conflict prevention on construction projects · group5 total comparison of the mean scores of...

21
Jump to first page Conflict Prevention on Construction Projects Prapapaow Awakul and Stephen Ogunlana School of Civil Engineering Asian Institute of Technology PO Box 4, Klong Luang Pathum Thani, THAILAND

Upload: others

Post on 01-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Conflict Prevention on Construction Projects

Prapapaow Awakul and Stephen Ogunlana

School of Civil EngineeringAsian Institute of Technology

PO Box 4, Klong LuangPathum Thani, THAILAND

Page 2: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Conflict Prevention on Large Construction Projects

Projectowners

Contractors Designers

Consultants

Academics,Experts

Internal Conflict

Largeconstruction project Interface Conflict

NGOs,Conservation

groups

The groupaffected bythe project

LocalGovernment

Officials

Model of Conflict encountered Large Construction Projects

Page 3: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Case Study

The Bangkok Mass Transit System Project in Thailand

Objectives

1. Determine the Attitudinal Differences Among:

Group 1: The Group Affected by the ProjectGroup 2: The Project ParticipantsGroup 3: NGOs, Interested OrganizationsGroup 4: Academics and ExpertsGroup 5: The Local Government Officials

2. Derive Factors Leading to the Interface Conflicts

Page 4: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

34 Variables to be TestedCode Variables Code VariablesA1.1 Quality of water in watercourses

during construction.C2.6 Queue length of trucks.

A2.1 Control of some operations causingloud noise and high vibration.

C2.8 The requirement of the Act on LandTraffic.

A2.2 Construction during the night. C3.1 Participation in EIA study.

A2.4 Noise in sensitive areas. C3.2 Technical hearing prior to EIAstudy.

A2.5 Public announcement for loud noiseoperations. C3.3 Public hearing prior to final

decision-making.A3.1 Construction of stations over roads. C3.4 Response to the requests made by

the public.A3.2 Control of dust from truck driving. C3.5 Chance to monitor during the

construction period.A3.3 Installation of fence along the site. C3.8 Survey on social impact data.

A3.4 Dust from solid waste outside the site. D1.1 Disturbance on business during theconstruction.

A3.5 Cover of excavated holes during theconstruction. D1.6 Information revelation.

C1.1 Construction of columns in the middleof roads. D1.7 The requirement of laws regarding

public information and publicopinion.

C1.2 Construction of stations in sidewalkareas. D4.1 Route passing nearby historical and

religious landmarks.C2.1 Placing construction materials and

equipment on roads or walkwayoutside construction fences.

D4.2 The construction at Lumpini Park.

C2.2 Entrances to construction sites. D5.1 Project’s elevated structures.C2.3 Management of site layout. D5.2 Visual impact during construction.C2.4 Information to road users. D6.1 Accident during the construction.C2.5 Traffic sign, signals and lane

channeling.D6.2 The requirement regarding Act on

control building construction

Page 5: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Hypothesis“Each group has the same attitude towards the factors

leading to interface conflicts encountered the project”Test by

ANOVA test: investigate whether the group mean scores are the same or notMultiple Comparisons with Tukey’s HSD test: pairwise comparisons

Testing Results (ANOVA)All variables exhibited significant difference at 5% sig.

Thus, the null hypothesis is rejected and the alternative hypothesis is accepted.

Page 6: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Testing Results: Tukey’s HSDNumbers of Variables That Have Similar Mean Scores

When Compared for Pairs of Respondents Groups

0

5

10

15

20

25

30

1--2 1--3 1--4 1--5 2--3 2--4 2--5 3--4 3--5 4--5

Less Moderately Important Very

Group (I-J)

No. of Variables

Page 7: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

0

1

2

3

4

5A1.1

A2.1A2.2A2.4

A2.5A3.1

A3.2A3.3

A3.4

A3.5

C1.1C1.2

C2.1C2.2

C2.3C2.4C2.5

C2.6C2.8C3.1

C3.2C3.3

C3.4

C3.5C3.8

D1.1

D1.6

D1.7D4.1

D4.2D5.1

D5.1D6.1D6.2

Group1Group2Group3Group4Group5Total

Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups

Page 8: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

ConclusionsThe group affected by the project, the academics and experts, the local government officials are close to each other. They ranked variables concerning noise and vibration impact, air impact, impact on road and traffic, impact on archaeological and historical issues, accidents as “important” and “moderately important.”

Page 9: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Conclusions (2)The group affected by the project and NGOs have several links to each other. They ranked variables concerning accident as “very important” and variables concerning noise and vibration impact, impact on road and traffic, EIA and public participation as “important.”

Page 10: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Conclusions (3)

The project participants are different from the other groups. They considered the issues either as “moderately important” or “less important.”The major reason for conflicts is attitudinal division between the project participants on one side and the other groups on the other side.

Page 11: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Recommendations to Reduce Conflicts on Projects

Accident: Protection of the public against falling object should be providedEIA study and public participation:Conducting EIA without public participation or failing to hold technical hearing can invite opposition and ignite resistance.

Page 12: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Recommendations to Reduce Conflicts on ProjectsSocioeconomic and information revelation: If social impacts cannot be minimized to a satisfactory degree, the whole role of development project could be called into question.Road and traffic: Construction over roads can cause traffic congestion. Information on the best alternative route should be given. Inform the public on expected regional traffic changes as a result of the construction.

Page 13: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Recommendations to Reduce Conflicts on Projects

Archaeological and historical sites:Eligible property should be preserved and protected without adverse effect from construction and the implementation of projects that have negative impacts on cultural heritage should be avoided.

Page 14: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Recommendations to Reduce Conflicts on Projects

Air impact: The construction of elevated structures over roads and between high buildings should be carefully considered. The structures can obstruct natural ventilation.

Page 15: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Recommendations to reduce conflicts on future projects

Noise and vibration impact: Source of noise from activities and action of the project should be controlled by following commitment of the legal standard. Working hours for particularly noisy operations should be minimized with appropriate local consultation in advance.

Page 16: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Recommendations to reduce conflicts on future projects

Visual impact: The project’s elevated structures may cause visual impact. The designers should prevent the exposure or creation of visual misfits. All possible mitigation measures should be considered.

Page 17: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

BTS Service

Page 18: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

The BTS

Page 19: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Page 20: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page

Page 21: Conflict Prevention on Construction Projects · Group5 Total Comparison of the Mean Scores of Individual Variables among the Five Respondent Groups. Jump to first page Conclusions

Jump to first page