Building the Future Current Activities this Week : Underground Utilities : Area 3 - Deep underground Plumbing continues. Foundations : Area 2 Concourse Level – Excavation for remaining D-Line footing has started. Concrete Flatwork : Area 4 Field Level – Prep work for lower dock slab on grade has started. Structural Steel Erection : Area 3 – Main Canopy Truss Erection are set to Column Line 1. Area 4 – Metal decking installation in Sequence 3-3 has started. Field Level Area 1 – Subroof decking installation is ongoing MEP Rough-in: Area 3 – Shallow electrical and plumbing rough-in is ongoing. West Building - Ductwork installation on Concourse, Suite and Press Levels are ongoing. Plumbing rough-in is ongoing on Suite and Press Levels. Fire Protection rough-in is ongoing on Concourse, Suite and Press Levels. Electrical rough-in is ongoing on Concourse, Suite and Press Levels. Metal Stud Framing : Area 1 – Metal stud framing for Field, Concourse, Suite and Press Levels are ongoing. Exterior metal stud framing and sheathing installation is ongoing at Field, Suite, and To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner From: Brandon Valdez Office: Kansas City Date: 9.15.2010 Re: Wizards Stadium Project Update – Week of 9.13.2010 Area 3 – Underground plumbing installation is nearly complete at the lower dock area. Area 4 – Decking being installed at North Elevation. Area 2 – CMU perimeter wall installation at Stage are nearly topped out.

Upload: kansas-city-wizards

Post on 26-Jun-2015

145 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Construction Update 09-15-2010

Building the Future

Current Activities this Week:

Underground Utilities:

Area 3 - Deep underground Plumbing continues.

Foundations:

Area 2 Concourse Level – Excavation for remaining D-Line

footing has started.

Concrete Flatwork:

Area 4 Field Level – Prep work for lower dock slab on

grade has started.

Structural Steel Erection:

Area 3 – Main Canopy Truss Erection are set to Column

Line 1. Area 4 – Metal decking installation in Sequence

3-3 has started. Field Level Area 1 – Subroof decking

installation is ongoing

MEP Rough-in:

Area 3 – Shallow electrical and plumbing rough-in is

ongoing. West Building - Ductwork installation on

Concourse, Suite and Press Levels are ongoing.

Plumbing rough-in is ongoing on Suite and

Press Levels. Fire Protection rough-in is ongoing on

Concourse, Suite and Press Levels. Electrical rough-in is

ongoing on Concourse, Suite and Press Levels.

Metal Stud Framing:

Area 1 – Metal stud framing for Field, Concourse, Suite

and Press Levels are ongoing. Exterior metal stud framing

and sheathing installation is ongoing at Field, Suite, and

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

From: Brandon Valdez

Office: Kansas City

Date: 9.15.2010

Re: Wizards Stadium Project

Update – Week of

9.13.2010

Area 3 – Underground plumbing installation

is nearly complete at the lower dock area.

Area 4 – Decking being installed at North

Elevation.

Area 2 – CMU perimeter wall installation at

Stage are nearly topped out.

Page 2: Construction Update 09-15-2010

Building the Future

Press Levels.

Masonry:

Area 1 Field Level – Masonry wall installation is ongoing

in Areas E, F, G and H.

Area 1, 2, 3 Concourse Level – Masonry wall installation at

Main Concourse Buildings are ongoing.

Curtainwall:

Area 1 – Curtainwall framing installation will continue

at West Elevation. Installation of Curtainwall glass is

ongoing.

Projected Activities occurring next Week:

Underground Utilities:

Deep Plumbing installation will continue in Area 3, moving

to the north.

Foundations:

Area 4 Field Level – Foundation wall installation for Main

Stair will begin.

Concrete Flatwork:

Area 3 Field Level – Concrete placement for Slab-on

Grade at lower dock area will begin. Prep work for slab-

on-grade for lower dock area will continue.

Area 3 and 4 Field Level – Installation of on-grade seating

risers and intermediate stairs will continue.

Structural Steel Erection:

Area 2 – Canopy truss installation at North side of Stadium

will continue.

MEP Rough-in:

MEP Rough-in at Concourse, Suite and Press Levels will

continue. Ductwork installation on Concourse, Suite, and

Press Level will continue. Fire Sprinkler installation will

continue on Concourse, Suite and Press Levels.

Field Level Area 3 – Formwork for Stairs to

Cauldron Club is set.

Area 1/2 – Filled and polished CMU Block

walls at the Southwest and South Concourse

Buildings.

Area 3 – Canopy Truss erection is nearly

complete in Sequence 3-5.

Page 3: Construction Update 09-15-2010

Building the Future

Metal Stud Framing:

Area 1 – Metal stud framing for Field, Concourse, Suite

and Press Levels will continue. Exterior Framing and

sheathing installation will continue.

Curtainwall:

Area 1 – Curtain Framing and Glass installation will

continue.

Area 1 – Installation of curtainwall framing

at Stair 4.

Area 1 – Shot of the west building showing

the progress of the canopy decking on

trusses.

Page 4: Construction Update 09-15-2010

Building the Future

Additional Photos:

Field Level Area 3 – Upper Dock concrete is

placed.

Concourse Level Area 3 – Exterior CMU walls

started northeast Concession and Men’s

Restroom Buildings.

Field Level Area 1 – Subroof decking

installation is ongoing.

Bowl – Shot of the bowl from the roof of the

Stadium Suite, showing the elevation

change of the canopy trusses.

Area 3 – 300 Ton Crane lifting Column Line 1

Truss into place.

Suite Level Area 1 – Metal stud framing and

in wall MEP rough-in is ongoing.