concept refinement report
TRANSCRIPT
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 1/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
Prepared for:
Minnesota Department of Transportation and
Wisconsin Department of Transportation
Prepared by:
Parsons Brinckerhoff
June 2010
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 2/110
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 3/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 i
Table of Contents
1 Executive Summary ....................................................................................................................... 1‐1
1.1 Pier Configuration ............................................................................................................ 1‐1
1.2 Box Girder Configuration ................................................................................................. 1‐2
1.3 Pedestrian Trail Location ................................................................................................. 1‐2
1.4
Cable Anchorage
Details
..................................................................................................
1‐2
1.5 Approach and Ramps Span Arrangement ........................................................................ 1‐2
1.6 Approach and Ramps Columns ........................................................................................ 1‐3
1.7 Bridge Lighting ................................................................................................................. 1‐3
2 Introduction .................................................................................................................................. 2‐1
2.1 Project Description .......................................................................................................... 2‐1
2.1.1 Proposed River Crossing Description ............................................................................... 2‐1
2.2 Report Purpose and Objective ......................................................................................... 2‐2
2.3 St. Croix River Crossing Development .............................................................................. 2‐3
2.4 General Definition of an Extradosed Bridge .................................................................... 2‐4
3 Acknowledgement of Commitments ............................................................................................ 3‐1
3.1
Reference Documents
.....................................................................................................
3‐1
3.2 Commitments .................................................................................................................. 3‐1
4 Risk Evaluation .............................................................................................................................. 4‐1
4.1 Risk Matrix and Summary ................................................................................................ 4‐1
4.2 Investigation and Evaluation of Risk Factors ................................................................... 4‐2
4.2.1 Structural Analysis ........................................................................................................... 4‐2
4.2.2 Bridge Lighting and Signing .............................................................................................. 4‐3
4.2.3 Visual Quality ................................................................................................................... 4‐4
4.2.4 Construction..................................................................................................................... 4‐5
4.2.5 Maintenance and Inspection ........................................................................................... 4‐6
5 Division I Structural Analysis ......................................................................................................... 5‐1
5.1
Introduction .....................................................................................................................
5‐1
5.2 Objectives ........................................................................................................................ 5‐1
5.3 Base Modeling ................................................................................................................. 5‐2
5.4 Longitudinal Analysis ....................................................................................................... 5‐2
5.5 Transverse Analysis .......................................................................................................... 5‐4
5.6 Superstructure Cross‐section Investigation ..................................................................... 5‐5
5.7 Inboard Pedestrian Trail .................................................................................................. 5‐6
5.8 Box Girder Depth ............................................................................................................. 5‐7
5.9 Single Box Girder Feasibility ............................................................................................. 5‐8
5.10 Transverse Diaphragm investigation ............................................................................... 5‐9
5.11 Pier Investigation ............................................................................................................. 5‐9
5.12
Fixity/Longitudinal Movement
Investigation
.................................................................
5‐12
5.13 Grade Induced Movement Investigation ....................................................................... 5‐13
5.14 Two Box Girder Load Distribution Investigation ............................................................ 5‐13
5.15 Wind Load—Vibration Analysis Investigation ................................................................ 5‐15
5.15.1 Back span Uplift/Maximum Back span Length Investigation......................................... 5‐17
5.16 Extradosed Stay Cable Analysis ...................................................................................... 5‐17
5.17 Points of Interest—Local Analysis .................................................................................. 5‐19
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 4/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
ii June 2010
6 Division II Structural Analysis ....................................................................................................... 6‐1
6.1 Introduction and Objectives ............................................................................................ 6‐1
6.1.1 Box Girder Width Transition Investigation ...................................................................... 6‐1
6.1.2 Box Girder Depth Economy Investigation ....................................................................... 6‐1
6.1.3 Fixity/Longitudinal Movement Investigation .................................................................. 6‐2
6.1.4 Grade Induced Movement Investigation ........................................................................ 6‐2
6.1.5 Box Girder Depth Transition Investigation ...................................................................... 6‐2
6.2 Investigation Methods: Longitudinal Analysis................................................................. 6‐2
6.3 Baseline Model Description ............................................................................................. 6‐4
6.3.1 Piers ................................................................................................................................. 6‐4
6.3.2 Box Girders ...................................................................................................................... 6‐6
6.3.3 Transition Span ................................................................................................................ 6‐7
6.3.4 Pedestrian Trail ................................................................................................................ 6‐7
6.4 Alternative R1 Investigation .......................................................................................... 6‐10
6.4.1 Grade‐Induced Movement Investigations ..................................................................... 6‐15
7 Bridge Lighting and Signing .......................................................................................................... 7‐1
7.1 Review of Requirements for Architectural and Roadway Lighting ................................. 7‐1
7.2
Lighting Criteria
...............................................................................................................
7‐1
7.3 Lighting Alternatives Analysis .......................................................................................... 7‐5
7.3.1 Source Selection .............................................................................................................. 7‐5
7.4 Architectural Lighting .................................................................................................... 7‐11
7.4.1 Option 1A ...................................................................................................................... 7‐12
7.4.2 Option 2A ...................................................................................................................... 7‐13
7.4.3 Option 2AA .................................................................................................................... 7‐14
7.4.4 Option 3 ......................................................................................................................... 7‐15
7.4.5 Option 4 ......................................................................................................................... 7‐16
7.4.6 Preferred Option ........................................................................................................... 7‐16
7.5 Roadway Lighting .......................................................................................................... 7‐17
7.6
Loop Trail
Lighting
.........................................................................................................
7‐18
7.7 Navigation and Obstruction Lighting ............................................................................. 7‐18
7.8 Light Trespass / Glare / Environmental Impacts ........................................................... 7‐18
7.9 System Maintenance ..................................................................................................... 7‐19
7.10 Box Section Inspection Lighting ..................................................................................... 7‐19
7.11 Signing ........................................................................................................................... 7‐20
7.11.1 Review of the Visual Quality Manual ............................................................................ 7‐20
7.11.2 Additional Concept Refinements .................................................................................. 7‐20
8 Visual Quality ................................................................................................................................ 8‐1
8.1 Introduction ..................................................................................................................... 8‐1
8.2 Objectives ........................................................................................................................ 8‐2
8.3
Refinement Process
.........................................................................................................
8‐2
9 Construction ................................................................................................................................. 9‐1
9.1 Introduction ..................................................................................................................... 9‐1
9.2 Construction Staging Areas ............................................................................................. 9‐1
9.3 Casting Yard ..................................................................................................................... 9‐1
9.4 Precast vs. Cast‐in‐place Construction ............................................................................ 9‐1
9.4.1 Precast Construction ....................................................................................................... 9‐2
9.4.2 Cast‐in‐ Place Construction ............................................................................................. 9‐3
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 5/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 iii
9.5 Permitting Requirements ................................................................................................. 9‐3
9.6 Erosion Control and Environmental Compliance ............................................................. 9‐4
9.7 Foundation Construction Methods .................................................................................. 9‐4
9.8 Substructure Pier and Tower Construction ..................................................................... 9‐5
9.9 Reinforcing steel arrangements congestion and detailing .............................................. 9‐5
9.10 Post‐tensioning tendons and grouting ............................................................................ 9‐6
9.11 Stay Installation ............................................................................................................... 9‐6
9.12 Special architectural forming and finishing ..................................................................... 9‐6
9.13 Industry forum ................................................................................................................. 9‐7
10 Maintenance and Inspection ...................................................................................................... 10‐1
10.1 Introduction ................................................................................................................... 10‐1
10.2 Critical Elements ............................................................................................................ 10‐1
List of Figures
Figure 4‐1. Risk Assessment ................................................................................................................ 4‐1
Figure 5‐1.
Stick
(top)
and
Rendered
(bottom)
Isometric
View
of
Global
Model
...............................
5‐2
Figure 5‐2. Rendered Isometric View of Global Model Showing Construction Sequence .................. 5‐3
Figure 5‐3. Box Girder Stress along Length of Bridge .......................................................................... 5‐4
Figure 5‐4. Transverse Framing at Cable Connection .......................................................................... 5‐5
Figure 5‐5. Baseline Box Girder Superstructure .................................................................................. 5‐6
Figure 5‐6. Proposed Box Girder Showing the Reduced Depth and Integrated Pedestrian Trail ....... 5‐7
Figure 5‐7. Typical Sections ................................................................................................................. 5‐9
Figure 5‐8. VQM Baseline Pier Configuration .................................................................................... 5‐10
Figure 5‐9. Proposed Pier Configuration ........................................................................................... 5‐12
Figure
5‐
10.
Deflected
Pier
Shape
.....................................................................................................
5‐
13
Figure 5‐11. Superstructure between Cable Supports ...................................................................... 5‐14
Figure 5‐12. Transverse Analysis ....................................................................................................... 5‐14
Figure 5‐13. Closure Pour Detail ........................................................................................................ 5‐15
Figure 5‐14. Mode Shapes from the Eigenvalue Dynamic Analysis .................................................. 5‐16
Figure 5‐15. Extradosed Stay Cable Configuration ............................................................................ 5‐18
Figure 5‐16. Live Load Stress Range .................................................................................................. 5‐19
Figure 5‐17. Local Model of Integral Pier (Bottom View) .................................................................. 5‐20
Figure 5‐18. Local Model of Integral Pier (Top View) ........................................................................ 5‐20
Figure 5‐19. Pier Cross Girder Interface Model ................................................................................. 5‐21
Figure 5‐20. Pier 8 Elevation Showing Widened Superstructure and Full Super Elevation .............. 5‐22
Figure 5‐21. Span 8 Typical Section ................................................................................................... 5‐23
Figure 5‐22. Isometric View of Precast Truss .................................................................................... 5‐23
Figure 5‐23. Isometric View of 3D Analysis ....................................................................................... 5‐24
Figure 6‐2. Detail of Segments on Pier and Accurate Section Property Input .................................... 6‐3
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 6/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
iv June 2010
Figure 6‐1. Balanced Cantilever Construction Method (Modeling of Construction Stage 6,
Bridge 82048) ..................................................................................................................... 6‐3
Figure 6‐3. Stress Output Checked at 10 Locations in the Cross‐section ........................................... 6‐4
Figure 6‐4. Pier 1 on TH 36 (Bridge No. 82045) .................................................................................. 6‐5
Figure 6‐5. Typical Pier on TH 36 Approaches (Others Similar) .......................................................... 6‐6
Figure 6‐6.
Baseline
Approach
Box
Girders.........................................................................................
6‐7
Figure 6‐7. Baseline Model 82045E‐r0A, Bridge 82045 EB (EB TH 36) ............................................... 6‐8
Figure 6‐8. Plan and Elevation of Baseline Model, Bridge 82045 EB (EB TH 36) ................................ 6‐8
Figure 6‐10. Model 82045E‐r1A—Double‐stem Columns in Alternative R1 Span Arrangement ..... 6‐11
Figure 6‐9. Plan and Elevation of Alternative “R1” Models for EB and WB TH 36. .......................... 6‐11
Figure 6‐11. Model 82045E‐r1B—Single‐stem Columns in Alternative R1 Span Arrangement ....... 6‐12
Figure 6‐12. Plan and Elevation of Model 82045W‐r1B—WB TH 36 with Single‐stem Columns
in Alternative R1 Span Arrangement ................................................................................ 6‐12
Figure 6‐13. Bridge No. 82047 (NE Ramp) Stick Model and Rendered Model ................................. 6‐13
Figure 6‐14.
Bridge
No.
82047
Rendered
Plan
and
Elevation
from
Structural
Model
with
Details ............................................................................................................................... 6‐13
Figure 6‐15. Bridge No. 82048 (SE Ramp) Stick Model (Left) and Rendered Sectional Model
(Right) ............................................................................................................................... 6‐14
Figure 6‐16. Bridge No. 82048 (SE Ramp) Plan and Elevation View of Rendered Model ................. 6‐14
Figure 6‐17. Models Used in Investigating Grade‐induced Deflection ............................................. 6‐15
Figure 7‐1. Typical LED ........................................................................................................................ 7‐6
Figure 7‐2. Schematic of LED Operation ............................................................................................. 7‐6
Figure 7‐3. Typical Representative Spatial Radiation Pattern for White Lambertian ......................... 7‐8
Figure 7‐4. Typical Polar Radiation Pattern for White Lambertian ..................................................... 7‐8
Figure 7‐5.
Typical
Luminous
Flux
.......................................................................................................
7‐9
Figure 7‐6. Typical Light Output Characteristics Over Temperature (Cool‐White at Test
Current) ............................................................................................................................ 7‐10
Figure 7‐7. Typical Lumen Maintenance Values for Various Light Sources ...................................... 7‐11
Figure 7‐8. Base Architectural Lighting Option ................................................................................. 7‐11
Figure 7‐9. Lighting Option 1a ........................................................................................................... 7‐12
Figure 7‐10. Lighting Option 1b ........................................................................................................ 7‐12
Figure 7‐11. Lighting Option 2a ......................................................................................................... 7‐13
Figure 7‐12. Lighting Option 2b ........................................................................................................ 7‐13
Figure
7‐
13.
Lighting
Option
2aa
.......................................................................................................
7‐
14
Figure 7‐14. Lighting Option 2bb ...................................................................................................... 7‐14
Figure 7‐15. Lighting Option 3 .......................................................................................................... 7‐15
Figure 7‐16. Lighting Option 4a ......................................................................................................... 7‐16
Figure 7‐17. Lighting Option 4b ........................................................................................................ 7‐16
Figure 7‐18. Preferred Option—View from Sunnyside Marina ........................................................ 7‐16
Figure 7‐19. Preferred Option—View from Stillwater ...................................................................... 7‐16
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 7/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 v
Figure 7‐20. Preferred Option—View Looking North ........................................................................ 7‐17
Figure 7‐21. Roadway Lighting .......................................................................................................... 7‐17
Figure 7‐22. Loop Trail Lighting Using Linear Luminaires .................................................................. 7‐18
Figure 7‐23. Navigation and Obstruction Lights ................................................................................ 7‐18
Figure 7‐24. LED Utility Light ............................................................................................................. 7‐19
Figure 7‐25. Typical Inspection Lighting ............................................................................................ 7‐20
Figure 8‐1. Section View Illustrates Curved Outside Edges of Cross Girder ........................................ 8‐3
Figure 8‐2. Tangent Segments Have Been Introduced Along Vertical Faces of Tower Forms
for Ease of Construction ...................................................................................................... 8‐4
Figure 8‐3. View along pedestrian trail located inside of tower line .................................................. 8‐5
Figure 8‐4. Section view of trail located on north edge along west bound travel lanes ..................... 8‐6
Figure 8‐5. Typical Pedestrian Overlook outside of tower on north elevation of bridge ................... 8‐7
Figure 8‐6. View of underside of Pedestrian overlook surrounding tower ......................................... 8‐7
Figure 8‐7. Higher curb height with 6” vertical picket spacing and integral LED light fixtures
incorporated into
post
on
pedestrian
hand
railing.
............................................................
8‐8
Figure 8‐8. North elevation view of structure with covered cable connections ................................. 8‐9
Figure 8‐10. View of Battered Abutment (Left) and Typical Single Stem Pier (Right) along
Minnesota Approach ........................................................................................................ 8‐10
Figure 8‐9. Enlarged view of covered cable connections .................................................................. 8‐10
List of Tables
Table 4‐1. Summary of Risk Assessment ............................................................................................. 4‐2
Table 5‐1. Box Girder Depth Cost Comparison .................................................................................... 5‐8
Table 6‐1.
Baseline
Span
Arrangement
...............................................................................................
6‐9
Table 6‐2. Span Arrangement “R1” ................................................................................................... 6‐10
Table 6‐3. Grade‐induced Movement Results ................................................................................... 6‐15
Table 7‐1. Illuminance Levels for Floodlighting Buildings and Monuments ........................................ 7‐2
Table 7‐2. Illuminance Method—Recommended Values ................................................................... 7‐2
Table 7‐3. Luminance Method—Recommended Values ..................................................................... 7‐3
Table 7‐4. Illuminance and Luminance Design Values (English) .......................................................... 7‐4
Table 7‐5. Recommended Illumination (Values in lux) ....................................................................... 7‐5
Table 7‐6. Flux Characteristics for LUXEON K2 with TFFC Junction and Case Temperature =
25C ..................................................................................................................................... 7‐9
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 8/110
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 9/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 i
Acronyms and Abbreviations
2D two dimensional
3D three dimensional
AASHTO American Association of State Highway and Transportation Officials
ASBI American Segmental Bridge Institute
avg average
BMP best management practice(s)
cd/m2 candelas per square meter
CSL Crosshole sonic logging
cy cubic yards
DB design build
EB eastbound
EoR engineer of record
f’c Concrete 28‐day compressive strength
fc
Footcandles
FEIS Final Environmental Impact Statement
FGUTS Prestressing strand guaranteed ultimate tensile strength
FHWA Federal Highway Administration
f pu Prestressing strand specified ultimate tensile strength
ft feet
I severity of impact
IES Illuminating Engineering Society
IESNA Illuminating Engineering Society of North America
InGaN
indium
gallium
nitride
kips thousand pounds
ksi thousands of pounds per square inch
LED light emitting diode
Lpile A Program for the Analysis of Piles and Drilled Shafts Under Lateral Loads
LRFD Load and Resistance Factor Design
lux SI unit of illuminance and luminous emittance
mA milliamps
max maximum
min minimum
Mn/DOT Minnesota Department of Transportation
NDE Nondestructive evaluation
NE northeast
P probability of occurrence
PB Parsons Brinckerhoff (PB Americas, Inc.)
PGL Profile grade line
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 10/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
ii June 2010
PTI Post‐Tensioning Institute
RFP request for proposal
RGB Red green blue color model
SE southeast
sf square feet
SFEIS Supplemental Final Environmental Impact Statement
Tj junction temperature
UP R/R Union Pacific Railroad
USCG U.S. Coast Guard
UV ultraviolet
VE value engineering
VQAC Visual Quality Advisory Committee
VQM Visual Quality Manual VQRC Visual Quality Review Committee
WB
westbound
WisDOT Wisconsin Department of Transportation
Certification
I hereby certify that this report was prepared by me or under my direct supervision,
and that I am a duly Licensed Professional Engineer under the laws of the State of
Minnesota.
Paul J. Towell
PE No. 42965
June 30, 2010
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 11/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 1‐1
1 Executive Summary
This Concept Refinement Report has been developed by Parsons Brinckerhoff (PB),
under contract with the Minnesota Department of Transportation (Mn/DOT). PB is
providing concept design and associated services for the proposed new St. Croix
River
Crossing
that
is
within
the
overall
St.
Croix
River
Crossing
Project.
These
services are part of the Preferred Alternative Package for the St. Croix River Crossing
Project as documented in the 2006 Supplemental Final Environmental Impact
Statement (SFEIS).
The purpose of the report is to document the results of investigations of the
following aspects of the bridge:
Structural Analysis
Bridge Lighting and Signing
Visual Quality
Construction
Maintenance and
Inspection
The report separates the structural analysis portion of the study into two divisions.
Division I is for the extradosed portion of Bridge 82045, and Division II is for the
approach spans of Bridge 82045 and the ramps designated Bridges 82047 and
82048. The other areas of study are reported in combined sections that cover both
divisions.
The starting point for the concept refinement is the concept design presented in the
Visual Quality Manual (VQM). This concept is based on the use of concrete
segmental bridges for the mainline and ramp structures. In addition, the river
crossing portion of the mainline structure is an extradosed bridge with short towers
above the
roadway
and
cable
support
of
the
girder.
The
objective
of
the
concept
refinement effort is to confirm the feasibility of the VQM concept and to develop
and refine the concept prior to advertising for final design and construction. A key
component of the concept refinement effort was coordination with the Visual
Quality Advisory Committee (VQAC). Meetings with the committee, consisting of a
subset of the stakeholder groups involved in the SFEIS process, were used to present
and discuss proposed concept refinements. Based on the results of the various
studies undertaken, and input from the committee, a number of refinements were
incorporated.
A summary of the results of the concept refinement effort are as follows:
1.1 Pier Configuration
The VQM concept three‐column pier with a center column under the box girder
girders was revised to a two‐column pier by eliminating the center column.
Structural analysis determined that the center column was not necessary, and with
post‐tensioning the cross girder between the two columns had sufficient strength to
support the box girders. From a visual quality aspect, the removal of the center
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 12/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
1‐2 June 2010
column had been the desire of the Visual Quality Review Committee during the
development of the VQM, but structural feasibility needed to be confirmed before
this goal could be attained. In addition the form of the pier columns was refined to
improve constructability.
1.2 Box Girder
Configuration
Two box girder configurations were studied for the roadway deck, a two‐box girder
configuration as shown in the VQM, and a one‐box girder configuration. Structural
analysis and constructability studies determined that both configurations were
viable.
1.3 Pedestrian Trail Location
The VQM concept with the pedestrian trail outboard of the box girders and passing
around the north pier column was revised to an inboard configuration with the
pedestrian trail located on the box girder and passing inside of the north pier
column. This
configuration
was
a recommendation
of
the
CRAVE
Study
completed
in
November 2008. Various studies confirmed that this arrangement was similar in cost
to the concept, but with the benefit of improved constructability and long‐term
durability. With the trail located inboard of the column, pedestrian overlooks were
at the piers to permit people to stop and view the scenic river while removed from
through bicycle traffic. After review by the VQAC, it was determined that three
overlooks located at alternating piers within the river would be appropriate.
1.4 Cable Anchorage Details
The VQM concept with the anchorages exposed along the side of the box girders
was revised to cover the side face of the anchorages providing a smooth line along
the roadway edge. This was a recommendation of Sumitomo Mitsui Construction
Co., Ltd., the technical advisor for the project. The saw tooth appearance of the
exposed anchorages did not seem to be in harmony with the smooth curving forms
of the bridge. Visually the covered anchorage gives the bridge a much cleaner
appearance and the added vertical face provides additional protection from the
elements for the cable anchorage.
1.5 Approach and Ramps Span Arrangement
The VQM concept assumed typical spans of approximately 300 feet for the
Minnesota approach spans and ramps to minimize the number of piers at the
approach spans
that
extend
from
the
bluff
toward
the
shoreline
in
Minnesota.
The
approach spans and two ramp structures cross four wetland areas, with the primary
impacts from construction in Basin Q and Basin Q Forested. The 300‐foot span
arrangement proposed in the concept design would have required extensive
falsework. To reduce the impacts from construction on falsework, an alternate span
arrangement was developed that permitted a greater amount of balanced cantilever
segmental construction and reduced the wetland impacts. The long spans proposed
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 13/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 1‐3
in the concept design are not conducive to segmental construction, specifically at
spans adjacent to expansion joints and at bridge sections that vary in width. Both of
these conditions occur over the Basin Q wetlands.
1.6 Approach and Ramps Columns
The VQM
concept
has
twin
stem
piers
with
a 10
‐foot
space
between
the
stems.
Visually the piers had a heavy look and structurally the piers stiffness could not be
reduced without the stems becoming overly slender. To resolve these issues, an
alternate twin stem arrangement with a 5‐foot space between the stems and a
single stem pier were studied. The structural results proved that the single stem pier
was feasible and based on review by the VQAC, the single stem pier was selected. In
addition to structural and aesthetic benefits, the single stem column is more
economical and improves constructability.
1.7 Bridge Lighting
Bridge lighting
studies
were
performed
for
both
functional
lighting
and
architectural
lighting. Functional lighting consists of roadway lighting, pedestrian trail lighting,
aerial obstruction lighting, and navigation lighting. In addition a number of options
for architectural lighting were added to the functional lighting in photo visualizations
for review by the VQAC. Based on input from the VQAC it was determined that lower
lighting levels were preferred, and the proposed architectural lighting is limited to
lighting of the pier columns below the roadway. In combination with the roadway
and trail lighting, which provide low levels of light on the cables and columns above
the roadway, the desired effect is achieved.
This concept refinement report is not a final engineering report, and it is anticipated
that final
design
will
be
performed
by
others
under
a separate
contract.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 14/110
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 15/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 2‐1
2 Introduction
2.1 Project Description
This Concept Refinement Report has been developed by PB, under contract with the
MnDOT. PB will provide concept design and associated services for the proposed
new St.
Croix
River
Crossing
that
is
within
the
overall
St.
Croix
River
Crossing
Project:
Minnesota S.P. 8214‐114, S.P. 8214‐(82045), S.P. 8214‐(82047), S.P. 8214‐(82048)
and Wisconsin Project I.D. 1550‐00‐02. The overall St. Croix River Crossing Project
termini are along TH 36/STH 64 from TH 5 in Minnesota to 150th
Avenue in
Wisconsin. These services are part of the Preferred Alternative Package for the St.
Croix River Crossing Project as documented in the 2006 SFEIS.
2.1.1 Proposed River Crossing Description
The proposed St. Croix River Crossing is comprised of three separate bridges that are
identified as MnDOT Bridge Nos. 82045, 82047, and 82048.
The alignment
of
the
bridge
follows
a horizontally
curved
extension
of
the
TH
36
alignment that will pass just to the south of the Oak Park Heights water treatment
plant and north of the King Power Plant. The alignment continues on a tangent
across and approximately perpendicular to the river intersecting the bluffs in
Wisconsin, and continuing on to new alignment for STH 64. The bridge approach
spans, which extend from the Minnesota bluff to the river cross both high quality
wooded wetlands adjacent to the river and lower quality wetlands inland from the
river. An eastbound entrance ramp structure and westbound exit ramp structure
connect TH 36 to TH 95 in Minnesota.
Requirements for these bridges have been developed and are documented in two
reports, the
2006
SFEIS,
and
the
VQM
(January
2007).
Those requirements are summarized as follows:
The extradosed river spans will have no more than 6 piers in the water.
The extradosed towers vary in height from approximately 220 feet on the
Wisconsin side to approximately 170 feet on the Minnesota side (tower heights
are above normal pool elevation and include approximately 60 feet of tower
above the deck).
The extradosed span lengths are approximately 480 feet and the backspans
approximately 290 feet.
The extradosed typical section consists of two 12 foot lanes in each direction, 6
foot inside
shoulders,
10
foot
outside
shoulders,
and
a 12
foot
sidewalk
on
the
north side of the bridge.
Aesthetics, landscaping, and context sensitive designs are in the VQM.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 16/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
2‐2 June 2010
Mn/DOT Bridge 82045 (WisDOT Bridge B-55-224) (Mainline TH 36 and
STH 64)
Bridge No. 82045 spans Minnesota TH 95, the Union Pacific Railroad(UP R/R),
wetlands, and the St. Croix River. Its west abutment is located immediately west of
TH 95. Its east abutment is located on the Wisconsin river bluff. The total bridge
length from
abutment
to
abutment
is
approximately
5,040
feet.
The
bridge
is
comprised of main river spans with a length of approximately 3,460 feet and
westerly approach spans with a length of approximately 1610 feet. The river spans
have an extradosed superstructure that combines concrete box girders with cable
stays. The approach spans have a concrete box girder superstructure. The transition
from approach spans to river spans occurs at a common pier located just inland from
the Minnesota shoreline. The Minnesota approach spans to the river crossing have
lengths ranging from 180 to 300 feet.
Mn/DOT Bridge 82047 (TH 36WB off -ramp to TH 95)
Bridge
No.
82047
spans
the
UP
R/R,
local
roadways,
and
wetlands.
This
bridge
has
a
concrete box girder superstructure that frames into an approach span of Bridge
82045. The structure depth is directly related to that of the Bridge 82045 river spans.
The typical section has a variable lane width ranging from 16 to 32 feet, with 4 foot
inside and outside shoulders.
Mn/DOT Bridge 82048 (TH 36EB on-ramp from TH 95)
Bridge No. 82048 spans the UP R/R, local roadways, and wetlands. This bridge has a
concrete box girder superstructure that frames into an approach span of Bridge
82045. The structure depth is directly related to that of the Bridge 82045 river spans.
The typical section has a variable lane width ranging from 16 to 32 feet, and 4 foot
inside and
outside
shoulders.
2.2 Report Purpose and Objective
The Concept Refinement Report that will look at a number of items for investigation
described in further detail within the report.
The content of the report is separated into two divisions:
Division I is for the extradosed portion of Bridge 82045 (B‐55‐224),
Division II is for the approach spans of Bridge 82045 (B‐55‐224) and the ramp
Bridges 82047 and 82048.
Items
for
study
and
evaluation
will
include:
Structural Analysis
Bridge Lighting and Signing
Visual Quality
Construction
Maintenance and Inspection
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 17/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 2‐3
The report provides the results of the investigation and evaluation of risk for each of
the items listed above. The evaluation of risk for each item assesses and reports the
impacts to design feasibility, constructability, costs, schedule, environmental risks,
aesthetics, long term durability, maintenance, etc. In addition to detailed findings, a
risk analysis matrix is provided that summarizes the risk assessment for ease of
understanding.
The report is arranged in the following format and content:
Table of Contents
Executive Summary
Introduction
Acknowledgement of Commitments—The Report will cite commitments made in
project documents that affect the bridge. This includes such documents as the
SFEIS, Visual Quality Manual, etc.
Risk Evaluation
Content—Divisions I and II
Portions of the report may be incorporated into a future design build request for
proposal (RFP) for the project.
2.3 St. Croix River Crossing Development
A new river crossing near Stillwater to replace the aging lift bridge has been
discussed for many years. The first formal effort to replace the existing bridge began
in 1985 with a Draft Study and Scoping Document. The planning process moved
forward until 1995 when FHWA approved and Final Environmental Impact
Statement (FEIS). Final design began in 1995, but in 1996 the National Park Service
reacting to federal permit applications determined that the proposed bridge would
have an
adverse
effect
on
the
St.
Croix
River,
a part
of
the
National
Wild
and
Scenic
River System. With this determination, the federal permits could not be issued and
work on the new river crossing stopped.
Beginning in 1998 efforts to revive the river crossing began culminating in the
approval of an SFEIS in 2006. The visual appearance of the St. Croix River Crossing
and the context of the bridge within the wild and scenic riverway were critical
factors in the development of the new river crossing. As the SFEIS was developed
between 2004 and 2006, the extradosed bridge type was select for the main river
crossing through an extensive stakeholder process that involved local state and
federal government agencies, as well as, local and national citizen organizations. In
parallel with
the
SFEIS
process,
a VQM
was
developed
to
outline
the
aesthetic
values
for the project. A VQRC with member participation from all of the stakeholder
groups was a key part of the visual quality process. In addition the VQM process
included a public open house to gather public input for the aesthetic development
of the bridge.
For a complete history of the planning stages for the St. Croix River Crossing refer to
Chapter 1 of the 2006 Supplemental Final Environmental Impact Statement.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 18/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
2‐4 June 2010
2.4 General Definition of an Extradosed Bridge
The extradosed bridge concept was first proposed by French engineer Jacques
Mathivat in 1988. In the past 20 years over 40 extradosed bridges have been built
around the world, with the majority of the bridges built in Japan. The extradosed
bridge combines a prestressed girder bridge with a cable stayed bridge. With a span
to depth ratio of 30 to 35 compared to a typical prestressed girder bridge with a
span to depth ratio of 20 to 25, the economy of a shallower girder is realized with
the extradosed bridge. The tower height: span ratio of 1:8 compared to 1:4 for a
cable stayed bridge gives a structure height that is much less imposing than a cable
stayed bridge. Finally because of the relatively stiff girder, the extradosed bridge
permits allowable cable stresses of 0.6 f pu compared to 0.45 f pu for a cable stayed
bridge. This leads to the economy of fewer strands in the cables and a reduction in
the number of post‐tensioning tendons needed to support the bridge.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 19/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 3‐1
3 Acknowledgement of Commitments
3.1 Reference Documents
2006 Supplemental Final Environmental Impact Statement
Visual Quality
Manual
3.2 Commitments
This Concept Refinement Report and associated Concept Drawings have been
developed by PB, under contract with Mn/DOT. PB has performed this work in
accordance with the concepts and commitments included in the 2006 Supplemental
Final Environmental Impact Statement and the Visual Quality Manual.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 20/110
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 21/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 4‐1
4 Risk Evaluation
4.1 Risk Matrix and Summary
Risk management is an integral part of all phases of project delivery, from planning
and preliminary engineering through final design and construction. Risk
management is
the
systematic
process
of
identifying,
analyzing,
and
responding
to
project risk. Risk management must be conducted throughout the life of a project. A
standard dictionary definition of risk is: “exposure to the chance of injury or loss; a
hazard or dangerous chance”. In the design and construction of large transportation
projects there are inherent risks that must be explored as the project develops. At
the beginning, these variables, such as, subsurface geology, material quantities and
costs, and material and labor availability, are uncertain. As a project develops, these
risks begin to be to become less variable as information is gathered and engineering
evaluation begins. Risk assessment is used to evaluate risks as part of risk
management. The first step is to identify the risk factors. For the St. Croix River
Crossing, eight
specific
risk
factors
have
been
identified.
Each
of
the
five
report
areas
are to be assessed for these eight risk factors, with an additional risks assessed as a
ninth risk factor.
Assessment of risk is based on a scale from 1 to 3 for the probability of occurrence
(P), and on a scale of 1 to 3 for the severity of impact (I). Scoring is qualitative, with
low defined as 1, medium defined as 2, and high defined as 3. The risk score is the
multiple of P x I, such that the lowest risk is 1 and the highest risk is 9. The process is
illustrated in Figure 4‐1.
Figure 4‐1. Risk Assessment
In some cases a category may not be applicable, in which case, a value of 0 will be
applied. Table 4‐1 shows the summary of risk assessment.
Low Med High
L o w
M e d
H i g h
Impact (I) P r o
b a b i l i t y o f O c c u r r e n c e ( P )
Significant
Risk Area
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 22/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
4‐2 June 2010
Table 4‐1. Summary of Risk Assessment
Risk Factor
Structural
Analysis
Bridge
Lighting &
Signing
Visual
Quality Construction
Maintenance
& Inspection
Design feasibility 3 1 1 1 2
Constructability
2
1
2
1
1
Cost 4 1 2 6 1
Schedule 1 1 1 6 0
Environmental risks 1 1 1 3 1
Aesthetics 1 1 1 1 2
Long‐term durability 2 1 1 2 3
Maintenance 2 1 1 2 3
Total 16 8 10 22 13
Average 2.0 1.0 1.25 2.75 1.63
4.2 Investigation and Evaluation of Risk Factors
4.2.1 Structural Analysis
Design Feasibility
Probability (P): 1 Implementation of a QA/QC procedure in the design process
will help confirm the design is feasible.
Impact (I): 3 When a major error is found during construction, the impact to
cost and schedule is severe.
Constructability
Probability (P): 1 Proper constructability reviews will significantly reduce the
chance of construction problems.
Impact (I): 2 Errors found during construction can be corrected.
Costs
Probability (P): 2 Overly conservative design and/or design errors will increase
construction cost.
Impact (I): 2 Conservative design will not significantly increase construction
cost, but design error may.
Schedule
Probability (P): 1 Design may impact schedule. The design process should be
clearly defined and the review process integrated into the
design process, to permit timely reviews and issuing of
construction drawings.
Impact (I): 1 Lack of approved construction drawings can slow or stop
construction.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 23/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 4‐3
Environmental Risks
Probability (P): 1 Low risk.
Impact (I): 1 Low impact.
Aesthetics
Probability (P):
1
Low risk.
Impact (I): 1 Low impact.
Long-term Durability
Probability (P): 1 Proper analysis and design detailing will ensure the long‐term
durability of the structure.
Impact (I): 2 Serviceability issues can be corrected with remedial work, but
additional costs are incurred.
Maintenance
Probability (P):
1
Accessibility for
inspection
and
maintenance
must
be
considered throughout the design process.
Impact (I): 2 Accessibility for maintenance and inspection is of critical
importance.
4.2.2 Bridge Lighting and Signing
Design Feasibility
Probability (P): 1 Proposed bridge light and signing details are fairly standard.
Impact (I): 1 Low impact.
Constructability
Probability (P): 1 Proposed bridge light and signing details are fairly standard.
Impact (I): 1 Low Impact.
Costs
Probability (P): 1 Proposed bridge light and signing details are fairly standard.
Impact (I): 1 Low impact.
Schedule
Probability (P): 1 Proposed bridge light and signing details are fairly standard.
Impact (I): 1 Low impact.
Environmental Risks
Probability (P): 1 Spillover lighting can be assessed during lighting tests and
adjustments made as needed.
Impact (I): 1 Low impact.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 24/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
4‐4 June 2010
Aesthetics
Probability (P): 1 Planned aesthetic lighting levels are minimized to subtly
highlight the structure. Current modeling techniques allow
accurate design and visualization of the lighting system
Impact (I): 1 Low impact.
Long-term Durability
Probability (P): 1 LED fixtures have long operating life and are low cost to
operate.
Impact (I): 1 Low impact.
Maintenance
Probability (P): 1 LED fixtures have long operating life and are low cost to
operate.
Impact (I): 1 Low impact.
4.2.3 Visual Quality
Design Feasibility
Probability (P): 1 Preliminary engineering has vetted the design feasibility of the
aesthetic design elements of the bridge.
Impact (I): 1 Low impact.
Constructability
Probability (P): 1 The design features include many curved surfaces, but the
concept refinement has conformed the various surfaces to
standard geometric shapes.
Impact (I): 2 The many curved surfaces will provide more of a challenge than
construction with flat surfaces.
Costs
Probability (P): 2 The forming systems required for the various design elements
will cost more than standard forming systems.
Impact (I): 1 The repetitive use of these forming systems will minimize this
additional cost.
Schedule
Probability
(P):
1
Some
reduction
in
production
rates
may
occur
due
to
curved
form of the various design elements.
Impact (I): 1 As with all construction operations, there is a learning curve,
but as operations are repeated productivity increases.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 25/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 4‐5
Environmental Risks
Probability (P): 1 Visual impacts are addressed in the visual quality process,
which provides guidance to ensure the bridge fits into the
environment.
Impact (I): 1 Low impact.
Aesthetics
Probability (P): 1 The visual quality process has developed aesthetic standards
for the bridge.
Impact (I): 1 Low impact.
Long-term Durability
Probability (P): 1 The aesthetic features do no impact long‐term durability.
Impact (I): 1 Low Impact
Maintenance
Probability (P): 1 The aesthetic features do not impact maintenance.
Impact (I): 1 Low Impact
4.2.4 Construction
Design Feasibility
Probability (P): 1 The planned construction methods are included in the design
process using construction stage analyses to ensure that the
construction methods are feasible. The planned construction
methods are standard methods.
Impact
(I):
1
Coordinated
construction
planning
during
the
design
phase
will
limit design impacts.
Constructability
Probability (P): 1 The planned construction methods using concrete segmental
construction with either cast‐in‐place or precast segments are
standard methods used throughout the world.
Impact (I): 1 Coordinated constructability reviews during the design phase
will limit constructability impacts.
Costs
Probability
(P):
2
Foundation
construction
costs
are
less
defined
than
other
costs,
because preliminary foundation capacity is relatively low.
Impact (I): 3 Foundation costs are significant, and cost reduction or increase
can be significant.
Schedule
Probability (P): 2 Construction is the largest project activity and controls the
contract duration. Proper scheduling is critical.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 26/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
4‐6 June 2010
Impact (I): 3 The construction schedule must be closely monitored to ensure
that progress toward schedule completion is maintained. If the
schedule begins to slip, work around schedules, or
supplemental schedules must be developed to get the project
back on track.
Environmental Risks
Probability (P): 1 Construction operations by their very nature impact the
environment. Proper environmental standards and controls are
necessary to ensure environmental compliance.
Impact (I): 3 The Minnesota approach spans cross environmentally sensitive
wetlands and the St. Croix River is a national scenic waterway
with mussel beds near the Wisconsin shore. Uncontrolled and
unmonitored construction operations can had serious
environmental impacts. Construction debris, excavated soils,
and petroleum products are among the numerous items that
can cause
environmental
damage.
Aesthetics
Probability (P): 1 Proper workmanship is utmost importance to produce finished
work of the specified quality.
Impact (I): 1 Typical finishing methods will remedy minor workmanship
errors.
Long-term Durability
Probability (P): 1 Material controls and construction QA/QC programs must be
implemented and maintained to ensure that the requirements
of the
plans
and
specifications
are
incorporated
into
the
work.
Impact (I): 2 Incorporating specified materials using proper construction
methods and workmanship are critical to long‐term durability.
Out of specification metal products and/or concrete will have a
detrimental effect on long‐term structure performance.
Maintenance
Probability (P): 1 See Long‐term Durability.
Impact (I): 2 See Long‐term Durability.
4.2.5 Maintenance and Inspection
Design Feasibility
Probability (P): 1 Design details will affect maintenance and inspection.
Maintenance and inspection should be considered throughout
the design process.
Impact (I): 2 Design that does not include consideration of maintenance and
inspection access will impact operations.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 27/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 4‐7
Constructability
Probability (P): 1 Maintenance and Inspection have little impact on
constructability.
Impact (I): 1
Costs
Probability (P): 1 Inspection and maintenance are directly related to cost.
Impact (I): 1 The cost of future maintenance and inspection is directly linked
to accessibility.
Schedule
Probability (P): 0 None.
Impact (I): 0 None.
Environmental Risks
Probability (P):
1
The maintenance
of
the
bridge
drainage
system
is
critical.
Impact (I): 1 Leakage of bridge drainage must be repaired quickly. The
overflow trough will limit leakage until repairs are made.
Aesthetics
Probability (P): 1 The architectural surface treatment is long lasting are requires
little maintenance.
Impact (I): 2 Lack of maintenance will have a negative impact on the
structures appearance.
Long-term Durability
Probability (P):
1
The long
‐term
durability
of
the
bridge
depends
on
the
inspection and maintenance programs, but concrete segmental
bridges are among the most durable bridges.
Impact (I): 3 Poor inspection and maintenance can greatly reduce the life
span of the bridge. For a concrete segmental bridge the parts
that are most vulnerable to wear and bearings and expansion
joints. In addition the stay cables of an extradosed bridge are
key structural components. The anchorages and cable
sheathing need to be inspected on a systematic basis.
Maintenance
Probability (P):
1
See Long
‐term
Durability.
Impact (I): 3 See Long‐term Durability.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 28/110
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 29/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 5‐1
5 Division I Structural Analysis
5.1 Introduction
The extradosed river spans for the St. Croix River Crossing are designated Mn/DOT
Br. No. 82045 (WisDOT Bridge B‐55‐224)(Mainline TH 36 and STH 64). For the
purpose of
this
report,
the
baseline
structure
is
defined
as
a structure
that
conforms
to the structural configuration presented in the VQM. The baseline structure is an
eight‐span, extradosed structure with a length of 3,460 feet, and a span
arrangement of 290 feet—480 feet—480 feet—480 feet—480 feet—480 feet—
480 feet—290 feet. Of the seven piers, six are located in the river with one pier
located on the Wisconsin bluff. The baseline structure’s configuration is such that
the seven piers consist of three columns below roadway level, with the two exterior
columns extending above the roadway as towers for anchoring of the extradosed
cables. The baseline superstructure is comprised of two concrete segmental box
girders connected by full‐depth diaphragms at the cable support locations. The
cables are
arranged
in
two
planes
and
anchor
in
an
anchor
pod
at
the
exterior
edge
of each box girder, with typical spacing of 20 feet between cables. There are a total
of 252 cables, with 36 cables anchored at each pier. The exterior piers extend
60 feet above the roadway, thus giving a tower vs. span ratio of 1:8, which is ideal
for an extradosed bridge. Various modifications to the baseline structure have been
made in order to satisfy the goals of the objectives. These modifications to the
baseline structure are described in the following sections of this report.
5.2 Objectives
The specific concept refinement program consists of developing appropriate
structural
models
and
performing
structural
analyses
to
determine
the
adequacy
and feasibility of the proposed concept design. As previously described, the baseline
model conforms to the structural configuration presented in the VQM. The
structural analysis utilizes a global model for longitudinal and transverse effects, and
localized modeling performed at two “points of interest” identified during the global
modeling. In addition to the general analysis task, specific investigations and
evaluations will include the following:
Base Modeling
Superstructure Cross‐section Investigation
Pier Investigation
Fixity/Longitudinal Movement Investigation
Grade Induced
Movement
Investigation
Two Box Girder Load Distribution Investigation
Wind Load—Vibration Analysis Evaluation
Back span Uplift Investigation
Extradosed Stay Cable Analysis
Points of Interest—Local Analysis
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 30/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
5‐2 June 2010
5.3 Base Modeling
The base model is configured according to the structure previously defined in the
VQM. The analysis of the bridge was carried out using a three‐dimensional (3‐D)
structural model of the bridge, including explicitly modeled foundation elements
with non‐linear springs to represent the soil properties. The superstructure and
substructure components are modeled using beam elements with prismatic section
properties. The stay cables are modeled as truss elements. The superstructure’s two
box girders are modeled independently and are connected by transverse members
at each cable connection location. The double stem portion of the pier columns are
also modeled independently to more realistically simulate the longitudinal stiffness.
The model simulates the anticipated construction sequence and duration to capture
the locked‐in dead load forces from construction and to simulate the long‐term
effects of creep and shrinkage on the structure. This model, as shown in Figure 5‐1,
is used for all global longitudinal analyses, with modifications incorporated as
preliminary results determined that proposed refinements were structurally
feasible.
Figure 5‐1. Stick (top) and Rendered (bottom) Isometric View of Global Model
5.4 Longitudinal
Analysis
As with all segmental bridges, the design of a segmental extradosed bridge is
dependent on the construction sequence used to build the bridge. For the St. Croix
River Crossing, the structural arrangement conforms to a balanced cantilever
construction sequence, as shown in Figure 5‐2. As with any segmental bridge built in
balanced cantilever fashion, the substructure consisting of the foundation and pier is
built first followed by construction of the superstructure girder. Segments of the
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 31/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 5‐3
girder are either cast on a form traveler for cast‐in‐place construction or erected
using a deck mounted lifting system or land/water‐based crane for precast
construction. As each segment is cast, or in the case of precast, as each pair of
segments is erected, cantilever post‐tensioning tendons in the top flange that
anchor at the ends of the two cantilevers are installed and stressed. In addition, for
the extradosed
structure,
the
cables
are
installed
and
stressed
and
cantilever
construction progresses.
Figure 5‐2. Rendered Isometric View of Global Model Showing Construction Sequence
The construction at the various piers can proceed in a number of sequences, but
typically construction either proceeds from one end of the structure to the other
end, or from both ends toward the middle. As balanced cantilever construction is
completed at a pier nearest to an abutment, a number of segments adjacent to the
abutment are supported on temporary falsework. A closure segment is cast between
the two sections of girder, and continuity post‐tensioning tendons in the bottom
flange are installed and stressed to make the first continuous span. As cantilever
construction is completed at subsequent piers, a closure segment is cast between
adjacent sections
of
girder,
and
continuity
post
‐tensioning
tendons
in
the
bottom
flange are installed and stressed to make the span continuous.
In addition to the changing structural system as the cantilevers are constructed and
the spans are made continuous, time dependent effects due to increasing concrete
strength, concrete creep and shrinkage, and post‐tensioning steel relaxation must be
considered in the design of segmental structures. Once the structure is completed,
the time dependent effects continue to occur, and the analysis evaluates these
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 32/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
5‐4 June 2010
effects for a predetermined time interval, typically to 10,000 days, which is defined
as time infinity, when it is assumed all time dependent effects have occurred.
Following the 10,000‐day analyses, external loads such as truck and wind forces are
applied to the completed structure. Stresses are checked for conformance within
AASHTO LRFD limits. These stress checks include limit states during and after
construction. A
girder
stress
profile
displaying
service
load
stresses
is
shown
in
Figure 5‐3.
Figure 5‐3. Box Girder Stress along Length of Bridge
5.5 Transverse Analysis
The extradosed bridge configuration in the VQM consists of two cable planes, which
are connected to the superstructure along the outside edge of each box girder.
Transverse members between the box girders are required to transfer and balance
the forces imposed by the stay cables in addition to transferring unbalanced live
loads between
the
individual
box
girders,
as
shown
in
Figure
5‐4.
The
lower
member
primarily resists tension forces and the upper closure pour member resists
compression forces as well as vertical shear forces caused by unbalanced live loads.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 33/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 5‐5
Figure 5‐4. Transverse Framing at Cable Connection
To determine the demands on the transverse members, a 3D analytical model of a
representative span was created. The box girders were modeled using plate
elements and the transverse members were modeled using beam elements. Various
live load conditions were studied as well as the forces induced in the members
during the stressing of the stay cables during construction. As a result of the
analysis, it has been determined that a post‐tensioning tendon of 24 strands is
required and
the
4 foot
deep
closure
pour
of
the
top
flange
is
sufficient
to
resist
compression and shear.
5.6 Superstructure Cross-section Investigation
The superstructure of the baseline structure described in the VQM consists of two
concrete segmental box girders connected by full depth diaphragms at the cable
support locations, as shown in Figure 5‐5. The box girders are comprised of a 3‐cell
cross‐section, with two vertical interior webs and two inclined exterior webs. The
box girders are 20 feet deep and 42.25 feet wide at the top flange or roadway level,
with a 16.0‐foot width at the girder soffit. The exterior webs and soffit have circular
curved faces
with
a radius
of
66.0
feet.
The
individual
curves
meet
at
the
web
‐soffit
intersection, forming an angular break point. The exterior webs curve to vertical at
roadway level by the addition of a smaller radius curve at the top 3 feet of the web.
The top flange of the box girder is haunched adjacent to each web to provide room
for post‐tensioning anchorages on either side of the interior webs, and on the
interior side of the exterior webs. The bottom flange is similarly haunched adjacent
to the interior webs to permit the top surface of the flange to follow the curved
soffit face and reduce the flange thickness at the midspan between the webs.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 34/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
5‐6 June 2010
Figure 5‐5. Baseline Box Girder Superstructure
The baseline
pedestrian
trail
cantilevers
from
the
edge
of
the
northern
box
girder,
outside the north cable plane. The trail consists of a sidewalk slab supported by
concrete brackets attached to the box girder at the same interval as the cable
diaphragms. This trail curves outward and around the north column at each pier.
Several aspects of the superstructure cross section were evaluated during the
project, which include girder depth, feasibility of a single box girder superstructure
and transverse diaphragm requirements. Another item investigated was the
feasibility and possible benefits of integrating the cantilevered pedestrian trail with
the box girder, as recommended in the Cost Reduction and Value Engineering
(CRAVE) Study.
5.7 Inboard Pedestrian Trail
After discussions with Mn/DOT, WisDOT and the VQAC, the cantilevered pedestrian
trail has been integrated with the box section. The trail is now located inboard of the
north cable plane. The recommendation is based on improved constructability,
improved operations, ease of maintenance and inspection, and potential cost
savings. More information regarding the benefits of integrating the pedestrian trail
with the box girder can be found in the Visual Quality Section of this report. The
overall shape and symmetry among the two box girders is maintained, however, the
median barrier is no longer located at the centerline of the bridge. Each box girder is
widened to a width of 49’‐3” and the median barrier is shifted 6’‐7” south of the
centerline of the bridge. The proposed section showing the revised configuration is shown in Figure 5‐6.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 35/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 5‐7
Figure 5‐6. Proposed Box Girder Showing the Reduced Depth and Integrated Pedestrian Trail
5.8 Box Girder Depth
As previously
mentioned,
the
box
girder
illustrated
in
the
VQM
has
a constant
depth
of 20 feet. After evaluating the longitudinal demands on the girder, it was concluded
that from a structural perspective, a 20 foot deep girder is not required. It has been
determined that a box girder depth of 16 feet is more advantageous. The 16 foot
deep girder was found to be more economical and more compatible with the
approach spans, while still maintaining the architectural proportions described in
the VQM. The shallower box girder is lighter and more efficient, especially since the
girder has a constant depth along the length of the spans. Our studies also indicate
that the 16‐foot deep girder alternative is approximately $12.50 per square foot of
bridge area less expensive than the 20‐foot deep girder alternative, as shown in
Table
5‐
1.
The
overall
shape
and
general
dimensions
of
the
shallower
girder
remain
the same.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 36/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
5‐8 June 2010
Table 5‐1. Box Girder Depth Cost Comparison
Bridge length ................................................ 3,460 ft
Number of piers ............................................ 7
Pier cross girder width .................................. 20 ft
Girder length ................................................ 3,320 ft
Bridge area ................................................... 354,000 sf
Concrete unit cost ........................................ $700.00/cy
Reinforcing, epoxy coated unit cost ............. $1.25/lb
Reinforcing weight ........................................ 250 lb/cy
Box Girder
Depth (ft)
Cross‐
section
Area (sf)
Web Width
(ft)
Concrete
Volume (cy)
Concrete
Cost ($)
Reinforcing
Cost ($)
Total Cost
Reduction
20 175.140 1.25 43,071 30,150,027 13,459,833
16 157.313 1.50 38,687 27,081,142 12,089,795
Difference ‐
4,384
(3,068,885)
(1,370,038)
(4,438,923.00)
Difference per sf (12.54)
5.9 Single Box Girder Feasibility
According to the VQM, both a single box girder and a double box girder
superstructure are acceptable alternatives. The basic configuration of both
superstructure alternatives is shown in Figure 5‐7.
Both alternatives have been evaluated from structural, constructability, and
architectural perspectives. Based on our analysis and engineering judgment, it has
been concluded
that
the
single
box
girder
alternative
is
feasible.
It
has
also
been
determined that the optimal superstructure depth for the single box girder
alternative is 16 feet. From a constructability perspective, the double box girder
alternative would most likely be constructed using precast segments and the single
box alternative would most likely constructed by casting the segments in place using
a form traveler, due to the size and weight of the segment as the weight of a single
box girder is too large for typical erection equipment. In terms of construction
duration, it is believed that the double box girder alternative would require less time
to construct since the precast segments can be cast concurrently with the
construction of the bridge substructure.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 37/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 5‐9
Figure 5‐7. Typical Sections
5.10 Transverse Diaphragm investigation
Although it is not explicitly stated, it appears that the structural systems shown in
the VQM utilize full depth diaphragms located at each cable. After conducting a
transverse analysis on the structure, it has been determined that full depth
diaphragms are not required. Instead, a much lighter transverse tie member and
partial depth diaphragms inside the girder are proposed. The post‐tensioned tie
member will most likely be constructed as a precast element. For additional
information on the transverse diaphragms, please see the Transverse Analysis
section of this report.
5.11 Pier Investigation
As shown in the VQM (baseline structure) and in Figure 5‐8, the deck is supported at
each pier by the two outside columns, which extend above the deck for anchoring of
the extradosed cables and one center column that terminates at the cross girder at
deck level. The pier configurations shown in the VQM have a constant height of
60 feet
above
the
girder,
and
so
therefore
vary
in
height
above
the
water
line
from
170 feet at the pier closest to the Minnesota shore to 212 feet at the pier on the
Wisconsin bluff. The pier columns are generally conical in shape with varying
dimensions from top to bottom, with the smaller dimension at the top of the pier.
The interior column is split into two stems below the girder, and combines into a
single column 104 feet below the roadway level. The exterior columns are split into
two stems from the top of the pier to 104 feet below the roadway level, with the
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 38/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
5‐10 June 2010
exception of the tower anchor housing, which extends from just below the top of
column to 17 feet above the girder. The exterior column stem connection occurs
only at the upstream and downstream face of the column, creating a C‐shaped
column in cross‐section. The three columns in the baseline structure are connected
by a 20‐foot wide by 25‐foot deep rectangular shaped cross girder at the roadway
level. The
cross
girder
is
a hollow
section
between
columns
with
5‐foot
thickness
for
the top and bottom flanges, and the two webs. At the columns, the cross girder has
a solid cross‐section comprised of a diaphragm infill in addition to the flange and
web section. Since it has been determined to reduce the depth of the superstructure
box girder from 20 feet to 16 feet, the cross girder depth has also been reduced the
same amount to maintain similar proportions shown in the VQM. The proposed
cross girder depth is 21 feet.
Figure 5‐8. VQM Baseline Pier Configuration
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 39/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 5‐11
The Visual Quality Advisory Committee’s preference is to have only the two stay
tower columns at each pier (eliminate the center column) to maintain the “light and
elegant” appearance of the chosen “Organic” design concept. The pier investigation
evaluated the feasibility of a two column design in place of the three column design
presented in the VQM. The evaluation considers the advantages and disadvantages
of cost,
constructability,
and
aesthetics
including
impact
to
the
overall
appearance
of the two column option compared to the three column option.
There are three critical components to be considered when determining the
feasibility of the two column alternative. The first item is the location and number of
the expansion joints on the bridge. It is preferred to have all eight extradosed spans
be continuous with expansion joints only at Pier 7 and the East Abutment. Having
the expansion joints only at the ends of the extradosed bridge create significant
demands on Piers 8 and 14 due to the longitudinal displacements from the thermal
loads and long term creep and shrinkage. The second item is the stiffness of the
individual pier columns. The pier cross girder strength is the third critical component
in determining
the
feasibility
of
tower
bents
consisting
of
two,
rather
than
three,
column legs. Since the superstructure is integrally connected to the substructure at
all piers, the pier cross girder is subjected to sizeable shear, vertical bending and
torsion.
Based on our analysis and our engineering judgment, it has been determined that
the two pier columns alternative is feasible. The two columns have adequate
capacity to resist the imposed loads and deformations. The relatively tall and slender
double stem section of the pier column provide adequate flexibility to accommodate
the longitudinal displacement demands from thermal effects and long term creep
and shrinkage. Although it is relatively minimal, additional flexibility of the
substructure is
provided
by
the
drilled
shaft
foundation.
Even
though
it
is
not
the
shortest pier, Pier 8 controls the design. This is due to shallow rock at the footing
location, resulting relatively short, stiff drilled shafts. The double stem sections of
the columns are the controlling component of the pier design. Utilizing the cracked
section properties, the double stem section will require approximately 2%
reinforcement, which is a feasible amount. It has also been determined that the
proposed cross girder has adequate strength to resist the imposed loads. The
proposed pier configuration is shown in Figure 5‐9. For additional information,
please see the Fixity / Longitudinal Movement Investigation section of this report.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 40/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
5‐12 June 2010
Figure 5‐9. Proposed Pier Configuration
5.12 Fixity/Longitudinal Movement Investigation
The fixity/longitudinal movement investigation evaluated the pier and bearing fixity
requirements, pier stiffness effects due to thermal movements, and other issues
unique to long, continuous bridges. As the superstructure shortens due to thermal
effects and long‐term creep and shrinkage, the pier columns are deflected and the
pier cross girders are subjected to torsional effects. Based on our analysis and our
engineering judgment, it has been determined that the eight span extradosed
portion
of
Bridge
82045
(B‐
55‐
224)
can
be
made
continuous
with
expansion
joints
only at Pier 7 and the East Abutment. The relatively tall and slender double stem
section of the pier columns provide adequate flexibility to accommodate the
longitudinal displacement demands from thermal effects and long term creep and
shrinkage, as shown in Figure 5‐10. Although it is relatively minimal, additional
flexibility of the substructure is provided by the drilled shaft foundation. Even
though it is not the shortest (therefore stiffest) pier, Pier 8 controls the design. This
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 41/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 5‐13
is due to shallow rock at the footing location, resulting relatively short, stiff drilled
shafts.
The expected movement of the extradosed bridge due to thermal effects is
approximately +/‐ 8 inches and the expected shortening of the superstructure due to
creep and shrinkage is approximately 6 inches. This results in the expansion joint at
the east
abutment
having
a movement
rating
of
26
inches
and
the
expansion
joint
at
Pier 7 having a movement rating of 38 inches. The increased expansion joint size at
Pier 7 accounts for the movement of the approach structure. Please see the Pier
Investigation section of this document for more information.
Figure 5‐10. Deflected Pier Shape
5.13 Grade Induced Movement Investigation
The bridge is on a constant +1.74% grade traveling toward Wisconsin. An
investigation to evaluate the tendency of the bridge to move permanently in the
downhill direction was conducted. It has been concluded that the bridge is not
susceptible to grade induced movements. The frame action of the integral pier
configuration alleviates this movement.
5.14 Two Box Girder Load Distribution Investigation
The two box girder load distribution investigation evaluated the requirements for
transfer of transverse loads in the regions along the bridge where cable stays and
diaphragms do not exist, as shown in Figure 5‐11.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 42/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
5‐14 June 2010
Figure 5‐11. Superstructure between Cable Supports
Once the closure between the individual girders is complete, the two girders no
longer act independently, but instead behave as if they are one. As shown in
Figure 5‐12, the deflection of both box girders is approximately the same when only
one box girder is subjected to full live load.
Figure 5‐12. Transverse Analysis
It has been determined that the closure pour between the two box girders is
sufficient to transfer unbalanced live loads and to prevent differential deflection
between the individual box girders. To improve the long‐term service
performance of the closure, transverse post‐tensioning will be integrated into
the design.
A
detail
of
the
proposed
closure
pour
is
shown
in
Figure
5‐13.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 43/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 5‐15
Figure 5‐13. Closure Pour Detail
5.15 Wind Load—Vibration Analysis Investigation
Long span bridges tend to be excited by dynamic wind load. The St. Croix River
Bridge River Crossing is a long span bridge with six 480’ spans. While the bridge is
extradosed type, it is actually a box girder bridge with partially exposed post‐
tensioning tendons
and
therefore
the
bridge
behavior
is
very
close
to
traditional
box
girder bridges. There are long span box girder bridges in Japan and other countries
that have experienced large vibrations under wind load and there is a possibility that
this bridge might also experience wind induced vibration. A study for the
vulnerability to excessive vibration has been performed and is discussed below.
An Eigenvalue dynamic analysis was performed on the St Croix River Crossing and
some modes of vibration are shown in Figure 5‐14. The period of the first vertical
mode is approximately 1.0 second. The period of the first torsional mode is found to
be approximately 0.5 second. The ratio of the first vertical mode to the first torsional
mode is approximately 2. Based on previous experience, when this ratio is near the
range of
2 to
3,
the
bridge
has
higher
possibility
of
wind
induced
vibration.
Therefore, a detailed wind study is deemed necessary during final design of this
bridge.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 44/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
5‐16 June 2010
Figure 5‐14. Mode Shapes from the Eigenvalue Dynamic Analysis
Bridge structural dynamic response to wind is commonly studied by performing
wind tunnel tests. An aero elastic model wind tunnel test can cover all modes of the
bridge and provide a realistic prediction of the bridge dynamic response to wind. A
partially completed structure is more vulnerable than a complete structure. The
most vulnerable condition of this bridge is before the spans are closed and while the
cantilever arms are the longest. Therefore, several critical construction conditions in
addition to the complete bridge are recommended for detailed study.
In accordance with these findings, it is recommended that the design criteria include
aerodynamic evaluation of the bridge with the testing criteria listed as follows:
13.3.3.1.10 Aerodynamic Evaluation
A wind expert shall perform wind data collection and analysis to
determine the design wind speed.
The aerodynamic stability of the structure shall be determined by
performing wind
tunnel
tests
on
aero
‐elastic
models
of
the
structure.
A buffeting analysis shall be performed based on the data measured
from the wind tunnel tests.
The buffeting analysis will generate equivalent static wind loads to
the structure. Aero‐elastic model wind tunnel tests shall include
critical construction conditions as well as the completed structure.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 45/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 5‐17
Large amplitude vibration of some stay cables in light rain and low wind has been
observed in of some cable stayed bridges around the world. This phenomenon is
called rain‐wind induced vibration. The stay cable industry has developed several
means to counteract this vibration. The most commonly used method is a spiral bar
placed around the PE pipe. This has been proven a very effective Measure and it is
recommended that
this
type
of
PE
pipe
be
required
for
the
St
Croix
River
Crossing.
The allowable stress in the cables of the extradosed bridge is 0.6 FGUTS or 162 ksi.
The allowable stress in the cables of cable‐stayed bridge is 0.45 FGUTS or 122 ksi.
The higher allowable tensile stress in the extradosed bridge has the effect of
lowering the possibility of excessive vibration.
The Contractor will be required to design the cables in accordance with PTI
Guide Specifications Recommendations for Stay Cable Design, Testing and
Installation, 3rd and 5th Editions. A properly designed cable is not expected to
experience wind induced vibration.
5.15.1 Back span Uplift/Maximum Back span Length Investigation
The back
span
uplift/maximum
back
span
length
investigation
evaluated
the
potential for uplift at the back span piers. It has been determined that the current
configuration of the spans does not result in uplift. One of the main reasons there is
no uplift is that the live load to dead load ratio on the extradosed bridge is quite low.
Another reason is that the proposed back span length is 290 feet, which is 50 feet
longer than half of the main span. The additional 50 feet of span length on the back
span effectively acts a counterweight to resist the uplifting forces when the main
span is fully loaded. The integral framing of the superstructure to the substructure at
the main piers is effective at resisting the longitudinal rotation of the superstructure
caused by the fully loaded main span, which also limits the ability of the back span to
uplift. It
had
been
determined
that
the
minimum
service
load
bearing
reaction
at
the
back span support is approximately 800 kips, based on a two bearing per girder
configuration.
5.16 Extradosed Stay Cable Analysis
The cables of the baseline structure are arranged in two planes and anchor in an
anchor pod at the exterior edge of each box girder, with typical spacing of 20 feet
between cables, as shown in Figure 5‐15. There are a total of 252 cables, with 36
cables anchored at each pier.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 46/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
5‐18 June 2010
Figure 5‐15. Extradosed Stay Cable Configuration
The cables are connected to the tower starting 22 feet above the roadway level,
with typical
spacing
of
4 feet
between
cables
at
centerline
of
pier.
The
cables
are
either anchored to the tower within a steel anchorage housing. The cables are
connected to the box girder at anchorage pods spaced at 20 feet along the exterior
edges of the two box girders. There are nine anchorage pods along each edge up
station and down station from the pier. The first cable pair is located 55 feet from
the centerline of pier, with the ninth cable pair located 215 feet from centerline of
pier. This leaves a space of 50 feet in the midspan between the ninth cable pair of
adjacent piers. The angle of the cables from the horizontal plane varies from 14
degrees to 22 degrees. At each anchorage pod there is a diaphragm connecting the
box girders together.
The extradosed
cables
were
initially
sized
assuming
that
they
would
resist
approximately 60% of the dead load moment of the cantilever prior to closure.
Following this initial sizing, the average cable tension (1250 kips) was selected to be
applied to each extradosed cable upon installation.
According to the Cable Stays Recommendations of the French Interministerial
Commission of Pre‐stressing, stay cables with a change in stress caused by live load
of less than 7.2 ksi are considered extradosed. The standard limits the cable tension
to 60% of the guaranteed ultimate tensile strength, that is, 0.6 GUTS, under the
effects of maximum service loading. It has been determined that the stress variation
caused by live load (HL‐93 with no pedestrian load) on the St. Croix River Bridge is
approximately 4 ksi
(as
shown
in
Figure
5‐16),
which
defines
the
cables
as
extradosed. Utilizing the allowable tension limit of 0.6 FGUTS, all cables are comprised
of 37 0.6‐inch diameter strands.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 47/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 5‐19
Figure 5‐16. Live Load Stress Range
5.17 Points of Interest—Local Analysis Two “points of interest” were identified during the global modeling. The first
location is the integral pier cross girder to column connection, which is a complex
area and critical component to the feasibility of the structure. A localized finite
element model was generated to study the force flow, stress concentrations and
deformations within the integral connection. The forces input into the localized
models have been derived from the global analytical model. The results of the
localized analysis indicate that proposed integral connection is still feasible.
However, there will be areas of stress concentration that will need to be addressed
during final design. Various stress diagrams can be seen in Figure 5‐17 through
Figure 5‐19.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 48/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
5‐20 June 2010
Figure 5‐17. Local Model of Integral Pier (Bottom View)
Figure 5‐18. Local Model of Integral Pier (Top View)
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 49/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 5‐21
Figure 5‐19. Pier Cross Girder Interface Model
The second area of interest is the configuration of the first two spans (spans 8 and 9)
of the extradosed bridge, which have a variable width superstructure caused by the
merging of Ramps SE and NE into the mainline. The majority of the width variation is
within span 8, in which the width varies from 135 feet at Pier 7 to 110 feet at Pier 8.
Special consideration of the framing of span 8 is required due to its increased width.
It should also be noted that in addition to the increased width, the super elevation is
also varying along the length of span 8. Although it doesn’t have a major impact on
the framing, the varying super elevation must be considered in the cross girder and
extradosed stay cable design. There are several viable alternatives, but one solution
is shown in Figure 5‐20 through Figure 5‐22. The proposed configuration utilizes a
precast truss member between the two precast box girders. This maintains a similar
“open” appearance to the rest of the extradosed structure as well as maintaining
the same geometry for the box girders.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 50/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
5‐22 June 2010
Figure 5‐20. Pier 8 Elevation Showing Widened Superstructure and Full Super Elevation
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 51/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 5‐23
Figure 5‐21. Span 8 Typical Section
Figure 5‐22. Isometric View of Precast Truss
To
determine
the
demands
on
the
transverse
members,
a
3D
analytical
model
of
a
representative span was created as shown in Figure 5‐23. The box girders were
modeled using plate elements and the transverse members were modeled using
beam elements. Various live load conditions were studied as well as the forces
induced in the members during the initial stressing of the stay cables during
construction. Based on the results from the localized and global analysis, it can be
concluded that the proposed precast truss alternative is feasible. The light weight
strut design will also keep the extradosed stay cable force increase to a minimum.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 52/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
5‐24 June 2010
Figure 5‐23. Isometric View of 3D Analysis
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 53/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 6‐1
6 Division II Structural Analysis
6.1 Introduction and Objectives
There are three bridges in this portion of the work: Bridge No. 82045 (Mainline TH
36 approach units), Bridge No. 82047 (TH 36WB off ‐ramp to TH 95), and Bridge No.
82048 (TH
36EB
on
‐ramp
from
TH
95).
The
typical
mainline
superstructure
is
comprised of two parallel concrete segmental box girders connected by a closure
pour at the top flange, while the ramp superstructures are a single concrete
segmental box girder. The baseline model piers are twin stem wall type that is
connected monolithically to the superstructure, with the exception of the mainline
pier nearest to the abutment that is a single column with bearings. The approach
span adjacent to the extradosed river spans is a transition span that has a wider
cross‐section to accommodate the on‐ramp and off ‐ramp lanes.
The concept refinement program consisted of developing appropriate structural
models and performing structural analyses to evaluate the adequacy of the
proposed design
concept.
The
baseline
model
conforms
to
the
structural
configuration presented in the VQM and the Mn/DOT‐provided roadway design files.
Variations on the baseline model were developed as the layout and construction
impacts were examined for reduction of impact and overall technical enhancement.
These variations were designated R1, R2, etc., to indicate the layout version being
modeled. Subsequent sections describe the baseline model and interpretation of the
VQM.
The modeling approach utilized global modeling for longitudinal and transverse
effects, and localized modeling was performed at “points of interest” identified
during the global modeling. In addition to the general analysis task, specific
investigations and
evaluations
included
the
following:
6.1.1 Box Girder Width Transition Investigation
The box girder width transition investigation evaluated the transition in box girder
width at the ramp termini, on the Minnesota side, and investigated options for
transitioning the box girders at the ramp termini. The transition was kept off of the
back span of the extradosed portion of the river crossing to the greatest extent
possible.
6.1.2 Box Girder Depth Economy Investigation
The box girder depth economy investigation evaluated ways to economize the depth
of the box girder section from the west abutment to pier 6. As referenced in the
VQM, the depth of section of the first 6 spans varies from 10 feet to 20 feet. The 10‐
foot depth is required to provide vertical clearance over TH 95 in Span 1 and the 20‐
foot depth is required to match the depth of the extradosed spans.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 54/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
6‐2 June 2010
6.1.3 Fixity/Longitudinal Movement Investigation
The fixity/longitudinal movement investigation evaluated pier and bearing fixity
requirements, pier stiffness effects due to thermal movements, and other issues
unique to long, continuous bridges. Continuous structures are desired with
expansion joints only expected to be at the ends of the extradosed spans and the
west abutment.
6.1.4 Grade Induced Movement Investigation
The grade induced movement investigation evaluated potential of the bridge to
move permanently in the downhill direction and provide performance requirements
for a Design‐Build RFP. The Minnesota approach spans of Bridge 82045 (B‐55‐224)
are on a ‐1.25% grade traveling toward Wisconsin.
6.1.5 Box Girder Depth Transition Investigation
The box girder depth transition investigation evaluated recommendations regarding
the location of the box girder depth transition. There are vertical clearance
restrictions over TH 95 at the first span of the river bridge approach spans that necessitate a 10‐foot maximum structure depth. The structure depth must increase
at some location after spanning over TH 95 to accommodate longer span lengths
and to match the depth of the extradosed spans. In the concept plan shown in the
VQM, the depth transition begins in Span 1 just east of TH 95 and terminates at
Pier 2.
6.2 Investigation Methods: Longitudinal Analysis
As with all segmental bridges, the design is dependent on the construction sequence
used to build the bridge. For the St. Croix River Crossing, the structural arrangement
conforms to
a balanced
cantilever
construction
sequence.
The
substructure
consisting of the foundation and pier is built first followed by construction of the
superstructure girder. Segments of the girder are either cast on a form traveler for
cast‐in‐place construction or erected using a deck mounted lifting system or
land/water‐based crane for precast construction. As each segment is cast, or in the
case of precast, as each pair of segments is erected, cantilever post‐tensioning
tendons in the top flange that anchor at the ends of the two cantilevers are installed
and stressed.
The construction at the various piers can proceed in a number of sequences, but
typically construction proceeds from one end of the structure to the other end. As
balanced cantilever
construction
is
completed
at
a pier
nearest
to
an
abutment,
a
number of segments adjacent to the abutment are supported on temporary
falsework. A closure segment is cast between the two sections of girder, and
continuity post‐tensioning tendons in the bottom flange are installed and stressed to
make the fist continuous span. As cantilever construction is completed at
subsequent piers, a closure segment is cast between adjacent sections of girder, and
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 55/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 6‐3
continuity post‐tensioning tendons in the bottom flange are installed and stressed to
make the span continuous.
Cantilever construction and
the span closures change the
structural system. Coinciding
with these
changes
are
time
dependent effects due to
increasing concrete strength,
concrete creep and
shrinkage, and post‐
tensioning steel relaxation
which must be considered in
the design of segmental
structures. Once the
structure is completed, the
time dependent
effects
continue to occur, and the
analysis evaluates these
effects for a predetermined
time interval, typically to
10,000 days, which is defined as time infinity, when it is assumed all time dependent
effects have occurred.
Figure 6‐2. Detail of Segments on Pier and Accurate Section Property Input
Following the 10,000‐day analyses, external loads such as truck and wind forces
were applied to the completed structure. Stresses were checked for conformance
within AASHTO LRFD limits. These stress checks include limit states before and after
construction.
Figure 6‐1. Balanced Cantilever Construction Method
(Modeling of Construction Stage 6, Bridge 82048)
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 56/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
6‐4 June 2010
Figure 6‐3. Stress Output Checked at 10 Locations in the Cross‐section
6.3 Baseline Model Description
6.3.1 Piers
The VQM illustrates twin stem wall piers having a curved surface on the outward
faces looking
up
station
and
down
station.
These
double
‐stem
piers
vary
in
width
from top to bottom with the smaller dimension at the top of the stem walls. A
diagonal cut on the side faces provides the taper. From the side, the outer and inner
stem faces are plumb, but the diagonal cut provides a side face that decreases in
dimension from top to bottom. The top width of the stem walls matches the bottom
flange width of the box girder.
The double stem piers were examined through initial visual renderings, bridge
elevation views of each structure, approximate material quantities and an estimated
construction impacts. Through discussions with Mn/DOT and the VQAC, there was
general consensus that a single stem pier would be preferred to obtain
constructability, economic
and
visual
benefits.
Since
substructure
geometry
significantly affects the structural analysis, all models were suffixed with either an
“A” or “B” to indicate whether double‐stem piers or single‐stem piers were
modeled, respectively. In other words, structural model 82045_R1A was variation 1
on the baseline model and utilized double‐stem columns, whereas model
82045_R1B was baseline variation one with single‐stem columns.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 57/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 6‐5
From our analyses it is apparent that a single stem column is a viable option with the
caveat that expansion joint locations will require a wider platform for bearings and
jack area for bearing replacement. This wider platform would equate to a single
column with an approximately 14’‐6” longitudinal dimension at Ramp Pier 5R and
the three columns of Pier 7. Alternatively, double‐stem columns connected with a
pier cap
may
be
utilized.
Figure 6‐4. Pier 1 on TH 36 (Bridge No. 82045)
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 58/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
6‐6 June 2010
Figure 6‐5. Typical Pier on TH 36 Approaches (Others Similar)
6.3.2 Box Girders
The baseline box girders along the TH 36 mainline are comprised of a 3‐cell cross‐
section, with two vertical interior webs and two inclined exterior webs. The bridge
begins at the west abutment with 10‐foot deep box girders that transition to a 20‐
foot deep box girder from the end of span 1 throughout span 2. These girders are
typically 42’‐8” wide at the top flange or roadway level, with a 16.0‐foot width at the
girder soffit. The exterior webs and soffit have circular curved faces with a radius of
66.0 feet. The individual curves meet at the web‐soffit intersection, forming an
angular break point. The exterior webs curve to vertical at roadway level by the
addition of a smaller radius curve within the top 3 feet of the web.
The baseline N.E. and S.E. ramp box girders emulate the shape of the mainline
girders. The depth of these ramp girders was undefined prior to preliminary design,
although there was some indication in the proposed railroad and Plant Access Road
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 59/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 6‐7
profiles that these girders would be 10 feet deep at these crossings. Considering this
indication, preliminary design proceeded with the assumption that the approach
ramp structures should also include a box girder depth transition from 10 feet to
20 feet. This assumption fit the ramp structures well because a constant 20’‐foot
depth appeared visually too deep for the ramps, especially as these structures
descended toward
the
respective
exit
or
entrance
intersection.
The baseline ramp box girders are typically 27’‐4” wide at the top flange or roadway
level, with a 12.0‐foot width at the girder soffit. The exterior webs and soffit have
circular curved faces with a radius of 50.0 feet for the exterior webs and 36.0 feet
for the soffit. The individual curves meet at the web‐soffit intersection, forming an
angular break point. The exterior webs curve to vertical at roadway level by the
addition of a smaller radius curve at the top 3 feet of the web.
Figure 6‐6. Baseline Approach Box Girders
The top flange of the box girder is haunched adjacent to each web to provide room
for post‐tensioning anchorages on either side of the interior webs, and on the
interior side of the exterior webs. The bottom flange is similarly haunched adjacent
to the interior webs to permit the top surface of the flange to follow the curved
soffit face and reduce the flange thickness at the midspan between the webs.
6.3.3 Transition Span
The approach span adjacent to the extradosed river spans is a transition span that
has a wider cross‐section to accommodate the on‐ramp and off ‐ramp lanes. The
cross‐section consists of two box girder similar to the mainline, but the box girder
dimensions vary to accommodate the additional roadway width.
6.3.4 Pedestrian Trail
A pedestrian trial cantilevers from the edge of the transition span and the northern
ramp box girder. The trail consists of a sidewalk slab supported by concrete brackets
attached to the box girder at approximately 20‐foot interval.
The six bridges are divided into four baseline models as follows:
The initial focus was on determining constructible and feasible box sections for use
in modeling. These design sections made use of repeatable forms and were
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 60/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
6‐8 June 2010
conceptually compatible with the VQM intent. Areas of wide variation were
relegated to cast‐in‐place construction on falsework. Such sections were kept
minimal to limit the environmental impacts and cost impacts, but nonetheless these
areas were accurately modeled in the analyses for construction staging and tendon
geometry. Bridge 82045 was modeled in a baseline model consisting of double‐stem
piers in
and
five
‐span
configuration
as
illustrated
in
Figure
6‐7 and
Figure
6‐8 and
Table 6‐1. Consistent with the model naming convention, the analysis is termed
82045E‐r0A to indicate Bridge 82045, Eastbound in the baseline configuration with
double‐stem columns.
Figure 6‐7. Baseline Model 82045E‐r0A, Bridge 82045 EB (EB TH 36)
Figure 6‐8. Plan and Elevation of Baseline Model, Bridge 82045 EB (EB TH 36)
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 61/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 6‐9
Table 6‐1. Baseline Span Arrangement
Bridge No.
Length
(feet)
Span Arrangement from
West to East (feet) Comment
82045 (EB) 1609 180‐229‐300‐300‐300 Mainline eastbound
82045 (WB) 1609 180‐229‐300‐300‐300 Mainline westbound, similar to eastbound and
not uniquely
modeled
82045 (EB) 300 300 Transition eastbound
82045 (WB) 300 300 Transition westbound, similar to eastbound and
not uniquely modeled
82047 1031 125‐300‐300‐301 Off ‐ramp TH 36WB/TH 95
82048 1296 91‐300‐300‐300‐300 On‐ramp TH 36EB/TH 95
Pursuant to the study’s objectives, the baseline box girder depth of 20 feet was
investigated in both the extradosed and approach unit models and span
arrangements. In
the
extradosed
span,
an
optimal
depth
of
16
feet
was
determined
by balancing girder and cable requirements. In the approach units, however, the 16‐
foot depth was not structurally viable in the transition span with the baseline span
configuration. One reason for this is that the N.E. and S.E. ramp expansion joints
force the transition span to be a single‐span, separate structure. Precast, balanced
cantilever construction envisioned for much of the bridge construction is not
possible in a single‐span configuration. Therefore, the baseline configuration would
require a 20‐foot deep box girder in the 300‐foot transition span that would be
entirely cast on falsework.
This finding initiated a focus on the transition span and span alternatives. Four goals
were set
for
the
transition
span
investigation:
To enable construction via the precast balanced cantilever method
To minimize the falsework and associated permanent impacts in the wetlands
below
To move the expansion joints over the support locations and eliminate hinges for
maintenance reasons
To enable use of a 16‐foot deep structure that was compatible with the optimal
structure depth found for the extradosed spans
Decreasing the box girder depth to 16’ would also introduce savings in material and
support structure costs due to the increased weight of the superstructure.
Parallel to the girder depth investigation, the baseline spans were examined for
feasibility. Results from these analyses indicated Bridge 82045 appeared to have a
viable arrangement given the 20’ box girder depth, but the N.E. and S.E. ramps had
baseline span arrangements that were not only inefficient but appeared impractical
for the 10‐foot box girder depth near the end spans as suggested by the profiles. For
this reason, no baseline model was developed for the N.E. and S.E. Ramps according
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 62/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
6‐10 June 2010
to the VQM, or baseline, span arrangement. Instead, variations of span
arrangements were investigated using engineering judgment which suited:
The VQM box girder section
Site constraints such as wetland avoidance and railroad clearances
Balanced cantilever construction method to minimize heavy duty falsework in
sensitive areas
The resulting span arrangements were drafted and presented at a wetland
coordination meeting on September 2nd, 2009. The proposed changes to span
configuration as suggested by PB were agreeable to the stakeholders and it was
agreed to further advance these configurations as the preferred arrangement. These
preferred arrangements are described in detail in the next sections.
6.4 Alternative R1 Investigation
Alternative R1 is the result of girder depth investigations, span efficiency and site
constraints. The R1 span arrangements are indicated in Table 6‐2.
Table 6‐2. Span Arrangement “R1”
Bridge No.
Length
(feet)
Span Arrangement from
West to East (feet) Comment
82045 (EB) 1909 184‐224‐300‐300‐183‐161 Mainline eastbound
82045 (WB) 1909* 184‐235‐300‐300‐183‐161* Mainline westbound
82047 1031 104‐195‐243‐233‐202 Off ‐ramp TH 36WB/TH 95
82048 1296 126‐192‐199‐199‐199‐199‐168 On‐ramp TH 36EB/TH 95
*Indicates span measurement with respect to EB TH 36 alignment
Within the
R1
span
arrangement,
various
column
configurations
were
investigated.
These models were suffixed with a letter designation to indicate the column type
used in the investigation. The suffixes to date are as follows:
A = baseline model with double stems typical except at Pier 1, Bridge 82045
B= single stem columns with an 8‐foot longitudinal dimension and f’c=4 ksi
C = single stem columns with an 6‐foot longitudinal dimension and f’c=5 ksi
In all of these instances bridge modeling using true coordinates along the respective
alignment. However, a horizontal datum of 70’ was established for a constant girder
elevation while the column heights were correctly calibrated to the height from PGL
to top of footing. At the top of footing, 3 rotational and 3 translational springs serve
to emulate the group pile behavior. These springs were determined elastically from
a refined piling arrangement and checked through the use of industry‐standard Lpile
Group software.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 63/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 6‐11
For all bridges it is assumed that a
pair of bearings supports the
superstructure at the West
Abutments, Pier 1 and the end piers.
The introduction of bearings at the
West Abutment
and
Pier
1 are
due
to
the short height of these support
structures, which creates a high
stiffness and resistance against
thermal movements. The end pier
bearings are necessary because they
are expansion joint locations.
Bridge 82045 EB was modeled with
both a double‐stem column and a
single‐stem column. These two
models served
as
a basis
for
evaluating the viability of the single‐stem piers. Once verified, column option A
(Double‐stem columns) were eliminated due to Mn/DOT preference and column
option B was continued through analyses that included WB TH 36 and the N.E. and
S.E. ramps. Figure 6‐10 through Figure 6‐12 illustrate the various analyses that were
developed in this program.
Figure 6‐10. Model 82045E‐r1A—Double‐stem Columns in Alternative R1 Span Arrangement
Figure 6‐9. Plan and Elevation of Alternative “R1”
Models for EB and WB TH 36.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 64/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
6‐12 June 2010
Figure 6‐11. Model 82045E‐r1B—Single‐stem Columns in Alternative R1 Span Arrangement
Figure 6‐12. Plan and Elevation of Model 82045W‐r1B—WB TH 36 with Single‐stem
Columns in Alternative R1 Span Arrangement
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 65/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 6‐13
Bridge 82047, or the N.E. Ramp, includes a cantilevered sidewalk in the VQM which
was integrated with the box section after discussions with Mn/DOT. With the
inclusion of the sidewalk, this ramp has a width very comparable with the typical TH
36 approach unit segments and a consistent shape was utilized. At the West end,
two turn lanes are added on the structure necessitating variable width sections up
to 60’
‐6”
in
width.
A
depth
increase
of
6‐foot
is
introduced
in
span
four
to
match
the
depth of TH 36 box girder at Pier 5R. This depth increase suits the higher end span
moments and provides a visually appropriate transition.
Figure 6‐13. Bridge No. 82047 (NE Ramp) Stick Model and Rendered Model
Figure 6‐14. Bridge No. 82047 Rendered Plan and Elevation from Structural Model with Details
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 66/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
6‐14 June 2010
Bridge 82048 (SE Ramp) is the narrowest and the longer of the two ramps. The ramp
width is largest at the beginning where the roadway would permit three 12‐foot
lanes and narrows to a 24’‐0 roadway for two potential loading lanes. Although the
roadway width is amenable to a single‐cell box girder, this bridge has been
envisioned as a two‐cell box girder due to the lack of counter‐balancing overhangs.
Without cantilever
overhangs
to
decrease
the
top
‐slab
span,
high
restraint
forces
will develop directly under the barriers and necessitate more transverse post‐
tensioning and a thicker, heavier slab section. For these reasons, a two‐cell structure
presents more efficiency than a single cell girder. The box girder depth transition is
placed in the second span from the end of the ramp to enable the deeper girder’s
effectiveness in the end span. Model R1B is illustrated in Figure 6‐15 through
Figure 6‐16.
Figure 6‐15. Bridge No. 82048 (SE Ramp) Stick Model (Left)
and Rendered Sectional Model (Right)
Figure 6‐16. Bridge No. 82048 (SE Ramp) Plan and Elevation View of Rendered Model
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 67/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 6‐15
6.4.1 Grade-Induced Movement Investigations
Grade induced movement was examined by using two models that were identical in
all respects except the grade. For this investigation the EB Bridge 82045 Alternative
R1 was used. To exaggerate the effects, a grade of 5% was modeled in lieu of the
actual 1.25% slope. Both models were run and the displacements at Pier 7, the
downhill end
support,
were
examined.
As can be seen in Table 6‐3, no appreciable difference is observed. The results are
taken at a time equal to 10,000 days after construction, which is an industry‐
standard time for which all construction‐induced load effects should be realized
(Self ‐weight, elastic shortening, creep, shrinkage, etc.).
Table 6‐3. Grade‐induced Movement Results
Model
Description Time
DX
(Feet)
DY
(Feet)
DZ
(Feet)
Vector Sum, Net
movement
(Feet)
Horizontal
T_INFINITY ‐
0.194 ‐
0.236 ‐
0.042
0.305
5% grade T_INFINITY ‐0.194 ‐0.236 ‐0.037 0.306
Figure 6‐17. Models Used in Investigating Grade‐induced Deflection
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 68/110
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 69/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 7‐1
7 Bridge Lighting and Signing
7.1 Review of Requirements for Architectural and Roadway Lighting
The Visual Quality Manual discusses many aspects of the different types of lighting
for the bridge, roadway, and trail. These include specific concerns about the impact
of lighting
as
well
as
the
lighting
approach
to
be
used
for
different
areas.
Specific concerns included:
Design should minimize the negative impact that bridge lighting could have on
the scenic river valley.
Lighting should meet the needs for required safety levels but minimize
“spillover” into the riverway.
Architectural lighting must be thoughtfully designed to enhance the structure
without intruding into the sensitive natural environment.
Preliminary investigations were conducted during the preparation of the VQM into
various types
of
lighting
approaches.
The
results
of
these
investigations
arrived
at
the following recommendations.
Roadway lighting using davit poles with twin arms and contemporary style
luminaires mounted in the median.
A “white” light source such as metal halide is preferred due to aesthetic and
quality reasons
Trail lighting could use a low level lighting system to provide adequate
pedestrian visibility with minimized light trespass.
Navigation channel lighting is not required but lighting identifying the piers
locations for boaters is required for safety reasons.
FAA
obstruction
lights
are
required
at
the
tops
of
the
pier
towers.
These concerns and recommendation were carried into this phase of design and are
addressed and discussed in the various lighting approaches in this report.
7.2 Lighting Criteria
Aesthetic lighting for the St. Croix River Crossing will accent its unusual forms. These
derive from the extradosed structural design and the biomorphic aesthetic concept.
The effects under consideration include illuminating the cables from below with
narrow beam floodlights, grazing the tower surfaces either inside or outside, and
outlining selected features with direct view fixtures. For floodlighting options the
criteria of
the
Illuminating
Engineering
Society
(IES)
will
apply.
The
criteria
recommended in IES RP‐33‐99 Lighting for Exterior Environments is shown in
Table 7‐1 (excerpted from Table 2 of that document).
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 70/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
7‐2 June 2010
Table 7‐1. Illuminance Levels for Floodlighting Buildings and Monuments
Area Description
Average Target Illuminance (Vertical)
(lux/footcandles)
Bright surroundings and light surfaces 50/5
Bright surroundings and medium light surfaces 70/7
Bright surroundings and dark surfaces 100/10
Dark surroundings and light surfaces 20/2
Dark surroundings and medium light surfaces 30/3
Dark surroundings and medium dark surfaces 40/4
Dark surroundings and dark surfaces 50/5
The vertical value on the structural elements will be designed to 20 to 30 lux (2 to 3
footcandles) associated with the categories of Dark Surroundings and Light to
Medium Light Surfaces (note : RP‐33 has an error in the table description).
For roadway lighting criteria the recommendations of IESNA Recommended Practice
8‐00 and AASHTO Guide for Roadway Lighting apply. The criteria recommended in
ANSI/IES RP‐8‐05 Standard Practice for Roadway Lighting is shown in Table 7‐2 and
Table 7‐3.
Table 7‐2. Illuminance Method—Recommended Values
Road
Pedestrian
Conflict
Area
Pavement Classification
(minimum maintained average values) Uniformity
Ratio
Eavg/Emin
Veiling
Luminance
Ratio
Lmax/Lavg
R1
(lux/fc)
R2 & R3
(lux/fc)
R5
(lux/fc)
Freeway Class A 6.0/0.6 9.0/0.9 8.0/0.8 3.0 0.3
Freeway Class B 4.0/0.4 6.0/0.6 5.0/0.5 3.0 0.3
Expressway High 10.0/1.0 14.0/1.4 13.0/1.3 3.0 0.3
Medium 8.0/0.8 12.0/1.2 10.0/1.0 3.0 0.3
Low 6.0/0.6 9.0/0.9 8.0/0.8 3.0 0.3
Major High 12.0/1.2 17.0/1.7 15.0/1.5 3.0 0.3
Medium 9.0/0.9 13.0/1.3 11.0/1.1 3.0 0.3
Low 6.0/0.6 9.0/0.9 8.0/0.8 3.0 0.3
Collector High 8.0/0.8 12.0/1.2 10.0/1.0 4.0 0.4
Medium
6.0/0.6
9.0/0.9
8.0/0.8
4.0
0.4
Low 4.0/0.4 6.0/0.6 5.0/0.5 4.0 0.4
Local High 6.0/0.6 9.0/0.9 8.0/0.8 6.0 0.4
Medium 5.0/0.5 7.0/0.7 6.0/0.6 6.0 0.4
Low 3.0/0.3 4.0/0.4 4.0/0.4 6.0 0.4
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 71/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 7‐3
Table 7‐3. Luminance Method—Recommended Values
Road
Pedestrian
Conflict
Area
Average
Luminance
Lavg
(cd/m
2
)
Uniformity
Ratio
Lavg/Lmin
(max
allowed)
Uniformity
Ratio
Lmax/Lmin
(max
allowed)
Veiling
Luminance
Ratio
Lmax/Lavg
(max
allowed)
Freeway Class A 0.6 3.5 6.0 0.3
Freeway Class B 0.4 3.5 6.0 0.3
Expressway High 1.0 3.0 5.0 0.3
Medium 0.8 3.0 5.0 0.3
Low 0.6 3.5 6.0 0.3
Major High 1.2 3.0 5.0 0.3
Medium 0.9 3.0 5.0 0.3
Low 0.6 3.5 6.0 0.3
Collector High 0.8 3.0 5.0 0.4
Medium 0.6 3.5 6.0 0.4
Low 0.4 4.0 8.0 0.4
Local High 0.6 6.0 10.0 0.4
Medium 0.5 6.0 10.0 0.4
Low 0.3 6.0 10.0 0.4
The American Association of State Highway and Transportation Officials (AASHTO)
also have recommendations in the AASHTO Roadway Lighting Design Guide 2005
which,
in
general,
are
in
agreement
with
the
IES
and
are
shown
in
Table
7‐
4.
Based on these recommendations considering the bridge roadway to be classified as
a freeway, a average illuminance of 6 to 12 lux (.6 to 1.1 footcandles) and average
luminance of 0.4 to 1.0 candelas/square meter (cd/m2) would be suitable design
ranges.
For the pedestrian area adjacent to the roadway, the lighting criteria described in IES
DG‐5‐94 Recommended Lighting for Walkways and Class 2 Bikeways is most suitable.
RP‐8 has a pedestrian area criteria but it applies to sidewalks and walkways adjacent
to the roadway where pedestrian conflicts can occur. The bridge pedestrian walkway
is separated and protected from the roadway so the recommendations of DG‐5 are
more applicable.
Using Table 2 of this guide and classifying the bridge walkway as a pedestrian
overpass an average horizontal value of 2 lux (0.2 footcandles) and a vertical
illuminance values of 5 lux (0.5 footcandles) should be used.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 72/110
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 73/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 7‐5
Table 7‐5. Recommended Illumination (Values in lux)
Average Conditions Special Conditions1
Avg Maintained
Illuminance
Levels
Horizontal Levels (Eavg)2
Horizontal
Avg to
Min
Avg
Min
Maintained
Avg Vertical
Levels (Eavg)3
Avg to
Min
Ratio
Sidewalks along streets by area classifications4
Commercial 10 4:1 20 5:1
Intermediate 5 4:1 10 5:1
Residential 2 10:1 5 5:1
Park walkways and class I bikeways 5 10:1 5 5:1
Pedestrian tunnels 20 4:1 55 5:1
Pedestrian overpasses 2 10:1 5 5:1
Pedestrian stairways 5 10:1 10 5:1
7.3 Lighting Alternatives Analysis
7.3.1 Source Selection
Based on the direction of the Visual Quality Manual for the use of a “white” light
source like metal halide, a review of possible sources meeting this criteria was
evaluated. The types of lamps which were considered were:
Metal Halide
Fluorescent
Induction
LED
Each of these sources has unique operating characteristics in terms of efficiency,
lamp life, temperature impacts, and lumen depreciation, so a description of each is
included below with an expanded description of LED’s. Because LED’s are a solid
state device and not a conventional lamp type, more information is provided
including some LED “basics”.
Metal Halide
Metal halide lamps are high intensity discharge lamps which operate by vaporizing
various materials at extremely high voltages, stabilizing after ignition. Metal halide
lamps are available in various color temperatures and are fairly efficient at about 70‐
80 lumens per watt. The life of a metal halide lamp will range from about 12,000 to
20,000 hours depending on the lamp wattage used (rated life is determined as the
time when 50% of the lamps have failed). Metal halide lamps do experience some
color shift during their life and generally need to be in enclosed luminaires. The
lamps are prone to shortened life in conditions encountering sustained vibration
because of arc tube failure and mechanical failure of the lamp components.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 74/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
7‐6 June 2010
Fluorescent / Induction
Fluorescent sources operate by generating an ultraviolet arc spanning over two ends
of the lamp. As the ultraviolet energy comes in contact with phosphors it produces
visible light. Induction technology uses coils, external to the lamp to generate an
electric field to perform this function. The use of these external coils, operating at
high frequency,
help
extend
the
lamp
life
of
this
source
to
over
100,000
hours.
Linear fluorescent lamps are sometimes considered for bridge lighting because of
their long life and efficiency. Typical arrangements are as linear rail lights or accent
lighting. A T8 fluorescent lamp with reduced mercury content, operating in
conjunction with a programmed start ballast will provide a lamp life of over 40,000
hours and a system efficiency of approximately 110 lumens per watt. The lamps with
electronic ballasts are durable in high vibration environments when used in properly
designed fixtures. Temperature however does effect lamp output. Typically
optimized for a bulb wall temperature of 77 degrees F, the lamps output can be
reduced by over half in very cold environments.
Induction lamps have a lower efficiency than some linear fluorescent lamps,
operating at approximately 75‐80 lumens per watt. Lamp life is very long at
approximately 100,000 hours. The end of life of an induction system is typically
when the high frequency driver fails to operate. LED
(parts of the text included in this section are excerpted from the US Department of Energy documents at www.netl.doe.gov) LEDs differ from traditional light sources in the way they
produce light. In an incandescent lamp, a tungsten
filament is heated by electric current until it glows or emits
light. In a fluorescent lamp, an electric arc excites mercury
atoms, which emit ultraviolet (UV) radiation. After striking
the phosphor coating on the inside
of glass tubes, the UV radiation is
converted and emitted as visible
light.
An LED, in contrast, is a
semiconductor diode.
It
consists
of
a chip of semiconducting material
treated to create a structure called
a p‐n (positive‐negative) junction.
When connected to a power
source, current flows from the p‐
side or anode to the n‐side, or cathode, but not in the reverse direction. Charge‐
carriers (electrons and electron holes) flow into the junction from electrodes. When
Figure 7‐1. Typical LED
Figure 7‐2. Schematic of LED Operation
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 75/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 7‐7
an electron meets a hole, it falls into a lower energy level, and releases energy in the
form of a photon (light).
The specific wavelength or color emitted by the LED depends on the materials used
to make the diode.
Red LEDs are based on aluminum gallium arsenide (AlGaAs). Blue LEDs are made
from indium gallium nitride (InGaN) and green from aluminum gallium phosphide
(AlGaP). “White” light is created by combining the light from red, green, and blue
(RGB) LEDs or by coating a blue LED with yellow phosphor.
Color Characteristics Unlike incandescent and fluorescent lamps, LEDs are not inherently white light
sources. Instead, LEDs emit light in a very narrow range of wavelengths in the visible
spectrum, resulting in nearly monochromatic light. This is why LEDs are so efficient
for
colored
light
applications
such
as
traffic
lights
and
exit
signs.
However,
to
be
used
as a general light source, white light is needed.
White light can be generated from LED’s by either coating a blue LED with a yellow
phosphor, or by using monochromatic red, green, and blue (RGB), LED’s and
operating them at different levels to “mix” and create white, or any other color light.
For most applications were the light source is visible, white (coated) LED are used.
For RGB configurations, unless using an intermediate optic material, when viewing
the sources directly you can see the individual red, green and blue LED’s and the
source does not appear white. When applied to a surface however the mix of the
colors creates a white surface.
LED’s with a high correlated color temperature (which are “cooler” or bluer in
appearance) tend to be the more efficient LED’s in terms of lumens per watt of
power consumed. “Warmer” LEDs are available but have a slightly lower efficiency..
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 76/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
7‐8 June 2010
Photometric Characteristics LED’s are available in different emitting patterns. An example of a typical pattern
(from Phillips Luxeon K2) is shown in Figure 7‐3 and Figure 7‐4.
Figure 7‐3. Typical Representative Spatial Radiation Pattern for White Lambertian
Figure 7‐4. Typical Polar Radiation Pattern for White Lambertian
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 77/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 7‐9
Effect of Electrical Variations The light output of an LED is related to the amount of current it is being operated.
The greater the current, the higher the light output of the LED. These variations in
current also alter the useable life and efficiency of the LED. It is important to look at
the performance data provided for particular LED’s and the current that they will be
actually operated.
Table 7‐6. Flux Characteristics for LUXEON K2 with TFFC Junction and Case Temperature = 25 C
Minimum Performance at Test Current Typical Performance at Indicated Current
Color Part Number
Minimum
Luminous Flux
(lm) at 100 mA
Typical Luminous Flux (lm)
at 1600 mA at 700 mA at 350 mA
Cool White LXK2‐PWC4‐0200 200 275 170 95
LXK2‐PWC4‐0180 180 250 150 85
LXK2‐PWC4‐0160 160 220 135 75
Figure 7‐5. Typical Luminous Flux
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 78/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
7‐10 June 2010
LED’s also require a driver, similar to the way a fluorescent and high‐intensity
discharge (HID) light sources cannot function without a ballast, which provides a
starting voltage and limits electrical current to the lamp. The driver converts line
power to the appropriate voltage (typically between 2 and 4 volts DC for high‐
brightness LEDs) and current (generally 200‐1000 milliamps or mA), and may also
include dimming
and/or
color
correction
controls.
Currently available LED drivers are typically about 85% efficient. So LED efficacy
should be discounted by 15% to account for the driver.
Effect of Temperature The luminous flux figures cited by LED manufacturers are based on an LED junction
temperature (Tj) of 25°C. LEDs are tested during manufacturing under conditions
that differ from actual operation in a fixture or system. In general, luminous flux is
measured under instantaneous operation (perhaps a 20 millisecond pulse) in open
air. Tj will always be higher when operated under constant current in a fixture or
system.
LEDs
in
a
well‐
designed
luminaire
with
adequate
heat
sinking
will
produce
10%‐15% less light than indicated by the “typical luminous flux” rating.
Source: Philips Luxeon K2—(10/07) Figure 7‐6. Typical Light Output Characteristics Over Temperature
(Cool‐White at Test Current)
Estimated Life LED’s, much like the mercury lamp, will continue to operate for long periods of time
but at a steadily deteriorating light output. For this reason the estimated life of an
LED cannot be based on how long it is still operating but how long it is still being an
effective lighting source. Research (ref. Mark Rea, Lighting Research Center, 2000)
has shown that for general lighting, a majority of occupants can accept a lighting
level reduction of up to 30%, when done gradually. For this reason, as well as for
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 79/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 7‐11
standardization, the life of an LED is established to be the time when its’ light level
has been reduced to 70% of its initially rated value. This is called an L70 life.
Source: Adapted from Bullough, JD. 2003. Lighting Answers: LED Lighting Systems. Troy, NY. National Lighting Product Information Program, Lighting Research Center, Rensselaer Polytechnic Institute.
Figure 7‐7. Typical Lumen Maintenance Values for Various Light Sources
By this
method,
most
currently
available
LED’s
are
rated
between
40,000
and
60,000
hours of life at rated current. Much longer operating life can be obtained by
operating the LED’s at a lower forward current and just using more LEDs. LED life can
be extended 120,000 hours or higher by driving the LEDs at reduced current.
Because LEDs are solid state devices, without arc tubes, they are very stable in high
vibration environments such as bridges assuming proper construction of the sold
state elements and circuit boards.
The advancement of LED technology is exponentially faster than conventional lamp
sources. Based on current advancements and expected continuation, LEDs should
surpass all other sources in terms of operating life and energy efficiency within the
next 2 years.
When
looking
at
current
technology
and
the
future
potential,
the
use
of LEDs seem appropriate for the St. Croix River Crossing if used with lower drive
currents and lower color temperatures to better compliment the proposed finishes
of the bridge and eliminate the environmental impacts of higher color temperature
sources.
7.4 Architectural Lighting The architectural lighting options
for the bridge ranged from no
accent lighting to either
floodlighting or
using
point
sources to accent most of the
structure and cables. In this
section of the report we will
discuss the progression of each
option as designed and presented
to the Visual Quality Committee and where consensus was reached.
Figure 7‐8. Base Architectural Lighting Option
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 80/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
7‐12 June 2010
The base architectural lighting option looked at no accent lighting for the bridge
structure using only required lighting for basic motorist safety. The roadway was
illuminated to the required lighting levels discussed in the criteria section using
metal halide lamps in standard cobra head style full cutoff luminaires on 35’ davit
arm style pole with 8’ arms. The walkway area met the minimum required horizontal
values.
7.4.1 Option 1A From the base option of just
using the roadway lighting, the
roadway lighting luminaires were
replaced with LED luminaires
having increased
distribution/output to the front
side of the luminaire. This
allowed more lighting to be
placed on
the
cables
from
the
roadway lighting equipment.
The roadway lighting however is
mounted on the median which is
not centered between the cables
due to the addition of the
walkway on one side of the
bridge. Because of this, the
lighting on the cables is different
depending on which direction
the bridge
is
viewed.
Looking
south,
the
cables
are
mostly
illuminated.
Looking
north, the illuminated section of the cables is not as high due the increased distance
to the luminaire so the effect is less pronounced.
Floodlights were added at the
base of the piers which light the
inside surface of the split pier.
Four floodlights were used for
each pier consisting of narrow
beam LED floodlights. These
floodlights were also RGB color
change floodlights
allowing
the
lower piers to change color for
the purpose of special occasions
or significant events. The RGB
LED arrangement can be tuned to produce virtually any color. In addition, each
group of floodlights on each pier and be individually controlled and set to different
preset colors.
Figure 7‐9. Lighting Option 1a
Figure 7‐10. Lighting Option 1b
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 81/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 7‐13
7.4.2 Option 2A
The next lighting alternative
investigated was to add LED
floodlights to the upper portion
of the towers. The intent of the
floodlighting alternatives
analysis is to keep adding layers
of light in an attempt to reach
the proper balance and
perspective.
Two LED floodlights were used
at the top portion of the pier
directed down the face of the
tower. These additional
floodlights added the effect of
visually lengthening
the
perceived height of the towers.
It also has the effect connecting
the bottom to the top of the
towers.
The negative effects of these
lights include the addition of
more lighting into the night
environment at the bridge and it
did somewhat compete with the cable lighting. Because the inside surface of the
cables are
illuminated,
an
observer
sees
the
cable
lighting
on
the
opposite
side
of
the bridge. Unless directly lined up with the bridge, the illuminated tower would not
usually line up with the illuminated cables causing some clutter and potentially an
unbalanced appearance.
Figure 7‐11. Lighting Option 2a
Figure 7‐12. Lighting Option 2b
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 82/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
7‐14 June 2010
7.4.3 Option 2AA The next progression of surface
floodlighting included another
group of floodlights mounted at
the top
of
the
towers
to
light
the
inside face of the towers. These
additional floodlights would add
symmetry to the illuminated
surfaces of the bridge and also
increase the visual interest to the
motorist passing over the bridge.
When using the white light the
floodlights did seem to more
evenly balance the bridge. From
the roadway
the
lighting
also
helped accentuate the full tower
height. The color change option
however did not produce the
same results. The roadway
lighting, particularly with the
higher angle forward distribution
tended to wash out the color
impact of the floodlights and
make the effect somewhat
muddy and inconsistent.
Figure 7‐13. Lighting Option 2aa
Figure 7‐14. Lighting Option 2bb
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 83/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 7‐15
7.4.4 Option 3 Option 3 investigated the use of
a conventional method of cable
lighting. Cable lighting for
bridges can
be
done
in
two
ways
resulting in different effects. The
most often used method is
floodlights mounted at the base
of the cable aimed along its
length towards the tower. This
type of lighting tends to
uniformly light the cables
regardless of the viewing
direction. Cable grazing is
another lighting method where
the floodlights
are
arranged
along the bridge and aimed
vertically, grazing the cables.
With this type of arrangement
the cables appear more brightly
lit on the side of the tower
where the observer is located.
When the observer changes, so
does the location of perceived
brightness for the cables. For
this alternative
however
the
first
method was used aiming along
the cables. This option can be
done with standard metal halide
floodlights or with LED
floodlights.
While this arrangement does give the towers a strong visual appearance from a
driver’s perspective it ignores the lower portion of the towers and front faces by
only illuminating the outside face.
Figure 7‐15. Lighting Option 3
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 84/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
7‐16 June 2010
7.4.5 Option 4 The last option investigated was
various arrangements of direct
view sources. In this type of
option, lower
wattage
sources
using globes or opaque lenses
are used to “dot” or line the
structure with points of light.
The most commonly used
application of this type of
lighting is the a necklace lighting
system often used on
suspension bridges.
While useful as necklace lighting
where the
curving
arch
of
the
main cables are highlighted by
the points of light, it only
seemed to detract from the
strong structural elements that
make up the St. Croix Bridge
design.
7.4.6 Preferred Option As a result of discussing the
various options and considering
the long
standing
concerns
about environmental impacts,
spill lighting, conflict with the
natural beauty of the river and
surrounding area, the simple
and subtle approach seemed to
be Option 1A. Also from a bridge
aesthetic standpoint, the
organic and graceful design of
the bridge seemed better
complemented by
a more
natural “moonlit” glow than a
strong “feature” type of
lighting system.
Figure 7‐17. Lighting Option 4b
Figure 7‐16. Lighting Option 4a
Figure 7‐18. Preferred Option—View from
Sunnyside Marina
Figure 7‐19. Preferred Option—View from Stillwater
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 85/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 7‐17
This option using lower pier LED
floodlights as the only added
lighting to the roadway and
pedestrian lighting was generally
agreed to be the correct
approach. To
arrive
at
the
proper balance of lighting in this
situation and environment will
require a strict criteria and
explicit specifications in the RFP
documents to achieve the
desired results. This can be done
by using the calculated results of the current design as the light level criteria for
various surfaces of the bridge and specifying fixture output and distribution required
for installation.
The lower
pier
lighting
would
also
be
RGB
color
change
lighting
programmed
with
preset lighting colors which can be activated remotely.
7.5 Roadway Lighting
The roadway lighting, as partially
described in the architectural
lighting section, is made up of
median mounted 35’ poles, with
8’ davit arms, spaced at 160’
centers. The pole spacing is
arranged
to
coincide
with
the
80’ tower spacing. The
luminaires are 292 watt LED
luminaires. For this initial
analysis the luminaire used was
a Beta LED 12 bar unit similar to
the luminaire currently used on
the St. Anthony Falls Bridge. It
should also be noted that the
lighting calculations were
performed at the rated output
and drive
current
of
the
luminaires and is therefore
higher than required.
In order to extend the
maintenance life of the LED’s a lower drive current will be specified in the
design/build RFP so that the lighting levels are lowered to the criteria levels and the
associated wattage will be reduced.
Figure 7‐20. Preferred Option—View Looking North
Figure 7‐21. Roadway Lighting
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 86/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
7‐18 June 2010
7.6 Loop Trail Lighting
The loop trail lighting consists of 40 watt LED linear luminaires, integrated into the
bridge railing. The lighting levels with this added lighting meet the requirements of
the IESNA for both standard and
enhanced security by providing 5
lux minimum vertical illuminance. By providing this
vertical illuminance, facial
recognition is enhanced. This
improves the pedestrian’s
comfort level and sense of
security while traveling over the
bridge. It also helps increase
object contrast in the walkway
area which will aid cyclists in
seeing unexpected
obstacles.
7.7 Navigation and Obstruction Lighting
Even though there is no defined navigable channel by the Coast Guard in the area of
the proposed bridge, concerns were raised about the visibility of the bridge piers by
boaters. The current option includes pier accent lighting but those lights may not be
in operation during all the hours of darkness. As a
result, bridge navigation lights are proposed to be
placed near the bottom of each of the piers, one on
each side. These lights would utilize LED sources to
increase
their
operating
life.
FAA obstruction lights will be required at the top of
the towers. Two of these lights would be used on
each of the towers. These lights are omni‐direction,
red obstruction lights and would also use LED
technology to lengthen their service life.
7.8 Light Trespass / Glare / Environmental Impacts
Because of the concerns contained in the Visual Quality Manual and from the
meetings discussing the project, minimizing light trespass, glare, and sky glow were
key design
elements.
The
use
of
LED
luminaires
allows
for
precise
control
of
lighting
both in the beam size but also by controlling the output of the LED’s. For this
concept design the following approaches were used to minimize environmental
impacts:
Lighting was designed to meet the minimum recommended values of the IESNA.
Lighting for the preferred option has limited uplight. The floodlights used at the
bottom of the piers are narrow distribution LEDs with most light contained, and
blocked, by the bridge deck.
Figure 7‐22. Loop Trail Lighting Using Linear
Luminaires
Figure 7‐23. Navigation and
Obstruction Lights
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 87/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 7‐19
The proposed control system for the lighting would leave the roadway lighting
system on, but turn off both the architectural lighting and the pedestrian lighting
at a predetermined time (possibly 12AM). By using the navigation lighting the
pier lighting is not required throughout the night. For the trail lighting the basic
horizontal illuminance requirements for the sidewalk can be met with the
roadway lighting
system.
The
enhanced
vertical
illumination
however
will
not
be
met but it is anticipated that pedestrian volumes will be very low and therefore
unnecessary.
Veiling luminance calculations have been performed to make sure the lighting
system provided limits disability glare to the prescribed limits of the IES.
7.9 System Maintenance
Maintenance was a strong consideration when evaluating proposed lighting systems
and source types. The use of LED technology minimizes the relamping requirements.
Also the use of reduced current operation extends the life and overall efficiency of
the LEDs
considerably.
For
the
systems
proposed
we
anticipate
a minimum
of
a 10
year source life. After this time the LEDs and drivers would need to be replaced, with
the next generation of LEDs gaining additional life expectancy and efficiency. Some
key considerations when reviewing the proposed system include:
The lower pier floodlights and pier navigation lights will need to be maintained
from the water level. That would mean the use of a boat or small barge with
ladders/scaffolds when the LEDs have reached their end of life. The control
system proposed and short “on” duration will likely yield a much longer than 10
year service cycle but maintenance predictions included in this report have been
kept conservative.
The obstruction lights on the tower would be maintained by access through the
towers
The roadway lighting would be maintained by conventional means, most likely
requiring a lane closure on both sides of the roadway
The trail pedestrian lighting system would require replacement of the LED strip
after the 10+ year expected life. Again the life is a
very conservative estimate based on the proposed
control system and hours of operation.
7.10 Box Section Inspection Lighting
The interior of the box section of the bridge will be
accessed for
periodic
inspection.
In
order
to
support
these inspections, a lighting and control system, as well
as maintenance receptacles, is used within the box. For
this project, it is proposed to use LED utility lights within
the box, controlled by 3 way switches and timer and/or
occupancy sensors. The timer/sensors are used for turning the lighting off, if it has
inadvertently been left illuminated after an inspection.
Figure 7‐24. LED Utility
Light
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 88/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
7‐20 June 2010
7.11 Signing
The signing limits for the St
Croix River Crossing will
include the entire bridge and
approximately 100 feet beyond
the ends of the bridge. The
purpose of the signing is to
convey the necessary
information in a
comprehensible manner
allowing the driver adequate
time to initiate any allowable
action required in a safe
manner.
7.11.1 Review of the Visual
Quality Manual
The location of signs will be based on current sign placement standards adopted by
Mn/DOT and WisDOT and where possible, will be placed in the roadside consistent
with the VQM. Mn/DOT has additionally stated that they did not want any large
overhead signs mounted in the median of the bridge.
Where overhead sign structures are required, they should be a neutral gray in color
in accordance with the VQM. However, Mn/DOT, in contrast to the VQM, has
specifically required that all overhead sign structures use the standard truss style
configuration mounted onto a standard sign post or where possible connected
directly
to
the
pier
columns
in
an
unobtrusive
acceptable
manner.
The
exact
elevation of the sign truss shall be consistent with adopted Mn/DOT standards for
overhead signing and will be a function of the sign panel sizes being accommodated.
The truss should also be mounted so as to allow for the possibility of adding a future
walkway and sign lighting system.
Where it is required that signs be mounted on a bridge overpass to serve the
motorists on the under passing road, the signs should be attached in an unobtrusive
manner consistent with the VQM. Where possible, that shall mean the top of the
sign should not extend above the bridge rail and the bottom of the sign should not
extend below the bottom of the structure.
The current
signing
concept
only
depicts
one
sign
to
be
mounted
on
each
sign
truss
at each location. As a result there is no contradiction with the VQM requirement
that all signs on the same structure have the same vertical dimension and are
mounted at the same elevation.
7.11.2 Additional Concept Refinements
All other signing beyond the limits of the project or not directly attached to the
bridge structure itself shall be provided for by others under a separate contract.
Figure 7‐25. Typical Inspection Lighting
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 89/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 7‐21
Additional signing for delineators, markers, speed limits, route confirmation signs,
and trail signs shall be located as need and defined by the Contractor and approved
by Mn/DOT.
As a result of eliminating the median mounted overhead sign structures, the
structure for the begin and end junction signs have not been defined at the time of
this writing
as
to
if they
will
be
mounted
overhead
or
mounted
off
to
the
side
of
the
bridge or ground mounted. Further discussion is needed to finalize this element.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 90/110
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 91/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 8‐1
8 Visual Quality
8.1 Introduction
The visual appearance of the St. Croix River Crossing and the context of the bridge
environs are a critical factor in the design development of the bridge. As the SFEIS
was developed
between
2004
and
2006,
the
extradosed
bridge
type
was
select
for
the main river crossing through an extensive stakeholder process that involved local
state and federal government agencies, as well as, local and national citizen
organizations. In parallel with the SFEIS process, a VQM was developed to outline
the aesthetic values for the project. A VQRC with member participation from all of
the stakeholder groups was a key part of the visual quality process. In addition the
VQM process included a public open house to gather public input for the aesthetic
development of the bridge.
Through the VQM process, a preferred architectural treatment was selected from a
number of options. The preferred concept is called “Organic” to compliment the
natural forms
of
the
setting.
The
VQM
describes
the
Organic
concept
as
“characterized by curved planes, tapered forms, smooth surfaces, and expressed joints between parts.” In the preliminary engineering phase of the project, the stakeholder involvement has
been continued with the formation of a VQAC. The VQAC is made up of a subset of
the VQRC member organizations, and includes the following members:
City of Bayport, MN
City of Oak Park Heights, MN
City of Stillwater, MN
Town of St. Joseph, WI
Minnesota State Historic Preservation Office
National Park Service
The purpose of the VQAC is to:
Perpetuate the work that has been accomplished through the Environmental
Process and Visual Quality Process
Assist the Project Team through the interpretation of the Visual Quality Manual
in areas where the intent is not fully defined.
Advise the Project Team regarding refinements to the conceptual design during
the preliminary engineering phase
Assist
the
Project
Team
in
evaluating
how
newly
discovered
aspects
discovered
during preliminary engineering relate to the previously developed concept
design.
Attend VQAC Meetings to offer input and comment on visual quality issues
related to the preliminary engineering.
Inform the agencies or organizations that are represented of information
presented or discussed with regard to the relationship between the conceptual
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 92/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
8‐2 June 2010
design documented in the Visual Quality Manual and the preliminary
engineering design.
In addition, public involvement was continued through two open houses, where the
concept refinement was presented for public input and comment.
8.2 Objectives
The specific objectives of the concept refinement through the preliminary
engineering phase include:
Collaborate with the structural discipline to study and execute refinements of
the concept design using the VQM for guidance.
Develop architectural drawings that support proposed structural design concepts
and compliment the intent described in the VQM including:
o 2D drawings showing the various concept refinements.
o 2D lighting drawings showing the river bridge at night, on the river up and
down stream and on the roadway from the Minnesota and Wisconsin sides.
o 2D drawings
to
describe
the
design
intent
to
both
the
professional
and
the
layman.
o 2D CAD drawings indicating accurate scale and proportion to be used for
discussion purposes with the Design Team and the VQAC
o 2D CAD drawings developed for formal presentations to the DOT’s, other
agencies, and the public at large.
o Refinements to the concepts presented in the VQM, such as further design
refinement of the two‐column vs. three‐column piers, to be presented to
obtain concurrence of the Design Team and input from the VQAC on the
refinements.
Provide
input
to
the
Mn/DOT
Visualization
Unit
for
their
preparation
of
photo
‐realistic renderings of the bridge in both daytime and nighttime simulations.
8.3 Refinement Process
The VQM presents a concept design and visual, functional, and engineering guidance
for the further development of the concept design. The VQM defines the selected
“Organic” concept as:
The parts look as if they were found in nature, or shaped by natural forces.
The vertical pier forms are reed‐like; the girders are rounded and tapered like
bones or tree branches; and walls, barriers and railings are curved and blended
into
the
larger
forms.
Transitions are gradual and smooth; edges are soft and curved; and colors are
unified and natural expressions of their materials.
In preparation for the concept refinement and as part of the preliminary
engineering, the concept design was reviewed and evaluated to more fully
understand these defining principles of the concept. The refinement of the concept
required close collaboration between the architectural discipline and the structural
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 93/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 8‐3
discipline, so that the aesthetic values outlined in the VQM are coordinated with the
structural requirements of a major river crossing. The outward appearance of the
bridge and its relationship to the bluffs, wetlands, and river are of utmost
importance, but the structural integrity of the bridge is the backbone that supports
that visual experience. The bridge structure must be functional and economical
while expressing
the
intended
context
sensitive
design.
With these values in mind, the focus of the Visual Quality effort was:
Pier Concept Refinement: The concept pier is a three‐column pier with two
exterior columns that extend above the roadway to provide an attachment for
the stay cables, while the interior column is under the bridge girders along the
centerline of bridge. During development of the VQM, the preference of the
VQRC was to have a two‐column pier, but a three‐column pier was included in
the concept until structural investigation was performed to verify the feasibility
of the two‐column pier. The “Organic” concept represents the light and elegant
character desired of the river bridge, and the two‐column conveys these
attributes to
the
fullest
extent.
Through technical analysis of the structure it was possible to confirm that the
number of columns can be reduced from three to two. This was achievable without
changing the size or form of the column while retaining the preferred shape and
proportions. While the depth and width of the cross girder was also retained, it
became necessary to modify the lower edge of the cross girder to provide greater
contact area of the girder with the tower legs. The original concept of a curved outer
edge along the cross girder was also retained though the radius of the curved edge
had to be shortened to increase the necessary surface area. This has resulted in a
slightly different but acceptable visual appearance of the cross girder.
Figure 8‐1. Section View Illustrates Curved Outside Edges of Cross Girder
Pier Column Shape Refinement: The pier column shape depicted in the VQM has
variable dimensions from top to bottom of column creating a tapered cylindrical
cross‐section that is slightly canted toward the bridge centerline as the column
extend upward from the water. The Cost Risk Assessment and Value Engineering
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 94/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
8‐4 June 2010
(CRAVE) study undertaken in late 2008, recommended that the pier column
shape be simplified to improve constructability and provide cost savings.
A number of refinements were explored but the one chosen retains the visual
character of the VQM column while providing a greater level of constructability. The
chosen refined design consists of a uniform sloping and canted exterior on three
outside column
faces
while
the
inboard
face
is
vertical
and
uniformly
tapered.
To
achieve this, short tangent segments were introduced into the column section on all
four sides so that transitional blocking could be more easily introduced into the
formwork. The interior face of the twin column sections above the roadway deck
line where closed with a single tangent. This was in part to enhance constructability
and to reduce cost.
Near the base of the river columns, a sloped concrete fill is proposed. This fill area is
to be located at the surface water elevation and slope upward closing the hollow
column form. The purpose for the fill is to prevent unauthorized entry of small
vessels or persons. It will also protect the columns from ice intrusion and reduce
lodging of
drift.
Figure 8‐2. Tangent Segments Have Been Introduced Along Vertical Faces of Tower Forms
for Ease
of
Construction
Pedestrian Trail Location: In the VQM concept, the pedestrian trail cantilevers from
the north edge of the bridge girder outboard of the north plane cable stays
(outboard scenario). This requires the trail to curve outward and around the north
column at each of the piers. The CRAVE study recommended that the pedestrian
trail be relocated onto the bridge girder, placing the trail inboard of the north cable
plane. The recommendation is based on improved constructability, improved
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 95/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 8‐5
operations, maintenance and inspection, and potential cost savings. With the trail
inboard of the cables, interference between pedestrian/bicycle travel and the cables
is eliminated, and pedestrians can be removed from the through traffic of the trail
by placing overlooks at the piers.
Both the outboard and inboard trail locations were evaluated for constructability,
safety, operations
and
maintenance,
cost
savings
and
visual
characteristics.
The
two
scenarios were modeled and compared and contrasted. The analysis concluded that
the inboard trail concept provides superior safety, operations and maintenance
characteristics. These include ease of access for safety, emergency, snow removal
and maintenance vehicles. Pedestrian movements are linear providing greater user
safety as the alignment affords trail users a clear sight lines along the entire length
of the bridge. Lighting is more easily and efficiently accomplished as roadway
lighting systems are adequate to provide pedestrian lighting needs for certain use
conditions and in times of higher use, it is easily supplemented with low level
lighting located within the hand rail. The inboard trail separates users from the cable
systems of
the
bridge
yet
still
provides
ample
viewing
of
the
structure
and
its’
components as well as views to the river beyond.
Figure 8‐3. View along pedestrian trail located inside of tower line
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 96/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
8‐6 June 2010
Figure 8‐4. Section view of trail located on north edge along west bound travel lanes
Pedestrian Trail Overlook: The VQM concept does not have specific locations
designated for pedestrians to stop along the bridge and view the river. The
inboard trail provides the opportunity to use the space adjacent to the north
column at each pier as an overlook. This will provide space off of the through
trail alignment for pedestrians to enjoy the scenic river valley, while separated
from bicycle traffic.
The overlook concept is the result of moving the trail inboard of the tower line. The
overlook concept was developed to take advantage of the opportunity for non
motorized bridge users to have an unobstructed view of the river north of the
bridge. The overlooks are cantilevered platforms that extend out over the water
from the tower locations. The overlooks provide a resting and viewing area which is
out of the flow of non motorized traffic and away from the vehicular roadway and
provide a commanding view of the river and bluffs. Because the overlooks are not
part of the through trail facility, the option was explored to construct an overlook at
alternating tower lines. This further refinement of the overlook concept has resulted
in the recommendation to include four overlooks on the bridge. They are to occur at
three locations, pier lines 9, 11, and 13.
The underside of the overlook structure was also studied in detail. The design team
considered the platform underside as an opportunity to provide a dynamic daytime
element and to use lighting at night to accentuate this feature.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 97/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 8‐7
Figure 8‐5. Typical Pedestrian Overlook outside of tower on north elevation of bridge
Figure 8‐6. View of underside of Pedestrian overlook surrounding tower
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 98/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
8‐8 June 2010
Pedestrian Trail Railing: The VQM concept is a full height metal railing with a
short concrete curb. The pedestrian rail provides a number of opportunities for
input from the VQAC related to curb height and railing details including trail
lighting fixtures built into the railing.
The pedestrian railing design was refined to simplify the rail as much as possible
while still maintaining the principles identified in the VQM. Both a full height rail with short curb and a taller curb with shorter rail were evaluated. The taller rail was
complicated in design. The rail has to meet safety requirement for containment up
to a height of 27” with a 4” vertical bar spacing and then 6” minimum vertical bar
spacing thereafter. Both a 4” spaced rail and a combined 4” and 6” spaced rail were
modeled and illustrated. These designs resulted in complicated and or visually dense
appearance. Both of these designs impeded the view to the river and increased
construction cost. It was also noted that these full height rail options with small curb
also would be subjected to greater mechanical damage from snow removal
operations and other maintenance activities.
The chosen
rail
consists
of
a taller
concrete
curb
upon
which
the
metal
rail
is
attached. The added curb height of 21‐3/4 inches allows the metal railing to be
constructed solely with 6‐inch center to center separation which reduces the
amount of material, as well as visually “lightens” the railing making it more
transparent and more easily seen through. The design of the rail can easily be
fabricated in modules which will reduce cost, and enhance constructability and
maintenance operations.
To increase the levels of lighting on the trail, the railing posts have been designed in
paired arrangement which provides a nesting location for the small LED lighting
fixture. This design provides protection for the lighting while reducing the visual
prominence of
the
fixtures.
Figure 8‐7.
Higher
curb
height
with
6”
vertical
picket
spacing
and
integral
LED
light
fixtures
incorporated into post on pedestrian hand railing.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 99/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 8‐9
Cable Anchorages: The VQM Concept has portrayed individual cable anchor
“pods” attached to the side of the box girder. This provides a certain texture to
the side of the bridge and exposes the supporting elements as part of the overall
visual appearance of the bridge. Refinement of the pods was performed to
confirm the structural dimensions needed to support the bridge and to maintain
the architectural
details
to
provide
a coordinated
and
smooth
transition
of
the
pod into the girders.
Two alternative cable connection details were studied. The exposed connection as
illustrated in the VQM and an alternative called a covered cable concept. The
structural requirements for the anchorages were determined and can be easily met
with either style. The motivation to evaluate alternative connection options was
largely as a result of visual consistency concerns of the design team. Both
alternatives were modeled and illustrated for the VQAC and Mn/DOT. The VQAC
unanimously chose the covered cable alternative because it supported the linear
form of the main bridge elements more effectively than the exposed cable
connection scenario.
There
are
also
some
construction,
maintenance
and
operations
benefits to the covered scenario as it easier to build, and provides a greater level of
protection for the cable terminations on the underside of the deck without limiting
inspection access to cable anchorages.
Figure 8‐8.
North
elevation
view
of
structure
with
covered
cable
connections
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 100/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
8‐10 June 2010
Minnesota approach Structures:
The VQM design of the Minnesota
Approach included a pier design
composed of tapered columns in
pairs. The columns are sloped at
1:33 and
the
pairs
are
separated
by
10’.
Two alternative column forms were
studied and modeled. This included
a paired column concept which
reduced the slope to 1:66 and the
separation between the pair to 5”
between columns. The other
concept was a single stem design
utilizing the 1:66 taper and reveals along the edges of the single column form. The
two alternatives
were
modeled
and
illustrated
from
various
view
points
along
the
Minnesota shore and adjacent river locations. It was determined that the single
tapered column form performed visually as well if not better than the pair
alternative and it was easier to construct. The VQAC and Mn/DOT agreed the single
column form was acceptable.
Figure 8‐10. View of Battered Abutment (Left) and Typical Single Stem Pier (Right) along
Minnesota Approach
Figure 8‐9. Enlarged view of covered cable
connections
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 101/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 9‐1
9 Construction
9.1 Introduction
This section discusses what are considered to be some of the more critical
construction issues for both land based construction and construction of the river
spans that
will
need
to
be
addressed
for
the
successful
construction
of
the
project.
In addition, construction of major bridges requires that constructability be
investigated and evaluated at every stage of design development as well as during
construction as the successful Design‐Build (DB) Contractor plans the construction of
the work. This constructability analysis is performed to ensure that the completed
bridge will be fully compliant with the contract requirements and that acceptable
standards for construction means and methods have been met.
9.2 Construction Staging Areas
Construction staging areas will be required for the river crossing bridge work and for
the approach
structures.
Some
of
these
will
fall
within
the
construction
limits
while
some may be located nearby. There are very limited areas for construction staging
adjacent to the project area because of the complexity of the terrain, the wetlands,
the river way, and numerous man‐made features. Therefore it may be necessary for
the DB Contractor to make arrangements for additional staging areas as necessary
to support his construction needs. The Contract documents should make clear what
potential staging areas are available to the contractor as well as that he is
responsible for any additional staging areas that he deems may be required.
9.3 Casting Yard
In addition
to
construction
staging
areas,
if the
DB
Contractor
elects
to
use
precast
construction for the approach spans, the river spans, or both, it will be necessary to
utilize an existing casting yard facility or to set up a new facility specifically for this
project. Either way, the casting yard will need to have sufficient area for the precast
operations, storage of materials and storage of an inventory for precast segments. It
can be expected that for a project of this size, a parcel of land that is 20 acres or
more may be needed for a new casting yard facility. It is not unusual that storage of
approximately one third of the total number of segments may be required though
this is clearly dependent on the planned and actual schedule for precasting and
erection.
9.4 Precast vs.
Cast
-in
-place
Construction
The DB Contractor may elect to utilize either precast or cast‐in‐place construction
methods or a combination thereof perhaps differentiating between the approaches
and the river crossing. Both methods are considered viable options and the selection
will be made in consideration of the contractor’s experience and preference,
availability of equipment, as well as precast plant considerations including transport,
schedule and economics.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 102/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
9‐2 June 2010
Some of the pros and cons of each construction method include the following.
9.4.1 Precast Construction
With over 5000 linear feet of bridge deck there is an opportunity for cost
effective utilization of precast segmental construction. The river crossing will
have constant depth segments and the approaches will transition to a shallower
depth consistent
with
the
shorter
spans.
Maintaining
a constant
depth
simplifies
and reduces the cost of precast forms and allows for improved efficiency.
If the schedule allows, precast operations could be set up indoors to allow year
round production of segments.
One advantage of precast construction is that precasting can proceed concurrent
with construction of substructure elements to further shorten the schedule.
Dependent on the location of the casting facility, transport of segments to the
erection site by barge and positioning the segments for lifting could be very
efficient. The smaller approach segments would more likely be transported by
truck.
Precast segment
height
is
expected
to
be
in
a range
from
10
feet
to
16
feet,
approximately 10 feet long and up to 52 feet wide.
Precast segment weights are expected to be in the range of 145 to 160 tons
which would require use of special haulers. Haul routes from the proposed
casting yard to the jobsite must be checked for any special restrictions or permits
that may apply.
Utilizing precast segments would limit the amount of concrete to be delivered on
the river to the piers, towers and some limited cast‐in‐place superstructure
closure joints.
The repetitious nature of precasting segments in a “factory” style environment
tends to
lead
to
a higher
quality
of
finished
concrete
product.
On the downside the precast method requires the use of either an existing
precast facility or establishment of a new facility for the project.
Some existing casting yards known to exist within a 100 mile radius of the
project site that could be considered include three commercial facilities
constructing precast bridge beams and pipe products and one contractor owned
facility previously utilized for precast segments.
Even if the precast method is selected, some cast‐in‐place work would still be
required on approaches at the transition sections.
Erection can be ongoing at multiple locations and can share erection equipment.
Erection
in
winter
months
can
proceed
provided
heated
enclosures
are
used
and
provisions are made for curing of epoxy joints and cast‐in‐place joints. It can be
expected that there may be times when it is simply too cold to proceed with
erection even with such measures being taken.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 103/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 9‐3
9.4.2 Cast -in- Place Construction
Again, the large quantity of bridge deck construction offers efficiency if the DB
Contractor elects to use travelers for cast‐in‐place construction, particularly for
spans over the water.
Cast‐in‐place work on the approaches could, alternatively, be done on falsework
rather than
by
use
of
travelers.
The travelers can be easily shipped to site by barge or truck.
Cast‐in‐place deck construction over water would be more likely to be restricted
during severe low temperatures from mid‐December to mid‐March.
Both methods require the use of specialized equipment and previous experience in
this type of construction should be mandatory including PT tendon installation and
tensioning and grouting. It is customary to require at least two previous projects or a
minimum of 5 years experience. Given the limited construction of extradosed
structures in the US, it may not be practical to include a similar requirement for the
St Croix River Crossing, though, requiring supervisory personnel to have experience
with the
construction
of
at
least
two
segmental
or
cable
‐stayed
structures
in
the
last
10 years should be considered.
In order to provide for segment erection to proceed through winter months, special
attention must be paid to grouting of tendons. If allowed by the Specifications,
tendon grouting may be postponed in the winter months by the use of a corrosion
inhibitor until substrate temperatures rise again where freezing of freshly placed
grout is no longer a concern.
9.5 Permitting Requirements
The Minnesota side of the river bridge has environmental restrictions with a high
quality wetland
in
the
area,
very
limited
access,
and
other
bluff
impacts.
The
Wisconsin side of the river has bluff impacts and mussel beds adjacent to the shore.
It is essential that the permitting is established based on reasonable assumptions of
how the bridge construction is to be carried out. Provisions need to be included for
the delivery and site relocations of large pieces of equipment such as cranes,
travelers, haulers, dirt moving equipment. This will require temporary haul roads
throughout the project limits extending to the river from TH 36 and STH 35.
Consideration needs to be given at this stage for permanent access typically in the
form of a 12‐ to 15‐foot wide corridor paralleling each structure.
Access to Pier 14 on the Wisconsin bluff will be particularly challenging as the grade
drops approximately
200
feet
from
STH
35
to
the
river.
It
is
important
that
the
land
acquisition on the Wisconsin side provide for switch backing of the access road as
needed.
It is noted that the concept drawing titled “Wetland Impact Details” includes an
aerial view of the Minnesota approach spans area showing temporary and
permanent access roads as well as areas that are expected to be impacted less than
and greater than 6 months during construction. It is recommended that the
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 104/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
9‐4 June 2010
Contractor be given some flexibility to develop his own means and methods that
could affect those areas perhaps by defining a limiting impact assessment and the
permitting requirements by the appropriate agencies for any DB Contractor
proposed deviations from what has been indicated.
9.6 Erosion Control
and
Environmental
Compliance
Given the sensitivity of the wetland areas and watercourses that the project is to be
constructed over, it is essential that erosion control measures be employed during
construction. Erosion control must also be considered during design so that the
contract documents adequately spell out the minimum requirements and
restrictions with which the DB Contractor must comply. For the land based
construction, this will be primarily based on standard best management practices
(BMP) for erosion and sediment control, establishment of construction limits,
signage, spill prevention and control, training of the workforce in environmental
awareness and monitoring.
For work
over
water,
the
Contractor
must
plan
his
operations
and
control
the
work
to prevent contamination of the watercourse particularly during cofferdam
installation, excavation, trestle construction, barge movements and
spudding/anchoring, dredging, handling and disposal of drill shaft spoils, equipment
fueling and accidental spillage. It is recommended that there be at least one
individual on the contractor’s staff whose sole responsibility is environmental
compliance. Consideration should also be given to creating a line item for
environmental compliance items so that Mn/DOT and Wis/DOT can control and
exactly what is required in this area.
9.7 Foundation Construction Methods
A cofferdam is anticipated to be constructed at each pier for the construction of the
drilled shaft foundation cap since the top of the structural cap is assumed to be at
the mudline or approx 20 feet below waterline. The cofferdam could be installed
before or after installing the steel casings and drilled shafts. If built prior to the
drilling of the shafts, the cofferdam could serve as a template for shaft construction.
Once the cofferdam frame work and steel sheeting is in place with several bracing
tiers that act as a drilled shaft liner template, the drilled shaft operation can begin.
Each drilled shaft casing will be placed by a large crane on a barge and driven by a
vibratory hammer to just above the top of rock. All of the casings for each pier will
be placed
prior
to
any
drilling
of
the
shafts.
Subsequent
to
placing
the
pier
casings,
a drill rig and the appropriate support equipment such as a mud plant, drilling tools
and a scow will be mobilized to begin drilling the shafts and rock sockets.
Once the rock socket is complete, an airlift can be used for cleaning the shaft by
recycling the drilling fluid though the mud plant which separates the fluid from the
suspended solids and allows the clean fluid to pass back to the drilled shaft. The
placement of the reinforcing cage will follow the cleaning process and will require a
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 105/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 9‐5
large crane due to the weight of the reinforcing which will likely be spliced in several
sections.
Tremies and CSL tubes will be placed prior to the concrete placement in each drilled
shaft. Due to the large quantity of concrete needed for each drilled shaft, a barge
mounted concrete batch plant may prove economically feasible.
Upon completion of the drilled shafts within the pier cofferdam, excavation for the
tremie seal can take place by using a water jet and an airlift coupled with a mud
plant and scow. Once excavated, concrete for the tremie seal will be placed up to an
elevation just short of the bottom of the foundation cap. It will be necessary to trim
the seal to remove laitance and humps from the tremie locations from protruding
into the foundation cap. When the trimming of the seal is complete, forming and
placement of the foundation cap and the bridge columns can then be constructed in
the dry.
9.8 Substructure Pier and Tower Construction
Access to the pier locations could be by barge as described above for drilled shaft
operations, by a series of floating pontoons/car barges or by trestle. Floating
pontoons would be quick to install and could be more easily reconfigured as work
progresses. Trestle construction would have the advantage of being off the water
and would not have to consider access and movements during winter months when
the river will be frozen. Either of these methods might be considered for perhaps
just one or two piers from either shore which would still leave the center spans open
for navigation. Whichever option is selected, it will be subject to USCG approval and
permitting.
The pier and tower construction will require delivery of rebar and concrete and will
require crane support. With the height of the towers exceeding 200 feet above the
water level, it may be efficient to utilize tower cranes supported on the permanent
pile caps. The tower cranes would also be able to service the towerhead assemblies,
stay anchor boxes, cable installation and tensioning.
The unique pier and tower cross section will pose some challenges in forming and
may limit the amount of reuse that each form can fulfill on a single column but
should permit reuse on other piers and towers.
It can be expected that the pier/tower construction will be made in approximately
ten lifts including three or four lifts for the towerhead incorporating the stay anchor
assemblies.
9.9 Reinforcing steel arrangements congestion and detailing
Since this is a Design‐Build project, it is to be expected that the DB Engineer of
Record’s (EoR) design drawings will be detailed such that rebar shop drawings are
not necessary. This would require that the detailer provide complete details and bar
bending diagrams for construction and to verify and resolve conflicts with stay
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 106/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
9‐6 June 2010
hardware, PT hardware and any other embeds required, such as ladders and
platforms or mechanical and electrical installations in the towers. The DB EoR should
also be responsible for identifying possible conflicts and for their resolution in the
development of the design drawings.
The design drawings should also identify any elements that are fracture critical such
as components
of
the
stay
anchor
assemblies
in
the
tower
heads
and
should
provide
clear requirements for all welds sizes, weld classification and NDE requirements.
9.10 Post -tensioning tendons and grouting
Complete details of the post‐tensioning system must be provided by the post‐
tensioning supplier. This should include records of all testing and material test
certificates that indicate compliance with the contract requirements. As stated in
the previous section, it is the responsibility of the EoR to ensure reinforcement
detailing is compatible with the post‐tensioning system and cable stay hardware and
that dimensional conflicts are resolved on the design drawings, not in the field.
Tensioning and grouting of the system should be performed by trained and
experienced personnel. American Segmental Bridge Institute certification for the
tensioning and grouting personnel is recommended. These operations also warrant
close inspection by QC personnel to ensure that the work is performed in
compliance with contract requirements to ensure that the life of the structure is not
compromised by lack of attention to detail. Consideration should be given to
inclusion of mock up tendon grouting to demonstrate adequacy of grouting
equipment and methods and for training of grouting crews.
9.11 Stay Installation
For an
extradosed
structure,
cable
tensioning
more
closely
resembles
post
‐
tensioning tendon stressing than the operations that are unique to cable stayed
bridge construction. The means and methods for the installation of the stay pipes
and for installation of the tendons do however need to be carefully planned and
carried out such that these critical elements are not damaged during construction.
9.12 Special architectural forming and finishing
It is noted that special architectural forming and finishing has been identified for this
structure. This relates to the form and shape of the piers, towers and the
superstructure. These are the result of the findings and recommendations contained
in the
Visual
Quality
Manual
(January
2007)
as
well
as
the
ongoing
concept
refinement process It should be recognized that there will be a premium cost
associated with the special architectural forming and finishing and the Contract
documents must be clear on what opportunity the DB Contractor may have to
propose alternate forms for any of these elements and the process for approval of
any such deviations.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 107/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 9‐7
9.13 Industry forum
An industry forum was held during the ASBI annual convention on Oct 25, 2009. At
the forum contractors were briefed on the conceptual details for the St Croix River
Crossing project and the schedule for procurement and for construction. This served
as a briefing to allow attending contractors to learn something about the Project. It
is recommended that a more formal forum be held prior to issuing the RFP to gather additional contractor input.
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 108/110
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 109/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report
June 2010 10‐1
10 Maintenance and Inspection
10.1 Introduction
Maintenance and Inspection are very critical considerations for any bridge project
particularly so when the bridge may be outside of the typical bridge construction
practice as
is
the
case
for
the
St
Croix
River
Crossing
utilizing
extradosed
spans
that
are relatively uncommon in the US.
The extradosed river spans for the St. Croix River Crossing will require a specific
maintenance and inspection strategy. Access to critical components of the structure
for maintenance and inspection must be incorporated into the design development,
and specific maintenance and inspection procedures must be developed for the
long‐life expected for the structure.
10.2 Critical Elements
Operation, inspection, maintenance and access requirements for each of the
following items listed below must be addressed in the RFP documents. The
Contractor will be required to address each of those requirements during the final
design. Deliverables from the successful DB Contractor should also include an
Operation, Inspection and Maintenance Manual prepared specifically for the St Croix
River Crossing. The manual must include comprehensive details for each component
of the bridge including a list of components likely to require replacement within the
expected life of the structure.
Items that will require ongoing operation and maintenance include:
Anti‐icing system
Bridge Lighting
Navigation Lighting
Aviation Lighting
Lighting inside the bridge
Lighting inside the towers
Drainage
Signage
It is anticipated that these elements will be inspected at least once per year but may
require immediate attention should something cease to function at any time.
Life expectancy of these items is less than the structure life expectancy and will
likely require
full
replacement
a number
of
times
over
the
life
of
the
structure.
Items that will require inspection and periodic maintenance include:
Bearings
Expansion joints
Overlay
Painted surfaces
8/12/2019 Concept Refinement Report
http://slidepdf.com/reader/full/concept-refinement-report 110/110
St. Croix River Crossing Preliminary Engineering
Concept Refinement Report It is recommended that these items be inspected every two years and in the event
that any unusual structure behavior or event has occurred.
It can be expected that these elements or components of them such as bearing
pads, will also have to be replaced a number of times over the expected life of the
structure.
Items that will require inspection and may require periodic maintenance include:
Cables and Protection Systems
Anchorage systems
Post‐tensioning systems
Concrete substructure elements
Concrete superstructure elements
Foundations including river piers below water
These are critical support elements of the structure and if constructed with care and
attention to detail should provide service for the life of the structure with little
maintenance. They
should
however
all
be
inspected
bi
‐annually
to
observe
any
changes in service and any indications of distress must be investigated and
addressed.
Access is a key aspect of any inspection program and it will be necessary to make
sure that equipment is available for regular inspection as indicated above. This will
be particularly the case for inspection of the exterior surfaces of the superstructure
elements of the river spans and the towers above deck. It will be important that
underbridge snoopers or manlifts that are currently in service will be able to reach
to those areas.
Substructure piers will require inspection from a manlift mounted on a barge.
For the Approach structures it will be important that permanent access be
constructed and maintained for future maintenance and inspection. This is
particularly important where there are wetlands adjacent to the bridge.