congo central africa backbone (cab) project congo component

37
AFRICAN DEVELOPMENT BANK CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT OITC/ORCE DEPARTMENTS May 2016 Translated document Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 21-Jun-2022

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

AFRICAN DEVELOPMENT BANK

CONGO

CENTRAL AFRICA BACKBONE (CAB) PROJECT

CONGO COMPONENT

OITC/ORCE DEPARTMENTS

May 2016

Translated document

Pu

bli

c D

iscl

osu

re A

uth

ori

zed

P

ub

lic

Dis

clo

sure

Au

tho

rize

d

Page 2: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

TABLE OF CONTENTS

I. STRATEGIC THRUST AND RATIONALE………………………………………………………………………………..1

1.1 Project Linkages with Country Strategy and Objectives ........................................................................... 1 1.2 Rationale for Bank’s Intervention ............................................................................................................. 1 1.3 Donor Coordination .................................................................................................................................. 2

II. PROJECT DESCRIPTION .................................................................................................................. 3 2.1. Project Objectives and Components ......................................................................................................... 3 2.2. Technical Solutions Adopted and Alternatives Explored ......................................................................... 5 2.3. Project Type .............................................................................................................................................. 6 2.4. Estimated Project Cost and Financing Arrangements ............................................................................... 6 2.5. Project Area and Beneficiaries .................................................................................................................. 8 2.6. Participatory Approach for Project Identification, Design and Implementation, including Active Private

Sector Participation……………………………………………………………………………………….8

2.7. Bank Group Experience and Lessons Reflected in Project Design ........................................................... 9 2.8. Key Performance Indicators ................................................................................................................... 9

III. PROJECT FEASIBILITY .................................................................................................................. 10 3.1. Economic and Financial Performance ..................................................................................................... 10 3.2. Environmental and Social Impact ........................................................................................................... 11

IV. PROJECT IMPLEMENTATION ...................................................................................................... 12 4.1. Implementation Arrangements ................................................................................................................ 12 4.2. Procurement Arrangements ..................................................................................................................... 13 4.3. Financial Management and Disbursement Arrangements ....................................................................... 13 4.4. Monitoring .............................................................................................................................................. 14 4.5. Governance ............................................................................................................................................. 15 4.6. Sustainability ........................................................................................................................................... 16 4.7. Risk Management ................................................................................................................................... 16 4.8. Knowledge Building ............................................................................................................................... 17

V. LEGAL FRAMEWORK ..................................................................................................................... 17 5.1. Legal Instrument ..................................................................................................................................... 17 5.2. Conditions Associated with AfDB Intervention ..................................................................................... 17 5.2.1. Conditions Precedent to Loan Effectiveness ........................................................................................... 17 5.2.2. Conditions Precedent to First Disbursement of AfDB Loan ................................................................... 17 5.2.3. Other Conditions ..................................................................................................................................... 17 5.2.4. Undertakings ........................................................................................................................................... 17

VI. RECOMMENDATION .........................................................................................................................18

ANNEX I: DESCRIPTION OF INSTITUTIONAL SUPPORT AND CAPACITY BUILDING

ANNEX II: RATIONALE FOR THE LEVEL OF COUNTERPART CONTRIBUTION TO AFDB

FINANCING

ANNEX III: COMPARATIVE SOCIO-ECONOMIC INDICATORS

ANNEX IV: STATUS OF BANK PORTFOLIO IN CONGO AS AT 31 JANUARY 2016

ANNEX V: MAP OF THE OPTICAL FIBRE INFRASTRUCTURE PROJECT AREA (AFDB AND

WORLD BANK FINANCING)

LIST OF TABLES AND GRAPHS

Table 2.1 : Project Components ................................................................................................................... 5 Table 2.2 : Alternative Solutions Explored and Reasons for Rejection ....................................................... 6 Table 2.3 : Summary of Estimated Project Cost by Component .................................................................. 7 Table 2.4 : Summary of Estimated Project Cost by Expenditure Category ................................................ 7 Table 2.5 : Summary of Estimated Project Cost by Source of Financing ................................................... 7 Table 2.6 : Summary of Project Components by Source of Financing (EUR million) ................................ 7 Table 2.7 : Expenditure Schedule by Source of Financing (EUR million)…………………………………8 Table 3.1 : Economic and Financial Assessment…………………………………………………………. 10 Table 3.2 : Sensitivity Test…………………………………………………………….………………… 11

Page 3: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

i

Currency Equivalents April 2016

EUR1 = CFAF 655.96

UA1 = EUR 1.27

Fiscal Year

1 January - 31 December

ACRONYMS AND ABBREVIATIONS

ACTIC Congolese Information and Communications Technology Agency

ADF African Development Fund

AfDB African Development Bank

ARPCE Posts and Electronic Communications Regulatory Authority

CAB Central Africa Backbone

CAR Central African Republic

CEAC Centre for Education and Community Action

CEMAC Central African Economic and Monetary Community

CFAF African Financial Community Franc

CSIRT Computer Security for Incident Response Team

DCC Digital Community Centre

DRC Democratic Republic of Congo

DUP Public Interest Statement

ECCAS Economic Community of Central African States

EIRR Economic Internal Rate of Return

ESMP Environmental and Social Management Plan

EU European Union

EWS Emergency Warning System

GDP Gross Domestic Product

GHG Greenhouse Gas

HDPE High-density Polyethylene

ICB International Competitive Bidding

ICT Information and Communications Technologies

IJSB Brazzaville Institute for Young Deaf People

INAC Congolese National Institute for the Blind

IsDB Islamic Development Bank

ITU International Telecommunication Union

JICA Japan International Cooperation Agency

KEXIM Korea Eximbank

LCB Local Competitive Bidding

LTS Long-Term Strategy

MAFDP Ministry of Land Tenure and State Property

Page 4: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

ii

MEFPPPI Ministry of Economy, Finance, Planning, Public Investment and Integration

METPFE Ministry of Technical and Vocational Education, Skills Training and Employment

MPFIFD Ministry of Women’s Empowerment and Integration in Development

MPT Ministry of Posts and Telecommunications

MTE Ministry of Tourism and Environment

NEPAD New Partnership for Africa's Development

NIS National Institute of Statistics

NPV Net Present Value

OF Optical Fibre

PAP Project Affected Person

PCN Project Concept Note

PCU Project Coordination Unit

PIDA Programme for Infrastructure Development in Africa

PIS Postal Information System

PKI Public Key Infrastructure

PVC Polyvinyl Chloride

RC Republic of Congo

RISP Regional Integration Strategy Paper

SOPECO Congolese Posts and Savings Corporation

TFP Technical and Financial Partner

UMNG Marien Ngouabi University

WB World Bank

Page 5: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

iii

PROJECT INFORMATION SHEET

Client Information

Borrower : REPUBLIC OF CONGO

Project Name : CENTRAL AFRICA BACKBONE (CAB) PROJECT –

CONGO COMPONENT

Project Location : SANGHA AND BRAZZAVILLE DIVISIONS

Executing Agency : MINISTRY OF POSTS AND TELECOMMUNICATIONS

(MPT)

CAB-CONGO PROJECT IMPLEMENTATION UNIT

(CAB-CONGO/PIU)

1. Financing Plan

Source of Financing Amount in

CFAF million Amount in

EUR million Amount in UA

million Instrument

AfDB 34 138 52.041 40.978 Project Loan

GOVERNMENT OF

CONGO 9 520 14.514 11.428 Public Investment Budget

TOTAL 43 658 66.555 52.406

2. Key AfDB Financial Information

Loan Currency : Euro (EUR)

Loan Interest Type : Floating (EURIBOR)

Interest Rate Margin : Base rate + Bank financing margin1 + 60 bp + maturity

premium2

Commitment Fee : Not applicable

Other Costs : Not applicable

Tenor : Six-monthly

Maturity : 20 years

Grace Period : 60 months

FNPV (baseline scenario) : EUR 143.42 million

FIRR (baseline scenario) : 18.88%

EIRR (baseline scenario) 29.12%

3. Timeframe - Milestones (expected)

Activities (Month/year)

Concept Note Approval November 2015

Project Approval May 2016

Effectiveness September 2016

Completion December 2020

Last Disbursement June 2021

Last Reimbursement of AfDB Loan December 2036

1 The financing margin corresponds to the cost of the Bank loan calculated twice a year. 2 Given that the weighted average maturity is < = 12.75, there is no maturity premium to be applied

Page 6: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

iv

EXECUTIVE SUMMARY

1. Project Overview: Building on the objectives set for the Information and

Communications Technologies (ICT) sector by the Growth, Employment and Poverty

Reduction Strategy Paper (GEPRSP), the Government of Congo requested the Bank to finance

the national component of the Central Africa Backbone (CAB) project through the laying of

550 kilometres of optical fibre cables on the interconnection links with Cameroon and the CAR

and the establishment of a national data centre (Datacentre). The project also envisages the

implementation of a number of ICT applications and services (Emergency Warning System, e-

Post, etc.), and an institutional support concerning, among others, feasibility studies for the

preparation of the next phase of the project, support to the Posts and Electronic Communications

Regulatory Authority (ARPCE) and the Congolese Information and Communications

Technology Agency (ACTIC), support to the Congolese National Institute for the Blind

(INAC), the Brazzaville Institute for Young Deaf People (IJSB) and Marien Ngouabi

University (UMNG), and support for women’s empowerment, the promotion of vocational

training and the development of indigenous people. The Ministry of Posts and

Telecommunications (MPT) will be the project executing agency. The project will be

implemented over a four-year period. The total project cost is estimated at Units of Account

(UA) 52.406 million. The Bank will provide UA 40.978 million through the AfDB window and

the country’s counterpart contribution will be UA 11.428 million.

2. Needs Assessment: In addition to its regional focus, the project aims to complete the

missing links in the national optical fibre backbone. It will help to extend the national optical

fibre network coverage in this region and to Congo’s borders with Cameroon and the Central

African Republic (CAR). The links with neighbouring countries (especially Cameroon) will

offer them an alternative service for international traffic through submarine cables with landfall

points in Cameroon. Thus, the cost of international connectivity should be reduced by

introducing these new international outlets. The project also enables Congo to take advantage

of the extension of its national optical fibre backbone to modernize the postal sector by

introducing e-Posts in the Congolese Posts and Savings Corporation (SOPECO), hence the

inclusion of the project (for which all the required studies have already been carried out) in the

mid-term review of Congo’s Country Strategy Paper (CSP) for 2013-2017 as well as the Central

Africa Regional Integration Strategy Paper 2011- 2015 (whose implementation period is being

extended to 2017).

3. Bank’s Value Added: the Bank’s value added stems from the experience garnered

through exchanges with countries since the project was initiated in 2007. In fact, in coordination

with the World Bank, the Bank has provided substantial resources for the financing of studies

on the regional CAB project, while continuing exchanges with countries involved ever since.

The Bank’s intervention will also enable Congo to carry out these major infrastructure projects,

particularly its interconnections with neighbouring countries, in accordance with international

norms and standards, in order to avoid possible risks of defects that may seriously undermine

the economic benefits of the project and its reasonable financing costs.

4. Knowledge Building: the project will offer an opportunity to improve knowledge in

the area of national optical fibre infrastructure. Provision has been made to prepare the first

Broadband Infrastructure Development Master Plan. ARPCE could use this Plan, among others,

based on the results of the study on the profitability thresholds of optical fibre deployment, to

develop all appropriate tools for regulating the broadband infrastructure sector. Failure to

control illegal trenching could cause serious damage to costly road infrastructure.

Page 7: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

v

RESULTS-BASED LOGICAL FRAMEWORK REPUBLIC OF CONGO

Country and Project Name: Congo: Central Africa Backbone (CAB) Project – Congo Component. Project Goal: Contribute to the diversification of the economy by fostering the emergence of a digital economy in Congo.

Results Chain Performance Indicators

Means of Verification Risks/Mitigation Measures Indicator (including CSI) Baseline Situation Target

Imp

act

Contribute to diversifying Congo’s economy, breaking the digital isolation

of rural areas coupled with regional

integration, and creating employment opportunities, especially for youths.

Percentage of ICT contribution to the country's GDP through sector tax reforms.

Number of interconnections with neighbouring countries.

4.4% (2014)

1 (2015)

10% (at least) in 2020

3 (2020)

Reports and statistics by the MPT, ARPCE, etc.

Project impact monitoring

and evaluation reports. Reports by the ITU and

ECCAS.

Ou

tco

mes

Outcome 1: Improved access of the

population, government services and businesses to quality

telecommunications/ICT services at

affordable prices.

Internet service penetration.

Price (USD/month) of a megabyte per second (Mbps) to Europe.

Number of people benefiting from online

government (informational and transactional) services.

Number of students benefiting from the

business incubator.

7% (2013)

1 076 (WACS/2014)

0 (2015)

0 (2015)

30% (2020)

358 (2020)

50 000 (2020)

5 000 (2020)

Reports and statistics by

the MPT, ARPCE, ACTIC, etc.

Reports by the METFPE,

MPFIFD, MAFDP, SOPECO, INCA, IJSB,

UMNG, etc.

Project impact

monitoring and

evaluation reports

prepared by CAB-Congo/PIU.

Reports by the ITU,

ECCAS and the World Bank (Doing Business).

Risks: (i) Non-compliance with

commitments regarding the laying of optical fibre cables; (ii) no impact on prices; (iii)

premature degradation of the optical fibre

due to lack of maintenance; (iv) lack of maintenance and upgradeability of the

various applications installed; and (v) social

tension arising from protests against the

result of the presidential election.

Mitigation measures: (i) Government's

commitment to implement the guidelines of the International Telecommunication Union

(ITU); (ii) technical assistance to ARPCE;

(iii) commitment by Congo Télécom and SOPECO to ensure the sustainability of the

infrastructure put in place; (iv) call for

inclusive dialogue by the opposition in order to ease the above-mentioned political and

social tension.

Outcome 2: Contribution to the social, economic and financial inclusion of the

population of the country's hinterland.

Number of beneficiaries of e-Post.

Number of people benefiting from solar

electric terminal systems.

Number of indigenous people benefiting from a community radio for awareness campaigns.

0 (2016)

0 (2016)

0 (2016)

5 000 (2020)

10 000 (2020)

90 000 (2020)

Outcome 3: Improved training and access to ICT in education.

Number of UMNG students with access to application tools (portal, services and an

online training medium, etc.).

Number of INAC and IJSB students with

access to ICT media in their training.

Number of women with access to training

programmes (ICT, entrepreneurship, etc.).

0 (2016)

0 (2016)

0 (2016)

30 000 students (2020)

350 (2020)

10 000 (2020)

Ou

tputs

Output 1: Optical fibre infrastructure

Optical fibre connections established Technical sites built

Length of optical fibre cable.

Number of technical sites along project links.

≈ 1800 km (2016)

0 (2016)

≈ 2 350 km (2020)

4 (2020)

CAB/Congo/PIU progress reports.

Control mission reports.

Project supervision reports.

Project completion

reports.

RISKS: (i) Delay in the release of counterpart contributions; (ii) slow pace and

lack of transparency in the procurement

process; (iii) escalation of the cost of works; and (iv) non-compliance with technical and

functional specifications in the context of

various project applications.

Mitigation measures: (i) Continuous

dialogue with the Ministry in charge of

Output 2: ICT applications and

services

ICT applications (Emergency Warning System, e-Post, and

standard e-Gov platform) installed.

Number of new ICT applications developed and put into operation

0 (2016)

3 (2020)

Page 8: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

vi

Output 3: Institutional support and

capacity building

Optical fibre infrastructure network

development and preservation.

Conduct of feasibility studies to prepare the next phase of the project: (i) a CSIRT+ PKI

project; (ii) an integrated electronic system for

the identification of persons (SIGIEP); (iii) a mobile financial service development project;

(iv) implementation of the e-Gov; (v)

establishment of a National ICT School; and

(vi) establishment of a hybrid mail system.

Number of women’s centres, digital community centres and community radios

equipped.

Number of students in industrial sections of government technical high schools awarded

scholarships.

Number of community radios for indigenous people in the Sangha and Likoula Regions.

2016: lack of

strategic framework

for the development of the national optical

fibre backbone

2015: absence of bases for a large-

scale deployment of

ICT applications /services

0 (2016)

0 (2016)

0 (2016)

2020: strategic decision-

making documents

prepared (Master Plan and study on profitability

thresholds)

2019: feasibility studies on the delivery of

electronic administrative

services to the public and private sectors

11 (2020)

24 (by 2020), 2/3 of them

female students

1 (2020)

CAB-Congo/PCU

progress reports.

Control mission reports. Project supervision

reports.

METPFE monitoring and evaluation report.

UN Women reports.

Statistics by MPFIFD. Project completion

reports.

finance in the context of the preparation of

forward-looking finance acts throughout the

project period; (ii) strict monitoring of Bank procurement procedures; (iii) consideration

of physical contingencies in the project; and

(iv) CAB/Congo/PIU capacity building.

Output 4: Project Management

Support for CAB-Congo/PCU.

Monitoring and evaluation of

technical implementation and socio-economic and environmental

impacts.

Project accounting and financial audit.

Project technical audit.

Audit reports.

Reports on the monitoring and evaluation of various aspects of the project.

Technical audit report.

2016: No report.

2020: at least 4 audit

reports, at least 3 monitoring and evaluation

reports, and 1 technical

audit report prepared, etc.

CAB-Congo/PCU

progress reports.

Control mission reports.

Project supervision

reports.

Project completion reports.

Key

Acti

vit

ies

Components Resources

A. Optical Fibre Infrastructure

B. ICT Applications and Services

C. Institutional Support and Capacity Building

D. Project Management

Components EUR million

Optical Fibre Infrastructure (Component A) 42.036

ICT Applications and Services (Component B) 8.258

Institutional Support and Capacity Building

(Component C) 6.911

Project Management (Component D) 3185

Base Cost 60.39

Physical Contingencies 4.227

Price Escalation 1.938

Total Project Cost 66.555

Page 9: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

vii

PROJECT IMPLEMENTATION SCHEDULE

Page 10: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

1

REPORT AND RECOMMENDATION OF MANAGEMENT TO THE BOARD OF

DIRECTORS CONCERNING A PROPOSAL TO GRANT A EUR 52.041 MILLION ADB

LOAN TO THE REPUBLIC OF CONGO TO FINANCE THE CENTRAL AFRICA

BACKBONE (CAB) PROJECT – CONGO COMPONENT

I. STRATEGIC THRUST AND RATIONALE

1.1 Project Linkages with Country Strategy and Objectives

1.1.1. Congo potentially occupies a strategic position for ICT development in Central Africa as it

shares borders with three countries with submarine cable (SAT3, WACS and ACE) landfall points

and which could provide it with an alternative to the single submarine cable (WACS) to which it has

access so far. Yet, of all its neighbours, the country has only one under-river optical fibre link with

the Democratic Republic of Congo (DRC). Moreover, its own use of connectivity for data is still

limited. In addition to the low Internet penetration rate, with only 7% of the population enjoying

Internet access, broadband Internet access in rural areas is almost non-existent, apart from localities

along the main roads crossed by the optical fibre thus far.

1.1.2. Given the significant needs in terms of regional and national connectivity, and the catalytic

effect of ICT in all sectors of the country, it was agreed that the Bank’s intervention will follow the

multi-phased programme-based approach. The project is consistent with the Growth, Employment

and Poverty Reduction Strategy Paper (GEPRSP) which is a component of Congo’s National

Development Plan (NDP) 2012-2016. Given the cross-cutting nature of ICT, it is in line with the five

GEPRSP pillars, namely: (i) governance; (ii) economic transformation; (iii) economic and social

infrastructure development; (iv) social development; and (v) sustainable development. The recent

adoption (2014) of a new National Cyber Strategy is in line with the GEPRSP and seeks to provide

wide ICT access for the Congolese people. The main objective of this strategy is to increase the

provision of high-quality broadband electronic communication services at competitive prices, in line

with the Brazzaville Declaration (February 2014) issued by Central African Ministers in charge of

ICT. Lastly, it is in keeping with Pillar I of Congo’s 2013-2017 CSP and the Central Africa Regional

Integration Strategy Paper (RISP) 2011-2015 (whose implementation period is being extended to

2017). It also contains positive externalities that will strengthen sector governance (Pillar II of the

said CSP), particularly through the modernization of major State applications.

1.1.3. Beyond strictly infrastructural aspects, the project is intended to help Congo to develop a

genuine digital economy in order to ultimately create enough jobs by improving factors of production.

Thus, the implementation of the e-Post project for SOPECO will complement the optical fibre system

through the introduction of new electronic products and services. In addition, the establishment of the

National Data Centre will help to lay physical bases in terms of application storage and hosting space

for the development of an e-government service in Congo. This should be complemented by the

establishment of a technology park during the implementation of the next phase of the project in order

to establish an ICT cluster housing in one place all actors of the technology value chain, namely

innovative enterprises (start-ups in particular), training institutions, research laboratories, etc.

1.2 Rationale for Bank’s Intervention

1.2.1. The project is consistent with the Bank’s Ten-Year Strategy (2013-2022) particularly the

two pillars on infrastructure development and the promotion of regional integration as well as its ICT

Sector Strategy with respect to components on regional integration and the adoption of online

services. It also addresses the issue of green growth and inclusive development (especially gender

issues) through the following initiatives: (i) capacity building of various women’s centres and digital

community centres; (ii) provision of support to the Congolese National Institute for the Blind (INAC)

and the Brazzaville Institute for Young Deaf People (IJSB); (iii) the establishment of an Emergency

Warning System (EWS); (iv) implementation of women’s empowerment and local population

Page 11: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

2

development activities; and (v) monitoring of project environmental and social impacts. All these

activities will be implemented in accordance with the requirements of the Bank’s Integrated

Safeguards System.

1.2.2. The Bank’s intervention in this project is justified by the fact that broadband connectivity is

a key component for the development, adoption and use of ICT in various economic activities with a

view to promoting socio-economic inclusion as well as social cohesion in the country. Based on

several studies carried out notably by the World Bank in 2010 in Africa, it is now proven that a 10%

increase in the number of Internet broadband connections will lead, among others, to a 1.3% boost in

economic growth. The ICT sector accounts for 6% of private employment in Congo and contributes

an estimated 4.4% (6% excluding oil) to gross domestic product (GDP). It could be even more

beneficial provided that the infrastructure and application prerequisites are in place since it already

makes up at least 50% of the tertiary sector.

1.2.3. It should be underscored that CAB-Congo Component is in line with the overall framework

of the CAB regional project, the Cameroonian component which had already been approved by the

Bank in July 2015. In addition, the establishment of optical fibre links by the CAB-Congo project is

in perfect synergy with the road projects financed by the Bank in Congo, among others, which has

systematically provided for the laying of ducts since 2008. All that is required is to procure the optical

fibre cables for the roads involved in the project, given that most of the costs will be borne by the

civil engineering component. This is the case with the Ketta-Djoum road under this project. These

links with neighbouring countries, particularly Cameroon, will induce competition between the

various additional underwater cables (ACE and SAT3) to which Congo will be connected and will,

in turn, lead to a sharp drop in international bandwidth prices.

1.2.4. The country is experimenting with a risky electoral process which may lead to the disruption

of political dialogue and social cohesion, causing social tension and the risk of falling back into

fragility. The context is indeed risky for the implementation of this project, but the risk related to its

“non-implementation” is higher insofar as the project could significantly help to limit the factors that

contribute to disrupting social cohesion. In fact, by increasing digital connectivity, the project will

contribute to enhancing trade, contacts and cohesion between communities, bringing government

services closer to the grassroots, offering virtual spaces for dialogue, increasing access to employment

opportunities, particularly for youths, promoting women’s empowerment, etc.

1.3 Donor Coordination

1.3.1. The Ministry of Economy, Finance, Budget and Public Investment and the Ministry of

Planning and Integration coordinate aid and cooperation with donors at the national level. Regarding

technical and financial partners (TFPs), the TFP Consultation Framework and Thematic Groups

(TGs), which focus on the five main pillars of the National Development Plan (NDP) 2012-2016

adopted in 2014, are a platform for dialogue and discussions on all key development issues in Congo.

The AfDB co-chairs the PTF Thematic Group on infrastructure and also participates actively in key

thematic groups such as governance, public finance management and statistics.

1.3.2. Regarding the ICT sector, in particular, there is a forum for constant dialogue between the

World Bank and the Bank, in consultation with the MPT. In addition to this operation, the Bank has

financed the CAB-Congo project through the review of the legal and regulatory framework as well

as the ongoing laying of optical fibre cables along the Pointe-Noire – Dolisie – Mbinda – Gabon

border road section (see map attached) and would like to continue to provide its support beyond end-

2016 (end of current financing). It is therefore ready to work closely with the Bank for its

Page 12: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

3

implementation, particularly through a joint PCU/CAB-Congo, the sharing of documents and

information, joint meetings, as well as mutual monitoring of the progress of actions undertaken.

1.3.3. The Bank has acquired extensive experience through its exchanges with all the countries of

the sub-region since the CAB project was initiated in 2007. In coordination with the World Bank, the

Bank allocated substantial resources to finance studies on the initial regional CAB project. Thus, the

CAB-Cameroon project was approved by the Bank in July 2015 and the CAB-CAR project is seeking

additional financing from the European Union (EU). This operation will enable Congo to carry out

these major infrastructure projects, particularly its interconnections with neighbouring countries,

while complying with international norms and standards, in order to avoid possible risks of defects

that could seriously undermine the economic benefits of the project and its reasonable financing costs.

1.3.4. During the project identification, preparation and appraisal missions, the Bank team held

discussions with these key TFPs (WB, JICA and KEXIM). The discussions helped to harmonize

views concerning specific project components and the joint financing of the Project Coordination

Unit (PCU/CAB-Congo) with the World Bank. All these partners have acknowledged the importance

and relevance of the project, which is fully consistent with the operations of other partners. This

explains the interest shown by JICA and KEXIM in co-financing the next phase of the project.

II. PROJECT DESCRIPTION

2.1. Project Objectives and Components

2.1.1. The overall objective of this project is to contribute to diversifying the Congolese economy

by significantly increasing tax revenue and considerably reducing the cost of economic and social

transactions, breaking the digital isolation of rural areas as well as enhancing regional integration

through optical fibre infrastructure enabling access to neighbouring countries (Cameroon and CAR)

and creating employment opportunities, particularly for youths.

2.1.2. The construction of optical fibre infrastructure will contribute to reducing the cost of

accessing high-quality ICT services. It will also generate additional resources for Congo not only

through induced economic activities within the country itself, but also through taxes on the data

streams passing through the WACS international underwater cable with landing points at Matombi,

near Pointe-Noire. It could also contribute to enhancing social cohesion by improving digital

connectivity between various communities as well as between government services and users.

2.1.3. In terms of ICT infrastructure, the project seeks particularly to: (i) extend the national optical

fibre backbone to two major sections (interconnection with neighbouring countries, namely

Cameroon and CAR) for about 550 kilometres of fibre; and (ii) set up a National Data Centre. In

addition, it may also be necessary to: (i) set up a mini-data centre and a business incubator for Marien

Ngouabi University; and (ii) rehabilitate the library, computer rooms and the demutization room of

the Brazzaville Institute for Young Deaf People (IJSB) and the Congolese National Institute for the

Blind (INAC). The purpose of establishing the business incubator is to provide students with a

suitable environment for ICT-based entrepreneurship.

2.1.4. Concerning the legal and regulatory framework of the ICT sector, the Congolese

Government imposes no restriction on inter-urban links which include the two connections covered

by this project or on urban links. However, given the investment cost of optical fibre deployment,

particularly inter-urban links, private operators fall back on the existing optical fibre links established

mainly through the National Coverage Programme (PCN) financed with own funds and marketed by

Congo Télécom, besides their microwave links. The main obstacle to the use of these inter-urban

links and, hence, ICT development in the country, is related to excessive taxation by successive

finance acts (FH management and usage fee, optical fibre royalty, authorization for international

Page 13: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

4

gateway access and annual fees, etc.). Thus, given the tax burden on the entire ICT sector value chain,

the conduct of the study on the ICT taxation model is relevant.

2.1.5. The project will support the regulation of the wholesale data market under the responsibility

of the ARPCE by fully enforcing the “open access” principle on each optical fibre link financed by

the Bank in order to ensure minimal competitive conditions on access costs, to the benefit of end

users in Congo. In this regard, a specific provision has been made concerning ARPCE, which involves

preparing an economic model for fixing the cost of access to national and international connectivity

through WACS, with a view to lifting barriers to entry into the optical fibre segment. All these

activities will be part and parcel of activities to extend ICT sector reforms funded by the World Bank

within the framework of the CAB project.

2.1.6. In addition, and through its “ICT Applications and Services” component, the project also

envisages the implementation of several ICT applications to support the diversification of the

Congolese economy. At present, access to financial services in Congo is quite low judging by the rate

of access to banking facilities which hardly exceeds 10%. The significant productivity gains that the

postal sector can derive from ICT applications should be kept in mind. Thus, an e-Post module will

be developed for SOPECO to strengthen financial inclusion and money transfer services for rural

populations through the networking of post offices nationwide.

2.1.7. The project will also support the efforts made by Congolese authorities to adopt a step-by-

step strategic approach to progressively lay the technical and institutional foundations for the

development of electronic government by establishing an e-Government platform. This will

contribute to enhancing the quality of life of citizens and improving the business climate in order to

promote the emergence of a dynamic job-creating private sector. To this should be added the

establishment of an Emergency Warning System (EWS) that will help to put at the disposal of the

competent national authorities a genuine data collection and processing system used to issue early

warnings about health and climatic risks (landslides, floods, etc.) to potentially vulnerable

populations.

2.1.8. The project will also support Marien Ngouabi University in developing infrastructure (mini-

data processing centre, application tools, multimedia centres, geomatics laboratory, etc.) which

sustains services and the management of teaching-, research- and institution administration-related

content. It also includes the establishment of a business incubator on the University website to enable

young entrepreneurs to take advantage of an environment that is conducive to the launching of their

activities concerning the development of ICT solutions. It will also provide targeted support for

vocational training by developing teaching media and awarding scholarships to promote the industrial

sector which is another outlet for Congo’s economic diversification.

2.1.9. The project also includes several feasibility studies relating, among others, to ICT

infrastructure and applications/services which will be considered under the next (second) CAB

project whose preparation should begin at end-2018 using a programme-based approach. Thus,

studies will be carried out on: (i) a comprehensive e-Government Strategy (analysis of the existing

situation, vision and action plan); (ii) a CSIRT+ PKI; (iii) an Integrated Electronic System for the

Identification of Persons (SIGIEP); and (v) the development of mobile financial services in Congo.

The project also envisages a component to build the capacity of key national stakeholders and provide

support to the Project Coordination Unit (PCU/CAB).

To achieve the above-mentioned objectives, project activities have been grouped into the four

components summarized in the table below.

Page 14: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

5

Table 2.1

Project Components No. Component Name Description

A

ICT INFRASTRUCTURE

(EUR 42.036 million)

A.1 - Optical fibre infrastructure execution works;

A.2 - Monitoring and evaluation of impacts and control and supervision of optical fibre

works; A.3 - Establishment of a National Data Centre.

B

ICT APPLICATIONS AND

SERVICES

(EUR 8.258 million)

B.1 - Establishment of an Emergency Warning System (EWS); B.2 - Establishment of a standard e-Government platform;

B.3 - Establishment of an e-Post platform.

C INSTITUTIONAL

SUPPORT AND

CAPACITY BUILDING

(EUR 6.911 million)

C.1 - Studies;

C.2 - Technical assistance to the Post and Electronic Communications Regulatory Authority (ARPCE) and the Congolese Information and Communication Agency

(ACTIC);

C.3 - Support to the Congolese National Institute for the Blind (INAC) and the Brazzaville Institute for Young Deaf People (IJSB);

C.4 - Support to Marien Ngouabi University;

C.5 - Support for women’s empowerment and development of indigenous people; C.6 - Support for the promotion of vocational training.

D

PROJECT

MANAGEMENT

(EUR 3.185 million)

D.1 - Staff of the PCU/ CAB-Congo;

D.2 - Sundry expenses;

D.3 - Technical accounting and financial audits.

2.2. Technical Solutions Adopted and Alternatives Explored

2.2.1. This project involves the installation and commissioning of 550 kilometres of optical fibre

cables, also comprising active equipment as well as power and cooling systems. It comprises two

sections, namely Ouesso-Souanké-Ntam (Cameroonian border) and Ouesso-Pokola-Bomassa (CAR

border) located in Sangha Region. These sections are part of the critical links of the national optical

fibre backbone (with terminals to neighbouring countries) that Congo intends to rapidly extend to 3

600 kilometres of optical fibre by end-2017 within the framework of the 3rd phase of the National

Coverage Plan (PCN).

2.2.2. Currently, there are two main technical alternatives for the deployment of optical fibre:

satellite or microwave links. The use of satellite links suffers from the combined effect of high access

cost and service quality that is far below that offered by optical fibre, not to mention the capacity

limitations inherent in the technologies used (even the latest). Even with the development of new

satellite facilities (for instance O3b) using low orbit satellites, the cost difference is significant. In

fact, satellite remains a redundancy technology, allowing operators to compensate for the

unavailability (especially due to technical damage) of optical fibre, but at operating costs two to ten

times higher than the latter. In short, satellite is not a sustainable alternative compared to optical fibre.

2.2.3. Microwave links allow for the extension of broadband service coverage, particularly to

underserved areas. However, though useful for point-to-point traffic (connection of base stations and

collection networks), they cannot carry the huge amount of data expected to be transmitted through

an optical fibre backbone. The migration of mobile operators in Congo to 3G and even 4G in the near

future will lead to a significant increase in the level of Internet access and the bandwidth required. To

this end, optical fibre is the only option that meets all these requirements (particularly to serve as

support for the potential international traffic of neighbouring countries).

2.2.4. Furthermore, it should be noted that, based on technical studies conducted, the manual laying

of optical fibre cables (as opposed to the mechanical method) was selected for this project. In fact,

this option (despite its slightly higher cost compared with the mechanical method) induces beneficial

Page 15: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

6

effects in terms of revenue generation for the population concerned and indirect support under the

project’s awareness component.

Table 2.2

Alternative Solutions Explored and Reasons for Rejection

Alternative Solution Brief Description Reason for Rejection

Mechanized laying of

optical fibre cables

Using slicers in digging ducts

along the two sections

identified in this project.

Quality risks related to the non-mastery of the

various reliefs concerned, reason for which this

method would not be easy to use. In addition,

manual laying generates income for labour from the

localities crossed, making the project favourable to

local residents.

Supply of dark fibre

(without active

equipment)

In this case, it means

supplying only optical fibre

cables without the

transmission equipment.

Solution chosen by Congo Télécom because it

would be operational from the first day of

commissioning of the installed links.

2.3 Project Type

2.3.1. The AfDB loan will help to finance most of the project with the exception of Components B

and C (ICT Applications and Services and Institutional Support and Capacity Building) which will

be financed with national counterpart contributions, excluding the component related to studies. The

investments to be financed are specifically defined. Therefore, the loan was considered appropriate

as an instrument for Bank intervention in the project. As comparison, World Bank interventions in

the ICT sector in Congo are funded through this type of operation (investment projects).

2.4 Estimated Project Cost and Financing Arrangements

2.4.1 The project cost net of taxes and customs duties amounts to EUR 66.555 million (UA 52.406

million). The provision for physical contingencies is 7% of the base cost. The provision for price

escalation is equal to 3% of the base cost plus physical contingencies. This cost was estimated on the

basis of feasibility studies carried out, discussions with other partners and similar contracts recently

implemented or being implemented by Congo Télécom.

2.4.2 The national counterpart contribution will be used to finance the “ICT Applications and

Services” component as well as part of the institutional support envisaged under the project in order

to establish a solid base for ICT development in Congo. In fact, the digital economy can only develop

with the advent of analogue supplements based on the strengthening of an appropriate legal,

regulatory and fiscal framework, enabling economic operators to take advantage of ICT, knowledge

building through the implementation of planned activities to popularize ICT for the benefit of the

general public, particularly vulnerable groups (women, visually impaired persons, hearing-impaired

persons, etc.) and, lastly, the improvement of digital governance that strengthens the accountability

of institutions to the Congolese people.

The summary of estimated project cost by component is presented in the table below:

Page 16: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

7

Table 2.3

Summary of estimated project cost by component

Components EUR Million UA Million

F.E. L.C. Total F.E. L.C. Total

A. OPTICAL FIBRE INFRASTRUCTURE 33.629 8.407 42.036 26.479 6.620 33.099

B. ICT APPLICATIONS AND SERVICES 6.607 1.652 8.259 5.202 1.301 6.503

C. INSTITUTIONAL SUPPORT AND

CAPACITY BUILDING 5.529 1.382 6.911 4.353 1.088 5.442

D. PROJECT MANAGEMENT 2.548 637 3.185 2.006 502 2.508

BASE COST 48.312 12.078 60.390 38.041 9.510 47.551

Physical Contingencies (7%) 3.382 845 4.227 2.663 666 3.329

Price Escalation (3%) 1.551 388 1.939 1.221 305 1.526

TOTAL 53.244 13.311 66.555 41.925 10.481 52.406

The summary of estimated project cost by expenditure category is given in the table below:

Table 2.4

Summary of estimated project cost by expenditure category

Expenditure Categories EUR Million UA Million

F.E. L.C. Total F.E. L.C. Total

A. GOODS 2.982 745 3.727 2.348 587 2.935

B. WORKS 33.595 8.399 41.994 26.453 6.613 33.066

C. SERVICES 8.917 2.229 11.147 7.022 1.755 8.777

D. OPERATION 2.257 564 2.822 1.778 444 2.222

E. MISCELLANEOUS 560 140 700 441 110 551

BASE COST 48.312 12.078 60.390 38.041 9.510 47.551

Physical Contingencies (7%) 3.382 845 4.227 2.663 666 3.329

Price Escalation (3%) 1.551 388 1.939 1.221 305 1.526

TOTAL 53.244 13.311 66.555 41.925 10.481 52.406

2.4.3 The project will be financed by the Bank Group and the national counterpart in accordance

with the financing plan below. The Bank Group will provide an AfDB loan of UA 40.978 million,

representing 78.2% of the project cost. The provisions justifying this level of counterpart financing

under the Policy on Expenditure Eligible for Bank Group Financing are detailed in Appendix II.

Table 2.5

Summary of estimated project cost by source of financing

Sources of Financing EUR Million UA Million

Percentage F.E. L.C. Total F.E. L.C. Total

AfDB 41.633 10.408 52.042 32.782 8.196 40.978 78.2%

Government of Congo 11.611 2.903 -14 514 9.143 2.286 11.428 21.8%

TOTAL 53.244 13.311 66.555 41.925 10.481 52.406 100%

Table 2.6

Summary of project components by source of financing (EUR million)

Components AfDB Government of Congo Total

Component A: OF Infrastructure 46.328 0.000 46.328

Component B: ICT Applications and Services 0.000 9.102 9.102

Component C: Institutional Support and Capacity Building 2.204 5.412 7.616

Component D: Project Management 3.510 0.000 3.510

TOTAL 52.042 -14 514 66.555

Page 17: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

8

2.4.4 The expenditure schedule (in UA million) by source of financing is shown in the table below: Table 2.7

Expenditure schedule by source of financing (UA million)

Source of Financing 15% 20% 35% 30% 100%

2017 2018 2019 2020 Total

AfDB 7.083 9.444 16.527 14.166 47.220

Government of Congo 1.975 2.634 4.609 3.951 13.169

BASE COST 9.058 12.078 21.136 18.117 60.390

Physical Contingencies (7%) 634 845 1.480 1.268 4.227

Price Escalation (3%) 291 388 678 582 1.939

TOTAL 9.983 13.311 23.294 19.967 66.555

2.5 Project Area and Beneficiaries

2.5.1 Project Area: This is a nationwide project with a regional focus. Five hundred and fifty

kilometres of optical fibre will be laid along the following roads: (i) Ouesso-Sembé-Souanké-Ntam

(Cameroonian border); and (ii) Ouesso-Pokola-Bomassa (CAR border). These two roads are located

in the Sangha Region. In addition to the local residents of these areas, the project will impact the

entire population of Congo and ultimately the population of the sub-region through the expected

reduction in the cost of ICT services following the integration of the telecommunications systems of

Central African countries. Moreover, the deployment of e-Post and the Emergency Warning System

(EWS) will help to improve the socio-economic inclusion of the rural population nationwide,

especially the population in the country’s interior, through access to money transfer services and

climate-related information in order to strengthen their resilience to natural hazards.

2.5.2 Direct Project Beneficiaries: the entire population of Congo and even the sub-region will

be the beneficiaries of the extended optical fibre project area. In fact, once the links are built to

connect neighbouring countries to the Congo optical fibre backbone, the population of Congo and

especially that of CAR stand to benefit. The entire Congolese population will benefit from ICT

applications and services through the use of the e-Government platform, the Emergency Warning

System and the e-Post module. In addition, at least 10 000 women are expected to be initiated in the

use of ICT tools each year. Lastly, graduate training scholarships could be awarded to 24 students

(2/3 of them female students) in the industrial sections of government technical high schools in order

to make the industrial sector more attractive. The country’s private operators (telephone companies,

banks, etc.) will also benefit from project achievements, as they would be able to easily extend their

services to all localities served by optical fibre facilities.

2.6 Participatory Approach for Project Identification, Design and Implementation, including

Active Private Sector Participation

2.6.1 The participatory approach was adopted during the preliminary studies, the environmental

and social assessment, and the preparation and appraisal missions. These consultations contributed to

better project design both in terms of component formulation and implementation arrangements.

2.6.2 During the identification, preparation and appraisal missions, all stakeholders were

consulted both in Government services (MPT, MTE, MPFIFD, etc.) and the private sector (MTN

Congo, Airtel Congo, Azur, etc.). Discussions with these entities were helpful, for example, in

defining the content of the technical assistance to be offered to ARPCE, under the “Institutional

Support and Capacity Building” component to ensure minimum conditions for the exercise of

competition in the sector by ultimately reducing the high tax burden, in particular.

2.6.3 As part of environmental and social assessment, public consultations were organized on the

Ouesso-Souanké-Ntam and Ouesso-Pokola-Bomassa road sections from 5 to 18 October 2013.

Page 18: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

9

Community meetings were organized in each of the villages concerned by the optical fibre alignment.

The meeting were attended, in most cases, by village chiefs and notables. The people expressed their

main concerns and expectations, as well as their support for the project in a development perspective.

The minutes of these meetings were prepared and may be consulted at PCU-CAB.

2.6.4 Generally, MPT will prepare and implement a communication plan for the information,

education and social mobilization of local communities, and public and private operators in the sector

during the implementation phase.

2.7 Bank Group Experience and Lessons Reflected in Project Design

2.7.1 As of 31 January 2016, the Bank’s portfolio in Congo comprised 14 operations for a total

net commitment of UA 158.91 million, that is 9 national operations for a volume of financing of UA

53.43 million and 5 regional operations for a total amount of UA 105.39 million. It included 8 public

investment operations, 3 institutional support operations, and 3 studies whose sector breakdown

shows the predominance of the infrastructure sector which represents 85% of current commitments.

The portfolio’s cumulative disbursement rate is 40.36% with an average age of 4 years. The

evaluation of portfolio performance during the last review was, on the whole, deemed satisfactory

with a rating of 2.40.

2.7.2 The major constraints and problems encountered, especially in the implementation of

infrastructure projects, include: (i) the slow pace of procedures for the procurement of goods, works

and services; (ii) the delayed mobilization of national counterpart funding; and (iii) the financing of

compensation.

2.7.3 In view of the foregoing, the Bank will, during project implementation, capitalize on the

following measures already taken or planned: (i) use of the advance contracting (AC) method to

minimize procurement delays; and (ii) steps taken by MPT and MEFPPPI to ensure the inclusion of

national counterpart financing in the budgets of the various fiscal years throughout the project as from

2017.

2.7.4 Lastly, this operation draws on the lessons learned from the ongoing implementation of

Congo’s CSP (2013-2017). Hence, the ICT sector-related challenges in the country were anticipated

by taking into consideration the strengthening of the regulatory framework. It cannot be denied that

this project is highly inclusive by virtue of its diverse components.

2.8 Key Performance Indicators

2.8.1 The key performance indicators and expected project outputs are presented in the logical

framework along with timeframes. The core sector indicators (CSIs) on which the project will focus

are: (i) the percentage of ICT-related jobs in the private sector; (ii) the number of additional

international connections installed; (iii) the penetration of Internet services; (iv) the price of one Mbps

to Europe; (v) the number of people benefiting from online government (informational and

transactional) services; (vi) the number of students benefiting from the business incubator; (vii) the

number of beneficiaries of e-Post; (viii) the number of people benefiting from solar electric terminal

systems; (ix) the number of indigenous people benefiting from the community radio for awareness

campaigns; (x) the number of women with access to training programmes (ICT, entrepreneurship,

etc.); and (xi) institutional support and capacity building for the ICT sector.

2.8.2 ARPCE’s ICT observer will be responsible for data collection and analysis. He may be

supported by Congo’s National Institute of Statistics (NIS). In that case, NIS, which is familiar with

this type of exercise, may: (i) establish the baseline situation of these indicators at project start-up;

Page 19: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

10

(ii) conduct an impact assessment at project completion; and (iii) continue the assessment after the

commissioning of the planned connections.

2.8.3 To ensure that all these operations are implemented on time, in addition to these outcome

indicators, implementation performance indicators have been established in line with the Bank’s

institutional performance indicators. They include: (i) the effectiveness timeframe; (ii) the timeframe

for fulfilling conditions precedent to first disbursement; (iii) the procurement timeframe; and (iv)

disbursement trends in relation to the expenditure schedule. These indicators will be monitored during

supervision missions and the day-to-day management of the project.

III. PROJECT FEASIBILITY

3.1. Economic and Financial Performance

A study of the financial and economic and rate of return was carried out for the following components:

(i) implementation of optical fibre infrastructure;

(ii) establishment of an Emergency Warning System (EWS);

(iii) establishment of online administrative services; and

(iv) establishment of an e-Post platform (postal information system, and development of

an electronic money transfer service and digital community centres).

The macro-economic assumptions are based on a 3% inflation rate and a stable CFAF/Euro exchange

rate. The interest rate on the AfDB loan is estimated at 1.17%. The financial discount rate is 2% and

the economic discount rate adopted is 10%.

Based on these assumptions, the main outcomes are listed below.

Table 3.1

Economic and financial assessment

FIRR, FNPV: 18.88%; EUR 143.42 million at 2%

EIRR, ENPV 28.63%; EUR 97 million at 10%

3.1.1 The economic lifespan of the project is 15 years. Based on the assumptions used, the FIRR

is 18.88 % and the EIRR 28.63%. The economic and financial analysis shows that the project is

economically and financially feasible.

Moreover, a project sensitivity test was conducted based on the following three parameters: (i) a 10%

increase in investment costs; (ii) 10% drop in income; and (iii) a combination of the two preceding

criteria. The outcomes of the sensitivity analysis shown in the table below (the details of which are

included in Technical Annex B.7) indicate slight variations which, in no way, affect the financial and

economic viability of the project.

Page 20: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

11

Table 3.2

Sensitivity Test

Assumptions

FNPV

(EUR Million)

ENPV

(EUR Million)

FIRR (%)

EIRR (%)

Baseline scenario

143.42

97.340

18.8

28.63

A1:10% increase in investment costs

136.41

83.91

17.28

23.60

A2: 10% drop in income

122.07

82.99

17.11

26.48

A3: Scenarios 1 and 2

115.06

69.56

15.56

21.71

3.2. Environmental and Social Impact

3.2.1. Environmental aspect: the project has been placed under Environmental Category 2, in

accordance with the Bank’s Integrated Safeguards System requirements. The Environmental and

Social Impact Assessment and the Environmental and Social Management Plan (ESMP) were

prepared in July 2014 and validated by the Ministry of Tourism and Environment (MTE). They have

been issued an environmental acceptance certificate. Optical fibre cables will be deployed along roads

for which a Public Interest Statement (DUP) has been issued.

3.2.2. The project environment is regional (Sangha and Brazzaville) on account of the deployment

links selected and the equipment installation sites. The optical fibre cables and chambers will be laid

strictly following the right-of-way of the roads selected. The Ouesso-Ntam road already has ducts.

Development will therefore be the main activity. The Ouesso-Bomassa road will require trenching

and duct-laying civil engineering works prior to the deployment of optical fibre cables. This

equipment will be set up within existing entities and buildings, and the National Data Centre within

Kintélé University in Brazzaville.

3.2.3. The impacts expected to be generated by civil engineering works on the Ouesso-Pokola-

Bomassa road are: (i) risk of obstruction of access roads used by local residents due to lack of road

signs and trenches that are not covered to ease crossing; (ii) compensation by repairing 4 fence walls

at Pokola and Ouesso; (iii) obstruction of access roads by various deposits; and (iv) risk of road

accidents involving workers improperly positioned on the road. The deployment of optical fibre

cables by portage on the two roads will generate occasional but very short-lived sound nuisances

(compressor for compressed air). The expected impact on the natural and physical environment will

be poor management of wastes (small pieces of ducts and fibre, abandoned empty wire strands,

rejected cement mortar laitance, packaging, etc.).

3.2.4. These identified impacts will be offset for the most part by appropriate measures to enable

the project’s environmental integration. PCU/CAB will be responsible for monitoring the mitigation

measures recommended during project implementation through the Environmental and Social

Management Plan (ESMP). It will be backed by a Contracting Authority Assistance (CAA) mission.

The related budget is CFAF 260 million, that is about EUR 396 500.

3.2.5. The "ICT Applications and Services" component will not generate any adverse impacts on

the environment. It allows for the economy of movement and, as a result, reduces sound nuisances

and traffic accidents and greenhouse gas emissions. Hence, the positive impacts will be extensive, as

reflected, among other things, in: (i) the creation of direct jobs related to equipment operation and (ii)

the improved living conditions of local residents of project areas and across the country, thanks to

increased connectivity and access to information of all kinds.

3.2.6. Climate Change: the project will help to reduce the carbon footprint of the electricity sector

in Congo by providing solar panels producing 153 000 kWh per year for 5 women’s empowerment

Page 21: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

12

centres, 5 digital community centres and the Sembé community radio. It will prevent the emission of

68.5 tonnes of CO2 per year. ICT services will also substantially reduce greenhouse gas emissions.

Indeed, the implementation of e-Post projects will lead to the substitution of transfers with data

transmissions, thus eliminating the movement of people estimated at 500 000 km/year. These avoided

movements therefore represent 92.5 tonnes of CO2 per year. Hence, a total emission of 161 tonnes

of CO2 will be avoided.

3.2.7. Social Impacts: the extended project impact area covers the entire population of Congo.

Moreover, the project’s positive externalities will benefit the entire population of Congo and the sub-

region. The main project positive impacts will be: (i) improved living conditions of rural residents

with the building of the capacity of women’s empowerment centres and CDCs in the project area; (ii)

the opening up of the project area; (iii) the creation of employment opportunities and improvement

of incomes; and (vi) improved functioning of community infrastructure. Contractor(s) will be

encouraged to recruit local labour for trenching, laying of ducts and optical fibre cables, etc. Improved

access to ICT will also help to reduce exclusion between the various communities within the

population and to strengthen social cohesion.

3.2.8. Involuntary Resettlement: there will be no resettlement under this project.

3.2.9. Gender and Women-specific Activities: Congo has a national gender policy and an Action

Plan for implementing the policy. The second strategic thrust of the Plan provides, among other

things, for improved access to information and communication technologies (ICT) which can

contribute to promoting women’s economic activities as well as improving their access to production

support services. To implement its national gender policy, the Government of Congo has a Ministry

of Women’s Empowerment and Integration in Development which comprises three general

directorates, namely: (i) the General Directorate of Women’s Empowerment (DGPF); the General

Directorate of the Centre for Research, Information and Documentation on Women; and (iii) the

General Directorate of Women’s Integration in Development (DGIFD). The Ministry also has

women’s empowerment centres (in Brazzaville, Kinkala, Djambala and Mayama) which are places

for reception, support, discussions and solidarity between all women. These women’s empowerment

centres are also forums for cultural activities, information and sensitization on women’s rights,

support and anonymous and free counselling on all issues relating to women’s day-to-day life.

3.2.10. The project provides for specific women’s empowerment support activities, namely (i)

procurement and installation of and training in digital equipment for the virtual library of the Centre

for Research, Information and Documentation on Women (CRIDF); (ii) procurement of computer

hardware (computers, multipurpose printers, inverters, etc.) for women’s empowerment centres; (iii)

support for the design and implementation of training programmes (ICT, entrepreneurship, etc.) in

women’s empowerment centres for 10 000 women by 2020; (iv) deployment of solar and computer

equipment for the five operational women’s empowerment centres; and (v) award of scholarships to

24 students (2/3 of them female students) in industrial sections of government technical high schools.

IV. PROJECT IMPLEMENTATION

4.1. Implementation Arrangements

4.1.1. The project executing agency is the Ministry of Posts and Telecommunications (MPT) acting

through the CAB-Congo Project Coordination Unit (PCU/CAB-Congo) set up in 2011 with Bank and

World Bank financing. This Unit currently comprises a Coordinator, an Environmental Officer, an

Administrative and Financial Officer (AFO), an Accountant, an Accounting Assistant, an Internal

Auditor, a Procurement Specialist (PS), an Administrative Assistant and a Monitoring and Evaluation

Specialist. It has a procedures manual which governs its operation. The Unit has the necessary

experience to conduct the sector’s operations. To implement this project, the PCU staff will be

Page 22: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

13

reinforced with a technical expert (an ICT engineer) whose CV will be submitted to the Bank for non-

objection opinion. Staff performance will be evaluated regularly on a yearly basis.

4.1.2. Specifically, the Unit will be responsible for the technical monitoring of project

implementation. In this regard, it will: (i) ensure that the Government’s commitments are honoured;

(ii) conduct monitoring and evaluation; (iii) ensure compliance with the project implementation

schedule; (iv) prepare semi-annual and annual project progress reports; (v) prepare counterpart

budgets and ensure their timely availability; (vii) ensure project financial management (verification

of detailed accounts, transmission of direct payment requests to the Bank, etc.); (viii) ensure timely

submission of project accounting and financial audit reports; and (ix) prepare the Borrower’s

completion report for submission to the Bank.

4.2. Procurement Arrangements

4.2.1. All procurement of goods and works by international competitive bidding (ICB) and

consultancy services financed by the Bank will be in accordance with the Procurement Policy on

Bank Group-financed Operations dated October 2015, using appropriate Bank standard bidding

documents (SBDs). The procurement of goods and works by local competitive bidding (LCB) will

be conducted in accordance with the national procurement legislation, using the country’s standard

bidding documents, as well as with the provisions set forth in the financing agreement.

4.2.2. MPT, acting through UCP/CAB, will be responsible for managing project-related

procurement. UCP/CAB was set up in 2011 as part of the CAB project financed by the World Bank.

This project plans to recruit a Procurement Assistant to strengthen the procurement team in place.

4.2.3. A procurement plan (PP) was validated by the Bank during the appraisal mission and will

be regularly updated during the project implementation phase. The procurement arrangements are

detailed in Annex B.5.

4.2.4. The Government has expressed the wish to use advance procurement action (APA) to

accelerate contract award and thus ensure rapid project implementation. In that regard, the

Government is preparing to submit a request to the Bank for that purpose, which would enable it to

use the advance contracting arrangement for optical fibre infrastructure works, control and

monitoring. The Bank will examine the request and notify the Government of its decision.

4.2.5. Regarding procurement, despite a number of gaps related to the Bank's fiduciary

requirements, the procurement procedures for the local competitive bidding (NCB) process are

deemed largely compliant. In view of the findings of Bank assessment and Government's efforts,

plans have been made to propose the use of national procedures for local competitive bidding (NCB)

to the Government. A letter of agreement to be signed with the Government will identify weaknesses

which should be remedied. As usual, the specific measures for mitigating the governance-related risks

of this project include: (i) recruitment of an independent financial audit firm to ensure that funds are

used rationally and for their intended purposes; (ii) prior review and approval by the Bank of all

procurement activities for the project; and (iii) the use of direct payment disbursement method to

transfer project funds directly to contractors and service providers.

4.3. Financial Management and Disbursement Arrangements

4.3.1. The fiduciary risk for CAB project financial management is deemed moderate. The financial

management arrangements within the CAB Project Coordination Unit at the Ministry of Posts and

Telecommunications meet the Bank’s minimum requirements defined under the policy on the

"Financial Management of Projects Financed by the African Development Bank", February 2014

edition. The PCU, which was established in 2011, recently acquired experience from the

Page 23: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

14

implementation of the first phase of the World Bank-funded CAB project. Pursuant to the donor

harmonization principle, this Unit was selected during this evaluation, the results of which will be

used to build its capacity to implement projects financed by donors and implemented by MPT. These

projects are expected to contribute to improving CAB project financial management through the

recommended measures in the financial management action plan presented in Annex B.6. These

measures will help to mitigate the fiduciary risk by reducing it to a lower level, if possible. Thus, by

reinforcing the financial management arrangements already in place, the implementation of these

measures will help to continue to provide, with reasonable assurance, reliable financial information

and to safeguard project assets, in accordance with Bank policy.

4.3.2. The Ministry of Posts and Telecommunications, acting through PCU placed under its

supervisory authority, will be the project executing agency. The PCU will be responsible for the

financial management of all project components, and will carry out all the controls required to ensure:

(i) proper, efficient and judicious use of project funds; (ii) the preparation of periodic, accurate,

reliable and timely financial reports; and (iii) the safeguard of project assets. This entity has proven

capacity and appropriate tools for CAB project financial management, and will be reinforced with

local technical assistance (individual consultant) responsible for project accounting, under the

supervision of an Administrative and Financial Officer. To ensure rapid project start and effective

implementation, the CAB project team will comprise the current PCU financial staff in compliance

with the decision establishing the PCU. The capacity of the team, which received financial

management and disbursement training during the quarterly portfolio review (conducted in June

2015), will be built during subsequent fiduciary clinic phases scheduled for 2016 in Congo.

4.3.3. Audit Arrangements: CAB projects financed with Loan resources will be audited annually

by an independent external audit firm recruited on a competitive basis and in accordance with the

Bank’s standard Terms of Reference (ToR). The PCU will be responsible for recruiting the external

auditor and will have to seek the Bank’s prior opinions. Audits will be conducted yearly throughout

the project, including the closing audit. The initial project audit could cover an 18-month financial

year from the date of loan effectiveness or the date of first disbursement. The external auditor will be

recruited by the PCU and audit costs will be borne by the project. The ToR of the external auditor

will be tailored to, and harmonized with, those of the World Bank to account for project specificities

and validated during the negotiation for the recruitment of an independent firm with experience in the

audit of Bank-financed projects. Audits will be conducted in accordance with ISA/ISSAI international

standards. The financial statements audited by the independent firm will be forwarded to the Bank

not later than six months following the end of the financial year concerned (see table for frequency).

4.3.4. Arrangements Relating to Disbursement Method: the disbursement of loan resources will

be in accordance with the Bank’s Disbursement Handbook, upon loan agreement effectiveness and

fulfilment of conditions precedent to first disbursement. Generally, three methods have been adopted

for fund disbursement at the Bank, namely: (i) the direct payment method; (ii) the working capital or

special account method; and (iii) the reimbursement method. The disbursement of counterpart

resources will be in accordance with national procedures which provide for the opening of an account

for external financing.

4.4. Monitoring

4.4.1. The Congo CAB Project Coordination Unit (PCU/CAB-Congo) will monitor the

implementation of the various project components. Joint supervision missions (donor and

Government) and inter-donor coordination meetings will also report on the performance of the project

in terms of project physical and financial outputs.

4.4.2. To strengthen the system in place, it was agreed with the Congolese authorities that a Project

Page 24: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

15

Steering Committee (COPIL) placed under the supervisory authority of MPT will be set up to support

the Project Coordination Unit in setting the broad guidelines of the CAB project in the PCN, issuing

the necessary directives and recommendations to improve the project implementation strategy and

methods as well as approving the project documents and deliverables. The composition of this

committee will be modified to reflect the participation of all project stakeholders.

4.4.3. Concerning the assessment of the level of achievement of development objectives, a socio-

economic impact monitoring and evaluation mechanism will be established and implemented by

PCU/CAB. Project environmental and social impacts will be monitored directly by the PCU/CAB.

Regarding the implementation of the “ICT Applications and Services” component, a technical audit

of each planned project achievement will be conducted to ensure compliance with the initial

specifications, given that the implementation of the optical fibre infrastructure will be entrusted to a

separate manager who will supervise the scheduled works on behalf of the beneficiary.

Table 4.1

Project Monitoring and Supervision

Deadline Phase Process Feedback Loop

Q3 -2016 Project Launch Field Mission Progress Reports

Q4 – 2016 Project Review –

Procurement

Field/Supervision

Mission

Progress reports/Aide-

memoire

Q3&Q4-2017 OF Infrastructure Works

& National Data Centre

Field/Supervision

Mission

Progress reports /Aide-

memoire

Q1&Q2&Q3&Q6-2017-

2018-2019

OF Infrastructure Works

& National Data Centre

Field/Supervision

Mission

Progress reports /Aide-

memoire

Q3 -2020 Warranty Period & First

Year of Operations

Field Mission

Progress reports /Aide-

memoire

Project Completion

Report

4.5. Governance

4.5.1 The governance risks in the areas of procurement and financial management were analysed

during project appraisal. On the whole, the implementation of the public finance modernization plan

will mitigate these risks by enhancing public expenditure efficiency in the ICT sector. Moreover, the

Bank, jointly with the World Bank and the European Union, carried out a review of public expenditure

management and financial accountability in 2014, the recommendations of which will be the subject

of regular dialogue in order to strengthen public expenditure efficiency, notably in the ICT sector.

4.5.2 In the procurement process, especially as concerns international bid invitations, the

governance-related risk would be mitigated by the Bank’s strict enforcement of its relevant rules and

procedures, and the conduct of ex-ante reviews. The Bank's supervision missions and independent

technical and financial audits will ensure consistency between the specifications, actual services

provided and work performed, disbursements and the loan agreement.

4.5.3. In the ICT sectors, the market has been liberalized, particularly with the authorization of

mobile telephone operators to provide data services (Airtel and MTN launched their 3G licences in

2011 and 2013 respectively). This should help to support the use of wholesale market capabilities.

For its part, the Posts and Electronic Communications Regulatory Authority (ARPCE) guarantees

competition in the telecommunications market. It should, however, be mentioned that the difficulties

faced by operators are constraints on access to the broadband internet wholesale market owing to the

rates charged for national and international connectivity collocation, in addition to the appalling

taxation system applicable to the sector.

Page 25: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

16

4.5.4 This explains why this operation includes the development of an economic model for costing

access to national and international connectivity. That will be beneficial to ARPCE since it will enable

the entity to sift through the catalogue of prices charged by the traditional operator and thus ensure

the implementation of the "open access" principle guaranteed by regulating the sector for all private

operators with licences. In addition, the project also includes a study on the assessment of the ICT

sector taxation model in order to carry out an exhaustive audit of all the taxes and royalties paid by

the operators and conduct a comparative study aimed at proposing concrete and viable alternatives to

the authorities for an accelerated ICT development in Congo.

4.6. Sustainability

4.6.1 The national optical fibre backbone maintenance management in Congo devolves on MPT

which delegates the function to the traditional operator, Congo Télécom, except for local urban loops

belonging to private operators. Congo Télécom will be responsible for programming and

implementing optical fibre maintenance on a force account basis. Indeed, within Congo Télécom,

there is a technical directorate responsible for network maintenance and servicing. It is in charge of

the maintenance of the national optical fibre network and has branches in Congo Télécom regional

representations. Maintenance is financed with Congo Télécom’s own resources. The PCN managed

by the General Directorate of Major Works also assists the traditional operator in installing some

segments.

4.6.2 However, the revenue generated by the project focus areas is largely sufficient to cover the

cost of equipment (fibre and assets) maintenance during the lifespan of the various components. The

same is true for e-Post business applications that will be procured by SOPECO under this project. As

part of its dialogue with the country, the Bank will ensure the actual availability of resources for the

maintenance and upgrade of the systems (physical and software) established.

4.7. Risk Management

4.7.1. Risks that may hinder the achievement of results include: (i) Congolese party’s non-

compliance with undertakings relating to the laying of optical fibre cables; (ii) failure to produce an

impact on prices; (iii) premature degradation of the optical fibre due to lack of maintenance; (iv) lack

of maintenance and upgrade of the various applications installed; and (v) social tension resulting from

the electoral process.

4.7.2. Mitigation Measures: (i) The Government's commitment to implement the guidelines of

the International Telecommunication Union (ITU); (ii) Bank support in the form of technical

assistance to enable the necessary reform of the ICT sector; (iii) commitment by Congo Télécom to

allocate a substantial portion of the resources generated by the new connections for the maintenance

of the road links and more generally the national backbone; and (iv) commitment by SOPECO, in

particular, to further invest in the extension of the reach of its existing e-post products and services

to ensure coverage of the entire country; and (v) the rest of the March 2016 presidential election

process bodes well for an end to political tension as the opposition, which rejected the results of the

election, has, nevertheless, called for inclusive dialogue.

4.7.3. Risks that may hinder the achievement of outputs are: (i) late release of counterpart

funds; (ii) the slow pace and lack of transparency in the procurement process; (iii) escalation of the

cost of works; and (iv) non-compliance with technical and functional specifications in the context of

the various applications envisaged in the project.

4.7.4. Mitigation Measures: (i) sustained dialogue with the Ministry in charge of finance as part

of the preparation of provisional appropriation acts throughout project implementation; (ii) expand

competition by taking advantage of the size of works contracts; (iii) take physical contingencies into

account in the project financing plan; (iv) strengthen the PCU by including a technical expert in

charge of project supervision, among other things.

Page 26: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

17

4.8. Knowledge Building

4.8.1. The project will provide an opportunity to improve knowledge in the area of national ICT

infrastructure. To better derive lessons from this project, a monitoring and evaluation mechanism will

be set up by the Unit. Establishing key impact indicators prior to the project start-up and conducting

impact assessment at the end of the project will help to provide useful information on the project

outcomes and impacts. The lessons, experiences and knowledge that will thus be derived from

implementing this project will be managed from UCP/CAB and disseminated through annual reports

and the Bank's website. The knowledge will be very useful, among others, for implementing the next

CAB project.

V. LEGAL FRAMEWORK

5.1. Legal Instrument

The project will be financed through an AfDB loan granted to the Republic of Congo. A Loan

Agreement will be signed between the Republic of Congo and the African Development Bank.

5.2. Conditions Associated with AfDB Intervention

5.2.1. Conditions Precedent to Loan Effectiveness

Effectiveness of the Loan Agreement shall be subject to fulfilment by the Borrower, to the Bank’s

satisfaction, of the conditions set out in Section 12.01 of the General Conditions Applicable to Loan

Agreements and Bank Guarantee Agreements (sovereign entities).

5.2.2. Conditions Precedent to First Disbursement of AfDB Loan

In addition to the effectiveness of this Agreement, the first disbursement of AfDB loan resources shall

be subject to fulfilment by the Borrower, to the Bank’s satisfaction, of the following conditions:

(i) Provide the Bank with evidence of opening a special account in a bank acceptable to

the Bank intended exclusively to receive the counterpart funds for financing some

project-related activities;

(ii) Provide the Bank with evidence of opening a special account, in the name of the

Project, and in a bank acceptableto the Bank, to receive the loan resources.

5.2.3. Other Conditions

The Borrower shall, not later than 30 June of each year, also provide evidence of inclusion of the

amount of the Government’s project counterpart funding in the Appropriation Act of the following

fiscal year.

5.2.4. Undertakings

The Borrower undertakes, to the Bank’s satisfaction, to:

(i) Open discussions with the Bank on practical arrangements for the effective

implementation of "open access" to the optical fibre planned under the project within six

(6) months following the first disbursement of loan resources;

(ii) Implement the project and the ESMP, and ensure their implementation by its

contractors, in accordance with: (a) Bank rules and procedures; (b) national law; and

(c) the recommendations, provisions and procedures contained in the ESMP;

(iii) Provide the Bank with half-yearly reports on the implementation of the ESMP,

including, as appropriate, any weaknesses and corrective measures initiated or

envisaged.

Page 27: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

18

VI. RECOMMENDATION

Management recommends that the Board of Directors approve the proposal to grant a EUR 52.041

million ADB loan to the Republic of Congo to finance the Central Africa Optical Fibre Backbone

Project (CAB) – Congo Component, under the conditions set forth in this report.

Page 28: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

I

ANNEX I

DESCRIPTION OF INSTITUTIONAL SUPPORT AND CAPACITY BUILDING

This institutional support operation will focus on strengthening sector governance through support

for structural reform of the sector, notably the reinforcement of its legal and regulatory framework by

the Posts and Electronic Communications Regulatory Authority (ARPCE), building the capacity of

entities that provide assistance to vulnerable people (visually impaired, hearing-impaired persons,

etc.), as well as support for the operationalization of the Congolese Information and Communication

Technology Agency (ACTIC). Furthermore, it will entail providing targeted support for higher and

vocational education, women’s empowerment as well as the development of the indigenous

population. In addition to these measures, there are several studies aimed, among other things, at

preparing the next CAB project which is largely devoted to the development of the application layer

with a view to consolidating the foundations of the digital economy in Congo, and supporting

women’s empowerment. Institutional support will focus on the following four activities:

i- Studies: the objective of this project in Congo is twofold. It is intended to lay the

groundwork, in terms of infrastructure (optical fibre, in particular), for the launch of

the development of an ICT economy and industry in the country. Meanwhile, the

Congolese authorities wanted this initiative to include feasibility studies for a second

CAB project which aims to accelerate the leveraging of the growth and job-creation

sources underlying the ICT sector. Thus, based on the National Data Centre, the

bedrock for the development of e-government in the country and included in this

project, a study should be carried out on the establishment of a Citizen Electronic

Identification System which will enhance the reliability of the official and compulsory,

permanent and continuous registration of events (births, deaths, marriages and

divorces) relating to the status of individuals and their characteristics, from birth to

death, for administrative and legal purposes. This component also includes two major

studies on the establishment of a National ICT School in Congo and the development

of an exhaustive national e-government strategy. It also comprises a study on the

development of mobile financial services available in Congo, particularly to promote

financial inclusion in rural areas.

ii- Technical Assistance for ARPCE: the three studies envisaged in this component are

intended to support the development of the national optical fibre backbone by building

ARPCE’s capacity to contribute to achieving the project’s development objectives

(access to better quality ICT services at lower costs by private operators and, indirectly,

by users wherever they may be across the country). They concern the development of:

(i) an economic model for costing access to national and international connectivity;

(ii) a study on the regulation of the "open access" principle; and (iii) a business model

on the profitability thresholds of optical fibre (OF) deployment in the country.

iii- Support for INAC and IJSB: the project plans to support the Congolese National

Institute for the Blind by: (i) rehabilitating the library and the ICT room; (ii) providing

the library with appropriate furniture and documents; (iii) procuring computer

hardware (computers with appropriate keyboards and equipped with a voice synthesis

software, braille printer and stamping machine); (iv) training computer hardware

maintenance staff; and (v) procuring a vehicle (24-seater bus), with the clear

understanding that operating and maintenance costs will be charged to a budget head

of the Ministry of Education.

It will also support the Brazzaville Institute for Deaf Young People by: (i) rehabilitating the

library and the demutization room; (ii) providing the library with appropriate furniture

Page 29: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

II

and documents (sign language); and (iii) procuring teaching material, computers,

photocopying machines, etc.

iv- Support for Higher and Vocational Education: the project intends to support ICT

development in Marien Ngouabi University (UMNG) by laying the foundations for a

consistent and efficient information system. This requires the following actions to be

undertaken: (i) the establishment of a data processing centre (Mini-Data Centre); (ii)

the development and establishment of application tools (internet portal, online

services, etc.) for administrative staff, students, lecturers, etc.; (iii) the establishment

of a geomatics laboratory (GIS); and (iv) the design of a University Computerization

Master Plan.

The 2008-2017 Ten-year Plan for Reviving and Developing Technical and Vocation Education in

Congo has made provision for improving access to ICT in schools and learning institutions. It is in

this connection that the project has provided for specific vocational training promotion support

activities, namely: (i) support for the development of teaching material in 10 specialties for the

Brazzaville Government Technical High School; (ii) procurement of computer hardware (computers,

multipurpose printers, inverter, etc.) for government technical high schools; and (iii) award of

scholarships to 24 students (2/3 of them female students) in technical high school industrial sections.

v- Support for Women’s Empowerment: the country has made significant progress

with respect to gender equality, at least from the commitments and legislation

standpoints. Congo has ratified all international conventions on women’s rights and

gender equality, notably the Convention on the Elimination of All Forms of

Discrimination Against Women (CEDAW). Article 8 of the country’s Constitution

guarantees equal rights and prohibits all forms of discrimination, including those based

on gender, and stipulates that women have the same rights as men by guaranteeing

women’s representation in all political, elective and administrative offices. Congo has

a national gender policy and an action plan for implementing the policy. In that

connection, the Government of Congo has a Ministry of Women’s Empowerment and

Integration in Development comprising three general directorates, namely: (i) the

General Directorate for Women’s Empowerment (DGPF); (ii) the General Directorate

of the Centre for Research, Information and Documentation on Women; and (iii) the

General Directorate of Women’s Integration in Development (DGIFD). The Ministry

also has women’s empowerment centres (in Brazzaville, Kinkala, Djambala and

Mayama) which are places for reception, support, discussions and solidarity between

all women. These empowerment centres are also forums for cultural activities,

information and sensitization on women’s rights, support and anonymous and free

counselling on all issues relating to women’s day-to-day life. Despite the progress

made, there is still need for much effort. In fact, the United Nations Development

Programme (UNDP) 2014 Human Development Report shows that the gender

inequality index dropped to 0.617 in 2014 against 0.610 in 2013. Regarding education,

there is equal enrolment of girls and boys in primary school, according to a UNESCO

report published in 2014. However, the gender parity index drops drastically from the

second cycle of secondary education, where it is only 37%. Women’s representation

in political, elective and administrative offices is still insufficient. The occupy only 10

out of 68 seats in the Senate (that is 14.7%), 10 out of 139 seats in the National

Assembly (that is 7.2%) and 4 out of 39 positions in Government (that is 10.2%).

There are also wide gender disparities regarding access to economic resources. Only

about 17% of businesses are managed by women. According to the Congolese

Household Survey conducted in 2011, the proportion of women wage earners in the

non-agricultural sector dropped from 48.48% in 2005 to 45.75% in 2011. In this sector,

Page 30: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

III

women are mainly involved in trade in processed products (33.53 %) and, to a very

small extent, in administration (8.91%) and service provision (8.39%). Barely 6.8% of

women have their own bank account, compared with 11.3% for men. To reduce these

inequalities, the Government adopted a National Gender Policy in 2008. An action

plan was designed in 2009 and an observatory for recording and controlling violence

against women and children has been established. The major challenge is to implement

these instruments. The project intends to contribute to improving gender equality

through support for the promotion of women’s empowerment. This is in line with

Thrust 2 of the Gender Policy Implementation Action Plan, namely improving access

to ICT that can contribute to promoting women’s economic activities as well as

improving their access to production support services. Thus, the activities to be carried

out under this project are: (i) procurement and installation of, and training in digital

equipment for the virtual library of the Centre for Research, Information and

Documentation on Women (CRIDF); (ii) procurement of computer hardware

(computers, multipurpose printers, inverters, etc.) for women’s empowerment centres;

(iii) support for the design and implementation of training programmes (ICT,

entrepreneurship, etc.) for women’s empowerment centres; and (iv) deployment of

solar equipment in the 5 operational women’s empowerment centres.

vi- Support for the Development of Indigenous People

One of the local populations’ concerns is the promotion of the identity and traditional value of the

Baka indigenous people living along the Ouesso-Ntam road as the thrust through which the Baka

indigenous people can actively participate in sustainable natural resource management. To that end,

the Sembé Municipal Council plans to build a "Baka cultural village" for which the project includes

a proposal to allocate equipment to operationalize a community radio for Baka culture.

Page 31: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

IV

ANNEX II

RATIONALE FOR THE LEVEL OF COUNTERPART CONTRIBUTION TO AfDB

FINANCING

In Congo, the project will be financed by the Bank Group and the national counterpart contribution.

The Bank Group’s contribution will be an AfDB loan of UA 40.978 million, representing a total of

78.2% of the project cost in the country. The national counterpart contribution is estimated at UA

11.428 million, representing 21.8% of the total project cost in Congo. This amount of counterpart

financing represents the current level of contribution affordable by the country.

The amount of Congo’s counterpart contribution to project financing is UA 11.428 million,

representing 21.8% of the total project cost. The level of the Government’s contribution is less than

the minimum rate of 50% of total project cost for AfDB member countries, as stipulated by Section

4.2.2 of the Policy on Expenditure Eligible for Bank Group Financing. Thus, in accordance with the

provisions of Section 4.2.2 of the above Policy (revised version of 19 March 2008), this annex

presents the analysis which justifies the request for a waiver of the amount of national counterpart

contribution, based on the following four criteria spelt out by the above Bank policy:

the country’s commitment to implement its overall development programme;

the financing allocated by the country to the sector targeted by Bank assistance;

the country’s fiscal situation and debt level;

the upper cost-sharing limit and guidelines laid down in the country financing

parameters.

Country’s Commitment to Implement its Overall Development Programme

By implementing its National Development Programme (PND) 2012-2016, the key objective of

which is to accelerate the industrialization of the economy so as to transform Congo into an emerging

country by 2025, the Government has shown a strong commitment to implement programmes that

contribute to diversified and inclusive growth, and poverty reduction. In line with PND’s priorities,

the authorities have made huge financial efforts to bridge the country’s wide social and infrastructure

gaps. Against this backdrop, an ambitious programme for average annual public investments of about

CFAF 1,500 billion has been implemented. These investments have stimulated economic growth

which reached 4.0% over the period 2013-2015, despite a difficult international economic

environment marked by a sharp drop in oil prices. They have also helped to reduce the infrastructure

gap, particularly by increasing installed electrical power seven-fold, providing the country with new

national and regional roads, and improving telecommunication infrastructure, notably through the

rehabilitation of telephone networks and the deployment of optical fibre. The authorities’

determination to implement their overall development programme also led to an increase in the share

of the budget allocated to social sectors from 18.3% in 2011 to 23.2% in 2015. The Government’s

financial effort has also resulted in a significant improvement in the country’s social indicators,

notably in the areas of health and education. Its commitment to implement its PND notwithstanding,

the Government is aware that the progress made in its implementation is moderate and that it must

step up its efforts, in particular concerning infrastructure, to achieve PND’s ambitious objectives.

Page 32: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

V

Financing Allocated by the Country to the Sector Targeted by Bank Assistance

Aware of the crucial role played by ICT in the Congolese economy, the Government has significantly

increased the budget resources allocated to the sector over the past years in order to improve its

performance. Public financing allocated to the ICT sector increased by more than 70% between 2012

and 2015 to stand at slightly above CFAF 9 billion. The authorities’ efforts have helped to implement

the National Telecommunication Coverage Project (PCN) and establish the optical fibre backbone.

However, the needs are still enormous despite the remarkable efforts made by the Government. Public

resources allocated for telecommunication infrastructure are not enough to achieve PND’s lofty

growth objectives. The required level of investment is above the Government’s financial capacity,

especially within a context marked by falling oil prices. Increased assistance from TFPs is necessary

to back the efforts of the Government which remains strongly committed to ICT infrastructure

development as evidenced by the inclusion of substantial resources in the 2016 budget for its

financing, despite the difficult fiscal situation.

Country’s Fiscal Situation and Debt Level

The country’s fiscal situation has improved over the past years, but the drop in oil prices is a risk to

the maintenance of macro-economic stability. Budget performance over the period 2011-2013 was

also generally satisfactory, with an overall average budget balance which stood at 11% of GDP,

reflecting a significant increase in oil revenue over the period, despite a sharp rise in public

expenditure, particularly investment expenditure which tripled. However, owing to budget

dependence on oil, the sharp drop in oil prices led to a fall in public revenue of [9.4]% in 2014 and

43% in 2015. Reflecting the substantial decrease in public revenue, the 2014 State budget, for the

first time in ten years, showed an overall deficit estimated at 8.2% of GDP, which widened to 11.8%

in 2015. The country’s fiscal situation in 2016 is expected to be tense as a result of falling oil prices.

Concerning the country’s debt level, external debt has continued to increase since the attainment of

the completion point of the HIPC Initiative, when it represented 20% of GDP, to reach 32% in 2013,

36.5% in 2014 and 47% in 2015. Such increase is mainly explained by continued borrowing and the

deterioration of terms of trade resulting from the drop in oil prices and the depreciation of the CFA

franc. Reflecting these trends, the last debt sustainability analysis (DSA) carried out in 2015 by IMF

and World Bank staff shows that the risk of debt overhang has gone from low to moderate. Such

increase in the country’s risk of debt overhang is confirmed by the assessment conducted by the

Standard and Poor’s (S&P) Rating Services which reduced Congo’s long-term score from B+ to B,

while Fitch Ratings reduced the outlook associated with the country’s B+ score from Stable to

Negative. On these grounds, the DSA strongly recommends that the Government should adopt a

prudent debt policy to avoid jeopardizing debt sustainability.

Upper Cost-sharing Limit and Guidelines Laid Down in the Country’s Financing Parameters

For countries like Congo whose financing parameters (CFPs) are not available, the World Bank’s

Operational Guidelines specify that the share of the total costs financed by the Bank in the overall

lending programme is determined according to the country’s ranking and per capita income.

Specifically, these Guidelines determine the cost-sharing limits as follows: (i) 90% for IDA member

countries whose per capita income is less than USD 1,235; (ii) 75% for IBRD and Blend countries in

the same per capita income group; (iii) 60% for countries whose per capita income ranges from USD

1,236 to USD 4,465; and (iv) 50% for countries with a per capita income of more than USD 4,465.

These limits apply to the Bank’s overall lending programme in the country3 and not to individual

projects. For individual projects, a 10% minimum contribution is generally expected from the

Borrower. Lastly, in exceptional cases, the Guidelines offer the possibility of financing the entire

3 A three-year rolling lending programme which covers the two previous years and the current year.

Page 33: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

VI

costs of projects with external resources. The above conditions are fulfilled in the specific case of

Congo whose per capita income is USD 2,660: (i) the Bank’s share in the overall lending programme

over the period 2014-2016 is 59.7%, compared with the 60% limit; and (ii) the national counterpart

contribution to the project concerned is 21.8%.

8. In conclusion, in light of the foregoing, and at the request of the Government, it is

proposed that the national counterpart contribution be set at 21.8% of total project cost, net of

taxes. The Congolese Government’s contribution will be used to finance the entire "ICT Applications

& Services" component as well as most of the institutional support operations provided for under the

project (except planned studies).

Page 34: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

VII

ANNEX III

COMPARATIVE SOCIO-ECONOMIC INDICATORS

Year Congo Africa

Develo-

ping

Countries

Develo-

ped

Countries

Basic Indicators

Area ( '000 Km²) 2014 342 30 067 80 386 53 939Total Population (millions) 2014 4,6 1 136,9 6,0 1,3Urban Population (% of Total) 2014 64,9 39,9 47,6 78,7Population Density (per Km²) 2014 13,3 37,8 73,3 24,3GNI per Capita (US $) 2013 2 590 2 310 4 168 39 812Labor Force Participation - Total (%) 2014 70,7 66,1 67,7 72,3Labor Force Participation - Female (%) 2014 48,7 42,8 52,9 65,1Gender -Related Dev elopment Index Value 2007-2013 0,928 0,801 0,506 0,792Human Dev elop. Index (Rank among 187 countries) 2013 140 ... ... ...Popul. Liv ing Below $ 1.25 a Day (% of Population)2008-2013 32,8 39,6 17,0 ...

Demographic Indicators

Population Grow th Rate - Total (%) 2014 2,5 2,5 1,3 0,4Population Grow th Rate - Urban (%) 2014 3,1 3,4 2,5 0,7Population < 15 y ears (%) 2014 42,5 40,8 28,2 17,0Population >= 65 y ears (%) 2014 3,4 3,5 6,3 16,3Dependency Ratio (%) 2014 78,7 62,4 54,3 50,4Sex Ratio (per 100 female) 2014 100,0 100,4 107,7 105,4Female Population 15-49 y ears (% of total population) 2014 23,6 24,0 26,0 23,0Life Ex pectancy at Birth - Total (y ears) 2014 59,2 59,6 69,2 79,3Life Ex pectancy at Birth - Female (y ears) 2014 60,7 60,7 71,2 82,3Crude Birth Rate (per 1,000) 2014 37,1 34,4 20,9 11,4Crude Death Rate (per 1,000) 2014 10,0 10,2 7,7 9,2Infant Mortality Rate (per 1,000) 2013 35,6 56,7 36,8 5,1Child Mortality Rate (per 1,000) 2013 49,1 84,0 50,2 6,1Total Fertility Rate (per w oman) 2014 4,9 4,6 2,6 1,7Maternal Mortality Rate (per 100,000) 2013 410,0 411,5 230,0 17,0Women Using Contraception (%) 2014 46,9 34,9 62,0 ...

Health & Nutrition Indicators

Phy sicians (per 100,000 people) 2004-2012 9,5 46,9 118,1 308,0Nurses (per 100,000 people)* 2004-2012 82,4 133,4 202,9 857,4Births attended by Trained Health Personnel (%) 2009-2012 93,6 50,6 67,7 ...Access to Safe Water (% of Population) 2012 75,3 67,2 87,2 99,2Healthy life ex pectancy at birth (y ears) 2012 50,0 51,3 57 69Access to Sanitation (% of Population) 2012 14,6 38,8 56,9 96,2Percent. of Adults (aged 15-49) Liv ing w ith HIV/AIDS 2013 2,5 3,7 1,2 ...Incidence of Tuberculosis (per 100,000) 2013 382,0 246,0 149,0 22,0Child Immunization Against Tuberculosis (%) 2013 92,0 84,3 90,0 ...Child Immunization Against Measles (%) 2013 65,0 76,0 82,7 93,9Underw eight Children (% of children under 5 y ears) 2005-2013 11,8 20,9 17,0 0,9Daily Calorie Supply per Capita 2011 2 195 2 618 2 335 3 503Public Ex penditure on Health (as % of GDP) 2013 3,2 2,7 3,1 7,3

Education Indicators

Gross Enrolment Ratio (%)

Primary School - Total 2011-2014 109,4 106,3 109,4 101,3 Primary School - Female 2011-2014 113,4 102,6 107,6 101,1 Secondary School - Total 2011-2014 53,7 54,3 69,0 100,2 Secondary School - Female 2011-2014 49,8 51,4 67,7 99,9Primary School Female Teaching Staff (% of Total) 2012-2014 53,5 45,1 58,1 81,6Adult literacy Rate - Total (%) 2006-2012 79,3 61,9 80,4 99,2Adult literacy Rate - Male (%) 2006-2012 86,4 70,2 85,9 99,3Adult literacy Rate - Female (%) 2006-2012 72,9 53,5 75,2 99,0Percentage of GDP Spent on Education 2009-2012 6,2 5,3 4,3 5,5

Environmental Indicators

Land Use (Arable Land as % of Total Land Area) 2012 1,6 8,8 11,8 9,2Agricultural Land (as % of land area) 2012 0,3 43,4 43,4 28,9Forest (As % of Land Area) 2012 65,6 22,1 28,3 34,9Per Capita CO2 Emissions (metric tons) 2012 1,5 1,1 3,0 11,6

Sources : AfDB Statistics Department Databases; World Bank: World Development Indicators; last update :

UNAIDS; UNSD; WHO, UNICEF, UNDP; Country Reports.

Note : n.a. : Not Applicable ; … : Data Not Available.

CongoCOMPARATIVE SOCIO-ECONOMIC INDICATORS

mai 2016

0

10

20

30

40

50

60

70

80

90

100

2000

2005

2008

2009

2010

2011

2012

2013

Infant Mortality Rate( Per 1000 )

Cong o Africa

0

500

1000

1500

2000

2500

3000

2000

2005

2007

2008

2009

2010

2011

2012

2013

GNI Per Capita US $

Cong o Africa

0,0

0,5

1,0

1,5

2,0

2,5

3,0

3,5

2000

2005

2008

2009

2010

2011

2012

2013

2014

Population Growth Rate (%)

Congo Africa

01020304050607080

2000

2005

2008

2009

2010

2011

2012

2013

2014

Life Expectancy at Birth (years)

Cong o Africa

Page 35: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

VIII

ANNEX IV

STATUS OF BANK PORTFOLIO IN CONGO AS AT 31 JANUARY 2016

Sector Project Name Approval Date Signature Effectiveness Effec. For 1st Disb.

Apprv-1st Disb. (m)

Net Commitments

(UA m)

Amounts Disbursed

Disb. Ratio (%)*

Closing Date

Project Age

A. NATIONAL PROJECTS

Environment Multi Resource Forest Inventory to Prepare the Land Allocation Plan (CNIAF)

5-Dec.-11 17-Feb.-

12 17-Feb.-12 14-May-12 5 1.91 0.56 29.45 31-March-17 4.2

Sub-total Environment 5 1.91 0.56 29.45 4.2

Energy Rural Electrification Project 6-Dec-12 5-April.-13 22-Sept.-14 22-Sept.-14 22 10.00 0.20 2.03 31-Dec.-17 3.2

Sub-total Energy

22 10.0 0.2 2.0 3.2

Social

Skills and Human Resource Development Project (PDCRH)

18-Dec-14 14-Sept.-

15 Not Yet Not Yet

7.30 0.00 0.00

31-Dec.-20 1.1

Sub-total Social

7.3 0.0 0.0 1.1

Multisector

Business Climate and Economic Diversification Support Project (PACADEC)

14-Oct.-10 3-Feb.-11 3-Feb.-11 28-Oct.-11

13 3.44 0.8 23.62

30-Dec.-16

5.4

Development of National Skills 19-July-13 9-Sept.-13 9-Sept.-13 19-Sept.-14 14 1.00 0.14 14.48 30-June-16 2.6

Technical Assistance and Public Finance Capacity Building Project

24-July-13 9-Sept.-13 9-Sept.-13 19-Sept.-14 14 1.25 0.59 47.44 30-June-16 2.6

Investment Climate and Forestry Governance Support Project (PACIGOF)

1-July-15 23-Dec.-

15 Not Yet Not Yet

15.02 0.00 0.00 31-Dec.-20 0.6

Sub-total Multisector 14 20.7 1.5 7.5 2.8

Water and Sanitation Sanitation of Brazzaville and Pointe-Noire 16-Sept.-09

10-Nov.-09

10-March-10 10-March-

10 6 12.75 11.42 89.59 31-March-16

6.5

EAEPA Centres Second. and Operation FDSE 4-Jan.-13

21-May-13

21-May-13 22-Aug.-13 8 0.86 0.74 85.96

31-July-16 3.1

Sub-total Water and Sanitation 7 13.61 12.16 89.36 4.8

SUB-TOTAL NATIONAL PROJECTS 11.66 53.52 14.48 27.05% 3.2

B. MULTINATIONAL PROJECTS

Transport

Ndende-Dolisie Road and Libreville-Brazzaville Corridor Transport Facilitation Project

18-Dec.-13 19-Feb.-

14 22-Jun.-15 22-June-15 18 30.49 0.00 0.00 30-June-19

2.2

Study on the Kinshasa-Brazzaville Bridge 3-Dec.-08

13-May-09

13-May-09 15-March-

11 28 5.00 2.59 51.77 31-Dec.-16

7.3

Page 36: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

IX

Sector Project Name Approval Date Signature Effectiveness Effec. For 1st Disb.

Apprv-1st Disb. (m)

Net Commitments

(UA m)

Amounts Disbursed

Disb. Ratio (%)*

Closing Date

Project Age

Cameroon/Congo: Ketta-Djoum Road (Phase I) 25-Sept.-09 11-Jan.-

10 11-Jan.-10 13-Feb.-12

29 61.90 46.05 74.39 30-Dec.-16

6.4

Study on Ouesso-Bangui-N'djamena Road and Navigability

1-Dec.-10 29-April-

11 29-April-11 29-April-11

5 8.00 1.02 12.79 30-Nov.-16

5.2

Ketta-Djoum Road and Yaounde-Brazzaville Corridor Transport Facilitation Project – Phase 2 21-Oct.-15

17-Dec.-15

Not Yet Not Yet

96.50 0.00 0.00

31-Dec.-20

0.3

Sub-total Transport 20 105.4 49.7 47.1 5.3

SUB-TOTAL MULTINATIONAL PROJECTS 20.03 105.39 49.66 47.12% 3,9

Total 14.70 158.91 64.14 40.36 3.9

Page 37: CONGO CENTRAL AFRICA BACKBONE (CAB) PROJECT CONGO COMPONENT

X

ANNEX V

MAP OF THE OPTICAL FIBRE INFRASTRUCTURE PROJECT AREA (AFDB AND

WORLD BANK FINANCING)

This map has been provided by the staff of the African Development

Bank exclusively for the use of the readers which it is attached. The names used and the borders shown do not imply on the part of the ADB

Group and its members any judgment concerning the legal status of a

territory nor any approval or acceptance of these borders.

BM funding

ADB funding