construction milestones 4 phases
TRANSCRIPT
Construction Milestones Magnolia Manor
Timeline
Acquire Property By Nov. 30, 2007
Site Preparation Completed By March 1, 2008
Foundation Completed By June 1, 2008
Concrete / Framing Completed By Aug. 31, 2008
Construction Completed By Jan. 31, 2009
Occupancy Date By Feb. 28, 2009
Rehab of Social Ministry Center By July 1, 2008
Construction Completed By Sept. 1, 2008
Occupancy Date By Sept. 30, 2008
Construction Milestones Whitewater Manor
Timeline
Acquire Property By Aug. 31, 2007
Site Preparation Completed By Oct. 30, 2007
Foundation Completed By Jan. 31, 2008
Move Modular Homes By Mar. 31, 2008
Homes set and rehabbed, if necessary By July 1, 2008
Occupancy Date By Aug. 31, 2008
Construction Milestones Walker Manor
Timeline
Acquire Property By Mar. 31, 2008
Site Preparation Completed By June 30, 2008
Foundation Completed By Sept. 1, 2008
Move Brick / Stone Homes By Oct. 31, 2008
Homes set and rehabbed, if necessary By Mar. 31, 2009
Occupancy Date By June 1, 2009
Construction Milestones Frederick Manor Timeline
Acquire Property By Mar. 31, 2008
Site Preparation Completed By June 30, 2008
Foundation Completed By Sept. 30, 2008
Concrete / Framing Completed By Nov. 30, 2008
Construction Completed By Sept. 30, 2009
Occupancy Date By Oct. 31, 2009