consolidated 2011-2014 business plan of the multilateral fund documents lib/1/6307.pdf ·...

25
Pre-session documents of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol are without prejudice to any decision that the Executive Committee might take following issuance of the document. UNITED NATIONS EP United Nations Environment Programme Distr. GENERAL UNEP/OzL.Pro/ExCom/63/7 3 March 2011 ORIGINAL: ENGLISH EXECUTIVE COMMITTEE OF THE MULTILATERAL FUND FOR THE IMPLEMENTATION OF THE MONTREAL PROTOCOL Sixty-third Meeting Montreal, 4-8 April 2011 CONSOLIDATED 2011-2014 BUSINESS PLAN OF THE MULTILATERAL FUND

Upload: buihuong

Post on 05-Feb-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Pre-session documents of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol are without prejudice to any decision that the Executive Committee might take following issuance of the document.

UNITED NATIONS EP United Nations

Environment

Programme

Distr. GENERAL UNEP/OzL.Pro/ExCom/63/7 3 March 2011 ORIGINAL: ENGLISH

EXECUTIVE COMMITTEE OF THE MULTILATERAL FUND FOR THE IMPLEMENTATION OF THE MONTREAL PROTOCOL Sixty-third Meeting Montreal, 4-8 April 2011

CONSOLIDATED 2011-2014 BUSINESS PLAN OF THE MULTILATERAL FUND

UNEP/OzL.Pro/ExCom/63/7

2

Introduction

1. Bilateral and implementing agencies provided initial business plan tables by 20 January 2011 to the Fund Secretariat. The Secretariat compiled the information provided and analyzed the business plans in the light of decisions taken in 2010 in particular with respect to decisions related to the 2010-2014 business plans and HCFC guidelines. The Secretariat and the bilateral and implementing agencies began their collaborative efforts on business planning at an Inter-agency coordination meeting held from 26 to 28 January 2011. The Secretariat provided a comprehensive analysis of the initial tables and indicated how the plans would need to be adjusted to comply with the relevant decisions of the Executive Committee. Revised business plan tables and narratives were submitted, as required, on 7 February 2011.

2. The agencies’ plans address the years from 2011 to 2014 pursuant to decision 60/5(o)(ii) but include activities planned after 2014.

3. A spreadsheet that includes data compiled from the business plans is available to Executive Committee members and is provided as Annex I to this document in a Microsoft Excel workbook.

4. The present document consists of the following eight sections:

Section I: Resource allocation in the business plan Section II: Multi-year agreements (MYAs) and standard costs including new methyl

bromide (MB) activities Section III: ODS disposal activities Section IV: HCFC activities Section V: Impact of adjustments based on existing Executive Committee decisions on business plans as submitted Section VI: Performance indicators Section VII: Other policy issues Section VIII: Recommendations

5. Section IV on HCFC activities also addresses tonnage included in the business plan compared to estimated baselines, the climate impact of HCFC activities, production sector, demonstration projects, additional project preparation, servicing, foam, and refrigeration sectors. All sections include comments on proposed adjustments that are summarized in Section V.

SECTION I: RESOURCE ALLOCATION IN THE BUSINESS PLAN 6. The budget for 2011 is the subject of the document on the Availability of cash flow for the 2011 budget (UNEP/OzL.Pro/ExCom/63/5). However, it is assumed that the budget will correspond to the level of replenishment and, therefore, the remaining funds in the 2009-2011 triennium amounting to US $287.7 million are assumed as the budget for 2011. The estimated budget for the 2011-2014 business plan overall is assumed to be US $777.7 million based on another US $490 million replenishment for the period 2012-2014.

7. Table 1 presents, by year, the value of activities included in the business plan according to categories “required for compliance” and “not required for compliance”. The values included in the business plan are lower than the remaining funds for 2011 by US $4.57 million and, based on previous replenishments, exceed the 2011-2014 budget by US $230.94 million.

UNEP/OzL.Pro/ExCom/63/7

3

Table 1

RESOURCE ALLOCATION IN BUSINESS PLANS SUBMITTED TO THE EXECUTIVE COMMITTEE (2011-2014) (US $000s)

Required/Not required by Model 2011 2012 2013 2014 Total

(2011 to 2014)

Required for compliance (MYAs and standard costs) 39,678 37,480 37,573 35,182 149,913 Required for compliance (HCFCs) 231,185 229,566 228,379 148,874 838,004 Not required for compliance (Resource mobilization) 1,451 0 0 0 1,451 Not required for compliance (ODS disposal) 9,590 8,291 0 0 17,881 Not required for compliance (Enforcement networks, Green Customs, MB workshops)

1,218 168 0 0 1,386

Grand total 283,122 275,505 265,952 184,055 1,008,634 Annual budgets and projected budgets* 287,696 163,333 163,333 163,333 777,696 Difference -4,574 112,172 102,619 20,722 230,939

* Assumed budget at same level of current replenishment.

8. HCFC activities required for compliance constitute the largest value in the business plan. The value of resources required for HCFC activities amounts to US $838 million for 2011 to 2014.

9. Although resource mobilization and ODS disposal are not required for compliance, the Executive Committee has deferred the resource mobilization requested at previous meetings for consideration at the 63rd Meeting in the context of bilateral activities and work programmes (see UNEP/OzL.Pro/ExCom/63/17-21). The Executive Committee and the Meeting of the Parties have also taken decisions relevant to the activities included in the business plan for ODS disposal. This document addresses the possible value of a window for ODS disposal activities for low-volume-consuming (LVC) countries.

10. The remaining category is for activities that are not required for compliance (mostly combating illegal trade and workshops). These activities constitute only US $1.22 million in 2011 and US $168,000 in 2012. The Czech Republic’s regional customs project was not removed from the business plan, nor was UNEP’s methyl bromide project in Africa. However, the Green customs and Asia and West Asia enforcement networks have been removed from UNEP’s business plan as per decision 61/8. The Secretariat’s proposed adjustments to the business plan include the removal of these activities that would reduce the business plan levels by US $1.05 million.

11. This document considers each of the other categories with a view to resolving inconsistencies with decisions of the Executive Committee.

SECTION II: MYAs AND STANDARD COSTS INCLUDING NEW MB ACTIVITIES 12. Table 2 presents the amounts included in the business plan for activities required for compliance in MYAs, MB, IS, the CAP. It also covers the costs related to the Secretariat, the Executive Committee, monitoring and evaluation, and the Treasurer.

UNEP/OzL.Pro/ExCom/63/7

4

Table 2

REQUIRED FOR COMPLIANCE FOR MYAs AND STANDARD COSTS (2011 to 2014) INCLUDING NEW MB ACTIVITIES (US $000s)

Required by Model 2011 2012 2013 2014 Total

(2011 to 2014)Approved MYAs 7,336 6,575 4,265 3,696 21,872 New MB activities 251 700 952 IS 9,414 6,929 9,414 6,957 32,714 CAP 10,019 10,320 10,630 10,948 41,917 Core unit 5,824 5,999 6,179 6,364 24,366 Secretariat, ExCom, and M&E Cost minus Canadian counterpart 6,334 6,457 6,585 6,716 26,092 Treasurer 500 500 500 500 2,000 Total (required for compliance for MYAs and standard costs) 39,678 37,480 37,573 35,182 149,913

13. The value associated with MYAs for the period 2011 to 2014 consists of US $8.78 million for HCFC activities, US $6.65 million for MB activities, US $1.07 million for CFC activities, US $1.3 million for a CFC production activity and US $4.07 million of MB production activities. Bilateral and implementing agencies proposed amounts for MYAs that exceed those remaining for them in the records of the Fund Secretariat by US $285,200. The Secretariat’s proposed adjustments would modify the MYA amounts in the agencies’ business plans to reflect the records of the Fund Secretariat.

14. New MB activities required for compliance amount to US $951,600 over the next two years.

15. The funding levels for IS have been agreed until 2015 as per decision 61/43(b). Information has been included in the business plan up to 2014, since the Executive Committee plans to review the level of funding for IS by 2015. The Executive Committee may wish to consider maintaining current levels of funding for IS for business planning purposes until a decision is taken on the actual levels.

16. Although funding levels for IS and the timing of the submission of those requests are known, implementing agencies have included values for IS in their business plans that vary from those allowed under the current funding structure by US $15,781, as well as requests in years for which they were not due. The Secretariat’s proposed adjustments would modify the business plans of the implementing agencies according to when IS renewals are due based on the last approvals of IS requests.

17. CAP, core unit costs, Secretariat/Executive Committee and monitoring and evaluation costs, and the Treasurer’s costs are expected to be maintained at the rates of increases that have been agreed to-date. SECTION III: ODS DISPOSAL ACTIVITIES 18. The Twenty-First Meeting of the Parties requested “the Executive Committee to continue its consideration of further pilot projects in Article 5 Parties pursuant to decision XX/7 and, in that context, to consider the costs of a one-time window within its current destruction activities to address the export and environmentally sound disposal of assembled banks of ozone-depleting substances in low-volume-consuming countries that are not usable in the Party of origin” (decision XXI/2, paragraph 2).

19. At its 59th Meeting, the Executive Committee approved project preparation funds for ODS disposal and requested “UNIDO to submit two additional project preparation requests for ODS disposal pilot projects, one for Africa and one for West Asia, in line with decision 58/19, as part of their business plan for 2010” (decision 59/10). At its 60th Meeting, the Committee requested agencies to “remove new project preparation requests for ODS disposal included in the business plans, except those required by

UNEP/OzL.Pro/ExCom/63/7

5

decision 59/10 and requests for countries that had been considered at the 59th Meeting” (decision 60/5(g)) and to “request the bilateral and implementing agencies at the 61st Meeting to suggest a level of funding for ODS [disposal] activities in LVC countries in light of decision XXI/2 of the Twenty-first Meeting of the Parties” (decision 60/5(i)). Table 3 presents ODS disposal demonstration and technical assistance projects that have been included in the business plans and whether project preparation had been approved to-date.

Table 3

ODS DISPOSAL DEMONSTRATION/TECHNICAL ASSISTANCE PROJECTS IN THE BUSINESS PLANS

Country Status Agency Type Title Approved Project

Preparation

Value ($000) in 2011

ODP in

2011

Value ($000) in 2012

ODP in

2012 Algeria Non-LVC Italy DEM ODS destruction demonstration project Yes 737 50.0 Algeria Non-LVC UNIDO DEM ODS destruction demonstration project Yes 710 50.0 Brazil Non-LVC UNDP DEM Demo on ODS Banks Mgt and

Destruction Yes 1,000 0.0 0 0.0

China Non-LVC Japan DEM Destruction Yes 1,000 China Non-LVC UNIDO DEM ODS destruction demonstration project Yes 1,419 100.0 Colombia Non-LVC UNDP DEM Demo on ODS Banks Mgt and

Destruction Yes 1,000 0.0 0 0.0

Georgia LVC UNDP DEM Demo on ODS Banks Mgt and Destruction

No 300 30.0 0 0.0

Georgia LVC UNDP PRP Preparation of Demo: ODS Bank Management/Destruction

No 30 0.0 0 0.0

Ghana LVC UNDP DEM Demo on ODS Banks Mgt and Destruction

Yes 281 8.8 0 0.0

India Non-LVC UNDP DEM Demo: ODS Bank Management/Destruction

Yes 1,419 100.0 0 0.0

Lebanon Non-LVC UNIDO DEM ODS destruction demonstration project Yes 1,419 100.0 Mexico Non-LVC UNIDO DEM ODS destruction demonstration project Yes 1,064 119.0 Nigeria Non-LVC UNIDO DEM ODS destruction demonstration project Yes 1,419 100.0 Region: AFR LVC Japan DEM Destruction No 600 Region: AFR LVC UNIDO DEM ODS destruction demonstration project No 568 40.0 Region: AFR LVC UNEP PRP Preparation of a regional disposal project

for LVCs in Africa with UNIDO No 75

Region: AFR LVC UNIDO PRP ODS destruction demonstration project - PRP

No 81 0.0

Region: AFR LVC UNEP TAS Regional Disposal Project - LVCs in Africa - with UNIDO

No 132 10.0

Region: ASP LVC Japan DEM Demonstration project on ODS disposal Yes 20 Region: ASP LVC UNIDO DEM ODS destruction demonstration project No 568 40.0 Region: ASP LVC UNEP PRP Preparation of a regional disposal project

for LVCs in Asia and Pacific - with UNIDO

No 50

Region: ASP LVC UNIDO PRP ODS destruction demonstration project - PRP

No 54 0.0

Region: ASP LVC UNEP TAS Regional Disposal Project - LVCs in Asia and Pacific - with UNIDO

No 132 10.0

Region: ECA LVC UNIDO DEM ODS destruction demonstration project No 568 40.0 Region: ECA LVC UNEP PRP Preparation of a regional disposal project

for LVCs in Europe and Central Asia - with UNIDO

No 50

Region: ECA LVC UNIDO PRP ODS destruction demonstration project - PRP

No 54 0.0

Region: ECA LVC UNEP TAS Regional Disposal Project - LVCs in Europe and Central Asia - with UNIDO

No 132 10.0

Region: LAC LVC UNIDO DEM ODS destruction demonstration project No 568 40.0

UNEP/OzL.Pro/ExCom/63/7

6

Country Status Agency Type Title Approved Project

Preparation

Value ($000) in 2011

ODP in

2011

Value ($000) in 2012

ODP in

2012 Region: LAC LVC UNEP PRP Preparation of a regional disposal project

for LVCs in Latin America and Caribbean - with UNIDO

No 50

Region: LAC LVC UNIDO PRP ODS destruction demonstration project - PRP

No 54 0.0

Region: LAC LVC UNEP TAS Regional Disposal Project - LVCs in LAC - with UNIDO

No 132 10.0

Region: WA LVC UNIDO DEM ODS destruction demonstration project No 568 40.0 Region: WA LVC UNEP PRP Preparation of the regional disposal

project for LVCs in West Asia - with UNIDO

No 50

Region: WA LVC UNIDO PRP ODS destruction demonstration project - PRP

No 54 0.0

Region: WA LVC UNEP TAS Regional Disposal Project - LVCs in WA - with UNIDO

No 132

Trinidad and Tobago

LVC UNDP DEM Demo on ODS Banks Mgt and Destruction

No 300 30.0 0 0.0

Trinidad and Tobago

LVC UNDP PRP Preparation of Demo: ODS Bank Management/Destruction

No 30 0.0 0 0.0

Turkey Non-LVC UNIDO DEM Destruction demonstration project Yes 1,064 75.0 Sub-total LVC 1,532 68.8 4,098 240.0 Sub-total Non-LVC 8,058 469.0 4,193 225.0 Total 9,590 537.8 8,291 465.0

20. The business plan includes US $17.88 million for ODS disposal demonstration, technical assistance projects and associated project preparation that would result in the destruction of 1,002 ODP tonnes. Project preparation amounting to US $630,625 would result in activities amounting to US $9.59 million in 2011 and US $8.29 million in 2012. The climate impact of these activities might be equivalent to the global warming potential (GWP) of the ODS being destroyed. However, information was not provided on the types of ODS to be destroyed; therefore the analysis was not performed.

21. If all LVC activities are maintained in the business plan, the Committee would be establishing a window for ODS destruction for LVC countries amounting to US $5.633 million for activities in 2010 and 2011 that would result in the destruction of 308.8 ODP tonnes. The Executive Committee may wish to determine the level of a window for ODS activities for LVC countries in the light of the above.

SECTION IV: HCFC ACTIVITIES HCFC tonnage required for compliance with HCFC controls and baseline/starting point calculations 22. Table 4 presents information in the business plan, including from approved projects according to the extent to which countries’ activities address the reduction from the baseline as estimated by the Fund Secretariat.

UNEP/OzL.Pro/ExCom/63/7

7

Table 4

TONNAGE IN BUSINESS PLAN PLUS TONNAGE FROM APPROVED PROJECTS AS A PERCENTAGE OF ESTIMATED BASELINES

(BY LVC CATEGORY, NUMBER OF COUNTRIES AND ODP TONNES)

Percentage of estimated baseline ~10% >10% <35% 35% >35% <100% 100%

Number of countries LVC 10 36 28 21 7 Non-LVC 3 28 3 8 Total number of countries 13 64 31 29 7

ODP tonnes LVC 18.7 166.4 61.3 80.3 77.8 Non-LVC 65.5 5,430.0 8.2 639.7 Total ODP tonnes 84.2 5,596.4 69.5 720.0 77.8

23. The tonnage in the business plan plus approved projects represents 20 per cent of the estimated baseline for Article 5 countries eligible for support from the Multilateral Fund.

Climate impact benchmarks in the business plan 24. Decision 60/5(o)(iii)b. requires implementing agencies to specify a climate impact for activities in the business plan. During the Inter-agency coordination meeting, a methodology for establishing a climate impact benchmark was developed for planning purposes. The climate impact benchmark for the refrigeration servicing sector is estimated at 1 ODP tonne equalling to 3,290 CO2-equivalent tonnes. This is based on the assumption that 10 per cent of the metric tonne reduction will result in a climate benefit based on the GWP of HCFC-22 due to better servicing practices. The GWP of HCFC-22 is 1,810 CO2-equivalent per tonne based on the Intergovernmental Panel Convention on Climate Change’s “Climate Change 2007: Working Group I: The Physical Science Basis (TS.2.5 Net Global Radiative Forcing, Global Warming Potentials and Patters of Forcing”.

25. For the manufacturing sector if the replacement technology has been provided, the climate impact benchmark equals (A*D) – (A*B*C) where:

A = metric tonne equivalent of the total ODP in the business plan; B = percentage of the replacement technology phase-in tonnage; C = Global warming potential of the replacement technology; D = Global warming potential of the HCFC replaced.

If no replacement technology is known at the time of the preparation of the business plan, the assumption is that there will be no positive climate impact. No phase-in amounts have been provided for the production sector, and therefore no climate impact is assessed for the HCFC production phase-out per se; however the phase-out of HCFC-22 production would result in the elimination of the HFC-23 by-product and a resulting minimum permanent annual climate impact of 24.39 million CO2-equivalent tonnes. 26. The climate impact benchmark is only for planning purposes as it is based solely on the tonnage of HCFCs, the alternatives, and the phase-in amount of the replacement technology. The amount of climate impact is for one year only and does not taken into account the permanent reduction in ODP and GWP. Factors that have a consequence on climate impact measurements such as energy efficiency are not known at the planning stage and therefore are not included in the calculation. The climate impact

UNEP/OzL.Pro/ExCom/63/7

8

calculation in the business plan, however, can be used as a benchmark against which HCFC phase-out management plan (HPMP) proposals can be assessed. Table 5 sets out the results of the climate impact measurements provided in the business plan by sub-sector and shows that the plans could result in the permanent annual reduction of 78.96 million CO2-equivalent tonnes, including 24.39 million CO2-equivalent tonnes for HFC-23 emissions saved from HCFC-22 production phase-out.

Table 5

CLIMATE IMPACT OF HCFC ACTIVITIES IN THE 2011-2014 BUSINESS PLAN (IN MILLIONS OF CARBON DIOXIDE-EQUIVALENT TONNES)

Sub-sector Total business

plan values* (US $000)

CO2-equivalent tonnage

(in millions) for one year of reductions

Aerosol 645 0.00 Approved Multi-Year 14,046 0.48 Foam 184,484 5.69 Foam Commercial 830 0.00 Foam Rigid 26,563 1.41 Foam XPS 110,407 20.07 HPMP 70,680 1.06 Refrigeration 20,692 0.59 Refrigeration AC 207,612 19.60 Refrigeration Commercial 17,886 0.00 Refrigeration Domestic AC 0 0.00 Refrigeration ICR 137,780 4.17 Refrigeration Manufacturing 2,854 0.05 Refrigeration Servicing (LVC countries) 11,182 0.35 Refrigeration Servicing (non-LVC countries) 17,475 0.53 Solvent 27,372 0.57 Sub-total Consumption 850,508 54.57 HCFC Production 133,247 24.39 Total 983,756 78.96

*Also includes values after 2014. 27. The cost-effectiveness for the climate impact for the consumption sector is US $15.60 per CO2-equivalent tonne and US $5.46 per CO2-equivalent tonne for the production sector. For the overall HCFC phase-out programme in the business plan, the cost-effectiveness is US $12.46 per CO2-equivalent tonne.

HCFC production sector 28. HCFC production sector activities amounting to US $133.25 million are included in the business plan for 2011 to 2014. US $56,500 is included in 2011 for project preparation activities in India and US $290,250 is included in 2012 for project preparation activities in Argentina and India.

29. At its 60th Meeting, the Executive Committee established an allocation of US $147 million for the production sector for the period 2010-2014 as per decision 60/5(j). Production sector activities for Argentina, China and India were pro-rated to stay within the allocation of the decision.

30. The World Bank indicated that the level of funding in its business plan could be supplemented by additional funding after 2014. Since the level of production phase-out that can be achieved will not be

UNEP/OzL.Pro/ExCom/63/7

9

known until 2015 or 2016, the Secretariat is proposing to adjust the business plan to include the balance of the allocation established in decision 60/5(j) to the year 2015 amounting to US $13.8 million.

HCFC demonstration projects

31. At its 60th Meeting, the Executive Committee decided to remove from the business plans activities for HCFC demonstration projects to be submitted after 2010 (decision 60/5(m)). A total of US $6.08 million is included in the business plans for activities that will phase out 35.5 ODP tonnes in two countries (table 6).

Table 6

HCFC DEMONSTRATION PROJECTS

Country Agency HCFC Title Value ($000) in 2011

ODP in

2011

Approved Project

Preparation China Japan HCFC-141b Demonstration project for conversion from HCFC-141b based

technology to iso-paraffin and siloxane (KC-6) technology for cleaning in the manufacture of medical devices at Zhejiang Kindly Medical Devices Co. Ltd.

210 7.6 Yes

China Japan HCFC-22/ HCFC-142b

Demonstration project for conversion from HCFC-22 to butane blowing technology in the manufacture of extruded polystyrene foam at Shanghai Xinzhao Plastic Enterprises Co. Ltd.

1,000 7.0 Yes

China Japan HCFC-22 Pilot project on HCFC management and phase-out in the refrigeration servicing sector

204 2.5 No

China UNDP HCFC-22 HCFC Demo (XPS Foam Sector - Feininger) 1,973 12.3 Yes China UNDP HCFC-141b HCFC Demo (Solvents Sector - Zhejiang Kindly Medical) 352 3.1 Yes China UNEP HCFC-22 Pilot project on HCFC management and phase-out in the

refrigeration servicing sector 700 N/P No

China UNIDO HCFC-22/ HCFC-142b

XPS demo project with butane technology 806 3.0 Yes

Nigeria Japan HCFC-22 Demonstration project to validate the trans-critical CO2 refrigeration technology for application to ice-block makers at Austin Laz

830 N/P Yes

Total 6,076 35.5

HPMP/HCFC project preparation 32. The total level of funding for project preparation for HPMPs (US $169,375) and HPMP associated investment projects (US $431,650) is US $601,025. Implementing agencies have proposed amounts in their business plans that exceed by US $33,900 the maximum level allowed for project preparation for HPMPs, HCFC demonstration projects, and HCFC investment projects pursuant to decisions 55/13 and 56/16. The Secretariat’s proposed adjustments would reduce the level of funding as per these decisions.

HCFC servicing sector for LVC countries 33. The total level of funding for projects for the HCFC servicing sector in LVC countries is US $20.31 million representing the phase-out of 157.7 ODP tonnes for the period 2011 to 2014.

34. At its 60th Meeting, the Executive Committee established values for HPMPs for activities to comply with the 2015 and 2020 control measures according to projected baselines. At its 62nd Meeting, the Executive Committee agreed to base a 100 per cent phase-out on a pro rata share of the 2020 funding level to meet the 35 per cent reduction (decision 62/10). The Secretariat’s proposed adjustments would limit the funding levels to the maximum allowable level provided for LVC countries in line with

UNEP/OzL.Pro/ExCom/63/7

10

decision 60/44(f)(xii) for the HCFC servicing sector, according to the reduction from the baseline. This would increase the total level of funding for these projects by US $888,618.

HCFC servicing sector for non-LVC countries 35. The total level of funding for projects for the refrigeration servicing sector in non-LVC countries is US $16 million representing the phase-out of 158.4 ODP tonnes for the period 2011 to 2014. Decision 60/44(f)(xv) establishes a threshold of US $4.50/metric kilogram (metric kg). The Secretariat’s proposed adjustments would limit the funding levels to the maximum allowable level for the refrigeration servicing sector in non-LVC countries as per this decision and reduce the total level of funding for these projects by US $795,540.

HPMPs for non-LVC countries 36. The total level of funding for HPMPs in non-LVC countries is US $51.43 million representing the phase-out of 354 ODP tonnes for the period 2011 to 2014. There is no adjustment to this category since it can contain a mixture of servicing and manufacturing sectors.

Foam general 37. The total level of funding for projects for the foam sector is US $183.03 million representing the phase-out of 2,164 ODP tonnes for the period 2011 to 2014. A combination of the replenishment study prepared in 2008 and decision 60/44(f) establishes a threshold of US $6.92/metric kg for the foam sector. The Secretariat’s proposed adjustments would limit the funding levels to the maximum of the agreed cost-effectiveness threshold and reduce the total level of funding for these projects by US $6.78 million.

Extruded polystyrene (XPS) foam 38. The total level of funding for projects for XPS foam is US $106.63 million representing the phase-out of 568.1 ODP tonnes. Under decision 62/12(c) the Executive Committee decided to consider projects for the phase-out of HCFC-22/HCFC-142b used in the manufacture of XPS foam when it was clearly demonstrated that they would be required by national circumstances and priorities to comply with the 2013 and 2015 control measures, and to consider all other XPS foam projects after 2014. A combination of the replenishment study prepared in 2008 and decision 60/44(f) establishes a threshold of US $6.92/metric kg for the foam sector. The Secretariat’s proposed adjustments would limit the funding levels to the maximum of the agreed cost-effectiveness threshold and reduce the total level of funding for these projects by US $58.11 million.

Rigid foam

39. The total level of funding for projects in the rigid foam sector, including rigid insulation refrigeration sub-sector, is US $25.61 million representing the phase-out 297 ODP tonnes for the period 2011 to 2014. Decision 62/13 establishes a threshold of US $7.83/kg with a maximum of up to 25 per cent above this threshold for low-global warming alternatives. The Secretariat’s proposed adjustments would limit the funding levels to the maximum allowable level for the rigid foam sector as per this decision and reduce the total level of funding for these projects by US $38,544.

Refrigeration general 40. The total level of funding for projects for the refrigeration sector is US $267.9 million representing the phase-out of 1,054.6 ODP tonnes for the period 2011 to 2014. A combination of the replenishment study prepared in 2008 and decision 60/44(f) establishes a threshold of US $10.65/metric kg for the refrigeration sector. The Secretariat’s proposed adjustments would limit the funding levels to

UNEP/OzL.Pro/ExCom/63/7

11

the maximum of the agreed cost-effectiveness threshold and reduce the total level of funding for these projects by US $17 million.

Aerosol 41. The total level of funding for projects for HCFCs in the aerosol sector is US $645,000 representing the phase-out of 9.7 ODP tonnes for the period 2011 to 2014 with a cost-effectiveness of US $5.50/metric kg. The aerosol sector is to be addressed on a case-by-case basis as per decision 60/44(f)(xvi).

Solvent 42. The total level of funding for projects for HCFCs in the solvent sector is US $26.3 million representing the phase-out of 83.4 ODP tonnes for the period 2011 to 2014 with a cost-effectiveness of US $32.60/metric kg. The solvent sector is to be addressed on a case-by-case basis as per decision 60/44(f)(xvi).

Pacific Island Countries (PIC) HPMP regional project

43. The 2011 business plan includes one regional HPMP project for PIC amounting to US $133,000. The overall PIC programme covers a regional component and individual country allocations.

HCFC Technical Assistance Project 44. The 2011 business plan includes one global project for information, communication and education activities in the development and implementation of a knowledge portal for HCFC phase-out and HPMP implementation amounting to US $100,000. The Executive Committee has already funded project preparation for HPMPs and has assigned implementing agencies agency fees to implement them. Moreover, the CAP is responsible for providing information, communication and education activities with respect to HCFCs. The Executive Committee may wish to consider whether to remove the global project for information, communication and education activities in the development and implementation of a knowledge portal for HCFC phase-out and HPMP implementation.

SECTION V: IMPACT OF ADJUSTMENTS BASED ON EXISTING EXECUTIVE COMMITTEE DECISIONS ON BUSINESS PLANS AS SUBMITTED

45. The value of the business plan (US $283.1 million) is below the remaining budget for the current triennium by US $4.6 million. However, the business plan value for 2011-2014 (assuming the same level of funding for the 2012-2014 triennium as for the 2009-2011 triennium) exceeds the budget by a total of about US $230.9 million.

46. After making the adjustments proposed above, the total value of the 2011-2014 business plan is US $925.44 million, which exceeds the expected budget of US $777.7 million for the same period by US $147.74 million as shown in Table 7.

UNEP/OzL.Pro/ExCom/63/7

12

Table 7

RESOURCE ALLOCATION IN BUSINESS PLANS SUBMITTED TO THE EXECUTIVE COMMITTEE, AS ADJUSTED BY EXISTING EXECUTIVE COMMITTEE DECISIONS

(2011-2014) (US $000s)

Required/Not required by model 2011 2012 2013 2014 Total (2011 to

2014)

Total (2015 to

2020)

Total After 2020

Required for compliance (MYAs and standard costs)

40,923 36,027 39,263 33,470 149,682 4,998 509

Required for compliance (HCFCs) 207,476 205,072 205,399 138,148 756,095 135,538 120 Not required for compliance (Resource mobilization)

1,451 0 0 0 1,451 0 0

Not required for compliance (ODS disposal) 9,590 8,291 0 0 17,881 0 0 Not required for compliance (Illegal trade, MB workshops)

241 91 0 0 332 0 0

Grand total 259,681 249,481 244,661 171,617 925,440 140,536 628

Annual budgets and projected budgets* 287,696 163,333 163,333 163,333 777,696

Difference -28,015 86,148 81,328 8,284 147,744 * Assumed budget at same level of current replenishment.

47. As noted in the document on the availability of cash flow for the 2011 budget (UNEP/OzL.Pro/ExCom/63/5), the Executive Committee has approved 79 per cent of the value of the business plan for the period 2003-2009. If this trend continues, the Committee would be likely to approve a level of about US $194.3 million below the total value as submitted for 2011 to 2014 in the business plan, which would more than account for over budgeting by US $147.7 million.

48. Table 8 shows the impact of the adjustments by agency.

Table 8

RESOURCE ALLOCATION IN BUSINESS PLANS SUBMITTED TO THE EXECUTIVE COMMITTEE, AS ADJUSTED BY EXISTING EXECUTIVE COMMITTEE DECISIONS

(2011-2014) BY AGENCY (US $000s)

Agency 2011 2012 2013 2014 Total (2011 to 2014)

Total (2015 to 2020)

Total After 2020

Australia 300 0 0 0 300 0 0 Czech Republic (the) 91 91 0 0 182 0 0 Germany 8,304 10,670 2,281 487 21,742 1,486 0 IBRD 53,741 86,785 102,675 70,087 313,287 13,691 0 Italy 1,098 68 0 79 1,245 141 0 Japan 3,273 2,600 0 0 5,873 0 0 Spain 0 893 0 0 893 0 0 UNDP 81,136 63,136 58,498 42,145 244,915 46,444 37 UNEP 28,844 15,360 24,408 15,167 83,780 9,682 591 UNIDO 76,060 62,921 49,714 36,436 225,131 69,091 0 Grand Total 252,847 242,523 237,577 164,401 897,348 140,536 628

UNEP/OzL.Pro/ExCom/63/7

13

49. If the Executive Committee would wish to reduce the business plan values to correspond to the value of the budget for 2011-2014, the Committee might wish to reduce the cost-effectiveness estimates for HCFC manufacturing activities or prioritize the phase-out, first, of those HCFCs with higher ozone-depleting potential, taking into account national circumstances as per decision XIX/6 paragraph 11(a).

SECTION VI: PERFORMANCE INDICATORS 50. Decision 41/93 established the current set of performance indicators for implementing agencies. Implementing agencies provided targets for these performance indicators in their business plans. All implementing agencies have indicated in their business plans their planned efforts to assist countries to comply with the Montreal Protocol’s control measures. UNEP included in its business plan expected missions to Article 5 countries and its special CAP services to assist countries with compliance needs. It also showed the extent to which its activities support those of other agencies.

51. Annex II presents information on historic performance indicators as requested in decision 42/5. The remainder of Annex II addresses investment and non-investment project indicators (2001-2005) and performance indicators that are unique to UNEP.

52. During and after the Inter-agency coordination meeting, the Fund Secretariat provided the implementing agencies with modified versions of their initial business plans based on existing Executive Committee decisions. During the Inter-agency coordination meeting, the rationale for implementing the decisions of the Executive Committee was discussed. However, implementing agencies have not modified their business plans as per those decisions. In the past, the Secretariat has modified performance indicators after receiving the submissions to correspond to new Executive Committee decisions. The Secretariat would recommend continuing this practice at this meeting; however, the Secretariat is suggesting that performance indicators should not be modified based on submissions that did not incorporate previous Executive Committee decisions. The Executive Committee may wish to decide whether to allow the modification of performance indicators based on data in business plans as submitted only if new Executive Committee decisions are applied to adjust submitted business plans.

SECTION VII: OTHER POLICY ISSUES Endorsement of consolidated business plan and notation of agency business plans 53. Traditionally, the consolidated business plan has been noted while implementing agency business plans have been endorsed with several caveats. The Executive Committee has often had to take decisions to modify the business plans of the bilateral and implementing agencies while in fact the Executive Committee was essentially developing an overall business plan for the Multilateral Fund based on the input of the implementing agencies. For this reason, the Secretariat is recommending that the consolidated business plan is endorsed with the traditional caveats and the business plans of the implementing agencies are noted.

Distribution of annual tranches of HPMPs 54. Table 9 shows the extent to which planned HPMP activities would result in commitments beyond the 2011-2014 business planning period.

UNEP/OzL.Pro/ExCom/63/7

14

Table 9

HPMP ACTIVITIES AFTER 2014 AS PER PROPOSED SECRETARIAT ADJUSTMENTS

(US $000)

2015 2016 2017 2018 2019 2020 After 2020 Approved 202 2,750 197 666 485 698 509 New planned activities 82,424 34,394 732 1,383 1,811 1,040 120 Total 82,626 37,144 929 2,049 2,296 1,738 629

55. It should be recalled that resources from pledged contributions to the Multilateral Fund are due on an annual basis. For this reason, the funding tranches of HPMPs should ideally be distributed equally. However, as shown in Table 9 above, neither the approved funding nor planned new activities have annual tranches distributed equally, in some cases due to planned funding requirements. This could result in a lack of resources to meet demand if not monitored closely. The Executive Committee may wish to monitor the results of proposed funding distributions in the light of approved commitments to ensure that planned funding would be available to meet commitments.

Stage II funding of HPMPs 56. The HCFC guidelines foresaw stage I as addressing at least the 2013 freeze and the 10 per cent reduction required by 2015 but many approved activities have exceeded the 10 per cent reduction with several LVC countries opting for a 2020 reduction of 35 per cent. On this basis, stage II is likely to be funded after the completion of stage I. Table 10 presents the last year of the funding requests for stage I HPMPs in the business plan.

Table 10

LAST YEAR OF FUNDING REQUESTED FOR HPMPs IN THE BUSINESS PLAN

Status 2013 2014 2015 2016 2017 2019 2020 After 2020 LVC 4 14 5 1 1 35 39 3 Non-LVC 6 17 11 1 3 4 Total 10 31 16 2 1 38 43 3

57. Table 10 shows that 103 countries would complete their stage I activities after 2014.

58. Implementing agencies have proposed HPMP activities in their business plans for the countries in Table 11 that have already received approved projects with tonnage amounting to more than 10 per cent of their estimated baseline/starting point.

UNEP/OzL.Pro/ExCom/63/7

15

Table 11

POSSIBLE STAGE II ACTIVITIES IN THE BUSINESS PLAN FOR COUNTRIES THAT HAVE ALREADY RECEIVED FUNDING THAT ADDRESSES AT LEAST A 10 PER CENT

REDUCTION FROM ESTIMATED BASELINES/STARTING POINTS

Country Estimated Baseline/Starting

Point (ODP tonnes)

HCFC Tonnage

Approved to-date (ODP

tonnes)

Percentage of Estimated

Baseline/Starting Point (ODP

tonnes)

Tonnage in the Business Plan (ODP

tonnes)

Value in Adjusted Business

Plan (US$000)

Argentina 356.9 53.5 15.0% 6.1 574 Bangladesh 72.9 20.2 27.7% 6.4 1,248 Egypt 420.4 63.9 15.2% 61.4 3,372 Jordan 73.7 8.1 11.0% 33.0 6,166 Morocco 68.0 11.0 16.2% 2.2 177 Philippines (the) 202.4 40.0 19.8% 4.6 1,209 Saudi Arabia 1,464.1 179.4 12.3% 64.6 8,019 Sudan (the) 50.6 11.9 23.5% 2.5 218 Turkey 640.8 293.7 45.8% 56.2 10,900 Total 3,349.8 681.7 20.4% 237 31,883

59. The Executive Committee may wish to confirm this definition and whether any possible stage II activities should be removed from the business plan.

60. Issues with respect to stage II funding in future business planning include: whether project preparation should be funded in the year prior to the end of stage I, and whether the value of stage II funding should be included in future business plans starting with the 2012-2014 business plan assuming existing guidelines. No stage II project preparation was included in the business plans as submitted. The Executive Committee may wish to opine on these matters to provide guidance for future business plans.

Duration for the next business plan 61. For the last two years, the Executive Committee has extended the traditional three-year business plan timeframe to five years in the case of the 2010-2014 adjusted business plan and to four years for the 2011-2014 business plan. The rationale for the extension was the fact that most of the funding was intended for HPMPs, which were foreseen as multi-year funding agreements that would extend at least to 2014 to meet the 2015 reduction targets. However, as noted above, actual approvals and planned activities for stage I HPMPs extend beyond 2014 and the issue of funding distributions is also relevant to the planning period. The funding level for the 2012-2014 triennium will be based on the replenishment decision to be taken by the Parties at the end of 2011. The Executive Committee may wish to consider the duration of the next business plan period in the light of the above.

Overlap: Change of implementing agency after project preparation funding 62. Both UNDP and UNIDO have included funding for the HPMP in the Gambia. UNDP included funding since it had received project preparation money; however, UNIDO has received an official request for it to implement the HPMP. UNIDO has not included project preparation for the Gambia in its business plan. Any additional project preparation would constitute double-counting. Depending upon the extent to which UNDP has already expended funds on project preparation, UNIDO would not have full access to preparatory funds without additional funding from the Executive Committee. The Executive Committee may wish to remove the UNDP HPMP activities from UNDP’s business plan as requested by the Government of the Gambia, and agree that any project preparation activity funding should be

UNEP/OzL.Pro/ExCom/63/7

16

deducted from the funding eligibility for the HPMP if a country chooses to assign an implementing agency different from the one originally approved to conduct the HPMP.

Tonnage distribution by agency in approved HPMPs 63. Table 12 presents a list of those HPMPs approved to-date, the tonnage approved in the agreement, and the participating implementing agencies.

Table 12

HPMPs APPROVED TO-DATE BY TONNAGE AND IMPLEMENTING AGENCY

Country Agency Tonnage Approved under Agreement

(ODP Tonnes)

Tonnage Approved in Previous Investment Project

(ODP Tonnes) Armenia UNDP/UNEP 2.23 Belize UNDP/UNEP 1.0 Burkina Faso UNEP/UNIDO 9.7 Cambodia UNDP/UNEP 13.8 Chad UNEP/UNIDO 9.5 Colombia UNDP/UNEP 22.89 56.02 Croatia Italy/UNIDO 4.3 3.7 Dominica UNEP 0.1 Gabon UNEP/UNIDO 10.4 Ghana UNDP/Italy 17.3 Grenada UNEP 0.3 Madagascar UNEP/UNIDO 6 Malawi UNEP/UNIDO 3.1 Maldives UNDP/UNEP 3.7 Nigeria UNDP/UNIDO 90.1 Pakistan UNIDO/UNEP 7.4 71.7 Serbia UNIDO/UNEP 3.3 Sri Lanka UNDP/UNEP 4.9 The Former Yugoslav Republic of Macedonia

UNIDO To 65% of HCFC-22 Baseline

Togo UNEP/UNIDO 7 Turkmenistan UNIDO 2.6

64. The agreements with the Executive Committee did not specify the tonnage by agency although this information is needed for accounting purposes. The Executive Committee may wish to decide to request the implementing agencies to agree on a distribution of the tonnage by agency and year. The lead agency should propose the distribution to the relevant countries with approved HPMPs, and report to the 64th Meeting on the agreement.

SECTION VIII: RECOMMENDATIONS 65. The Executive Committee may wish to:

(a) Endorse the Consolidated 2011-2014 Business Plan of the Multilateral Fund as adjusted by the Secretariat contained in UNEP/OzL.Pro/ExCom/63/7, while noting that endorsement denotes neither approval of the projects identified therein nor their funding or tonnage levels, and the endorsement is with any modifications based on consideration of whether:

UNEP/OzL.Pro/ExCom/63/7

17

(i) Any further modifications are warranted to reduce the business plan levels to the planned budget for the 2011-2014 business plan period;

(ii) To remove the global project for information, communication and education activities in the development and implementation of a knowledge portal for HCFC phase-out and HCFC phase-out management plan (HPMP) implementation.

(iii) To maintain possible stage II activities in the business plan for those countries that have already received funding to phase out more than 10 per cent of their estimated baseline/starting point;

(b) Maintain current levels of funding for institutional strengthening for business planning purposes until such time as a decision is taken on the actual levels;

(c) Set a window for ODS destruction for low-volume-consuming (LVC) countries pursuant to decision XXI/2 amounting to US $5.633 million in 2010 and 2011 that would result in the destruction of 308.8 ODP tonnes;

(d) Allow the modification of performance indicators based on data in business plans, as submitted, only if new Executive Committee decisions are applied to adjust submitted business plans;

(e) Monitor the results of proposed funding distributions in the light of approved commitments to ensure that planned funding would be available to meet those commitments;

(f) Determine that stage II HPMPs should begin upon the completion of stage I HPMPs;

(g) Consider whether:

(i) Project preparation should be funded for stage II activities the year prior to the completion of stage I;

(ii) The value of stage II HPMPs should be included in future business plans assuming existing HCFC cost guidelines;

(iii) The duration of the next business plan should be only for the next triennium 2012-2014, or longer to accommodate planned future funding requirements;

(h) Remove the UNDP HPMP activities for the Gambia from UNDP’s business plan as requested by the Government of the Gambia;

(i) Agree that any project preparation activity funding should be deducted from the funding eligibility for the HPMP if a country chooses to assign another implementing agency, different from the one originally approved to conduct the HPMP; and

(j) Request the bilateral and implementing agencies to agree on a distribution of the tonnage for HPMPs followed by agreement with the relevant countries and report to the 64th Meeting on the agreement.

---------------

UNEP/OzL.Pro/ExCom/63/7 Annex II

1

Annex II

HISTORICAL PERFORMANCE INDICATORS

This annex presents the following tables: a) Proposed 2011, and Actual 2010, 2009, 2008 and 2007 Business Plan Performance Indicators.

2006 data will be available upon request; b) Quantitative Performance Indicators (2004 and 2005); c) Investment Project Performance Indicators (2001-2005); d) Non-investment Project Performance Indicators (2001-2005); and e) Proposed 2011, and Actual 2010, 2009, 2008 and 2007 Performance Indicators for UNEP’s

Compliance Assistance Programme (CAP). 2006 data will be available upon request.

UNEP/OzL.Pro/ExCom/63/7 Annex II

2

A: PROPOSED 2011 AND ACTUAL 2010, 2009, 2008 AND 2007 BUSINESS PLAN PERFORMANCE INDICATORS BY AGENCY

Item UNDP 2007

UNDP 2008

UNDP 2009

UNDP 2010

UNDP 2011

UNEP 2007

UNEP 2008

UNEP 2009

UNEP 2010

UNEP 2011

UNIDO 2007

UNIDO 2008

UNIDO 2009

UNIDO 2010

UNIDO 2011

World Bank 2007

World Bank 2008

World Bank 2009

World Bank 2010

World Bank 2011

Number of annual programmes of multi-year agreements approved vs. those planned

45 39 40 49 41 35 35 56 105 65 32 30 28 25 40 191 21/21 14/14 8 7/72

Number of individual projects/activities (investment projects, RMPs, halon banks, TAS, institutional strengthening) approved vs. those planned

22 24 12 51

22 30 56 (excl. CAP)

88

88 70 22 55 20 36 7 4 6/6 7 3 3/3

Milestone activities completed (e.g. policy measures, regulatory assistance)/ODS levels achieved for approved multi-year annual tranches vs. those planned

20 27 36 10 7 9 20 51 26 23 20 19 26 13 6 18 21/21 14 5/5 2/23

ODS phased-out for individual projects vs. those planned per progress reports (ODP tonnes)

1,229 1,888 633 250.5

tbd 0 0 0 0 0 346.2 762.9 155.2 311.8 0 1,334 253 229 240.3 6974

1 Includes one annual programme of new multi-year projects expected to be approved by the Executive Committee in 2007. 2 Following the recommendation of the Secretariat, subsectors under one HPMP are not counted separately, even if under different agencies. 3 Another 8 multi-year agreements are under implementation and being supervised by the Bank for sustainable phase-out, for which funding is not requested. 4 This figure is based on the 2009 progress report, following the Secretariat’s recommendation. An update will be provided later in the year according to the 2010 progress report.

UNEP/OzL.Pro/ExCom/63/7 Annex II

3

Item UNDP 2007

UNDP 2008

UNDP 2009

UNDP 2010

UNDP 2011

UNEP 2007

UNEP 2008

UNEP 2009

UNEP 2010

UNEP 2011

UNIDO 2007

UNIDO 2008

UNIDO 2009

UNIDO 2010

UNIDO 2011

World Bank 2007

World Bank 2008

World Bank 2009

World Bank 2010

World Bank 2011

Project completion (pursuant to Decision 28/2 for investment projects) and as defined for non-investment projects vs. those planned in progress reports

60 61 98 87

tbd 86 86 86 33 33 20 19 13 14 7 105 86 67 58 59

Number of policy/regulatory assistance completed vs. that planned

4/6 (67%)

4/6 (67%)

1/1 (100%)

100% tbd 64 countries10

64 countries

100%11 109 countries

100%12

11 9 N/A N/A N/A 9/9 12/12 100% 100% 100%

Speed of financial completion vs. that required per progress report completion dates

On time

On time

On time

On time

On time

On time

On time

On time

On time

On time

12 months after

operational completion

12 months after

operational completion

12 months after

operational completion

12 months after

operational completion

12 months after

operational completion

11 months

11 months

11 months

11 months

11 months

Timely submission of project completion reports vs. those agreed

On time

On time

On time

On time

On time

On time

On time

On time

On time

On time

On time

On time

On time

On time

On time

100% 100% 100% 100% 100%

Timely submission of progress reports and responses unless otherwise agreed

On time

On time

On time

On time

On time

On time

On time

On time

On time

On time

On time

On time

On time

On time

On time

100% 100% 100% 100% 100%

5 Represents the number of projects expected to be completed in 2007, which will lead to an expected phase-out of 1,334 ODP tonnes. 6 Represents the number of projects expected to be completed in 2008, which will lead to an expected phase-out of 253 ODP tonnes. 7 Includes two investment projects, three institutional strengthening projects, and one technical assistance project. 8 Includes one investment project, two institutional strengthening projects, and two technical assistance projects. 9 This figure is based on the 2009 progress report, following the Secretariat’s recommendation. An update will be provided later in the year according to the 2010 progress report. 10 or 100% of countries listed in Annex I either received assistance or assistance was offered 11 100% of countries listed in Annex I of UNEP’s business plan narrative either received assistance or assistance was offered 12 100% of countries listed in Annex I of UNEP’s business plan narrative either received assistance or assistance was offered

UNEP/OzL.Pro/ExCom/63/7 Annex II

4

B: QUANTITATIVE PERFORMANCE INDICATORS (2004 and 2005)

Item UNDP 2004

UNDP 2005

UNEP 2004

UNEP 2005

UNIDO 2004

UNIDO 2005

World Bank 2004

World Bank 2005

Multi-year tranches approved 19 12 3 4 18 28 18 18 Individual projects/ activities approved 25 32 19 25 11 31 5 7 Milestone activities completed 12 15.5 N/a 3 14 17 15 19 ODS phased-out for individual projects in ODP tonnes

2,579 1,288 0 20 4,790.6 1,654 4,961 2,277

Project completion 97 42 8 24 84 28 40 44 Policy/ regulatory assistance completed N/a N/a 2 63 15 11 All targets in

annual phase-out

N/a

Speed of financial completion 88 of 104 (85%)

174 19 of 34 (56%)

12 of 49 (24%)

9.3 months

8 months 12 months 9 months

Timely submission of project completion reports

97% 111 100% On Time 100% On Time 84% On Time

Timely submission of progress reports On Time On Time On Time Not On Time

On Time On Time On Time On Time

UNEP/OzL.Pro/ExCom/63/7 Annex II

5

C: INVESTMENT PROJECT PERFORMANCE INDICATORS (2001-2005)

ITEM UNDP 2005

UNDP 2004

UNDP 2003

UNDP 2002

UNDP 2001

UNIDO 2005

UNIDO 2004

UNIDO 2003

UNIDO 2002

UNIDO 2001

World Bank 2005

World Bank 2004

World Bank 2003

World Bank 2002

World Bank 2001

ODP phased out 1,663 6,200 5,871 4,582 5,997 1,544.64 5,545.52 6,096 2,890 2,480 N/A 21,812.59 17,395 16,139 6,340

Funds disbursed 26,601,892 $31,240,209 $24,483,520 $29,320,118 $33,358,056 31,840,094 31,963,576 $28,773,312 $28,747,215 $27,671,558 N/A 55,729,832 $65,083,377 $56,531,824 $40,175,452

Project completion reports

111 97% 106% 86.50% 86.16% 78 100% 625% 300% 100% N/A 84% 84% 103% 74%

Distribution among countries*

14 28 18 18 22 23 18 14 19 24 N/A 12 11 11 10

Timely submission of progress report

N/a On Time On Time N/a N/a On Time On Time N/a N/a On Time On Time N/a

Number of project completed in year of business plan

N/a 116 106 N/a N/a 54 46 N/a N/a 45 46 N/a

Value of projects approved*

$26,123,608 $24,422,808 $29,290,743 $37,661,853 $40,533,068 55,170,547 36,878,656 $23,624,603 $32,884,334 $28,436,163 US $68 million

(excluding Support

Costs)

$82,629,695 $75,107,277 $62,531,489 $48,139,038

ODP to be phased out*

2,940 3,606.40 3,810 3,312.90 4,352 16,540.00 9,587 1,120 4,074 4,645.80 65,722.00 20,534 11,352 12,605.90 11,456

Cost of project preparation

1.44% 3.61% 1.60% 2.54% 1.10% 0.86 2.01% 3.64% 3.28% 2.73% 0.40 0.16% 0.64% 0.43% 1.26%

Cost-effectiveness $8.24 $6.27 $7.10 $10.35 $8.30 3.10 $3.58 $9.79 $7.28 $6.12 1.04 $3.74 $6.12 $4.57 $3.85

Speed of first disbursement

12.9 months

12.91 months

12.8 months 12.8 months 12.84 months

8.97 months

9.06 months

9.2 months 9.16 months 9.29 months 25 months 26.02 months

26 months 26.28 months

25.33 months

Speed of completion

32.9 months

32.41 months

32.4 months 32.7 months 33.6 months 32.98 months

32.35 months

31.7 months 30.89 months

29.85 months

40 months 40.88 months

41 months 41.35 months

40.09 months

Net emission due to delays

13,508 12,440 9,322 13,375 14,381 5,354.00 15,874 5,114 6,579.50 5,940 17,651.00 18,155 21,807 24,889 25,257

UNEP/OzL.Pro/ExCom/63/7 Annex II

6

D: NON-INVESTMENT PROJECT PERFORMANCE INDICATORS (2001-2005)

AGENCY UNDP 2005

UNDP 2004

UNDP 2003

UNDP 2002

UNDP 2001

UNEP 2005

UNEP 2004

UNEP 2003

UNEP 2002

UNEP 2001

UNIDO 2005

UNIDO 2004

UNIDO 2003

UNIDO

2002

UNIDO

2001

World Bank 2005

World Bank 2004

World Bank 2003

World Bank 2002

World Bank 2001

Number of Projects Completed

22 11 8 69% of approve

d

66% of approve

d

62% of approve

d

16 13 3 5 2 1

Funds Disbursed (US$)

3,224,343

2,488,374

3,693,816

2,167,508

1,684,702

10,855,433

54% of approve

d

72% of approve

d

68% of approve

d

68% of approve

d

1,387,905

1,353,861

1,201,983

775,244

461,385

1,221,964

813,599

2,246,337

546,533

281,715

Speed until first disbursement

11.5 months

11.44 months

11 months

11.4 months

10.5 months

8.41 months

8.49 months

7.6 months

7.3 months

6.87 months

8.95 months

9.34 months

9.4 months

9.85 months

9.15 months

14 months

14.58 month

s

13.7 months

12.05 month

s

11.95 months

Speed until project completion

35.4 months

35.36 months

35 months

34.7 months

35.1 months

32.44 months

31.8 months

31 months

30.4 months

29.66 months

31.93 months

33.89 months

33.7 months

33.84 months

33.66 months

32 months

30.39 month

s

30 months

28.85 month

s

29.24 months

Timely submission of progress report

N/a On Time On- time N/a N/a On Time

On Time

N/a N/a On Time On- time

N/a N/a On Time On- time

N/a

Policies initiated from non-investment activities

N/a 6 28 8 countrie

s

N/a 21 countries

11 countrie

s

N/p N/a 2 countrie

s

7 countrie

s

Policies in 2–

4 countrie

s

N/a None 1 countr

y

2 countrie

s

Reduction in ODP from non-investment activities

N/a 0 1 125 tonnes

N/a 0 0 N/p N/a 45 0 65 tonnes

N/a 86.9 0 0 tonnes

UNEP/OzL.Pro/ExCom/63/7 Annex II

7

E. PROPOSED 2011, AND ACTUAL 2010, 2009, 2008 AND 2007 PERFORMANCE INDICATORS FOR UNEP’S COMPLIANCE ASSISTANCE PROGRAMME (CAP)

Performance Indicator UNEP 2007 target UNEP 2008 target UNEP 2009 target UNEP 2010 target UNEP 2011 target

Efficient follow-up to regional network/thematic meetings

100 % implementation rate

100 % implementation rate

90 % implementation rate

90 % implementation rate

90 % implementation rate

Effective support to NOUs in their work, particularly guidance to new National Ozone Units (NOUs)

7 such ways/means/products/services

7 such ways/means/ products/services; All new NOUs receive capacity building support

7 such ways/means/ products/services; All new NOUs receive capacity building support

7 such ways/means/ products/services; All new NOUs receive capacity building support

7 such ways/means/ products/services;

All new NOUs receive capacity building support.

10 additional countries submit CP reports using the Multilateral Fund Secretariat’s online data reporting system

Assistance to countries in actual or potential non-compliance (as per MOP decisions and/or as per reported Article 7 data and trend analysis)

All such countries All such countries All such countries All such countries All such countries

Innovations in production and delivery of global and regional information products and services

7 such products and services

7 such products and services

7 such products and services

7 such products and services

7 such products and services

Close cooperation between CAP regional teams and bilateral and multilateral implementing agencies working in the regions

5 in each region 5 in each region 5 in each region 5 in each region 5 in each region

-----