complete this form in accordance with the attachment … · 2021. 4. 2. · unfccc/ccnucc cdm –...
TRANSCRIPT
UNFCCC/CCNUCC
CDM – Executive Board Page 1
Project design document form forCDM project activities
(Version 05.0)
Complete this form in accordance with the Attachment “Instructions for filling out the projectdesign document form for CDM project activities” at the end of this form.
PROJECT DESIGN DOCUMENT (PDD)
Title of the project activityPAMUKÖREN GEOTHERMAL ENERGY POWER
PLANT
Version number of the PDD 01
Completion date of the PDD 01.04.2015
Project participant(s)ÇELİKLER JEOTERMAL ELEKTRİK ÜRETİM
A.Ş.
Host Party TURKEY
Sectoral scope and selectedmethodology(ies), and where
applicable, selected standardizedbaseline(s)
RENEWABLE ENERGIES
ACM0002 “Grid-connected electirict generation fromrenewable sources, version 16”, EB 81.
Estimated amount of annualaverage GHG emission reductions
292837,93 t CO2/yr
UNFCCC/CCNUCC
CDM – Executive Board Page 2
SECTION A. Description of project activity
Purpose and general description of project activity
Pamukören Geothermal Energy Power Plant project (called “the Project” hereinafter) will bedeveloped by ÇELİKLER JEOTERMAL ELEKTRİK ÜRETİM A.Ş. (ÇELİKLERGEOTHERMAL ELECTRICITY PRODUCTION INC.) at Aydın Province, KuyucakDistrict, Pamukören Town. The total installed capacity of the plant is 67,53 MWe. The annualelectricity generation of the plant is 540.240.000 kWh. According to calculations based onelectricity generation estimates, Pamukören GEPP project will result in a CO2 reduction of292837 tons annually, due to use of renewable resources. The construction of the project hadbeen starts on 15.09.2012. The commissioning date is 31.10.2013.
The Pamukören GEPP project had been considered as 45 MWe. The feasilibility studt hadbeen conducted for this capacity. Then, the project had been designed as 61,72 MWe (2 x22,51 MWe + 1 x 16,7 MWe). The electricity production license had been EIA had beenprepared this capacity and the project had the document of “EIA is Positive”. After that, theproduction license was amended as 67,53 MWe (3 x 22,51). For this reason in order to makeup the capacity difference in EIA, a new project description file was prepared for 5,81 MWe.The project description file had the document of “EIA is not required”. Now, two turbines(22,51 x 2 MWe = 45,02 MWe) are operating. The electromechanical equipment installationworks of last turbine (22,51 MWe) are going on. The milestones of the project are given intable below.
Table 1: Milestones of the Project
TASK NAME DATES
Licensing by EMRA 26.05.2011
Feasibility Study Report May, 2012
Contract with EN-ÇEV, the Consultant of CarbonCredits 01.06.2012
EIA Approval15.08.2012
20.03.2014 (capacity addition)
Construction starting date 15.09.2012
Turbine Contract 23.06.2012
Commissioning Date 31.10.2013
Licensing Amendment 04.06.2014
UNFCCC/CCNUCC
CDM – Executive Board Page 3
The ÇELİKLER JEOTERMAL ELEKTRİK ÜRETİM A.Ş. was decided to apply to the GoldStandard to go for the Carbon Credits by means of Pamukören GEPP project and selling themat Voluntary Carbon Market.
Contribution to sustainable development
The renewable energy projects represent a clear contribution to the sustainable developmentsince they substitute the consumption of fossil fuels by using the abundant natural resourcesof the region in an environmentally friendly way.
For the long-lasting of world resources and wellness of human being, a declaration wasendorsed by 189 world leaders at the UN in September 2000, which is a commitment to worktogether to build a safer, more prosperous and equitable world. The Declaration was translatedinto a roadmap setting out eight time-bound and measurable goals to be reached by 2015,known as the Millennium Development Goals (MDGs).1
The Seventh MDG (Millennium Development Goals) proposed by UNDP is about ensuringenvironmental sustainability. In fact, unlike the most of the other MDG targets, its goal isneither quantitative nor time-bounded. Since human well-being is related to environmentalfactors, it is plain that the existence of human being is directly linked to environmentalsustainability. As UNDP emphasize that: “If forests are lost, soils degraded, fisheriesdepleted, waters polluted, or the air unbreathable, and then achievements in poverty reductionmay not be sustainable.”2 Hence, seeking power sources which has minimum adverse effect toenvironment, with the maximum generation capacity, especially by using renewable sourcesis crucial in the 21th century.
In this chapter, the possible effects of Pamukören GEPP project will be assessed in the light ofthe knowledge bases “Tool for the demonstration and assessment of additionality, version07.0.0, EB70, Annex 08”.
As a matter of fact, these types of sustainable projects represent a strategic importance in thedeveloping countries result in generating jobs, reducing resource (petroleum, coal and naturalgas) imports, and it’s well known that they can contribute to bring the welfare associated withthe energy services to the remotes and poorest rural communities.3 Sustainability consideredin three headings as follows.
a) Socio-Economic Sustainability This kind of projects will increase local employment of skilled labor for the
installation, operation and maintenance of equipment. The project promotes the
1 Retrieved from http://content.undp.org/go/cms-service/download/asset?asset_id=28830302 Chapter 6: Ensuring Environmental Sustainability at the National Level, Global Monitoring Report 2008, pg. 1813 Retrieved from http://www.sica.int/busqueda/Noticias.aspx?IDItem=55899&IDCat=3&IdEnt=117&Idm=2&IdmStyle=2
UNFCCC/CCNUCC
CDM – Executive Board Page 4
sustainable economic development which complies with Long-Term DevelopmentStrategy of Turkey.4
Improvement of vital conditions of the population, and poverty reduction byincreasing the employment is achieved in between project continuation.
This kind of projects increase the stability of Turkey’s electricity generating capacityand installed capacity while substantially reducing the import rate of fossil fuel whichis used in coal fired electricity generation.
By means of usin geothermal technology, Turkey will reduce its dependency on adirty and non-renewable commodity such as diesel, coal and natural gas.
b) Environmental Sustainability
Electricity generated from the geothermal power plant directly reducing emissionssuch as CO2, SOx, NOx, suspended particles and other air pollutants associated with thecombustion of fossil fuels (coal, natural gas, etc).
There are no pollutants or any hazardous, toxic or noxious substances are released tothe atmosphere by the geothermal power plant due to the application of the binarycycle technology.
Binary technologies (with non-contact condensing technology) have close to zeroemissions of hydrogen sulfide or mercury to the atmosphere because of reinjection ofall geothermal fluids and gases.5 All fluids will be reinjected to the underground withreinjection wells.
c) Technological Sustainability
By the way of producing electricity and transferring to the national grid, the capacityof generating electricity capacity of Turkey is increased.
This energy self-sufficiency, will introduce a low carbon technology and reduce GHGproduced by fossil fuels.
Technology and know-how transfer are in progress during project installation andoperation.
Location of project activity
Host Party(ies)
Turkey.
Region/State/Province etc.Aegean Region /Aydın Province
4 T.R Prime Ministry State Planning Organization, 2001, www.dpt.gpv.tr5 Environmental, Health and Safety Guidelines for Geothermal Power Generation, IFC, World Bank Group, Page 3.
UNFCCC/CCNUCC
CDM – Executive Board Page 5
City/Town/Community etc.Aydın Province, Pamukören Region, Kuyucak District.
Physical/Geographical location
The project area is located on the 1/25.000 scale M21-a1 and M20-b2 sections Province ofAydın, District of Kuyucak, Pamukoren town which is at a distance of 6-7 km to the center ofKuyucak. Access to the project site is provided through the Denizli-Aydın highway.
The figure below shows the location of the project site.
Figure 1. Map and Satellite View of Project Area
UNFCCC/CCNUCC
CDM – Executive Board Page 6
The coordinates of project are given next tables.
Table 1. J-451 License and Blocked Area Coordinates
Licence AreaBlocked Area
License Coordinates No. J-451License Coordinates No. J-451
POINT NO RIGHT (Y) UP (X) POINT NO RIGHT (Y) UP (X)
1 625900 4199500 1 626000 4196100
2 639300 4200100 2 639200 4196500
3 639200 4196500 3 640700 4193700
4 626000 4196100 4 626550 4190000
Table 2. Plant Area Coordinates
License Coordinates No. J-451
POINT
NORIGHT (Y) UP (X)
1 634333.40 4198012.53
2 634498.00 4198027.98
3 634504.52 4198006.19
4 634513.02 4197995.35
5 634520.48 4197988.49
6 634557.03 4197954.77
7 634566.10 4197955.35
8 634577.16 4197929.47
9 634740.89 4197929.47
10 634749.85 4197886.03
11 634774.22 4197767.94
12 634763.50 4197765.97
13 634755.18 4197763.84
14 634629.88 4197735.42
15 634337.54 4197699.52
16 634364.94 4197782.61
UNFCCC/CCNUCC
CDM – Executive Board Page 7
The Pamukören GPP area to be established within the scope of the project remainsapproximately 500 m southwest of the Pamukören Town. The nearest residential area to theplant area is the Fethiye Neighborhood, located on the east of the plant site, being at adistance of approximately 250 m and approximately 1 km to the Pamukören region. The 3opened drilling wells are located averagely 375 m to the west of the Pamukören Town as the 4units of production and reinjection wells planned to be opened are located approximately 750m to the west and southwest of the Pamukören town.
Technologies and/or measuresApplied approved baseline and monitoring methodology:
ACM0002 “Grid-connected electirict generation from renewable sources, version 16”,EB 81.
Used tools:
Tool for the demonstration and assessment of additionally, version 07.0.0 EB 70. Tool to calculate Project or leakage CO2 emissions from fossil fuel combustion,
version 02, EB 41. Tool to calculate the emission factor for an electricity system, version 04.0” EB 75.
Parties and project participants
Table 3. Parties And Project Participants
Name of Party involved (*)((host) indicates a host party)
Private and/or public entity(ies)project
participants (*)(as applicable)
Kindly indicate if the Partyinvolved wishes to be considered
as project participant(Yes/No)
Turkey ( host country)ÇELİKLER JEOTERMALELEKTRİK ÜRETİM A.Ş.
(private company)No
(*) In accordance with the CDM modalities and procedures, at the time of making the CDM-PDD public at thestage of validation, a Party involved may or may not have provided its approval. At the time of requesting
registration, the approval by the Party(ies) involved is required.
ÇELİKLER JEOTERMAL ELEKTRİK ÜRETİM A.Ş. is the project participant of the project activity.EN-ÇEV Enerji Çevre Yatırımları ve Danışmanlığı Haritacılık İmar İnşaat A.Ş. is the carbonadvisor in the project activity.
Public funding of project activity
The project does not obtain public funding. Please see Annex 2 for relevant document.
UNFCCC/CCNUCC
CDM – Executive Board Page 8
The Project will be financed partly by Private investing company’s own equity and the rest isplanned to be realised by bank loan.
SECTION B. Application of selected approved baseline and monitoring methodology
Reference of methodology
Applied approved baseline and monitoring methodology:
ACM0002 “Grid-connected electirict generation from renewable sources, version 16”,EB 81.
Used tools:
Tool for the demonstration and assessment of additionally, version 07.0.0 EB 70. Tool to calculate Project or leakage CO2 emissions from fossil fuel combustion,
version 02, EB 41. Tool to calculate the emission factor for an electricity system, version 04.0” EB 75.
Applicability of methodology
Methodology “ACM0002 “Grid-connected electricity generation from renewablesources, version 16”, EB 81.” is applicable to the proposed project activity because itfulfils the required criteria:
• The project comprises renewable energy generation by means of geothermal power.• It is a grid-connected electricity generation project.• The installed capacity of the proposed project activity is 67,53 MW which is upper
than 15 MW.
The project activity will not have a capacity extension at any year of the crediting period. Theproject activity may include renewable energy power plant of geothermal power plant.
Project boundaryRegarding the “ACM0002-Grid-connected electricity generation from renewable sources,version 16, EB 81”; “The spatial extent of the project boundary includes the project powerplant/unit and all power plants/units connected physically to the electricity system that theCDM project power plant is connected to.”
The proposed project and the power plants which are connected to the Turkish National Gridare included in the spatial extent of the project boundary.
UNFCCC/CCNUCC
CDM – Executive Board Page 9
Source Gas Included Justification/explanation
Baseline
CO2 emissionsfrom electricitygeneration in
fossil fuel firedpower plants
that aredisplaced dueto the project
activity
CO2 Yes Major Emission Source
CH4 No Minor Emission Source
N2O No Minor Emission Source
ProjectActivity
Fugitiveemissions ofCH4 and CO2
from non-condensable
gases containedin geothermal
steam CO2
CO2 Yes Major Emission Source
CH4 No Minor Emission Source
N2O No Minor Emission Source
CO2 emissionsfrom
combustion offossil fuels for
electricitygeneration
CO2 Yes Major Emission Source
CH4 No Minor Emission Source
N2O No Minor Emission Source
B.1. Establishment and description of baseline scenario>> In respect of large-scale consolidated methodology ACM0002 “Grid Connected ElectricityGeneration from Renewable Sources, version 16”, the baseline scenario is that the electricitydelivered to the grid by the project activity would have otherwise been generated by theoperation of grid-connected power plants and by the addition of new generation sources, asreflected in the combined margin (CM) calculations described in the “Tool to calculate theemission factor for an electricity system”.
Since the proposed project activity is " the installation of a new grid-connected renewablepower plant/unit ", the baseline scenario is defined as the consolidation of electricity delivered
UNFCCC/CCNUCC
CDM – Executive Board Page 10
to the grid by the project activity and electricity generated by the operation of grid-connectedpower plants in Turkey and electricity produced by the new generation sources as reflected inthe combined margin (CM) calculations described in the “Tool to calculate the emissionfactor for an electricity system, ver 04.0”.
Installed electricity generation capacity in Turkey has reached 64,007.5 megawatts (MW) asof 2013. Fossil fuels account for % 60.38 of the total installed capacity and hydro,geothermal, and wind account for the remaining % 39.62.6
Table 4. Breakdown of installed capacity of Turkish grid, 20137
Primary Energy Source MW % of installed capacity, 2013
Thermal 38,648 60.38
Hydro 22,289 34.82
Geothermal 310.8 0.49
Wind 2,759.7 4.31
TOTAL 64,007.5 100
Based on the above can be concluded that geothermal power constitutes the lowest share ofthe total electricity generation capacity of Turkey.
Electricity demand of Turkey has been growing continuously since the last decade due to therapid growth in economy. In 2013, the electricity demand was 248,324 GWh whichcorresponds to an increase of 2.5 % compared to the previous year. The increase or decreaserates for electricity are presented in table below.
Table 5. The energy demand and increase rates between years 2004-20138
Year Energy Demand(GWh) % increase
2004 150018 6,3
2005 160794 7,2
2006 174637 8,6
2007 190000 8,8
6 http://www.teias.gov.tr/T%C3%BCrkiyeElektrik%C4%B0statistikleri/istatistik2013/kguc(1-13)/1.xls7 http://www.teias.gov.tr/T%C3%BCrkiyeElektrik%C4%B0statistikleri/istatistik2013/kguc(1-13)/4.xls8 http://www.teias.gov.tr/YayinRapor/APK/projeksiyon/index.htm, page 6.
UNFCCC/CCNUCC
CDM – Executive Board Page 11
2008 198085 4,3
2009 194079 -2,0
2010 210434 8,4
2011 230306 9,4
2012 242370 5,2
2013 248324 2,5
Even if the energy demand has decreased from 2008 to 2009, it must be noted that it isbecause of the fact that a significant economic crisis has occurred in 2008 and the energyconsumptions decreased accordingly.
Turkey, who intends to sustain its development, has tent to manage its energy supply-demandbalance by the way of developing and constructing high capacity coal and natural gas powerplants. The large natural resource availability, especially the abundance of economicallyaccessible lignite and the governmental agreements on purchasing natural gas and accordinglydeveloping infrastructure works promote the development of thermal power plants. In theabsence of the proposed project activity, the same amount of electricity is required to besupplied by either the current power plants or by increasing the number of thermal powerplants thus increasing GHG emissions.
According to the methodology ACM0002 “Large scale consolidated methodology : gridconnected electricity generation from renewable sources, version 16.0” the baseline is onlyCO2 emissions from electricity generation in fossil fuel fired power plants that are displaceddue to the project activity.
yCMgridyPYy EFEGBE ,,, (Equation 1)
Where:
BE y = Baseline Emissions in year y (tCO2/yr)
EG PJ, y = Quantity of net electricity generation that is produced and fed into the grid asa result of the implementation of the CDM project activity in year y (MWh/yr)
EF grid, CM, y = Combined margin CO2 emission factor for grid connected power generationin year y calculated using the latest version of the “Tool to calculate theemission factor for an electricity system” (t CO2/MWh)
Quantity of net electricity generation (EG PJ, y) is equal to quantity of net electricity generation(EGfacility,y)supplied by the project plant/unit to the grid in year y (MWh/yr) for greenfieldplants.
UNFCCC/CCNUCC
CDM – Executive Board Page 12
Demonstration of additionalityThe project additionally is demonstrated through use of the “Tool for the demonstration andassessment of additionally, version 07.0.0”.
Step 1: Identification of alternatives to the project activity consistent with current laws andregulations
Realistic and credible alternatives to the project activity that can be a part of the baselinescenario are defined through the following steps:
Sub-step 1a: Define alternatives to the project activity
The alternatives to the proposed project activity are listed in table below.
Table 6. Alternatives to the project activity
Alternative A Proposed project developed without the VER revenues
Alternative B The continuation of the current situation (no project activity & no otheralternative undertaken)
Alternative C Construction of a thermal power plant with the same installed capacity or thesame annual power output.
Alternative A is the implementation of the project without carbon revenue. Alternative B isthe continuation of current situation, no project activity. Alternative B does not seem as arealistic option due to expected energy demand increase in Turkey. The next figure shows theenergy demand projection (conservative scenario) between 2014 and 2023 prepared byTEİAS. Based on this fact, the electric generation in Turkey should be increased anyway inaccordance with the expected energy demand. Therefore, no action alternative is not aplausible option and GEPPs should be constructed in order to generate clean energy whereapplicable.
UNFCCC/CCNUCC
CDM – Executive Board Page 13
Figure 2. The energy demand projection between 2014 and 2023 (low demand)9
The last alternative, Alternative C, is considered as a significant alternative to the projectactivity as baseline scenario. Since the share of thermal plants in the installed capacity ofTurkey is considerably high which correspond 38,648 MW of total 64,007.5 MW installedcapacity according to 2013 Turkish electrical statistics taken from TEIAS (Turkish ElectricityTransmission Company).10
Figure 3. The distribution of installed capacity of Turkey by primary energy sources in 200911
Outcome of Step 1a
9 http://www.teias.gov.tr/YayinRapor/APK/projeksiyon/index.htm, page 14.10 http://www.teias.gov.tr/T%C3%BCrkiyeElektrik%C4%B0statistikleri/istatistik2013/kguc(1-13)/4.xls11 Retrieved from http://www.teias.gov.tr/istatistik2009/7.xls
UNFCCC/CCNUCC
CDM – Executive Board Page 14
Three alternatives are considered for the proposed project. However due to the increasingelectricity demand in Turkey, Alternative B, which is the continuation of the current situationis an unrealistic option. Therefore, Alternatives A and C are the two alternatives to beevaluated.
Sub-step 1b: Consistency with mandatory laws and regulations
The following applicable mandatory laws and regulations have been identified:
1. Electricity Market Law [Law Number: 6446 Enactment Date: 30.03.2013]12
2. Law on Utilization of Renewable Energy Resources for the Purpose of GeneratingElectricity Energy [Law Number: 5346 Ratification Date: 10.05.2005 Enactment Date:18.05.2005]13
3. Environment Law [Law Number: 2872 Ratification Date: 09.08.1983 Enactment Date:11.08.1983]14
4. Energy Efficiency Law [Law Number 5627, Enactment Date 02/05/2007] 15
5. Forest Law [Law Number 6831, Enactment Date 31/08/1956]16
All the alternatives to the project outlined in Step 1a above are in compliance with applicablelaws and regulations.
Outcome of Step 1b
Mandatory legislation and regulations for each alternative are taken into account in sub-step1b. Based on the above analysis, the proposed project activity is concluded not to be the onlyalternative amongst the ones considered by the project participants that is in compliance withmandatory regulations.
Step 2: Investment analysis
The investment analysis for Pamukören geothermal Energy Power plant project in this Step 2will be evaluated the following the four sub-steps:
(i) Determine appropriate analysis method;(ii) Apply analysis method;(iii) Calculation and comparison of financial indicators;(iv) Sensitivity analysis.
Sub-step 2a: Determine appropriate analysis method
12
http://www.resmigazete.gov.tr/main.aspx?home=http://www.resmigazete.gov.tr/eskiler/2013/03/20130330.htm&main=http://www.resmigazete.gov.tr/eskiler/2013/03/20130330.htm13 Retrieved from http://www.eie.gov.tr/duyurular/YEK/LawonRenewableEnergyReources.pdf14 Retrieved from http://rega.basbakanlik.gov.tr15 Retrieved from http://www.eie.gov.tr/english/announcements/EV_kanunu/EnVer_kanunu_tercume_revize2707.doc16 Retrieved from http://web.ogm.gov.tr/birimler/merkez/kadastro/Dokumanlar/KD1/Mevzuat/6831%20ORMAN%20KANUNU.pdf
UNFCCC/CCNUCC
CDM – Executive Board Page 15
The “Tool for the demonstration and assessment of additionally, ver 07.0.0”, lists threepossible analysis methods;
Option I. Simple cost analysis; Option II. Investment comparison analysis; and Option III. Benchmark analysis.
Option I cannot be used, since the financial and economic benefits generated by the proposedproject activity.
Between Option II and Option III, benchmark analysis method (Option III) is preferred as theinvestment analysis method for the proposed project.
Sub-step 2b: Option III. Apply benchmark analysis
To select or calculate a benchmark with reliable and valid is very difficult in due to the marketvolatility (government bond rates etc.), its changes over time and project type has its owncharacteristics (supply, demand, price etc.). Institutional capacity is necessary for thesecalculations. In this regard, the recognized and accepted widely the calculations (indicators)of international institutions (WB, IMF, UNCTAD, IFF etc.) can be used as benchmark. Sincethis IRR refers to geothermal plant in the republic of Turkey, the Equity IRR of World Bankcan be used which is 15% for geothermal. 17 This accepted benchmark IRR provides a moreaccurate and conservative view of the investment analysis effort. Eventually, the benchmark(15%) will be applied for comparison with the equity IRR determined in this investmentanalysis of the Pamukören GEPP project.
As is known, there are also benchmarks for other countries in the appendix of “Guidelines onthe assessment of investment analysis, version 05” When it is seen, the highest benchmark is%17 and the lowest benchmark is % 9.5 among the lots of countries for energy industries. Inthis Tool, the benchmark IRR (The expected return on equity) is composed of four elements:(a) a risk free rate of return; (b) an equity risk premium; (c) a risk premium for the hostcountry; and (d) an adjustment factor to reflect the risk of projects in different sectorialscopes. All values are expressed in real terms.
Sub-step 2c: Calculation and comparison of financial indicators
The internal rate of return (IRR) calculation is a convenient technique for Pamukören GEPPproject in benchmark analysis. As it is known, Equity IRR is a percentage figure thatdescribes the yield or return on an investment over a multiyear period. For a given series ofcash flows, the IRR is the discount rate that results in a net present value (NPV) of zero.
17 Retrieved from World bank-Project Appraisal Document on a IBRD Loan and a Proposed Loan from Clean TechnologyFund to TKSB an TB with the Guarantee of Turkey (Report No: 46808-TR, dated May 1, 2009, page 81)
UNFCCC/CCNUCC
CDM – Executive Board Page 16
All the main parameters of project and other relevant financial items used in the equity IRRcalculation is taken from the Feasibility Report of Pamukören GEPP and legal norms.Likewise, some items (corporate tax, tax deduction, tax exemption, etc.) are including for IRRcalculation in line with the suggestion in “Tool for the demonstration and assessment ofadditionality”.
Figure 4. Main parameters used for investments analysis
No Parameters Unit Value1 Installed Capacity MW 67.534 Total electricity generation GWh/year 540.240
Net marketable electricitygeneration
GWh/year 445.754,7
5 Investment cost USD 190,532,0407 VAT USD 20,694,5178 Investment cost + VAT USD 211,226,557
11 Feed-in tariff $ / KWh 0,10512 Annual total revenue USD/ year 46,804,245.513 VAT % 1814 Expected VERs price €/ tCO2-eq 3
The main parameters were gathered at the table above to be used for the cash inflow and cashoutflow of the Project:
(i) The cash outflow and costs (investment costs & operation costs)
Costs can be classified into two categories: Investment costs and operational/maintenancecosts. The total investment cost of the proposed project was determined as 190,532,040USDbased on unit prices. After inclusion of VAT within the scope of investment analysis, the totalinvestment cost of Pamukören GEPP is 211,226,557USD (included VAT) and is itemized asfollows;
Table 7. Total Local Cost and Total Investment Cost of Pamukören Weir and HEPP
USD USD
Cost for twoturbines
(2 x 22,51 MWe)
Cost for threeturbines
(3 x 22,51 MWe)*
Wells 11.700.000,00 17.550.000,00
Transmission 1.990.000,00 2.985.000,00
Automation 3.000.000,00 4.500.000,00
Land and Plant Construction 1.750.000,00 2.625.000,00
Piping and Transportation 1.995.000,00 2.992.500,00
UNFCCC/CCNUCC
CDM – Executive Board Page 17
Source: Pamukören GEPP, Feasibility Study Report
*The Feasibility Study was conducted for 2 x 22,51 MWe turbines. However, the project cost and investmentanalysis have been conducted for 3 x 22,51 MWe turbines. For this reason, the costs have been divided by two
and multiplied by three in order to find correct values.
While it is not considered value add tax in the feasibility report, we included VAT within theinvestment costs to be more realistic and conservative. It is important to note thatelectromechanical equipment cost is exempt from VAT by-law. The VAT ratio is 18% inaccording to the VAT Law (no: 3067, date: 25/10/1984) and applied to investment cost ofunits.
Operating Expenses
The operating expenses can be classified as fixed operating cost and variable operating cost.
Table 8. The fixed and variable operating cost of Pamukören GEPP.
USD USDCost for two turbines
(2 x 22,51 MWe)Cost for three turbines
(3 x 22,51 MWe)*
Operating Expenses 2.440.507,09 3.660.760,63
Maintenance and repair 2.603.207,56 3.904.811,34
State’s Allocation 341.671,00 512.506,50
VARIABLE OPERATING COST 5.385.385,65 8.078.078,47
EMRA-annual license fee 423.387,00 635.080,50
TETC-Transmission System Usage Fee 402.558,00 603.837,00
Consulting and Engineering 1.000.000,00 1.500.000,00
Local Cost 21.435.000,00 32.152.500,00
Machinery and Equipment 50.375.000,00 75.562.500,00
Local Cost 21.435.000,00 32.152.500,00
License Fee 52.211.360,00 78.317.040,00
Erection 3.000.000,00 4.500.000,00
TOTAL INVESTMENT COST 127.021.360,00 190.532.040,00
VAT 13,796,344.8 20,694,517
TOTAL INVESTMENT COST+VAT 140,817,704.8 211,226,557
UNFCCC/CCNUCC
CDM – Executive Board Page 18
TETC-Transmission System Operation Fee 11.768,00 17.652,00
Insurance 200.000,00 300.000,00
Depreciation and amortization 6.977.424,00 10.466.136,00
FIXED OPERATING COST 8.015.137,00 12.022.705,50
TOTAL OPERATING COST 13.400.522,65 20.100.783,97
Source: Pamukören GEPP, Feasibility Study Report
(ii) The cash inflow or income stream
The primary legislation for a reasonable projection of income stream is the “Law onUtilization of Renewable Energy Resources for the Purpose of Generating Electrical Energy(No.5346)”. According to Article 6 of the Law, the price to be applicable to the electricalenergy to be purchased within the scope of Law for each year shall be the Turkish averagewholesale electricity price in the previous year determined by the Energy Market RegulatoryAgency (EMRA). The applicable electricity price is 0,105 $ per kWh.
1 USD = 1.585TL18 and 1 EURO = 2.3150 TL (exchange selling rate).19
Annual generation has been taken as 540.240 GWh (540,240,000 kW). However,94.485.280,82 of electricity is loss and is used for plant internal consumption. Therefore netmarketable electricity generation is 445.754.719,18 kWh.
Correspondingly; the annual income will be 46.804.245,51 USD. It is assumed constantselling price of electricity during the 29 years of operation.
(iii) Earnings before Interest, Taxes, Depreciation (EBITD)
This gross earnings figures are stated in the excel sheet.
(iv) Depreciation
Depreciation related to the project, which has been deducted in estimating EBITD , addedback to net profits in line with the suggestion in “Tool for the demonstration and assessmentof additionality”.
18 Pamukören Feasibility Study Report19 The exchange selling rate on May 2012 was used for conversion to be in line with the feasibility study submission date.
UNFCCC/CCNUCC
CDM – Executive Board Page 19
(v) Corporate Tax Base
Corporate Tax Base = Revenue – Costs – Depreciation – Interest Expenses
(vi) Corporate Tax Amount
Corporate income tax is applied at 22 % rate on the tax amount. The tax amount is defined asthe 22% of the tax base which was the difference of costs and revenues excludingdepreciation. However taxpayers pay provisional tax at the rate of corporate tax, thesepayments are deducted from corporate tax of current period. It is important that when businessprofit (dividend) is distributed company holders as project participants, the income tax islevied on the income of these persons from business activities as well as corporate taxliability. The rates of income tax are progressive. It is not considered this point in investmentanalysis.
(vii) Net Earnings
Net Earnings = Tax Base – Tax Amount
(viii) Deduction of input VAT
Project participant has the right to deduct input VAT of investment cost.
(ix) Repayments of Principal
Repayments of principal are stated in the excel sheet.
(x) Net Cash Flow
Net Cash Flow = Net Earnings + Depreciation + Deduction(Netting) of Input VAT -Instalment payment
(xi) Net present value (NPV), Equity IRR and Project IRR
For a given series of net cash flows (the difference between the present value of cash inflowsand cash outflows), Equity IRR of the Pamukören GEPP Project 11,60% is the discount ratethat results in an NPV of zero (without considering the carbon revenue).
With respect to “Guidelines on the Assessment of Investment Analysis”, version 04; the fairvalue of project activity assets at the end of the assessment period should be included as acash inflow in the final year. Hence, the fair value was calculated in accordance with localaccounting regulations and included as a cash inflow in the final year.
However, as per 4628 numbered Law of Turkish Legislations, at the end of electricityproduction license, the project activity with all units shall be granted to government with nosalvage value. Hence, in reality, the salvage value of project activity assets will be not begiven to investor.
UNFCCC/CCNUCC
CDM – Executive Board Page 20
When we consider to today’s technology, high capital stock will be transferred from Project tothe public contributing to public welfare. Therefore, this salvage value can be seen positiveimpact on community (public utility) in terms of sustainability development matrix.
(xii) Equity IRR, Project IRR, VER income and the Benchmark
As is mentioned above, equity IRR has been calculated as 11,60% without considering thecarbon revenue. When benchmark IRR is taken as 15%, the Project is not financiallyattractive. We consider 3EURO VER Sales Unit Price (conservative prediction) and taxation.
When we include the carbon revenues in the cash flows, equity IRR increases to nearly15,84%. The IRR with VERs rise up than the benchmark of 15%.
In conclusion, the Equity IRR is 11,60 % and turns to 15,84 % by the addition of VERrevenues. Since the benchmark is accepted as 15 %, the calculated IRRs with VER revenueexpress the project is attractive financially.20
Sub-step 2d: Sensitivity analysis
The sensitivity analysis assessed to shows whether the conclusion regarding thefinancial/economic attractiveness is robust to reasonable variations in the critical assumptions.
The parameters are applied as investment cost, operation and maintenance cost, electricityprice and amount of electricity generated which are assessed below.
(i) Investment Cost;
The 10% increase and 10% decrease were applied to investment cost of Equity IRR analysis,respectively. Furthermore, in accordance with the decrease or increase in the cost, the VATamount was decreased or increased. Hence, the distribution of netting of VAT by years shouldbe reconsidered to give the total VAT amount which was decreased or increased.
(ii) Operation and Maintenance Cost;
The 10% increase and 10% decrease were applied to operation and maintenance cost ofEquity IRR analysis for all operational years of project, respectively.
(iii) Electricity Price and Amount of Electricity Generated;
The 10% increase and 10% decrease were applied to income flow of Equity IRR analysis,respectively. The income has two variables; amount of electricity generated and unit price ofelectricity.21 Therefore, income can be a parameter just by the way of variation in these 2variables, which means that the increase in income can be a result of either increase in amount
20 Please follow the excel sheet of IRR analysis.21 Income = electricity generated ( KWh) x unit price of electricity (USD/KWh)
UNFCCC/CCNUCC
CDM – Executive Board Page 21
of electricity generated or increase in unit price of electricity. The decrease in income can be aresult of either decrease in amount of electricity generated or decrease in unit price ofelectricity.
In line with the variation of income, netting of VAT amount should be changed, since theamount of netting of VAT in year y was the 18% of revenue in year y. The consideration ofvariation in netting of VAT amount was applied to the IRR sensitivity analysis (when incomeincrease or decrease 10%).
Table 9. The results of sensitivity analysis to Equity IRR of Pamukören GEPP project
When cost;increases 10% stable decreases 10%
Whenincome;
decreases 10% 7,96% 9,58% 12,41%
stable 9,76% 11,60% 13,55%
increases 10% 11,49% 13,35% 16,47%
It may be seen from the sensitivity analysis that the 29 years Equity IRR value for theproposed project activity is more than the benchmark IRR (15%) for only one condition; ifcost decreases 10% and income increases 10%, then the IRR will be 16,47%. Likewise, thisanalysis has not been considered macro risks (a projection about budget deficits, currentaccount deficits, saving deficits, public and private debt stock etc. of Turkey economy) aswell as micro risks (project, sectorial etc.).
Outcome of Step 2:
The investment and sensitivity analysis shows that the VER revenues will improve the EquityIRR and make the project more attractive for investors. Considering that figures above do notprecisely reflect the investment risk (systematic and unsystematic risks) the role of the carbonincome is significant to enable the project to proceed and for a favourable investment decisiontaken. Based on the analysis and information above, it is concluded that investing in theproject is not the most attractive option considering the alternative investment opportunities.Therefore, Project can be considered as additional to the baseline scenario.
Step 3: Barrier analysis
The barrier analysis step has not been applied for the proposed project.
Step 4: Common practice analysis
This section includes the analysis of the extent to which the proposed project type (e.g.technology or practice) has already diffused in the relevant sector and region.
The following Sub-steps discuss the existing common practice.
UNFCCC/CCNUCC
CDM – Executive Board Page 22
Sub-step 4a- Analyse other activities similar to the proposed project activity
The list of operational geothermal power plants could be seen in next table.
Table 10. The List of Operational Geothermal Power Plant222324
Plant Province
Installed
Capacity Company Phase Scale CDM Technology
AlaşehirGEPP Manisa 45
TÜRKERLERJEOTERMALENERJİARAMA VEÜRETİM
A.Ş
Construction LargeScale
BabadereGEPP
Çanakkale 3
MTN ENERJİELEKTRİK ÜRETİM
SANAYİ VETİCARET ANONİM
ŞİRKETİ
Construction SmallScale
ÇeliklerPamukören GEPP
Aydın67,53
22,51 c
ÇELİKLERJEOTERMAL
ELEKTRİKÜRETİM ANONİM
ŞİRKETİ
PartialConstructio
n
(22,51 inconstruction, 45,02 inoperation)
Large
ScaleListed Binary
ÇeliklerSultanhisar
GEPPAydın 9,9
ÇELİKLERJEOTERMAL
ELEKTRİK ÜRETİMANONİM ŞİRKETİ
Construction SmallScale Binary
Deniz(Maren II
GEPP)Aydın 24
MAREN MARAŞELEKTRİK ÜRETİM
SANAYİ VETİCARET A.Ş.
Operation LargeScale
Registered Binary
Dora-1GEPP Aydın 7.951
MENDERESGEOTHERMAL
ELEKTRİK ÜRETİMANONİM ŞİRKETİ
Operation SmallScale
VCS
ActiveBinary
22 http://lisans.epdk.org.tr/epvys-web/faces/pages/lisans/elektrikUretim/elektrikUretimOzetSorgula.xhtml23 http://geka.org.tr/yukleme/dosya/5f60844e55155eb66280abe69e42aa51.pdf24 http://www.geothermal-energy.org/pdf/IGAstandard/EGC/2013/EGC2013_CUR-32.pdf
UNFCCC/CCNUCC
CDM – Executive Board Page 23
Dora-2GEPP Aydın 9.5
MENDERESGEOTHERMAL
ELEKTRİK ÜRETİMANONİM ŞİRKETİ
Operation SmallScale Issued Binary
Dora-3GEPP Aydın 34
MENDERESGEOTHERMAL
ELEKTRİK ÜRETİMANONİM ŞİRKETİ
Operation LargeScale Listed Binary
Dora-4JES Aydın 17
MENDERESGEOTHERMAL
ELEKTRİK ÜRETİMANONİM ŞİRKETİ
Construction LargeScale Binary
EfelerGEPP Aydın
162,3 GÜRMATELEKTRİK ÜRETİMANONİM ŞİRKETİ
PartialConstruction
(139,8 inconstruction,
22,5 inoperation)
LargeScale Double Flash
EnerjeoKemaliye
GEPPManisa 20
ENERJEOKEMALİYE ENERJİÜRETİM ANONİM
ŞİRKETİ.
Construction LargeScale
GalipHocaGEPP
Aydın 47.4GÜRMAT
ELEKTRİK ÜRETİMANONİM ŞİRKETİ
Operation LargeScale Double Flash
Gök GEPP Denizli 3
İN-ALTI TERMALTURİZM SAĞLIK
TEKSTİL GIDA VETEMİZLİK
MADDELERİSANAYİ VE
TİCARET LİMİTEDŞİRKETİ
ConstructionSmallScale
GümüşköyGEPP Aydın 13,2
GÜMÜŞKÖYJEOTERMAL
ENERJİ ÜRETİMANONİM ŞİRKETİ
Operation SmallScale
Registered Binary
Jeoden Denizli 2,52
JEODEN ELEKTRİKÜRETİM İNŞAAT
SANAYİ VETİCARET ANONİM
ŞİRKETİ
Construction SmallScale Binary
UNFCCC/CCNUCC
CDM – Executive Board Page 24
KarkeyUmurluGEPP
Aydın 12
KARKEYKARADENİZ
ELEKTRİK ÜRETİMANONİM ŞİRKETİ
Construction SmallScale
VCS
Active
Ken KipaşGEPP Aydın 24
KEN KİPAŞELEKTRİK ÜRETİMANONİM ŞİRKETİ
Construction LargeScale
KeremGEPP Aydın 24
MAREN MARAŞELEKTRİK ÜRETİM
SANAYİ VETİCARET A.Ş.
Operation LargeScale Binary
KiperGEPP Aydın 20
KİPER ELEKTİRİKÜRETİM ANONİM
ŞİRKETİConstruction Large
Scale
Kızıldere Denizli 6,85
BEREKETJEOTERMAL
ENERJİ ÜRETİMANONİM ŞİRKETİ
Operation SmallScale Binary
KızıldereGEPP Denizli 15
ZORLU DOĞALELEKTRİK
ÜRETİMİ A.Ş.Operation Small
Scale Flash
KızıldereII GEPP Denizli 80
ZORLU DOĞALELEKTRİK
ÜRETİMİ A.Ş.Operation Large
Scale Flash
MarenGEPP Aydın 44
MAREN MARAŞELEKTRİK ÜRETİM
SANAYİ VETİCARET A.Ş.
Operation LargeScale
Registered Binary
SankoGEPP Manisa 15
SANKO ENERJİSANAYİ VE
TİCARET ANONİMŞİRKETİ
Construction LargeScale
Tuzla Çanakkale 7.5
TUZLAJEOTERMAL
ENERJİ ANONİMŞİRKETİ
Operation SmallScale Issued Binary
Construction
CDM Activities
UNFCCC/CCNUCC
CDM – Executive Board Page 25
Different Technology
Small Scale
As per the guidance in “Tool to for the Demonstration and Assessment of Additionality”,“Other CDM project activities (registered project activities and project activities which havebeen published on the UNFCCC website for global stakeholder consultation as part of thevalidation process) are not to be included in this analysis.”, the CDM projects have not beenincluded in the analysis. The CDM projects are shown with grey colour in the table.
The Pamukören Geothermal Power Plant is designed as binary cycle technology, installed as67,53 MWe (large scale) and in operation phase. The projects that have differenttechnologies, different scales and the projects are in construction phase depart from thePamukören Project. Only Kerem GEPP can be considered as an option similar to the projectactivity.
As it is seen in table above, total geothermal energy power plants’ installed capacity is 738,65MWe. 434.92 MWe is installed capacity of power plants in operation, 333,73 MWe is inconstruction. Total installed capacity of Turkey is 64,007.5 MWe in year 2013. Therefore, theinstalled capacity of geothermal energy power plant is 1.15 % of all energy power plant.
Sub-step 4b: Discuss any similar Options that are occurring
It has been established in sub-step 4a above that there is only one project similar to thePamukören project in Turkey. Hence it complies with all criteria laid out by the “Tool to forthe Demonstration and Assessment of Additionality” and is thus additional.
This in turn shows that the electricity generation from GEPP business is not a commonpractice in Turkey. Therefore Step 4 is satisfied and the proposed project is additional.
Emission reductionB.6.1. Explanation of methodological choicesProject Emissions
The project activity makes use of ACM0002 as the main methodology. According toACM0002 the project emission shall be calculated by using the following equation.
yHPyGPyFFy PEPEPEPE ,,, (Equation 2)
= Project emissions in year y (t CO2e/yr), = Project emissions from fossil fuel consumption in year y (t CO2/yr)
UNFCCC/CCNUCC
CDM – Executive Board Page 26
, = Project emissions from the operation of geothermal power plants due to the release ofnon-condensable gases in year y (t CO2e/yr)
, = Project emissions from water reservoirs of hydro power plants in year y (t CO2e/yr)
1. Project emissions from fossil fuel consumption
For geothermal projects, which also use fossil fuels for electricity generation, CO2 emissionsfrom the combustion of fossil fuels shall be accounted for as project emissions (PEFF,y).
PEFF,y shall be calculated as per the the “Tool to calculate project or leakage CO2 emissionsfrom fossil fuel combustion, ver 02”.
i yiyjiyjFC COEFFCPE ,,,,, (Equation 3)
PEFC,j,y = PEFF,y= Are the CO2 emissions from fossil fuel combustion in process j during theyear y (tCO2/yr);
FCi,j,y = Is the quantity of fuel type i combusted in process j during the year y (mass or volumeunit/yr);
COEFi,y = Is the CO2 emission coefficient of fuel type i in year y (tCO2/mass or volume unit)i = Are the fuel types combusted in process j during the year y
The CO2 emission coefficient COEFi,y is calculated based on net calorific value and CO2emission factor of the fuel type i, as follows:
yiCOyiyi EFNCVCOEF ,,2,, (Equation 4)
COEFi,y = Is the CO2 emission coefficient of fuel type i in year y (tCO2/mass or volume unit)
NCVi,y = Is the weighted average net calorific value of the fuel type i in year y (GJ/mass orvolume unit)
EFCO2,i,y = Is the weighted average CO2 emission factor of fuel type i in year y (tCO2/GJ)
i = Are the fuel types combusted in process j during the year y
2. Project emissions from the operation of geothermal power plants due to the release ofnon-condensable gases
PEGP,y is calculated as follows:
ysteamCHyCHsteamyCOsteamyGP MGWPwwPE ,4,4,,2,, )( (Equation 5)
UNFCCC/CCNUCC
CDM – Executive Board Page 27
, = Project emissions from the operation of geothermal power plants due to the release ofnon-condensable gases in year y (t CO2e/yr)
,2, = Average mass fraction of CO2 in the produced steam in year y (t CO2/t steam)
,4, = Average mass fraction of CH4 in the produced steam in year y (t CH4/t steam)
4 = Global warming potential of CH4 valid for the relevant commitment period (tCO2e/t CH4)
, = Quantity of steam produced in year y (t steam/yr)
3. Project emissions from water reservoirs of hydro power plantsThe project is a geothermal power plant project. Hence, the project emission from waterreservoir of hydro power plants is zero.
Baseline EmissionsBaseline emissions include only CO2 emissions from electricity generation in fossil fuel firedpower plants that are displaced due to the project activity. The methodology assumes that allproject electricity generation above baseline levels would have been generated by existinggrid-connected power plants and the addition of new grid connected power plants. Thebaseline emissions are to be calculated as follows:
yCMgridypjy EFEGBE ,,, (Equation 6)
= Baseline emissions in year y (t CO2/yr), = Quantity of net electricity generation that is produced and fed into the grid as a result
of the implementation of the CDM project activity in year y (MWh/yr),, = Combined margin CO2 emission factor for grid connected power generation in year
y calculated using the latest version of the “Tool to calculate the emission factor for anelectricity system” (t CO2/MWh)
1.Quantity of net electricity generation that is produced and fed into the grid as a resultof the implementation of the CDM project activity in year y (MWh/yr)
The planned project is a new geothermal power plant (greenfield power plant). Therefore,when the EGPJ,y is calculated, the next equation is used.
yfacilityypj EGEG ,, (Equation 7)
UNFCCC/CCNUCC
CDM – Executive Board Page 28
, = Quantity of net electricity generation that is produced and fed into the grid as a resultof the implementation of the CDM project activity in year y (MWh/yr)
, = Quantity of net electricity generation supplied by the project plant/unit to the gridin year y (MWh/yr)
2. Combined margin CO2 emission factor for grid connected power generation in year y
The combined margin CO2 emission factor is calculated using “Tool to calculate the emissionfactor for an electricity system, ver. 04.0”.
The following six steps below are used to determine combined margin (CM) emission factor:
Step 1: Identify the relevant electricity systems;
According to the “Tool to calculate the emission factor for an electricity system, version04.0”, a grid/Project electricity system is defined by the spatial extent of the power plants thatare physically connected through transmission and distribution lines to the project activity(e.g. the renewable power plant location or the consumers where electricity is being saved)and that can be dispatched without significant transmission constraints. In Turkey, only onetransmission system which is national transmission system is defined and only TEİAŞ is inthe charge of all transmission system. Correspondingly, in this project activity the projectelectricity system include the project site and all power plants attached to the InterconnectedTurkish National Grid.
Electricity imports are defined as transfers from connected electricity systems to the projectelectricity system. Hence, determining the operating margin emission factor, 0 tCO2/MWhemission factor has been determined for net electricity imports from the connected electricitysystem.
Step 2: Choose whether to include off-grid power plants in the project electricity system(optional)
For the calculation of the operating margin and build margin emission factor, “Option I: Onlygrid power plants are included in the calculation”, is used.
Step 3: Select a method to determine the operating margin (OM)
The calculation of the operating margin emission factor (EFgrid,OM,y) is based on one of thefollowing methods;
UNFCCC/CCNUCC
CDM – Executive Board Page 29
(a) Simple OM; or(b) Simple adjusted OM; or(c) Dispatch data analysis OM; or(d) Average OM.
Options (b) and (c) are not preferred due to the scarcity of data for Turkey. Option (d) is notpreferred since low-cost/must run resources do not constitute more than 50% of total gridgeneration. Simple OM method will be used in the calculations. Other methods are notapplicable due to lack of data.
Step 4: Calculate the operating margin emission factor according to the selected method
The simple OM emission factor is calculated as the generation-weighted average CO2
emissions per unit net electricity generation (tCO2/MWh) of all generating power plantsserving the system, not including low-cost/must-run power plants/units.
The simple OM may be calculated by following two options;
Option A: Based on the net electricity generation and a CO2 emission factor of each powerunit; or
Option B: Based on the total net electricity generation of all power plants serving the systemand the fuel types and total fuel consumption of the project electricity system.
Option B can only be used if; (1) no necessary data for option (A), (2) only nuclear andrenewable power generation are considered as low-cost/must-run power sources and thequantity of electricity supplied to the grid by these sources is known, (3) off-grid power plantsare not included in the calculation.
For the project in question, Option B is preferred since,
Electricity generation and CO2 data for individual power units are not available. Only renewable power generation are considered as low cost/must run resources. Off-grid power plants are not included in calculations. The fuel consumption of different fuel types data for power plants/ units are available
in the official source, TEIAS.
Under Option B, the simple OM emission factor is calculated based on the net electricitysupplied to the grid by all power plants serving the system, not including low-cost / must runpower plants / units, and based on fuel type(s), and total fuel consumption of the projectelectricity system, and OM simple is determined as follows;
UNFCCC/CCNUCC
CDM – Executive Board Page 30
y
iyiCOyiyi
yOMsimplegrid EG
EFNCVFCEF
)( ,,2,,
,, (Equation 8)
EF grid, OM simple, y: Simple operating margin CO2 emission factor in year y (t CO2/MWh)
FC i,y = Amount of fossil fuel type i consumed in the project electricitysystem in year y (mass or volume unit)
NCV i,y = Net calorific value (energy content) of fossil fuel type i in year y
(GJ / mass or volume unit)
EFCO2, i,y = CO2 emission factor of fossil fuel type i in year y (t CO2/GJ)
EGy = Net electricity generated and delivered to the grid by all powersources serving the system, not including low-cost / must-run powerplants / units, in year y (MWh)
i = All fossil fuel types combusted in power sources in the projectelectricity system in year y
y = the three most recent years for which data is available at the time ofsubmission of the CDM-PDD to the DOE for validation (ex anteoption) on data vintage in step 3.
Step 5: Calculate the build margin (BM) emission factor
In terms of vintage data, the “Tool to Calculate the Emission Factor for an Electricity System,ver. 04.0”, provides two options to be chosen; option 1 and option 2.
Option 1 states that; for the first crediting period, the BM emission factor ex-ante based onthe most recent information available on units already built for sample group m at the time ofCDM-PDD submission to the DOE for validation. For the second crediting period, the BMemission factor should be updated based on the most recent information available on unitsalready built at the time of submission of the request for the renewable of the crediting periodto the DOE. For the third crediting period, the BM emission factor calculated for the secondcrediting period should be used. This option does not require monitoring the emission factorduring the crediting period.
UNFCCC/CCNUCC
CDM – Executive Board Page 31
In this respect, option 1 was chosen to identify the vintage data.
The sample group of power unit m used to calculate the build margin should be determined asper the procedure in the tool.
a) Identify the set of five power units, excluding power units registered as CDM projectactivities, that started to supply electricity to the grid most recently (SET5-units) anddetermine their annual electricity generation (AEGSET-5-units, in MWh);
b) Determine the annual electricity generation of the project electricity system, excludingpower units registered as CDM project activities (AEG total in MWh). Identify the setof power units, excluding power units registered to CDM project starting with powerunits, that started to supply electricity to the grid most recently and that comprise 20%of AEG total (SET≥20%) and their annual electricity generation (AEGSET≥20% in MWh);
c) From SET 5-units and SET≥20% select the set of power units that comprises the largerannual electricity generation (SET sample);
Identify the date when the power units in SET sample started to supply electricity to the grid. Ifnone of the power units in SET sample started to supply electricity to the grid more than 10years ago, then use SET sample to calculate the build margin.
Turkey’s total electricity generation in 2013 is 240,154.00 GWh. The 20% of AEG total wascalculated as 48,030.00 GWh, accordingly.
The selected set of power units (SET≥20%) which was started to supply electricity to the gridmost recently and comprise 20% of AEG total is the capacity addition is selected from year2012 to 2010. Power plants registered as CDM projects were excluded from the set.
The AEGSET≥20% is calculated as 49,155.40 GWh as per the set of power units.
The build margin emissions factor is the generation-weighted average emission factor(tCO2/MWh) of all power units m during the most recent year y for which power generationdata is available, calculated as follows:
mym
mymELym
yBMgrid EG
EFEGEF
,
,,,
,, (Equation 9)
EFgrid, BM, y = Build margin CO2 emission factor in year y (tCO2/MWh)
UNFCCC/CCNUCC
CDM – Executive Board Page 32
EGm, y = Net quantity of electricity generated and delivered to the grid by power unitm in year y (MWh)
EFEL, m, y = CO2 emission factor of power unit m in year y (tCO2/MWh)
m = Power units included in the build margin
y = Most recent historical year for which power generation data is available
The CO2 emission factor of each power unit m (EFEL,m,y)should be determined as per theguidance in Step 4 section 6.4.1 for the simple OM, using Options A1, A2 or A3, using for ythe most recent historical year for which electricity generation data is available, and using form the power units included in the build margin.
Option A2 is preferred because plant specific fuel consumption data is not available forTurkey. The calculation of the CO2 emission factor for each power unit m (EFEL,m,y) is shownbelow.
ym
yimCOmyEL
EFEF
,
,,,2,
6.3
(Equation 10)
Where:
EFEL,m, y = CO2 emission factor of the power unit m in year y (tCO2/MWh)
EFCO2,m,i,y = Average CO2 emission factor of fuel type I used in power unit m in year y(tCO2/GJ)
nm,y = Average net energy conversion efficiency of power unit m in year y(ratio)
y = the relevant year as per the data vintage chosen in Step 3
Step 6: Calculate the combined margin emissions factor
The calculation of the combined margin (CM) emission factor, EFgrid, CM, y , is based on thefollowing methods;
a) Weighted average CMb) Simplified CM
UNFCCC/CCNUCC
CDM – Executive Board Page 33
The weighted average CM method is preferred to calculate.
a) Weighted average CM method:
The combined margin emissions factor is calculated as follows:
BMyBMgridOMyOMgridyCMgrid wEFwEFEF ,,,,,, (Equation 11)
EF grid, CM, y = Combined margin CO2 emission factor in year y (tCO2/MWh)
EF grid, OM, y = Operating margin CO2 emission factor in year y (tCO2/MWh)
EF grid, BM, y = Build margin CO2 emission factor in year y (tCO2/MWh)
wOM = Weighting of the operating margin emission factor (%)
wBM = Weighting of the build margin emission factor (%)
“Tool to calculate the emission factor for an electricity system, ver. 04.0” states that;
The following default values should be used for wOM and wBM:
• Wind and solar power generation project activities: wOM = 0.75 and wBM = 0.25 (owing totheir intermittent and non-dispatchable nature) for the first crediting period and for subsequentcrediting periods;
• All other projects: wOM = 0.5 and wBM = 0.5 for the first crediting period, and wOM = 0.25and wBM = 0.75 for the second and third crediting period, unless otherwise specified in theapproved methodology which refers to this tool.
Emission Reductions (ERy)
Emission reductions are calculated as follows:
PEyBEyERy (Equation 12)
ER y = Emission reductions in year y (t CO2e/y)
BE y = Baseline Emissions in year y (t CO2e/y)
PE y = Project emissions in year y (t CO2e/y)
UNFCCC/CCNUCC
CDM – Executive Board Page 34
B.6.2.Data and parameters fixed ex ante
Data / Parameter EF grid, OM simple, y
Unit t CO2/MWh
Description Simple operating margin CO2 emission factor in year ySource of data Calculated by equation 8Value(s) applied 0.685 by Table 13Choice of data orMeasurementmethods andprocedures
The used data in formula is taken from justified sources as is seen from other tables inpart B.6.2 of this PDD.
Purpose of data EFgrid,CM
Additionalcomment
UNFCCC/CCNUCC
CDM – Executive Board Page 35
Data / Parameter EGyUnit MWhDescription Net electricity generated and delivered to the grid by all power sources serving the
system, excluding low-cost/must-run units/plants, in year ySource of data TEIAS (Turkish Electrical Transmission Company)
Annual development of Turkey’s gross electricity generation-imports-exports anddemand 1975-2013, Annual development of electricity generation-consumption-lossesin Turkey between 1984-2013.http://www.teias.gov.tr/T%C3%BCrkiyeElektrik%C4%B0statistikleri/istatistik2013/uretim%20tuketim(23-47)/34(84-13).xlshttp://www.teias.gov.tr/T%C3%BCrkiyeElektrik%C4%B0statistikleri/istatistik2013/uretim%20tuketim(23-47)/24.xls
Value(s) applied Table 12Choice of data orMeasurementmethods andprocedures
According to ‘‘Turkish Statistics Law and Official Statistics Program’’ TEIAS, TurkishElectricity Transmission Company is the official source for the related data, henceproviding the most up-to-date and accurate information available.
Purpose of data EFEL,m,y
Additionalcomment
Data / Parameter FC i, y
Unit ton/gas 103 m3
Description Amount of fossil fuel consumed in the project electricity system by generation sourcesin year y
Source of data TEIAS (Turkish Electricity Transmission Company)Fuels consumed in thermal power plants in Turkey by the electric utilities for year y
http://www.teias.gov.tr/T%C3%BCrkiyeElektrik%C4%B0statistikleri/istatistik2013/yak%C4%B1t48-53/49.xls
Value(s) applied Table 11Choice of data orMeasurementmethods andprocedures
According to ‘‘Turkish Statistics Law and Official Statistics Program’’ TEIAS, TurkishElectricity Transmission Company is the official source for the related data, henceproviding the most up-to-date and accurate information available.
Purpose of data NCVi,y, EFEL,m,y
Additionalcomment
UNFCCC/CCNUCC
CDM – Executive Board Page 36
Data / Parameter Heat Value
Unit Tcal
Description Amount of heat produced by the consumption of a unit quantity of fuel types consumedin thermal power plants
Source of data TEIAS (Turkish Electricity Transmission Company)
Heating values of fuels consumed in thermal plants in Turkey by the electricity utilities(2006-2013)
http://www.teias.gov.tr/T%C3%BCrkiyeElektrik%C4%B0statistikleri/istatistik2013/yak%C4%B1t48-53/51.xls
Value(s) applied Table 11Choice of data orMeasurementmethods andprocedures
According to ‘‘Turkish Statistics Law and Official Statistics Program’’ TEIAS, TurkishElectricity Transmission Company is the official source for the related data, henceproviding the most up-to-date and accurate information available.
Heat value is divided by FC to determine NCV.( The formula is taken from 2006 IPCCGuidelines for National Greenhouse Gas Inventories, Chapter 1 of Volume 2,Box 1.1)
Purpose of data NCVi,y
Additionalcomment
In order to convert the data from Tcal to GJ; the equations below are used.1Tcal=1000Gcal, 1GJ = 0.238846 Gcal, Density of natural gas is considered to be0.695kg/m3
Data / Parameter NCV i, y
UnitGJ/kg
Description Net calorific value (energy content) of fossil fuel type i in year y
Source of data TEIAS (Turkish Electricity Transmission Company)Fuels consumed in thermal power plants in Turkey by the electric utilities for year y
http://www.teias.gov.tr/T%C3%BCrkiyeElektrik%C4%B0statistikleri/istatistik2013/yak%C4%B1t48-53/49.xls
Heating values of fuels consumed in thermal plants in Turkey by the electricity utilities(2006-2013)
http://www.teias.gov.tr/T%C3%BCrkiyeElektrik%C4%B0statistikleri/istatistik2013/yak%C4%B1t48-53/51.xls
Value(s) applied Table 11Choice of data orMeasurementmethods andprocedures
According to ‘‘Turkish Statistics Law and Official Statistics Program’’ TEIAS, TurkishElectricity Transmission Company is the official source for the related data, henceproviding the most up-to-date and accurate information available.
Purpose of data EFEL,m,y
UNFCCC/CCNUCC
CDM – Executive Board Page 37
Additionalcomment
In order to convert the data source units to the required units; 1ton=1000 kg.
Data / Parameter EF C02,i,y
Unit t CO2/GJ
Description CO2 emission factor of fossil fuel type i in year y
Source of data IPCC default values at the lower limit of the uncertainty at a 95% confidence interval asprovided in Table 1.4 and Annex 1 for sub-bituminous of Chapter 1 of Volume 2(Energy) of the 2006 IPCC Guidelines for National Greenhouse Gas Inventory
https://www.ipcc.ch/meetings/session25/doc4a4b/vol2.pdfValue(s) applied Table 11; Table16Choice of data orMeasurementmethods andprocedures
There is no information on the fuel specific default emission factor in Turkey, hence,IPCC values has been used as referred in the ‘‘Tool to calculate the emission factor foran electricity system, version 04.’’.
Purpose of data EFEL,m,y
Additionalcomment
In order to convert the data source units to the required units; 1ton=1000 kg.
Data / Parameter EF grid, BM, y
Unit tCO2/MWhDescription Build margin CO2 emission factor in year ySource of data Calculated by equation 9 at Table 17Value(s) applied 0.398Choice of data orMeasurementmethods andprocedures
Calculated ex-ante and comprised capacity addition of power plants between years2012-2010 according to the “Tool to calculate emission factor for an electricity system,version 04.0”
Purpose of data EFgrid, CMAdditionalcomment
Data / Parameter EF EL, m, y
Unit tCO2e/MWhDescription CO2 emission factor of power unit m in year y
Source of data Calculated by equation 10Value(s) applied Table 16Choice of data orMeasurementmethods andprocedures
Calculated ex-ante according to the “Tool to calculate emission factor for an electricitysystem” version 04.0”
Purpose of data EF grid, BM, y
UNFCCC/CCNUCC
CDM – Executive Board Page 38
Additionalcomment
Data / Parameter η m, y
Unit -Description Average net energy conversion efficiency of power unit m in year ySource of data Tool to calculate the emission factor for an electricity system, ver. 04.0, Annex 1 (new
units after 2000)Value(s) applied Table 16Choice of data orMeasurementmethods andprocedures
Since there is no current efficiency values of power units in Turkey, the efficiencyvalues o are retrieved from Tool, ver. 04.0, Annex 1.
Purpose of data EF EL, m, y
Additionalcomment
Data / Parameter EG m, y
Unit MWhDescription Net quantity of electricity generated and delivered to the grid by power unit m, in year y
Source of data TEIAS (Turkish Electrical Transmission Company)
Annual development of Turkey’s gross electricity generation of primary energy sourcesbetween 2006-2013
http://www.teias.gov.tr/T%C3%BCrkiyeElektrik%C4%B0statistikleri/istatistik2013/uretim%20tuketim(23-47)/37(06-13).xls
Value(s) applied Table 17Choice of data orMeasurementmethods andprocedures
According to ‘‘Turkish Statistics Law and Official Statistics Program’’ TEIAS, TurkishElectricity Transmission Company is the official source for the related data, henceproviding the most up-to-date and accurate information available.
Purpose of data EF grid, BM, y
Additionalcomment
In order to convert the data from GWh to MWh GJ; the equation below is used.1GWh=1000 MWh
Data / Parameter EF grid, CM, y
Unit tCO2e/MWhDescription Combined margin CO2 emission factor in year y
Source of data Calculated data applied to the equation 11Value(s) applied 0.542
UNFCCC/CCNUCC
CDM – Executive Board Page 39
Choice of data orMeasurementmethods andprocedures
Calculated ex-ante according to the “Tool to calculate emission factor for an electricitysystem, version 04.0”
Purpose of dataAdditionalcomment
B.6.3.Ex ante calculation of emission reductionsFor the purpose of calculation of emission reductions, the following steps have to be applied:Project Emissions
1. Project emissions from fossil fuel consumption
i
yiyji COEFFCPE ,,, (Equation 13)
yiCOyiyi EFNCVCOEF ,,2,, (Equation 14)
2. Project emissions from the operation of geothermal power plants due to the release ofnon-condensable gases
ysteamCHCHsteamyCOsteamyGP MGWPwwPE ,44,,2,, )( (Equation 15)
Baseline Emissions1.Quantity of net electricity generation that is produced and fed into the grid as a resultof the implementation of the CDM project activity in year y (MWh/yr)
yCMgridypjy EFEGBE ,,, (Equation 16)
facilityypj EGEG , (Equation 17)
2. Combined margin CO2 emission factor for grid connected power generation in year y
The operating margin emission factor
For the calculation of the Simple OM, the amounts of fuel consumption (FCi, y) values forrelevant years are given in table below for year 2012.
UNFCCC/CCNUCC
CDM – Executive Board Page 40
Table 11. Heat Values, FC, NCV and EFCO2 values of each fuel source in 2012
Fuel Type FC (tones) Heat Value (MJ) NCV (MJ/kg)EFCO2
(kg/TJ = tones/ GJ)
Hard Coal+ImportedCoal+Asphaltite 12258462,00 298194320152,00 24,33 92800,00
Lignite 55742463,00 391566493392,00 7,02 90900,00
Fuel Oil 564796 23534012576,00 41,67 75500,00
Diesel Oil 176379 7881170680,00 44,68 72600,00
LPG 0 0,00 0,00 61600,00
Naphta 0 0,00 0,00 69300,00
Natural Gas 23090121 852558500448,00 36,92 54300,00
The values of the other years’can be found in Annex 3 in a tabular form.
In order to calculate the OM, the net electricity generated and delivered to the grid by allsources excluding the low-cost/must run resources is required. However, net generationnational data is only available for total of power sources. Due to this fact, the internalconsumption ratio is used to identify the net electricity generation by thermal sources. Thedifference of low-cost/must-run generation and supplied to grid amount is the generation bythermal sources. The internal consumption of thermal plants is determined by means of ratio.The thermal generation excluding internal consumption gives the net generation excludinglow-cost/must-run as is followed by next table. After addition of import electricity, the EGyis determined.
Table 12. Net electricity generated and delivered to the grid by all power sources serving the system, notincluding low-cost / must-run power plants / units, in year y (GWh)
ElectricityGeneration
(GWh)
Suppliedto grid
Low-cost/
must -run
ThermalInternal
consumption (%)
Internalconsumption
of thermalNet generation Import EG y (Wh)
2010 204189,9 55380,10 155827,6 3,86 6021,57 149806,03 1143,8 150949827,21
2011 222113,5 57756,80 171638,3 5,16 8856,99 162781,31 4555,8 167337105,18
2012 233534,0 64625,10 174871,7 4,92 8608,26 166263,44 5826,7 172090143,41
UNFCCC/CCNUCC
CDM – Executive Board Page 41
Table 13. Electricity Weighted EFgrid, OMsimple, y (tCO2/MWh)
2010 2011 2012
EF grid, OM simple, y, i (tCO2/MWh)
Hard Coal+ImportedCoal+Asphaltite 0,11 0,13 0,16
Lignite 0,31 0,24 0,21
Fuel Oil 0,02 0,01 0,01
Diesel Oil 0,00 0,00 0,00
LPG 0,00 0,00 0,00
Naphta 0,00 0,00 0,00
Natural Gas 0,31 0,27 0,27
Total 0,75 0,66 0,65
3-year generationweighted average
(tCO2/MWh)0.685
The build margin (BM) emission factor
The build margin emissions factor is the generation-weighted average emission factor(tCO2/MWh) of all power units m during the most recent year y for which power generationdata is available, calculated as equation 9.
In order to use equation 9, it is required to know EFEL,m,y.
EFEL,m,y is determined according to equation 10. In this process, average net energyconversion efficiency and other required datas are given in next tables.
Table 14. Average net energy conversion efficiency by energy sources (%)
Average Net Energy Conversion Efficiency by Energy Sources (%)
Hard Coal+ImportedCoal+Asphaltite Lignite Fuel-oil Diesel-oil LPG Naphtha Natural Gas
0.390 0.390 0.46 0.46 0.46 0.46 0.600
UNFCCC/CCNUCC
CDM – Executive Board Page 42
Table 15. Average CO2 emission factor by fuel types (tCO2/Tj)
EF CO2 (t CO2/ GJ )
Hard Coal+ImportedCoal+Asphaltite Lignite Fuel-oil Diesel-oil LPG Naphtha Natural Gas
0,0928 0,0909 0,0755 0,0726 0,0616 0,0693 0,0543
Table 16. EFEL, m, y Calculation
EF CO2
(tCO2/Gj)
η
GenerationEfficiency
(%)
EFEL,m,y
(tCO2/MWh)Fuel Type
Hard Coal+ImportedCoal+Asphaltite 0,0928 0,390 0,8566
Lignite 0,0909 0,390 0,8391
Fuel Oil 0,0755 0,460 0,5909
Diesel Oil 0,0726 0,460 0,5682
LPG 0,0616 0,460 0,4821
Naphta 0,0693 0,460 0,5423
Natural Gas 0,0543 0,600 0,3258
The multiplication of emission factor and electricity generation of capacity addition by sourceis the amount of emission by source which is divided by total capacity addition between year2012- 2010 which comprises 20% of total generation, excluding projects registered to CDM,gives the build margin CO2 emission factor (see equ. 9). Next table shows the data applied.
Table 17. BM calculation by capacity addition
UNFCCC/CCNUCC
CDM – Executive Board Page 43
Fuel Type
Electricity generationCapacity addition
(GWh)
EF,EL,m,y(tCO2/MWh)
Emission bysource
IMPORTEDCOAL+ASPHALTITE 13052,77 0,9354 3,420.748
LIGNITE 0
Fuel-oil 1289,95 0,7744 975.815
Natural Gas 23520,44 0,4250 6,692.439
Wind 751,40 0 0
Geothermal 532,00 0 0
Hydro 9455,21 0 0
Waste 553,63 0 0
Total 49155,40 19606,35
EF grid, BM, y = 19606,35 / 49155,40 = 0.398 tCO2/MWh
The combined margin (CM) emission factor
“Tool to calculate the emission factor for an electricity system, ver. 04.0” states that;
The following default values should be used for wOM and wBM:
• Wind and solar power generation project activities: wOM = 0.75 and wBM = 0.25 (owing totheir intermittent and non-dispatchable nature) for the first crediting period and for subsequentcrediting periods;
• All other projects: wOM = 0.5 and wBM = 0.5 for the first crediting period, and wOM = 0.25and wBM = 0.75 for the second and third crediting period, unless otherwise specified in theapproved methodology which refers to this tool.
Since the proposed project is GEPP, the weighs for the operating margin and build marginemission factors are 0.50 and 0.50 respectively. Therefore;
EF grid, CM = (0.685 x 0. 50) + (0.398 x 0. 50) = 0. 542 tCO2/ MWh
Project Emissions
UNFCCC/CCNUCC
CDM – Executive Board Page 44
1. Project emissions from fossil fuel consumption
For geothermal projects, which also use fossil fuels for electricity generation, CO2 emissionsfrom the combustion of fossil fuels shall be accounted for as project emissions (PEFF,y).
Emissions from diesel engines have not been considered in ex-ante GHG emission reductioncalculations as it is envisaged that the diesel engine shall be used only in emergencysituations. Therefore;
PEFF,y = 0 t CO2e/yr
2. Emissions from the operation of geothermal power plants due to the release of non-condensable gases
The main assumptions for this solution are that the average NCG content is in the range of1,5% +/- 0.125 and all non-condensable gases are CO2.
Wsteam,CO2,y= 28.7 % NCG of total steam (1,5 % of total geothermal resource)
Wsteam,CH4,y= 0%
GWPCH4=21 t CO2e/t CH4
Msteam,y=1,220,800 t steam/yr
PEGP,y =350,369.6 t CO2/yr
3. Project emissions from water reservoirs of hydro power plantsThe project is a geothermal power plant project. Hence, the project emission from waterreservoir of hydro power plants is zero.
, =0.PEy = 350,369.6 t CO2/yr
However, non-condensable gases resulting from the operation (350,369.6 t CO2/yr) will becaptured and carried out of the project boundary with pipelines to be used as industrial gas inproduction. Therefore; project emission will be zero.Emission Reductions (ERy)
The emission reduction is:
25 Pamukören GEPP Feasibility Study, Page 7.
UNFCCC/CCNUCC
CDM – Executive Board Page 45
(540240 MWh/y x 0. 542 t CO2e/MWh) – 0 = 292837.93 t CO2e/yr
B.6.4.Summary of ex ante estimates of emission reductionsBased on the calculations in section B.6.3, the resulting emission reductions (in tCO2e) for thewhole project activity for the years 2013-2020 is show in table below:
Table 18. Summary of the ex-ante estimation of emission reductions
Year Baseline emissions(t CO2e)
Project emissions(t CO2e)
Emissionreductions(t CO2e)
31.10.2013 –31.12.2013
73,209.5 0 73,209.5
2014 292,837.93 0 292,837.93
2015 292,837.93 0 292,837.93
2016 292,837.93 0 292,837.93
2017 292,837.93 0 292,837.93
2018 292,837.93 0 292,837.93
2019 292,837.93 0 292,837.93
01.01.2020 –31.10.2020
219,628.4 0 219,628.4
Total 2,049,865.5 0 2,049,865.5
Total number ofcrediting years
7 years
Annual averageover the
crediting period
292,837.93 0 292,837.93
UNFCCC/CCNUCC
CDM – Executive Board Page 46
Monitoring plan
B.1.1. Data and parameters to be monitored
Data / Parameter Msteam,y
Unit t steam/yrDescription Quantity of steam produced in year ySource of data Project Developer – main inlet steam flow-meterValue(s) applied 1,220,800 ton of steam / year as referred to the Feasibility Study page 7Measurement methodsand procedures
The steam quantity discharged from the geothermal wells should bemeasured with a flow meter (or other equipment with at least the sameaccuracy). Pressure and temperature upstream of the venture meter ismeasured using the same flow meter to define the steam properties. Themeasurement results will be summarised transparently in regularproduction reports.
Monitoring frequency Daily continuous measurementQA/QC procedures Meters will be calibrated according to the manufacturer standard. Period of
calibration: every yearPurpose of data Project emission calculationAdditional comment
Data / Parameter wsteam,CO2,y
Unit tCO2/t steamDescription Average mass fraction of carbon dioxide in the produced steam in year ySource of data The NCG data is taken from sampling as prescribed in the methodologyValue(s) applied 0.287 or 28 % of steam (or 1,5 % of total geothermal reservoir
liquid+steam)Measurement methodsand procedures
Non-condensable gases sampling should be carried out every year in thesteam field-power plant interface using ASTM Standard Practice E1675for Sampling 2-Phase Geothermal Fluid for Purposes of Chemical Analysis(as applicable to sampling single phase steam only) by a third independentparty or internal laboratory. The CO2 sampling and analysis procedureconsists of collecting non-condensable gases samples from the main steamline with glass flasks.
Monitoring frequency Every yearQA/QC procedures PGE Laboratory QA / QC ProcedurePurpose of data Project emission calculationAdditional comment
Data / Parameter EGfacility,y
UNFCCC/CCNUCC
CDM – Executive Board Page 47
Unit MWh/yrDescription Quantity of net electricity generation supplied by the project plant/unit to
the grid in year ySource of data Project Developer – revenue meter (electricity sales)Value(s) applied Annual production : 540,240 MWh/yr
Net production after internal consumption and loss: 445,754.7 MWh/yrMeasurement methodsand procedures
Electricity produced will be measured by a watthour meter (connected to adigital control system and recorded continuously), which can measure bothpower delivered to the grid and received from the grid. Net electricitygeneration will be calculated according to internal consumption and loss.In the case of main revenue meter failure, a cross-check meter will be usedas a back-up meter to measure both power delivered to the grid andreceived from the grid.
Monitoring frequency Continuous basis with monthly reportsQA/QC procedures The QA/QC will be conducted through cross checking with electricity
sales receipts. Meters will be calibrated according to the StandardOperation Procedures (SOPs) signed between PGE and PLN. The QA/QCwill also be applied to both revenue and back-up meters. Period ofcalibration: every year, based on PPA signed between PGE and PLN.
Purpose of data Baseline emission calculationAdditional comment Standard Operation Procedures (SOPs) or other documents, which replace
the SOPs signed between PGE and PLN.
UNFCCC/CCNUCC
CDM – Executive Board Page 48
B.7.2.Sampling planAll monitoring procedures and requirements of the proposed project activity will be inaccordance with the methodologies ACM0002 “Grid-connected electirict generation fromrenewable sources, version 16”, EB 81.
The project developer has planned and will implement monitoring procedures and measureswith regard to the monitoring methodology chosen for this project activity, guaranteeing thatemission reductions are calculated in an accurate and conservative manner. The projectdeveloper will designate a person in charge for monitoring and recording of all the requiredinformation and documentation related with the GHG emissions covered in this PDD. Thedesignated person in charge will be directly under the control of the Managing Director of thecompany. He will collect, record and store all the information for further archieval orverification. Detailed responsibilities and authorities for project management, monitoringprocedures and QA/QC procedures would be drawn up for the purpose and put in place. Thecollected information will be stored in the form of raw data in log books developed especiallyfor the purpose of monitoring and recording data related to VER GS protocols.
These records will form part of the registered monitoring protocol for the use by verificationcompanies. All the parameters monitored under the monitoring plan will be kept for a periodof 2 years after the end of the crediting period or the last issuance of GS VERs, whicheveroccurs later.
B.7.3.Other elements of monitoring plan
Operating Manager: Overall responsibilities of compliance with VER monitoring plan andoperation of plant.
Operator-Technician: Responsible for keeping data to day running of plant, recording,monitoring of relevant data and periodical reporting. Staff will responsible for day to dayoperation and maintenance of the plant and equipments. All staff will be trained and will havecertificate for working with high voltage equipments.
Accounting and Chancellery: Responsible for keeping data about power sales, invoicing andpurchasing.
EN-ÇEV (The Consultant): Responsible for emission reduction calculations, preparingmonitoring report and periodical verification process.
The potential sustainable development benefits of Pamukören GEPP will be monitored as pereffected indicators of sustainable development matrix. Those indicators are either crucial foran overall positive impact on sustainable development or particularly sensitive to changes inthe framework conditions.
UNFCCC/CCNUCC
CDM – Executive Board Page 49
B.7.4.Date of completion of application of methodology and standardized baseline andcontact information of responsible persons/ entitiesDate of completing the final draft of this baseline section: 01.04.2015
Name of entity determining the baseline:
EN-ÇEV Energy Environmental Investments Consultancy Inc.
EN-ÇEV which is the carbon consultant of Pamukören GEPP project is not a projectparticipant.
Address: Mahatma Gandi Caddesi, No: 92/2-3-4-6-7 06680 G.O.P – Ankara/ TURKEY
Tel: +90 312 447 26 22
Fax: +90 312 446 38 10
Contact Person: Pelin ZENGİN, Emrah ÖZTÜRK
E-mail: [email protected], [email protected]
UNFCCC/CCNUCC
CDM – Executive Board Page 50
SECTION C. Duration and crediting period
C.1. Duration of project activity
C.1.1. Start date of project activity
29.03.2011; the preparing date of Project Description File of drilling wells (AP-4, AP-5, AP-6, AP-8)
C.1.2. Expected operational lifetime of project activity
29 years
C.2. Crediting period of project activity
C.2.1. Type of crediting period
Renewable, first crediting period
C.2.2. Start date of crediting period
31.10.2013
C.2.3. Length of crediting period
7 years
UNFCCC/CCNUCC
CDM – Executive Board Page 51
SECTION D. Environmental impacts
D.1. Analysis of environmental impactsThe project will contribute to improve the environmental situation in the region and in thecountry. Avoiding fossil fuel-based electricity will enhance the air quality and help to reducethe adverse affects on the climate. Renewable technologies and geothermal power basedelectricity will be introduced and sustainable development will be promoted. The projectactivity itself will not have any significant negative impacts on humans, plants, animal lifeand biodiversity.
In Turkey, it is mandatory to assess projects and construction activities such as power plants,factories, mining projects and large buildings in terms of physicochemical aspects, ecology,socio-economy, socio-culture and public health. This assessment called Environmental ImpactAssessment Report (or Project Description File for small scale project). If Ministry ofEnvironment and Forestry decides that the project does not have major impacts or degradableimpacts, they give the document of “EIA is Positive” for large scaled projects.
If the projects is small scale; Project Description File is prepared. If Ministry of Environmentand Forestry decides that Project Description File is not satisfying, the further one, called EIA(Environmental Impact assessment), must be prepared. T
The Pamukören GEPP project had been considered as 45 MWe. The feasilibility studt hadbeen conducted for this capacity. Then, the project had been designed as 61,72 MWe (2 x22,51 MWe + 1 x 16,7 MWe). The electricity production license had been EIA had beenprepared this capacity and the project had the document of “EIA is Positive”. After that, theproduction license was amended as 67,53 MWe (3 x 22,51). For this reason in order to makeup the capacity difference in EIA, a new project description file was prepared for 5,81 MWe.The project description file had the document of “EIA is not required”. Now, two turbines(22,51 x 2 MWe = 45,02 MWe) are operating.
D.2. Environmental impact assessment
Air quality:
Non-condensable gases resulting from theoperation (350,369.6 t CO2/yr) will be capturedand carried out of the project boundary withpipelines to be used as industrial gas inproduction. Therefore; project emission will bezero.
Water quality and quantity The geothermal fluid will be re-injected into thereinjection wells.
Soil condition The geothermal fluid will be re-injected into thereinjection wells.
Other pollutantsThe noise level relevant to the project remainsunder the limit value 70 dBA at a distance fromthe settlements.
UNFCCC/CCNUCC
CDM – Executive Board Page 52
Further, the energy generation building in wheregenerators will be located, designed and coveredwith sound/noise isolation material.
Waste oil and solid waste will be handledaccording to the national regulations.
Biodiversity
During the excavation works which shall becarried out under the Project, vegetal soil shall bescraped off at the site. Such vegetal soil to bescraped off shall be used in landscaping worksaround the activity units.
Quality of employment
Staff will be trained on health and safety.Furthermore, all Health and Safety measurementswill be applied according to the “Legislation onWorkers Health and Work Safety”.
UNFCCC/CCNUCC
CDM – Executive Board Page 53
SECTION E. Local stakeholder consultation
E.1. Solicitation of comments from local stakeholders
The Deputies of Aydın in the Grand National Assembly of Turkey has to be invited since thepeople who live in the project area are being presented by Deputies. The Mayors ofPamukören and Kuyucak Municipalities and the Governor of Aydın Governorate were alsoinvited since the municipality personnel are directly related to all of the activitiesimplemented within the borders of the municipality and province. These are governmentalauthorities and responsible of where they are in charge. The regional NGOs and the localNGO (TEMA) were invited to receive their comments and their opinions regarding theproject. Another local NGO is the Pamukören Solidarity Foundation of Education andCulture. By the way of a phone call, it was identified that the headman of foundation is theMayor of Pamukören Municipality. The Mayor states that, it was not necessary to sendanother letter, since he received the invitation sent to the Municipality. Since there is not aDNA in the host country Turkey, the invitation was not performed.
Invitation methods are detailed below.
1. The following invitation letter was sent out in Turkish via telefax to the above mentionedstakeholders:
Dear Sir/Madam,
We request you to participate in the Local Stakeholder Consultation Meeting of “PamukörenGeothermal Energy Power Plant” planned to be constructed in Aydın Province, KuyucakDistrict, Pamukören Town, with the capacity of 61.72 MWe, by Çelikler Jeotermal ElektrikÜretim A.Ş. The Local Stakeholder Consultation Meeting aims to give out information aboutthe geothermal energy power plant project, its environmental and socioeconomic impacts,and its significance in Gold Standard Organization Platform due to the leading reduction incarbon emissions. The meeting will be held on 17 July 2012 at 11.00 pm at the WediingSaloon of Pamukören Municipality, Pamukören, Kuyucak/Aydın. Your participation will be apleasure for us.
Özge Şahin
2.Newspaper Advertisement:
The English version is as follows:
We have the pleasure of inviting you to participate in the Public Stakeholder ConsultationMeeting of the Pamukören Geothermal Energy Power Plant Project that is planned to beconstructed in Province of Aydın, Kuyucak District, Pamukören Town. The aim the of themeeting is to obtain feedback and provide information about the project and its significancein Gold Standard Organization Platform due to leading reduction in carbon emissions.
UNFCCC/CCNUCC
CDM – Executive Board Page 54
Location: Pamukören Wedding Hall, Pamukören , Kuyucak/AydınDate: 17.07.2012Time: 11.00Project Proponent: EN-ÇEV Ltd. Şti.Project Owner: Çelikler Jeotermal Elektrik Üretim A.Ş.
3. Written Notice
The written notice were attached to the Pamukören post office, Cuma Yeri coffee house,Nokta internet cafe. Furthermore, the written notices were attached to the Yöre VillageMukhtar’s Coffee House and Yöre Village Orta Coffee House.
The written notice in English;NOTICE
An information meeting will be held on 17/07/2012, Tuesday regarding the PamukörenGeothermal Energy Project.
The meeting agenda is as follows;
- Opening of the meeting- Explanation of the project
- Discussion of continuous input /grievance mechanism- Questions for clarification about the project
- Blind SD exercise- Discussion on monitoring SD
- Closure of the meeting
Your participation will be a pleasure for us.
Location: Pamukören Wedding Hall, Pamukören , Kuyucak/AydınDate: 17.07.2012,TuesdayTime: 11.00Organizer of the meeting: The consultant EN-ÇEV Ltd. Şti. on behalf of Çelikler JeotermalElektrik Üretim A.Ş.
After sending letters to stakeholders at the invitation tracking table, telephone calls were doneto confirm receipt of invitation letters. The feedbacks on participating the meeting or not wereachieved by this phone calls.
The representatives of REC and WFF stated that, they will not attend.
UNFCCC/CCNUCC
CDM – Executive Board Page 55
Information sharing concerning the project, local area, community and culture are aimedduring the LSC.
E.2. Summary of comments receivedThe stakeholder meeting was held on 17.07.2012, 11.00 pm at Aydın Province, KuyucakDistrict, Pamukören Wedding Hall. At the meeting besides project developers and localpeople, there were representatives of local authorities. The comments are given below;
Selection of local personnel in the closest vicinity of Project area Effects of olive and apricot trees Benefit of this Project on people Construction of other gains such as hotels by company instead of power plant Job opportunities Impact of water vapour
E.3. Report on consideration of comments received
No major concerns were raised during the entire initial stakeholder consultation process.During the consultation, the concerns of stakeholders (unemployment, pollution, jobopportunity, etc.) have been taken into consideration all the way. The information below aregiven to the local stakeholders.
“There are two types of cooling systems; "water cooling tower and condenser" which havewater consumption through evaporation and result in water vapour and PM10 emission andthe other one is "dry air cooled condensers" which do not have water consumption and nowater vapour emission. The dry air cooled condensers are the state of art technology and tobe used in Pamukören GPP directly to avoid water consumption and water vapour emission.Information regarding dry air cooled condenser to be used will be distributed during SFR toeliminate concerns of locals. Furthermore, the non condensable gases will be collected fromthe outlet and sold to relevant firms/buyers to avoid NCG emissions.
The only negative impacts of a GPP are NGC emissions and water consumption and resultedwater vapour formation. By above mentioned design selections (air cooled condenser andrecycling of emitted NCG), those negative impacts will completely hindered. The state of arttechnology has been preferred to precisely avoid/minimize the negative impacts ofPamukören GPP both to vegetation and water resources.
Regarding the respondents’ comments on lack of information; During the LSC meeting, thenon-technical summary was distributed to all participants, due to the technical knowledge ofsome of the participants, the technical details of the proposed project were also explained.Even though, the Pamukören GPP Project Manager Yüksel Çakır was answered all questions
UNFCCC/CCNUCC
CDM – Executive Board Page 56
in detail, those respondents could not be completely satisfied. The PP and PDs explanationsregarding the minimized impact of GPP on the vegetation, agricultural activities etc. [by theway of air conditioned cooling system (no water vapor release),complete reinjection ofgeothermal fluid, and complete recycling of non-condensable gases, no emissions due tofiring of fluid likewise conventional power plants], took place during the LSC meeting.
During the SFR, the EIA report and a summary of the subjects related to the (minimized)impacts of the Pamukören GPP to vegetation and agricultural activities supported with somereferences will be distributed to local and other invitees of SFR.”
UNFCCC/CCNUCC
CDM – Executive Board Page 57
SECTION F. Approval and authorization
The authorization documents are given in Annex.
UNFCCC/CCNUCC
CDM – Executive Board Page 58
Annex-1
ODA DECLARATION
UNFCCC/CCNUCC
CDM – Executive Board Page 59
UNFCCC/CCNUCC
CDM – Executive Board Page 60
Annex-2
BASELINE INFORMATION
2012
COMPANY INSTALLEDPOWER (MW) TYPE ELEC. GENERATION
ACARSOY TERMİK KOM.ÇEV.SANT.(ACARSOY EN.) 50 NATURAL GAS 375,0
AFYON DGKÇ (DEDELİ DOĞALGAZELEKTRİK ÜR.) 126,1 NATURAL GAS 945,0
AGE DOĞALGAZ KOM. ÇEV. SANT.(AGE DENİZLİ) 94 NATURAL GAS
1057,0AGE DOĞALGAZ KOM. ÇEV. SANT.
(AGE DENİZLİ) 47 NATURAL GAS
ALES DOĞALGAZ KOM. ÇEV. SANT.(ALES ELEKT.) 49 NATURAL GAS 370,0
BİLECİK DOĞALGAZ ÇS. (TEKNODOĞALGAZ ÇEV.) 25,8 NATURAL GAS 190,0
BİLECİK DOĞALGAZ KÇS. (DEDELİDOĞALGAZ EL.) 19,4 NATURAL GAS
945,0BİLECİK DOĞALGAZ KÇS. (DEDELİ
DOĞALGAZ EL.) 107,03 NATURAL GAS
BİNATOM ELEKTRİK ÜRETİM A.Ş.(Emet/KÜTAHYA) 2,145 NATURAL GAS
78,0
BİNATOM ELEKTRİK ÜRETİM A.Ş.(Emet/KÜTAHYA) 2,145 NATURAL GAS
BİNATOM ELEKTRİK ÜRETİM A.Ş.(Emet/KÜTAHYA) 4,044 NATURAL GAS
BİNATOM ELEKTRİK ÜRETİM A.Ş.(Emet/KÜTAHYA) 2,022 NATURAL GAS
BİS ENERJİ(Sanayi/ Bursa) 458 NATURAL GAS 3450,0
BOSEN ENERJİ ELEKTRİK ÜRETİMAŞ.(Bursa) 27,96 NATURAL GAS 209,9
ENERJİ-SA (ÇANAKKALE) 0,915 NATURAL GAS 7,3
ENERJİ-SA (KÖSEKÖY) 120 NATURAL GAS 930,0
ENERJİ-SA (MERSİN) 1,465 NATURAL GAS 11,5
ENERJİ-SA (Zeytinli/ADANA) 0,83 NATURAL GAS 5,8
İŞBİRLİĞİ ENERJİ ÜRETİM SAN. VETİC. A.Ş. 19,46 NATURAL GAS 146,0
NAKSAN ENERJİ ELEKTRİK ÜRETİMA.Ş. 8 NATURAL GAS 60,0
NAKSAN ENERJİ ELEKTRİK ÜRETİMA.Ş. 8 NATURAL GAS 60,0
UNFCCC/CCNUCC
CDM – Executive Board Page 61
ODAŞ DOĞALGAZ KÇS (ODAŞELEKTRİK ÜRETİM) 54,96 NATURAL GAS 414,1
ODAŞ DOĞALGAZ KÇS (ODAŞELEKTRİK ÜRETİM) 18,32 NATURAL GAS 138,0
OFİM ENERJİ SANTRALI (OSTİMFİNANS VE İŞ MER.) 2,05 NATURAL GAS 16,0
PANCAR ELEKTRİK ÜRETİM A.Ş. 17,46 NATURAL GAS260,0
PANCAR ELEKTRİK ÜRETİM A.Ş. 17,46 NATURAL GAS
SODA SANAYİ A.Ş. (Mersin) 252,2 NATURAL GAS 1765,0
ŞANLIURFA OSB (RASA ENERJİÜRETİM A.Ş.) 11,72 NATURAL GAS 82,1
YENİ UŞAK ENERJİ ELEKTRİKSANTRALI 8,73 NATURAL GAS
71,0YENİ UŞAK ENERJİ ELEKTRİK
SANTRALI 1 NATURAL GAS
ZORLU ENERJİ (B.Karıştıran) 25,7 NATURAL GAS 192,8
1582,916 NATURAL GAS 11779,58
AKKÖY II HES (AKKÖY ENERJİ A.Ş.) 114,84 HYDRO899
AKKÖY II HES (AKKÖY ENERJİ A.Ş.) 114,84 HYDRO
AKKÖY-ESPİYE HES (KONİ İNŞAATSAN. A.Ş.) 8,912 HYDRO 40
ALABALIK REG. VE HES SANTRALI I-II(DARBOĞAZ ELK. ÜR. SAN.) 13,84 HYDRO 41
ANAK HES (KOR-EN KORKUTELİELEK. ÜRET. SAN.) 3,76 HYDRO 15
ARAKLI-1 REG. VE HES(YÜCEYURTENERJİ ÜRETİM) 10,203 HYDRO 38,94
ARAKLI-1 REG. VE HES(YÜCEYURTENERJİ ÜRETİM) 13,067 HYDRO 50
ARCA HES (GÜRSU TEMİZ ENERJİÜRETİM A.Ş.) 5,45 HYDRO
65ARCA HES (GÜRSU TEMİZ ENERJİ
ÜRETİM A.Ş.) 10,9 HYDRO
ARPA REG. VE HES (MCK ELEKTRİKÜRETİM A.Ş.) 32,412 HYDRO 78
AVCILAR HES (AVCILAR ENERJİELEKTRİK ÜRET.) 16,743 HYDRO 49
AYANCIK HES (İLK ELEKTRİK ENERJİÜRETİMİ SN.) 15,6 HYDRO 65
AYRANCILAR HES (MURADİYEELEKTRİK ÜRETİM) 9,359 HYDRO 38,112
BAĞIŞTAŞ II HES (AKDENİZLİELEKTRİK ÜRETİM) 32,4 HYDRO 122
UNFCCC/CCNUCC
CDM – Executive Board Page 62
BALKUSAN BARAJI VE HES 1 NOLUSANT. (KAREN) 13 HYDRO 40
BALKUSAN BARAJI VE HES 2 NOLUSANT. (KAREN) 25 HYDRO 80
BANGAL REG. VE KUŞLUK HES(KUDRET ENERJİ) 17 HYDRO 56
BEKTEMUR HES (DİZ-EP ELEKTRİKÜRETİM LTD.) 3,492 HYDRO 20
BOYABAT BARAJI VE HES (BOYABATELEKTRİK) 513 HYDRO 1468
BÜYÜKDÜZ HES (AYEN ENERJİ A.Ş.) 68,862 HYDRO 192
CAN 1 HES (HED ELEKTRİK ÜRETİMA.Ş.) 1,844 HYDRO 10
CEYHAN HES (BERKMAN HES)(ENOVA EN ÜRET.) 12,605 HYDRO 50,35
CUNİŞ REG. VE HES (RİNERJİ RİZEELEKTRİK ÜR.) 2,8 HYDRO
36CUNİŞ REG. VE HES (RİNERJİ RİZE
ELEKTRİK ÜR.) 5,6 HYDRO
ÇAĞLAYAN HES (ÇAĞLAYAN HESENERJİ ÜRETİM) 6 HYDRO 21
ÇARŞAMBA HES (ÇARŞAMBA ENERJİELEKTRİK) 11,31 HYDRO 63
ÇINAR-1 HES (AYCAN ENERJİ ÜRETİMTİC. VE SN.) 9,26 HYDRO 34
ÇUKURÇAYI HES (AYDEMİRELEKTRİK ÜRETİM A.Ş.) 1,8 HYDRO 4
DEMİRCİLER HES (PAK ENERJİÜRETİMİ SAN.) 3,124 HYDRO
35DEMİRCİLER HES (PAK ENERJİ
ÜRETİMİ SAN.) 5,317 HYDRO
DOĞANKAYA HES (MAR-EN ENERJİÜRET. TİC.) 20,55 HYDRO 98
DUMLU HES (DUMLU ENERJİELEKTRİK ÜRETİM) 3,982 HYDRO 9
EGER HES (EGER ELEKTRİK ÜRETİMLTD. ŞTİ.) 1,92 HYDRO 10
ESENDURAK HES (MERAL ELEKTRİKÜRETİM) 9,33 HYDRO 43
FEKE 1 HES (AKKUR ENERJİ ÜRETİMTİC. VE SAN.) 29,4 HYDRO 117
FEKE 2 BARAJI VE HES (AKKURENERJİ ÜRETİM) 69,34 HYDRO 223
FINDIK I HES (ADV ELEKTRİK ÜRETİMLTD. ŞTİ.) 11,25 HYDRO 48
GEMCİLER REG. VE HES (BOZTEPEENERJİ ÜRET.) 7,98 HYDRO 35
GÖKGEDİK HES (UHUD ENERJİÜRETİM TİC.) 20,49 HYDRO
100GÖKGEDİK HES (UHUD ENERJİ
ÜRETİM TİC.) 3,776 HYDRO
UNFCCC/CCNUCC
CDM – Executive Board Page 63
GÜDÜL 2 HES (YAŞAM ENERJİELEKTRİK ÜRETİM) 4,88 HYDRO 20
GÜLLÜBAĞ BARAJI VE HES(SENENERJİ ENERJİ) 96 HYDRO 384
GÜNDER REG. VE HES (ARIK ENERJİÜRETİM A.Ş.) 28,22 HYDRO
84GÜNDER REG. VE HES (ARIK ENERJİ
ÜRETİM A.Ş.) 0 HYDRO
HORU REG. VE HES (MARAŞ ENERJİYATIRIM SN.) 4,24 HYDRO
34HORU REG. VE HES (MARAŞ ENERJİ
YATIRIM SN.) 4,24 HYDRO
HORYAN HES (HORYAN ENERJİ A.Ş.) 5,68 HYDRO 23
KARTALKAYA HES (SIR ENERJİÜRETİM SAN.) 8,001 HYDRO 27
KAYAKÖPRÜ 2 HES (ARSAN ENERJİA.Ş.) 10,2 HYDRO 36
KIRIKDAĞ HES (ÖZENİR ENERJİELEKTRİK ÜRET.) 16,86 HYDRO 71
KOZDERE HES (ADO MADENCİLİKELEKTRİK ÜR.) 6,12 HYDRO 9,21
KÖKNAR HES (AYCAN ENERJİÜRETİM TİC.) 8,024 HYDRO 25
KÜRCE REG. VE HES (DEDEGÖLENERJİ) 12,046 HYDRO 48
MENGE BARAJI VE HES (ENERJİSAENERJİ) 44,71 HYDRO 102
MİDİLLİ REG. VE HES (MASAT ENERJİELEKTRİK) 20,97 HYDRO 81
MURAT I-II REG. VE HES (MURAT HESENERJİ EL.) 35,628 HYDRO 189
MURATLI REG. VE HES (ARMAHESELEKTRİK ÜR.) 11 HYDRO 27,43
MURSAL I HES (PETA MÜHENDİSLİKENERJİ) 4,18 HYDRO 17
NİKSAR HES (NİKSAR ENERJİ ÜRETİMLTD. ŞTİ.) 20,08 HYDRO
248NİKSAR HES (NİKSAR ENERJİ ÜRETİM
LTD. ŞTİ.) 20,08 HYDRO
ÖREN REG. VE HES (ÇELİKLERELEKTRİK ÜRETİM) 19,932 HYDRO 21,73
PAPART HES (ELİTE ELEKTRİKÜRETİM) 22 HYDRO
106PAPART HES (ELİTE ELEKTRİK
ÜRETİM) 4,6 HYDRO
POLAT HES (ELESTAŞ ELEKTRİKÜRETİM A.Ş.) 3,28 HYDRO
28POLAT HES (ELESTAŞ ELEKTRİK
ÜRETİM A.Ş.) 3,28 HYDRO
SANCAR REG. VE HES (MELİTAELEKTRİK ÜRETİM) 0,74 HYDRO 3
UNFCCC/CCNUCC
CDM – Executive Board Page 64
SARIHIDIR HES (MOLU ENERJİÜRETİM A.Ş.) 6 HYDRO 24
SEYRANTEPE HES (SEYRANTEPEELEKT. ÜRET.) 56,84 HYDRO 207
SIRAKONAKLAR HES (2M ENERJİÜRETİM A.Ş.) 18 HYDRO 69
SULUKÖY HES (DU ELEKTRİK ÜRETİMA.Ş.) 6,924 HYDRO 28
ŞİFRİN REG. VE HES (BOMONTİ ELK.MÜH. MÜŞ.) 6,744 HYDRO 18
TELEME REG. VE HES (TAYENELEKTRİK ÜRET.) 1,57 HYDRO 11
TELLİ I-II HES (FALANJ ENERJİELEKTRİK ÜRET.) 8,72 HYDRO 32
TUĞRA REG. VE HES (VİRA ELEKTRİKÜRETİM A.Ş.) 4,9 HYDRO 18
TUNA HES (NİSAN ELEKTROMEKANİKENERJİ) 37,19 HYDRO 92
TUZKÖY HES (BATEN ENERJİÜRETİMİ A.Ş.) 8,44 HYDRO 68
TUZLAKÖY-SERGE REG. VE HES(TUYAT ELEKT.) 7,14 HYDRO 21
UMUT I REG. VE HES (NİSANELEKTROMEKANİK) 5,8 HYDRO 21
ÜÇKAYA HES (ŞİRİKÇİOĞLUELEKTRİK ÜRETİM A.Ş.) 1,04 HYDRO 5
VİZARA REG. VE HES (ÖZTÜRKELEKT. ÜRET. LTD.) 8,578 HYDRO 27
YAĞMUR REG. VE HES (BT BORDOELK. ÜR.) 8,946 HYDRO 32
YAMANLI III KAPS. GÖKKAYA HES(MEM ENERJİ) 28,54 HYDRO 105
YAMANLI III KAPS. HİMMETLİ HES(MEM ENERJİ) 26,98 HYDRO 100
YAVUZ HES (AREM ENERJİ ÜRETİMA.Ş.) 5,8 HYDRO 14
YEDİSU HES (ÖZALTIN ENERJİÜRETİM VE İNŞAAT) 15,14 HYDRO
72YEDİSU HES (ÖZALTIN ENERJİ
ÜRETİM VE İNŞAAT) 7,57 HYDRO
YILDIRIM HES (BAYBURT ENERJİÜRETİM VE TİC.) 7,118 HYDRO
39YILDIRIM HES (BAYBURT ENERJİ
ÜRETİM VE TİC.) 3,559 HYDRO
YOKUŞLU KALKANDERE HES (SANKOENERJİ) 5,2 HYDRO 23,40
ZEYTİN BENDİ HES (ZEYTİN ENERJİÜRET. SAN.) 5,2 HYDRO 18
ZEYTİN BENDİ HES (ZEYTİN ENERJİÜRET. SAN.) 0 HYDRO 0
1987,288 HYDRO 6922,172
UNFCCC/CCNUCC
CDM – Executive Board Page 65
AKSU RES (AKSU TEMİZ ENERJİELEKTRİK ÜRETİM) 36 WIND
216AKSU RES (AKSU TEMİZ ENERJİELEKTRİK ÜRETİM) 30 WIND
AKSU RES (AKSU TEMİZ ENERJİELEKTRİK ÜRETİM) 6 WIND
BALIKESİR RES (BARES ELEKTRİKÜRETİM A.Ş.) 13,75 WIND
434
BALIKESİR RES (BARES ELEKTRİKÜRETİM A.Ş.) 16,5 WIND
BALIKESİR RES (ENERJİSA ENERJİÜRETİM A.Ş.) 24,75 WIND
BALIKESİR RES (ENERJİSA ENERJİÜRETİM A.Ş.) 16,5 WIND
BALIKESİR RES (ENERJİSA ENERJİÜRETİM A.Ş.) 19,25 WIND
BALIKESİR RES (ENERJİSA ENERJİÜRETİM A.Ş.) 22 WIND
BANDIRMA RES (YAPISAN ELEKTRİKÜRETİM A.Ş.) 5 WIND 20
BOZYAKA RES (KARDEMİRHADDECİLİK VE ELEKT.) 12 WIND 38
DAĞPAZARI RES (ENERJİSA ENERJİÜRETİM A.Ş.) 36 WIND
120DAĞPAZARI RES (ENERJİSA ENERJİ
ÜRETİM A.Ş.) 3 WIND
DİNAR RES (OLGU ENERJİ YATIRIMÜRETİM) 16,1 WIND 60
GÜNAYDIN RES (MANRES ELEKTRİKÜRETİM A.Ş.) 10 WIND 40
İNNORES ELEKTRİK YUNTDAĞRÜZGAR (Aliağa-İZMİR) 5 WIND 20,26
KARADAĞ RES (GARET ENERJİÜRETİM) 10 WIND 34
KAYADÜZÜ RES (BAKTEPE ENERJİA.Ş.) 7,5 WIND
129KAYADÜZÜ RES (BAKTEPE ENERJİA.Ş.) 25 WIND
KAYADÜZÜ RES (BAKTEPE ENERJİA.Ş.) 6,5 WIND
KOZBEYLİ RES (DOĞAL ENERJİELEKTRİK ÜRETİM) 20 WIND 70
METRİSTEPE RES (CAN ENERJİENTEGRE ELEKT.) 27,5 WIND
85METRİSTEPE RES (CAN ENERJİ
ENTEGRE ELEKT.) 11,5 WIND
POYRAZ RES (POYRAZ ENERJİELEKTRİK ÜRETİM) 14 WIND
156,4POYRAZ RES (POYRAZ ENERJİ
ELEKTRİK ÜRETİM) 20 WIND
SAMURLU RES (DOĞAL ENERJİELEKTRİK ÜRET.) 12 WIND 70
UNFCCC/CCNUCC
CDM – Executive Board Page 66
SAMURLU RES (DOĞAL ENERJİELEKTRİK ÜRET.) 10 WIND
SOMA RES (SOMA ENERJİ ELEKTRİKÜRETİM A.Ş.) 24 WIND 82,27
SÖKE-ÇATALBÜK RES (ABK ENERJİELEKTRİK) 18 WIND
110SÖKE-ÇATALBÜK RES (ABK ENERJİ
ELEKTRİK) 12 WIND
ŞENKÖY RES (EOLOS RÜZGARENERJİSİ ÜRETİM) 26 WIND 87
515,85 WIND 1771,93
AREL ENERJİ BİYOKÜTLE TESİSİ(AREL ÇEVRE) 1,2 WASTE
18AREL ENERJİ BİYOKÜTLE TESİSİ
(AREL ÇEVRE) 1,2 WASTE
BEREKET ENERJİ ÜRETİM A.Ş.(BİOGAZ) 0,635 WASTE 5
EKİM BİYOGAZ (EKİM GRUPELEKTRİK ÜRETİM) 1,2 WASTE 10
ITC ADANA ENERJİ ÜRETİM (ADANABİOKÜTLE SNT) 4,245 WASTE 31,83
ITC BURSA ENERJİ ÜRETİM SAN. VETİC. A.Ş. 7 WASTE
80ITC BURSA ENERJİ ÜRETİM SAN. VETİC. A.Ş. 1,4 WASTE
ITC BURSA ENERJİ ÜRETİM SAN. VETİC. A.Ş. 1,4 WASTE
İZAYDAŞ (İZMİT ÇÖP)(Köseköy) 0,33 WASTE 2,2
KAYSERİ KATI ATIK DEPONİ SAHASI(HER ENERJİ) 1,305 WASTE 9,9
KOCAELİ ÇÖP BİYOGAZ (LFG)(KÖRFEZ ENERJİ) 1,2 WASTE 18
KOCAELİ ÇÖP BİYOGAZ (LFG)(KÖRFEZ ENERJİ) 1,063 WASTE
ORTADOĞU ENERJİ (KÖMÜRCÜODA)(Şile/İSTANBUL) 2,83 WASTE 22,04
ORTADOĞU ENERJİ (ODA YERİ)(Eyüp/İSTANBUL) 4,092 WASTE 31,805
SAMSUN AVDAN KATI ATIK (SAMSUNAVDAN EN.) 2,4 WASTE 18
SEZER BİO ENERJİ (KALEMİRLERENERJİ ELEKTR.) 0,5 WASTE 4
32 WASTE 250,775
64 WASTE 501,55
UNFCCC/CCNUCC
CDM – Executive Board Page 67
DENİZ JEOTERMAL (MAREN MARAŞELEKTRİK) 24 GEOTHERMAL 191
SİNEM JEOTERMAL (MAREN MARAŞELEKTRİK) 24 GEOTHERMAL 191
48 GEOTHERMAL 382
AKSA AKRİLİK KİMYA SAN. A.Ş. (İTHALKÖM.+D.G) 75 COAL 525
EREN ENERJİ ELEKTRİK ÜRETİM A.Ş. 30 COAL 195,97
105 COAL 720,97
2011
COMPANY INSTALLEDPOWER (MW) TYPE ELEC. GENERATION
ADİLCEVAZ (MOSTAR ENERJİ ELEKTRİK) 0,394 HYDROLIC0,8
AHLAT (MOSTAR ENERJİ ELEKTRİK) 0,201 HYDROLIC0,6
AKSU REG. VE HES (KALEN ENERJİ) 5,2 HYDROLIC16
ALKUMRU BARAJI VE HES (LİMAK HİD.) 174,18
HYDROLIC
828
ALKUMRU BARAJI VE HES (LİMAK HİD.) 87,09
AYRANCILAR HES (MURADİYE ELEKTRİK) 18,718HYDROLIC 128
AYRANCILAR HES (MURADİYE ELEKTRİK) 13,377
AYVACIK RES (AYRES AYVACIK RÜZG.) 5 HYDROLIC17
BALKONDU I HES (BTA ELEKTRİK ENERJİ) 9,191 HYDROLIC33
BAYBURT (BOYDAK ENERJİ) 0,396 HYDROLIC7,9
UNFCCC/CCNUCC
CDM – Executive Board Page 68
BAYRAMHACILI BARAJI VE HES 47 HYDROLIC175
BERDAN 10,2 HYDROLIC47,2
BESNİ KAYSERİ VE CİVARI ENERJİ) 0,272 HYDROLIC0,5
BOĞUNTU HES (BEYOBASI ENERJİ) 3,801 HYDROLIC17
BÜNYAN (KAYSERİ VE CİVARI EL. T.A.Ş) 1,156 HYDROLIC3,4
CEVHER I-II REG. VE HES (ÖZCEVHER EN.) 16,36 HYDROLIC65
ÇAĞ-ÇAĞ (NAS ENERJİ A.Ş.) 14,4 HYDROLIC25
ÇAKIRMAN REG. VE HES (YUSAKA EN.) 6,98 HYDROLIC22
ÇAMARDI (KAYSERİ VE CİVARI EL. T.A.Ş) 0,069 HYDROLIC0,2
ÇAMLICA III HES (ÇAMLICA ELEKTRİK) 27,618 HYDROLIC 43
ÇAMLIKAYA REG.VE HES (ÇAMLIKAYA EN) 2,824 HYDROLIC6,31
ÇANAKÇI HES (CAN ENERJİ ENTEGRE) 4,633
HYDROLIC
39
ÇANAKÇI HES (CAN ENERJİ ENTEGRE) 4,633
ÇEMİŞKEZEK (BOYDAK ENERJİ) 0,116 HYDROLIC0,8
ŞELALE HES (MURADİYE ELEKTRİK ÜR.) 13,377 HYDROLIC 56,57
467,186 HYDROLIC 1532,28
AKIM ENERJİ BAŞPINAR (SÜPER FİLM) 25,32 NATURAL GAS 177,00
AKSA AKRİLİK (İTHAL KÖM.+D.G) 25 NATURAL GAS 175,00
AKSA ENERJİ (Antalya) 300 NATURAL GAS3600,00
AKSA ENERJİ (Antalya) (İlave) 300
ALİAĞA ÇAKMAKTEPE ENERJİ (İlave) 130,95 NATURAL GAS1054,00
ALİAĞA ÇAKMAKTEPE ENERJİ (İlave) 8,73
BOSEN ENERJİ ELEKTRİK ÜRETİM AŞ. 93 NATURAL GAS 698,09
CENGİZ ÇİFT YAKITLI K.Ç.E.S. 131,335 NATURAL GAS 985,00
CENGİZ ENERJİ SAN.VE TİC.A.Ş. 35 NATURAL GAS 281,30
UNFCCC/CCNUCC
CDM – Executive Board Page 69
GLOBAL ENERJİ (PELİTLİK) 4 NATURAL GAS 29,90
GOREN-1 (GAZİANTEP ORGANİZE SAN.) 48,65 NATURAL GAS 277,00
HAMİTABAT (Lisans Tadili) 36 NATURAL GAS 237,90
HG ENERJİ ELEKTRİK ÜRET. SAN.TİC. A.Ş. 52,38 NATURAL GAS 366,00
NUH ENERJİ EL. ÜRT.A.Ş. (ENERJİ SANT.-2) 119,98 NATURAL GAS 900,00
ODAŞ DOĞALGAZ KÇS (ODAŞ ELEKTRİK) 54,96 NATURAL GAS 415,00
SAMSUN TEKKEKÖY EN. SAN. (AKSA EN.) 131,335 NATURAL GAS 980,00
ŞANLIURFA OSB (RASA ENERJİ ÜR. A.Ş.) 116,76 NATURAL GAS 800,00
TİRENDA TİRE ENERJİ ÜRETİM A.Ş. 58,38 NATURAL GAS 410,00
YENİ UŞAK ENERJİ ELEKTRİK SANTRALI 8,73 NATURAL GAS 65,00
ZORLU ENERJİ (B.Karıştıran) 7,2 NATURAL GAS 54,07
1687,71 NATURAL GAS 11505,26
AKRES (AKHİSAR RÜZGAR EN. ELEKT.) 20
WIND 165,00AKRES (AKHİSAR RÜZGAR EN. ELEKT.) 20
AKRES (AKHİSAR RÜZGAR EN. ELEKT.) 3,75
BAKİ ELEKTRİK ŞAMLI RÜZGAR (İlave) 24 WIND 92,60
BANDIRMA ENERJİ (BANDIRMA RES) 3 WIND 10,97
ÇANAKKALE RES (ENERJİ-SA ENERJİ) 25,3WIND 92,00
ÇANAKKALE RES (ENERJİ-SA ENERJİ) 4,6
ÇATALTEPE RES (ALİZE ENERJİ ELEKTRİK) 16 WIND 52,00
İNNORES ELEKTRİK YUNTDAĞ RÜZGAR 10 WIND 40,57
KİLLİK RES (PEM ENERJİ A.Ş.) 20
WIND 86,00KİLLİK RES (PEM ENERJİ A.Ş.) (İlave) 15
KİLLİK RES (PEM ENERJİ A.Ş.) (İlave) 5
166,65 WIND 539,14
UNFCCC/CCNUCC
CDM – Executive Board Page 70
AYDIN/GERMENCİK JEOTERMAL 20 GEOTHERMAL 150
BOLU BELEDİYESİ ÇÖP TOP. TES. BİYOGAZ 1,131 WASTE 7,50
CEV ENERJİ ÜRETİM(GAZİANTEP ÇÖP BİOGAZ) 4,524 WASTE 29,40
ITC ADANA ENERJİ ÜRETİM (İlave) 1,415 WASTE 10,40
ITC-KA EN. (ASLIM BİYOKÜTLE) KONYA 4,245WASTE 44,50
ITC-KA EN. (ASLIM BİYOKÜTLE) KONYA 1,415
ITC-KA ENERJİ MAMAK KATI ATIK TOP. 2,826 WASTE 18,91
ITC-KA ENERJİ (SİNCAN) (İlave) 1,416 WASTE 44,50
KAYSERİ KATI ATIK DEPONİ SAHASI 1,56 WASTE 12,00
18,532 WASTE 167,21
BATMAN 0,475 FUEL-OIL 3,30
KARKEY (SİLOPİ 1) 100,44 FUEL-OIL 701,15
MARDİN-KIZILTEPE (AKSA ENERJİ) 32,1 FUEL-OIL 225,00
MOSB Enerji Elektrik Üretim Ltd. Şti.(İlave) 43,5 FUEL-OIL 360,50
176,515 FUEL-OIL 1289,95
BEKİRLİ TES (İÇDAŞ ELEKTRİK EN.) 600 IMPORTED COAL 4320,00
UNFCCC/CCNUCC
CDM – Executive Board Page 71
2010
COMPANY INSTALLEDPOWER (MW) TYPE ELEC. GENERATION
AKSA ENERJİ (ANTALYA) 25 NATURAL GAS385
AKSA ENERJİ (ANTALYA) 25 NATURAL GAS
ALİAĞA ÇAKMAKTEPE ENERJİ (İlave) 69,84 NATURAL GAS 557,92
ALTEK ALARKO ELEKTRİK SANTRALLARI 60,1 NATURAL GAS567
ALTEK ALARKO ELEKTRİK SANTRALLARI 21,89 NATURAL GAS
ATAER ENERJİ ELEKTRİK ÜRETİM A.Ş. 49 NATURAL GAS 277,88
BİNATOM ELEKTRİK ÜRETİM A.Ş. 2 NATURAL GAS 13
CAN ENERJİ ELEKTRİK ÜR. A.Ş.(Tekirdağ) 29,1 NATURAL GAS 203
CENGİZ ENERJİ SAN. VE TİC. A.Ş. (Tekkeköy) 101,95 NATURAL GAS1604
CENGİZ ENERJİ SAN. VE TİC. A.Ş. (Tekkeköy) 101,95 NATURAL GAS
ENERJİ-SA (BANDIRMA) 1.000,00 NATURAL GAS 7540
GLOBAL ENERJİ (PELİTLİK) 3,544 NATURAL GAS 27,06
RASA ENERJİ (VAN) 26,19 NATURAL GAS231
RASA ENERJİ (VAN) (İlave) 10,124 NATURAL GAS
SÖNMEZ ENERJİ ÜRETİM (UŞAK) 33,242 NATURAL GAS276,06
SÖNMEZ ENERJİ ÜRETİM (UŞAK) (İlave) 2,564 NATURAL GAS
UĞUR ENERJİ ÜR. TİC.VE SAN. A.Ş. (İlave) 12 NATURAL GAS506
UĞUR ENERJİ ÜRETİM TİC. VE SAN. A.Ş. 48,2 NATURAL GAS
1621,694 NATURAL GAS 12187,92
ALAKIR HES (YURT ENERJİ ÜRETİM) 2,06 HYDROLIC 6,00
AKIM ENERJİ (CEVİZLİK REG. VE HES) 91,4 HYDROLIC 330,00
UNFCCC/CCNUCC
CDM – Executive Board Page 72
ASA ENERJİ (KALE REG.ve HES) 9,57 HYDROLIC 32,00
BAYBURT HES (BAYBURT ENERJİ ÜRET.) 14,631 HYDROLIC 51,00
BEYTEK EL. ÜR. A.Ş. (ÇATALOLUK HES) 9,54 HYDROLIC 31,00
BİRİM HİDR. ÜRETİM AŞ. (ERFELEK HES) 3,225 HYDROLIC19,00
BİRİM HİDR. ÜRETİM AŞ. (ERFELEK HES) 3,225 HYDROLIC
BULAM REG. VE HES (MEM ENERJİ ELK.) 7,03 HYDROLIC 33,00
BURÇ BENDİ VE HES (AKKUR ENERJİ) 27,33 HYDROLIC 113,00
CEYHAN HES (BERKMAN HES)(ENOVA EN.) 12,605 HYDROLIC
201,00CEYHAN HES (BERKMAN HES)(ENOVA EN.) 12,605 HYDROLIC
CEYHAN HES (OŞKAN HES) (ENOVA EN.) 23,889 HYDROLIC
CİNDERE HES (İlave) 9,065 HYDROLIC 28,28
ÇAKIT HES (ÇAKIT ENERJİ A.Ş.) 20,18 HYDROLIC 96,00
ÇAMLIKAYA REG. VE HES 5,648 HYDROLIC 19,00
DAMLAPINAR HES (CENAY ELEKTRİK ÜR.) 16,424 HYDROLIC 92,00
DİM HES (DİLER ELEKTRİK ÜRETİM) 38,25 HYDROLIC 123,00
DİNAR HES (ELDA ELEKTRİK ÜRETİM) 4,44 HYDROLIC 15,00
DOĞUBAY ELEKTRİK (SARIMEHMET HES) 3,1 HYDROLIC 10,00
EGEMEN 1 HES (ENERSİS ELEKTRİK) 8,82 HYDROLIC72,00
EGEMEN 1B HES (ENERSİS ELEKTRİK) 11,1 HYDROLIC
ERENKÖY REG. VE HES (TÜRKERLER) 21,456 HYDROLIC 87,00
ERENLER REG. ve HES (BME BİR.MÜT.EN.) 45 HYDROLIC 85,00
ERİKLİ-AKOCAK REG. ve AKOCAK HES 41,25 HYDROLIC 257,00
ERİKLİ-AKOCAK REG. ve AKOCAK HES 41,25 HYDROLIC 257,00
FEKE 2 BARAJI VE HES (AKKUR ENERJİ) 69,34 HYDROLIC 223,00
FIRTINA ELEKTRİK ÜR. A.Ş. (SÜMER HES) 21,6 HYDROLIC 70,00
GÖK REG. ve HES (GÖK ENERJİ EL. SAN.) 10,008 HYDROLIC 43,00
UNFCCC/CCNUCC
CDM – Executive Board Page 73
GÜDÜL I REG. VE HES (YAŞAM ENERJİ) 2,36 HYDROLIC 14,00
GÜZELÇAY-I HES (İLK ELEKTRİK ENERJİ) 3,14 HYDROLIC43,00
GÜZELÇAY-II HES (İLK ELEKTRİK ENERJİ) 4,96 HYDROLIC
HETAŞ HACISALİHOĞLU (YILDIZLI HES) 1,2 HYDROLIC 5,00
KAHRAMAN REG. VE HES (KATIRCIOĞLU) 1,42 HYDROLIC 6,00
KAHTA I HES (ERDEMYILDIZ ELEK. ÜRT.) 7,12 HYDROLIC 35,00
KALE REG. VE HES (KALE ENERJİ ÜR.) 34,14 HYDROLIC 116,00
KALKANDERE REG. VE YOKUŞLU HES 14,54 HYDROLIC 63,00
KARADENİZ EL. (UZUNDERE-1 HES)(İlave) 31,076 HYDROLIC165,00
KARADENİZ EL.ÜRET. (UZUNDERE-1 HES) 31,076 HYDROLIC
KAR-EN KARADENİZ EL.A.Ş. ARALIK HES 12,41 HYDROLIC 56,00
KARŞIYAKA HES (AKUA ENERJİ ÜRET.) 1,592 HYDROLIC 8,00
KAYABÜKÜ REG. VE HES (ELİTE ELEKT.) 14,58 HYDROLIC 49,00
KİRPİLİK REG. VE HES (ÖZGÜR ELEKTRİK) 6,24 HYDROLIC 22,00
KOZAN HES (SER-ER ENERJİ) 4 HYDROLIC 9,00
KULP IV HES (YILDIZLAR EN.ELK.ÜR.AŞ.) 12,298 HYDROLIC 41,00
MURGUL BAKIR (Ç.Kaya) (İlave) 19,602 HYDROLIC 40,50
NARİNKALE REG. VE HES (EBD ENERJİ) 3,1 HYDROLIC 10,00
NİSAN E.MEKANİK EN. (BAŞAK REG. HES) 6,85 HYDROLIC 22,00
NURYOL ENERJİ (DEFNE REG. VE HES) 7,23 HYDROLIC 22,00
ÖZGÜR ELEKTRİK (AZMAK I REG.VE HES) 5,913 HYDROLIC43,00
ÖZGÜR ELEKTRİK (AZMAK I REG.VE HES) 5,913 HYDROLIC
PAŞA REG. VE HES (ÖZGÜR ELEKTRİK) 8,68 HYDROLIC 34,00
PETA MÜHENDİSLİK EN. (MURSAL II HES) 4,5 HYDROLIC 19,00
REŞADİYE 1 HES (TURKON MNG ELEKT.) 15,68 HYDROLIC 126,00
REŞADİYE 2 HES (TURKON MNG ELEKT.) 26,14 HYDROLIC 210,00
UNFCCC/CCNUCC
CDM – Executive Board Page 74
SABUNSUYU II HES (ANG ENERJİ ELK.) 7,35 HYDROLIC 21,00
SELEN ELEKTRİK (KEPEZKAYA HES) 28 HYDROLIC 124,00
SELİMOĞLU REG. VE HES 8,8 HYDROLIC 35
TEKTUĞ ELEKTRİK (ANDIRIN HES) 40,5 HYDROLIC 106,00
ULUABAT KUVVET TÜNELİ VE HES 48,51 HYDROLIC 372,00
ULUABAT KUVVET TÜNELİ VE HES (İlave) 48,51 HYDROLIC 372,00
UMUT III REG. VE HES (NİSAN ELEKTR.) 12 HYDROLIC 26,00
UZUNÇAYIR HES (Tunceli) (İlave) 27,33 HYDROLIC 216,64
UZUNÇAYIR HES (Tunceli) (İlave) 27,33 HYDROLIC 216,64
YAVUZ REG. VE HES (MASAT ENERJİ) 22,5 HYDROLIC 83,00
YEDİGÖZE HES (YEDİGÖZE ELEKTRİK) 155,33 HYDROLIC 474,00
1295,961 HYDROLIC 5498,06
ALİZE ENERJİ (KELTEPE RES) 1,8 WIND 6,35
AKDENİZ ELEKTRİK (MERSİN RES) 33 WIND 100,00
ASMAKİNSAN (BANDIRMA 3 RES) 20 WIND85,00
ASMAKİNSAN (BANDIRMA 3 RES) 4 WIND
BAKRAS EN. ELKT.ÜR. A.Ş. ŞENBÜK RES 15 WIND 47,00
BELEN ELEKTRİK (BELEN RES) (İlave) 6 WIND 19,00
BERGAMA RES EN. ÜR. A.Ş. ALİAĞA RES 52,5 WIND355,00
BERGAMA RES EN. ÜR. A.Ş. ALİAĞA RES 37,5 WIND
BORASKO ENERJİ (BANDIRMA RES) 12 WIND 47,78
BOREAS ENERJİ (BOREAS I ENEZ RES) 15 WIND 49,00
DENİZ ELEKTRİK (SEBENOBA RES) 10 WIND 36,66
KUYUCAK RES (ALİZE ENERJİ ÜR.) (İlave) 17,6 WIND110,00
KUYUCAK RES (ALİZE ENERJİ ÜRET.) 8 WIND
UNFCCC/CCNUCC
CDM – Executive Board Page 75
MAZI-3 RES ELEKTRİK (MAZI-3 RES) 7,5 WIND 26,25
ROTOR ELEKTRİK (GÖKÇEDAĞ RES) 20 WIND 84,97
ROTOR ELEKTRİK (GÖKÇEDAĞ RES) (İlave) 2,5 WIND 84,97
ROTOR ELEKTRİK (OSMANİYE RES) 20 WIND
207,70ROTOR ELEKTRİK (OSMANİYE RES) 17,5 WIND
ROTOR ELEKTRİK (OSMANİYE RES) 17,5 WIND
SARES RES (GARET ENERJİ ÜRETİM) 15 WIND 60,00
SOMA ENERJİ ÜRETİM (SOMA RES) 4,5 WIND
114,00
SOMA ENERJİ ÜRETİM (SOMA RES) 7,2 WIND
SOMA ENERJİ ÜRETİM (SOMA RES) 7,2 WIND
SOMA ENERJİ ÜRETİM (SOMA RES) 6,3 WIND
SOMA ENERJİ ÜRETİM (SOMA RES) (İlave) 9 WIND
SOMA RES (BİLGİN RÜZGAR SAN) (İlave) 27,5 WIND
307,00SOMA RES (BİLGİN RÜZGAR SAN. EN.ÜR.) 32,5 WIND
SOMA RES (BİLGİN RÜZGAR SAN.)(İlave) 30 WIND
TURGUTTEPE RES (SABAŞ ELEKTRİK ÜR.) 22 WIND 64,00
ÜTOPYA ELEKTRİK (DÜZOVA RES) (İlave) 15 WIND 46,00
ZİYARET RES (ZİYARET RES ELEK.)(İlave) 22,5 WIND140,00
ZİYARET RES (ZİYARET RES ELEKTRİK) 12,5 WIND
528,6 WIND 1990,677
MENDERES GEOTERMAL DORA-2 9,5 GEOTHERMAL 73
TUZLA JEOTERMAL 7,5 GEOTHERMAL 55
17 GEOTHERMAL 128
UNFCCC/CCNUCC
CDM – Executive Board Page 76
ITC-KA ENERJİ (SİNCAN) 1,416 WASTE 11,12
ORTADOĞU ENERJİ (ODA YERİ) (Eyüp/İST.) 4,245 WASTE 33,35
ITC ADANA BİOKÜTLE SANT. 11,32 WASTE 80
16,981 WASTE 124,47
EREN ENERJİ ELEKTRİK ÜR. A.Ş. (İlave) 600 IMPORTED COAL
9080EREN ENERJİ ELEKTRİK ÜR. A.Ş. (İlave) 600 IMPORTED COAL
EREN ENERJİ ELEKTRİK ÜRETİM A.Ş. 160 IMPORTED COAL
1360 imported coal
CDM Projects benefitting from VER revenues
2012
BALIKESİR RES (BARESELEKTRİK ÜRETİM A.Ş.) 13,75 WIND
434
BALIKESİR RES (BARESELEKTRİK ÜRETİM A.Ş.) 16,5 WIND
BALIKESİR RES (ENERJİSAENERJİ ÜRETİM A.Ş.) 24,75 WIND
BALIKESİR RES (ENERJİSAENERJİ ÜRETİM A.Ş.) 16,5 WIND
BALIKESİR RES (ENERJİSAENERJİ ÜRETİM A.Ş.) 19,25 WIND
BALIKESİR RES (ENERJİSAENERJİ ÜRETİM A.Ş.) 22 WIND
DAĞPAZARI RES (ENERJİSAENERJİ ÜRETİM A.Ş.) 36 WIND
120DAĞPAZARI RES (ENERJİSA
ENERJİ ÜRETİM A.Ş.) 3 WIND
GÜNAYDIN RES (MANRESELEKTRİK ÜRETİM A.Ş.) 10 WIND 40
İNNORES ELEKTRİK YUNTDAĞRÜZGAR (Aliağa-İZMİR) 5 WIND 20,26
KAYADÜZÜ RES (BAKTEPEENERJİ A.Ş.) 7,5 WIND 129
UNFCCC/CCNUCC
CDM – Executive Board Page 77
KAYADÜZÜ RES (BAKTEPEENERJİ A.Ş.) 25 WIND
KAYADÜZÜ RES (BAKTEPEENERJİ A.Ş.) 6,5 WIND
METRİSTEPE RES (CANENERJİ ENTEGRE ELEKT.) 27,5 WIND
85METRİSTEPE RES (CAN
ENERJİ ENTEGRE ELEKT.) 11,5 WIND
SOMA RES (SOMA ENERJİELEKTRİK ÜRETİM A.Ş.) 24 WIND 82,27
SÖKE-ÇATALBÜK RES (ABKENERJİ ELEKTRİK) 18 WIND
110SÖKE-ÇATALBÜK RES (ABK
ENERJİ ELEKTRİK) 12 WIND
298,75 WIND 1020,53
ITC ADANA ENERJİ ÜRETİM(ADANA BİOKÜTLE SNT) 4,245 WASTE 31,83
KOCAELİ ÇÖP BİYOGAZ (LFG)(KÖRFEZ ENERJİ) 1,2 WASTE
18KOCAELİ ÇÖP BİYOGAZ (LFG)
(KÖRFEZ ENERJİ) 1,063 WASTE
SAMSUN AVDAN KATI ATIK(SAMSUN AVDAN EN.) 2,4 WASTE 18
8,908 WASTE 67,83
Total 1088,36
2011
ŞELALE HES (MURADİYE ELEKTRİKÜR.) 13,377 HYDROLIC 56,57
AKRES (AKHİSAR RÜZGAR EN.ELEKT.) 20
WIND 165,00AKRES (AKHİSAR RÜZGAR EN.ELEKT.) 20
AKRES (AKHİSAR RÜZGAR EN.ELEKT.) 3,75
BAKİ ELEKTRİK ŞAMLI RÜZGAR(İlave) 24 WIND 92,60
BANDIRMA ENERJİ (BANDIRMA RES) 3 WIND 10,97
ÇANAKKALE RES (ENERJİ-SA ENERJİ) 25,3WIND 92,00
ÇANAKKALE RES (ENERJİ-SA ENERJİ) 4,6ÇATALTEPE RES (ALİZE ENERJİ
ELEKTRİK) 16 WIND 52,00
UNFCCC/CCNUCC
CDM – Executive Board Page 78
İNNORES ELEKTRİK YUNTDAĞRÜZGAR 10 WIND 40,57
KİLLİK RES (PEM ENERJİ A.Ş.) 20
WIND 86,00KİLLİK RES (PEM ENERJİ A.Ş.) (İlave) 15
KİLLİK RES (PEM ENERJİ A.Ş.) (İlave) 5
166,65 WIND 539,14
BOLU BELEDİYESİ ÇÖP TOP. TES.BİYOGAZ 1,131 WASTE 7,50
CEV ENERJİ ÜRETİM(GAZİANTEP ÇÖPBİOGAZ) 4,524 WASTE 29,40
ITC ADANA ENERJİ ÜRETİM (İlave) 1,415 WASTE 10,40
7,07 WASTE 47,3
Total 643,01
2010
AKIM ENERJİ (CEVİZLİK REG. VE HES) 91,4 HYDROLIC 330,00
BEYTEK EL. ÜR. A.Ş. (ÇATALOLUK HES) 9,54 HYDROLIC 31,00
ÇAKIT HES (ÇAKIT ENERJİ A.Ş.) 20,18 HYDROLIC 96,00
KALKANDERE REG. VE YOKUŞLU HES 14,54 HYDROLIC 63,00
KAR-EN KARADENİZ EL.A.Ş. ARALIK HES 12,41 HYDROLIC 56,00
REŞADİYE 1 HES (TURKON MNG ELEKT.) 15,68 HYDROLIC 126,00
SELEN ELEKTRİK (KEPEZKAYA HES) 28 HYDROLIC 124,00
SELİMOĞLU REG. VE HES 8,8 HYDROLIC 35
ULUABAT KUVVET TÜNELİ VE HES 48,51 HYDROLIC 372,00
ULUABAT KUVVET TÜNELİ VE HES (İlave) 48,51 HYDROLIC 372,00
297,57 HYDROLIC 1605
AKDENİZ ELEKTRİK (MERSİN RES) 33 WIND 100,00
UNFCCC/CCNUCC
CDM – Executive Board Page 79
BAKRAS EN. ELKT.ÜR. A.Ş. ŞENBÜK RES 15 WIND 47,00
BELEN ELEKTRİK (BELEN RES) (İlave) 6 WIND 19,00
BERGAMA RES EN. ÜR. A.Ş. ALİAĞA RES 52,5 WIND355,00
BERGAMA RES EN. ÜR. A.Ş. ALİAĞA RES 37,5 WIND
BOREAS ENERJİ (BOREAS I ENEZ RES) 15 WIND 49,00
KUYUCAK RES (ALİZE ENERJİ ÜR.) (İlave) 17,6 WIND110,00
KUYUCAK RES (ALİZE ENERJİ ÜRET.) 8 WIND
MAZI-3 RES ELEKTRİK (MAZI-3 RES) 7,5 WIND 26,25
ROTOR ELEKTRİK (OSMANİYE RES) 20 WIND
207,70ROTOR ELEKTRİK (OSMANİYE RES) 17,5 WIND
ROTOR ELEKTRİK (OSMANİYE RES) 17,5 WIND
SARES RES (GARET ENERJİ ÜRETİM) 15 WIND 60,00
SOMA ENERJİ ÜRETİM (SOMA RES) 4,5 WIND
114,00
SOMA ENERJİ ÜRETİM (SOMA RES) 7,2 WIND
SOMA ENERJİ ÜRETİM (SOMA RES) 7,2 WIND
SOMA ENERJİ ÜRETİM (SOMA RES) 6,3 WIND
SOMA ENERJİ ÜRETİM (SOMA RES) (İlave) 9 WIND
SOMA RES (BİLGİN RÜZGAR SAN) (İlave) 27,5 WIND
307,00SOMA RES (BİLGİN RÜZGAR SAN. EN.ÜR.) 32,5 WIND
SOMA RES (BİLGİN RÜZGAR SAN.)(İlave) 30 WIND
TURGUTTEPE RES (SABAŞ ELEKTRİK ÜR.) 22 WIND 64,00
ZİYARET RES (ZİYARET RES ELEK.)(İlave) 22,5 WIND140,00
ZİYARET RES (ZİYARET RES ELEKTRİK) 12,5 WIND
443,3 WIND 1598,95
MENDERES GEOTERMAL DORA-2 9,5 GEOTHERMAL 73
UNFCCC/CCNUCC
CDM – Executive Board Page 80
TUZLA JEOTERMAL 7,5 GEOTHERMAL 55
17 GEOTHERMAL 128
ITC ADANA BİOKÜTLE SANT. 11,32 WASTE 80
Total 3411,95
Electricity generation from capacity additions by fuel type
2012 2011 2010
HYDROLIC6922,17 1475,71 1057,33 9455,21
NATURAL GAS 11779,58 11505,26 235,6 23520,44
WIND 751,40 0,00 0 751,40
WASTE 433,72 119,91 0 553,63
GEOTHERMAL 382,00 150 0 532,00
FUEL OIL 0,00 1289,95 0 1289,95
LIGNITE 0 0 0 0,00
IMPORTED COAL+ASPHALTITE 720,97 4320,00 8011,80 13052,77
20989,84 18860,83 9304,73 49155,40
49155,40
UNFCCC/CCNUCC
CDM – Executive Board Page 81
OPERATING MARGIN CALCULATION
Heat values of fuel types for 2010-2012
Heat Value(Tcal) Heat Value (MJ)
Fuel Type 2010 2011 2012 2010 2011 2012
Hard Coal+ImportedCoal+Asphaltite
39.546 57.567 71.270 165462543448,00 240861457680,00 298194320152,00
Lignite 96.551 107.210 93.587 403969363080,00 448564673520,00 391566493392,00
Fuel Oil 8.569 5.280 5.625 35853227368,00 22090976080,00 23534012576,00
Diesel Oil 209 155 1.884 876472688,00 648854720,00 7881170680,00
LPG 0 0 0 0,00 0,00 0,00
Naphta 105 0 0 439859736,00 0,00 0,00
Natural Gas 194.487 202.064 203.766 813734674920,00 845436194400,00 852558500448,00
The consumption of fuel types between 2010-2012
FC (tonnes (gas: 103m3 ))
Fuel Type 2010 2011 2012
Hard Coal+ImportedCoal+Asphaltite 7419703,00 10574434,00 12258462,00
Lignite 56689392,00 61507310,00 55742463,00
Fuel Oil 891782 531608 564796
Diesel Oil 20354 15047 176379
LPG 0 0 0
Naphta 13140 0 0
Natural Gas 21783414 22804587 23090121
Electricity production from plants, low-cost/must-run production, its exclusion and share of it.
UNFCCC/CCNUCC
CDM – Executive Board Page 82
Electricity generation (GWh) 2008 2009 2010 2011 2012
Thermal Total 164139,3 156923,4 155827,6 171638,3 174871,7
Hydro+Jeothermal+Wind Total 34278,70 37889,50 55380,10 57756,80 64625,1
Turkey's Total 198418 194812,9 211207,7 229395,1 239496,8
Share of low-cost/must-runproduction 17,28 19,45 26,22 25,18 26,98
Average share (%) 22,03
Heat Values, FC, NCV and EFCO2, EG net+ import, simple operation margin CO2 emission factor values ofeach fuel source in 2010
Fuel typeFC (tonnes(gas: 103m3
))
Heat value(MJ)
NCV(MJ/kg)
EFCO2
(kg/TJ)
EFgrid,Omsimple,y
(tCO2/MWh)
HardCoal+ImportedCoal+Asphaltite
7419703,00 165462543448,00 22,30 92800,00 0,11
Lignite 56689392,00
403969363080,00 7,13 90900,00 0,31
Fuel Oil 891782 35853227368,00 40,20 75500,00 0,02
Diesel Oil 20354 876472688,00 43,06 72600,00 0,00
LPG 0 0,00 0,00 61600,00 0,00
Naphta 13140 439859736,00 33,47 69300,00 0,00
Natural Gas 21783414 813734674920,00 37,36 54300,00 0,31
TOTAL 0,75
Heat Values, FC, NCV and EFCO2, EG net+ import, simple operation margin CO2 emission factor values ofeach fuel source in 2011
UNFCCC/CCNUCC
CDM – Executive Board Page 83
Fuel typeFC
(tonnes(gas: 103m3 ))
Heat value(MJ)
NCV(MJ/kg)
EFCO2
(kg/TJ)
EFgrid,Omsimple,y
(tCO2/MWh)
HardCoal+ImportedCoal+Asphaltite
10574434,00 12258462,00 22,78 24,33 0,13
Lignite61507310,0
0 55742463,00 7,29 7,02 0,24
Fuel Oil 531608 564796 41,56 41,67 0,01
Diesel Oil 15047 176379 43,12 44,68 0,00
LPG 0 0 0,00 0,00 0,00
Naphta 0 0 1,00 0,00 0,00
Natural Gas 22804587 23090121 37,07 36,92 0,27
TOTAL 0.66
Heat Values, FC, NCV and EFCO2, EG net+ import, simple operation margin CO2 emission factor values ofeach fuel source in 2012
Fuel typeFC
(tonnes(gas: 103m3 ))
Heat value(MJ)
NCV(MJ/kg)
EFCO2
(kg/TJ)
EFgrid,Omsimple,y
(tCO2/MWh)
HardCoal+ImportedCoal+Asphaltite
12258462,00 33.310 24,33 92800,00 0,16
Lignite55742463,0
0 108.227 7,02 90900,00 0,21
Fuel Oil 564796 20.607 41,67 75500,00 0,01
Diesel Oil 176379 1.328 44,68 72600,00 0,00
LPG 0 0 0,00 61600,00 0,00
Naphta 0 113 0,00 69300,00 0,00
UNFCCC/CCNUCC
CDM – Executive Board Page 84
Natural Gas 23090121 189.057 36,92 54300,00 0,27
TOTAL 0,65
2010-2012 generation weighted average of simple operation margin CO2 emission factor
EF,grid,OMsimple,y(tCO2/MWh)
Year 2010 2011 2012
Total 0.75 0.66 0.65
3-year GenerationWeighted Average
(tCO2/MWh)0.685
BUILD MARGIN CALCULATION
Average CO2 emission factor, generation efficiency, CO2 emission factor by fuel type
EFCO2(kg/Tj)*
EFCO2
(t/Gj)
GenerationEfficiency (%)
EF EL,m,y
(tCO2/MWh)Fuel Type
Hard Coal+ImportedCoal+Asphaltite 92800,00 0,0928 0,390 0,8566
Lignite 90900,00 0,0909 0,390 0,8391
Fuel Oil 75500,00 0,0755 0,460 0,5909
Diesel Oil 72600,00 0,0726 0,460 0,5682
LPG 61600,00 0,0616 0,460 0,4821
Naphta 69300,00 0,0693 0,460 0,5423
Natural Gas 54300,00 0,0543 0,600 0,3258
Electricity generation, CO2 emission factor and build margin CO2 emission factor by fuel type
Generation EF,EL,m,y Emission by
UNFCCC/CCNUCC
CDM – Executive Board Page 85
(GWh) (tCO2/MWh) sourceHard Coal+Imported
Coal+Asphaltite13052,77 0,8566 11181,204
Lignite 0 0,8391 0
Fuel Oil 1289,95 0,5909 762,1922
Diesel Oil 0 0,5682 0LPG 0 0,4821 0
Naphta 0 0,5423 0
Natural Gas 23520,44 0,3258 7662,9594
TOTAL 49155.40 17,194.26
EF,grid,BM,y (tCO2/MWh) 0.3988
COMBINED MARGIN CALCULATION
Combined margin emission factor (EF,grid,CM,y) for projects other than solar and wind powergeneration activities
EF,grid ,OMsimple,y(tCO2/MWh) 0.685
EF,grid,BM,y(tCO2/MWh) 0.3988
EF,grid,CM,y(tCO2/MWh) 0.542
UNFCCC/CCNUCC
CDM – Executive Board Page 86
EMISSION REDUCTION CALCULATION
MW 1st crediting period
67,53 for 1 year for 7 years
period MWh t co2 tco2
1 540240 292837,93 2049865,498