CONSTRUCTION UPDATE JULY 27, 2017 Legend 1) Confed Phase #2 2) Emergency Access Road 3) Hwy 63 & Mackenzie Intersection 4) Hwy 63 & Saprae Creek Trail 5) Lift Station upgrades South Mackenzie 6) Mackenzie Blvd Lift Stations Diversion 7) Mills Avenue Stormwater Management 8) PLB Phase 2 9) PLB Phase 4 Hardin St to Morrison 10) Saline Watermain from Hardin to King Booster Station 11) SW Water Supply Line Phase 1 12) UIR 2014-2016 Contract 14 Road Rehab 13) C15 Road Construction 14) C15 Road Construction 15) C15 Road Construction Map 16) UIRP 2014-2016 C3 17) UIRP 2014-2016 C6 18) UIRP 2014-2016 C8 19) Road Rehab C13 20) C2 Rehab of Mckenzie, King & Grayling 21) UIRP 2017 C1 22) UIRP 2017 C3 23) C4 Rehab of Hill Drive & Mcleod Street 24) C5 Rehab of Poplar Cr., Crescent Heights, Biggs Ave. & Rae Cr. 25) RIRP Anzac C2 Pipes and Road Rehab 26) Rural Servicing Conklin C3 27) GLE Contract 1 Water & Sewer install 28) Thickwood Blvd- Abasand Drive Erosion

Upload: trinhquynh

Post on 20-Mar-2018

230 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

CONSTRUCTION UPDATE JULY 27, 2017

Legend

1) Confed Phase #2

2) Emergency Access Road

3) Hwy 63 & Mackenzie Intersection

4) Hwy 63 & Saprae Creek Trail

5) Lift Station upgrades South Mackenzie

6) Mackenzie Blvd Lift Stations Diversion

7) Mills Avenue Stormwater Management

8) PLB Phase 2

9) PLB Phase 4 Hardin St to Morrison

10) Saline Watermain from Hardin to King Booster Station

11) SW Water Supply Line Phase 1

12) UIR 2014-2016 Contract 14 Road Rehab

13) C15 Road Construction

14) C15 Road Construction

15) C15 Road Construction Map

16) UIRP 2014-2016 C3

17) UIRP 2014-2016 C6

18) UIRP 2014-2016 C8

19) Road Rehab C13

20) C2 Rehab of Mckenzie, King & Grayling

21) UIRP 2017 C1

22) UIRP 2017 C3

23) C4 Rehab of Hill Drive & Mcleod Street

24) C5 Rehab of Poplar Cr., Crescent Heights, Biggs Ave. & Rae Cr.

25) RIRP Anzac C2 Pipes and Road Rehab

26) Rural Servicing Conklin C3

27) GLE Contract 1 Water & Sewer install

28) Thickwood Blvd- Abasand Drive Erosion

Page 2: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete
Page 3: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name:

Confed Sanitary Sewer –Const, C1- MA30 to eagle ridge Overpass

Project Manager: Muhammad Asghar

Start Date: 5/24/2017 Completion Date: 9/20/2017

Project Phase: Construction Contractor Name: OCL

Road Closure: ☒Full ☐ Partial ☐ Both ☐No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• Laying of new sanitary line (larger diameter) along Confederation Way. Milestone Complete:

• Piping work complete 75% complete.

Current Progress to date:

• To complete 25% of remaining piping work. This includes Micro tunneling work.

• Landscape work.

Plan for Next 2 weeks:

• To complete 8% of remaining 25% piping work. This includes Micro tunneling work

Detour/Road Closure Details:

• There will be a partial closure of lane road during construction. (Full lane will be closed from July 10, 2017 to August 15, 2017 giving room for vehicles to have right turn at Eagle ridge overpass up.)

1 July 27, 2017

Page 4: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/17/2017 Project/Contract Name:

Emergency Access Road -Construction

Project Manager: Joseph Zachariah

Start Date: TBD Completion Date: TBD

Project Phase: Construction Contractor Name: TBD

Road Closure: ☐Full ☐ Partial ☐ Both ☒No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• Construction of emergency egress road for Abasand, Beaconhill & Wood Buffalo area.

Milestone Complete:

• Tender closed on June 29, 2017

Current Progress to date:

• Contract Award letter issued to Wilco Contracting Inc. Contract execution in progress

Plan for Next 2 weeks:

• Start Construction tentatively in first week of August, subjected to contract execution.

Detour/Road Closure Details:

• None at this point

2 July 27, 2017

Page 5: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name:

Highway 63 and Mackenzie Intersection Improvements

Project Manager: Shanta Chakrovortty

Start Date: 5/29/2017 Completion Date: 11/30/2017

Project Phase: Construction Contractor Name: Sureway Construction Group Ltd

Road Closure: ☐Full ☐ Partial ☐ Both ☒No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• Intersection upgrade with traffic signals Milestone Complete:

• Subgrade 50% complete, GBC 25% complete, culvert complete, traffic signal 20% complete

Current Progress to date:

• Temporary light plants installed, traffic signal work, TAS, top soil stripped all sides, subgrade completed on SE, NE, NW and North median, GBC 25%.

• Over all progress: 40%

Plan for Next 2 weeks:

• Complete subgrade on all direction, GBC (weather dependent), traffic signal, street light

Detour/Road Closure Details:

• No detour expected. Two lanes will be open all times.

3 July 27, 2017

Page 6: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name:

Highway 63 Intersection Improvements at Saprae Creek Trail

Project Manager: Shanta Chakrovortty

Start Date: 5/17/2017 Completion Date: 11/30/2017

Project Phase: Construction Contractor Name: E Construction Ltd.

Road Closure: ☐Full ☐ Partial ☐ Both ☒No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• Intersection upgrade with traffic signals Milestone Complete:

• Subgrade complete, GBC 85% complete, asphalt paving 30% complete, culvert complete

Current Progress to date:

• ATCO Electric salvaged existing streetlight, temporary light plants installed, TAS, top soil stripped all sides, subgrade completed all area, GBC 85%, 30% ACP, streetlight concrete bases complete, traffic signal 35%.

• Over all progress: 65%

Plan for Next 2 weeks:

• Complete GBC and first lift of ACP, traffic signal, street light

Detour/Road Closure Details:

• No detour expected. Two lanes will be open all times.

4 July 27, 2017

Page 7: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name:

Lift Station Upgrades (South) - C 2: MacKenzie Lift Station

Project Manager: Adel Youssef

Start Date: 5/2/2016 Completion Date: 8/30/2017

Project Phase: Construction Contractor Name: Nason

Road Closure: ☐Full ☐ Partial ☐ Both ☒No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• This project is to upgrade the MacKenzie Lift Station due to its lifecycle.

Milestone Complete:

• 95%

Current Progress to date:

• Commissioning of SCADA between the LS and WWTP

• Preparing for the landscape scope

• Working on the deficiency list

Plan for Next 2 weeks:

• Working on the deficiency items

Detour/Road Closure Details:

• N/A

5 July 27, 2017

Page 8: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017

Project/Contract Name:

Mackenzie Blvd Lift Station Diversion & Sewer Upgrade ‐ Construction

Project Manager:

Adel Youssef

Start Date: 5/2/2016 Completion Date: 8/30/2017

Project Phase: Construction Contractor Name: Sureway

Road Closure: ☐Full ☐ Partial ☐ Both ☒No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• Contract #1: The Construction of a new Forcemain from the MacKenzie Blvd & Hwy 63 intersection to the newly build Gregoire East Sanitary Outfall. The existing Forcemain is scheduled to be relocated and upsized to coincide with the new MacKenzie Lift Station.

Contract #2: The MacKenzie Sewer Upgrades ‐ Phase 2 Project is proposed to divert flows from the Prairie Creek neighbourhood and the southern region of the MacKenzie Industrial area through the green space east of the Gregoire Neighborhoods. The upstream portion of this sewer between MacKenzie Boulevard and MacMillan Road will replace the existing sewer along the same alignment which travels through a 9 m wide RMWB right‐of‐way (ROW).

Milestone Complete:

• 95%

Current Progress to date: The majority of the Sewer, Storm and Water piping are complete. The restoration activities are currently taking place (Landscape and re‐paving of Mackenzie Blvd and Mackay Cres.

Plan for Next 2 weeks:

• Working on the deficiency items

• Landscape Scope

Detour/Road Closure Details:

• N/A

6 July 27, 2017

Page 9: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/10/2017 Project/Contract Name:

Mills Avenue Stormwater Management - Construction - Contract 2: Storm Sewer & Outfall Upgrade

Project Manager: Abdur Rashid

Start Date: 7/25/2017 Completion Date: 10/31/2017

Project Phase: Construction Contractor Name: Sureway

Road Closure: ☐Full ☒ Partial ☐ Both ☐No Detour Plan: ☒Yes ☐Not Required

Project Status Scope:

• Stormwater main in Centennial & Tolen Drive with Outfall structure in Hangingstone River

Milestone Complete:

• Award Letter to Sureway

Current Progress to date:

• Checking Regulatory compliances

• Kick off Meeting – July 21, 2017

• Coordination with Shallow Utilities and Hydrovac to expose shallow utilities – Started July 17, 2017

• Engaging environmental consultant to provide instream construction approach

Plan for Next 2 weeks:

• Sign contract Agreement and Issue PO – in process of executing contract agreement

• Award PO to Environmental Consultant - awarded

• Hydrovac work – started & it could take week to get survey data

Detour/Road Closure Details:

• There will be a partial closure on Tolen and Centennial Dr. Detour may or may not be needed based on finding of shallow utilities

7 July 27, 2017

Page 10: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name: PLB Phase 2 construction Project Manager: Mizan Rahman

Start Date: 5/15/2017 Completion Date: 11/30/2017

Project Phase: Construction Contractor Name: E Construction

Road Closure: ☒Full ☐ Partial ☐ Both ☐No Detour Plan: ☒Yes ☐Not Required

Project Status Scope:

• Construction of Prairie Loop Boulevard Phase 2(Macleod to Hardin) Milestone Complete:

• Substantially complete by November 2017 Current Progress to date:

• Installed 400 mm Water main from phase 1 towards north and connected 400mm water main to existing at the intersection of PLB and Father Merc

• Installed storm main, Catch Basin, CBMHs and backfilled the trench

• Continued to build embankment slopes between station 1+ 580 and 1+ 760

• Removed ATCO overhead power lines Plan for Next 2 weeks:

• Subgrade Construction 1+760 to 1+580

• 750 STM from 105 to 2+020

• 750mm STM from MH103 to MH102

• Subgrade Construction 1+620 to 1+460

• Cement Stabilization 1+770 to 1+500

• 750mm ST from 101 to 100; STMH 100

• STMH100 CBs, leads and inlet

• Subgrade Construction 1+460 to 1+280

• Cement stabilizing 1+46 to 1+280 Detour/Road Closure Details:

• There will be full closure on Hardin street (Between Public School Board to Morimoto and Hardin intersection). Detour will be available from Riedel to Snye Building (Note: Until PLB is open from Riedel to Snye Building, Hardin Street will not be closed.)

8 July 27, 2017

Page 11: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name: PLB Phase#4 Project Manager: Muhammad Asghar

Start Date: 8/15/2017 Completion Date: 10/25/2018

Project Phase: Construction Contractor Name: OCL

Road Closure: ☒Full ☐ Partial ☐ Both ☐No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• Road Construction from Hardin to Morrison. Milestone Complete:

• Design is complete.

Current Progress to date:

• Tender is posted.

Plan for Next 2 weeks:

• Pre-Construction was held at Engineering on July 18, 2017

• Closing date for tender is July 25, 2017

• To start construction from August 15, 2017.

Detour/Road Closure Details:

• Morrison Street - Full closure (TBD for schedule)

• Detour Plan -Morimoto Drive

• Main Street - Partial Closure - No Detour plan.

9 July 27, 2017

Page 12: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name:

Saline Watermain from Hardin Street to King Street Booster Station - Construction

Project Manager: Abdur Rashid

Start Date: 1/29/2014 Completion Date: 10/31/2018

Project Phase: Construction Contractor Name: Consun

Road Closure: ☐Full ☐ Partial ☐ Both ☒No Detour Plan: ☐Yes ☐Not Required

Project Status Scope:

• Watermain from Intersection of Hardin & Franklin Ave to King St

Milestone Complete:

• Work on Site has completed

Current Progress to date:

• Processing final invoices

Plan for Next 2 weeks:

• Process final payment

• Additional work to erect fence around PRV chamber subject to availability of the fund

Detour/Road Closure Details:

• NO Road Closure or Detour

10 July 27, 2017

Page 13: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name:

Southwest Water Supply Line Phase 1 - Construction

Project Manager: Adel Youssef

Start Date: 5/2/2016 Completion Date: 9/30/2017

Project Phase: Construction Contractor Name: Direct Horizontal Drilling

Road Closure: ☐Full ☐ Partial ☐ Both ☒No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• This project is to bring new water supply mains across the Athabasca River from the Water Treatment Plant, for servicing the Horse Plateau and Hangingstone Plateau, and tying into Lower Townsite and Abasand Reservoir, effectively providing complete redundancy in the system between the South and Southwest supply lines. Eventually (i.e. after 2016), this water supply main might extend down to the Southlands Industrial Area to meet the ultimate build-out of this area. (Ref: Water Master Plan - Associated Engineering, 2011).

Milestone Complete:

• 75% Current Progress to date: The Contractor mobilized back to the Abasand Site for the LTS Reservoir tie-in works and commenced setup of rigid fence panels, trail closure signage as well as take down of trail light poles from the north and east side of the reservoir fence. The Contractor locates and began hydrovac to expose the end of the steel casing pipe adjacent the skate park/reservoir as well as other key locations for the new watermain installation. The Contractor plans to commence open cut pipe installation at the LTS Reservoir site in early June

Plan for Next 2 weeks:

• Continue working on the water main entering the LTS Detour/Road Closure Details:

• N/A

11 July 27, 2017

Page 14: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name: UIR 2014-16 – C14 Project Manager: Yogesh Acharya

Start Date: 5/2/2017 Completion Date: 7/30/2017

Project Phase: Construction Contractor Name: H Wilson

Road Closure: ☐Full ☒ Partial ☐ Both ☐No Detour Plan: ☐Yes ☐Not Required

Project Status Scope:

• Rehab of Cochrane Cres, Cameron Drive and Christina Ct. Milestone Complete:

• Its substantially completed (98%) in 2016

Current Progress to date:

• Second lift of Asphalt is still outstanding

• Landscaping has been largely completed

Plan for Next 2 weeks:

• Asphalt and remaining landscaping work to complete the project (100%)

Detour/Road Closure Details:

• There will be a partial on Cochrane Crescent (South) and Christina Court when top lift asphalt is completed.

12 July 27, 2017

Page 15: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

RGI ON U M UN I CIPALIT Y

of Wood BUFFALO

Project Information

Project/Contract Construction Coordination Sheet

Date: 7/18/2017

Project/Contract Name: UIR 2015-17- C15 Project Manager: Malik Lasker

Start Date: 5/20/2017 Completion Date: 8/25/2017

Project Phase: Construction Contractor Name: H Wilson

Road Closure: Full Partial Both No Detour Plan:

Yes Required

Project Status

Scope:

Asphalt road surface milling and overlay (2017):

• INTERSECTION (Rainbow Creek Drive/ Millennium Drive)

• Bennett Crescent

• Biggs Avenue

• Centennial Drive

• Clark Crescent

• Duncan Drive

• Fraser Avenue

• Hospital Street

• Laffont Way

• Loutit Road

• Main Street

• Manning Avenue

• Manning Avenue

• Millennium Drive

• Morrison Street

• Paquette Drive

• Thickwood Boulevard

Roads previously completed in 2016:

• Bacon Place

• Ball Place

• Barber Drive

• Biggs Avenue

• Dickins Close

• Kennedy Crescent

• King Street

• Manning Avenue

• Silin Forest Road

• Thicket Drive

• Tolen Drive

• Whitley Road

• Windsor Drive

• Wylie Place

13 July 27, 2017

Page 16: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Current Progress to date:

Millennium Drive – milling done

INTERSECTION (Rainbow/ Millennium) – milling done

Thickwood Blvd. – concrete done

Laffont Way – concrete done

Plan for Next 2 weeks:

Millennium Drive – asphalt paving to be done - Completed

INTERSECTION (Rainbow/ Millennium) – asphalt paving to be done – 1st week of August

Thickwood Blvd. – asphalt paving to be done – 2nd week of August

Laffont Way – asphalt paving to be done -1st week of August

Loutit Way – road core removals to be done – 4th week of August

Paquette – milling and paving (spot or full TBD) – 3rd week of August

Detour/Road Closure Details:

There will be a partial temporary closure on all roads where work is being done.

14 July 27, 2017

Page 17: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

15 July 27, 2017

Page 18: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name: UIR 2014-16 – C3 Project Manager: Ihsan-Ul Haq

Start Date: 5/3/2016 Completion Date: 9/30/2017

Project Phase: Construction Contractor Name: E Construction

Road Closure: ☒Full ☐ Partial ☐ Both ☐No Detour Plan: ☒Yes ☐Not Required

Project Status Scope:

• Rehab of Fullerton Drive, Farrell Crescent, Leigh Crescent and Torrie Crescent Milestone Complete:

• Work not yet complete. Current Progress to date:

• Fullerton Drive – Underground, concrete (excluding driveways) and bottom lift asphalt complete. Landscaping ongoing.

• Farrell Crescent - Underground, concrete and bottom lift asphalt complete. Landscaping ongoing.

• Leigh Crescent – Underground installation ongoing towards Dickins Drive. Concrete sidewalks and curb and gutter 50% installed. First phase of work is ready to be paved.

• Torrie Crescent (NW leg) - Underground installation complete. Ready for concrete sidewalk to be poured. Plan for Next 2 weeks:

• Fullerton Drive – Complete landscaping. Top lift asphalt to be completed.

• Farrell Crescent - Landscaping and top lift to be completed.

• Leigh Crescent – Complete the underground installation as far as Dickins Drive. Backfill and prepare sidewalks and road for paving.

• Torrie Crescent (NW leg) – Install sidewalks and pave road. Detour/Road Closure Details:

• Fullerton Drive – Fully open. Partial closure will be required to complete top lift asphalt.

• Leigh Crescent – Full Lane Closure.

• Torrie Crescent (NW leg) – Full Lane Closure. Road should be open to public in the next two weeks.

16 July 27, 2017

Page 19: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name: UIR 2014-16 – C6 Project Manager: Ihsan-Ul Haq

Start Date: 6/12/2017 Completion Date: 8/31/2017

Project Phase: Construction Contractor Name: E Construction

Road Closure: ☒Full ☐ Partial ☐ Both ☐No Detour Plan: ☒Yes ☐Not Required

Project Status Scope:

• Rehab of Silica Place (PULs and Laneway) Milestone Complete:

• Work not yet complete.

Current Progress to date:

• Silica Place – Underground completed at Silin Forest Drive intersection. Road open to public on gravel.

• Silica Place SW leg – Full Road closure. WM installed to dead end. Backfilling and road construction ongoing.

• Lane 20 - Underground installation and backfill 100% complete. Closed to traffic.

• Lane 24 – Underground installation commenced. 15% complete.

Plan for Next 2 weeks:

• Silica Place – Concrete sidewalks to be poured at Silin Forest Drive intersection and driveways completed.

• Silica Place SW leg – Road structure to be built and sidewalks installed. Will be done at same time as Silica Place

• Lane 24 - Underground installation to be completed.

Detour/Road Closure Details:

• Silica Place – Entrance at Silin Forest Drive will remain open until Lane 20 can be reopened as a detour.

• Silica Place SW leg – Will remain closed until road is paved.

• Lane 20 – Will be closed to vehicles until underground installation is complete.

17 July 27, 2017

Page 20: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name: UIR 2014-16 – C8 Project Manager: Ihsan-Ul Haq

Start Date: 8/7/2016 Completion Date: 8/31/2017

Project Phase: Construction Contractor Name: E Construction

Road Closure: ☐Full ☐ Partial ☐ Both ☐No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• Rehab of Manning Avenue (Richard Street to Morrison Street & MacIver Street to McLeod Street) Milestone Complete:

• Work is substantially complete.

Current Progress to date:

• Manning Avenue (Richard Street to Morrison Street) – Underground, bottom lift asphalt and concrete complete. Atco Electric completing TAC design of streetlights. Streetlights to be relocated to allow existing separate sidewalk to be widened to meet RMWB standards. Top lift asphalt to be completed. Manning Avenue (MacIver Street to McLeod Street) – Top lift asphalt has been completed.

Plan for Next 2 weeks:

• Manning Avenue (Richard Street to Morrison Street) – Top lift asphalt to be planned. To be confirmed by E-Construction.

• Manning Avenue (MacIver Street to McLeod Street) - No activity Planned. Complete. Detour/Road Closure Details:

• Manning Avenue (Richard Street to Morrison Street) – Top lift asphalt to be planned. To be confirmed by E-Construction..

• Manning Avenue (MacIver Street to McLeod Street) - No activity Planned.

18 July 27, 2017

Page 21: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name: UIR 2014-16 – C13 Project Manager: Yogesh Acharya

Start Date: 4/26/2016 Completion Date: 11/30/2017

Project Phase: Construction Contractor Name: H Wilson

Road Closure: ☒Full ☐ Partial ☐ Both ☐No Detour Plan: ☒Yes ☐Not Required

Project Status Scope:

• Road, Sanitary and water Rehab at Caldwell crescent and Cowley Bay. Milestone Complete:

• It is about 45% completed.

Current Progress to date:

• Laneway parallel to Cornwall Drive – Work completed in 2016

• Cowley Bay – 50% of work completed in 2016. The remainder will be completed as Phase 2 of 2017 construction.

• Caldwell Crescent – Contractor H.Wilson closed down 150m of Caldwell Crescent from Cornwall Drive (Deep Road). Water and storm lines have been installed as far as the Caldwell Crescent landscaped island. Backfilling is following on behind underground installation.

Plan for Next 2 weeks:

• Caldwell Crescent – Phase 1 installation including underground completion to Caldwell Crescent landscaped island. Phase 2 start which will complete construction on.

• Cowley Bay - Phase 2 start which will complete construction on Cowley Bay.

Detour/Road Closure Details:

• 150m of Caldwell Crescent from Cornwall Drive (Deep Road) will remain closed

• Preparations will be made for 2017 Phase 2 construction in Cowley Bay and construction may start depending on Phase 1 progress and weather.

19 July 27, 2017

Page 22: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name: UIR 2014-16 – C2 Project Manager: Malik Lasker

Start Date: 8/5/2015 Completion Date: 8/31/2017

Project Phase: Construction Contractor Name: H Wilson

Road Closure: ☐Full ☐ Partial ☐ Both ☒No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• Rehab of McKenzie, King Street, and Grayling Crescent Milestone Complete:

• Substantially Complete

Current Progress to date:

• McKenzie King Street –Complete

• Grayling Crescent - Underground, concrete, landscaping and bottom lift asphalt complete

Plan for Next 2 weeks:

• McKenzie King Street – Complete.

• Grayling Crescent – Top Lift Asphalt and concrete swales to be started. Landscaping deficiencies to be addressed.

Detour/Road Closure Details:

There will be partial closures required on Grayling Crescent for top lift asphalt. Contractor to apply for Utility Installation Permit and confirm schedule.

20 July 27, 2017

Page 23: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name: UIRP 2017 – C1 Project Manager: Muhammad Asghar

Start Date: 5/30/2017 Completion Date: 11/13/2017

Project Phase: Construction Contractor Name: Bird Construction

Road Closure: ☒Full ☐ Partial ☐ Both ☐No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• Rehab of Becker Cres, Parmenter Cres, Leigh Cres, Oaks Cresc & Brintnell Road. Milestone Complete:

• Piping work complete at Oaks Crescent.

• 100% of piping work is complete on Parmenter Crescent.

• Construction started on Becker Crescent July 12 Current Progress to date:

• Oaks Crescent - Sidewalks have been poured and asphalt is being laid July 17.

• Parmenter Crescent - Final underground is being completed. The first 200m of street has road structure completed and is ready for concrete sidewalks.

• Becker Crescent – Phase 1 of the road was closed on July 12. First section of asphalt has been stripped. Plan for Next 2 weeks:

• Oaks Crescent - Landscaping and driveways to be completed.

• Parmenter Crescent – Concrete Sidewalks July 28, Asphalt Bottom Lift August 4.

• Becker Crescent Phase 1 – Underground installation scheduled for completion August 17.

• Construction on Brintnell will start from August 2, 2017.

• Construction on Leigh will start from September 20, 2017. Detour/Road Closure Details:

• Oaks Crescent should be open to public this week.

• There will be a full closure on roads during construction.

21 July 27, 2017

Page 24: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name: UIRP 2017 – C3 Project Manager: Muhammad Asghar

Start Date: 6/5/2017 Completion Date: 10/10/2017

Project Phase: Construction Contractor Name: H. Wilson

Road Closure: ☒Full ☐ Partial ☐ Both ☐No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• Rehab of Deep Road, Castle Ridge Lane & Timberline Drive PUL. Milestone Complete:

• Underground work (water and storm) is complete 100% at Deep Road. Current Progress to date:

• Phase 1-Deep Road – subbase and granular base is complete, continue working on concrete sidewalks.

• Phase 1 –Castle Ridge Lane –installing water, sanitary and services. Plan for Next 2 weeks:

• Asphalt paving at Deep Road (Phase1) is scheduled for the next week (July 24 –July 30).

• Deep Road (Phase2) - pavement structure removal is scheduled for July 24.

• Castle Ridge Lane (Phase 1) – continue installing water and sanitary and planning to complete underground work by August 3.

Detour/Road Closure Details:

• There will be a full closure on roads during construction.

22 July 27, 2017

Page 25: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name: UIRP – C4 Project Manager: Malik Lasker

Start Date: 6/16/2017 Completion Date: 9/30/2017

Project Phase: Construction Contractor Name: OCL Group

Road Closure: ☒Full ☐ Partial ☐ Both ☐No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• Rehab of Hill Drive and McLeod Street Milestone Complete:

• Work not yet completed

Current Progress to date:

• Hill Drive – 1st phase of underground is in progress

Plan for Next 2 weeks:

• Hill Drive– 1st phase of underground is planned to be completed by August 1, 2017, the contractor is planning to complete subbase preparation.

Detour/Road Closure Details:

• 1st phase of Hill Drive should be opened on August 2,2017

• Entire Hill Drive should be opened on September 2, 2017

23 July 27, 2017

Page 26: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination

Sheet Project Information Date: 7/18/2017 Project/Contract Name: UIRP 2017– C5 Project Manager: Malik Lasker

Start Date: 6/1/2017 Completion Date: 10/14/2017

Project Phase: Construction Contractor Name: E Construction

Road Closure: ☒Full ☐ Partial ☐ Both ☐No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• Rehab of Poplar Crescent, Crescent Heights/Biggs Ave and Rae Crescent Milestone Complete:

• Underground work (water, sanitary and storm) on Poplar Crescent is complete 100%

Current Progress to date:

• Poplar Crescent – continue trench backfilling, preparing for subbase

• Crescent Heights/Biggs Avenue – removing pavement structure

Plan for Next 2 weeks:

• Poplar Crescent – subbase and base course preparation will start on July 26, concrete work is scheduled for August 1, asphalt paving is scheduled on August 8.

• Crescent Heights/Biggs Avenue – underground work is scheduled on July 28,2017

Detour/Road Closure Details:

• Poplar Crescent should be opened by August 15

• Crescent Heights/Biggs Avenue should be opened on September 22, 2017

• Rae Crescent should be opened on October 12, 2017

24 July 27, 2017

Page 27: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name:

RIRP 2015-2017 Anzac C:2 Pipes & Road rehabilitation on the North & South half of Anzac

Project Manager: Adel Youssef

Start Date: 9/15/2017 Completion Date: 9/30/2019

Project Phase: Construction Contractor Name: Tender Phase

Road Closure: ☐Full ☐ Partial ☐ Both ☐No Detour Plan: ☐Yes ☐Not Required

Project Status Scope:

• Construct the roads in the rural areas within the hamlets of Anzac, water piping and the sewer collection system. Pipes & road rehabilitation will be on the North & South half of Anzac.

Milestone Complete:

• 0.00%

Current Progress to date: • Tender Phase

Plan for Next 2 weeks:

• Close the tender

Detour/Road Closure Details:

• N/A

25 July 27, 2017

Page 28: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/19/2017 Project/Contract Name:

Rural Servicing Conklin-Contract 3 -Pine Lane

Project Manager:

Mansoor Shaikh

Start Date: 8/7/2017 Completion Date:

12/28/2018

Project Phase: Construction Contractor Name:

In-Line contracting Partnership

Road Closure: ☐Full ☒ Partial ☐ Both ☐No Detour Plan: ☐Yes ☐Not Required

Project Status Scope:

• Provide Water and sewer services to Pine Lane Area in Conklin. Involves Water and Sewer Network and Road Rehab.

Milestone Complete:

• Tender Process

Current Progress to date:

• In process of awarding the contract. P-Req has been approved.

Plan for Next 2 weeks:

• Complete award process and plan for kick off Detour/Road Closure Details:

• There will be a partial closure on Pine Lane and surrounding areas.

26 July 27, 2017

Page 29: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/18/2017 Project/Contract Name: GLE Contract 1 Project Manager: Maureen Nakonechny

Start Date: 7/4/2017 Completion Date: 11/30/2017

Project Phase: Construction Contractor Name: Knelsen/R.Ex

Road Closure: ☐Full ☒ Partial ☐ Both ☐No Detour Plan: ☐Yes ☐Not Required

Project Status Scope:

• Water and sewer install for all of Gregoire Lake Estates

• Upgrade to curb and gutter, and full road rehab Milestone Complete:

• None to date

Current Progress to date:

• Contractor not yet mobilized – waiting for shallow utilities

Plan for Next 2 weeks:

• Mobilize and start construction

Detour/Road Closure Details:

• Partial closure on Gregoire Ave and Poplar Crescent

27 July 27, 2017

Page 30: CONSTRUCTION UPDATE JULY 27, 2017 LegendUpdate+July+27+2017.pdfCONSTRUCTION UPDATE JULY 27, 2017 Legend 1) ... E Construction Ltd. ... Storm and Water piping are complete

Project/Contract Construction Coordination Sheet Project Information Date: 7/17/2017 Project/Contract Name:

Thickwood Blvd – Abasand Drive Erosion Remediation -Construction

Project Manager: Joseph Zachariah

Start Date: TBD Completion Date: TBD

Project Phase: Construction Contractor Name: TBD

Road Closure: ☐Full ☐ Partial ☐ Both ☒No Detour Plan: ☐Yes ☒Not Required

Project Status Scope:

• Erosion remediation work behind the curb on Thickwood Blvd and Abasand Drive between the HWY interface and top of the hill. Includes grading, landscaping & concreting behind the curbs.

Milestone Complete:

• Tender closed on July 13, 2017

Current Progress to date:

• Bid evaluation in progress.

Plan for Next 2 weeks:

• Complete bid evaluation & award the construction contract.

Detour/Road Closure Details:

• None at this point

28 July 27, 2017