condenser supply contract report jose botelho direito en/cv/dc thermosyphon cooling workshop §5...
TRANSCRIPT
Condenser supply contract report
Jose Botelho Direito EN/CV/DC
Thermosyphon cooling workshop §5Thursday, October 20, 2011
Thermosyphon cooling workshop §5 2
Outline
• Technical Requirements
• Request for Quotation
• Design from D.A.T.E.
• Construction Schedule
20/10/2011
Thermosyphon cooling workshop §5 3
Technical Requirements
• Thermal Requirements:– Total Condenser cooling power: 170kW
• De-superheating: 28.7 kW• Condensing: 135.8 kW• Sub-cooling: 5.5 kW
• DO-26673/EN-CV – EMDS document number 1134974
20/10/2011
Thermosyphon cooling workshop §5 4
Technical Requirements• Stainless Steel Shell and Cupronickel or SSt cooling tubes• FOAMGLAS Insulation• Storage capacity of 2.5m3• Pressure: PN25• Design temperature from -70°C to 63°C• Leak tightness of 10-4mbar.lt/s• Standards:
– Pressure Equipment Directive 97/23 (PED)– Leak tightness: BS EN13184:2001– Cleaning: ASTM A380– Earthquake loading: EUROCODE 8
20/10/2011
Thermosyphon cooling workshop §5 5
Request for Quotation• Companies contacted (11x):
– AEL (de); KLIMAL (de); ALFA LAVAL (se); APPARETEBAU-CRIMMITSCHAU (de); ARSOPI (pt); BOWMAN (uk); D.A.T.E. (fr); Novoa Equipment Limited (uk); Onda (it); SWEP (se); GEA (de).
• Offers received (3x):– D.A.T.E. – ARSOPI – GEA
• DO-26673/EN-CV – EMDS document number 1134974
20/10/2011
Thermosyphon cooling workshop §5 6
Design proposal from D.A.T.E.
20/10/2011
DESUPERHEATING and CONDENSATION ZONE SUBCOOLING ZONEHEAT TRANSFER COEFFICIENT 299,65 W.m.-2°C-1 112,8 W.m.-2°C-1
HEAT TRANSFERT SURFACE 86,85 m2 9,07 m2
PRESSURE DROP 6 mbar 10 mbarNUMBER OF TUBES 240 tubes 28 tubes
Thermosyphon C3F8 Liquid outlet
Thermosyphon C3F8 Vapour inlet
Brine Condenser IN
Brine Condenser OUT
Brine Sub-cooler IN
Brine Sub-cooler OUT
De-superheating & Condensing tubes (240x)
Sub-cooling tubes (28x)
Thermosyphon cooling workshop §5 7
Construction Schedule
• Condenser Construction Schedule– October 2011: Contract start– November 2011: Detailed design– January 2012 : Purchasing of material– March 2012: Condenser construction– April 2012: Final pressure tests– April 2012: Insulation of the condenser– April 2012: Delivery at CERN
20/10/2011
Thermosyphon cooling workshop §5 8
• Any questions?
20/10/2011