Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF) WORK COMPLETION REPORT TILL 9 TH JULY, 2014 M/s AAM India Manufacturing Corporation Pvt Ltd Table of contents 1. At-a-glance Project key milestones status 2. EHS Issues 3. Construction Progress Update 4. Open Issues and Risk Log 5. Quality Issues 6. General issues closed this week 7. Pictures Prepared by : Zuber Ahmed

Upload: zuber-ahmed

Post on 21-Jul-2016

8 views

Category:

Documents


0 download

TRANSCRIPT

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

WORK COMPLETION REPORT

TILL 9TH JULY, 2014

M/s AAM India Manufacturing Corporation Pvt Ltd

Table of contents

1. At-a-glance Project key milestones status 2. EHS Issues 3. Construction Progress Update 4. Open Issues and Risk Log 5. Quality Issues 6. General issues closed this week 7. Pictures

Prepared by : Zuber Ahmed

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

AAM PMF COMPLETION REPORT ON 9th JULY, 2014

ITEM DESCRIPTION SCHEDULED

START

SCHEDULED

FINISH

ACTUAL

START

ACTUAL

FINISH

STATUS

CANTEEN WORKS

• PLACING FURNITURE 26-3-14 8-4-14 31-3-14 - IN PROGRESS

• CLEANING 19-3-14 19-3-14 1-4-14 1-4-14 COMPLETED

• HANDOVER 20-3-14 20-3-14 1-4-14 1-4-14 COMPLETED

LANDSCAPING WORKS

• DRESSING, LEVELLING & CLEANING THE DEBRIS

6-4-14 15-4-14 17-4-14 24-5-14 COMPLETED

• Planting Grass, Shrubs, Herbs, etc… 5-5-14 10-5-14 30-4-14 21-6-14 COMPLETED

OUTSIDE BOUNDARY WALL WORKS

• RR MASONARY WORKS 18-4-14 8-5-14 10-4-14 28-5-14 COMPLETED

• FINISHING WORKS 8-5-14 9-5-14 8-5-14 15-6-14 COMPLETED

• HANDOVER 10-5-14 10-5-14 30-6-14 30-6-14 COMPLETED

OFFICE INTERIOR WORKS

• FALSE CEILING WORKS 14-4-14 20-4-14 12-4-14 6-6-14 COMPLETED

• HVAC EQUIPMENT ERECTION 15-4-14 20-4-14 29-5-14 11-6-14 COMPLETED

• PAINTING & POLISHING 22-4-14 28-414 22-4-14 10-6-14 COMPLETED

• FURNITURE INSTALLATION 25-4-14 30-414 8-5-14 30-5-14 COMPLETED

• GENTS TOILET WORKS 15-4-14 30-4-14 16-4-14 7-7-14 COMPLETED

• MEDICAL & STORAGE ROOM 15-5-14 30-5-14 15-7-14 - IN PROGRESS

• HANDING OVER 30-4-14 30-4-14 15-7-14 - IN PROGRESS

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

MANHOURS LAST WEEK

CUMULATIVE MANHOURS

SAFETY NOTICES ISSUED

NEAR MISSES REPORTABLE ACCIDENTS

LOST WORK DAYS

OVERALL JOB SITE SAFETY

0 0 0 0 0

Man Power Labour per day Labour per

week Average Labour strength per day

Labours planned for

coming week

18 130 19 15

OPEN ISSUES AND RISK LOG

ISSUE/ RISK DESCRIPTION CATE-GORY

IMPACT MITIGATION PLAN RESP. TARGET DATE

Fire door in canteen near bean marries Civil Low Medium Low As/client response

Category Legend:

ACTIVITIES PLANNED NEXT WEEK SCHEDULED START DATE

SCHEDULED FINISH DATE

• Workstation Chairs 12-7-14

13-7-14

• Canteen furniture 14-7-14 14-7-14

High Medium Low

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

GENERAL ISSUES TH

IQUALITY ISSUES PROPOSED CANTEEN/OFFICE Works:

• Civil Works

• Services Works

• Finishing Works

• Electrical Works

• HVAC Works

• Plumbing Works

• Fire Fighting Works FORCE VENTILATION WORKS:

• AHU/DUCTING WORKS

Desription Test Reports Submitted Test Report Submitted Test Reports Submitted

No Certificates Submitted Test Reports Submitted Test Report Submitted Test Report Submitted

Test Reports Submitted

Remarks

S.NO DESCRIPTION PLANNED DATE RESPONSIBILITY CLOSED DATE

1. Canteen Extra Works PO Issue 15-4-14 Mr.Prashant/ Mr.Zuber (PO ISSUED)

2 Mechanical Ventilation Work PO issue 17-4-14 Mr.Prashant/ Mr.Zuber (PO ISSUED)

3. Medical Room & Guest Room PO Issue 16-4-14 Mr.Prashant/ Mr.Zuber (PO ISSUED)

4. Boundary Wall Work PO Issue 18-4-14 Mr.Prashant/ Mr.Zuber (PO ISSUED)

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

BOUNDARY WALL WORK COMPLETED SOME SNAG POINTS TO BE COMPLETED

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

LANDSCAPING WORKS COMPLETED OPPOSITE TO CANTEEN AREA

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

CARPET LANDSCAPING WORK IS COMPLETED OPPOSITE TO RECEPTION AREA

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

CARPET LANDSCAPING WORK COMPLETED VIEW FROM ENTRANCE CANOPY

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

CARPET LANDSCAPING WORKS COMPLETED OPPOSITE TO ADMIN AREA

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

LANDSCAPING WORKS COMPLETED NEAR NEW OFFICE & CANTEEN AREA

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

CANTEEN FININSHING WORKS COMPLETED EAST SIDE VIEW

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

BEAN MARRIES AND OTHER PENDING WORKS COMPLETED IN CANTEEN AREA

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

HANDWASH & DOOR INSTALLATION WORK COMPLETED IN CANTEEN AREA

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

GENTS TOILET WORKS COMPLETED EXECUTIVE TOILET WORK COMPLETED

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

GENTS TOILET COUNTER WASHBASIN WORK COMPLETED

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

PATHWAY BETWEEN WORKSTATION AND CABINS WORK COMPLETED

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

CABIN WORKSTATION WORK COMPLETED ON EAST SIDE

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

CABIN WORKSTATION INSTALLED ON WEST SIDE

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

OFFICE GALLERY VIEW FROM CANTEEN AND RECEPTION SIDE

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

WORKSTATION WORK COMPLETED EAST SIDE

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

WORKSTATION WORK COMPLETED MIDDLE SIDE

Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)

WORKSTATION WORK COMPLETED WEST SIDE