construction sector update jun 12 edel1
TRANSCRIPT
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
1/25
Edelweiss Research is also available on www.edelresearch.com,
Bloomberg EDEL , Thomson First Call, Reuters and Factset. Edelweiss Securities Limited
The ambitious Dedicated Freight Corridor (DFC) project, targeting
creation of high-capacity, high-speed railway corridors dedicated to
freight movement, boasts of being Indias largest-ever infrastructure
project. The Delhi-Mumbai and Delhi-Kolkata corridors, with an
estimated completion cost of ~INR900bn, are expected to revolutionise
freight transport in India. With a 2017-18 completion target, steady
progress in land acquisition and funding, we expect the next couple of
years to see a lot of action on the project award side. This will trigger
significant opportunities for EPC players like L&T, IVRCL, NCC, among
others, apart from giving a fillip to the countrys logistic network.
DFC development imperative as existing network grossly clogged
Saturation of existing railway capacity has led to congestion and loss of freight market
share for Indian Railways (from ~90% in 1950s to
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
2/25
Construction
2 Edelweiss Securities Limited
Dedicated Freight Corridor: The fine print
Dedicated Freight Corridor (DFC) is Indias largest-ever infrastructure project. It is being
piloted by the Dedicated Freight Corridor Corporation of India (DFCCIL), a wholly-owned
special purpose vehicle (SPV) of the Ministry of Railways. Its aim, in the first phase of the
project, is to construct over 3,300 kms of high-capacity, high-speed railway corridors
dedicated for freight movement along the Delhi-Mumbai (Western corridor) and Delhi-
Kolkata (Eastern corridor) rail routes. This phase is estimated to cost ~USD16bn.
Fig. 1: Proposed freight corridors in India
Source: Indian Railways, Edelweiss research
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
3/25
Construction
3 Edelweiss Securities Limited
In the future, four additional corridorsNorth-South Corridor (Delhi-Chennai, 2,173 kms),
East-West Corridor (Kolkata-Mumbai, 2,000 kms), East Coast Corridor (Kharagpur-
Vijayawada, 1,100 kms) and Southern Corridor (Chennai-Goa, 890 kms)are planned to be
undertaken by DFCCIL. The corporation has already engaged RITES to undertake feasibility
studies for these stretches. The latter has submitted the interim report for Preliminary
Engineering cum Traffic Survey work for these corridors.
Note: In this report, we have limited ourselves to 3,300 km corridors between Delhi-
Mumbai and Delhi-Kolkata.
Need for DFC: India lagging global peers in logistics infrastructure
India lags way behind when it comes to logistic infrastructure compared to global peers.
Logistics cost in India is at 13-14% of GDP compared to ~10% in developed countries.
Of more concern is the fact that logistic network development is not keeping pace with the
countrys economic growth (freight traffic generally has an elasticity of 1.25 to GDP
growth). As a result, in the World Bank logistic performance index, India has slipped to 46th
rank in 2012 compared to 39th position five years ago.
Chart 1: Average surface freight cost (in US cents) per tonne-km:
Source: KPMG-CII, Edelweiss research
When it comes to railways, Indias freight carrying efficiency is hampered by a lack of
investment in infrastructure.
Table 1: Comparison of carrying efficiency of railways
Source: Indian Railways, Edelweiss research
1.0
2.6
4.2
5.8
7.4
9.0
US Canada Japan Europe India
(cents/ton-km)
Average surface freight cost
Country India Developed worldAvg speed (kmph) 23.3 100
Capacity (TEUs) 90 150
Axle load of wagons (Tonnes) 22 30
Load capacity per wagon (Tonnes) 88 120
Pay load: Tare weight of wagon 2 - 2.6 4.5 - 5.5
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
4/25
Construction
4 Edelweiss Securities Limited
Thus, Indian Railway carries 450 kg of wagons dead weight for every 1,000 kg of freight
carried compared to only 170 kg in the US. This highlights the need of timely investment in
the countrys rail infrastructure.
A Mckinsey study on logistics in India had highlighted that there are seven high density
corridors in the country that carry 50% of freight traffic. These include the Golden
Quadrilaterals of Indian Railways as well as Phases I and II (GQ and NSEW) of the National
Highway Development Programme. Going ahead, the share of these corridors is projected
to inch even higher.
Fig. 2: Freight traffic concentrated along certain corridors
Source: Mckinsey, Edelweiss research
One of the ways suggested in the study to efficiently cope with the expected increase in
freight traffic, was the creation of dedicated freight corridors (DFCs).
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
5/25
Construction
5 Edelweiss Securities Limited
Fig. 3: DFC is the best alternative for freight management
Source: Mckinsey, Edelweiss research
The study had suggested creation of five DFCs which will have the following benefits:
DFCs are the most cost-effective way to add freight traffic capacity. The cost per tonne-km of capacity added by a DFC (around USD25-30mn) is lower than investments in
other modes (~45% lower per tonne-km than that of an equivalent build-out of
expressways and approximately one-third of that for new roads).
DFCs enable higher-quality service compared to other modes. At higher average speedsof 75 km per hour, DFCs can cut travel time on rail by up to 66%.
Reducing variability in transit times also significantly reduces inventory requirements.
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
6/25
Construction
6 Edelweiss Securities Limited
Meeting notes with DFCCIL
Mr. P N Shukla - Director
(Operations & Business Devp.),
DFCCIL
The Insider
We met Mr. P N Shukla, Director (Operations & Business Development), DFCCIL. Key
takeaways from our meeting:
Q. What is the basic purpose behind DFC?
A. The basic purpose behind DFC is to improve the freight carrying efficiency of IndianRailways. The Golden Quadrilateral carries freight of ~600 mtpa. Currently, both freight
and passenger trains run on the same network, which has resulted in average speed of
freight trains being low at ~25 km per hour. DFC will increase this by a factor of three. It
will also improve the carrying capacity of trains (from 4,000 tonnes/train currently to
15,000 tonnes/train).
Q. What are the main advantages of DFC?
A. DFC will result in increase in the freight carrying capacity of railways. It will also lower
the unit cost of operations apart from helping in development of multi-modal logistic
parks. Current network has a mix of passenger and freight facilities which has prevented
optimum utilisation. A dedicated logistic park for cargo services is expected to deal with
such problems by making expansion easier.
Also, the DFC will decongest the current network in a significant way. The effective
capacity of the DFC would be as high as ~600 mtpa due to enhanced design features,
double stacking etc.
Q. What will be the revenue model for DFC?
A. Indian Railways will be the sole user of DFC. DFC will not have any marketing rights of its
own. Indian Railways will pay DFC track access charges to ensure cost recovery for
DFCCIL. The track access agreement is under finalisation.
Q. What is the estimated cost of the project?
A. The estimated completion cost of the project is INR900bn. The Western corridor will
cost ~INR460bn while the Eastern corridor will cost ~INR440bn. The average cost of the
Western corridor at INR250mn/ km is higher than the INR200mn/km cost of Eastern
corridor due to more bridges and higher technical requirements.
Q. Which components are included in the completion cost?
A. The completion cost includes construction cost, interest during construction, taxes,
insurance, inflation etc. It does not include land acquisition cost which is estimated to be
~INR60bn. Land acquisition will be done directly by Indian Railways (under Government
of India) which will then make the land available to DFCCIL at a nominal cost.
Q. What will be the broad break-up of construction cost?
A. The construction cost can be broadly broken up into civil construction (65%), electrical
(20%) and signalling (15%) work.
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
7/25
Construction
7 Edelweiss Securities Limited
Q. What will be the funding arrangement for the same?
A. While JICA is funding the Western corridor, World Bank is funding the Eastern corridor.
The overall debt/equity earlier envisaged for the project was 2:1, which may eventually
be finalised at 1.2:1. The Eastern corridor will have a higher equity component than the
Western corridor.
Q. What are the various types of contracts in DFC?
A. There are basically four types of works needed to be done under DFC:
Civil construction, structures etc. Track works, sleepers etc. Overhead equipment (OHE). Signaling and systems work.
Q. What is the progress as far as tendering is concerned?
A. Package 1 & 2 (costing INR80-90bn) on Phase I of Western corridor will be awarded this
year. Similarly, Phase I on Eastern corridor (overall cost ~INR80-90bn and civilconstruction cost of INR60bn) is expected to be awarded by September 2012. The
Sonnagar-Dankuni project (~INR110bn) will be done on PPP basis for which the PPP
mode is under finalisation. We are evaluating a number of models (e.g. the annuity
mode of project award) for the same.
For the 109 km stretch between New Ganjkhwaja to New Karwandia, civil construction
contract had been awarded earlier. We are now in the process of awarding the package
for construction of track and related works for the 66km stretch from New Karwandiya
to Durgawati on the same section.
Q. What are the timelines for the project?
A. it will take ~4 years post contract award for the project to be completed. We expect that
a significant part of the corridor will be operational by 2017. We are focused on getting
the requisite clearances necessary for project award and expect to see meaningful
progress soon.
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
8/25
Construction
8 Edelweiss Securities Limited
Rationale: Declutter over burdened, saturated network
DFC is needed due to the following concerns:
Saturation of existing capacity: Indian Railways golden quadrilateral, which links thefour metros and two diagonals viz., Delhi-Chennai and MumbaiKolkata, accounts for
just 16% of the entire railway route in India, but carries 58% of the total freight and
52% of passenger traffic.
Specifically, Delhi-Kolkata and Delhi-Mumbai corridors are highly saturated with line
capacity utilisation varying between 115% and 150%. Chronic under investment in
capacity expansion has raised the spectre of choking of Indian Railways freight carrying
capacity.
The DFC project, once completed, will meet the transport requirements of the two busy
trunk routes for the next 15-20 years.
Loss of market share: Due to congestion in the railway network, rail transport, in spiteof being cheaper than road transport, has steadily lost market share. Indian Railways'
share in the freight transportation market has declined from 89% in 1950-51 to less
than 40% currently. Highways have been prime gainers, increasing their share from 11%to around 60% over the same period.
Chart 2: Share of different modes in freight transport across countries
Source: Mckinsey, Edelweiss research
The low share of railways is surprising given that 65% of Indias freight comprises bulk
commodities which move across long distances and thus can be more economically served
by rail transport. Also, about 80% of the bulk freight is transported (in tonne-km) over
distances of more than 400 km.
22
37
57
47
48
36
30
~146
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
9/25
Construction
9 Edelweiss Securities Limited
Chart 3: Break-up of bulk freight traffic in India as per distance travelled
Source: Mckinsey, Edelweiss research
Slow speeds: Indian Railways currently runs mixed traffic (passenger and freight) on itsexisting network. With passenger trains getting priority over goods trains, the average
speed of freight trains is limited to 22-25 kmph.
Need for a new approach: Keeping in mind the expected surge in freight traffic in thefuture and the need to eliminate logistic inefficiencies in the network, an integrated
approach like the DFC is required rather than the incremental approach which has been
followed historically by Indian Railways (putting up additional lines or improving
signaling in times of capacity constraints).
Advantages: Fast tracking growth
Faster freightmovement: DFC is expected to revolutionise freight movement. This willfructify via reduced congestion, a high-capacity efficient network and enhanced designfeatures, much superior to the current network. The table below gives a comparative
framework of the same:
0-400 km
19%
400-700 km
26%
> 700 km
55%
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
10/25
Construction
10 Edelweiss Securities Limited
Fig. 4: Comparison of existing rail network and DFC
Source: DFCCIL, Edelweiss research
As can be seen, DFCs superior capacity will emanate from bigger dimensions of
rolling stock as well as the networks improved design features. This will reduce
the unit cost of operations.
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
11/25
Construction
11 Edelweiss Securities Limited
Fig. 5: Comparison of DFC with competing modes
Source: Indian Railways, World Bank, Edelweiss research
Another advantage will be that freight trains on DFC can run at an average speed of
over 65 kmph against 22 kmph currently, thus limiting transit time.
Also, due to smaller workforce (one person per track km on DFC), latest loading
technology and efficiency of rolling stock, operating costs are expected to be half of the
existing railway system.
Superior planning and optimum network utilisation: Segregation of freight andpassenger traffic will enable better planning and optimum utilisation of the network,
resulting in faster movement of goods. This will also remove inefficiencies, as seen in
the current system, and save costs by eliminating uncertainties on transit time. This will
enhance railways freight market share with it becoming better suited for freight
movement over shorter distances.
Development of associated infrastructure: Multimodal logistic park (MMLPs) willenhance industrial development and create the necessary base for the Delhi-Mumbai
Industrial Corridor. They will act as hubs providing state-of-the-art integrated logistic
facilities. Features like mechanised handling and intelligent inventory management are
likely to reduce overall logistics costs. This will be further leveraged by the modern,
high-capacity rail connectivity of DFCs capable of meeting time-sensitive freight
transportation requirement.
A RITES report has suggested development of such parks at Rewari, Vapi, Navi Mumbai
and Ahmedabad on the Western corridor, and Ludhiana, Durgapur and Kanpur on theEastern corridor. These terminals will be set up as one-stop shops for all value-added
services like warehousing, packaging, custom bonding, etc.
Techno economic feasibility study for logistic parks at Ahmedabad, Navi Mumbai and
Kanpur has been taken up already.
With reduction in load on the existing network, Indian Railways can run additionalpassenger trains.
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
12/25
Construction
12 Edelweiss Securities Limited
Indirect benefits to economy: A 2007 study by the Japan International CooperationAgency (JICA) assessed the financial viability of DFC project. JICAs calculations, taking
into account the total investment cost, maintenance, and operation cost for 35 years,
indicates that the economic IRR was 13.95% for the Western corridor and 15.09% for
the Eastern corridor. The study judged the project as viable, given that 12% economic
IRR is considered a minimum base for considering a project feasible.
The financial IRR was 9.08% for the Western corridor and 15.59% for the Eastern
corridor. The economic IRR includes indirect benefits to the economy that are unlikely
to be ploughed back to investors, whereas the financial IRR measures the direct
financial benefits from the project over a 35 year cycle.
The business model: SPV structure
DFCCIL will enter into a concession agreement with the Ministry of Railways. The Indian
Railways will pay track access charges to the company. These charges will essentially cover
DFCCILs entire debt obligations as well as its operation and maintenance costs. The
corporation will work on a no-profit no-loss basis. It will not own any rolling stock.
The corporation will not be able to approach customers and market its infrastructure; this
will be done by Indian Railways. DFCCIL will be paid by the latter for providing a certain
number of paths, with certain speed and specified transit time.
The total track access charges will comprise primarily of fixed and some variable costs.
Significant portion of the total DFCCIL network cost will be fixed (capital, financing, material
for consumables, staff) while the variable cost element will cover traction fuel.
Current scope and various phases
DFC, in its current form, consists of the following two corridors which will be interlinked at
Khurja (Uttar Pradesh):
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
13/25
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
14/25
Construction
14 Edelweiss Securities Limited
West Bengal and Khurja in Uttar Pradesh, and an electrified single-track segment of 447
km between Ludhiana-Khurja-Dadri in the states of Punjab and Uttar Pradesh. The
corridor is proposed to be extended in the future to serve a new deep sea port in
Kolkata area.
About 80% of the corridors will run along existing tracks.
Traffic on the two corridors will consist of the following:
Western corridor: It will mostly cater to container traffic between various ports on thewestern coast (JNPT, Mumbai Port, Pipavav, Mundra and Kandla) and the North Indian
hinterland, specifically the inland container depots (ICDs) located at Tughlakabad, Dadri
and Ludhiana.
Table 3: Traffic projections on Western DFC as per RITES report
Source: DFCCIL, Edelweiss research
Eastern corridor: It will mostly cater to coal and steel movement from Eastern toNorthern India as well of food grains, cement, fertilisers, lime stone etc., from
Northern to Eastern India.
Direction/Commodity (mn tonnes/year) 2016-17 2021-22
UP Direction
Food grains, Fertil iser 1.2 1.8
POL 0.3 0.5
Cement, Salt, Miscellaneous 0.4 0.8Containers 26.6 37.8
Sub-Total 28.5 40.9
DN Direction
Coal, Cement, Iron & Steel 6.3 9.4
Ferti l izer, Foodgrains, Salt 1.6 2.6
POL 1.0 1.5
Containers 26.6 36.4
Sub-Total 35.5 49.9
Grand Total 64.0 90.8
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
15/25
Construction
15 Edelweiss Securities Limited
Table 4: Traffic projections on Eastern DFC as per RITES report
Source: DFCCIL, Edelweiss research
One may very well argue the significance of DFCs considering the fact that the desig ned
capacity is only ~200 mn tonnes (mt), that too in FY22, whereas the Indian Railways carried
970 mt of freight in FY12 itself.
However, this would be not taking into account the multiplier effect that projects like DFC
have on the freight carrying capacity.
Mega projects like DFC are known to add eight times to existing freight capacity. A similarmodel exists in China over 650 km. This line was commissioned in 2002 with a coal carrying
capacity of 200 mt. In 2009, 800 mt was carried on the same corridor. One single line carried
almost half of Chinas coal requirement. Similarly, the Eastern corridor will carry the entire
North Indias coal requirement from collieries.
Source: Infraline Energy
The two corridors will consist of various phases which along with their lengths are as
follows:
Direction/Commodity (mn tonnes/year) 2016-17 2021-22
UP Direction
Power House coal 54.5 62.0
Public Coal 0.6 1.0
Steel 8.2 9.7
Others 1.6 3.0
Logistic Park 1.2 2.4
Sub-Total 66.1 78.0
Down Direction
Fertil izer 0.2 0.4
Cement 0.8 1.5
Limestone for the
Steel Pl ants
Salt 0.7 1.0
Others 1.6 3.0
Logistic Park 1.2 2.4
Sub-Total 9.5 13.3
Grand Total 75.6 91.3
5.0 5.0
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
16/25
Construction
16 Edelweiss Securities Limited
Table 5: Lengths of the corridors
Source: DFCCIL, Edelweiss research
Money bags: Analysing project cost
The projects current completion cost is estimated at ~INR900bn. It has changed over the
years due to increase in scope of work, change in specifications, escalations etc. A brief over
view of the same is as follows:
In January 2007, RITES estimated the project cost for the Eastern and Western corridorsat INR282bn at 2007 prices (INR166bn for the Western and INR116bn for the Eastern
corridor).
The same was later revised to ~INR370bn by JICA in its feasibility report submitted tothe Ministry of Railways in October 2007.
Later, a number of additions were made to the project like junction arrangement (forseamless operation), double track, electrification of the Western corridor, increase in
width of formation from 12.5 to 13.5 meters for moving wider wagons etc. This, along
with inflation, escalated completion cost to ~INR780bn (based on 2009 prices).
As per the Ministry of Railways business plan, the total project cost was estimated atINR818bn, which included completion cost of INR776bn (INR391bn for Eastern DFC and
INR385bn for Western DFC) and land cost of INR42bn.
Recent news reports suggest that the overall project completion cost has been revisedupwards to INR900bn.
The completion cost translates into a per km cost of INR200mn-250mn (as mentioned
before, DFCCIL will not bear cost of rolling stock). This represents a significant EPC
opportunity for construction players.
Money trail: Combination of budgetary support, loans, equity
The DFC project with an overall requirement of ~INR900bn will be funded through a
combination of general budgetary support (GBS), commercial loans and equity.
The GBS from the Government of India will be in the form of loans contracted via the
Ministry of Finance from bilateral/multilateral agencies like the World Bank and JICA.
Kms
Phase I Rewari- Vadodara 930
Package 1 - Rewari - Ajmer 283
Package 2 - Ajmer - Ikbalgarh 342
Package 3 - Ikbalgarh - Vadodara 305
Phase II Vadodara - JNPT and Dadri - Rewari 569
Phase I Khurja - Kanpur 343
Phase II Kanpur - Mughals arai 393
Phase III Ludhiana - Khurja 447
Phase IV Sonnagar - Dankuni 538
Phase I (a) Mugal Sarai - Sonnagar 118
Western Corridor
Eastern Corridor
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
17/25
Construction
17 Edelweiss Securities Limited
Additional funding will be in the form of equity from Indian Railways and commercial
borrowings, which DFCCIL will raise from the market.
The project has a debt: equity ratio of roughly 2:1 (GBS: ~INR450bn, equity of ~INR215bn),
funding through the PPP mode with the shortfall met through commercial borrowings.
Funding sources of two corridors are given below:
Table 6: Funding sources of DFC
Source: DFCCIL, Edelweiss research
Western Corridor: It will be funded via a STEP (Special Terms of Economic Partnership)loan from JICA. JICA is providing a (Japanese yen) JPY679bn loan on soft terms (0.2%
p.a., 0.01% p.a. for consulting services) for 40 years with a moratorium of 10 years. This
loan will be sufficient to fund 80-85% of the total project cost. Balance cost (mainly
towards land acquisition) will be borne by Ministry of Railways in the form of equity to
DFCC.
JICA has already sanctioned JPY405bn for Phase I between Rewari and Vadodara. The
loan agreement for the first tranche of JPY90.2bn has already been signed.
For Phase II (Vadodara-JNPT and Rewari-Dadri), an Engineering Services loan
agreement for JPY1.6bn has been signed. Main loan agreement for Phases II and III of ~
JPY274bn is targeted for signing soon.
Apart from this, the work for design and construction of 54 major and important
bridges in Vasai-Bharuch section is being executed from Indian Railways resources.
Work has already been awarded by DFCCIL in February 2009.
Japanese funding has come with the following conditions:
Mandatory requirement of prime contractor being a Japanese firm. In case of a JV,the lead partner in the consortium should be a Japanese company with 51% stake.
Sub-contractors can be from any country.
Not less than 30% of the total amount of contracts (excluding consulting services)financed by the STEP loan must be accounted for by goods and services from
Japan.
Funding source
Phase I Rewari- Vadodara JICA
Phase II Vadodara - JNPT and Dadri - Rewari JICA
Funding source
Phase I Khurja - Kanpur World Bank
Phase II Kanpur - Mughalsarai World Bank
Phase III Ludhiana - Khurja World Bank
Phase IV Sonnagar - Dankuni PPP mode
Phase I (a) Mugal Sarai - Sonnagar Indian Railways
Western Corridor
Eastern Corridor
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
18/25
Construction
18 Edelweiss Securities Limited
In case of consulting services, the prime contractor i.e., consultants will be eitherJapanese or a JV with Indian partners where the formers total share of work in the
JV is more than 50% of the contract amount.
Eastern corridor: It will have three main sources of funds. World Bank will fund Phase I-III (which will cover the 1,183 km section between Ludhiana and Mughalsarai) via a loan
of USD2.725bn. It will fund about 67% of the project cost.
The World Bank loan is an Adaptable Programme Loan (APL) in which loans for
subsequent sections will be sanctioned based on achievement of certain milestones
(with regards to land acquisition, civil contract award etc.) in the previous sections.
The World Bank Board has already approved USD975mn loan for the Khurja-Kanpur
section; it has a maturity period of 22 years including a seven year grace period. There
will be another two tranches of USD1.05bn and USD700mn.
For Phase IV between Sonnagar and Dankuni, the PPP mode will be used. Initial
estimates available with DFCCIL indicate that around INR110bn will be required for
completing the segment. As per a recent meeting called by the Prime Minister for FY13infrastructure targets, the contract for this segment is to be awarded in FY13.
Phase I (a) between Mughalsarai and Sonnagar is being implemented with Indian
Railways resources. Civil construction contract for 109 km section (New Ganjkhwaja to
New Karwandia) has already been awarded in December 2008 and work is in progress.
Opportunities galore
DFC will have multi-fold benefits. Both EPC contractors as well as rolling stock
manufacturers will have increased opportunities from DFC.
Near-term beneficiaries include EPC contractors like L&T, IVRCL, NCC, HCC, Simplex,Gammon, among others. However, competition is likely to be high as is evident fromthe number of companies applying for pre-qualification.
Long-term beneficiaries include companies related with associated infrastructure likeTexmaco, Titagarh Wagons, CONCOR, BEML, Kalindee Rail Nirman, Siemens, among
others.
Land acquisition: Current status
Land for the project is being acquired under the Railways (Amendment) Act, 2008, since the
DFC has been declared as Special Railway Project. The amendment, which gives Indian
Railways special powers to take possession of land, was essentially brought in to hasten the
land acquisition process for key projects.
Land Acquisition Act, 1894, is not applicable to land acquired under the 2008 act.
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
19/25
Construction
19 Edelweiss Securities Limited
Fig. 7: Flowchart of land acquisition process
Source: Indian Railways, Edelweiss research
The project has seen steady progress on the land acquisition front. By FY12 end, more than
60% of total land required had been acquired. A brief snapshot of the land acquisition
progress is given below:
Table 7: Land acquisition progress of DFC
Source: DFCCIL, Edelweiss research
Project Description/SectionLength
(km)Area (Ha.)
Length
(km)Area (Ha.)
Length
(km)Area (Ha.)
Length
(km)Area (Ha.)
Award
(INR mn)
Disbursed
(INR mn)
Eastern Corridor
Khurja-Kanpur APL-1 343 1,320 343 1,320 343 1,320 314 1,172 89% 2,360 840
Kanpur-Mughalsarai APL-2 393 1,400 393 1,400 393 1,400 363 1,083 77% 2,360 980
Ludhiana-Khurja Section APL-3 447 802 447 802 447 802 317 520 65% 9,372 137
Mughalsarai-Sonnagar 118 319 118 319 106 303 74 186 58% 2,630 490
Sonnagar-Dhankuni 538 1,002 123 180 0 0 0 0 0% - -Sub-total 1,839 4,843 1,424 4,021 1,289 3,825 1,068 2,961 61% 16,722 2,447
Western Corridor
Phase-I Rewari-Vadodara 930 3,608 930 3,608 826 3,205 776 2,998 83% 7,930 5,970
Phase-II Vadodara-JNPT & Dadri - Rewari 569 2,252 569 2,252 464 1,718 143 782 35% 3,660 3,460
Sub-total 1,499 5,860 1,499 5,860 1,290 4,923 919 3,780 65% 11,590 9,430
Grand Total 3,338 10,703 2,923 9,881 2,579 8,748 1,987 6,741 63% 28,312 11,877
Total ScopeSection/Area
notified under 20A
Section/Area
notified under 20E
Progress of issuing
of 20FAmount
% of land
acquired
(20 F
stage)
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
20/25
Construction
20 Edelweiss Securities Limited
The comparatively slow progress on land acquisition for the Sonnagar-Dankuni stretch has
pushed the overall figure down. However, with the new directive from the Prime Ministers
Office, we now expect things to gather pace.
Meaning of various stages highlighted in the table above is given below:
Section 20A: The issuance of 20A means marking of the land identified for acquisition,which is ready for further survey and compensation studies.
Section 20E: This notification is issued for declaration of acquisition' by the UnionGovernment under the Indian Railways (Amendment) Act 2008. 20E is an important
milestone as it allows the railways to take steps required to build, maintain and manage
the project.
Section 20F: This relates to the eventual declaration of award by paying compensationto the owner and closing the deal by taking possession of the land.
Tendering: Current status
DFCCIL has been preparing the framework for this humungous project over the past coupleof years. Work had commenced more than four years ago when tenders for detailed
engineering construction survey were awarded. Since then, ~20 contracts for project
management and consultancy works as well as other ancillary jobs have been awarded.
As far as civil construction is concerned, till date, two major tenders have been awarded on
DFC (both awarded in FY09):
Construction of 54 major bridges in the Vasai-Bharuch section (Phase II i.e., JNPT-Vadodara stretch) of the Western corridor - INR6.05bn order bagged by Soma
Enterprises.
Civil construction contract for 109 km section form New Ganjkhwaja to New Karwandia(Phase I (a) MughalsaraiSonnagar stretch) on Eastern corridor - INR7.8bn contractbagged by B. Seenaiah.
Currently, DFCCIL is in the process of awarding four major tenders:
INR80bn-90bn contract for civil construction, building and track works for package 1and 2 on Phase I (Rewari-Vadodara) of the Western corridor. Phase I has been further
sub-divided into three separate packages:
Package 1: Rewari-Ajmer section of 283 kms. Package 2: Ajmer-Ikbalgarh section of 342 kms. Package 3: Ikbalgarh-Vadodara section of 305 kms.
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
21/25
Construction
21 Edelweiss Securities Limited
Fig. 8: Tendering on Western DFC
Source: DFCCIL, Edelweiss research
The RfQ process for package 1 & 2 (overall 625 kms) is already over. Competition for
this is now limited to two contendersL&T-Sojitz Corporation and the IRCON-Leighton
Welspun-Mitsui consortium. We expect the contract to be awarded over the nextcouple of months.
INR60bn-70bn contract for civil construction, structure and track laying work for Phase I(Khurja-Kanpur) on the Eastern corridor. The RfQ process for this contract is already
over; 27 companies expressed interest, of which 14 have been pre-qualified for bidding.
The contract will be awarded by September 2012.
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
22/25
Construction
22 Edelweiss Securities Limited
Fig. 9: Eastern DFC
Source: Edelweiss research
Design, procurement and construction of track and related works for 66km stretch fromNew Karwandiya to Durgawati on Phase I (a) (Mughalsarai-Sonnagar section of the
Eastern corridor. The RfQ process is over and 22 firms have been pre-qualified for this
stretch.
Design, construction and commissioning of 2*25 kV electrification and signalling worksfor the 66km stretch from New Karwandiya to Durgawati. The RfQ process is over and 4
firms have been pre-qualified for this stretch.
Apart from this, work for awarding the following contracts has already commenced:
RfQ process for design and construction of civil, building and track works for package 3on Phase I (Rewari-Vadodara) of the Western corridor has already started. The RfQ
document mentions that submission of bids will happen in Feb 2013.
Preparation for awarding the systems contract (electrical, signaling and telecom) forPhase I (Khurja-Kanpur section) on Eastern corridor is already on.
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
23/25
Construction
23 Edelweiss Securities Limited
World Bank has approved short listing of general consultants for Phases II and III on theEastern corridor and RfP documents for the same have been issued. DFCCIL expects to
award these contracts by July 2013 and October 2013, respectively.
The way ahead: DFC gathering pace
The governments emphasis on the project is evident from the proposed guarantee to be
provided by Indian Railways (assuring timely servicing of the underlying principal/interestobligations) against DFCCILs future borrowing programme. Also, given its strategic
importance, the project is being directly monitored by the Prime Ministers Office.
In this backdrop, along with steady progress in land acquisition and financing, we expect the
DFC project to roll on smoothly going ahead. The World Banks and JICAs involvement will
ensure its regular monitoring.
This is evident from the fact that one of the conditions laid down for project award is the
achievement of milestones for land acquisition (currently, tenders have been invited only
for packages which have acquired more than 80% of land). We believe the focus on getting
land acquisition/ other regulatory approvals in place before project award is likely to ensure
that there are no hiccups in execution.
The objective of completing the project by 2017-18 means the next two years are expected
to see a lot of action on the tendering side. Overall, we believe the project will be a
significant value enhancer for the Indian logistics space apart from being a new opportunity
for EPC contractors.
Table 8: Valuations snapshot
*P/E & P/BV for implied construction business
Source: Edelweiss research
CMP Target price Asset value
(INR per share) (INR per share) (INR per share) FY13E FY14E FY13E FY14E FY13E FY14E FY13E FY14E
Sadbhav Engg* 141 170 91 8.8 11.6 5.7 4.3 58.7 69.7 0.8 0.7
Ramky Infra* 90 253 64 23.7 29.3 1.1 0.9 192.7 222.0 0.1 0.1
IVRCL Infra* 51 40 20 1.6 2.4 19.2 12.9 74.8 75.7 0.4 0.4NCC* 40 59 22 4.2 6.1 4.2 2.9 97.8 103.6 0.2 0.2
Hindustan Construction 20 24 24 (3.5) (2.9) NA NA 17.9 15.0 1.1 1.3
Simplex Infra 209 218 0 24.3 33.9 8.6 6.2 266.3 297.8 0.8 0.7
B.L. Kashyap 9 11 0 0.8 1.5 10.4 5.8 28.2 29.7 0.3 0.3
Consolidated Construction 13 12 0 1.2 2.3 11.5 5.8 34.6 36.3 0.4 0.4
Rel iance Infra 534 936 936 50.1 50.7 10.7 10.5 747.0 789.6 0.7 0.7
CompanyEPS (INR) P/E Book value (INR) P/BV
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
24/25
Construction
24 Edelweiss Securities Limited
Edelweiss Securities Limited, Edelweiss House, off C.S.T. Road, Kalina, Mumbai 400 098.
Board: (91-22) 4009 4400, Email: [email protected]
Vikas Khemani Head Institutional Equities [email protected] +91 22 2286 4206
Nischal Maheshwari Co-Head Institutional Equities & Head Research [email protected] +91 22 4063 5476
Nirav Sheth Head Sales [email protected] +91 22 4040 7499
Coverage group(s) of stocks by primary analyst(s):ConstructionConsolidated Construction Co., Hindustan Construction Co., IL&FS Transportation Networks, IRB Infrastructure, IVRCL Infra, Jaiprakash Associates, BL
Kashyap & Sons Ltd, Nagarjuna Construction Co, Ramky Infrastructure, Sadbhav Engineering, Simplex Infrastructures Ltd
Distribution of Ratings / Market Cap
Edelweiss Research Coverage Universe
Rating Distribution* 104 60 18 183
* 1 stocks under review
Market Cap (INR) 114 58 11
Date Company Title Price (INR) Recos
Recent Research
19-Jun-12 Construction Highway to growth;
Sector Update
07-Jun-12 IL&FS
ransporation
In pole position;
Visit Note
175 Buy
06-Jun-12 Sadbhav
Engineering
Temporary hiccup;
Result Update
120 Buy
> 50bn Between 10bn and 50 bn < 10bn
Buy Hold Reduce Total
Rating Interpretation
Buy appreciate more than 15% over a 12-month period
Hold appreciate up to 15% over a 12-month period
Reduce depreciate more than 5% over a 12-month period
Rating Expected to
-
7/28/2019 Construction Sector Update Jun 12 EDEL1
25/25
SECTOR UPDATE
Access the entire repository of Edelweiss Research on www.edelresearch.com
DISCLAIMERGeneral Disclaimer:
This document has been prepared by Edelweiss Securities Limited (Edelweiss). Edelweiss, its holding company and associate companies are a full service, integrated
investment banking, portfolio management and brokerage group. Our research analysts and sales persons provide important input into our investment banking
activities. This document does not constitute an offer or solicitation for the purchase or sale of any financial instrument or as an official confirmation of any
transaction. The information contained herein is from publicly available data or other sources believed to be reliable, but we do not represent that it is accurate or
complete and it should not be relied on as such. Edelweiss or any of its affiliates/ group companies shall not be in any way responsible for any loss or damage that
may arise to any person from any inadvertent error in the information contained in this report. This document is provided for assistance only and is not intended to
be and must not alone be taken as the basis for an investment decision. The user assumes the entire risk of any use made of this information. Each recipient of this
document should make such investigation as it deems necessary to arrive at an independent evaluation of an investment in the securities of companies referred to
in this document (including the merits and risks involved), and should consult his own advisors to determine the merits and risks of such investment. The investment
discussed or views expressed may not be suitable for all investors. We and our affiliates, group companies, officers, directors, and employees may: (a) from time to
time, have long or short positions in, and buy or sell the securities thereof, of company (ies) mentioned herein or (b) be engaged in any other transaction involving
such securities and earn brokerage or other compensation or act as advisor or lender/borrower to such company (ies) or have other potential conflict of interest
with respect to any recommendation and related information and opinions. This information is strictly confidential and is being furnished to you solely for your
information. This information should not be reproduced or redistributed or passed on directly or indirectly in any form to any other person or published, copied, in
whole or in part, for any purpose. This report is not directed or intended for distribution to, or use by, any person or entity who is a citizen or resident of or located
in any locality, state, country or other jurisdiction, where such distribution, publication, availability or use would be contrary to law, regulation or which would
subject Edelweiss and affiliates/ group companies to any registration or licensing requirements within such jurisdiction. The distribution of this document in certain
jurisdictions may be restricted by law, and persons in whose possession this document comes, should inform themselves about and observe, any such restrictions.
The information given in this document is as of the date of this report and there can be no assurance that future results or events will be consistent with this
information. This information is subject to change without any prior notice. Edelweiss reserves the right to make modifications and alterations to this statement as
may be required from time to time. However, Edelweiss is under no obligation to update or keep the information current. Nevertheless, Edelweiss is committed toproviding independent and transparent recommendation to its client and would be happy to provide any information in response to specific client queries. Neither
Edelweiss nor any of its affiliates, group companies, directors, employees, agents or representatives shall be liable for any damages whether direct, indirect, special
or consequential including lost revenue or lost profits that may arise from or in connection with the use of the information. Past performance is not necessarily a
guide to future performance. The disclosures of interest statements incorporated in this document are provided solely to enhance the transparency and should not
be treated as endorsement of the views expressed in the report. Edelweiss Securities Limited generally prohibits its analysts, persons reporting to analysts and their
dependents from maintaining a financial interest in the securities or derivatives of any companies that the analysts cover. The information provided in this document
remains, unless otherwise stated, the copyright of Edelweiss. All layout, design, original artwork, concepts and other Intellectual Properties, remains the property
and copyright Edelweiss and may not be used in any form or for any purpose whatsoever by any party without the express written permission of the copyright
holders.
Analyst Certification:
The analyst for this report certifies that all of the views expressed in this report accurately reflect his or her personal views about the subject company or companies
and its or their securities, and no part of his or her compensation was, is or will be, directly or indirectly related to specific recommendations or views expressed in
this report.
Analyst holding in the stock: No.
Additional Disclaimer for U.S. Persons
This research report is a product of Edelweiss Securities Limited, which is the employer of the research analyst(s) who has prepared the research report. The
research analyst(s) preparing the research report is/are resident outside the United States (U.S.) and are not associated persons of any U.S. regulated broker-dealer
and therefore the analyst(s) is/are not subject to supervision by a U.S. broker-dealer, and is/are not required to satisfy the regulatory licensing requirements of
FINRA or required to otherwise comply with U.S. rules or regulations regarding, among other things, communications with a subject company, public appearances
and trading securities held by a research analyst account.
This report is intended for distribution by Edelweiss Securities Limited only to "Major Institutional Investors" as defined by Rule 15a-6(b)(4) of the U.S. Securities and
Exchange Act, 1934 (the Exchange Act) and interpretations thereof by U.S. Securities and Exchange Commission (SEC) in reliance on Rule 15a 6(a)(2). If the recipient
of this report is not a Major Institutional Investor as specified above, then it should not act upon this report and return the same to the sender. Further, this report
may not be copied, duplicated and/or transmitted onward to any U.S. person, which is not the Major Institutional Investor.
In reliance on the exemption from registration provided by Rule 15a-6 of the Exchange Act and interpretations thereof by the SEC in order to conduct certain
business with Major Institutional Investors, Edelweiss Securities Limited has entered into an agreement with a U.S. registered broker-dealer, Marco Polo Securities
Inc. ("Marco Polo").
Transactions in securities discussed in this research report should be effected through Marco Polo or another U.S. registered broker dealer.
Copyright 2009 Edelweiss Research (Edelweiss Securities Ltd). All rights reserved