completion report till 9-7-14
TRANSCRIPT
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
WORK COMPLETION REPORT
TILL 9TH JULY, 2014
M/s AAM India Manufacturing Corporation Pvt Ltd
Table of contents
1. At-a-glance Project key milestones status 2. EHS Issues 3. Construction Progress Update 4. Open Issues and Risk Log 5. Quality Issues 6. General issues closed this week 7. Pictures
Prepared by : Zuber Ahmed
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
AAM PMF COMPLETION REPORT ON 9th JULY, 2014
ITEM DESCRIPTION SCHEDULED
START
SCHEDULED
FINISH
ACTUAL
START
ACTUAL
FINISH
STATUS
CANTEEN WORKS
• PLACING FURNITURE 26-3-14 8-4-14 31-3-14 - IN PROGRESS
• CLEANING 19-3-14 19-3-14 1-4-14 1-4-14 COMPLETED
• HANDOVER 20-3-14 20-3-14 1-4-14 1-4-14 COMPLETED
LANDSCAPING WORKS
• DRESSING, LEVELLING & CLEANING THE DEBRIS
6-4-14 15-4-14 17-4-14 24-5-14 COMPLETED
• Planting Grass, Shrubs, Herbs, etc… 5-5-14 10-5-14 30-4-14 21-6-14 COMPLETED
OUTSIDE BOUNDARY WALL WORKS
• RR MASONARY WORKS 18-4-14 8-5-14 10-4-14 28-5-14 COMPLETED
• FINISHING WORKS 8-5-14 9-5-14 8-5-14 15-6-14 COMPLETED
• HANDOVER 10-5-14 10-5-14 30-6-14 30-6-14 COMPLETED
OFFICE INTERIOR WORKS
• FALSE CEILING WORKS 14-4-14 20-4-14 12-4-14 6-6-14 COMPLETED
• HVAC EQUIPMENT ERECTION 15-4-14 20-4-14 29-5-14 11-6-14 COMPLETED
• PAINTING & POLISHING 22-4-14 28-414 22-4-14 10-6-14 COMPLETED
• FURNITURE INSTALLATION 25-4-14 30-414 8-5-14 30-5-14 COMPLETED
• GENTS TOILET WORKS 15-4-14 30-4-14 16-4-14 7-7-14 COMPLETED
• MEDICAL & STORAGE ROOM 15-5-14 30-5-14 15-7-14 - IN PROGRESS
• HANDING OVER 30-4-14 30-4-14 15-7-14 - IN PROGRESS
•
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
MANHOURS LAST WEEK
CUMULATIVE MANHOURS
SAFETY NOTICES ISSUED
NEAR MISSES REPORTABLE ACCIDENTS
LOST WORK DAYS
OVERALL JOB SITE SAFETY
0 0 0 0 0
Man Power Labour per day Labour per
week Average Labour strength per day
Labours planned for
coming week
18 130 19 15
OPEN ISSUES AND RISK LOG
ISSUE/ RISK DESCRIPTION CATE-GORY
IMPACT MITIGATION PLAN RESP. TARGET DATE
Fire door in canteen near bean marries Civil Low Medium Low As/client response
Category Legend:
ACTIVITIES PLANNED NEXT WEEK SCHEDULED START DATE
SCHEDULED FINISH DATE
• Workstation Chairs 12-7-14
13-7-14
• Canteen furniture 14-7-14 14-7-14
•
•
•
•
•
•
•
High Medium Low
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
GENERAL ISSUES TH
IQUALITY ISSUES PROPOSED CANTEEN/OFFICE Works:
• Civil Works
• Services Works
• Finishing Works
• Electrical Works
• HVAC Works
• Plumbing Works
• Fire Fighting Works FORCE VENTILATION WORKS:
• AHU/DUCTING WORKS
Desription Test Reports Submitted Test Report Submitted Test Reports Submitted
No Certificates Submitted Test Reports Submitted Test Report Submitted Test Report Submitted
Test Reports Submitted
Remarks
S.NO DESCRIPTION PLANNED DATE RESPONSIBILITY CLOSED DATE
1. Canteen Extra Works PO Issue 15-4-14 Mr.Prashant/ Mr.Zuber (PO ISSUED)
2 Mechanical Ventilation Work PO issue 17-4-14 Mr.Prashant/ Mr.Zuber (PO ISSUED)
3. Medical Room & Guest Room PO Issue 16-4-14 Mr.Prashant/ Mr.Zuber (PO ISSUED)
4. Boundary Wall Work PO Issue 18-4-14 Mr.Prashant/ Mr.Zuber (PO ISSUED)
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
BOUNDARY WALL WORK COMPLETED SOME SNAG POINTS TO BE COMPLETED
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
LANDSCAPING WORKS COMPLETED OPPOSITE TO CANTEEN AREA
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
CARPET LANDSCAPING WORK IS COMPLETED OPPOSITE TO RECEPTION AREA
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
CARPET LANDSCAPING WORK COMPLETED VIEW FROM ENTRANCE CANOPY
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
CARPET LANDSCAPING WORKS COMPLETED OPPOSITE TO ADMIN AREA
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
LANDSCAPING WORKS COMPLETED NEAR NEW OFFICE & CANTEEN AREA
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
CANTEEN FININSHING WORKS COMPLETED EAST SIDE VIEW
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
BEAN MARRIES AND OTHER PENDING WORKS COMPLETED IN CANTEEN AREA
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
HANDWASH & DOOR INSTALLATION WORK COMPLETED IN CANTEEN AREA
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
GENTS TOILET WORKS COMPLETED EXECUTIVE TOILET WORK COMPLETED
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
GENTS TOILET COUNTER WASHBASIN WORK COMPLETED
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
PATHWAY BETWEEN WORKSTATION AND CABINS WORK COMPLETED
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
CABIN WORKSTATION WORK COMPLETED ON EAST SIDE
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
CABIN WORKSTATION INSTALLED ON WEST SIDE
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
OFFICE GALLERY VIEW FROM CANTEEN AND RECEPTION SIDE
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
WORKSTATION WORK COMPLETED EAST SIDE
Proposed Canteen, Office & Other Miscellaneous Works of Pune Manufacturing Facility (PMF)
WORKSTATION WORK COMPLETED MIDDLE SIDE