construction site earthwork calculation

Upload: masteriraga

Post on 04-Jun-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 Construction Site Earthwork Calculation

    1/4

    11/29/13 Construction Site Earthwork Calculation

    www.nbmcw.com/equipments/surveying-testing/29427-construction-site-earthwork-calculation.html 1/4

    With advancement of Technology there is a lot of progress in the way we take Ground reading. Earlier

    only Auto Levels were used, whereas now Total Station, GPS, LIDAR are being used to take ground

    reading. Previously Earthwork Calculations were simply done on paper followed by some simple

    computer applications. Now, however, either Spread Sheets likes Excel are used or advanced software

    products which are specifically designed for earthwork calculation are used. But volumetric calculations

    done by software still have to presented in understandable manner even while getting different results

    from different software products.

    There are three different methods popularly used for doing Earthwork Calculation for Cutting/FillingProjects. Before discussing these in detail let us try to understand Some Basic definition of Terms

    related to Earthwork Calculation.

    Earthworks

    Earthworks are engineering works created through the moving and/or process ing of massive quantities

    of soil or unformed rock. Earthwork is done to reconfigure the topography of a site to achieve the

    design levels. Earthwork involves cutting and filling to achieve the required topography.

    Cutting

    Cutting is the process of excavating earth material from a work location to achieve the desiredtopography.

    Filling

    Filling is the process of moving the excavated material or additional earth material to a work location to

    achieve the desired topography.

    Let us take 2 Simple Examples for our Study

    In the Example below the plot is 30 X 30 Meters and all the Grid levels measured at Grid level of

    10M

    Example 1 (Only Cutting)

    Ground Level

    Section 0 10 20 30

    30192.51193.71193.21193.47

    20193.04193.14192.92193.01

    10192.61192.56192.63192.67

    0192.56192.68192.67192.57

    Formation Level

    191.9 193.1 192.6192.87192.43192.53192.31 192.4

    192.01191.96192.03192.06

    191.95192.07192.07191.97

    Example 2 (Both Cutting andFilling)

    Ground Level

    192.51 193.71 193.21 193.47

    193.04 193.14 192.92 193.01

    192.61 192.56 192.63 192.67

    192.56 192.68 192.67 192.57

    Formation Level

    193.4 193.5 193.3 193.2193.5 193.3 193.2 193.4

    193.4 193.6 193.4 193.4

    193.1 193.4 193.5 193.3

    Average method:

    In this method Levels at each grid point is found out. Difference between the Average of Two Sets of

    Levels multiplied by Area gives the Result. This is a very simple and straight forward method. But this

    can be used only when there is cutting or filling. When Leveling of surface includes both cutting and

    filling, Average method gives wrong result as cutting and filling values nullify each other whileaveraging.

    Example 1(Only Cutting)

    Filling

    Example 2 (Both Cutting andFilling)

  • 8/13/2019 Construction Site Earthwork Calculation

    2/4

    11/29/13 Construction Site Earthwork Calculation

    www.nbmcw.com/equipments/surveying-testing/29427-construction-site-earthwork-calculation.html 2/4

    0 0 0 0

    0 0 0 0

    0 0 0 0

    0 0 0 0

    Average 0 0

    Cutting

    0.61 0.61 0.61 0.60.61 0.61 0.61 0.61

    0.6 0.6 0.6 0.61

    0.61 0.61 0.6 0.6

    Average 0.606 545.62

    Filling

    00.21 0 0.27

    0 0 0 0

    0 0 0 0

    0 0 0 0

    Average 0.03 27

    Cutting

    0.89 0 0.09 00.460.16 0.28 0.39

    0.791.04 0.77 0.73

    0.540.72 0.83 0.73

    Average0.526 473.625

    Volume = Average * 900 = 0.606 * 900 = 545.62

    Block Method (Division of Square Method):

    In this method, volume of cutting or filling is found out for each block and added together to get thefinal volume. This is mathematically simpler then Section Method, but more accurate than Average

    method. The problem of nullification is also encountered here when in the same block there is both

    cutting and filling. But here the margin of error is very small when compared to Average method for

    whole area.

    Example 1(Only Cutting):

    Difference in Average for Each 10 X 10 Block

    0.61 0.61 0.6075

    0.605 0.605 0.6075

    0.605 0.6025 0.6025

    Volume = Sum * 100 (Area of Each block) = 5.455 * 100 = 545.5 (Cutting)

    Note: Value 0.61 = Average (192.51, 193.71, 193.04, 193.14) Average (191.9, 193.1, 192.43, 192.53)

    [Values taken from first 2 rows and 2 columns of ground and formation level)

    Example 2 (Both Cutting and Filling) :

    Difference in Average for Each 10 X 10 Block

    0.325 0.08 0.1225

    0.6125 0.5625 0.54250.7725 0.84 0.765

    Volume = Sum * 100 (Area of Each block) = 4.6225 * 100 = 462.25 (Filling).

    Note: Although in this example there is some cutting, because of nullification of value in same block we

    are not getting any value in Cutting.

    Section Method:

    In this method Sections are drawn for Each Line of Value. Area of Cutting and Filling is found out for

    each Section w ith Trapezoidal Method or Nett Area Calculation Method. Then volume is de termined bymultiplying Average Area w ith Distance between Sections. This method is more accurate, but for larger

    area, finding the area becomes difficult as we need to find intersection of points where lines

    representing Surfaces meet.

  • 8/13/2019 Construction Site Earthwork Calculation

    3/4

    11/29/13 Construction Site Earthwork Calculation

    www.nbmcw.com/equipments/surveying-testing/29427-construction-site-earthwork-calculation.html 3/4

    Example 1(Only Cutting):

    Sl.

    No.Section

    Cutting Volume Filling Volume

    Area

    Sq. Mtrs

    Previous

    Area

    Average

    Sq. Mtrs

    Volume

    Cu Meters

    Area

    Sq. Mtrs

    Previous

    Area

    Average

    Sq. Mtrs

    Volume

    Cu Meters

    1 0.000 18.150 0.000 9.075 0.000 0.000 0.000 0.000 0.000

    2 10.000 18.050 18.150 18.100 181.000 0.000 0.000 0.000 0.000

    3 20.000 18.300 18.050 18.175 181.750 0.000 0.000 0.000 0.000

    4 30.000 18.250 18.300 18.275 182.750 0.000 0.000 0.000 0.000

    Total 545.500 0.000

    Sections Related to Example 2 (Both Cutting and Filling) :

    Example 2 (Both Cutting and Filling) :

    Sl.

    No.Section

    Cutting Volume Filling Volume

    Area

    Sq. Mtrs

    Previous

    Area

    Average

    Sq. Mtrs

    Volume

    Cu Meters

    Area

    Sq. Mtrs

    Previous

    Area

    Average

    Sq. Mtrs

    Volume

    Cu Meters

    1 0.000 0.000 0.000 0.000 0.000 21.850 0.000 10.925 0.000

    2 10.000 0.000 0.000 0.000 0.000 25.700 21.850 23.775 237.750

    3 20.000 0.000 0.000 0.000 0.000 8.650 25.700 17.175 171.750

    4 30.000 1.948 0.000 0.974 9.740 3.848 8.650 6.249 62.490

    Total 9.740 471.990

    Summary of Results

    Sl. Method Example 1 Example 2

    Cutting Filling Cutting Filling

    1 Average Method 545.62 0 27.000 473.625

    2 Block method 545.5 0 0.000 462.25

    3 Section Method 545.500 0 9.740 471.990

    Summary of Various Methods

    Methods /

  • 8/13/2019 Construction Site Earthwork Calculation

    4/4

    11/29/13 Construction Site Earthwork Calculation

    www.nbmcw.com/equipments/surveying-testing/29427-construction-site-earthwork-calculation.html 4/4

    Methods Formula Advantages Disadvantages Applicability

    Average

    Method

    Volume=Depth of

    cutting/filling*

    area

    Easiest Method for

    calculation

    Approximate,

    cannot be

    applied when

    both cutting

    and filling are

    there

    Used for very small

    projects

    Block

    Method

    Volume=Sum of(Depth o f

    cutting/filling*

    area of each

    block)

    It Is very easy to

    calculate the area

    Box method willnullify volume when

    both cutting and

    filling are there in

    the same block

    Commonly used to

    find volume for

    leveling projects

    before the

    construction of a

    building

    Section

    Method

    Area to be found

    out using

    Trapezoidal

    Method

    Nett area

    Method

    Volume =

    Lx1/2(A1+ A2)

    Mathematically,

    very good and

    hence adopted in

    majority of

    infrastructureprojects

    Involves a lot of

    calculations

    Used in most of the

    infrastructure

    Projects including

    Roads, Irrigation

    Projects, Rail RoadProjects, etc.

    Conclusion

    From the above examples, we can conclude that Section Method is complex compared to any other

    method but gives accurate results. Also if the Average method or Block Method is used for calculation

    then it is likely that Volume w ill be little lesser and the contractor will get lesser quantity and hence less

    payment for his work.