construction update city council meeting october 26, 2010
DESCRIPTION
Construction Update City Council Meeting October 26, 2010. Coming Attractions Spring 2011. Project Milestones. Underground Work Complete Pacific/Hall New Signal Operational 10/12 Pacific/Greenburg/Main Signal 10/28 Paving and sidewalks as weather allows - PowerPoint PPT PresentationTRANSCRIPT
Construction UpdateCity Council Meeting
October 26, 2010
Coming Attractions Spring 2011
• Underground Work Complete• Pacific/Hall New Signal Operational 10/12• Pacific/Greenburg/Main Signal 10/28• Paving and sidewalks as weather allows• Finishing Touches in Spring, 2011• New travel lanes could open earlier
Project Milestones
• Project Hotline 503-846-7807• http://www.tigard-or.gov/pacifichwy_99w• http://twitter.com/99W_Tigard• Or Call Our Project Managers– Dan Erpenbach 503-846-7877– Mike McCarthy 503-718-2462
Ways to Stay Informed
Pavement Management Program – Slurry Seal
Pavement Management Program – Overlay
• Sequoia Pkwy (Cardinal to Upper Boones)• 72nd Ave (Baylor to Beveland)• 121st Ave (Springwood to Scholls Ferry)• Pfaffle Street (Hall to Pacific Hwy 99W)
2010 PMP Pavement Overlays
Construction UpdateCity Council Meeting
October 26, 2010