construction site earthwork calculation
TRANSCRIPT
-
8/13/2019 Construction Site Earthwork Calculation
1/4
11/29/13 Construction Site Earthwork Calculation
www.nbmcw.com/equipments/surveying-testing/29427-construction-site-earthwork-calculation.html 1/4
With advancement of Technology there is a lot of progress in the way we take Ground reading. Earlier
only Auto Levels were used, whereas now Total Station, GPS, LIDAR are being used to take ground
reading. Previously Earthwork Calculations were simply done on paper followed by some simple
computer applications. Now, however, either Spread Sheets likes Excel are used or advanced software
products which are specifically designed for earthwork calculation are used. But volumetric calculations
done by software still have to presented in understandable manner even while getting different results
from different software products.
There are three different methods popularly used for doing Earthwork Calculation for Cutting/FillingProjects. Before discussing these in detail let us try to understand Some Basic definition of Terms
related to Earthwork Calculation.
Earthworks
Earthworks are engineering works created through the moving and/or process ing of massive quantities
of soil or unformed rock. Earthwork is done to reconfigure the topography of a site to achieve the
design levels. Earthwork involves cutting and filling to achieve the required topography.
Cutting
Cutting is the process of excavating earth material from a work location to achieve the desiredtopography.
Filling
Filling is the process of moving the excavated material or additional earth material to a work location to
achieve the desired topography.
Let us take 2 Simple Examples for our Study
In the Example below the plot is 30 X 30 Meters and all the Grid levels measured at Grid level of
10M
Example 1 (Only Cutting)
Ground Level
Section 0 10 20 30
30192.51193.71193.21193.47
20193.04193.14192.92193.01
10192.61192.56192.63192.67
0192.56192.68192.67192.57
Formation Level
191.9 193.1 192.6192.87192.43192.53192.31 192.4
192.01191.96192.03192.06
191.95192.07192.07191.97
Example 2 (Both Cutting andFilling)
Ground Level
192.51 193.71 193.21 193.47
193.04 193.14 192.92 193.01
192.61 192.56 192.63 192.67
192.56 192.68 192.67 192.57
Formation Level
193.4 193.5 193.3 193.2193.5 193.3 193.2 193.4
193.4 193.6 193.4 193.4
193.1 193.4 193.5 193.3
Average method:
In this method Levels at each grid point is found out. Difference between the Average of Two Sets of
Levels multiplied by Area gives the Result. This is a very simple and straight forward method. But this
can be used only when there is cutting or filling. When Leveling of surface includes both cutting and
filling, Average method gives wrong result as cutting and filling values nullify each other whileaveraging.
Example 1(Only Cutting)
Filling
Example 2 (Both Cutting andFilling)
-
8/13/2019 Construction Site Earthwork Calculation
2/4
11/29/13 Construction Site Earthwork Calculation
www.nbmcw.com/equipments/surveying-testing/29427-construction-site-earthwork-calculation.html 2/4
0 0 0 0
0 0 0 0
0 0 0 0
0 0 0 0
Average 0 0
Cutting
0.61 0.61 0.61 0.60.61 0.61 0.61 0.61
0.6 0.6 0.6 0.61
0.61 0.61 0.6 0.6
Average 0.606 545.62
Filling
00.21 0 0.27
0 0 0 0
0 0 0 0
0 0 0 0
Average 0.03 27
Cutting
0.89 0 0.09 00.460.16 0.28 0.39
0.791.04 0.77 0.73
0.540.72 0.83 0.73
Average0.526 473.625
Volume = Average * 900 = 0.606 * 900 = 545.62
Block Method (Division of Square Method):
In this method, volume of cutting or filling is found out for each block and added together to get thefinal volume. This is mathematically simpler then Section Method, but more accurate than Average
method. The problem of nullification is also encountered here when in the same block there is both
cutting and filling. But here the margin of error is very small when compared to Average method for
whole area.
Example 1(Only Cutting):
Difference in Average for Each 10 X 10 Block
0.61 0.61 0.6075
0.605 0.605 0.6075
0.605 0.6025 0.6025
Volume = Sum * 100 (Area of Each block) = 5.455 * 100 = 545.5 (Cutting)
Note: Value 0.61 = Average (192.51, 193.71, 193.04, 193.14) Average (191.9, 193.1, 192.43, 192.53)
[Values taken from first 2 rows and 2 columns of ground and formation level)
Example 2 (Both Cutting and Filling) :
Difference in Average for Each 10 X 10 Block
0.325 0.08 0.1225
0.6125 0.5625 0.54250.7725 0.84 0.765
Volume = Sum * 100 (Area of Each block) = 4.6225 * 100 = 462.25 (Filling).
Note: Although in this example there is some cutting, because of nullification of value in same block we
are not getting any value in Cutting.
Section Method:
In this method Sections are drawn for Each Line of Value. Area of Cutting and Filling is found out for
each Section w ith Trapezoidal Method or Nett Area Calculation Method. Then volume is de termined bymultiplying Average Area w ith Distance between Sections. This method is more accurate, but for larger
area, finding the area becomes difficult as we need to find intersection of points where lines
representing Surfaces meet.
-
8/13/2019 Construction Site Earthwork Calculation
3/4
11/29/13 Construction Site Earthwork Calculation
www.nbmcw.com/equipments/surveying-testing/29427-construction-site-earthwork-calculation.html 3/4
Example 1(Only Cutting):
Sl.
No.Section
Cutting Volume Filling Volume
Area
Sq. Mtrs
Previous
Area
Average
Sq. Mtrs
Volume
Cu Meters
Area
Sq. Mtrs
Previous
Area
Average
Sq. Mtrs
Volume
Cu Meters
1 0.000 18.150 0.000 9.075 0.000 0.000 0.000 0.000 0.000
2 10.000 18.050 18.150 18.100 181.000 0.000 0.000 0.000 0.000
3 20.000 18.300 18.050 18.175 181.750 0.000 0.000 0.000 0.000
4 30.000 18.250 18.300 18.275 182.750 0.000 0.000 0.000 0.000
Total 545.500 0.000
Sections Related to Example 2 (Both Cutting and Filling) :
Example 2 (Both Cutting and Filling) :
Sl.
No.Section
Cutting Volume Filling Volume
Area
Sq. Mtrs
Previous
Area
Average
Sq. Mtrs
Volume
Cu Meters
Area
Sq. Mtrs
Previous
Area
Average
Sq. Mtrs
Volume
Cu Meters
1 0.000 0.000 0.000 0.000 0.000 21.850 0.000 10.925 0.000
2 10.000 0.000 0.000 0.000 0.000 25.700 21.850 23.775 237.750
3 20.000 0.000 0.000 0.000 0.000 8.650 25.700 17.175 171.750
4 30.000 1.948 0.000 0.974 9.740 3.848 8.650 6.249 62.490
Total 9.740 471.990
Summary of Results
Sl. Method Example 1 Example 2
Cutting Filling Cutting Filling
1 Average Method 545.62 0 27.000 473.625
2 Block method 545.5 0 0.000 462.25
3 Section Method 545.500 0 9.740 471.990
Summary of Various Methods
Methods /
-
8/13/2019 Construction Site Earthwork Calculation
4/4
11/29/13 Construction Site Earthwork Calculation
www.nbmcw.com/equipments/surveying-testing/29427-construction-site-earthwork-calculation.html 4/4
Methods Formula Advantages Disadvantages Applicability
Average
Method
Volume=Depth of
cutting/filling*
area
Easiest Method for
calculation
Approximate,
cannot be
applied when
both cutting
and filling are
there
Used for very small
projects
Block
Method
Volume=Sum of(Depth o f
cutting/filling*
area of each
block)
It Is very easy to
calculate the area
Box method willnullify volume when
both cutting and
filling are there in
the same block
Commonly used to
find volume for
leveling projects
before the
construction of a
building
Section
Method
Area to be found
out using
Trapezoidal
Method
Nett area
Method
Volume =
Lx1/2(A1+ A2)
Mathematically,
very good and
hence adopted in
majority of
infrastructureprojects
Involves a lot of
calculations
Used in most of the
infrastructure
Projects including
Roads, Irrigation
Projects, Rail RoadProjects, etc.
Conclusion
From the above examples, we can conclude that Section Method is complex compared to any other
method but gives accurate results. Also if the Average method or Block Method is used for calculation
then it is likely that Volume w ill be little lesser and the contractor will get lesser quantity and hence less
payment for his work.