construction management - work study

Upload: rubbydean

Post on 03-Jun-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Construction Management - Work Study

    1/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    1

    FACULTY OF BUILT ENVIRONMENT

    DEPARTMENT OF QUANTITY SURVEYING

    SEM I 2010/2011

    SBQ 4612

    CONSTRUCTION MANAGEMENT

    WORK STUDY

    Topic: Apply a production improvement method using work study to

    identify a standard time of a construction activity

    GROUP MEMBERS:

    1. JESSYNTHA WILLIAMS D/O SOOSAY WILLIAMS 881129-01-67362. MOTHILAL S/O MUNIANDY 880718-56-50933. NUR FADILAH BINTI DARMANSAH 870118-49-53284. NURKHAIRANI BINTI MOHD RUSDI 881207-26-52105. SAMIDAH BINTI SAMLAWI 880921-01-5222

    LECTURER: ASSOC. PROF DR RAZALI BIN ADUL HAMID

    SUBMISSION DATE: 11THOCTOBER 2010

  • 8/12/2019 Construction Management - Work Study

    2/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    2

    TABLE OF CONTENT

    NO. ITEM PAGE

    1.0 Work study1.1 Why is Work Study Valuable? 41.2 Objective of Work Study 71.3 Techniques of Work Study and Their Relationship 71.4 Basic Procedure of Work Study 91.5 Work Study and Production Management 10

    2.0 Method Study2.1 Procedure of Method Study 132.2 Factor considered in the Method Study 14

    2.2.1 Economic Considerations 142.2.2 Technical Consideration 162.2.3 Human Reactions 17

    2.3 Recording Technique2.3.1 Flow Process Charts 182.3.2 Flow Diagrams 212.3.3 String Diagrams 212.3.4 Models and Templates 22

    2.4 Critical examination2.4.1 Site Layout Problems 232.4.2 Multiple Activity Chart 23

    3.0 Work Measurement3.1 General Remarks on Work Measurement 243.2 Definition 253.3 The Purpose of Work Measurement 273.4 The Uses of Work Measurement 27

  • 8/12/2019 Construction Management - Work Study

    3/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    3

    3.5 The Basic Procedure 283.6 The Technique of Work Measurement 29

    4.0 Time Study4.1 What is Time Study? 304.2 Time Study Equipment 30

    4.2.1 Stop Watch 304.2.2 Study Board 31

    4.3 Step in Making a Time Study 314.4 Breaking the Job Into Elements 324.5 Deciding on The Elements 324.6 Sample Size 334.7 Factors Affecting the Rate of Working 34

    4.7.1 Effectiveness 344.7.2 Speed 35

    4.8 Terminology Explained 36

    5.0 Case Study5.1 Ceiling Skim Coating 38555.2 Cement Rendering 56735.3 Electrical Trunking 74915.4 Plastering On Beam 921035.5 Tiling Works 104127

    6.0 References 128

  • 8/12/2019 Construction Management - Work Study

    4/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    4

    1.0 WORK STUDY

    1.1 Why is Work Study Valuable?

    There is nothing new about the investigation and improvement of operationat

    workplace; good managers have been investigating and improving ever since human effort

    was first organized on a large scale. Managers of outstanding ability have always been able to

    make notable advances. Unfortunately, no country seems to have adequate supply of

    competent managers. The prime value of work study lies in the fact that, by carrying out it

    systematic procedures, a manager can achieve results as good as or better than the less

    systematic procedures, a manager can achieve results as good as or better than the less

    systematic genius was able to achieve in the past.

    Work study succeeds because it is systematic both in the investigation of the problem

    being considered and in the development in the solution. Systematic investigation takes time.

    It is therefore necessary, in all but the smallest firms, to separate the job of making work

    studies from the task of management. Factory managers or supervisors, in their day-to- day

    work, with its many human and material problems, are never free from interruption for log.

    However capable they may be, managers can rarely afford to devote a long time, without

    interruption to the study of a single activity on the factory floor in a working area.

    This means that it is almost always impossible for them to obtain all the facts about

    what is happening in the course of that activity. Unless all the facts are known, it is impossibleto be sure that any alterations in procedure which are made are based on accurate information

    and will be fully effective. It is only by continuous observation and study at the workplace or

    in the area where the activity is taking place that the facts can be obtained. This means that the

    work study must always be the responsibility of someone who is able to undertake it full time,

    without direct management duties: someone in a staff and not a line position. Work study is a

    service to management and supervision.

    Jessyntha

  • 8/12/2019 Construction Management - Work Study

    5/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    5

    We now discussed, very briefly, some aspects of the nature of the work and study and

    why it is such a valuable tool of management. There are other reasons to be added to the

    above. These may be summarized as follows:

    a) It is means of raising the productivity of a plant or operating unit by the reorganizationof work, a method which normally involves little or no capital expenditure on facilities

    and equipment.

    b) It is systematic. This ensures no factor affecting the efficiency of an operation isoverlooked, whether in analyzing the original practices or in developing the new, and

    all the facts about that operation are available.

    c) It is the most accurate means evolved of setting standards of performance, on whichthe effective planning and control of production depends.

    d) It can contribute to the improvement of safety and working conditions at work byexposing hazardous operations and developing safer methods of performing

    operations.

    e) The savings resulting from properly applied work study start at once and continue aslong as the operation continues in the improved form.

    f) It is a tool which can be applied everywhere. It can be used with success whereverwork is done or plant is operated, not only in manufacturing shops but also in offices,stores, laboratories and service industries such as wholesale and retail distribution and

    restaurants, and on farms.

    g) It is relatively cheap and easy to apply.h) It is one of the most penetrating tools of investigation available to management. This

    makes it an excellent weapon for starting on attack on inefficiency in any organization

    since, in investigating one set of problems, the weakness of all the other functions

    affecting them will be gradually be laid bare.

    This last point is worth further discussion. Because work study is systematic, and

    because it involves investigation by direct observation, it will show up any shortcomings in all

    activities affecting that operation. For example, observation may show that the time of an

    operative on a production job is being wasted through having to wait for supplies of materials

    or to remain idle through the breakdown of the machine. This point at once to a failure of

    material control or a failure on the part of the maintenance engineer to carry out proper

    Jessyntha

  • 8/12/2019 Construction Management - Work Study

    6/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    6

    maintenance procedures. Similarly, time may be wasted through short batches of work,

    necessitating the constant resetting of machines, on a scale which may only become apparent

    after prolonged study. This point to poor production planning or marketing policy which

    requires looking into.

    Work study acts like a surgeons knife, laying bare the activities of a company and

    their functioning, good or bad, for all to see. It can therefore show up people. For this

    reason it must be handled, like the surgeons knife with skill and care. Nobody likes being

    shown up, and unless the work study specialist displays great tactic in handling people he or

    she may arouse the animosity of management and workers alike, which will make it

    impossible to do the job properly.

    Managers and supervisors have generally failed to achieve the savings and

    improvements which can be affected by work study because they have been unable to apply

    themselves continuously to such things, even when they have been trained. It is not enough

    for work study to be systematic. To achieve really important results it must be applied

    continuously, and throughout the organization.It is no use work study practitioners doing a

    good job and then sitting back and congratulating themselves, or being transferred shortly

    afterwards by management to something else.

    The savings achieved on individual jobs, although sometimes large in them, are

    generally small when compared with the activity of the company as a whole. The full effect is

    felt in an organization only when work study is applied everywhere, and when everyone

    becomes imbued with theattitude of mind which is the basis of successful work study:

    intolerance of waste in any form, whether of material, time, effort or human ability: and the

    refusal to accept without question that things must be done in a certain way because that is

    the way they have always be done.

  • 8/12/2019 Construction Management - Work Study

    7/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    7

    1.2 Objectives of Work Study

    Work study has contributed immeasurably to the search for better method, and the

    effective utilisation of this management tool has helped in the accomplishment of higher

    productivity. Work study is a management tool to achieve higher productivity in any

    organisation whether manufacturing tangible products or offering services to its customers.

    The objectives of work study are:

    a) To analyse the present method of doing a job, systematically in order to develop a newand better method.

    b) To measure the work content of a job by measuring the time required to do the job fora qualified worker and hence to establish standard time.

    c) To increase the productivity by ensuring the best possible use of human, machine andmaterial resources and to achieve best quality product/ service at minimum possible

    cost .

    d)

    To improve operational efficiency.

    1.3 Techniques of work study and their relationship

    The term work study embraces several techniques, but in particular method study

    and work measurement. What are these two techniques and what is their relationship to one

    another?

    Method study is the systematic recording and critical examination of ways

    of doing things in order to make improvements.

    Work measurement is the application of techniques designed to establish

    the time for a qualified worker to carry out a task at a defined rate of

    working.

    Jessyntha

  • 8/12/2019 Construction Management - Work Study

    8/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    8

    Method study and work measurement are therefore, closely linked. Method study is

    concerned with the reduction of the work content of a job or operation, while work

    measurement is mostly concerned with the investigation and of any ineffective time

    associated it; and with the subsequent establishment of time standards for the operation when

    carried out in the improved fashion, as determined by method study.The relationship of

    method to work measurement when time standards for output are being set, it is often

    necessary to use one of the technique or work measurement, such as work sampling. In order

    to determine why ineffective time is occurring and what is its extent, so that management can

    take action to reduce it before method study is begun. Again time study used to compare the

    effectiveness of alternative methods of work before deciding on the best method to install.

    Work Study

    Work Study

    Method study

    To simply the job and

    develop more economical

    methods of doing it.

    Work Measurement

    To determine how long

    it should take to carry

    out.

    Higher Productivity

    Jessyntha

  • 8/12/2019 Construction Management - Work Study

    9/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    9

    These techniques will be dealt with in detail in the chapters devoted to them. For the

    present we must consider the basic procedure of work study which applies to every study,

    whatever the operation of process being examined whether in industry, in a service enterprise

    or in the office. This procedure is fundamental to the whole of work study. There is no shortcut.

    1.4 Basic Procedures of Work Study

    There are eight steps in performing a complete work study. They are:

    a) Select the job or process to be studied.b) Record or collect all relevant data about the job or process, using the most suitable

    data collection techniques, so that the data will be in the most convenient form to be

    analyzed.

    c) Examine the recorded factscritically and challenge everything that is done,considering in turn: the purpose of the activity; the place where it is performed; the

    sequence in which it is done; the person who is doing it; the means by which it isdone.

    d) Develop the most economic method, taking into account all the circumstances anddrawing as appropriate on various production management techniques, as well as on

    the contributions of managers, supervisors, workers and other specialists with whom

    new approaches should be explored.

    e) Evaluate the results attained by the improved method compared with the quantity ofwork involved and calculate a standard time for it.

    f) Define the new method and the related time and present it to all those concerned,either verbally or in writing, using demonstrations.

    g) Install the new method, training those involved, as an agreed practice with the allottedtime of operation.

    h) Maintain the new standard practiceby monitoring the results and comparing themwith the original targets.

    Jessyntha

  • 8/12/2019 Construction Management - Work Study

    10/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    10

    Steps i, ii and iii occur in every study, whether the technique being used is method

    study or work measurement. Step iv is part of method study practice, while step iv calls for

    the use of work measurement. It is possible that after a certain time the new method may

    prove to be in need of modification, in which case it would be re-examined again using theabove sequence.

    1.5 Work Study and Production Management

    When work study emerged in the early part of this century as a technique aimed at

    rationalizing and measuring work, the emphasis was on economy of motion and movement.

    Because of that it was called time and motion study. Later on, it began to encompass other

    aspects of observing and analyzing work, and the earlier term was abandoned in favor of

    work study. Simultaneously, in the late 1940s and later on in the 1960s other disciples

    were developed, namely industrial engineering and production management respectively.

    These disciplines differed from work study in the sense that they were devoted to increasing

    the efficiency of a production operation as a whole, not just the methods of work.

    Thus modernproduction management looks at various aspects of production such as

    product design, quality control, layout and materials handling, production planning and

    control, maintenance management and invariably work study.These techniques may be

    applied, singly or in combination, in the enterprise. Furthermore, with time many of them

    began to rely increasingly on sophisticated quantitative methods such as operations research

    to solve ever more complicated operational problems. Advances I the fields of computers and

    information systemshelped to boost production management techniques to the level attained

    at present.

    Jessyntha

  • 8/12/2019 Construction Management - Work Study

    11/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    11

    The Approach of Work Study

    SELECT

    the job to be studied

    RECORD

    by collecting data or

    by direct observation

    EXAMINE

    by challenging purpose, place,

    sequence and method of work

    EVALUATE

    results of different alternative

    solutions

    DEFINE

    new method and present it

    Install

    new method and train person in

    applying it

    Maintain

    and establish control procedures

    DEVELOP

    new method, drawing on

    contributions of thoseconcerned

    Jessyntha

  • 8/12/2019 Construction Management - Work Study

    12/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    12

    While work study has continued to be a relatively simple and cheap method of

    rationalizing methods of work, it has also continued to develop. Thus, many work study

    trained specialists realize that several of the existing production management techniques can

    also be used advantageously by them to help develop improved methods of work. In a sensethey provide an array of techniques that cannot and need not be ignored.

    2.0 METHOD STUDY

    Method study is the systematic recording, analysis and critical examination of the

    methods and movement involve in the performance of existing or proposed ways of

    doing work, as a mean of developing easier and more productive methods.

    Method study is essentially concerned with finding better ways of doing things, and it

    contributes to improved efficiency by getting rid of necessary work, available delays, and

    others forms of waste. This is achieving through:

    a) Improved the layout and design of factory, plant and work placeb) Improved working proceduresc) Improved use of material, plant and equipment and manpowerd) Improved working environmente) Improved design or specification of the end product

    The technique of method study aim at doing 3 things:

    a) To reveal and analyse the true facts concerning the situationsb) To examine those facts criticallyc) To develop from the examination of the facts the best answer possible under the

    circumstances.

    Nurkhairani

  • 8/12/2019 Construction Management - Work Study

    13/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    13

    2.1 Procedure of Method Study

    Method-study is a well established approach for systematic recording and critical

    examination of existing and proposed ways of doing work, as a means of developing and

    applying easier and more effective methods and reducing cost. Still, the greatest thing about

    this approach is its flexibility with which it may be used in different situations. Following

    sequence of phases are involved in it:

    Phase 6:

    FOLLOW UP (the implementation)

    Phase 5:

    IMPLEMENT (the solution)

    Phase 4:

    CONSIDER (the alternative course of actions, and

    solutions and deliberate on which way to follow)

    Phase 3:

    EXAMINE (the facts critically but impartially)

    Phase 2:

    RECORD (all facts relevant to the problem)

    Phase 1:

    DEFINE (the problem)

    Nurkhairani

  • 8/12/2019 Construction Management - Work Study

    14/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    14

    2.2 Factors Considered In the Method Study

    Three important factors, which govern the selection process, are:

    a) Economic considerationsb) Technical considerationsc) Human reactions

    2.2.1 Economic Considerations

    Economic considerations in method-study include:

    a) Cost of studyb) Time loss due to investigationc) Costs associated with the implementation of changes in the present methods.

    The considerations for above three costs are important, as the method-study is

    primarily based on the principle of economic use of resources (such as human effort, machine

    utilization, material handling, efforts, etc.).Some process, though poorly planned, may not fit

    into the economic viability of motion-study. An example could be processes for a product,

    which is unlikely to have repeat order. On the contrary, a process in an assembly line, which

    is likely to be repeated for next few years, would score better on economic viability, despite

    offering marginal improvements.

    Nurkhairani

  • 8/12/2019 Construction Management - Work Study

    15/128

  • 8/12/2019 Construction Management - Work Study

    16/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    16

    2.2.2 Technical Considerations

    It is important to understand that requisite technical know-how must be available to suggest

    improvements. In this, we must consider two areas.

    Technical Considerations

    Area Purpose Example

    Skill, competence and

    training of work-study

    practitioners

    To handle the present assignment The assembly line is running

    poorly due to bad line

    balancing. The work-study

    experts must have the

    expertise in individual work-

    element and line balancing at

    the bottleneck station.

    Technical limitation of

    process

    Avoid landing at unworkable

    alternates.

    No need to invent a new

    process/machine.

    Establishing the non-availability

    of appropriate technical expertise

    The machine tool is not

    cutting at optimal condition

    of speed. There is a need to

    devise new tools, but tool

    material is not available in

    market. Hence, expert advice

    is needed, otherwise abandon

    this item from study.

    Nurkhairani

  • 8/12/2019 Construction Management - Work Study

    17/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    17

    2.2.3 Human Reactions

    A lot of emphasis is needed in the selection step on understanding the human reactions

    to the task undertaken. Work-study can only be implemented with active cooperation with

    workers and supervisors. For this, some understanding of human reactions to work-study is

    needed. One need is to handle mental and emotional blocks in the mind of worker.Proper

    scheme to handle resistance-to-change is needed. For this, we need to do the following:

    a) Consultation, meeting with workers and unionb) Defining objectives scope and needsc) Proper written and oral communication with workersd) Dispelling fears related to cut in wages, firing of workers, more efforts in work, higher

    target, etc.

    2.3 Recording Techniques

    There are 3 main group of recording technique available for setting down the problem. There

    are:

    a) The Flow Diagram.b) The String Diagram.c) Models and Templates.

    Nurkhairani

  • 8/12/2019 Construction Management - Work Study

    18/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    18

    Charts Outline process charts

    Flow process charts (man-type, equiment material and

    material type)

    Multiple activity chartsTwo- handed process charts

    Diagrams and models (2 & 3

    dimensional)

    String diagrams

    Flow diagrams

    Models (Three-dimensional)

    Cut- out templates (Two- dimensional models)

    Photographic Photographs

    Films

    2.3.1 Flow Process Charts

    This technique can be useful in helping to solve problems of layout such as those in

    site workshop areas where the operationas are likely to be repetitive.

    All activities are shown by means of symbols, with a description against each. This is

    very simple method of showing a sequence of work, and employs the following symbols:

    Samidah

  • 8/12/2019 Construction Management - Work Study

    19/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    19

    Operation

    The result of this is to further the process, such as changing the

    shape, assembling, repairing part of a plant. The symbol also

    covers the operation of a chemical reaction, or, in office work,filling up a form.

    Inspection

    The result of this is to verify quantity and or quality, such as

    counting, measuring, weighing, testing and grading.

    Transport

    The result of this is to move, either the operator having to go to the

    stores for material, or the material being transported through the

    factory by any means.

    Storage

    This will include tools or materials awaiting issue and use,

    documents filed in a cabinet, and finished products in a warehouse.

    Delay

    This symbol is used when work is delayed, such as when an

    operator is waiting for work to be delivered to him, or when an

    operation is held up because of a shortage of components. With the

    use of these standard symbols, process charts may be made out.

    These are of two kinds: The Operation Process Chart and the Flow

    Process Chart.

    Samidah

  • 8/12/2019 Construction Management - Work Study

    20/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    20

    The movements of men, materials or equipment are followed through a process, and

    the symbols are used to indicate what is happening at the various stages. The distance

    travelled maybe shown on the transport activities, and the time for each element can be given.

    The operation Process Chartis a graphic representation of the points at which

    materials are introduced into the process, and the sequence of inspections and all operations

    expect those involved in material handling. Provision is made in the chart for recording units

    of time and quantity, but the chart does not indicate where the activities take place or who

    performs them. This chart therefore employs two symbols only, Operation and Inspection.

    Samidah

  • 8/12/2019 Construction Management - Work Study

    21/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    21

    These process charts show the sequence of movements and not the path of movement.

    The latter can be shown by three other recording techniques.

    2.3.2 Flow Diagrams

    This is usually linked to a Flow Process Chart, and is a scale drawing of the area,

    showing the location of the various activities represented by their numbered symbols. The

    route followed is shown by joining the symbols together by a line corresponding to the actual

    path of movement followed. The direction of movement is indicated by using numbered

    transportation symbols and including them in the flow-line.

    2.3.3 String Diagrams

    This is a refinement of the above. It consists of scale drawing of the area, fixed to a

    board. Pins are inserted to represent the various machines or processes involved, and a thread

    is wound round the pins in the sequence in which the operations are carried out. Different

    processes can be distinguished by the use of different coloured pins and the corresponding

    coloured thread. The distance travelled can be measured by the length of the thread. The main

    uses of this technique are:

    a) To test the relative value of different layouts.b) To investigate the movement of a team of operators.c) To investigate the movement of one operator minding a number of machines.

    This technique is very useful in solving problems of movement. It is applied to repetitive

    situations, and is therefore most useful is working areas such as factories producing

    industrialised components, machine shops, precasting yards, and steel-bending areas on site.

    The diagram will show points of congestion and any excessive distance travelled.

    Samidah

  • 8/12/2019 Construction Management - Work Study

    22/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    22

    The procedure for improving a layout is first to draw to scale a plan of the area under

    consideration with the work places or stackign areas etc, and all changes in direction denoted

    by pins. String or thread is then tied round the starting point and passed from pin to pin

    showing movement. Men, mateials or machine can be denoted by different coloured string. Ifthe string is then measured, any excessive distances travelled will be obvious and pay points

    of congestion will be seen on the diagram.

    Routes that are travelled regularly should be kept as short as possible and alternative

    methods can be examined to obviate the faults of the first.

    2.3.4 Models and Templates

    These are particularly useful when dealing with major method changes or alterations

    in plant layout. The movement can be shown on the model, and the latter is more easily

    understood than is a diagram.

    2.4 Critical Examination

    The next step is to examine them. This calls for a critical analysis, which must be

    carried out thoroughly and logically. Much will depend on the investigator, as it is on

    efficiency of his analysis that the whole success will depend. He must:

    a) Examine the facts as they are and not as they appear to beb) Avoid the influence of preconceived ideas.c) Challenge every detail of the chart, accepting no answer until he is thoroughly

    satisfied that is correct.

    d)

    Avoid jumping to conclusionse) Give close attention to detail

    Samidah

  • 8/12/2019 Construction Management - Work Study

    23/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    23

    f) Reserve bright ideas until the appropriate timeg) Not consider improving the method until he has thoroughly studied the existing

    method.

    The step Examine is the key step in method studies, and consists of a detailed

    examination of every aspect of the work. The purpose is to:

    a) Establish the true facts surrounding the problem;b) Establish the reasons for these facts and determine whether they are valid;c) On this foundation, to consider all the possible alternatives and hence the optimum

    solutions.

    2.4.1 Site Layout Problems

    When deciding in the relative positions of plant, working areas and storage areas on

    sites, reference has to be made to various activities to be performed; that is, the number andtypes of activity and the minimum transports and storages required. This basic information

    can be provided from materials flow process charts, which may be used in conjunction with a

    scale drawing of the site layout and paper templates. String diagrams can then be used either

    to evaluate or represent visually the movement intensity for the alternative arrangement of the

    templates.

    2.4.2 Multiple Activity Chart

    This technique is used to help solve problems when a number of subjects (operatives,

    machines or equipment) are dependent on each other. It shows the occupied time (divided into

    elements of work if necessary) and unoccupied time for the subjects in both the present and

    the proposed methods. The subjects are recorded on a common time scale and periods of

    unoccupied time can be readily seen. Alternatives may then be considered, the aim being to

    Samidah

  • 8/12/2019 Construction Management - Work Study

    24/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    24

    balance the work content for the subjects. It is necessary to plot more than one cycle of work,

    as the first taken may not be representative.

    3.0 WORK MEASUREMENT

    3.1 General Remarks on Work Measurement

    There remains the aspect of how long jobs should take, which is the field of work

    measurement. To be more precise, and following the British Standards Institution

    recommendations, it seeks to establish the time for a qualified worker to carry out a specified

    job at a defined level of performance. This is related to average performance over the

    working day or shift, to be achieved without over-exertion, by qualified workers who are

    motivated to apply themselves to their work, using the correct methods.

    Why should we need to know how long a job should take? The answer to this question

    lies in the importance of time in our everyday life. We need to know how long it should take

    to walk to the train station in the morning, one needs to schedule the day's work and even

    when to take out the dinner from the oven.

    In the business world these standard times are needed for:

    a) planning the work of a workforce,b) manning jobs, to decide how many workers it would need to complete certain jobs,c) scheduling the tasks allocated to peopled) costing the work for estimating contract prices and costing the labour content in

    general

    e) calculating the efficiency or productivity of workers - and from this:f) providing fair returns on possible incentive bonus payment schemes.

    Mothilal

  • 8/12/2019 Construction Management - Work Study

    25/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    25

    The standard times are set, not on how long a certain individual would take to complete a

    task but on how long a trained, experienced worker would take to do the task at a defined

    level of pace or performance. Specially trained and qualified observers set these standard

    times, using the most appropriate methods or techniques for the purpose.

    3.2 Definition

    Work measurement is the application of techniques designed to establish the time for a

    qualified workerto carry out specified jobs at a defined level of performance. It covers

    several different ways of finding out how long a job or part of a job should take to complete.

    It can be defined as the systematic determination, through the use of various techniques, of the

    amount of effective physical and mental work in terms of work units in a specified task.

    The work units usually are given in standard minutes or standard hours. Work

    measurement (WM) is concerned with investigating, reducing and eliminating ineffective

    time, whatever may be the cause.In practice, proving existence of the ineffective time is the

    most difficult task. After existence is proved, nature and extent is easy to see.

    WM is also used to set standard times to carry out the work, so that any ineffective

    time is not included later. Any addition the standard time would show up as excess time and

    thus can be brought to attention. Since, standard times are set for all the activities through

    WM; it has earned bad reputation amongst workers. Major reason for that has been the initial

    focus of the WM methods, which essentially targeted only the worker controllable ineffective

    times. Management controllable ineffective times were ignored traditionally.

    It is usually considered logical for work measurement to follow the establishment of

    correct methods for a job, otherwise the time standards would need revision; but it is possible

    to study the times for similar elements of similar jobs, done, perhaps in different factories, toobtain guidance as to where improvements may be made. After selection of the job to be

    Mothilal

  • 8/12/2019 Construction Management - Work Study

    26/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    26

    studied and the definition of the method by which it is to be done, the work is broken into

    elements, which, in the case of repetitive work, are parts of the work cycle selected to be

    convenient to observe, measure and analyze. These are not the same as their bilges used in

    used method study. A common technique is the timing of elements by means of a stopwatchover several cycles of the work. The times for like elements in the various cycles will be

    totaled and averaged.

    The difficulties of establishing standards in connection with suchpersonal mattersas

    the rate at which a man works and the effort he gives are obvious. To a limited extent people

    may be pulled along by a production system geared for a certain rate of working, and it has

    not been unknown for moving belts to be run at speeds corresponding to the psychological

    changes that take place throughout the day, related to factors such as meal breaks, and seem to

    cause workers to respond to different rates of working. In work measurement the observer is

    trained to gauge the standard rate of working and he records how the workers rate compares

    with this by estimating a number from the rating scale when performing the study.

    As an alternative to observing a job, records of predetermined standard data may be

    used to produce synthetics studies, especially useful for new jobs and for non-repetitive work.

    Analytical estimating brings in the use of synthetics, so far as these are available,

    supplemented by estimates based on knowledge or experience of the time likely to be taken.

    Various predetermined motion time systems (PMTS) have been evolved, in which the time

    is built up from times established for basic human motions done under specified conditions.

    Method time measurement (MTM) and the work factor system, which both had their

    origins in the early 1930s, are probably the best known examples.

    Mothilal

  • 8/12/2019 Construction Management - Work Study

    27/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    27

    3.3 The purpose of work measurement

    The purpose of this work measurement is:

    a) To reveal the nature and extent of ineffective time, from whatever causeb) So that action can be taken to eliminate it; and then,c) To set standards of performance that are attainable only if all avoidable ineffective

    time is eliminated and work is performed by the best method available.

    In another word, the aim of work measurement is to determine the time it takes for a

    qualified worker to carry out a specific job at a defined level of performance and to eliminate

    ineffective elements of works it seeks to provide the standard times for jobs and thus supplies

    basic, essential data for management.

    3.4 The uses of work measurement

    The use of the work measurement is to compare the efficiency of alternative methods.

    Other conditions being equal, the method which takes the least time will be the best method.

    It can also balance the work of members of teams, in association with the multiple activity

    charts, so that, as far as possible, each member has tasks taking an equal time. WM is also

    important to determine, in association with man and machine multiple activity charts, the

    number of machines a worker can run.

    In summation, WM will be found to have the following uses:

    a) to assist in method study by comparison of time for alternative methods, and forallocating labor to jobs in proportion to the work involved so that the labor on

    the job is properly balanced

    b) to enable realistic schedules of work to prepare by relating reasonably accurateassessments of human work to plant capacity.

    c) as the basis of realistic and fair incentive schemes

    Mothilal

  • 8/12/2019 Construction Management - Work Study

    28/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    28

    d) to assist in the organization of labor by enabling a daily comparison to be madebetween actual times and target times.

    e) as a basis for labor budgeting and budgetary control systemsf)

    to enable estimate to prepared of future labor requirement

    3.5 The basic procedure

    The method chosen for each individual situation to be measured depends on several

    factors which include:

    a) the length on the job to be measured in time unitsb) the precision which is appropriate for the type of work in terms of time units (i.e.

    should it be in minutes, hundredths or thousandths of a minute)

    c) the general cycle-time of the work, i.e. does it take seconds, minutes or days tocomplete

    The length of time necessary for the completion of the range of jobs can vary from a

    few seconds in highly repetitive factory work to several weeks or months for large projects

    such as major shutdown maintenance work on an oil refinery. It is quite clear that using a

    stop-watch, for example, on the latter work would take several man-years to time to measure.

    Thus, more "overall" large-scale methods of timing must be employed.

    The precision is an important factor, too. This can vary from setting times of the order

    of "to the nearest thousandth of a minute" (e.g. short cycle factory work) to the other end of

    the scale of "to the nearest week" (e.g. for large project work).

    Mothilal

  • 8/12/2019 Construction Management - Work Study

    29/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    29

    3.6 The technique of work measurement

    For the purpose of the work measurement, work maybe regarded as repetitive or on

    repetitive. By repetitive i.e. meant that type of work in which the main operation or group of

    operations recurs continuously during the time spent at the job. This applies equally to work

    cycles of extremely short duration as, for instance, light press work jobs and to those of

    several minutes or even hours duration.

    Non-repetitive work includes some types of maintenance and construction work,

    where the work cycle itself is hardly ever repeated identically. Even in such work, which are

    same small movements and groups of movements occurring repeatedly, and are often

    common to quite different jobs, such as painting and bricklaying. It is this fact which has

    made it possible to apply certain work measurement techniques to this type of work.

    Following is the lists of techniques used to measure WM:

    a) Time studyb) Activity sampling; and rated activity samplingc) Synthesis from standard datad) Pre-determined motion time systeme) Estimatingf) Analytical estimatingg) Comparative estimating.

    Mothilal

  • 8/12/2019 Construction Management - Work Study

    30/128

  • 8/12/2019 Construction Management - Work Study

    31/128

  • 8/12/2019 Construction Management - Work Study

    32/128

  • 8/12/2019 Construction Management - Work Study

    33/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    33

    4.6 Sample Size

    a) Fly back timingAs the worker commences the first element the watch is clicked back to zero, the time

    which has elapsed between taking the time check and the start of the first element being

    entered in the column headed ineffectiveor check time on the observation record sheet.

    This entry is marked checktime in the column scale watch, time should expressed in one or

    two figure only, the watch is zeroed similarly at the conclusion of each element.

    b) Cumulative timingBy this method the position of the stop watch and is recorded at the commencement of

    the study and at the end of each element without ever returning it to zero. The individual

    element times are afterwards arrived at by substation of successive readings.

    Toward the end of the first element its number and rating are entered in the appropriate

    columns, and at the arrival of the breakpoint the time indicated is put down. Any unusual

    happening during or between the elements, such as fumble by the worker, must be mentioned

    in the elements should be recorded in the ineffective time column of the study sheet and a

    note made of the cause of the delay.

    c) Ineffective timePeriod during which the man is not working, or is doing work not forming a necessary

    part of the particular job being studied. Whatever the causes of the ineffective time are as

    follow-

    a) Management responsible. Waiting for work, instructions, material or equipment .b) Worker responsible. Stopping work to talk unnecessarily with neighbour, etc.c)

    Contingencies. Construction with supervision, fellow workers, other department.Obtaining special equipment, instructions, drawings.etc.

    Fadilah

  • 8/12/2019 Construction Management - Work Study

    34/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    34

    The remaining elements are then treated in the same way. Between cycles the work study

    officer should change his opinion his position so as to be sure that he is getting a full view of

    the work.

    It should be an inflexible rule that to erasures are permitted on time study sheets. If an

    error in a time or rating figure is noticed at the time is made, it should be struck out

    immediately and the right value inserted alongside. If it is not noticed until some time later it

    can be regarded as suspect and not valid for inclusion in the subsequent calculations. No

    attempt should ever be made to alter an observed time or rating figure after completion of the

    study

    4.7 Factors Affecting the Rate of Working

    4.7.1 Effectiveness

    Factor which will influence the effectiveness of a mans work must be clearly recognized

    according to whether or n not they are within the worker control:

    a) Outsides the worker control

    Variation in quality of specification of the materials used, although these materialsare within prescribed tolerance limits.

    Changes in the operating efficiency of tools and equipment within their useful life. Minor changes in methods or conditions of operation. Changes in lighting, temperature, climate and other temporary condition of

    environment.

    Variation in the mental attention necessary for the performance of certain elementsof the work.

    Fadilah

  • 8/12/2019 Construction Management - Work Study

    35/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    35

    b) Dependent on the worker

    Variations in the quality of work within specification.

    The degree to which the worker is suited and accustomed to his work, determinednot only by his physical and mental faculties but also his past training, acquired

    skill and knowledge.

    The attitude of mind of the worker which still affect his desire to get the workdone quickly. This includes interest and pride in the job. The opinion held of

    supervisor and many others psychological factors, some of which may have

    nothing to do with the job.

    4.7.2 Speed

    Factor which will affect the speed are-

    a) The types of effort demanded by the jobGenerally the demand for increases physical effort will lead to a slower speed.

    For example, the speed turning a particular hand wheel will largely depend on the

    resistance to be overcome. The facility with which physical effort can be increased to

    overcome harsher resistance must influence rating, which is considering speed of

    working in terms of expenditure of energy. For example, there is difference in carrying

    a heavy load comfortably balanced on the shoulder and carrying the same load by

    hand.

    b) The care required on the part of the workerA need for increased care in carrying out an element of work will also reduce

    speed. For example, threading a piece of string through a curtain ring can easily be

    done using rapid movements, but if the string is to be threaded through the eye of a

    bagging needle it is necessary to control the movements carefully, and in consequence

    they are made rapidly, even though no less effort may be involved

    Fadilah

  • 8/12/2019 Construction Management - Work Study

    36/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    36

    4.8 Terminology Explained

    a) Timing- The observer records the actual time taken to do the element or operation.This usually is in centiminutes (0.01 min.) and is recorded, using a stop-watch or

    computerized study board.

    b) Rating- When someone is doing work his/her way of working will vary throughoutthe working period and will be different from others doing the same work. This is due

    to differing speeds of movement, effort, dexterity and consistency. Thus, the time

    taken for one person to do the work may not be the same as that for others and may or

    may not be 'reasonable' anyway. The purpose of rating is to adjust the actual timeto a

    standardized basic timethat is appropriate and at a defined level of performance.

    Rating is on a scale with 100 as itsstandard rating

    c) Elements- A complete job usually will be too long and variable to time and rate in onego, so it would be analysed into several smaller parts (elements) which, separately,

    will each be timed and rated.

    d) Basic time- This is the standardised time for carrying out an element of work atstandard rating.

    Example:An observer times an element as 30 centiminutes (cm) and because it

    is performed more slowly than the standard 100, he rates it as 95. Thus the basic time

    is 95% of 30 or 28.5 basic cm. The formula is: (actual time x rating)/100.

    e) Allowances- Extra time is allowed for various conditions which obtain, the main onesbeing relaxation allowancefor:

    Fadilah

  • 8/12/2019 Construction Management - Work Study

    37/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    37

    recovery from the effort of carrying out specified work under specified conditions(fatigue allowance)

    attention to personal needs adverse environmental conditions,

    plus:

    others concerned with machine operations

    f) Frequency- The basic time is the time for a complete cycle to be performed but as notall elements are repeated in every cycle their timesper average cyclemust bepro

    rata. In the example which follows, element 2 only occurs once every eight cycles so

    its basic time is one eighth of the element time, per cycle. Similar treatment for

    element 7 (one twelfth).

    5.0 CASE STUDY

    Work Activity Standard Minutes1 Ceiling Skim Coating 58.56

    2 Cement Rendering at Staircase 16.24

    3 Electrical Trunking 3.02

    4 Plastering on Beam 3.61

    5 Tiling Works 4.23

    Fadilah

  • 8/12/2019 Construction Management - Work Study

    38/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    38

    CONSTRUCTION MANAGEMENT

    WORK STUDY

    WORK 1: Ceiling Skim Coating

    BY: Jessyntha Williams

  • 8/12/2019 Construction Management - Work Study

    39/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    39

    WORK 1: CEILING SKIM COATING

    Table 1 - Operation: Ceiling Skim Coating

    1Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 6.02 4.02

    B. Mix skim coat 60 10.34 4.32

    C. Clean and level ceiling 80 12.36 2.02

    D. Apply first layer skim coating 100 37.36 25.00

    E. Apply final layer skim coating 85 53.36 16.00

    53.36

    2Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 6.00 4.00

    B. Mix skim coat 60 10.50 4.50

    C. Clean and level ceiling 80 12.50 2.00

    D. Apply first layer skim coating 100 32.50 20.00

    E. Apply final layer skim coating 85 47.50 15.00

    47.50

  • 8/12/2019 Construction Management - Work Study

    40/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    40

    3Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 6.02 4.02

    B. Mix skim coat 60 10.32 4.30

    C. Clean and level ceiling 80 11.89 1.57

    D. Apply first layer skim coating 100 41.89 30.00

    E. Apply final layer skim coating 85 56.89 15.00

    56.89

    4Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 5.55 3.55

    B. Mix skim coat 60 9.75 4.20

    C. Clean and level ceiling 80 11.75 2.00

    D. Apply first layer skim coating 100 36.75 25.00

    E. Apply final layer skim coating 85 52.75 16.00

    52.75

  • 8/12/2019 Construction Management - Work Study

    41/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    41

    5Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 6.00 4.00

    B. Mix skim coat 60 10.30 4.30

    C. Clean and level ceiling 80 12.30 2.00

    D. Apply first layer skim coating 100 36.30 24.00

    E. Apply final layer skim coating 85 51.38 15.08

    51.38

    6Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 6.02 4.02

    B. Mix skim coat 60 10.34 4.32

    C. Clean and level ceiling 80 12.36 2.02

    D. Apply first layer skim coating 100 37.36 25.00

    E. Apply final layer skim coating 85 52.36 15.00

    52.36

  • 8/12/2019 Construction Management - Work Study

    42/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    42

    7Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 5.54 3.54

    B. Mix skim coat 60 10.07 4.53

    C. Clean and level ceiling 80 14.07 4.00

    D. Apply first layer skim coating 100 34.07 20.00

    E. Apply final layer skim coating 85 52.07 18.00

    52.07

    8Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 6.02 4.02

    B. Mix skim coat 60 10.17 4.15

    C. Clean and level ceiling 80 13.17 3.00

    D. Apply first layer skim coating 100 33.17 20.00

    E. Apply final layer skim coating 85 52.17 19.00

    52.17

  • 8/12/2019 Construction Management - Work Study

    43/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    43

    9Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 7.00 5.00

    B. Mix skim coat 60 10.00 3.00

    C. Clean and level ceiling 80 11.49 1.49

    D. Apply first layer skim coating 100 36.59 25.10

    E. Apply final layer skim coating 85 52.59 16.00

    52.59

    10Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 7.00 5.00

    B. Mix skim coat 60 13.00 6.00

    C. Clean and level ceiling 80 15.00 2.00

    D. Apply first layer skim coating 100 38.00 23.00

    E. Apply final layer skim coating 85 52.50 14.50

    52.50

  • 8/12/2019 Construction Management - Work Study

    44/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    44

    11Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 5.30 3.30

    B. Mix skim coat 60 9.30 4.00

    C. Clean and level ceiling 80 10.75 1.45

    D. Apply first layer skim coating 100 33.75 23.00

    E. Apply final layer skim coating 85 48.75 15.00

    48.75

    12Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 5.40 3.40

    B. Mix skim coat 60 9.70 4.30

    C. Clean and level ceiling 80 11.70 2.00

    D. Apply first layer skim coating 100 38.70 27.00

    E. Apply final layer skim coating 85 58.70 20.00

    58.70

  • 8/12/2019 Construction Management - Work Study

    45/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    45

    13Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 5.00 3.00

    B. Mix skim coat 60 11.00 6.00

    C. Clean and level ceiling 80 12.45 1.45

    D. Apply first layer skim coating 100 32.45 20.00

    E. Apply final layer skim coating 85 48.45 16.00

    48.45

    14Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 6.02 4.02

    B. Mix skim coat 60 10.34 4.32

    C. Clean and level ceiling 80 12.44 2.10

    D. Apply first layer skim coating 100 40.44 28.00

    E. Apply final layer skim coating 85 55.44 15.00

    55.44

  • 8/12/2019 Construction Management - Work Study

    46/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    46

    15Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 2.00 2.00

    A .Fix Scaffolding 75 6.02 4.02

    B. Mix skim coat 60 10.34 4.32

    C. Clean and level ceiling 80 12.36 2.02

    D. Apply first layer skim coating 100 37.36 25.00

    E. Apply final layer skim coating 85 53.36 16.00

    53.36

    Total Observed Time (min)

    Summary for A) Fix Scaffolding 58.91

    Summary for B) Mix skim coat 66.56

    Summary for C) Clean and level ceiling 31.12Summary for D) Apply first layer skim coating 360.10

    Summary for E) Apply final layer skim coating 204.58

    721.27

    Total Cumulative Time (min)

    Summary for A) Fix Scaffolding 88.91

    Summary for B) Mix skim coat 155.47

    Summary for C) Clean and level ceiling 186.59

    Summary for D) Apply first layer skim coating 546.69

    Summary for E) Apply final layer skim coating 788.27

    1,765.93

  • 8/12/2019 Construction Management - Work Study

    47/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    47

    Table 2 - Extend observed times to basic times

    1

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)Check time 2.00 2.00

    A. Fix Scaffolding 75 6.02 4.02 4.02 x 72 = 2.89

    100

    B. Mix skim coat 60 10.34 4.32 4.32 x 60 = 2.59

    100

    C. Clean and level ceiling 80 12.36 2.02 2.02 x 80 = 1.62

    100

    D. Apply first layer skim coating 100 37.36 25.00 25.00 x 100 = 25.00

    100

    E. Apply final layer skim coating 85 53.36 16.00 16.00 x 85 = 13.60

    100

    53.36

    2

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)Check time 2.00 2.00

    A. Fix Scaffolding 75 6.00 4.00 4.00 x 75 = 3.00

    100

    B. Mix skim coat 60 10.50 4.50 4.50 x 60 = 2.70

    100

    C. Clean and level ceiling 80 12.50 2.00 2.00 x 80 = 1.60

    100

    D. Apply first layer skim coating 100 32.50 20.00 20.00 x 100 = 20.00

    100

    E. Apply final layer skim coating 85 47.50 15.00 15.00 x 85 = 12.75

    100

    47.50

  • 8/12/2019 Construction Management - Work Study

    48/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    48

    3

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    Check time 2.00 2.00

    A. Fix Scaffolding 75 6.02 4.02 4.02 x 75 = 3.02

    100

    B. Mix skim coat 60 10.32 4.30 4.30 x 60 = 2.58

    100

    C. Clean and level ceiling 80 11.89 1.57 1.57 x 80 = 1.26

    100

    D. Apply first layer skim coating 100 41.89 30.00 30.00 x 100 = 30.00

    100

    E. Apply final layer skim coating 85 56.89 15.00 15.00 x 85 = 12.75

    100

    56.89

    4

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    Check time 2.00 2.00

    A. Fix Scaffolding 75 5.55 3.55 3.55 x 75 = 2.66

    100

    B. Mix skim coat 60 9.75 4.20 4.20x 60 =2.52

    100

    C. Clean and level ceiling 80 11.75 2.00 2.00 x 80 = 1.60

    100

    D. Apply first layer skim coating 100 36.75 25.00 25.00 x 100 = 25.00

    100

    E. Apply final layer skim coating 85 52.75 16.00 16.00 x 85 = 13.60

    100

    52.75

  • 8/12/2019 Construction Management - Work Study

    49/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    49

    5

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    Check time 2.00 2.00

    A. Fix Scaffolding 75 6.00 4.00 4.00 x 75 = 3.00

    100

    B. Mix skim coat 60 10.30 4.30 4.30 x 60 = 2.58

    100

    C. Clean and level ceiling 80 12.30 2.00 2.00 x 80 = 1.60

    100

    D. Apply first layer skim coating 100 36.30 24.00 24.00 x 100 = 24.00

    100

    E. Apply final layer skim coating 85 51.38 15.08 15.08 x 85 = 12.82

    100

    51.38

    6

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    Check time 2.00 2.00

    A. Fix Scaffolding 75 6.02 4.02 4.02 x 75 = 3.02

    100

    B. Mix skim coat 60 10.34 4.32 4.32 x 60 = 2.59

    100

    C. Clean and level ceiling 80 12.36 2.02 2.02 x 80 = 1.62

    100

    D. Apply first layer skim coating 100 37.36 25.00 25 x 100 = 25.00

    100

    E. Apply final layer skim coating 85 52.36 15.00 15 x 85 = 12.75

    100

    52.36

  • 8/12/2019 Construction Management - Work Study

    50/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    50

    7

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    Check time 2.00 2.00

    A. Fix Scaffolding 75 5.54 3.54 3.54 x 75 = 2.66

    100

    B. Mix skim coat 60 10.07 4.53 4.53 x 60 = 2.72

    100

    C. Clean and level ceiling 80 14.07 4.00 4.00 x 80 = 3.20

    100

    D. Apply first layer skim coating 100 34.07 20.00 20.00 x 100 = 20.00

    100

    E. Apply final layer skim coating 85 52.07 18.00 18.00 x 85 = 15.30

    100

    52.07

    8

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    Check time 2.00 2.00

    A. Fix Scaffolding 75 6.02 4.02 4.02 x 75 = 3.02

    100

    B. Mix skim coat 60 10.17 4.15 4.15 x 60 = 2.49

    100

    C. Clean and level ceiling 80 13.17 3.00 3.00 x 80 = 2.40

    100

    D. Apply first layer skim coating 100 33.17 20.00 20.00 x 100 = 20.00

    100

    E. Apply final layer skim coating 85 52.17 19.00 19.00 x 85 = 16.15

    100

    52.17

  • 8/12/2019 Construction Management - Work Study

    51/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    51

    9

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    Check time 2.00 2.00

    A. Fix Scaffolding 75 7.00 5.00 5.00 x 75 = 3.75

    100

    B. Mix skim coat 60 10.00 3.00 3.00 x 60 = 1.80

    100

    C. Clean and level ceiling 80 11.49 1.49 1.49 x 80 = 1.19

    100

    D. Apply first layer skim coating 100 36.59 25.10 25.10 x 100 = 25.10

    100

    E. Apply final layer skim coating 85 52.59 16.00 16.00 x 85 = 13.60

    100

    52.59

    10

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    Check time 2.00 2.00

    A. Fix Scaffolding 75 7.00 5.00 5.00 x 75 = 3.75

    100

    B. Mix skim coat 60 13.00 6.00 6.00 x 60 = 3.60

    100

    C. Clean and level ceiling 80 15.00 2.00 2.00 x 80 = 1.60

    100

    D. Apply first layer skim coating 100 38.00 23.00 23.00 x 100 = 23.00

    100

    E. Apply final layer skim coating 85 52.50 14.50 14.50 x 85 = 12.33

    100

    52.50

  • 8/12/2019 Construction Management - Work Study

    52/128

  • 8/12/2019 Construction Management - Work Study

    53/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    53

    13

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    Check time 2.00 2.00

    A. Fix Scaffolding 75 5.00 3.00 3.00 x 75 = 2.25

    100

    B. Mix skim coat 60 11.00 6.00 6.00 x 60 = 3.60

    100

    C. Clean and level ceiling 80 12.45 1.45 1.45 x 80 = 1.16

    100

    D. Apply first layer skim coating 100 32.45 20.00 20.00 x 100 = 20.00

    100

    E. Apply final layer skim coating 85 48.45 16.00 16.00 x 85 = 13.60

    100

    48.45

    14

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    Check time 2.00 2.00

    A. Fix Scaffolding 75 6.02 4.02 4.02 x 75 = 3.02

    100

    B. Mix skim coat 60 10.34 4.32 4.32 x 60 = 2.59

    100

    C. Clean and level ceiling 80 12.44 2.10 2.10 x 80 = 1.68

    100

    D. Apply first layer skim coating 100 40.44 28.00 28 x 100 = 28.00

    100

    E. Apply final layer skim coating 85 55.44 15.00 15.00 x 85 = 12.75

    100

    55.44

  • 8/12/2019 Construction Management - Work Study

    54/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    54

    15

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    Check time 2.00 2.00

    A. Fix Scaffolding 75 6.02 4.02 4.02 x 75 = 3.02

    100

    B. Mix skim coat 60 10.34 4.32 4.32 x 60 = 2.59

    100

    C. Clean and level ceiling 80 12.36 2.02 2.02 x 80 = 1.62

    100

    D. Apply first layer skim coating 100 37.36 25.00 25.00 x 100 = 25.00

    100

    E. Apply final layer skim coating 85 53.36 16.00 16.00 x 85 = 13.60

    100

    53.36

    Table 3 - Calculate average of basic times

    Element Basic time (min)

    Total

    basicFrequency

    Average

    (min)times(min)

    A. Fix Scaffolding 2.89, 3.00, 3.02, 2.66, 3.00, 3.02, 2.66, 3.02, 3.75, 3.75,

    2.48, 2.55, 2.25, 3.02, 3.0244.09 15 2.94

    B. Mix skim coat 2.59, 2.70, 2.58, 2.52, 2.58, 2.59, 2.72, 2.49, 1.80, 3.60,

    2.40, 2.58, 3.60, 2.59, 2.5939.93 15 2.66

    C. Clean and level

    ceiling

    1.62, 1.60, 1.26, 1.60, 1.60, 1.62, 3.20, 2.40, 1.19, 1.60,

    1.16, 1.60, 1.16, 1.68, 1.62 24.91 15 1.66

    D. Apply first layer

    skim coating

    25.00, 20.00, 30.00, 25.00, 24.00, 25.00, 20.00, 20.00,

    25.10, 23.00, 23.00, 27.00, 20.00, 28.00, 25.00 360.10 15 24.01

    E. Apply final layer

    skim coating

    13.60, 12.75, 12.75, 13.60, 12.82, 12.75, 15.30, 16.15,

    13.60, 12.33, 12.75, 17.00, 13.60, 12.75, 13.60 205.35 15 13.69

  • 8/12/2019 Construction Management - Work Study

    55/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    55

    Table 4 - Total relaxation allowance and contingency allowance

    Element

    Basic

    time

    (min)

    Total

    relaxation

    allowance %

    Contingency Total

    allowances

    (%)

    Standard time (min)allowance

    %

    A. Fix Scaffolding 2.94 27 5 32 2.94 x 132 = 3.88

    100

    B. Mix skim coat 2.66 25 5 30 2.66 x 130 = 3.46

    100

    C. Clean and level ceiling 1.66 35 5 40 1.66 x 140 = 2.32

    100

    D. Apply first layer skimcoating 24.01 20 5 25 24.01 x 125 =30.01

    100

    E. Apply final layer skim

    coating 13.69 33 5 38 13.69 X 138

    =

    18.89

    100

    The total relaxation allowance and contingency allowance are assumed as in Table 4.

    The standard time for the operation is 3.88 + 3.46 + 2.32 + 30.01 + 18.89 = 58.56 minutes

    8%

    7%

    5%

    41%

    39%

    Elements of Work

    Fix Scaffolding Mix skim coat Clean and level ceiling

    Apply first layer skim coating Apply final layer skim coating

  • 8/12/2019 Construction Management - Work Study

    56/128

  • 8/12/2019 Construction Management - Work Study

    57/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    57

    WORK 2: CEMENT RENDERING AT STAIRCASE

    Table 1 - Operation: Cement Rendering at Staircase

    1

    Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 1.00 1.00

    a. Cleaning the staircase 85 1.28 0.28

    b. Prepare gam 75 2.18 0.90

    c. Mix mortar 65 2.70 0.52

    d. 1st Layer of rendering 80 6.95 4.25

    e. Final Layer 100 13.42 6.47

    f. Touch up 60 13.84 0.42

    13.84

    2Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 1.00 1.00

    a. Cleaning the staircase 85 1.33 0.33

    b. Prepare gam 75 2.25 0.92

    c. Mix mortar 65 2.74 0.49

    d. 1st Layer of rendering 80 7.36 4.62

    e. Final Layer 100 13.77 6.41

    f. Touch up 60 13.98 0.21

    13.98

  • 8/12/2019 Construction Management - Work Study

    58/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    58

    3Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 1.00 1.00

    a. Cleaning the staircase 85 1.31 0.31

    b. Prepare gam 75 2.20 0.89

    c. Mix mortar 65 2.73 0.53

    d. 1st Layer of rendering 80 7.34 4.61

    e. Final Layer 100 13.76 6.42

    f. Touch up 60 13.95 0.19

    13.95

    4Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 1.00 1.00

    a. Cleaning the staircase 85 1.34 0.34

    b. Prepare gam 75 2.29 0.95

    c. Mix mortar 65 2.86 0.57

    d. 1st Layer of rendering 80 7.36 4.50

    e. Final Layer 100 13.85 6.49

    f. Touch up 60 14.08 0.23

    14.08

  • 8/12/2019 Construction Management - Work Study

    59/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    59

    5Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 1.00 1.00

    a. Cleaning the staircase 85 1.28 0.28

    b. Prepare gam 75 2.16 0.88

    c. Mix mortar 65 2.66 0.50

    d. 1st Layer of rendering 80 7.15 4.49

    e. Final Layer 100 13.42 6.27

    f. Touch up 60 13.84 0.42

    13.84

    6Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 1.00 1.00

    a. Cleaning the staircase 85 1.40 0.40

    b. Prepare gam 75 2.27 0.87

    c. Mix mortar 65 2.89 0.62

    d. 1st Layer of rendering 80 7.71 4.82

    e. Final Layer 100 14.33 6.62

    f. Touch up 60 14.58 0.25

    14.58

  • 8/12/2019 Construction Management - Work Study

    60/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    60

    7Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 1.00 1.00

    a. Cleaning the staircase 85 1.25 0.25

    b. Prepare gam 75 2.22 0.97

    c. Mix mortar 65 2.73 0.51

    d. 1st Layer of rendering 80 7.22 4.49

    e. Final Layer 100 13.61 6.39

    f. Touch up 60 13.85 0.24

    13.85

    8Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 1.00 1.00

    a. Cleaning the staircase 85 1.28 0.28

    b. Prepare gam 75 2.19 0.91

    c. Mix mortar 65 2.72 0.53

    d. 1st Layer of rendering 80 7.26 4.54

    e. Final Layer 100 13.70 6.44

    f. Touch up 60 13.90 0.20

    13.90

  • 8/12/2019 Construction Management - Work Study

    61/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    61

    9Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 1.00 1.00

    a. Cleaning the staircase 85 1.32 0.32

    b. Prepare gam 75 2.27 0.95

    c. Mix mortar 65 2.85 0.58

    d. 1st Layer of rendering 80 7.29 4.44

    e. Final Layer 100 13.60 6.31

    f. Touch up 60 13.81 0.21

    13.81

    10Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 1.00 1.00

    a. Cleaning the staircase 85 1.45 0.45

    b. Prepare gam 75 2.40 0.95

    c. Mix mortar 65 3.03 0.63

    d. 1st Layer of rendering 80 7.70 4.67

    e. Final Layer 100 14.29 6.59

    f. Touch up 60 14.59 0.30

    14.59

  • 8/12/2019 Construction Management - Work Study

    62/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    62

    11Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 1.00 1.00

    a. Cleaning the staircase 85 1.46 0.46

    b. Prepare gam 75 2.43 0.97

    c. Mix mortar 65 3.03 0.60

    d. 1st Layer of rendering 80 7.56 4.53

    e. Final Layer 100 14.14 6.58

    f. Touch up 60 14.34 0.20

    14.34

    12Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 1.00 1.00

    a. Cleaning the staircase 85 1.25 0.25

    b. Prepare gam 75 2.10 0.85

    c. Mix mortar 65 2.59 0.49

    d. 1st Layer of rendering 80 7.37 4.78

    e. Final Layer 100 13.86 6.49

    f. Touch up 60 14.26 0.40

    14.26

  • 8/12/2019 Construction Management - Work Study

    63/128

  • 8/12/2019 Construction Management - Work Study

    64/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    64

    15Element Rating

    Cumulative Observed

    time (min) time (min)

    Check time 1.00 1.00

    a. Cleaning the staircase 85 1.28 0.28

    b. Prepare gam 75 2.18 0.90

    c. Mix mortar 65 2.70 0.52

    d. 1st Layer of rendering 80 7.22 4.52

    e. Final Layer 100 13.69 6.47

    f. Touch up 60 13.89 0.20

    13.89

    Total Observed Time (min)

    Summary for A) Cleaning the staircase 4.84

    Summary for B) Prepare gam 13.61

    Summary for C) Mix mortar 8.28

    Summary for D) 1st Layer of rendering 68.28

    Summary for E) Final layer 96.95

    Summary for F) Touch up 3.92

    195.88

    Total Cumulative Time (min)

    Summary for A) Cleaning the staircase 19.84

    Summary for B) Prepare gam 33.45

    Summary for C) Mix mortar 41.73

    Summary for D) 1st Layer of rendering 110.01

    Summary for E) Final layer 206.96

    Summary for F) Touch up 210.88

    622.87

  • 8/12/2019 Construction Management - Work Study

    65/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    65

    Table 2 - Extend observed times to basic times

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    1 Check time 1.00 1.00

    a. Cleaning the staircase 85 1.28 0.28 0.28 x 85 0.24

    100

    b. Prepare gam 75 2.18 0.90 0.90 x 75 0.68

    100

    c. Mix mortar 65 2.70 0.52 0.52 x 65 0.34

    100

    d. 1st Layer of rendering 80 6.95 4.25 4.25 x 80 3.40

    100

    e. Final Layer 100 13.42 6.47 6.47 x 100 6.47

    100

    f. Touch up 60 13.84 0.42 0.42 x 60 0.25

    100

    13.84

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    2 Check time 1.00 1.00

    a. Cleaning the staircase 85 1.33 0.33 0.33 x 85 0.28

    100

    b. Prepare gam 75 2.25 0.92 0.92 x 75 0.69

    100

    c. Mix mortar 65 2.74 0.49 0.49 x 65 0.32

    100

    d. 1st Layer of rendering 80 7.36 4.62 4.62 x 80 3.70100

    e. Final Layer 100 13.77 6.41 6.41 x 100 6.41

    100

    f. Touch up 60 13.98 0.21 0.21 x 60 0.13

    100

    13.98

  • 8/12/2019 Construction Management - Work Study

    66/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    66

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    3 Check time 1.00 1.00

    a. Cleaning the staircase 85 1.31 0.31 0.31 x 85 0.26

    100

    b. Prepare gam 75 2.20 0.89 0.89 x 75 0.67

    100

    c. Mix mortar 65 2.73 0.53 0.53 x 65 0.34

    100

    d. 1st Layer of rendering 80 7.34 4.61 4.61 x 80 3.69

    100

    e. Final Layer 100 13.76 6.42 6.42 x 100 6.42

    100f. Touch up 60 13.95 0.19 0.19 x 60 0.11

    100

    13.95

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    4 Check time 1.00 1.00

    a. Cleaning the staircase 85 1.34 0.34 0.34 x 85 0.29

    100

    b. Prepare gam 75 2.29 0.95 0.95 x 75 0.71

    100

    c. Mix mortar 65 2.86 0.57 0.57 x 65 0.37

    100

    d. 1st Layer of rendering 80 7.36 4.50 4.50 x 80 3.60

    100

    e. Final Layer 100 13.85 6.49 6.49 x 100 6.49100

    f. Touch up 60 14.08 0.23 0.23 x 60 0.14

    100

    14.08

  • 8/12/2019 Construction Management - Work Study

    67/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    67

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    5 Check time 1.00 1.00

    a. Cleaning the staircase 85 1.28 0.28 0.28 x 85 0.24

    100

    b. Prepare gam 75 2.16 0.88 0.88 x 75 0.66

    100

    c. Mix mortar 65 2.66 0.50 0.50 x 65 0.33

    100

    d. 1st Layer of rendering 80 7.15 4.49 4.49 x 80 3.52

    100

    e. Final Layer 100 13.42 6.27 6.27 x 100 6.27

    100f. Touch up 60 13.84 0.42 0.42 x 60 0.25

    100

    13.84

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    6 Check time 1.00 1.00

    a. Cleaning the staircase 85 1.40 0.40 0.40x 85 0.34

    100

    b. Prepare gam 75 2.27 0.87 0.87 x 75 0.65

    100

    c. Mix mortar 65 2.89 0.62 0.62 x 65 0.40

    100

    d. 1st Layer of rendering 80 7.71 4.82 4.82 x 80 3.86

    100

    e. Final Layer 100 14.33 6.62 6.62 x 100 6.62100

    f. Touch up 60 14.58 0.25 0.42 x 60 0.15

    100

    14.58

  • 8/12/2019 Construction Management - Work Study

    68/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    68

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    7 Check time 1.00 1.00

    a. Cleaning the staircase 85 1.25 0.25 0.25x 85 0.21

    100

    b. Prepare gam 75 2.22 0.97 0.97 x 75 0.73

    100

    c. Mix mortar 65 2.73 0.51 0.51x 65 0.33

    100

    d. 1st Layer of rendering 80 7.22 4.49 4.49 x 80 3.59

    100

    e. Final Layer 100 13.61 6.39 6.39 x 100 6.39

    100f. Touch up 60 13.85 0.24 0.24 x 60 0.14

    100

    13.85

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    8 Check time 1.00 1.00

    a. Cleaning the staircase 85 1.28 0.28 0.28x 85 0.24

    100

    b. Prepare gam 75 2.19 0.91 0.91 x 75 0.68

    100

    c. Mix mortar 65 2.72 0.53 0.53x 65 0.34

    100

    d. 1st Layer of rendering 80 7.26 4.54 4.54 x 80 3.63

    100

    e. Final Layer 100 13.70 6.44 6.44 x 100 6.44100

    f. Touch up 60 13.90 0.20 0.20 x 60 0.12

    100

    13.90

  • 8/12/2019 Construction Management - Work Study

    69/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    69

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    9 Check time 1.00 1.00

    a. Cleaning the staircase 85 1.32 0.32 0.32x 85 0.27

    100

    b. Prepare gam 75 2.27 0.95 0.95 x 75 0.71

    100

    c. Mix mortar 65 2.85 0.58 0.58x 65 0.38

    100

    d. 1st Layer of rendering 80 7.29 4.44 4.44 x 80 3.55

    100

    e. Final Layer 100 13.60 6.31 6.31 x 100 6.31

    100f. Touch up 60 13.81 0.21 0.21 x 60 0.13

    100

    13.81

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    10 Check time 1.00 1.00

    a. Cleaning the staircase 85 1.45 0.45 0.45x 85 0.38

    100

    b. Prepare gam 75 2.40 0.95 0.95 x 75 0.71

    100

    c. Mix mortar 65 3.03 0.63 0.63x 65 0.41

    100

    d. 1st Layer of rendering 80 7.70 4.67 4.67 x 80 3.74

    100

    e. Final Layer 100 14.29 6.59 6.59 x 100 6.59100

    f. Touch up 60 14.59 0.30 0.30 x 60 0.18

    100

    14.59

  • 8/12/2019 Construction Management - Work Study

    70/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    70

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    11 Check time 1.00 1.00

    a. Cleaning the staircase 85 1.46 0.46 0.46x 85 0.39

    100

    b. Prepare gam 75 2.43 0.97 0.97 x 75 0.73

    100

    c. Mix mortar 65 3.03 0.60 0.60x 65 0.39

    100

    d. 1st Layer of rendering 80 7.56 4.53 4.53 x 80 3.62

    100

    e. Final Layer 100 14.14 6.58 6.58 x 100 6.58

    100f. Touch up 60 14.34 0.20 0.20 x 60 0.12

    100

    14.34

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    12 Check time 1.00 1.00

    a. Cleaning the staircase 85 1.25 0.25 0.25x 85 0.21

    100

    b. Prepare gam 75 2.10 0.85 0.85 x 75 0.64

    100

    c. Mix mortar 65 2.59 0.49 0.49x 65 0.32

    100

    d. 1st Layer of rendering 80 7.37 4.78 4.78 x 80 3.82

    100

    e. Final Layer 100 13.86 6.49 6.49 x 100 6.49100

    f. Touch up 60 14.26 0.40 0.40 x 60 0.24

    100

    14.26

  • 8/12/2019 Construction Management - Work Study

    71/128

  • 8/12/2019 Construction Management - Work Study

    72/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    72

    Element RatingCumulative

    time (min)

    Observed

    Basic time (min)time

    (min)

    15 Check time 1.00 1.00

    a. Cleaning the staircase 85 1.28 0.28 0.28 x 85 0.24

    100

    b. Prepare gam 75 2.18 0.90 0.90 x 75 0.68

    100

    c. Mix mortar 65 2.70 0.52 0.52 x 65 0.34

    100

    d. 1st Layer of rendering 80 7.22 4.52 4.52 x 80 3.62

    100

    e. Final Layer 100 13.69 6.47 6.47 x 100 6.47

    100f. Touch up 60 13.89 0.20 0.20 x 60 0.12

    100

    13.89

    Table 3 - Calculate average of basic times

    Element Basic time (min)

    Total

    basic

    Frequency

    Average

    (min)times(min)

    a. Cleaning the staircase 0.28, 0.28, 0.26, 0.29, 0.24, 0.34, 0.21, 0.24, 4.11 15 0.27

    0.27, 0.38, 0.39, 0.21, 0.25, 0.27, 0.24

    b. Prepare gam 0.68, 0.69, 0.67, 0.71, 0.66, 0.65, 0.73, 0.68, 10.21 15 0.68

    0.71, 0.71, 0.73, 0.64, 0.68, 0.60, 0.68

    c. Mix mortar 0.34,0.32, 0.34, 0.37, 0.33, 0.40, 0.33, 0.34, 5.38 15 0.36

    0.38, 0.41, 0.39, 0.32, 0.36, 0.42, 0.34

    d. 1st Layer of rendering 3.40, 3.70, 3.69, 3.60, 3.52, 3.86, 3.59, 3.63, 54.55 15 3.64

    3.55, 3.74, 3.62, 3.82, 3.62, 3.59, 3.62

    e. Final Layer 6.47, 6.41, 6.42, 6.49, 6.27, 6.62, 6.39, 6.44 96.95 15 6.46

    6.31, 6.59, 6.58, 6.49, 6.90, 6.10, 6.47

    f. Touch up 0.25, 0.13, 0.11, 0.14, 0.25, 0.15, 0.14, 0.12, 2.35 15 0.16

    0.13, 0.18, 0.12, 0,24, 0.15, 0.12, 0.12

  • 8/12/2019 Construction Management - Work Study

    73/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    73

    Table 4 - Total relaxation allowance and contingency allowance

    ElementBasic time

    Total

    relaxation Contingency

    allowance %

    Total

    allowances (%)

    Standard time

    (min)

    (min)

    allowance

    %

    a. Cleaning the

    staircase 0.27 25 5 30 0.27 x 130 0.35

    100

    b. Prepare gam 0.68 30 5 35 0.68 x 135 0.92

    100

    c. Mix mortar 0.36 26 5 31 0.36 x 131 0.47

    100

    d. 1st Layer of

    rendering 3.64 30 5 35 3.64 x 135 4.91100

    e. Final Layer 6.46 38 5 43 6.46 x 143 9.24

    100

    f. Touch up 0.16 29 5 34 0.26 x 134 0.35

    100

    Assume that the total relaxation allowance and contingency allowance are as shown in Table 4.

    The standard time for the operation is 0.35 + 0.92 + 0.47 + 4.91 + 9.24 + 0.35 = 16.24 standard

    minutes.

    2%6%

    3%

    30%

    57%

    2%

    Elements of Works

    Cleaning the staircase

    Prepare gam

    Mix mortar

    1st Layer of rendering

    Final Layer

    Touch up

  • 8/12/2019 Construction Management - Work Study

    74/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    74

    CONSTRUCTION MANAGEMENT

    WORK STUDY

    WORK 3: Electrical Trunking

    BY: Nurkhairani Mohd Rusdi

  • 8/12/2019 Construction Management - Work Study

    75/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    75

    WORK 3: ELECTRICAL TRUNKING

    Table 1 - Operation: Electrical Trunking

    1

    Element Rating Cumulativetime (min)

    Observed

    time

    (min)

    Check time 2.00 2.00

    A. Measure the trunking 80 2.17 0.17

    B. Cut the trunking 90 2.71 0.54

    C. Fix and drill to wall 100 3.88 1.17

    D. Screw 70 4.10 0.22

    4.10

    2

    Element Rating Cumulativetime (min)

    Observed

    time

    (min)

    Check time 2.00 2.00

    A. Measure the trunking 80 2.23 0.23

    B. Cut the trunking 90 2.71 0.48

    C. Fix and drill to wall 100 3.75 1.04

    D. Screw 70 4.00 0.25

    4.00

  • 8/12/2019 Construction Management - Work Study

    76/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    76

    3

    Element RatingCumulative

    time (min)

    Observed

    time

    (min)

    Check time 2.00 2.00

    A. Measure the trunking 80 2.35 0.35

    B. Cut the trunking 90 2.90 0.55

    C. Fix and drill to wall 100 4.47 1.57

    D. Screw 70 4.77 0.30

    4.77

    4

    Element RatingCumulative

    time (min)

    Observed

    time

    (min)

    Check time 2.00 2.00

    A. Measure the trunking 80 2.46 0.46

    B. Cut the trunking 90 2.79 0.33

    C. Fix and drill to wall 100 4.08 1.29

    D. Screw 70 4.30 0.22

    4.30

  • 8/12/2019 Construction Management - Work Study

    77/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    77

    5

    Element RatingCumulative

    time (min)

    Observed

    time

    (min)

    Check time 2.00 2.00

    A. Measure the trunking 80 2.38 0.38

    B. Cut the trunking 90 2.85 0.47

    C. Fix and drill to wall 100 4.30 1.45

    D. Screw 70 4.65 0.35

    4.65

    6

    Element RatingCumulative

    time (min)

    Observed

    time

    (min)

    Check time 2.00 2.00

    A. Measure the trunking 80 2.25 0.25

    B. Cut the trunking 90 2.60 0.35

    C. Fix and drill to wall 100 3.98 1.38

    D. Screw 70 4.38 0.40

    4.38

  • 8/12/2019 Construction Management - Work Study

    78/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    78

    7

    Element RatingCumulative

    time (min)

    Observed

    time

    (min)

    Check time 2.00 2.00

    A. Measure the trunking 80 2.30 0.30

    B. Cut the trunking 90 2.72 0.42

    C. Fix and drill to wall 100 3.80 1.08

    D. Screw 70 4.50 0.70

    4.50

    8

    Element RatingCumulative

    time (min)

    Observed

    time

    (min)

    Check time 2.00 2.00

    A. Measure the trunking 80 2.29 0.29

    B. Cut the trunking 90 2.67 0.38

    C. Fix and drill to wall 100 3.92 1.25

    D. Screw 70 4.18 0.26

    4.18

  • 8/12/2019 Construction Management - Work Study

    79/128

  • 8/12/2019 Construction Management - Work Study

    80/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    80

    11

    Element RatingCumulative

    time (min)

    Observed

    time

    (min)

    Check time 2.00 2.00

    A. Measure the trunking 80 2.39 0.39

    B. Cut the trunking 90 2.72 0.33

    C. Fix and drill to wall 100 4.08 1.36

    D. Screw 70 4.52 0.44

    4.52

    12

    Element RatingCumulative

    time (min)

    Observed

    time

    (min)

    Check time 2.00 2.00

    A. Measure the trunking 80 2.33 0.33

    B. Cut the trunking 90 2.82 0.49

    C. Fix and drill to wall 100 4.01 1.19

    D. Screw 70 4.53 0.52

    4.53

  • 8/12/2019 Construction Management - Work Study

    81/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    81

    13

    Element RatingCumulative

    time (min)

    Observed

    time

    (min)

    Check time 2.00 2.00

    A. Measure the trunking 80 2.26 0.26

    B. Cut the trunking 90 2.81 0.55

    C. Fix and drill to wall 100 4.24 1.43

    D. Screw 70 4.69 0.45

    4.69

    14

    Element RatingCumulative

    time (min)

    Observed

    time

    (min)

    Check time 2.00 2.00

    A. Measure the trunking 80 2.31 0.31

    B. Cut the trunking 90 2.82 0.51

    C. Fix and drill to wall 100 4.09 1.27

    D. Screw 70 4.51 0.42

    4.51

  • 8/12/2019 Construction Management - Work Study

    82/128

    SBQ 4612 Construction ManagementWork Study GROUP 5

    82

    15

    Element