connecting petersham€¦ · 1 0% petersham ftth project 116 days thu 12/1/16 thu 5/11/17 2 0%...
TRANSCRIPT
![Page 1: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/1.jpg)
![Page 2: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/2.jpg)
![Page 3: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/3.jpg)
![Page 4: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/4.jpg)
![Page 5: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/5.jpg)
![Page 6: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/6.jpg)
Project Management
Telecommunications
Civil Engineering
Permitting
FTTH
11 Melanie Lane SUITE 14 East Hanover, NJ 07936 Tel: 973.503.1400 Fax: 973.503.5666
COMPANY OVERVIEW
Matrix Design Group Millennium Communications Group
11 Melanie Lane, Suite 14 11 Melanie Lane, Suite 13
East Hanover, NJ 07936 East Hanover, NJ 07936
www.matrixdg.com www.millenniuminc.com
P (973) 503-1400 P (800) 677-1919
F (973) 503-5666 F (973) 503-0111
Matrix Design Group and Millennium Communications Group were founded in 1995 by a group
of professionals experienced specifically in the telecommunications industry. As a full service
provider of fiber solutions, we are equipped to serve both the design and build aspects of any
fiber project. Matrix has a long standing reputation for having the ability to plan, permit, design,
and manage the installation of your fiber optic network on budget and ahead of schedule. When
you retain Matrix’s team of engineers and construction experts, you have employed experienced
partners who work closely with you to develop cost effective solutions that satisfy the
pronounced demands of all applicable state and local review agencies.
Matrix and Millennium have been in business for over 20-years. The companies have done
hundreds of fiber projects and have installed thousands of miles of fiber network. A partial list of
some of our customers over the past 20-years include:
AT&T Allied Signal
CableVision CitiGroup
Con Edison Conn DoT
Level 3 Lucent Technologies
Marriott International Nabisco
NJ DoT OnFiber
Public Service of NJ Rutgers University
Sprint PCS Time Warner Telecom
Verizon Verizon Wireless
Zayo Group XO Communications
Some of the New England towns we have worked with include:
Alford, MA Barnard, VT
Chelsea, VT Leverett, MA
Norwich, VT Pomfret, VT
Randolph, VT Royalton, VT
Sharon, VT Stratford, VT
Thetford, VT Turnbridge, VT
Vershire, VT WiredWest
Our technology partners include:
![Page 7: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/7.jpg)
![Page 8: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/8.jpg)
![Page 9: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/9.jpg)
![Page 10: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/10.jpg)
![Page 11: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/11.jpg)
![Page 12: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/12.jpg)
![Page 13: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/13.jpg)
![Page 14: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/14.jpg)
![Page 15: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/15.jpg)
![Page 16: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/16.jpg)
![Page 17: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/17.jpg)
![Page 18: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/18.jpg)
![Page 19: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/19.jpg)
![Page 20: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/20.jpg)
![Page 21: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/21.jpg)
![Page 22: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/22.jpg)
![Page 23: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/23.jpg)
![Page 24: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/24.jpg)
![Page 25: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/25.jpg)
![Page 26: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/26.jpg)
![Page 27: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/27.jpg)
![Page 28: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/28.jpg)
![Page 29: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/29.jpg)
![Page 30: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/30.jpg)
![Page 31: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/31.jpg)
![Page 32: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/32.jpg)
![Page 33: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/33.jpg)
![Page 34: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/34.jpg)
ID % Complete Task Name Duration Start Finish Predecessors
1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17
2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17
3 0% Project Kick-Off 4 days Thu 12/1/16 Tue 12/6/16
4 0% Contract Award 1 day Thu 12/1/16 Thu 12/1/16
5 0% Contract Review 3 days Fri 12/2/16 Tue 12/6/16 4
6 0% Information Gathering / Transfer 5 days Wed 12/7/16 Tue 12/13/16 5
7 0% Field Surveying 17 days Wed 12/14/16 Thu 1/5/17
8 0% Pole Survey & Initial Design 5 days Wed 12/14/16 Tue 12/20/16 6
9 0% Pole Licensing & Conduit Licensing Surveying 10 days Wed 12/21/16 Tue 1/3/17 8
10 0% Survey Permitting Locations 2 days Wed 1/4/17 Thu 1/5/17 9
11 0% Fiber Route Design 25 days Fri 1/6/17 Thu 2/9/17
12 0% Design an Optimal FTTH Network Route 10 days Fri 1/6/17 Thu 1/19/17 10
13 0% Quality Control 5 days Fri 1/20/17 Thu 1/26/17 12
14 0% Final Design to 100% 10 days Fri 1/27/17 Thu 2/9/17 13
15 0% Specify Equipment 19 days Fri 1/6/17 Wed 2/1/17
16 0% Specifiy Network Technology 4 days Fri 1/6/17 Wed 1/11/17 10
17 0% Specify Architecture 10 days Thu 1/12/17 Wed 1/25/17 16
18 0% Submit Cut Sheet to Town for Approval 5 days Thu 1/26/17 Wed 2/1/17 17
19 0% Pole and Conduit Applications 92 days Wed 1/4/17 Thu 5/11/17
20 0% Submit Pole and Conduit Applications 2 days Wed 1/4/17 Thu 1/5/17 9
21 0% Oversee Licensing Process 60 days Fri 1/6/17 Thu 3/30/17 20
22 0% Receive Licenses 30 days Fri 3/31/17 Thu 5/11/17 21
23 0% Engineering & Design Complete 0 days Thu 5/11/17 Thu 5/11/17 22
24 0% Prepare Construction Bid Package & Project Budget
22 days Thu 2/2/17 Fri 3/3/17
25 0% Develop Overall Project Budget 5 days Thu 2/2/17 Wed 2/8/17 18
26 0% Prepare Overall Construction Bid Package 10 days Thu 2/9/17 Wed 2/22/17 25
27 0% Review Construction Bid Package with Town 5 days Thu 2/23/17 Wed 3/1/17 26
28 0% Final Construction Bid Package 2 days Thu 3/2/17 Fri 3/3/17 27
29 0% Construction Support Documents 7 days Mon 3/6/17 Tue 3/14/17
30 0% Review Construction Schedule 2 days Mon 3/6/17 Tue 3/7/17 28
31 0% Specify Testing Procedures 5 days Wed 3/8/17 Tue 3/14/17 30
32 0% Project Close Out 42 days Wed 3/15/17 Thu 5/11/17
33 0% Documentation Package 10 days Wed 3/15/17 Tue 3/28/17 31
34 0% Project Review 5 days Wed 3/29/17 Tue 4/4/17 33
35 0% Project Acceptance 1 day Wed 4/5/17 Wed 4/5/17 34
36 0% Begin Construction 0 days Thu 5/11/17 Thu 5/11/17 35,22
Estimated Project Time. Actual Time TBD by Verizon / National Grid
5/11
Constuction Tasks Timeline TBD
T F S S M T W T F S S M T W T F S S M T W T0, '16 Dec 11, '16 Jan 1, '17 Jan 22, '17 Feb 12, '17 Mar 5, '17 Mar 26, '17 Apr 16, '17 May 7, '17
Task
Split
Milestone
Summary
Project Summary
External Tasks
External MileTask
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Split
Petersham Broadband FTTH Schedule
Page 1
Project: Petersham ScheduleDate: Wed 10/12/16
![Page 35: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/35.jpg)
21 Oversee Licensing ProcessEstimated Project Time. Actual Time TBD by Verizon / National Grid
36 Begin ConstructionConstuction Tasks Timeline TBD
Petersham Broadband FTTH Schedule
Page 2
![Page 36: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/36.jpg)
![Page 37: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/37.jpg)
![Page 38: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/38.jpg)
![Page 39: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/39.jpg)
![Page 40: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/40.jpg)
![Page 41: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/41.jpg)
![Page 42: Connecting Petersham€¦ · 1 0% Petersham FTTH Project 116 days Thu 12/1/16 Thu 5/11/17 2 0% Design & Engineering 116 days Thu 12/1/16 Thu 5/11/17 3 0% Project Kick-Off 4 days Thu](https://reader036.vdocuments.site/reader036/viewer/2022081408/6060538a3ca10a00647f8668/html5/thumbnails/42.jpg)