Building the Future
Current Activities this Week:
Underground Utilities:
Area 3 - Deep underground Plumbing continues.
Foundations:
Area 2 Concourse Level – Excavation for remaining D-Line
footing has started.
Concrete Flatwork:
Area 4 Field Level – Prep work for lower dock slab on
grade has started.
Structural Steel Erection:
Area 3 – Main Canopy Truss Erection are set to Column
Line 1. Area 4 – Metal decking installation in Sequence
3-3 has started. Field Level Area 1 – Subroof decking
installation is ongoing
MEP Rough-in:
Area 3 – Shallow electrical and plumbing rough-in is
ongoing. West Building - Ductwork installation on
Concourse, Suite and Press Levels are ongoing.
Plumbing rough-in is ongoing on Suite and
Press Levels. Fire Protection rough-in is ongoing on
Concourse, Suite and Press Levels. Electrical rough-in is
ongoing on Concourse, Suite and Press Levels.
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels are ongoing. Exterior metal stud framing
and sheathing installation is ongoing at Field, Suite, and
To: David Ficklin - OnGoal
Rory O’Connor – OnGoal
Lee Turner – OnGoal
Andy Heitmann – Turner
Dave Dudzik - Turner
From: Brandon Valdez
Office: Kansas City
Date: 9.15.2010
Re: Wizards Stadium Project
Update – Week of
9.13.2010
Area 3 – Underground plumbing installation
is nearly complete at the lower dock area.
Area 4 – Decking being installed at North
Elevation.
Area 2 – CMU perimeter wall installation at
Stage are nearly topped out.
Building the Future
Press Levels.
Masonry:
Area 1 Field Level – Masonry wall installation is ongoing
in Areas E, F, G and H.
Area 1, 2, 3 Concourse Level – Masonry wall installation at
Main Concourse Buildings are ongoing.
Curtainwall:
Area 1 – Curtainwall framing installation will continue
at West Elevation. Installation of Curtainwall glass is
ongoing.
Projected Activities occurring next Week:
Underground Utilities:
Deep Plumbing installation will continue in Area 3, moving
to the north.
Foundations:
Area 4 Field Level – Foundation wall installation for Main
Stair will begin.
Concrete Flatwork:
Area 3 Field Level – Concrete placement for Slab-on
Grade at lower dock area will begin. Prep work for slab-
on-grade for lower dock area will continue.
Area 3 and 4 Field Level – Installation of on-grade seating
risers and intermediate stairs will continue.
Structural Steel Erection:
Area 2 – Canopy truss installation at North side of Stadium
will continue.
MEP Rough-in:
MEP Rough-in at Concourse, Suite and Press Levels will
continue. Ductwork installation on Concourse, Suite, and
Press Level will continue. Fire Sprinkler installation will
continue on Concourse, Suite and Press Levels.
Field Level Area 3 – Formwork for Stairs to
Cauldron Club is set.
Area 1/2 – Filled and polished CMU Block
walls at the Southwest and South Concourse
Buildings.
Area 3 – Canopy Truss erection is nearly
complete in Sequence 3-5.
Building the Future
Metal Stud Framing:
Area 1 – Metal stud framing for Field, Concourse, Suite
and Press Levels will continue. Exterior Framing and
sheathing installation will continue.
Curtainwall:
Area 1 – Curtain Framing and Glass installation will
continue.
Area 1 – Installation of curtainwall framing
at Stair 4.
Area 1 – Shot of the west building showing
the progress of the canopy decking on
trusses.
Building the Future
Additional Photos:
Field Level Area 3 – Upper Dock concrete is
placed.
Concourse Level Area 3 – Exterior CMU walls
started northeast Concession and Men’s
Restroom Buildings.
Field Level Area 1 – Subroof decking
installation is ongoing.
Bowl – Shot of the bowl from the roof of the
Stadium Suite, showing the elevation
change of the canopy trusses.
Area 3 – 300 Ton Crane lifting Column Line 1
Truss into place.
Suite Level Area 1 – Metal stud framing and
in wall MEP rough-in is ongoing.