computer and network accommodation strategy …as4214, as2444, as1850, as2118, as1905, as1670,...
TRANSCRIPT
Originally Prepared by IPP Consulting Pty. Ltd. on behalf of The University of Melbourne
University Services
Infrastructure Services & Project Services
COMPUTER AND NETWORK
ACCOMMODATION STRATEGY
(“CANAS”)
2015
Standard for the construction of NaTH-1, NaTH-2 and NaTH-3 Communications Rooms
Revision – 2015.4d
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 2
SECTION 1 CONTROL SHEET
REV SECTION PAGE REVISION DESCRIPTION
APPROVED/
DATE
August 2011 All All Updated to 2011 standards and requirements
2015.1 All All Updated to 2015 standards and requirements
2015.2 All All Updated to 2015 standards and requirements
2015.3 All All Updated to 2015 standards and requirements
2015.4 All All Updated to 2015 standards and requirements
2015.4a All All Updated to 2015 standards and requirements
2015.4b All All Tidied up formatting
2015.4c All All Removed example pages and bad links
2015.4d Fixed Checklist to have correct rack facing distance
Document Ownership
This document is jointly owned by
University of Melbourne
Infrastructure Services and Project Services
All updates are to be approved by:
Head of Infrastructure Services or Delegate
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 3
Table of Contents
SECTION 1 CONTROL SHEET........................................................................................................ 2 SECTION 2 INTRODUCTION .......................................................................................................... 4
2.1 GLOSSARY AND ABBREVIATIONS ................................................................................... 4 2.2 BACKGROUND AND CONTEXT ......................................................................................... 5
SECTION 3 STANDARD REQUIREMENTS .................................................................................. 6 3.1 PROCESS WORKFLOW ......................................................................................................... 6 3.2 RACI MATRIX......................................................................................................................... 8
3.3 AGREED REQUIREMENTS ................................................................................................... 9
3.4 COMMS ROOM FLOOR LAYOUT ..................................................................................... 20 3.5 COMMS ROOM POWER DISTRIBUTION ......................................................................... 20
3.6 NETWORK STANDARDS .................................................................................................... 20
3.7 CHECKLISTS ......................................................................................................................... 20 SECTION 4 APPENDIX .................................................................................................................. 21
4.1 COMMS ROOM FLOOR LAYOUT ..................................................................................... 21
4.2 NaTH-2 COMMS ROOM RACK POWER DISTRIBUTION .............................................. 22 4.3 NATH-3 COMMS ROOM RACK POWER DISTRIBUTION ............................................. 23
4.4 IS COMMUNICATIONS ROOM SITE ACCEPTANCE CHECKLIST............................... 25 4.5 COMMUNICATIONS ROOM UPS AND PDU AUDIT CHECKLIST ............................... 26
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 4 Page 4
SECTION 2 INTRODUCTION
This document defines the build requirements and workflow process for development at each
of the non-Data Centre classifications of computer and network accommodation to be
provided at the University of Melbourne.
The classifications cover three differing types of accommodation ranging from small
communications cupboards to large telecommunications hubs, and are given in the following
table.
Acronym Expansion Description
NaTH-1 Network and
Telecommunications
Hub-1
A major communications hub on the backbone
Optical Fibre network feeding a number of
buildings with NaTH-2 rooms. It may also contain
a number of computing systems. An example is
Law 1.
NaTH-2 Network and
Telecommunications
Hub-2
A main building communications hub usually
feeding a number of floor based switches in
NaTH-3 rooms.
NaTH-3 Network and
Telecommunications
Hub-3
Usually a room feeding a single or multiple floors
in the building.
2.1 GLOSSARY AND ABBREVIATIONS
Term Meaning
ANSI American National Standards Institute
BD Building Distributor for incoming communications services
Cat 6 Category 6 cabling
CRAC Computer Room Air Conditioner
FFL Finished Floor Level
FIP Fire Indicator Panel
GPO General Power Outlet
IPP IPP Consulting
IT Information Technology
IS Infrastructure Services
N Number of units to perform a function
2N Twice the number of units required to perform a function (i.e.
100% redundancy)
N+1 Number of units to perform a function plus one additional spare
unit.
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 5 Page 5
Term Meaning
PS Project Services
PABX Private Automatic Branch Exchange
PIN Personal Identification Number
RU Rack Unit – a unit of vertical space in a computer rack
TIA Telecommunications Industry Association
TPF Test Point Frame
UoM University of Melbourne
UPS Uninterruptible Power Supply
UTP Unshielded Twisted Pair (e.g. Cat 6 cabling)
VESDA Very Early Smoke Detection Apparatus
2.2 BACKGROUND AND CONTEXT
The University requires a resilient infrastructure to match the heightened reliance of the
University’s business on electronic systems, particularly learning management, student
information and management systems, e-research and publishing management.
As such, all aspects of design and construction shall, as a minimum, comply with the relevant
Australian Standards, as well as ANSI/TIA-942. These include (but are not limited to) the
following: AS1428, AS4154, AS4155, AS3080, AS3084, AS3000, AS2293, AS1680,
AS4214, AS2444, AS1850, AS2118, AS1905, AS1670, AS1768, AS1668, AS1020, AS2201
and AS2107.
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 6 Page 6
SECTION 3 STANDARD REQUIREMENTS
3.1 PROCESS WORKFLOW
The process for delivery of a NaTH site is described below, and in the attached workflow
diagram – refer to section 4.8. PS and IS will agree on building specifications and document
requirements. The tasks include:
A standard brief is created for each building/room and then signed off by both PS and
IS.
Once agreement has been reached the NaTH Brief is provided to the external
consultant(s) &/or builder.
The site will then be constructed by the external party with commissioning being
performed by PS and IS in collaboration.
PS will manage the defects report and external consultants to resolve identified issues.
Once resolved PS will sign off the build and will then handover the building to IS for
operational use.
Once ownership has been accepted, IS will perform periodic site inspections.
IS will perform all maintenance and correct identified faults.
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 7
University of Melbourne - CANAS Standard
Exte
rna
l
Co
nsu
lta
nt(
s)
&/o
r B
uild
er
P&
CS
ITS
Workflow for Network and Telecommunications Hub (NaTH) Sites Development
10. Construct
11. Commission
13. Correct
Defects
14. Sign-off
Build and
handover
15. Accept
operational
ownership
1. Assemble
relevant
overall
design
parameters
& available
details
2. Send
request for a
NaTH Brief to
ITS based on
CANAS
standard
7. Liaise with
P&CS until
agreement for site
reached
7. Liaise with ITS
until agreement for
site reached
8. Sign-off site
brief
9. Site NaTH brief
provided
12. Report
Defects
18. Periodic
site
inspections
1. ASSEMBLE RELEVANT OVERALL DESIGN PARAMETERS & AVAILABLE DETAILS
Receive advice of new building / refurbishment of building
Gather building specifications and details
Document requirements including overall design parameters and available details
2. SEND REQUEST FOR A NATH BRIEF TO ITS BASED ON CANAS STANDARD
Once all design parameters and details are available, PS sends a request to IS for a NaTH standard
Send one request per site (may be batched)
3. ASSIGN NETWORK RESOURCE
S Network Services to assign responsible IS person to determine requirements
4. PERFORM NETWORK DESIGN
Network Resource to create Network design
5. DETERMINE NATH-2 OR NATH-3
Select NaTH standard most appropriate to this site
6. CREATE STANDARD NATH BRIEF
One per site with exceptions as applicable
7. LIAISE WITH P&CS/ITS UNTIL AGREEMENT FOR SITE REACHED
PS and IS teams (Facility Services, Network Services, Network BAU Project Manager) to liaise
Agreement of NaTH standard ensuring both IS and PS site exceptions are met
8. SIGN-OFF SITE BRIEF
Both PS and IS to signoff their acceptance and receive project schedule including site commissioning and site fit-
out dates
9. SITE NATH BRIEF PROVIDED
Once agreement reached between PS and IS, agreed site NaTH Brief to be provided to the external consultant(s)
&/or builder
10. CONSTRUCT
External consultant(s) &/or builder to construct site
5. Determine
NaTH-2 or
NaTH-3
6. Create
standard
NaTH brief
17. Site Fit-
Out and
Test -
Networks
11. COMMISSION
When build is complete, IS and PS will commission site using the Commissioning Checklist in
collaboration.
12. REPORT DEFECTS
PS to create report for all defects identified at time of commissioning
PS to provide report to external consultant (s) &/or builder
13. CORRECT DEFECTS
External consultant(s) &/or builder receives defect report
External consultant(s) &/or builder to correct all identified defects
14. SIGN-OFF BUILD AND HANDOVER
PS ensures all defects have been corrected in collaboration with IS Facilities Services team including
satisfactory completion of a Builder’s clean
PS signs off build and hands site over to IS for operational use
15. ACCEPT OPERATIONAL OWNERSHIP
IS accepts operational ownership of site
16. SITE FIT-OUT AND TEST - FACILITIES
IS Facilities Services coordinates the installation of UPS, PDU and Network Hardware in
collaboration with Builder’s electrical contractors.
IS Facilities Services configures and tests the UPS and PDU
17. SITE FIT-OUT AND TEST - NETWORKS
IS Networks Services installs network cables and configures and tests the Network hardware
18. PERIODIC SITE INSPECTION
IS to perform periodic site inspections
3. Assign
Network
Resource
4. Perform
Network
Design
16. Site Fit-
Out and
Test -
Facilities
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 8
3.2 RACI MATRIX
A RACI Matrix has been developed to support the above process workflow.
Activity
IS P
roje
ct
Ma
na
ger
IS N
etw
ork
Serv
ices
IS F
acil
ity
Ser
vic
es
IS D
ata
cen
ter S
up
port
Servic
es
IS H
ost
ing
Serv
ices
Ma
na
ger
PS
Pro
ject
Ma
nag
er
Ex
tern
al
Co
nsu
lta
nt
/
Bu
ild
er
PS
Ass
et S
ervic
es
1 Assemble relevant overall design parameters & available details RA
2 Send request for NaTH brief to IS based on CANAS standard I RA
3 Assign network resource A R I
4 Perform network design A R I
5 Determine NaTH-2 or NaTH-3 A C R
6 Create standard NaTH brief A R
7 Liaise with PS until agreement for site reached RA C C
7 Liaise with IS until agreement for site reached RA
8 Sign off site brief A I I R
9 Site NaTH brief provided RA
10 Construct A R
11 Commission A I R R
12 Report defects RA
13 Correct defects A R
14 Sign-off build & handover RA
15 Accept operational ownership A I I R
16 Site fit-out and test - Facilities A C R
17 Site fit-out and test - Networks A R C
18 Periodic site inspections R C A
19 Maintenance RA
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 9 Page 9
3.3 AGREED REQUIREMENTS
The following table lists all building requirements and their relevance to the NaTH type. Refer to
section 4.1 for NaTH-2 and NaTH-3 individual standard briefs which include columns for IS and
PC&S requirements, additional details and commission checklist.
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 10
Item Description NaTH-3 NaTH-2 NaTH-1
1. ARCHITECTURAL / BUILDING
1.1 General
1.1.1 Example of usage Floor Comms Distributor with less
than 200 data outlets
Main Building or campus switch room and major Communications room
(connects building to campus network) and/or
Network infrastructure providing at least 200 ports or more to the
building
Major network nodes
1.1.2 Location within building Minimal number of rooms per building subject to 90m copper cabling rule. Centrally located within floor.
At least one (1) per building. Centrally located within building and floor subject to 90 metre copper cabling rule and provision of additionally connected NaTH-3 or NaTH-2 rooms.
Preferably away from exterior walls
1.1.3 Proximity to service risers, goods lift etc.) Easy access to service risers Easy access to service risers Easy access to service risers
1.1.4 Aspect ratio (Length/width 1.0 to 1.5 is recommended) N/A N/A Maximum of 1:1.5 is strongly
recommended
1.1.5 Room Size (m2)
Typically 3 to 4m2
(Typically 1 rack)
If Main Building Switch Room then: Typically about 15 m
2 for 3-4 racks
Otherwise Typically about 10 m
2 for 2-3 Racks.
Typically about 40 m2
1.1.6 General level of fire rating (Nil / 1 hour / 2 hours)
1 hour 2 hours 2 hours
1.1.7 Dual-fed campus optical fibre services N/A Mandatory – Inter building and intra
building via separate cable pathways Mandatory – from separate cable
pathways
1.1.8 Building external perimeter security N/A N/A Mandatory – to Infrastructure
Services standards, with appropriate security across any external windows
1.1.9 Building goods access (Access to enable delivery of 45RU equipment racks).
Yes Mandatory Mandatory
1.1.10 Other requirements N/A N/A Mandatory – Adequate turning space needs to be allowed around ramps
and entrance doors
1.1.11 Plant Ante room N/A N/A Site specific
1.1.12 Water pipes crossing overhead? Not desirable Any hazards are to be remediated as agreed between Infrastructure
Services and Project Services.
Any hazards are to be remediated as agreed between Infrastructure
Services and Project Services.
1.2 Floors
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 11
Item Description NaTH-3 NaTH-2 NaTH-1
1.2.1 If exposed, painted? Yes and sealed Mandatory and sealed Mandatory and sealed
1.2.2 Sealed against ingress of water Site specific. Particularly important for
basement areas Site specific. Particularly important
for basement areas Site specific. Particularly important
for basement areas
1.2.3 Floor surface Dust & lint free, e.g. No carpet Anti-static Vinyl Anti-static Vinyl
1.2.4 Anti static measures N/A N/A Yes – anti static mat, dirt collecting
mat
1.2.5 Raised floor installed? N/A N/A Optional, but preferable
1.2.6 Access floor height N/A N/A 300 mm from slab to FFL
1.2.7 Tile dimensions N/A N/A 600 mm x 600 mm
1.2.8 Air plenum under floor N/A N/A Site specific
1.2.9 Tiles along walls shall be able to be lifted N/A N/A Yes
1.2.10 Tile supports N/A N/A Heavy duty, bolted stringers. Must be
able to be removed when needed
1.2.11 Floor loading capacity (Ref: AS4154 categories) N/A N/A Heavy Duty category
1.2.12 Maximum tile weight (For uniformity, all tiles should be of the type as those used in the 258Q Data Halls 1 & 2)
N/A N/A 10 Kg
1.2.13 Tile surface N/A N/A High pressure laminate
1.2.14 Surface colour N/A N/A Light
1.2.15 Edge strips on perimeter of floor tiles N/A N/A Yes
1.2.16 Ramp required N/A N/A Yes – removable type is acceptable
1.2.17 Carpet floor tiles on top N/A N/A No
1.2.18 Average load per rack N/A N/A 200Kg
1.2.19 Maximum load per rack N/A N/A 400 Kg per 600 mm x 600 mm floor
tile, also site specific
1.2.20 Maximum point load (e.g. from tape silo etc.) N/A N/A 200 Kg (based on 800 Kg item with
four (4) corner feet)
1.2.21
Number of vented tiles (underfloor cooled locations only) (Vents to feature adjustable air flow rate as well as front to back directional control (i.e. ability to be biased to flow towards or away from a rack.)
N/A N/A One (1) per planned rack space
1.2.22 Number of cut tiles (Vents to be ½ tile size) N/A N/A Site specific
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 12
Item Description NaTH-3 NaTH-2 NaTH-1
1.2.23 Tile cut – shape(s) N/A N/A Site specific
1.2.24 Tile cuts to be edged? (Vinyl/brustle) N/A N/A Yes – this is critical to prevent
damage to power cables (Prefer bristle type to stop cold air leakage)
1.2.25 Number of spare cut tiles required N/A N/A Site specific
1.2.26 Number of spare uncut tiles required N/A N/A One per 30 square metres or part
thereof
1.2.27 Tile Lifter (With wall mounting rack) N/A N/A One (1)
1.2.28 Design load per rack
1.2.29 Acoustic properties
Specific provisions should be made to reduce noise levels from 80 dBA inside to 40dbA-50 dBA outside,
depending on the adjacent occupancy
Specific provisions should be made to reduce noise levels from 80 dBA
inside to 40dbA-50 dBA outside, depending on the adjacent
occupancy
Specific provisions should be made to reduce noise levels from 80 dBA inside to 40 dbA-50 dBA outside,
depending on the adjacent occupancy
1.3 Walls
1.3.1 Room walls to extend from floor slab to roof slab No, provided that the room fire rating
and soundproofing is maintained. Optional, provided that the room fire
rating is maintained. Optional, provided that the room fire
rating is maintained.
1.3.2 Room walls to be fire rated (Hours) Yes - 1 hour Mandatory - 2 hour Mandatory - 2 hour
1.3.3 Acoustic properties
Specific provisions should be made to reduce noise levels from 80 dBA inside to 40 dbA-50 dBA outside,
depending on the adjacent occupancy
Specific provisions should be made to reduce noise levels from 80 dBA inside to 40 dbA-50 dBA outside,
depending on the adjacent occupancy
Specific provisions should be made to reduce noise levels from 80 dBA inside to 40 dbA-50 dBA outside,
depending on the adjacent occupancy
1.3.4 Room walls painted If exposed to seal against dust. Yes Yes
1.3.5 Paint type & colour N/A N/A Semi-gloss
1.3.6 Sealed against ingress of water Site specific. Particularly important for
basement areas. Site specific. Particularly important
for basement areas. Site specific. Particularly important
for basement areas.
1.4 Ceiling
1.4.1 Suspended or fixed ceiling required? No ceiling is preferred No ceiling is preferred No ceiling is preferred
1.4.2 If exposed slab, painted? Yes and sealed against moisture Mandatory and sealed against
moisture Mandatory and sealed against
moisture
1.4.3 Ceiling space access If a ceiling is in place it must allow for adequate access (i.e. access hatch or
similar).
If a ceiling is in place it must allow for adequate access (i.e. access hatch
or similar).
If a ceiling is in place it must allow for adequate access (i.e. access hatch
or similar).
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 13
Item Description NaTH-3 NaTH-2 NaTH-1
1.4.4 Height – access floor to first obstruction (minimum) - mm 2550mm 2700mm 2700mm
1.4.5 Typical equipment rack height (mm) 2200mm (45RU) rack plus pallet plus jack
2200mm (45RU) rack plus pallet plus jack
2200mm (45RU) rack plus pallet plus jack
1.4.6 Acoustic properties
Specific provisions should be made to reduce noise levels from 80 dBA inside to 40 dBA-50 dBA outside,
depending on the adjacent occupancy
Specific provisions should be made to reduce noise levels from 80 dBA inside to 40 dBA-50 dBA outside,
depending on the adjacent occupancy
Specific provisions should be made to reduce noise levels from 80 dBA inside to 40 dBA-50 dBA outside,
depending on the adjacent occupancy
1.4.7 Ceiling / slab to protect from leaks Appropriate works required to mitigate the risks
Appropriate works required to mitigate the risks
Appropriate works required to mitigate the risks
1.4.8 Power cable tray space required Yes – Above rack Mandatory – Above rack Mandatory – Above rack
1.4.9 Data cable tray / catenary space required Yes – refer to University of Melbourne Standards for the installation of voice
and data cabling
Mandatory – refer to University of Melbourne Standards for the
installation of voice and data cabling
Mandatory – refer to University of Melbourne Standards for the
installation of voice and data cabling
1.5 Doors
1.5.1 Number of doors Minimum of one Minimum of one Minimum of one
1.5.2 Door control (Key/access control)
Proximity card access and Cyberlock electronic key – Designed to restrict
unauthorised access to room (e.g. no standard traditional physical key
access).
Proximity card access and Cyberlock electronic key – Designed to restrict
unauthorised access to room (e.g. no standard traditional physical key
access).
Proximity card access and Cyberlock electronic key – Designed to restrict
unauthorised access to room (e.g. no standard traditional physical key
access).
1.5.3 Laminated glass in door? No Optional Optional
1.5.4 Door width (mm) For a new room build: 900 mm Minimum for existing rooms 820 mm
For a new room build: 900 mm Minimum for existing rooms 820 mm
Minimum of 1350 mm
1.5.5 Door Height (mm) Minimum effective height of 2030 mm Minimum effective height of 2030 mm Minimum effective height of 2030 mm
1.5.6 Twin Leaf style N/A N/A Yes
1.5.7 Door closer Dorma TS73 or functional equivalent Dorma TS73 or functional equivalent Dorma TS73 or functional equivalent
1.5.8 Door seals Raven RP24 stop and RP38 draft stopper or functional equivalent
Raven RP24 stop and RP38 draft stopper or functional equivalent
Raven RP24 stop and RP38 draft stopper or functional equivalent
1.5.9 Acoustic properties
Specific provisions should be made to reduce noise levels from 80 dBA inside to 40 dBA-50 dBA outside,
depending on the adjacent occupancy
Specific provisions should be made to reduce noise levels from 80 dBA inside to 40 dBA-50 dBA outside,
depending on the adjacent occupancy
Specific provisions should be made to reduce noise levels from 80 dBA inside to 40 dBA-50 dBA outside,
depending on the adjacent occupancy
2. Mechanical Services
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 14
Item Description NaTH-3 NaTH-2 NaTH-1
2.1 Equipment heat load
Infrastructure Services to specify Network equipment load at design
stage. Use by other departments to be determined in agreement with
Infrastructure Services
Infrastructure Services to specify Network equipment load at design stage. Use by other departments to be determined in agreement with
Infrastructure Services
Infrastructure Services to specify Network equipment load at design stage. Use by other departments to be determined in agreement with
Infrastructure Services
2.2 Independent of base building chilled water system N/A N/A Yes – this is mandatory
2.3 Underfloor cooling N/A N/A Site specific
2.4 Redundancy No Optional, however this is site specific Optional, however this is site specific
(CRAC N + 2)
2.5 Modular system to allow additional units to be added later N/A N/A Yes
2.6 Computer Room Pressurisation N/A N/A Yes, positive pressure to prevent
dust ingress
2.7 Run off base building generator Yes, if available Yes, if available Yes, if available
2.8 Cooling method (Air/Water/Dry condenser) N/A N/A As specified by the Services
Engineer
2.9 Cooling equipment re-settable on fault? N/A N/A Yes – so that staff can keep system
operating whilst waiting for help
2.10 Automatic fault dial out? N/A N/A Yes
2.11 Fire dampers for supply and return air ducting N/A N/A Yes
2.12 Interface mechanical control panel to EMS for alerts N/A N/A Yes
2.13 Temperature and humidity sensors connected to EMS No Mandatory – via UPS add-on feature Mandatory – via UPS add-on feature
3. Electrical Services
3.1 Lighting
3.1.1 Grid pattern N/A N/A Yes – Design to minimize shadows and provide maximum light into the
racks
3.1.2 Light to penetrate racks
Yes - Lighting must be installed so as to provide adequate horizontal
illumination into the equipment racks
Mandatory - Lighting must be installed so as to provide adequate
horizontal illumination into the equipment racks
Mandatory - Lighting must be installed so as to provide adequate
horizontal illumination into the equipment racks
3.1.3 High efficiency ballasts N/A N/A Yes
3.1.4 Light to penetrate racks N/A N/A Lighting must be installed so as to
provide adequate horizontal
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 15
Item Description NaTH-3 NaTH-2 NaTH-1 illumination into the equipment racks
3.2 Power
3.2.1 Dual feed from electrical supplier N/A N/A Yes, if available
3.2.2 Operating capacity (KW)
Infrastructure Services to specify Network equipment load at design
stage. Use by other departments to be determined in agreement with
Infrastructure Services
Infrastructure Services to specify Network equipment load at design stage. Use by other departments to be determined in agreement with
Infrastructure Services
Infrastructure Services to specify Network equipment load at design stage. Use by other departments to be determined in agreement with
Infrastructure Services
3.2.3 Electrical outlets – type (Screw down, captive) Captive Captive Captive
3.2.4 Power Distribution Unit (PDU) Type (model number)
PDU must be able to communicate via the network with the Infrastructure Services Communications Room Monitoring Software and must have sufficient 10A and 16A outputs as required.
Infrastructure Services to provide final bill of materials.
Use Schneider Electric AP8853 as 32A Mains PDU or Functional Equivalent.
Use Schneider Electric AP7821 or AP8858 as 16A UPS PDU or Functional Equivalent.
PDU must be able to communicate via the network with the Infrastructure Services Communications Room Monitoring Software and must have sufficient 10A and 16A outputs as required.
Infrastructure Services to provide final bill of materials.
Use Schneider Electric AP8853 as 32A Mains PDU or Functional Equivalent.
Use Schneider Electric AP7821 or AP8858 as 16A UPS PDU or Functional Equivalent.
PDU must be able to communicate via the network with the Infrastructure Services Communications Room Monitoring Software and must have sufficient 10A and 16A outputs as required.
Use Schneider Electric AP8853 as 32A as UPS PDU or Functional Equivalent.
3.2.5 Power Distribution Units (PDU) per Active Equipment Rack (number)
Two (2) powered via Mains
Provide 50% of rack with required number of PDUs powered via Mains and 50% required number of PDUs powered via UPS. Typical configuration will have 1-2 Mains PDUs and 1-2 UPS PDUs depending on load within rack.
Two (2) powered via UPS
3.2.6 Electrical outlets per active rack (number) Two (2) outlets. One (1) Per PDU. 1 outlet per PDU. 1 Outlet per UPS. Two (2) outlets. One (1) Per PDU.
3.2.7 Outlets location relative to racks Yes - Above Rack Mandatory - Above Rack Mandatory - Above Rack or below
raised floor if one exists
3.2.8 One circuit per power outlet Yes
To restate: Each power outlet must
Mandatory
To restate: Each power outlet must
Mandatory
To restate: Each power outlet must
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 16
Item Description NaTH-3 NaTH-2 NaTH-1 be connected to an independent
circuit breaker
Note: Use of domestic power extender boards is banned.
be connected to an independent circuit breaker
Note: Use of domestic power extender boards is banned.
be connected to an independent circuit breaker
Note: Use of domestic power extender boards is banned.
3.2.9 GPO (Quantities to be advised at detailed design stage. Must be RCD protected).
One (1) GPO near door 200 AFL [for use by cleaner]
& one (1) per security panel (no
extension boards allowed)
One (1) GPO near door 200 AFL [for use by cleaner]
& one per security panel (no extension boards allowed)
Two types of GPOs required: 1) Essential supply GPOs, with RED
faceplates 2) Non-essential supply GPOSs to
have white faceplates 2 x double GPOs of each type at
either end of room
3.2.10 UPS No
UPS Provides building switch with filtering and up time during mains interruptions to maintain network service and assist with service recovery.
UPS must be able to communicate via the network with the Infrastructure Services Communications Room Monitoring Software and must have sufficient 10A and 16A outputs as required.
Infrastructure Services to provide detailed specifications at design stage.
Use Schneider Electric SRT10KRMXLI with SRT192RMBP2 Battery Units as required or Functional Equivalent.
UPS must be able to communicate via the network and MODBUS protocols with the Environment Monitoring System.
Infrastructure Services to provide detailed specifications at design stage.
Use Emerson NXR90KVA or Functional Equivalent.
3.2.11 UPS Warranty to be purchased (Years) N/A Yes, minimum of 2 year warranty is
required. Yes, minimum of 1 year warranty is
required.
3.2.12 UPS Redundancy (N / N+1 / 2N) N N N
3.2.13 UPS Minutes of backup (Autonomy) at full power (minutes) N/A
10 Min. to keep load active during majority of short Mains interruptions. Only Main Building Switch equipment
is required to be running during Mains interruptions to assist with
network service recovery.
10 Min. to keep load active during majority of short Mains interruptions. All network equipment within the data
hall must be kept alive during this period.
3.2.14 UPS SNMP interface for remote monitoring N/A Mandatory – built in Mandatory – built in
3.2.15 UPS – temperature and humidity sensing module N/A Mandatory – purchase separately Mandatory – purchase separately
3.2.16 UPS – rack mounting rail kit N/A Mandatory Mandatory
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 17
Item Description NaTH-3 NaTH-2 NaTH-1
3.2.17 Interface UPS to environmental monitoring panel N/A Mandatory - Purchase separately Mandatory - Purchase separately
3.2.18 Generators independent of base building N/A N/A Yes – one (1)
3.2.19 Generator capacity to suit (base or independent) N/A N/A All of room
3.2.20 Generator fuel tank quantities (base or independent) N/A N/A Three (3) days, contingent on assured fuel delivery contract.
3.2.21 Generator Testing N/A N/A
Monthly. Controls within the Computer Room to allow for generator testing and power
maintenance activities. Generator status indication to be provided in Computer Room and Gatekeeper
area.
3.2.22 Power Distribution board features N/A N/A
Power distribution boards (2 off) are to be installed within the room.
To be fitted with phase present LEDs
To be fitted with intelligent power meters connected to the EMS
To be fitted with surge suppression (SAD type)
To be fitted with Generator power present LEDs
3.3 Earthing
3.3.1 Each cabinet to be separately earthed 6 mm earth strap from nearest board to each rack terminating earth bar.
6 mm earth strap from nearest board to each rack terminating earth bar.
Yes
3.3.2 Other Items to be earthed Yes - Cable trays and IT Network
Switches as appropriate Mandatory - Cable trays and IT
Network Switches as appropriate Mandatory - Cable trays and IT
Network Switches as appropriate
3.3.3 TRC required N/A N/A Only for NaTH-1 sites with a PABX
3.4 Lightning
3.4.1 Building protection As per standard As per standard As per standard
3.4.2 Electrical mains protection Yes, prior to UPS bypass switching Yes, prior to UPS bypass switching Yes, prior to UPS bypass switching
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 18
Item Description NaTH-3 NaTH-2 NaTH-1
3.5 Power Cabling
3.5.1 Cable tray to be supplied by electrical contractor Yes Mandatory Mandatory
3.5.2 Separate cable trays for electrical and data Yes Mandatory Mandatory
3.5.3 As built drawings of cable tray and cable routes No Yes Yes
3.5.4 Overhead cable tray route separation Yes - Must maintain separation from electrical and light fixtures of at least
0.6m
Mandatory - Must maintain separation from electrical and light
fixtures of at least 0.6m
Mandatory - Must maintain separation from electrical and light
fixtures of at least 0.6m
4. Equipment Racks
4.1 Update this section with rack requirements
4.2 Rack type
Yes - Bolted to floor
Refer cabling standards
Racks MUST have square cage nut holes
Mandatory - Bolted to floor
Refer cabling standards
Racks MUST have square cage nut holes
Mandatory - Bolted to floor
Refer cabling standards
Racks MUST have square cage nut holes
4.3 Rack bracing Yes – bolted to floor Mandatory – bolted to floor Mandatory – bolted to floor
5. Fire Protection
5.1 General level of fire rating – walls, doors (Hours) 1 hour 2 hours 2 hours
5.2 Sprinkler type As per building code. Wire guard for
sprinkler heads if fitted. As per building code. Wire guard for
sprinkler heads if fitted. As per building code. Wire guard for
sprinkler heads if fitted.
5.3 Smoke detectors
Yes, 1 (No) detector to be fitted – to be either an
ionization type or an obscuration type.
Thermal sensors are not suitable.
Yes, 1 (No) detector to be fitted – to be either an
ionization type or an obscuration type.
Thermal sensors are not suitable.
Yes, both ionization and obscuration sensors within a smoke detector to
be in alarm before the smoke detector raises an alarm to the FIP
5.4 Portable fire extinguishers Yes – CO2 type. Dry chemical type are NOT to be supplied for use within the
IT equipment areas
Mandatory – CO2 type. Dry chemical type are NOT to be supplied for use
within the IT equipment areas
Mandatory – CO2 type. Dry chemical type are NOT to be supplied for use
within the IT equipment areas
5.5 EWIS N/A
Special attention to be made to EWIS and fire alarm strobes due to the very high ambient noise in there spaces and the sound absorption treatment to stop noise transfer out of the room
to adjacent areas
Special attention to be made to EWIS and fire alarm strobes due to the very high ambient noise in there spaces and the sound absorption treatment to stop noise transfer out of the room
to adjacent areas
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 19
Item Description NaTH-3 NaTH-2 NaTH-1
6. Security Services
6.1 System Use standard UoM system Use standard UoM system Use standard UoM system
6.2 Remote monitoring N/A N/A Yes, to be accessible remotely for
both monitoring and control.
6.3 Proximity cards and keys
Proximity card access and Cyberlock electronic key
Designed to restrict unauthorised access to room (e.g. no standard traditional physical key access).
Proximity card access and Cyberlock electronic key
Designed to restrict unauthorised access to room (e.g. no standard traditional physical key access).
Proximity card access and Cyberlock electronic key
Designed to restrict unauthorised access to room (e.g. no standard traditional physical key access).
6.4 Hold open door alarms Yes Mandatory Mandatory
6.5 CCTV monitoring of computer room None Optional Optional
6.6 CCTV Recorded None Optional Optional
6.7 Evacuation floor plan Yes - On back of door Mandatory - On back of door Mandatory - On back of door
6.8 Signage level Room number only Room number only Room number only
7. Environmental Monitoring System Services
7.1 Elements to be monitored Yes - Temperature, humility and power capacity monitored via UPS
Mandatory - Temperature, humility and power capacity monitored via
UPS
Mandatory - Temperature, humility and power capacity monitored via
UPS
8. Cabling Services
8.1 Cable standards Yes - Refer to the University of Melbourne Standards
Mandatory - Refer to the University of Melbourne Standards
Mandatory - Refer to the University of Melbourne Standards
9. Other Requirements
9.1 In room telephone N/A N/A Yes, cordless phone required
9.2 Additional telephone lines N/A N/A Yes, one for the Ems and one for the
mechanical services alarms
9.3 Equipment maintenance N/A N/A
Maintenance for a minimum of 12 months to be purchased with major
capital items such as UPS, Generators, Mechanical services and
similar
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 20
3.4 COMMS ROOM FLOOR LAYOUT
Refer to section 4.2 for Comms Room Layout diagrams.
3.5 COMMS ROOM POWER DISTRIBUTION
There are special requirements for NaTH-2 and NaTH3 Comms Room Rack Power
Distribution.
For NaTH-2 all power connections from switch power supplies must be connected to the
UPS and PDU as down in the diagram in section 4.3.
The UPS and PDU loads must be limited to 6KW or a second UPS and PDU will be required.
For NaTH-3 each 16A rated supply outlet of each power supply is to be powered off its own
16A Bank PDU outlet in the configuration shown in section 4.4. Distribution of 10A rated
connections to each PDU must be balanced between each 16A bank. Switches with single
10A rated supplies are to have their power evenly distributed across each PDU to minimise
the number of switch outages when a PDU fails. Switches with dual 10A supplies are to
have their power split between both PDUs.
3.6 NETWORK STANDARDS
The procedure – standards for the installation of Tele Networks can be found in section 4.5.
The document can be launched from this section by clicking on the link.
3.7 CHECKLISTS
Refer to section 4.6 for the IS Communications Room Site Acceptance Checklist and section
4.7 for the Communications Room Managed Objects Audit Checklist. These checklists may
be used as part of the Site Acceptance.
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 21
SECTION 4 APPENDIX
4.1 COMMS ROOM FLOOR LAYOUT
30
00
10
00
10
00
10
00
100010001000
94
6 x
10
67
94
6 x
10
67
3800
Se
cu
rity p
an
els
Three (3) Rack NaTH-2 layout
94
6 x
10
67
800
800
NOTE: Where a single communications room attends to the comms needs of a whole building, more racks (hence additional
floor space) is required, typically 4-5.
30
00
10
00
10
00
10
00
100010001000
94
6 x
10
67
94
6 x
10
67
3000
Se
cu
rity p
an
els
Two (2) Rack NaTH-3 layout
NOTE: In some cases a larger space is required.
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 22
4.2 NaTH-2 COMMS ROOM RACK POWER DISTRIBUTION
ONLINE
PROBE 10/100Base-T
ON
16A
16A
SWITCH POWER
SUPPLIES
UPS
PDU
Input circuit breaker to ON
UPS is ONLINE and not in bypass
Output circuit breaks are ON
To LAN PortTo temp/humidity sensor
To LAN
Port
To Mains Supply
(captive outlet)
NaTH-2 Comms Room Rack Power Distribution (typical)
All power connections from switch power supplies must be
connected to the UPS and PDU as shown in the above
diagram.
Assumptions:
-
Building power failure condition:
- UPS will sustain switch using battery power for a limited
time depending on load. Switch power supplies will not
remain redundant.
PDU Failure condition:
- UPS will sustain switch via mains. Switch power supplies
will not remain redundant.
UPS Failure condition: (eg. inverter thermal overload)
- PDU will sustain switch via mains. Switch power supplies
will not remain redundant.
To Mains Supply
(captive outlet)
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 23
4.3 NATH-3 COMMS ROOM RACK POWER DISTRIBUTION
16A
16A
Cisco 6500 or Equivalent Switch
power supplies
PDU
NaTH-3 Comms Room Rack Power Distribution (typical)
16A
16A
PDU
Each 16A rated supply outlet of each power supply is to be
powered off its own 16A Bank PDU outlet in the configuration
shown.
Assumptions:
- Switch power draw is not to exceed 6kW (25A)
PDU or Switch Power supply Failure Condition:
- Switch will draw up to 25A via its other supply from the
other PDU evenly spread across both 16A banks. Switch will
no longer have power supply redundancy.
16A Rated supply outlet
16A Bank Pdu Outlet
To Mains Supply
(captive outlet)
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 24
16A
16A
PDU
NaTH-3 Comms Room Rack Power Distribution (typical)
16A
16A
PDU
Distribution of 10A rated connections to each PDU must be
balanced between each 16A Bank.
Switches with single 10A rated supplies are to have their
power evenly distributed across each PDU to minimise the
number of switch outages when a PDU fails.
Switches with dual 10A supplies are to have their power
spread between both PDUs.
To Mains Supply
(captive outlet)
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 25
4.4 IS COMMUNICATIONS ROOM SITE ACCEPTANCE CHECKLIST
Date: Name:
Building: No: Room/Level:
Pre-Installation Room Checklist: √ or X
Access card and EKA Key (if installed) entry to the room is functioning
Smoke detector(s) in room and fire extinguisher for electrical fires
Separate, working automatically controlled split system air conditioner installed
with functioning remote control available if model permits
Room is complete as per CANAS Requirements i.e. all building works for the
room are finished, all painting complete, is sealed to avoid dust, water or
contaminant entry and all cable entry points have been ‘stopped’
Lights are functioning and are adequate for visibility of all components
Networks specified switch rack has been installed and as per standards
recommendation i.e. a minimum of 1000mm from the back and front facing
walls. Rack placement allows for easy installation of equipment with front and
doors able to be fully opened
The rack is earthed, stable and ready for equipment installation
Captive outlets for PDUs on independent C/B per rack, overhead
Power outlets are labelled with relevant C/B
UPS power feed installed with Distribution Board and Circuit Breaker Labelled
Room free of tripping hazards, electrical hazards, building materials and is dust
free
Has an EHS implications check been considered? Yes or No
Summary of risk rating: None Low Medium High
Ensure any other/additional requirements are completed
If the room is EHS compliant are all boxes ticked? That is, if there are no defects that require
immediate remediation which prevents proceeding, then installation of managed objects can
begin.
Incomplete work / Defect list / Issues to Remediate:
Checked by:
Name:
UoM Standards for NaTH sites Commercial-in-Confidence
Ref: CANAS 2015 Rev 4d.doc Page 26
4.5 COMMUNICATIONS ROOM UPS AND PDU AUDIT CHECKLIST
Audit date: Building: No:
Name: Room:
UPS Installation Checklist: √ or X
UPS physically installed in rails and fitted to rack
UPS has battery cover plates installed
UPS breakers are correctly set to ON and UPS is online (not in bypass)
UPS load equipment is properly balanced and mains cables labeled with
‘UPS’
UPS Temp/humidity sensor properly installed
UPS orange network cable connected to switch:
Switch name: Blade/Port:
UPS name and overpower warning label has been placed on the front.
Name:
UPS has connectivity over the LAN e.g. can visit UPS via web browser
UPS has been configured in Infrastructure Central EMS System
PDU Installation Checklist:
PDU physically installed into rack and not loose
PDU has 16A supply cables connected one on each bank
PDU orange network cable connected to switch
Switch name: Blade/Port:
PDU has connectivity over the LAN e.g. can visit PDU via web browser
AC Installation Checklist:
AC installed and turned on – temp set to
UOM Asset tag:
A/C No: Serial No: Model:
UPS No: Model:
PDU No:
Other / Additional requirements:
Incomplete work / Defect list: