This project is scheduled to be completed Summer 2020.
Community Outreach UpdateSan Diego Symphony
Bayside Performance Park222 Embarcadero Marina Park South, San Diego, CA 92101
Construction Activities & Events - June 2020
Project Overview:
The San Diego Symphony is working with the UnifiedPort of San Diego in the development of the BaysidePerformance Park. This park improvement project will
allow the Symphony to enhance its musicalpresentations by replacing the temporary
performance and event venue with a permanentarchitecturally remarkable and acoustically superiorstage. The project will allow the park to become animportant public resource as a site for a range ofperformances and transform it into a year-round
community gathering space.
Project Highlights:
• 13,000 square feet of covered stage performance space and back-of-house facilities.• Bay viewing deck at the back of the performance stage for public use during non-event hours.• Temporary seating with lawns open to the public during non-event periods.• Event seating capacity up to 10,000.• New public restrooms.• Widened public promenades that will remain open to the public.• Environmentally sustainable landscaping.
Page 2 of 6
Community Outreach UpdateSan Diego Symphony
Bayside Performance Park222 Embarcadero Marina Park South, San Diego, CA 92101
Construction Activities & Events - June 2020
Special Note:
The Port of San Diego hasclosed Embarcadero MarinaPark South to the Public due
to the Coronavirus.
COVID-19 [Novel Coronavirus] Provisions are being Practiced onsite The safety, protection and wellbeing of everyone in our community is of the highest concern to Rudolph and Sletten, Inc. Precautions and protocols are being practiced onsite with instructions distributed to participants, visitors and personnel entering the SDS Bayside Performance project. In addition to the notifications are visible signage posted in and on the project site limits further referencing the guidelines published by the CDC, Government Notifications, County Health and Rudolph and Sletten mandated initiatives. Rudolph and Sletten, Inc. and all our trade partners take the responsibility to comply with our essential service obligation presented by the State’s Executive Order very seriously https://covid19.ca.gov/stay-home-except-for-essential-needs/#top and will continue to do so with the safety and protection of all Citizens as our number one priority.
SAN DIEGO SYMPHONY BPP LOGISTICS:CONSTRUCTION OPERATIONS - PHASE 1
SITE PERIMETER FENCING
PUBLIC AND EMERGENCY VEHICLE ACCESS
PEDESTRIAN ACCESS
PHASE 1CURRENT - JUNE 30, 2020
Directional Signage for VehicularAccess to Joe's Crab Shack
VEHI
CLE
ACCE
SS
PEDE
STRI
AN A
CCES
S
BLDGA
BLDGB
BLDGD
BLDGE
BLDGC
NO PARKING - 3Spaces for VehicleTurning Radius
Joe'sCrab Shack
CONSTRUCTIONSITE
Directional Signage for PedestrianAccess to Joe's Crab Shack
R&STrailer
Controlled Vehicle Access:Gate Attendant During Construction HoursSecurity Guard For Off Hours
2 ADA Parking Spotsw/ Access Ramp
Public Parking Spaces, Park,Basketball Courts, and FishingPier are closed to the PublicUNTIL FURTHER NOTICE
No Parking
Key Activities in June:
• Park and Pier will remain closed by the Port due to the Coronavirus Until Further Notice.• Installing new fitness equipment around the perimeter of the Embarcadero. • Flatwork around Public Restrooms and Burgers, Bait & Beer.• Installing new bollards and lighting around the perimeter of the Embarcadero. • Buildout & Framing of Bandshell, Annex, and Pavilion Buildings.• Installing finishes in Building B • Installing Glazing at Building A.
Page 3 of 6
Community Outreach UpdateSan Diego Symphony
Bayside Performance Park222 Embarcadero Marina Park South, San Diego, CA 92101
Construction Activities & Events - Phasing Plan 2
SAN DIEGO SYMPHONY BPP LOGISTICS:CONSTRUCTION OPERATIONS - PHASE 2
SITE PERIMETER FENCING
PUBLIC AND EMERGENCY VEHICLE ACCESS
PEDESTRIAN ACCESS
5
PHASE 2JUNE 30, 2020 - COMPLETION
VEHI
CLE
ACCE
SS
PEDE
STRI
AN A
CCES
S
BLDG A
5
BLDG A
NGOUND
MAINCONSSITE
5
BLDG A
5
BLDG A
NGUND
OPEN TOPUBLIC
Directional Signage for Vehicular Access to:Joe's Crab ShackBurgers, Bait and BeerPublic ParkingEmbarcadero Promenade Park and Pier
2 ADA Parking Spotsw/ Access Ramp
Joe'sCrab Shack
Directional Signage for Pedestrian Access to:Joe's Crab ShackBurgers, Bait and BeerEmbarcadero Promenade Park and Pier
NO PARKING -Vehicle Turn Around
BLDGA
BLDGB
BLDGD
BLDGE
BLDGC
R&STrailer
Burgers,Bait & Beer
PublicRestrooms
Controlled Vehicle Access:Gate Attendant During Construction HoursSecurity Guard For Off Hours
CONSTRUCTIONSITE
CONSTRUCTIONSITE
Page 4 of 6
Community Outreach UpdateSan Diego Symphony
Bayside Performance Park222 Embarcadero Marina Park South, San Diego, CA 92101
Construction Activities & Events - Progress Photos
Page 5 of 6
Click here to access the project webcam.
Community Outreach UpdateSan Diego Symphony
Bayside Performance Park222 Embarcadero Marina Park South, San Diego, CA 92101
Construction Activities & Events - Progress Photos
Page 6 of 6
Community Outreach UpdateSan Diego Symphony
Bayside Performance Park222 Embarcadero Marina Park South, San Diego, CA 92101
Construction Activities & Events - June 2020
Question or Comments:
General Contractor
Rudolph and Sletten, Inc. (License #198069)7584 Metropolitan Dr., Suite 100San Diego, CA 92108Phone Number: 619.432.0122
Sammy RiveraField Office [email protected]
Doug OgieSr. [email protected]
Daniel StewartProject [email protected]