concrete paving association of minnesota cpam … paving association of minnesota ... concrete...
TRANSCRIPT
Concrete Paving Association of Minnesota
CPAM Annual Workshop
March 11, 2016
Gordy Bruhn- Senior Engineering Specialist
Revised Reinforcing Steel Sizing from metric back to standard numbering of 1/8th inch increments.
For example: #13 mm bar is now a #4 bar.
Type BE Repair
Allow either water or grout to bond the old and new concrete
Continue to require grout to seal outside perimeter of the partial depth repair
Increased Drill and Grout Dowel Bar Size, From 1-inch to 1.25-inch Dowel Bar Diam.
Low Volume Full Depth Repair will Remain 1’’ Diameter Dowel Bars
Full Depth Repair
12’ wide (typical)
Start Dowels 1foot in from both ends
Increased Minimum Number of Dowel Bars as Roadway Width Wider Required
Need to add an additional dowel bar per side for each 1’ increase in
lane width
Roadway Lane Width
Dowel Bars Required
12 feet 11 Dowels
13 feet 12 Dowels
14 feet 13 Dowels
Projects with both Paving & CPR will separately tabulate dowel bars.
Will include 2301 and 2302 Dowel Bar Pay Items
Concrete Mixes previously designed by MnDOT – now Contractor/Producer designed
New mix numbers for all concrete mixes
Concrete Grade
OLDMix
Number
NEWMix
Number
Intended Use
Maximum w/c ratio
Maximum Cementitio
usContent(lbs/cy)
Maximum%SCM
(Fly Ash/ Slag/
Ternary)
SlumpRange
Minimum
Compressive
Strength, f’c
(28-day)
3137 Spec.
R
Pavement
Rehab
3A32
3B423R52
CPR - Full
depth
concrete
repairs,
concrete
base
0.45 750 30/35/40 2 - 5” 4000 psi 2.D.3
Opened at a minimum of 48 hours of age and strength of 3000 psi◦ HE concrete requires approval of the Engineer prior to
incorporation into the work
◦ HE concrete requires control cylinders
Table 2461-7
High-Early (HE) Concrete Requirements (Not applicable to Mass Concrete)
OLD
Mix
Number
NEW
Mix
Number
Concrete
Grades
Allowed
Minimum
Time to
Opening
Maximu
m w/c
ratio
Maximum
Cementitio
us
Content
(lbs/yd3) *
Slump
Range
Minimum
Strength
to
Opening
Minimum
28-day
Compress
ive
Strength,
f’c
3137
Spec.
3A22HE 3HE32 F 48 hrs 0.42 7501 – 3”
║3000 psi 4500 psi 2.D.1
3A32HE
3Y43HE3HE52 B, F, G 48 hrs 0.42 750 2 – 5” 3000 psi 4500 psi 2.D.1
3Y33HE
3Y46HE
3Y37HE
3YHE52
Y
(Repairs
Only)
48 hrs 0.42 750 2 – 5” 3000 psi 4000 psi 2.D.2
3A32HE 3RHE52
R
(Repairs
Only)
48 hrs 0.42 750 2 – 5” 3000 psi 4000 psi 2.D.3
* Supplementary Cementitious Materials allowed.
║ Adjust slump in accordance with 2461.3.G.7.a for slipform concrete placement.
Standard Mixes UNCHANGED FROM PAST PRACTICES…Store in same condition as structure
Allowed to cure HE control cylinders in temperature monitored coolers
Both the structure and storage/curing vessel need to be temperature monitored
Must maintain temperature within storage / curing
vessel at ≤ 5ºF of the poured concrete structure
The Contractor may choose to make additional control cylinders (beyond MnDOT’s3) to determine strength at any time other than 28-days.
The Contractor may request the use of concrete maturity to determine opening to traffic, removal of forms, or loading.
MnDOT uses as part of acceptance
Based on an average of 3 cylinders
Cured under controlled conditions
MnDOT Defined Curing Periods
Moist Curing Environment Provided,
By Contract
Use of ventilation,
Use of ice,
Use of thermostatically controlled heating or cooling devices, or
Use heating methods such as stoves or light bulbs.
Other suitable methods are allowed provided the requirements limiting specimen storage temperature and moisture loss requirements are met.
Initial Cure up to 48 hours
The Contract requires providing moist curing environments of adequate size and number for initial and intermediate curing
(first 7 days) of concrete cylinders
Part of Field Office Spec (2031.3.C)
If no Field Office, still required
by Standard Specification (2461)
2016 Spec Book Requirement◦ Walks(2521) and Curb and Gutter (2531)
Concrete Contractor or Subcontractor required to have the following:◦ 2 - ACI Certified Flatwork Finisher or
Technicians
◦ 1 required to be on site at all times
Concrete Paving Association of Minnesota
CPAM Annual Workshop
March 11, 2016
Maria Masten, Concrete Engineer
MnDOT has allowed two methods to achieve texture in concrete
◦Astroturf Drag
◦ Broom Drag
Beyond those requirements, we do not specify how to achieve the required texture.
In 2015, lateral wandering with certain types of vehicles felt on some roadways
Seems attributed to some broom texturing options
Met with Industry to discuss options
Beginning November 2015◦ Astroturf drag only for mainline paving
◦ Broom drag allowed for lower speeds, edge of pavements and hand placed concrete
Looking for volunteer project to install some different broom drag test sections in 2016
Used for locating dowel baskets and centerline tie bars
Original use ~ concrete pavement thickness◦ Five (5) pilot projects using the MIT-SCAN T2 to
determine the thickness of the concrete were conducted in 2015.
Evaluated the concrete thickness with the following:
(1) Contractor Probing (1 per 1,000 lineal ft)
(2) Probe Verification Scan (1 per 4 probes)
(3) Quality Acceptance Core (1 per 4,000 lineal ft)
What we learned??
Probe vs. Scan Location ◦ Correlation was acceptable but not great
◦ Variation was likely caused by the probe measurements which are typically measured to the nearest 1/8 to 1/4 inch depending on the Contractor.
Core vs. Scan Location◦ Difference was typically a few hundredths of an
inch.
What we are going to do different.
Not require the Contractor to probe at specified locations…they can probe at their discretion
Instead, the Contractor will scan the concrete at the former probe locations (1 per 1,000 lineal ft)
Required to core some of the scan locations for verification and a better comparison
Reduce overall coring◦ Scan Verification Core (1 per 8 scans)
◦ Quality Acceptance Core (1 per 8,000 lineal ft)
The MIT-SCAN T2 is currently being used to determine thickness by several state DOT’s and is accepted by the FHWA.
MnDOT’s goal is for full implementation in 2017 or 2018.
In 2015, MnDOT reviewed approximately 10 projects with unsealed joint test sections installed between 1994 – 1999
Cored 5 projects
In all cases where the seal was breached, the face of concrete cores looked worse than unsealed
Well sealed joints looked the best
Seal the following:◦ All Roadways: Speed limit 45 mph or less
◦ Whitetopping < 6” thick
◦ CPR projects: Speed limit 45 mph or less
◦ Bridge Approach Panels
MnDOT Standard Plans updated to reflect unsealed joint recommendations