    SECTION 01 79 00 Page 1

    *****************************************************************************

    ELECTRONIC COMMENT TRACKING PERIOD OPEN (01-AUG-13 to 01-Nov-13)

    During the period where this review is open, interested parties may ask

    questions or offer suggestions through the designated website. Questions

    submitted by email or telephone will not be acknowledged or answered.

    The website used allows users to submit their questions without other

    submitters seeing who asked the question. Question authorship will, however,

    be visible to those answering the questions. Reviewers will be notified by

    email when their question has been answered. At that point, reviewers may

    return to view the answers to their question.

    Submitting the first question:

    a. Go to https://www.projnet.org/. Complete the form as follows:1. Managing Agency Select USACEfrom the list2. Email Your business email3. Password This field MUST be left blank4. Quick Add Key EnterWXU4MAin the first Quick Add Key box5. Quick Add Key Enter 8N98KE in the second Quick Add Key box6. Terms of Use Button "I Agree MUST be checked7. Sign In Button Click the button

    b. On your first visit, a page will open asking you to create a useraccount. Remember the Secret Question and Secret Answer you will

    need to it to see when returning for the answers to your question(s).

    Complete this form and submit it.

    c. Once you have created your user account, you will be registered andready to begin entering your questions.

    Returning with more questions, or to see answers:

    d. Login to the system as described in step (a) above. Then go to step (e)below.

    e. When challenged, answer your Secret Question and Secret AnswerEXACTLY as you entered them in step (b).

    f. Once you have correctly provided this information, you will be ready tobegin entering additional questions and reviewing reports that show the

    answers to your, and others, questions.

    *****************************************************************************

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    2/15

    SECTION 01 79 00 Page 2

    *****************************************************************************

    DRAFT UFGS-01 79 00 (AUG 2013)

    ------------------------

    Drafting Activity: USACE

    UNIFIED FACILITIES GUIDE SPECIFICATION

    *****************************************************************************

    SECTION TABLE OF CONTENTS

    DIVISION 01 GENERAL REQUIREMENTS

    SECTION 01 79 00

    Construction-Operations Building information exchange (COBie)08/2013

    *****************************************************************************

    1 GENERAL ................................................................. 41.1 REFERENCES .......................................................... 41.2 SUBMITTALS .......................................................... 41.2.1 COBie Information Delivery Plan.................................. 51.2.2 COBie-Specific Submittals........................................ 51.2.3 COBie-Formatted Submittals....................................... 51.2.4 Installed Equipment Photographs.................................. 5

    1.3 GOVERNMENT FURNISHED INFORMATION .................................... 51.3.1 COBie Tool Kit................................................... 51.3.2 COBie Design File................................................ 6

    1.4 QUALITY ASSURANCE ................................................... 61.4.1 COBie-Specific Submittals........................................ 61.4.2 COBie-Formatted Submittals....................................... 71.4.3 COBie Data File and Photographs.................................. 7

    1.5 INFORMATION DELIVERY, STORAGE, AND HANDLING ......................... 81.5.1 Delivery Method COBie-Specific Submittals...................... 81.5.2 Electronic Media................................................. 81.5.3 Transmission of Physical Media................................... 81.5.4 Encryption....................................................... 8

    1.6 RETAINAGE ........................................................... 81.6.1 Architectural Design Phase(30% Design)........................... 91.6.2 Coordinated Design Phase (60% Design)............................ 91.6.3 Construction Documents Phase (100% Design)....................... 91.6.4 Construction Mobilization Phase.................................. 91.6.5 Construction 60% Complete........................................ 9

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    3/15

    SECTION 01 79 00 Page 3

    1.6.6 Beneficial Occupancy Phase....................................... 91.6.7 Fiscal Completion................................................ 9

    2 PRODUCTS ................................................................ 92.1 COMMERCIAL OFF-THE SHELF (COTS) SOFTWARE ............................ 92.2 COBIE TOOL KIT ...................................................... 92.3 APPLICATION ........................................................ 102.3.1 COBie Information Delivery Plan................................. 102.3.2 COBie-Specific Submittal Set.................................... 112.3.3 COBie-Specific Submittals....................................... 112.3.4 COBie-Formatted Submittals...................................... 122.3.5 Installed Equipment Photograph.................................. 15

    3 EXECUTION .............................................................. 15

    -- End of Section Table of Contents --

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    4/15

    SECTION 01 79 00 Page 4

    *****************************************************************************

    DRAFT UFGS-01 79 00 (AUG 2013)

    ------------------------

    Drafting Activity: USACE

    UNIFIED FACILITIES GUIDE SPECIFICATION

    *****************************************************************************

    DIVISION 01 GENERAL REQUIREMENTS

    SECTION 01 79 00

    Construction-Operations Building information exchange (COBie)08/2013

    *****************************************************************************NOTE:

    This specification section is intended for inclusion in design-build and construction contracts.

    For construction-only contracts, design deliverables shall beremoved from this specification before inclusion in the contract.

    ****************************************************************************

    1 GENERAL1.1 REFERENCESThe publications listed below form a part of this specification to the extent

    referenced. The publications are referred to within the text by the basicdesignation only.

    UNITED STATES NATIONAL BUILDING INFORMATION MODEL STANDARD (NBIMS-US)

    COBie, (v 2.4) Construction-Operations Building information exchange

    COBie Guide, (2013) buildingSMART alliance

    INDUSTRY FOUNDATION CLASS MODEL

    ISO 16739:2013, Industry Foundation Classes (IFC) for data sharing in

    the construction and facility management industries

    OMNICLASS

    OmniClass Tables (2013), OCCS Development Committee Secretariat,

    Construction Specification Institute, omniclass.org.

    1.2 SUBMITTALSGovernment approval is required for all submittals provided in this section.

    The Contractor shall submit the following in accordance with Section 01 33 00

    SUBMITTAL PROCEDURES:

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    5/15

    SECTION 01 79 00 Page 5

    1.2.1 COBie Information Delivery PlanThe Contractor shall provide a COBie Information Delivery Plan to document

    their plan to complete the work described in this specification.

    1.2.2 COBie-Specific SubmittalsThe Contractor shall provide COBie-Specific submittals at the major project

    milestones listed below:

    *****************************************************************************NOTE: Remove project phases not included in this Design-Build orConstruction contract.

    *****************************************************************************

    Concept Design Phase (30% Design) COBie File

    Coordinated Design Phase (60% Design) COBie File

    Construction Documents Phase (100% Design) COBie File

    Construction Mobilization Phase COBie File

    Construction 60% Fiscally Complete COBie File

    Beneficial Occupancy Phase COBie File

    Fiscal Completion Phase COBie File

    1.2.3COBie-Formatted SubmittalsThe Contractor shall provide the following submittals, required elsewhere in

    this contract, in COBie-compatible format:

    *****************************************************************************NOTE: Remove submittals not included in this Design-Build orConstruction contract.

    *****************************************************************************

    As-Installed Equipment Schedule

    As-Installed Warranty Tags

    Approved Submittals

    Door Schedule

    Hardware Schedule

    Key Biting Schedule

    Signage ScheduleSpare Parts Schedule

    Warranty Certificates and Data

    Preventative Maintenance Plans

    Diagnostic Testing Plans

    Repair and Replacement Plans

    Real Property Equipment Transfer Report

    1.2.4 Installed Equipment PhotographsThe Contractor shall provide a minimum of two (2) photographs for each piece

    of individually scheduled equipment identified on the Construction Documents

    stage design drawings. The Contractor shall provide one (1) photograph of the

    installed equipment prior to covering by insulation, walls, or ceilings. The

    Contractor shall provide one (1) photograph clearly showing that equipments

    nameplate. The Contractor shall submit a complete set of all photographs in

    digital format, cumulative of all photos to date.

    1.3 GOVERNMENT FURNISHED INFORMATION1.3.1 COBie Tool KitThe Government shall provide one (1) copy of the COBie Tool Kit software to

    the Contractor to support the preparation, testing, and submission of all

    COBie deliverables. For full COBie submittals (1.2.1 COBie-Specific

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    6/15

    SECTION 01 79 00 Page 6

    Submittals) the COBie Tool Kit provides the Design and Construction Quality

    Control Reports. For submittals that rely on the use and re-use of COBie

    information (1.2.2 COBie-Formatted Submittals, 1.2.3 Installed Equipment

    Photographs) the COBie Tool Kit provides partially completed templates

    through which COBie data may be correctly captured in the field.

    *****************************************************************************

    NOTE: Remove the section below if (1) this is a Design-Buildcontract or (2) the Government -DOES NOT HAVE- a Design COBiefile to provide to the Contractor.

    *****************************************************************************

    1.3.2 COBie Design FileThe Government shall provide one (1) electronic copy of the COBie Design File

    to the Contractor. This file is provided for information only. If the

    Contractor chooses to utilize the COBie Design File provided by the

    Government, then the Contractor shall be fully responsibility for any

    corrections and changes needed to bring the format or content of that COBie

    Design File up to the quality standards identified in this specification.

    1.4 QUALITY ASSURANCE1.4.1 COBie-Specific SubmittalsThe Contractor shall meet the following minimum quality standards for all

    COBie-Specific Submittals:

    1.4.1.1COBie Guide General RequirementsThe buildingSMART COBie Guide shall define the minimum quality

    standards for COBie submittals.

    1.4.1.2COBie Guide USACE AppendixThe USACE COBie Guide Appendix shall clarify and supersede the minimum

    quality standards for COBie submittals found in the buildingSMART COBie

    Guide.

    1.4.1.3COBie Data File Facility Asset ScopeThe Contractor shall provide one (1) COBie-Specific Submittal Set for

    each facility identified in a project.

    1.4.1.4COBie Data File Site Asset ScopeThe Contractor shall provide one (1) COBie-Specific Submittal Set for

    SITE assets, if SITE assets are used by multiple facilities.

    1.4.1.5COBie Data File - Reported ErrorsThe Contractor shall be responsible to update all COBie Data files

    until zero (0) errors are reported from the relevant COBie Tool Kit

    Quality Control Report.

    1.4.1.6COBie Data File Reported WarningsThe Contractor shall be responsible to document and submit, for

    Government Approval, the reason for warnings reported from the relevant

    COBie Tool Kit Quality Control Report.

    1.4.1.7COBie Data File Design PhaseThe Contractor shall be responsible to accurately reproduce all design

    drawing schedules in COBie-Specific Submittals. For products scheduled

    by Type, the Contractor shall individually list each specific asset.

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    7/15

    SECTION 01 79 00 Page 7

    *****************************************************************************NOTE: Remove the section below if (1) this is a Design-Buildcontract or (2) the Government HAS- a Design COBie file to

    provide to the Contractor.*****************************************************************************

    1.4.1.8COBie Data File Construction PhaseThe Contractor shall be responsible to provide a Mobilization PhaseCOBie-Specific submittal that reflects the spatial and equipment

    schedules in contraction contract drawings and all subsequent

    amendments.

    1.4.2 COBie-Formatted SubmittalsThe Contractor shall meet the following minimum quality standards for all

    COBie-Formatted Submittals:

    1.4.2.1COBie Tool Kit TemplatesThe Contractor shall utilize the COBie Tool Kit to produce templates

    for all COBie-Formatted Submittals. The Contractor shall identify any

    substitutions in their COBie Information Delivery Plan.

    1.4.2.2COBie-Formatted Submittal ContentsThe Contractor shall be responsible to ensure that the information

    contained in COBie-Formatted Submittals accurately reflects current

    state of the as-built project at the time of the submission.

    1.4.2.3COBie-Formatted SubstitutionsThe Contractor shall be required to explicitly identify all

    substitutions in the Contractors Information Delivery Plan.

    1.4.3 COBie Data File and PhotographsThe Contractor shall be responsible to ensure that location of all linked

    COBie in either COBie-Specific Submittals or COBie-Formatted Submittals

    confirm to the following standards:

    1.4.3.1File Types AllowedThe Contractor shall use the following COBie Document File and

    Photograph types: PDF, JPEG, and native design or shop drawing file

    format.

    1.4.3.2File LinkingThe Contractor shall link COBie Document Files and Photographs to the

    relevant records in the COBie Data File per COBie specification.

    1.4.3.3File SizeThe Contractor shall down-size all COBie Document Files and Photographs

    in a format suitable for on-line viewing. High-Quality (large size) PDF

    files shall be returned to the contractor for revision.

    1.4.3.4File ProtectionThe Contractor shall not restrict COBie Data Files, Document Files or

    Photographic Files from being modified or copied.

    1.4.3.5Single Purpose FilesThe Contractor shall split COBie Document Files to ensure that the

    files pertaining to products contain information from a single

    manufacturer. Furthermore, The Contractor shall split single

    manufacturer files to ensure that the file contains information from on

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    8/15

    SECTION 01 79 00 Page 8

    a single product type. Furthermore, the Contractor shall split specific

    manufacturers product type specific files to ensure that the file

    contains information pertaining to a single submittal type.

    1.5 INFORMATION DELIVERY, STORAGE, AND HANDLING1.5.1 Delivery Method COBie-Specific SubmittalsThe Contractor shall provide COBie-Specific Submittals to the Government in a

    mutually agreed upon method and media as described in the Contractors COBie

    Information Delivery Plan. The COBie Information Delivery Plan shall

    specifically address the following minimum requirements:

    1.5.2 Electronic MediaThe Contractor shall provide data on either disk-based (CD or DVD) or

    portable hard drive media. The Contractor shall be responsible to select and

    apply technology used for COBie electronic data transmission to ensure that

    the full data set is provided on one single "disk" or "drive." The selection

    of disk-based on drive-based media shall be made by the Contractor in the

    COBie Information Delivery Plan.

    1.5.2.1Disk-Based MediaIf disk-based media are provided by the Contractor to the Government,

    then a printed label shall be applied to the data disk and the label

    shall list the name of the project, project location, contract number,

    design firm or prime Contractor companys name, title of submission,

    and security classification of the data contained on the disk The label

    shall also include the name and contact information of the individual

    who produced the final data disk to insure that any problems with the

    data or media can be easily resolved.1.5.2.2 Drive-Based MediaIf drive-based media are provided by the Contractor to the Government,

    then the drive content and date shall be legibly labeled on the outside

    of the drive. The label shall include the phrase "COBie DATA" and the

    appropriate contract or task order number. The label shall also includethe name and contact information of the individual who produced the

    final data disk to insure that any problems with the data or media may

    be easily resolved.

    1.5.3 Transmission of Physical MediaWhen media is not physically delivered to the Government the Contractor may

    utilize, within the United States, an accountable commercial delivery service

    such as US Postal Service, Federal Express, or United Parcel Service. The

    Contractor shall provide the tracking number to the Government and signed

    receipt of the package must be acknowledged by the Government office

    receiving the package. All Storage media shall be wrapped within a separate

    envelope with full mailing address in case the exterior envelop is damaged.

    1.5.4 EncryptionThe Contractor shall encrypt COBie data as directed by Area/Resident/Project

    Office Engineer. The encryption to be used shall be documented in the

    Contractors COBie Information Delivery Plan.

    1.6 RETAINAGEFailure of the Contractor to provide to the Government approved COBie-

    Specific Submittals (1.2.2 COBie-Specific Submittals) shall result in the

    following retainages. The retainage shall be released following the

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    9/15

    SECTION 01 79 00 Page 9

    Contractors compliance with the specifications and Government approval of

    the required COBie data set. These retainages reflect the cost to the

    Government to independently recreate the required COBie Data File (1.2.2.a

    COBie-Specific Submittals COBie Data File) and COBie Document Files (

    1.2.2.b COBie-Specific Submittals COBie Document Files).

    *****************************************************************************

    NOTE: Remove project phases not included in this Design-Build orConstruction contract.

    *****************************************************************************

    *****************************************************************************NOTE: Update retainage to reflect the cost to contract outreplacement COBie deliverables.

    *****************************************************************************

    1.6.1Architectural Design Phase(30% Design)An additional $5,000 retainage shall be held from the Contractor if COBie

    data is not provided upon delivery of the Architectural Design Set.

    1.6.2Coordinated Design Phase (60% Design)An additional $10,000 retainage shall be held from the Contractor if COBie

    data is not provided upon delivery of the Coordinated Design Set.

    1.6.3 Construction Documents Phase (100% Design)An additional $15,000 retainage shall be held from the Contractor if COBie

    data is not provided upon delivery of the Construction Documents Set.

    1.6.4 Construction Mobilization PhaseAn additional $15,000 retainage shall be held from the Contractor if COBie

    data is not provided upon delivery of the Construction Documents Set.

    1.6.5 Construction 60% CompleteAn additional $20,000 retainage shall be held from the Contractor if COBie

    data is not provided at the earlier of 70% fiscal completion or four (4)months prior to the date of beneficial occupancy.

    1.6.6 Beneficial Occupancy PhaseAn additional $25,000 retainage shall be held from the Contractor if COBie

    data is not provided on the date of beneficial occupancy.

    1.6.7 Fiscal CompletionAn additional $30,000 retainage shall be held from the Contractor if COBie

    data is not provided with the as-built drawings at fiscal completion of the

    project.

    2PRODUCTS

    2.1 COMMERCIAL OFF-THE SHELF (COTS) SOFTWAREA variety of COTS software systems have been tested against the COBie

    requirements. The Contractor is responsible for the selection and use of any

    and all software used in the production of COBie deliverables.

    2.2 COBIE TOOL KITThe COBie Tool Kit (1.3 GOVERNMENT FURNISHED INFORMATION) provides: (1)

    quality control testing reports for COBie-Specific Submittals (1.2.2 COBie-

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    10/15

    SECTION 01 79 00 Page 10

    Specific Submittals), (2) templates and merging routines for COBie-Formatted

    Submittals (1.2.3 COBie-Formatted Submittals), (3) reports such as the DD1354

    Transfer of Real Property Report, and (4) a consolidated project eBook that

    may be generated in support (or in lieu) separate Operations and Maintenance

    Documentation.

    2.3APPLICATION2.3.1 COBie Information Delivery PlanWithin 90 days following Notice to Proceed the Contractor shall provide an

    Information Delivery Plan describing the roles and responsibilities, software

    and services that the Contractor plans to use to capture COBie data that

    shall include, but not be limited to, the topics below:

    2.3.1.1COBie Quality Control ResponsibilityThe Contractor shall designate one (1) individual and one (2) alternate

    party responsible for the production of COBie submittals in accordance

    with this specification.

    2.3.1.2COBie Creation and Capture ResponsibilityThe Contractor shall prepare a table that identifies any partyresponsible for the creation and/or capture of each specific COBie data

    elements.

    2.3.1.3COTS Software SelectionThe Contractor shall identify each COTS software product used in the

    production of COBie submittals.

    2.3.1.4COBie Tool KitThe contractors shall identify their expected use of the COBie Tool Kit

    for purposes of Quality Control, production of submittal templates,

    production of contractually required reports, and production of

    electronic O&M manuals.

    2.3.1.5Authoritative Sources

    The Contractor shall describe the way in which the selected COTS

    Software and/or COBie Tool Kit shall be used to collect COBie data and

    provide that data in the appropriate COBie-Specific Submittals (1.2.2

    COBie-Specific Submittals) or COBie-Formatted Submittals (1.2.3 COBie-

    Formatted Submittals).

    2.3.1.6Multiple Data Source MergingThe Contractor shall explicitly identify how the COTS Software and/or

    COBie Tool Kit shall be used to merge electronic information provided

    by multiple design consultants and/or subcontractors.

    2.3.1.7Manual Transcription EliminationThe Contractor shall explicitly identify how the COTS Software and/or

    COBie Tool Kit shall be used to capture COBie data without intermediatepaper documents, manual data transcription, or manual copying of COBie

    data. Contractors COBie Implementation Plans that fail to directly

    address reductions in cost to collect COBie data shall be returned to

    the Contractor for revision.

    2.3.1.8Site Survey EliminationThe Contractor shall explicitly identify how the Manual Transcription

    Elimination described in the COBie Information Delivery Plan have been

    used to eliminate site survey data collection. Contractors COBie

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    11/15

    SECTION 01 79 00 Page 11

    Implementation Plans that fail to directly address the elimination of a

    minimum of one (1) job site survey shall be returned to the Contractor

    for revision.

    2.3.2 COBie-Specific Submittal SetThe Contractor shall provide a complete set of files in each COBie-Specific

    Submittal Set as described below:

    2.3.2.1COBie Data FileOne (1) COBie Data File shall be provided with each COBie-Specific

    Submittal Set.

    2.3.2.2COBie Data File Quality Control ReportOne (1) COBie Quality Control Report shall be provided with each COBie-

    Specific Submittal Set. The Contractor shall select the COBie Tool Kit

    software (1.3 GOVERNMENT FURNISHED INFORMATION) Quality Control report

    for Design or Construction depending on the phase of the COBie Data

    File.

    2.3.2.3COBie Document FilesIndividual Portable Document Format (PDF) files shall be created for

    each approved submittal and linked in the COBie Data File to the

    related facility information.

    2.3.2.4COBie Equipment PhotographsPhotographs of installed equipment as of the date of submission of the

    COBie-Specific Submittal Set shall be provided as specified by the

    COBie format.

    2.3.3 COBie-Specific SubmittalsThe Contractor shall provide COBie-Specific Submittal Sets as described

    below, as documented in the Contractors COBie Information Delivery Plan:

    *****************************************************************************

    NOTE: Remove project phases not included in this Design-Build orConstruction contract.*****************************************************************************

    2.3.3.1Architectural Design Phase (30% Design)The Contractor shall provide an Architectural Design Phase COBie file

    that contains the same information found on the design drawings

    submitted at this stage of the project. COBie contents at this stage

    are focused on room, room types, and finish schedules; and equipment

    such as plumbing and lighting fixtures found in the associated design

    drawings.

    2.3.3.2 Coordinated Design Phase (60% Design)The Contractor shall provide a Coordinated Design Phase COBie file that

    contains the same information found on the design drawings submitted atthis stage of the project. COBie contents at this stage update the

    Architectural Design Phase (30% Design) COBie file and emphasize the

    inclusion of equipment schedules provided by design and engineering

    consultants.

    2.3.3.3 Construction Documents Phase (100% Design)The Contractor shall provide a Construction Documents Phase COBie file

    that contains the same information found on the design drawings

    submitted at this stage of the project. COBie contents at this stage

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    12/15

    SECTION 01 79 00 Page 12

    update the Coordinated Design Phase (60% Design) COBie file and

    emphasize the completion of room finish and equipment schedules. The

    basis of design for all scheduled equipment types shall be provided.

    *****************************************************************************NOTE: Remove the section below if (1) this is a Design-Buildcontract or (2) the Government HAS- a Design COBie file to

    provide to the Contractor.*****************************************************************************

    2.3.3.4 Construction Mobilization PhaseWithin 90 days following construction Notice to Precede the Contractor

    shall provide a Construction Mobilization COBie file that contains the

    same information found on the Construction Documents (100% Design)

    COBie file as updated to include all contract amendments. The

    Contractors Information Delivery Plan shall discuss the re-use and

    updating of this COBie file as the basis for the delivery of subsequent

    COBie deliverables.

    2.3.3.5 Construction 60% Fiscal Complete PhaseThe Contractor shall provide a Construction 60% Fiscal Complete COBiefile updated to reflect the current state of the project at this

    milestone. This COBie deliverable shall reflect all changes to COBie

    data resulting from executed modifications at the time of the

    submission of this file. The Contractors Information Delivery Plan

    shall discuss the re-use and updating of this COBie file as the basis

    for the delivery of subsequent COBie deliverables.

    2.3.3.6 Beneficial Occupancy PhaseThe Contractor shall provide a Beneficial Occupancy Phase COBie file

    updated to reflect the current state of the project at the time of

    Beneficial Occupancy. This COBie deliverable shall reflect all changes

    to COBie data resulting from executed modifications at the time of the

    submission of this file. The Contractor shall include COBie data

    needed to inform the facility manager of the maintenance activityconducted by the Contractor prior to Beneficial Occupancy. The

    Contractors Information Delivery Plan shall discuss the re-use and

    updating of this COBie file as the basis for the delivery of subsequent

    COBie deliverables.

    2.3.3.7 Fiscal Completion PhaseThe Contractor shall provide a Fiscal Completion Phase COBie file

    updated to reflect the current state of the project at the time of

    Fiscal Completion. The Contractor shall include COBie data needed to

    inform the facility manager of the maintenance activity conducted by

    the Contractor between the previous COBie deliverable and this final

    COBie deliverable. This file shall fully reflect the as-built

    conditions and include changes required to COBie data resulting from

    all contract amendments and modifications.

    2.3.4 COBie-Formatted SubmittalsThe Contractor shall provide COBie-Formatted Submittal Sets as described

    below, as documented in the Contractors COBie Information Delivery Plan:

    *****************************************************************************NOTE: Remove if UFGS 01 33 00 is not in this Design-Build orConstruction contract.

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    13/15

    SECTION 01 79 00 Page 13

    *****************************************************************************

    2.3.4.1Approved SubmittalsThe Contractor shall prepare and submit monthly updates of all approved

    submittal line items. The following minimum information shall be

    provided in COBie format: product type, specification section, document

    name, document type, document website location. The Contractor shall

    also provide a compressed, but legible, PDF of the approved submittaldocument. If the submittal document contains multiple sub-types of

    documents, the Contractor shall split the file into documents each of a

    category (1.4.3.5 Single Purpose Files).

    *****************************************************************************NOTE: Remove if UFGS 01 75 00 is not in this Design-Build orConstruction contract.

    *****************************************************************************

    2.3.4.2Diagnostic Testing PlansThe Contractor shall prepare and submit information on preventative

    maintenance testing requirements. The following minimum information

    shall be provided in COBie format: product type, manufacturer, modelnumber, test name, expected test values and/or testing limits, actual

    test value.

    *****************************************************************************NOTE: Remove if UFGS 01 78 00 is not in this Design-Build orConstruction contract.

    *****************************************************************************

    2.3.4.3As-Installed Equipment ScheduleThe Contractor shall prepare and submit monthly updates of installed

    equipment. The following minimum information shall be provided in

    COBie format: component name, installed manufacturer, installed model

    number, serial number, manufacturers catalog reference number, room

    number from which equipment is operated, specification section andparagraph, installation date, and start-up date.

    2.3.4.4As-Installed Warranty TagsThe contractor shall prepare and submit monthly updates of information

    provided on installed equipment tags. The following minimum

    information shall be provided in COBie format: product or material

    name, product type, manufacturer name, installed model number, serial

    number, responsible contractor contact information, warranty start

    date, warranty duration, warranty contact information, warranty

    response time priority code.

    2.3.4.5Spare Parts ScheduleThe Contractor shall prepare and submit information on spare parts.

    The following minimum information shall be provided in COBie format:

    product type, manufacturer, model number, manufacturers part number,

    part name, minimum stock level, replacement ordering level, part

    supplier, supplier part number, and related manufacturer or

    commissioning agent documents.

    2.3.4.6Warranty Certificates and DataThe Contractor shall prepare and submit information on product

    warranties. The following minimum information shall be provided in

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    14/15

    SECTION 01 79 00 Page 14

    COBie format: product type, manufacturer contact information, model

    number, suppliers contact information, warranty guarantors contact

    information, warranty description, durations, warranty start date,

    expected warranty response time, and related manufacturer warranty

    certificate documents.

    2.3.4.7Preventative Maintenance PlansThe Contractor shall prepare and submit information on preventativemaintenance. The following minimum information shall be provided in

    COBie format: product type, manufacturer, model number, job name, job

    description, required tools, materials, and training, and related

    manufacturer or commissioning agent documentation.

    2.3.4.8Repair and Replacement PlansThe Contractor shall prepare and submit information on product and

    system troubleshooting, repair, and replacement. The following minimum

    information shall be provided in COBie format: product type,

    manufacturer, model number, job name, job description, required tools,

    materials, and training, and related manufacturer or commissioning

    agent documentation.

    2.3.4.9Real Property EquipmentThe contractor shall provide all required deliverables of the DD 1354,

    Transfer and Acceptance of Military Real Property, Form using COBie

    data as the basis for real property assets. A separate report of

    personal property installed by the contractor shall also be provided.

    *****************************************************************************NOTE: Remove if UFGS 08 11 13 is not in this Design-Build orConstruction contract.

    *****************************************************************************

    2.3.4.10 Door ScheduleThe Contractor shall prepare and submit information on installed doors.

    The following minimum information shall be provided in COBie format:door type, door number, door size, frame type, fire rating, door

    finish, operating room number, connecting room number.

    *****************************************************************************NOTE: Remove if UFGS 08 71 00 is not in this Design-Build orConstruction contract

    *****************************************************************************

    2.3.4.11 Hardware ScheduleThe Contractor shall prepare and submit information on installed

    hardware. The following minimum information shall be provided in COBie

    format: hardware set type, installed manufacturer, installed model

    number, manufacturers catalog reference number, quantity used, size,

    finish, BHMA finish designation, fire rating, key control number.

    2.3.4.12 Key Biting ScheduleThe Contractor shall prepare and submit information on keyed locks.

    The following minimum information shall be provided in COBie format:

    individual keys (identified as COBie Component records), key cuts

    (identified as COBie Type records), door operated, identification of

    additional key cuts available.

  • 7/30/2019 Construction-Operations Building Information Exchange (COBie)

    15/15

    SECTION 01 79 00 Page 15

    *****************************************************************************NOTE: Remove if UFGS 10 14 02 is not in this Design-Build orConstruction contract

    *****************************************************************************

    2.3.4.13 Signage ScheduleThe Contractor shall prepare and submit information on door/room

    signage. The following minimum information shall be provided in COBieFormat: room number, signage type, signage text, signage inserts,

    symbol text, remarks.

    2.3.5 Installed Equipment PhotographThe Contractor shall prepare and submit the minimum specified

    electronic photographs of installed equipment reported in the As-

    Installed Equipment Schedule in COBie Format. Additional photographs

    maybe provided documenting the as-installed condition of equipment to

    be covered later by insulation, ceilings, floors, or partitions. The

    set of all photographs shall be provided as attachments to the monthly

    As-Installed Equipment Schedule. The following minimum information

    shall be provided in COBie format: component name, photograph name,

    date photograph was taken, description/notes regarding the job progressor condition.

    3 EXECUTIONNot used.