construction sector update jun 12 edel1

Upload: nit111

Post on 03-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    1/25

    Edelweiss Research is also available on www.edelresearch.com,

    Bloomberg EDEL , Thomson First Call, Reuters and Factset. Edelweiss Securities Limited

    The ambitious Dedicated Freight Corridor (DFC) project, targeting

    creation of high-capacity, high-speed railway corridors dedicated to

    freight movement, boasts of being Indias largest-ever infrastructure

    project. The Delhi-Mumbai and Delhi-Kolkata corridors, with an

    estimated completion cost of ~INR900bn, are expected to revolutionise

    freight transport in India. With a 2017-18 completion target, steady

    progress in land acquisition and funding, we expect the next couple of

    years to see a lot of action on the project award side. This will trigger

    significant opportunities for EPC players like L&T, IVRCL, NCC, among

    others, apart from giving a fillip to the countrys logistic network.

    DFC development imperative as existing network grossly clogged

    Saturation of existing railway capacity has led to congestion and loss of freight market

    share for Indian Railways (from ~90% in 1950s to

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    2/25

    Construction

    2 Edelweiss Securities Limited

    Dedicated Freight Corridor: The fine print

    Dedicated Freight Corridor (DFC) is Indias largest-ever infrastructure project. It is being

    piloted by the Dedicated Freight Corridor Corporation of India (DFCCIL), a wholly-owned

    special purpose vehicle (SPV) of the Ministry of Railways. Its aim, in the first phase of the

    project, is to construct over 3,300 kms of high-capacity, high-speed railway corridors

    dedicated for freight movement along the Delhi-Mumbai (Western corridor) and Delhi-

    Kolkata (Eastern corridor) rail routes. This phase is estimated to cost ~USD16bn.

    Fig. 1: Proposed freight corridors in India

    Source: Indian Railways, Edelweiss research

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    3/25

    Construction

    3 Edelweiss Securities Limited

    In the future, four additional corridorsNorth-South Corridor (Delhi-Chennai, 2,173 kms),

    East-West Corridor (Kolkata-Mumbai, 2,000 kms), East Coast Corridor (Kharagpur-

    Vijayawada, 1,100 kms) and Southern Corridor (Chennai-Goa, 890 kms)are planned to be

    undertaken by DFCCIL. The corporation has already engaged RITES to undertake feasibility

    studies for these stretches. The latter has submitted the interim report for Preliminary

    Engineering cum Traffic Survey work for these corridors.

    Note: In this report, we have limited ourselves to 3,300 km corridors between Delhi-

    Mumbai and Delhi-Kolkata.

    Need for DFC: India lagging global peers in logistics infrastructure

    India lags way behind when it comes to logistic infrastructure compared to global peers.

    Logistics cost in India is at 13-14% of GDP compared to ~10% in developed countries.

    Of more concern is the fact that logistic network development is not keeping pace with the

    countrys economic growth (freight traffic generally has an elasticity of 1.25 to GDP

    growth). As a result, in the World Bank logistic performance index, India has slipped to 46th

    rank in 2012 compared to 39th position five years ago.

    Chart 1: Average surface freight cost (in US cents) per tonne-km:

    Source: KPMG-CII, Edelweiss research

    When it comes to railways, Indias freight carrying efficiency is hampered by a lack of

    investment in infrastructure.

    Table 1: Comparison of carrying efficiency of railways

    Source: Indian Railways, Edelweiss research

    1.0

    2.6

    4.2

    5.8

    7.4

    9.0

    US Canada Japan Europe India

    (cents/ton-km)

    Average surface freight cost

    Country India Developed worldAvg speed (kmph) 23.3 100

    Capacity (TEUs) 90 150

    Axle load of wagons (Tonnes) 22 30

    Load capacity per wagon (Tonnes) 88 120

    Pay load: Tare weight of wagon 2 - 2.6 4.5 - 5.5

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    4/25

    Construction

    4 Edelweiss Securities Limited

    Thus, Indian Railway carries 450 kg of wagons dead weight for every 1,000 kg of freight

    carried compared to only 170 kg in the US. This highlights the need of timely investment in

    the countrys rail infrastructure.

    A Mckinsey study on logistics in India had highlighted that there are seven high density

    corridors in the country that carry 50% of freight traffic. These include the Golden

    Quadrilaterals of Indian Railways as well as Phases I and II (GQ and NSEW) of the National

    Highway Development Programme. Going ahead, the share of these corridors is projected

    to inch even higher.

    Fig. 2: Freight traffic concentrated along certain corridors

    Source: Mckinsey, Edelweiss research

    One of the ways suggested in the study to efficiently cope with the expected increase in

    freight traffic, was the creation of dedicated freight corridors (DFCs).

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    5/25

    Construction

    5 Edelweiss Securities Limited

    Fig. 3: DFC is the best alternative for freight management

    Source: Mckinsey, Edelweiss research

    The study had suggested creation of five DFCs which will have the following benefits:

    DFCs are the most cost-effective way to add freight traffic capacity. The cost per tonne-km of capacity added by a DFC (around USD25-30mn) is lower than investments in

    other modes (~45% lower per tonne-km than that of an equivalent build-out of

    expressways and approximately one-third of that for new roads).

    DFCs enable higher-quality service compared to other modes. At higher average speedsof 75 km per hour, DFCs can cut travel time on rail by up to 66%.

    Reducing variability in transit times also significantly reduces inventory requirements.

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    6/25

    Construction

    6 Edelweiss Securities Limited

    Meeting notes with DFCCIL

    Mr. P N Shukla - Director

    (Operations & Business Devp.),

    DFCCIL

    The Insider

    We met Mr. P N Shukla, Director (Operations & Business Development), DFCCIL. Key

    takeaways from our meeting:

    Q. What is the basic purpose behind DFC?

    A. The basic purpose behind DFC is to improve the freight carrying efficiency of IndianRailways. The Golden Quadrilateral carries freight of ~600 mtpa. Currently, both freight

    and passenger trains run on the same network, which has resulted in average speed of

    freight trains being low at ~25 km per hour. DFC will increase this by a factor of three. It

    will also improve the carrying capacity of trains (from 4,000 tonnes/train currently to

    15,000 tonnes/train).

    Q. What are the main advantages of DFC?

    A. DFC will result in increase in the freight carrying capacity of railways. It will also lower

    the unit cost of operations apart from helping in development of multi-modal logistic

    parks. Current network has a mix of passenger and freight facilities which has prevented

    optimum utilisation. A dedicated logistic park for cargo services is expected to deal with

    such problems by making expansion easier.

    Also, the DFC will decongest the current network in a significant way. The effective

    capacity of the DFC would be as high as ~600 mtpa due to enhanced design features,

    double stacking etc.

    Q. What will be the revenue model for DFC?

    A. Indian Railways will be the sole user of DFC. DFC will not have any marketing rights of its

    own. Indian Railways will pay DFC track access charges to ensure cost recovery for

    DFCCIL. The track access agreement is under finalisation.

    Q. What is the estimated cost of the project?

    A. The estimated completion cost of the project is INR900bn. The Western corridor will

    cost ~INR460bn while the Eastern corridor will cost ~INR440bn. The average cost of the

    Western corridor at INR250mn/ km is higher than the INR200mn/km cost of Eastern

    corridor due to more bridges and higher technical requirements.

    Q. Which components are included in the completion cost?

    A. The completion cost includes construction cost, interest during construction, taxes,

    insurance, inflation etc. It does not include land acquisition cost which is estimated to be

    ~INR60bn. Land acquisition will be done directly by Indian Railways (under Government

    of India) which will then make the land available to DFCCIL at a nominal cost.

    Q. What will be the broad break-up of construction cost?

    A. The construction cost can be broadly broken up into civil construction (65%), electrical

    (20%) and signalling (15%) work.

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    7/25

    Construction

    7 Edelweiss Securities Limited

    Q. What will be the funding arrangement for the same?

    A. While JICA is funding the Western corridor, World Bank is funding the Eastern corridor.

    The overall debt/equity earlier envisaged for the project was 2:1, which may eventually

    be finalised at 1.2:1. The Eastern corridor will have a higher equity component than the

    Western corridor.

    Q. What are the various types of contracts in DFC?

    A. There are basically four types of works needed to be done under DFC:

    Civil construction, structures etc. Track works, sleepers etc. Overhead equipment (OHE). Signaling and systems work.

    Q. What is the progress as far as tendering is concerned?

    A. Package 1 & 2 (costing INR80-90bn) on Phase I of Western corridor will be awarded this

    year. Similarly, Phase I on Eastern corridor (overall cost ~INR80-90bn and civilconstruction cost of INR60bn) is expected to be awarded by September 2012. The

    Sonnagar-Dankuni project (~INR110bn) will be done on PPP basis for which the PPP

    mode is under finalisation. We are evaluating a number of models (e.g. the annuity

    mode of project award) for the same.

    For the 109 km stretch between New Ganjkhwaja to New Karwandia, civil construction

    contract had been awarded earlier. We are now in the process of awarding the package

    for construction of track and related works for the 66km stretch from New Karwandiya

    to Durgawati on the same section.

    Q. What are the timelines for the project?

    A. it will take ~4 years post contract award for the project to be completed. We expect that

    a significant part of the corridor will be operational by 2017. We are focused on getting

    the requisite clearances necessary for project award and expect to see meaningful

    progress soon.

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    8/25

    Construction

    8 Edelweiss Securities Limited

    Rationale: Declutter over burdened, saturated network

    DFC is needed due to the following concerns:

    Saturation of existing capacity: Indian Railways golden quadrilateral, which links thefour metros and two diagonals viz., Delhi-Chennai and MumbaiKolkata, accounts for

    just 16% of the entire railway route in India, but carries 58% of the total freight and

    52% of passenger traffic.

    Specifically, Delhi-Kolkata and Delhi-Mumbai corridors are highly saturated with line

    capacity utilisation varying between 115% and 150%. Chronic under investment in

    capacity expansion has raised the spectre of choking of Indian Railways freight carrying

    capacity.

    The DFC project, once completed, will meet the transport requirements of the two busy

    trunk routes for the next 15-20 years.

    Loss of market share: Due to congestion in the railway network, rail transport, in spiteof being cheaper than road transport, has steadily lost market share. Indian Railways'

    share in the freight transportation market has declined from 89% in 1950-51 to less

    than 40% currently. Highways have been prime gainers, increasing their share from 11%to around 60% over the same period.

    Chart 2: Share of different modes in freight transport across countries

    Source: Mckinsey, Edelweiss research

    The low share of railways is surprising given that 65% of Indias freight comprises bulk

    commodities which move across long distances and thus can be more economically served

    by rail transport. Also, about 80% of the bulk freight is transported (in tonne-km) over

    distances of more than 400 km.

    22

    37

    57

    47

    48

    36

    30

    ~146

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    9/25

    Construction

    9 Edelweiss Securities Limited

    Chart 3: Break-up of bulk freight traffic in India as per distance travelled

    Source: Mckinsey, Edelweiss research

    Slow speeds: Indian Railways currently runs mixed traffic (passenger and freight) on itsexisting network. With passenger trains getting priority over goods trains, the average

    speed of freight trains is limited to 22-25 kmph.

    Need for a new approach: Keeping in mind the expected surge in freight traffic in thefuture and the need to eliminate logistic inefficiencies in the network, an integrated

    approach like the DFC is required rather than the incremental approach which has been

    followed historically by Indian Railways (putting up additional lines or improving

    signaling in times of capacity constraints).

    Advantages: Fast tracking growth

    Faster freightmovement: DFC is expected to revolutionise freight movement. This willfructify via reduced congestion, a high-capacity efficient network and enhanced designfeatures, much superior to the current network. The table below gives a comparative

    framework of the same:

    0-400 km

    19%

    400-700 km

    26%

    > 700 km

    55%

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    10/25

    Construction

    10 Edelweiss Securities Limited

    Fig. 4: Comparison of existing rail network and DFC

    Source: DFCCIL, Edelweiss research

    As can be seen, DFCs superior capacity will emanate from bigger dimensions of

    rolling stock as well as the networks improved design features. This will reduce

    the unit cost of operations.

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    11/25

    Construction

    11 Edelweiss Securities Limited

    Fig. 5: Comparison of DFC with competing modes

    Source: Indian Railways, World Bank, Edelweiss research

    Another advantage will be that freight trains on DFC can run at an average speed of

    over 65 kmph against 22 kmph currently, thus limiting transit time.

    Also, due to smaller workforce (one person per track km on DFC), latest loading

    technology and efficiency of rolling stock, operating costs are expected to be half of the

    existing railway system.

    Superior planning and optimum network utilisation: Segregation of freight andpassenger traffic will enable better planning and optimum utilisation of the network,

    resulting in faster movement of goods. This will also remove inefficiencies, as seen in

    the current system, and save costs by eliminating uncertainties on transit time. This will

    enhance railways freight market share with it becoming better suited for freight

    movement over shorter distances.

    Development of associated infrastructure: Multimodal logistic park (MMLPs) willenhance industrial development and create the necessary base for the Delhi-Mumbai

    Industrial Corridor. They will act as hubs providing state-of-the-art integrated logistic

    facilities. Features like mechanised handling and intelligent inventory management are

    likely to reduce overall logistics costs. This will be further leveraged by the modern,

    high-capacity rail connectivity of DFCs capable of meeting time-sensitive freight

    transportation requirement.

    A RITES report has suggested development of such parks at Rewari, Vapi, Navi Mumbai

    and Ahmedabad on the Western corridor, and Ludhiana, Durgapur and Kanpur on theEastern corridor. These terminals will be set up as one-stop shops for all value-added

    services like warehousing, packaging, custom bonding, etc.

    Techno economic feasibility study for logistic parks at Ahmedabad, Navi Mumbai and

    Kanpur has been taken up already.

    With reduction in load on the existing network, Indian Railways can run additionalpassenger trains.

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    12/25

    Construction

    12 Edelweiss Securities Limited

    Indirect benefits to economy: A 2007 study by the Japan International CooperationAgency (JICA) assessed the financial viability of DFC project. JICAs calculations, taking

    into account the total investment cost, maintenance, and operation cost for 35 years,

    indicates that the economic IRR was 13.95% for the Western corridor and 15.09% for

    the Eastern corridor. The study judged the project as viable, given that 12% economic

    IRR is considered a minimum base for considering a project feasible.

    The financial IRR was 9.08% for the Western corridor and 15.59% for the Eastern

    corridor. The economic IRR includes indirect benefits to the economy that are unlikely

    to be ploughed back to investors, whereas the financial IRR measures the direct

    financial benefits from the project over a 35 year cycle.

    The business model: SPV structure

    DFCCIL will enter into a concession agreement with the Ministry of Railways. The Indian

    Railways will pay track access charges to the company. These charges will essentially cover

    DFCCILs entire debt obligations as well as its operation and maintenance costs. The

    corporation will work on a no-profit no-loss basis. It will not own any rolling stock.

    The corporation will not be able to approach customers and market its infrastructure; this

    will be done by Indian Railways. DFCCIL will be paid by the latter for providing a certain

    number of paths, with certain speed and specified transit time.

    The total track access charges will comprise primarily of fixed and some variable costs.

    Significant portion of the total DFCCIL network cost will be fixed (capital, financing, material

    for consumables, staff) while the variable cost element will cover traction fuel.

    Current scope and various phases

    DFC, in its current form, consists of the following two corridors which will be interlinked at

    Khurja (Uttar Pradesh):

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    13/25

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    14/25

    Construction

    14 Edelweiss Securities Limited

    West Bengal and Khurja in Uttar Pradesh, and an electrified single-track segment of 447

    km between Ludhiana-Khurja-Dadri in the states of Punjab and Uttar Pradesh. The

    corridor is proposed to be extended in the future to serve a new deep sea port in

    Kolkata area.

    About 80% of the corridors will run along existing tracks.

    Traffic on the two corridors will consist of the following:

    Western corridor: It will mostly cater to container traffic between various ports on thewestern coast (JNPT, Mumbai Port, Pipavav, Mundra and Kandla) and the North Indian

    hinterland, specifically the inland container depots (ICDs) located at Tughlakabad, Dadri

    and Ludhiana.

    Table 3: Traffic projections on Western DFC as per RITES report

    Source: DFCCIL, Edelweiss research

    Eastern corridor: It will mostly cater to coal and steel movement from Eastern toNorthern India as well of food grains, cement, fertilisers, lime stone etc., from

    Northern to Eastern India.

    Direction/Commodity (mn tonnes/year) 2016-17 2021-22

    UP Direction

    Food grains, Fertil iser 1.2 1.8

    POL 0.3 0.5

    Cement, Salt, Miscellaneous 0.4 0.8Containers 26.6 37.8

    Sub-Total 28.5 40.9

    DN Direction

    Coal, Cement, Iron & Steel 6.3 9.4

    Ferti l izer, Foodgrains, Salt 1.6 2.6

    POL 1.0 1.5

    Containers 26.6 36.4

    Sub-Total 35.5 49.9

    Grand Total 64.0 90.8

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    15/25

    Construction

    15 Edelweiss Securities Limited

    Table 4: Traffic projections on Eastern DFC as per RITES report

    Source: DFCCIL, Edelweiss research

    One may very well argue the significance of DFCs considering the fact that the desig ned

    capacity is only ~200 mn tonnes (mt), that too in FY22, whereas the Indian Railways carried

    970 mt of freight in FY12 itself.

    However, this would be not taking into account the multiplier effect that projects like DFC

    have on the freight carrying capacity.

    Mega projects like DFC are known to add eight times to existing freight capacity. A similarmodel exists in China over 650 km. This line was commissioned in 2002 with a coal carrying

    capacity of 200 mt. In 2009, 800 mt was carried on the same corridor. One single line carried

    almost half of Chinas coal requirement. Similarly, the Eastern corridor will carry the entire

    North Indias coal requirement from collieries.

    Source: Infraline Energy

    The two corridors will consist of various phases which along with their lengths are as

    follows:

    Direction/Commodity (mn tonnes/year) 2016-17 2021-22

    UP Direction

    Power House coal 54.5 62.0

    Public Coal 0.6 1.0

    Steel 8.2 9.7

    Others 1.6 3.0

    Logistic Park 1.2 2.4

    Sub-Total 66.1 78.0

    Down Direction

    Fertil izer 0.2 0.4

    Cement 0.8 1.5

    Limestone for the

    Steel Pl ants

    Salt 0.7 1.0

    Others 1.6 3.0

    Logistic Park 1.2 2.4

    Sub-Total 9.5 13.3

    Grand Total 75.6 91.3

    5.0 5.0

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    16/25

    Construction

    16 Edelweiss Securities Limited

    Table 5: Lengths of the corridors

    Source: DFCCIL, Edelweiss research

    Money bags: Analysing project cost

    The projects current completion cost is estimated at ~INR900bn. It has changed over the

    years due to increase in scope of work, change in specifications, escalations etc. A brief over

    view of the same is as follows:

    In January 2007, RITES estimated the project cost for the Eastern and Western corridorsat INR282bn at 2007 prices (INR166bn for the Western and INR116bn for the Eastern

    corridor).

    The same was later revised to ~INR370bn by JICA in its feasibility report submitted tothe Ministry of Railways in October 2007.

    Later, a number of additions were made to the project like junction arrangement (forseamless operation), double track, electrification of the Western corridor, increase in

    width of formation from 12.5 to 13.5 meters for moving wider wagons etc. This, along

    with inflation, escalated completion cost to ~INR780bn (based on 2009 prices).

    As per the Ministry of Railways business plan, the total project cost was estimated atINR818bn, which included completion cost of INR776bn (INR391bn for Eastern DFC and

    INR385bn for Western DFC) and land cost of INR42bn.

    Recent news reports suggest that the overall project completion cost has been revisedupwards to INR900bn.

    The completion cost translates into a per km cost of INR200mn-250mn (as mentioned

    before, DFCCIL will not bear cost of rolling stock). This represents a significant EPC

    opportunity for construction players.

    Money trail: Combination of budgetary support, loans, equity

    The DFC project with an overall requirement of ~INR900bn will be funded through a

    combination of general budgetary support (GBS), commercial loans and equity.

    The GBS from the Government of India will be in the form of loans contracted via the

    Ministry of Finance from bilateral/multilateral agencies like the World Bank and JICA.

    Kms

    Phase I Rewari- Vadodara 930

    Package 1 - Rewari - Ajmer 283

    Package 2 - Ajmer - Ikbalgarh 342

    Package 3 - Ikbalgarh - Vadodara 305

    Phase II Vadodara - JNPT and Dadri - Rewari 569

    Phase I Khurja - Kanpur 343

    Phase II Kanpur - Mughals arai 393

    Phase III Ludhiana - Khurja 447

    Phase IV Sonnagar - Dankuni 538

    Phase I (a) Mugal Sarai - Sonnagar 118

    Western Corridor

    Eastern Corridor

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    17/25

    Construction

    17 Edelweiss Securities Limited

    Additional funding will be in the form of equity from Indian Railways and commercial

    borrowings, which DFCCIL will raise from the market.

    The project has a debt: equity ratio of roughly 2:1 (GBS: ~INR450bn, equity of ~INR215bn),

    funding through the PPP mode with the shortfall met through commercial borrowings.

    Funding sources of two corridors are given below:

    Table 6: Funding sources of DFC

    Source: DFCCIL, Edelweiss research

    Western Corridor: It will be funded via a STEP (Special Terms of Economic Partnership)loan from JICA. JICA is providing a (Japanese yen) JPY679bn loan on soft terms (0.2%

    p.a., 0.01% p.a. for consulting services) for 40 years with a moratorium of 10 years. This

    loan will be sufficient to fund 80-85% of the total project cost. Balance cost (mainly

    towards land acquisition) will be borne by Ministry of Railways in the form of equity to

    DFCC.

    JICA has already sanctioned JPY405bn for Phase I between Rewari and Vadodara. The

    loan agreement for the first tranche of JPY90.2bn has already been signed.

    For Phase II (Vadodara-JNPT and Rewari-Dadri), an Engineering Services loan

    agreement for JPY1.6bn has been signed. Main loan agreement for Phases II and III of ~

    JPY274bn is targeted for signing soon.

    Apart from this, the work for design and construction of 54 major and important

    bridges in Vasai-Bharuch section is being executed from Indian Railways resources.

    Work has already been awarded by DFCCIL in February 2009.

    Japanese funding has come with the following conditions:

    Mandatory requirement of prime contractor being a Japanese firm. In case of a JV,the lead partner in the consortium should be a Japanese company with 51% stake.

    Sub-contractors can be from any country.

    Not less than 30% of the total amount of contracts (excluding consulting services)financed by the STEP loan must be accounted for by goods and services from

    Japan.

    Funding source

    Phase I Rewari- Vadodara JICA

    Phase II Vadodara - JNPT and Dadri - Rewari JICA

    Funding source

    Phase I Khurja - Kanpur World Bank

    Phase II Kanpur - Mughalsarai World Bank

    Phase III Ludhiana - Khurja World Bank

    Phase IV Sonnagar - Dankuni PPP mode

    Phase I (a) Mugal Sarai - Sonnagar Indian Railways

    Western Corridor

    Eastern Corridor

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    18/25

    Construction

    18 Edelweiss Securities Limited

    In case of consulting services, the prime contractor i.e., consultants will be eitherJapanese or a JV with Indian partners where the formers total share of work in the

    JV is more than 50% of the contract amount.

    Eastern corridor: It will have three main sources of funds. World Bank will fund Phase I-III (which will cover the 1,183 km section between Ludhiana and Mughalsarai) via a loan

    of USD2.725bn. It will fund about 67% of the project cost.

    The World Bank loan is an Adaptable Programme Loan (APL) in which loans for

    subsequent sections will be sanctioned based on achievement of certain milestones

    (with regards to land acquisition, civil contract award etc.) in the previous sections.

    The World Bank Board has already approved USD975mn loan for the Khurja-Kanpur

    section; it has a maturity period of 22 years including a seven year grace period. There

    will be another two tranches of USD1.05bn and USD700mn.

    For Phase IV between Sonnagar and Dankuni, the PPP mode will be used. Initial

    estimates available with DFCCIL indicate that around INR110bn will be required for

    completing the segment. As per a recent meeting called by the Prime Minister for FY13infrastructure targets, the contract for this segment is to be awarded in FY13.

    Phase I (a) between Mughalsarai and Sonnagar is being implemented with Indian

    Railways resources. Civil construction contract for 109 km section (New Ganjkhwaja to

    New Karwandia) has already been awarded in December 2008 and work is in progress.

    Opportunities galore

    DFC will have multi-fold benefits. Both EPC contractors as well as rolling stock

    manufacturers will have increased opportunities from DFC.

    Near-term beneficiaries include EPC contractors like L&T, IVRCL, NCC, HCC, Simplex,Gammon, among others. However, competition is likely to be high as is evident fromthe number of companies applying for pre-qualification.

    Long-term beneficiaries include companies related with associated infrastructure likeTexmaco, Titagarh Wagons, CONCOR, BEML, Kalindee Rail Nirman, Siemens, among

    others.

    Land acquisition: Current status

    Land for the project is being acquired under the Railways (Amendment) Act, 2008, since the

    DFC has been declared as Special Railway Project. The amendment, which gives Indian

    Railways special powers to take possession of land, was essentially brought in to hasten the

    land acquisition process for key projects.

    Land Acquisition Act, 1894, is not applicable to land acquired under the 2008 act.

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    19/25

    Construction

    19 Edelweiss Securities Limited

    Fig. 7: Flowchart of land acquisition process

    Source: Indian Railways, Edelweiss research

    The project has seen steady progress on the land acquisition front. By FY12 end, more than

    60% of total land required had been acquired. A brief snapshot of the land acquisition

    progress is given below:

    Table 7: Land acquisition progress of DFC

    Source: DFCCIL, Edelweiss research

    Project Description/SectionLength

    (km)Area (Ha.)

    Length

    (km)Area (Ha.)

    Length

    (km)Area (Ha.)

    Length

    (km)Area (Ha.)

    Award

    (INR mn)

    Disbursed

    (INR mn)

    Eastern Corridor

    Khurja-Kanpur APL-1 343 1,320 343 1,320 343 1,320 314 1,172 89% 2,360 840

    Kanpur-Mughalsarai APL-2 393 1,400 393 1,400 393 1,400 363 1,083 77% 2,360 980

    Ludhiana-Khurja Section APL-3 447 802 447 802 447 802 317 520 65% 9,372 137

    Mughalsarai-Sonnagar 118 319 118 319 106 303 74 186 58% 2,630 490

    Sonnagar-Dhankuni 538 1,002 123 180 0 0 0 0 0% - -Sub-total 1,839 4,843 1,424 4,021 1,289 3,825 1,068 2,961 61% 16,722 2,447

    Western Corridor

    Phase-I Rewari-Vadodara 930 3,608 930 3,608 826 3,205 776 2,998 83% 7,930 5,970

    Phase-II Vadodara-JNPT & Dadri - Rewari 569 2,252 569 2,252 464 1,718 143 782 35% 3,660 3,460

    Sub-total 1,499 5,860 1,499 5,860 1,290 4,923 919 3,780 65% 11,590 9,430

    Grand Total 3,338 10,703 2,923 9,881 2,579 8,748 1,987 6,741 63% 28,312 11,877

    Total ScopeSection/Area

    notified under 20A

    Section/Area

    notified under 20E

    Progress of issuing

    of 20FAmount

    % of land

    acquired

    (20 F

    stage)

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    20/25

    Construction

    20 Edelweiss Securities Limited

    The comparatively slow progress on land acquisition for the Sonnagar-Dankuni stretch has

    pushed the overall figure down. However, with the new directive from the Prime Ministers

    Office, we now expect things to gather pace.

    Meaning of various stages highlighted in the table above is given below:

    Section 20A: The issuance of 20A means marking of the land identified for acquisition,which is ready for further survey and compensation studies.

    Section 20E: This notification is issued for declaration of acquisition' by the UnionGovernment under the Indian Railways (Amendment) Act 2008. 20E is an important

    milestone as it allows the railways to take steps required to build, maintain and manage

    the project.

    Section 20F: This relates to the eventual declaration of award by paying compensationto the owner and closing the deal by taking possession of the land.

    Tendering: Current status

    DFCCIL has been preparing the framework for this humungous project over the past coupleof years. Work had commenced more than four years ago when tenders for detailed

    engineering construction survey were awarded. Since then, ~20 contracts for project

    management and consultancy works as well as other ancillary jobs have been awarded.

    As far as civil construction is concerned, till date, two major tenders have been awarded on

    DFC (both awarded in FY09):

    Construction of 54 major bridges in the Vasai-Bharuch section (Phase II i.e., JNPT-Vadodara stretch) of the Western corridor - INR6.05bn order bagged by Soma

    Enterprises.

    Civil construction contract for 109 km section form New Ganjkhwaja to New Karwandia(Phase I (a) MughalsaraiSonnagar stretch) on Eastern corridor - INR7.8bn contractbagged by B. Seenaiah.

    Currently, DFCCIL is in the process of awarding four major tenders:

    INR80bn-90bn contract for civil construction, building and track works for package 1and 2 on Phase I (Rewari-Vadodara) of the Western corridor. Phase I has been further

    sub-divided into three separate packages:

    Package 1: Rewari-Ajmer section of 283 kms. Package 2: Ajmer-Ikbalgarh section of 342 kms. Package 3: Ikbalgarh-Vadodara section of 305 kms.

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    21/25

    Construction

    21 Edelweiss Securities Limited

    Fig. 8: Tendering on Western DFC

    Source: DFCCIL, Edelweiss research

    The RfQ process for package 1 & 2 (overall 625 kms) is already over. Competition for

    this is now limited to two contendersL&T-Sojitz Corporation and the IRCON-Leighton

    Welspun-Mitsui consortium. We expect the contract to be awarded over the nextcouple of months.

    INR60bn-70bn contract for civil construction, structure and track laying work for Phase I(Khurja-Kanpur) on the Eastern corridor. The RfQ process for this contract is already

    over; 27 companies expressed interest, of which 14 have been pre-qualified for bidding.

    The contract will be awarded by September 2012.

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    22/25

    Construction

    22 Edelweiss Securities Limited

    Fig. 9: Eastern DFC

    Source: Edelweiss research

    Design, procurement and construction of track and related works for 66km stretch fromNew Karwandiya to Durgawati on Phase I (a) (Mughalsarai-Sonnagar section of the

    Eastern corridor. The RfQ process is over and 22 firms have been pre-qualified for this

    stretch.

    Design, construction and commissioning of 2*25 kV electrification and signalling worksfor the 66km stretch from New Karwandiya to Durgawati. The RfQ process is over and 4

    firms have been pre-qualified for this stretch.

    Apart from this, work for awarding the following contracts has already commenced:

    RfQ process for design and construction of civil, building and track works for package 3on Phase I (Rewari-Vadodara) of the Western corridor has already started. The RfQ

    document mentions that submission of bids will happen in Feb 2013.

    Preparation for awarding the systems contract (electrical, signaling and telecom) forPhase I (Khurja-Kanpur section) on Eastern corridor is already on.

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    23/25

    Construction

    23 Edelweiss Securities Limited

    World Bank has approved short listing of general consultants for Phases II and III on theEastern corridor and RfP documents for the same have been issued. DFCCIL expects to

    award these contracts by July 2013 and October 2013, respectively.

    The way ahead: DFC gathering pace

    The governments emphasis on the project is evident from the proposed guarantee to be

    provided by Indian Railways (assuring timely servicing of the underlying principal/interestobligations) against DFCCILs future borrowing programme. Also, given its strategic

    importance, the project is being directly monitored by the Prime Ministers Office.

    In this backdrop, along with steady progress in land acquisition and financing, we expect the

    DFC project to roll on smoothly going ahead. The World Banks and JICAs involvement will

    ensure its regular monitoring.

    This is evident from the fact that one of the conditions laid down for project award is the

    achievement of milestones for land acquisition (currently, tenders have been invited only

    for packages which have acquired more than 80% of land). We believe the focus on getting

    land acquisition/ other regulatory approvals in place before project award is likely to ensure

    that there are no hiccups in execution.

    The objective of completing the project by 2017-18 means the next two years are expected

    to see a lot of action on the tendering side. Overall, we believe the project will be a

    significant value enhancer for the Indian logistics space apart from being a new opportunity

    for EPC contractors.

    Table 8: Valuations snapshot

    *P/E & P/BV for implied construction business

    Source: Edelweiss research

    CMP Target price Asset value

    (INR per share) (INR per share) (INR per share) FY13E FY14E FY13E FY14E FY13E FY14E FY13E FY14E

    Sadbhav Engg* 141 170 91 8.8 11.6 5.7 4.3 58.7 69.7 0.8 0.7

    Ramky Infra* 90 253 64 23.7 29.3 1.1 0.9 192.7 222.0 0.1 0.1

    IVRCL Infra* 51 40 20 1.6 2.4 19.2 12.9 74.8 75.7 0.4 0.4NCC* 40 59 22 4.2 6.1 4.2 2.9 97.8 103.6 0.2 0.2

    Hindustan Construction 20 24 24 (3.5) (2.9) NA NA 17.9 15.0 1.1 1.3

    Simplex Infra 209 218 0 24.3 33.9 8.6 6.2 266.3 297.8 0.8 0.7

    B.L. Kashyap 9 11 0 0.8 1.5 10.4 5.8 28.2 29.7 0.3 0.3

    Consolidated Construction 13 12 0 1.2 2.3 11.5 5.8 34.6 36.3 0.4 0.4

    Rel iance Infra 534 936 936 50.1 50.7 10.7 10.5 747.0 789.6 0.7 0.7

    CompanyEPS (INR) P/E Book value (INR) P/BV

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    24/25

    Construction

    24 Edelweiss Securities Limited

    Edelweiss Securities Limited, Edelweiss House, off C.S.T. Road, Kalina, Mumbai 400 098.

    Board: (91-22) 4009 4400, Email: [email protected]

    Vikas Khemani Head Institutional Equities [email protected] +91 22 2286 4206

    Nischal Maheshwari Co-Head Institutional Equities & Head Research [email protected] +91 22 4063 5476

    Nirav Sheth Head Sales [email protected] +91 22 4040 7499

    Coverage group(s) of stocks by primary analyst(s):ConstructionConsolidated Construction Co., Hindustan Construction Co., IL&FS Transportation Networks, IRB Infrastructure, IVRCL Infra, Jaiprakash Associates, BL

    Kashyap & Sons Ltd, Nagarjuna Construction Co, Ramky Infrastructure, Sadbhav Engineering, Simplex Infrastructures Ltd

    Distribution of Ratings / Market Cap

    Edelweiss Research Coverage Universe

    Rating Distribution* 104 60 18 183

    * 1 stocks under review

    Market Cap (INR) 114 58 11

    Date Company Title Price (INR) Recos

    Recent Research

    19-Jun-12 Construction Highway to growth;

    Sector Update

    07-Jun-12 IL&FS

    ransporation

    In pole position;

    Visit Note

    175 Buy

    06-Jun-12 Sadbhav

    Engineering

    Temporary hiccup;

    Result Update

    120 Buy

    > 50bn Between 10bn and 50 bn < 10bn

    Buy Hold Reduce Total

    Rating Interpretation

    Buy appreciate more than 15% over a 12-month period

    Hold appreciate up to 15% over a 12-month period

    Reduce depreciate more than 5% over a 12-month period

    Rating Expected to

  • 7/28/2019 Construction Sector Update Jun 12 EDEL1

    25/25

    SECTOR UPDATE

    Access the entire repository of Edelweiss Research on www.edelresearch.com

    DISCLAIMERGeneral Disclaimer:

    This document has been prepared by Edelweiss Securities Limited (Edelweiss). Edelweiss, its holding company and associate companies are a full service, integrated

    investment banking, portfolio management and brokerage group. Our research analysts and sales persons provide important input into our investment banking

    activities. This document does not constitute an offer or solicitation for the purchase or sale of any financial instrument or as an official confirmation of any

    transaction. The information contained herein is from publicly available data or other sources believed to be reliable, but we do not represent that it is accurate or

    complete and it should not be relied on as such. Edelweiss or any of its affiliates/ group companies shall not be in any way responsible for any loss or damage that

    may arise to any person from any inadvertent error in the information contained in this report. This document is provided for assistance only and is not intended to

    be and must not alone be taken as the basis for an investment decision. The user assumes the entire risk of any use made of this information. Each recipient of this

    document should make such investigation as it deems necessary to arrive at an independent evaluation of an investment in the securities of companies referred to

    in this document (including the merits and risks involved), and should consult his own advisors to determine the merits and risks of such investment. The investment

    discussed or views expressed may not be suitable for all investors. We and our affiliates, group companies, officers, directors, and employees may: (a) from time to

    time, have long or short positions in, and buy or sell the securities thereof, of company (ies) mentioned herein or (b) be engaged in any other transaction involving

    such securities and earn brokerage or other compensation or act as advisor or lender/borrower to such company (ies) or have other potential conflict of interest

    with respect to any recommendation and related information and opinions. This information is strictly confidential and is being furnished to you solely for your

    information. This information should not be reproduced or redistributed or passed on directly or indirectly in any form to any other person or published, copied, in

    whole or in part, for any purpose. This report is not directed or intended for distribution to, or use by, any person or entity who is a citizen or resident of or located

    in any locality, state, country or other jurisdiction, where such distribution, publication, availability or use would be contrary to law, regulation or which would

    subject Edelweiss and affiliates/ group companies to any registration or licensing requirements within such jurisdiction. The distribution of this document in certain

    jurisdictions may be restricted by law, and persons in whose possession this document comes, should inform themselves about and observe, any such restrictions.

    The information given in this document is as of the date of this report and there can be no assurance that future results or events will be consistent with this

    information. This information is subject to change without any prior notice. Edelweiss reserves the right to make modifications and alterations to this statement as

    may be required from time to time. However, Edelweiss is under no obligation to update or keep the information current. Nevertheless, Edelweiss is committed toproviding independent and transparent recommendation to its client and would be happy to provide any information in response to specific client queries. Neither

    Edelweiss nor any of its affiliates, group companies, directors, employees, agents or representatives shall be liable for any damages whether direct, indirect, special

    or consequential including lost revenue or lost profits that may arise from or in connection with the use of the information. Past performance is not necessarily a

    guide to future performance. The disclosures of interest statements incorporated in this document are provided solely to enhance the transparency and should not

    be treated as endorsement of the views expressed in the report. Edelweiss Securities Limited generally prohibits its analysts, persons reporting to analysts and their

    dependents from maintaining a financial interest in the securities or derivatives of any companies that the analysts cover. The information provided in this document

    remains, unless otherwise stated, the copyright of Edelweiss. All layout, design, original artwork, concepts and other Intellectual Properties, remains the property

    and copyright Edelweiss and may not be used in any form or for any purpose whatsoever by any party without the express written permission of the copyright

    holders.

    Analyst Certification:

    The analyst for this report certifies that all of the views expressed in this report accurately reflect his or her personal views about the subject company or companies

    and its or their securities, and no part of his or her compensation was, is or will be, directly or indirectly related to specific recommendations or views expressed in

    this report.

    Analyst holding in the stock: No.

    Additional Disclaimer for U.S. Persons

    This research report is a product of Edelweiss Securities Limited, which is the employer of the research analyst(s) who has prepared the research report. The

    research analyst(s) preparing the research report is/are resident outside the United States (U.S.) and are not associated persons of any U.S. regulated broker-dealer

    and therefore the analyst(s) is/are not subject to supervision by a U.S. broker-dealer, and is/are not required to satisfy the regulatory licensing requirements of

    FINRA or required to otherwise comply with U.S. rules or regulations regarding, among other things, communications with a subject company, public appearances

    and trading securities held by a research analyst account.

    This report is intended for distribution by Edelweiss Securities Limited only to "Major Institutional Investors" as defined by Rule 15a-6(b)(4) of the U.S. Securities and

    Exchange Act, 1934 (the Exchange Act) and interpretations thereof by U.S. Securities and Exchange Commission (SEC) in reliance on Rule 15a 6(a)(2). If the recipient

    of this report is not a Major Institutional Investor as specified above, then it should not act upon this report and return the same to the sender. Further, this report

    may not be copied, duplicated and/or transmitted onward to any U.S. person, which is not the Major Institutional Investor.

    In reliance on the exemption from registration provided by Rule 15a-6 of the Exchange Act and interpretations thereof by the SEC in order to conduct certain

    business with Major Institutional Investors, Edelweiss Securities Limited has entered into an agreement with a U.S. registered broker-dealer, Marco Polo Securities

    Inc. ("Marco Polo").

    Transactions in securities discussed in this research report should be effected through Marco Polo or another U.S. registered broker dealer.

    Copyright 2009 Edelweiss Research (Edelweiss Securities Ltd). All rights reserved