sleeves embedded in the concrete.
6. TOLERANCES
Not applicable.
7. TESTING
The Contractor may be requested to provide approved Marsh flow cones, thermometers, mud
balance and measuring cylinders (60mm diameter) to enable the Engineer to check the
consistency of the grout at any time. The applicable limits shall be jointly established by
laboratory and field tests prior to work commencing.
7.1. Density (Mud Balance)
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
177
Determination of the relative density of freshly mixed grout shall be with a mud-balance.
Reading of relative density taken directly from the calibrated beam shall be converted to a water
cement ratio by means of an agreed curve or table.
7.2. Viscosity (Marsh Cone)
The fluidity of grout shall be measured with a flow cone, immersion apparatus or viscometer.
The instrument shall be accurately calibrated in a laboratory so that the specified viscosity of the
grout can be controlled satisfactorily.
The procedure for conducting the flow-cone test for measuring the fluidity of grout shall be as
follows:
The type of flow shall be subject to the approval of the Engineer.
Immediately after the grout has been mixed, the pre-wetted flow cone, which is held firmly with
its top rim in a level position, shall be filled with grout to the level indicated by the pre-set pointer,
whilst the bottom orifice is held closed with a finger.
As soon as the required volume of grout (± 1 750mℓ), is reached, the finger shall be released to
allow the grout to flow out freely through the bottom orifice. A stop watch shall be used to
determine the flow time for emptying the cone, to the nearest second.
The readings obtained during grouting shall be compared with the times determined in the
laboratory for grouts of the specified viscosities.
7.3. Bleeding
The bleeding of grout shall be measured in a metal or glass container with an internal diameter
of approximately 100mm and a height of approximately 120mm. The grout and water levels in
the container shall be controlled with a metal bridge into which two adjustable studs A and B are
secured.
The procedure for determining the bleeding of grout shall be as follows:
Studs A and B in the metal bridge shall be adjusted and locked so that the distance from the
lower tips of the studs to the bottom of the container will be approximately 100mm and 107mm
respectively. The volumes VAand VB for the container at the respective levels of the stud settings
shall then be determined to the nearest millilitre.
The container shall be filled with freshly mixed grout to a level where the grout will just touch the
tip of stud A which points downwards. The bridge shall then be removed and the container
tightly sealed to prevent evaporation. The container shall then be stored at 20°C and kept free
from vibrations for the entire duration of the test.
Three hours after the grout has been mixed, the container shall be opened and the free (bleed)
water poured off. The bridge shall be placed over the container with the tip of stud B pointing
downwards and water poured onto the grout with a measuring apparatus until the water level
touches the tip of stud B. The volume of water added shall be determined to the nearest millilitre and designated as .
The percentage of bleeding shall be calculated from the formula.
7.4. Test Cubes
If requested by the Engineer, samples of grout shall be taken by the Contractor at the point of
mixing or of deposition as instructed by the Engineer and in the presence of a representative of
the Engineer, all in accordance with the sampling procedures described in SANS 5862.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
178
Samples shall be taken on the basis of one for each 50m³ of grout pumped but in any case not
less than one sample per day per mixing station.
The Contractor shall cast from each sample, cure and test six test cubes as set out in
SANS 5863. Three cubes shall be tested at 7 days and 3 at 28 days.
The average strength of the 3 cubes crushed shall be referred to as one test result.
Grout shall be deemed to comply with the strength specified if the average strength of any 4
consecutive test results exceeds the agreed characteristic strength by 2MPa and the strength of
any test result is not less than the specified characteristic strength minus 3MPa.
8. MEASUREMENT AND PAYMENT 8.1. General Principles
Specific items such as percussion drilling, casings and standpipes shall be measured according
to Section 11A. Water pressure testing of boreholes shall be measured according to
Section 11B. Materials used in the permanent works shall be classified according to their nature
and usage and generally measured by mass of the dry materials.
The Contractor shall at his own expense, replace by another drilled hole any grout hole that is
lost or damaged due to mechanical failure of equipment, the grouting in of packers or the
inadequacy of grout supply, clear or replace all grout holes that become clogged due to the
ingress of grout from nearby grout holes and redrill any hole that is lost due to failure of the
Contractor to timeously remove partially set grout.
8.2. Scheduled Items
8.2.1. Grout Connections to Drilled Holes Unit: litre (ℓ)
The number of connections to drilled holes for grouting purposes shall be measured. Grout
connections shall be measured once only for each stage or section of hole unless the Engineer
orders the grouting equipment to be removed and subsequently set up again. The rate shall
include for the supply and installation of packers, other equipment and labour.
8.2.2. Grouting Unit: litre (ℓ)
The grout volume for payment shall be measured by the volume of grout that was pumped and
injected. The rate for payment shall include for mixing of the grout, keeping of grout records,
flushing of holes to remove partially set grout, for cleaning operations and any caulking required.
The rate shall include for removing any standpipes and casings as specified in Sub-clause
11C.5.3.1(k) and final plugging of the holes as specified in Sub-clause 11C.5.3.1(j).
No distinction between downstage and upstage grouting shall be made.
The grouting materials shall be measured for payment under Clause 11C.8.2.3.
8.2.3. Materials used in all Grouting Operations
8.2.3.1. Cementitious material Unit: tonne (t)
The weight of cementitious material actually used in the grouting operations shall be measured.
The rate for payment shall include furnishing and batching and screening. Grout that was lost as
a result of failure of equipment or on account of the Contractor's failure to comply with the
requirements of this specification or which was rejected by the Engineer as being unsuitable for
use in grouting operations, including grout that has not been injected within 2 hours after mixing
and has subsequently been disposed of, shall not be measured for payment.
Distinction between different kinds of cementitious materials as scheduled shall be made.
Tender No.W 0686 WTE Part C3: Scope of Work
Mdloti River Development: Hazelmere Dam Raising
179
8.2.3.2. Sand Unit: m³
The volume of sand used in the grouting operation shall be measured separately in the dry.
8.2.3.3. Additives Unit: litre (ℓ)
The mass of additive scheduled or ordered by the Engineer shall be measured.
The rate for payment shall cover all costs of including the additives in the grout mix.
8.2.3.4. Chemical grouts Unit: kg
The mass of chemical grouts before mixing shall be measured. The rate shall cover all costs for
handling, batching and mixing.
8.2.4. Grout Cap Unit: m³
The cubic metres of concrete needed to form the grout cap shall be measured. The rate shall
include the cost of all materials and plant required for excavating for the cap, mixing and placing
of the concrete, formwork and casting in of any standpipes or casings where ordered.
Standpipes or casings shall be measured for payment in accordance with Section 11A.
8.2.5. Rinsing drilled holes Unit: h
The number of hours of rinsing of drilled holes that the Engineer has ordered to prevent clogging
during the grouting operation shall be measured. Rinsing of a portion of a hole above a packer
while injecting grout shall not be measured for payment.
8.2.6. Tube-a-manchette (TAM) grouting Unit: litre (ℓ)
The grout volume for payment shall be measured by the volume of grout that was injected. The
rate for payment shall include for mixing of the grout, keeping records, flushing the pipes, supply
and installation of TAM pipes, cleaning operations and caulking required. No additional payment
for connections to grout pipes will be made.
Extra over payment items shall be scheduled for regrouting of TAM pipes.
8.2.7. Density (Mud Balance) Test Unit: No
The rate shall cover all the costs to carry out and complete grout density tests as ordered by the
Engineer according to Clause 11C.7.1.
8.2.8. Viscosity (Marsh Cone) Test Unit: No
The rate shall cover all costs to carry out and complete grout viscosity tests as ordered by the
Engineer according to Clause 11C.7.2.
8.2.9. Bleed Test Unit: No
The rate shall cover all the costs to carry out and complete grout bleed tests as ordered by the
Engineer according to Clause 11C.7.3.
8.2.10. Test Cubes Unit: No
The rate shall cover all the costs for sampling, curing and crushing six test cubes, including
recording and providing test records according to Clause 11C.7.4 as ordered by the Engineer.