Complete Streets Chicago: Data Driven Design
Luann Hamilton
Deputy Commissioner
AGENDA •Chicago’s goals • Complete Streets & Sustainable
Infrastructure Guides • Data-Driven Planning
• Setting goals • Scoping/research • Mapping • Informed design
• Priority Models • Mode Counts • Case Studies: using data for
complete streets
Why Complete Streets? • Health: support active
transportation and health, address obesity.
• Economy: draw people to shop, live, and work in walkable, livable communities.
• Safety: design to protect all users; reduce speeding and crashes.
• Changing Needs: Chicagoans driving less and using other modes
• Return on investment: create resilient, environmentally sound infrastructure that controls long term costs.
Driving is down; transportation choices up
Annual Vehicle Miles Traveled
Chicago Annual Vehicle Miles
CDOT Goals
• Eliminate pedestrian crash fatalities in ten years
• Reduce pedestrian and bike crash injuries 50% in five years
• Reach 50% of commute trips made by walking, biking, transit, and working from home by 2030 (currently 38%)
Modal Hierarchy: Pedestrian First
Project Delivery Process Stage 4: Construction: Ensure project is built as designed for complete streets
Stage 5: Measurement: Measure the effectiveness of complete streets
Stage 6: Maintenance: Ensure all users are accommodated through the project’s lifespan
1. Selection: Identify projects that advance complete streets
2. Scoping: Collect data, examine all modes, consider building and roadway form and function, review sustainability data
3. Design: Address objectives defined during scoping
4. Construction: Ensure project built as designed, for complete streets
5. Measurement: Evaluate effectiveness of complete streets
6. Maintenance: Ensure all users continue to be accommodated
Project Delivery Process – by Project Type Stage 4: Construction: Ensure project is built as designed for complete streets
Stage 5: Measurement: Measure the effectiveness of complete streets
Stage 6: Maintenance: Ensure all users are accommodated through the project’s lifespan
1. Project Selection Stage 4: Construction: Ensure project is built as designed for complete streets
Stage 5: Measurement: Measure the effectiveness of complete streets
Stage 6: Maintenance: Ensure all users are accommodated through the project’s lifespan
Select projects that advance complete, sustainable streets
• Rank projects based on Chicago Forward and complete streets opportunities • Safety First • Creating choices • Fuel the economy • Sustainable City
• Set numeric goals: How will we measure success?
2. Scoping Stage 4: Construction: Ensure project is built as designed for complete streets
Stage 5: Measurement: Measure the effectiveness of complete streets
Stage 6: Maintenance: Ensure all users are accommodated through the project’s lifespan
Collect data, examine modes, consider building and roadway form and function (typologies)
2.1 Establish goals
2.2 Research: crash reports, modal plans, relevant projects, developments, prior studies, public engagement
2.3 Conduct site visits; establish typologies
2.4 Assemble data, maps, analysis
2.5 Confirm modal hierarchy or request variance
2.6 Revisit goals
Research Before designing, consider:
Data Sets and Plans • Crash data, neighborhood plans,
environmental conditions, zoning plans and synergies
Building Form & Function • Land use, structures, regulatory
framework, businesses
Roadway Form & Function • Character of roadway, speeds,
number of lanes, users, parking demand, traffic operations
Special Designations • Statutory and operational categories
such as snow routes, Pedestrian Streets, bicycling spoke routes
Crash Data
Crash Maps
Mode Analysis Maps
Typology Maps
Upfront Planning & Data Driven Design Approach
Expanding data sets to measure success and inform future projects
Design based on data & research
Use existing and collect new data
Create data repository and capture collected data
Set performance metrics
Evaluate and monitor
3. Design Stage 4: Construction: Ensure project is built as designed for complete streets
Stage 5: Measurement: Measure the effectiveness of complete streets
Stage 6: Maintenance: Ensure all users are accommodated through the project’s lifespan
Meet goals from Initiation & Scoping
3.1 Draft alternatives & sustainable elements
3.2 Schematic Design
3.3 Evaluate Impacts: intersection design, signal timing, traffic impact, MMLOS
3.4 Obtain Feedback and Approvals
3.5 Final Design
Design Guidance Design Trees
Design Guidance Cross Section Elements
Stoop area Door Zone Yards Building Setbacks Walkways Trees Sidewalk Furniture Driveways
Curbs Bicycle Lanes Protected Bike Lanes Parking Turn Lanes
Landscaping Pedestrian Refuges Bus-rapid Transit Protected Bike Lanes Turn Lanes
Curbs Bicycle Lanes Protected Bike Lanes Parking Turn Lanes
Stoop area Door Zone Yards Building Setbacks Walkways Trees Sidewalk Furniture Driveways
Priority Models Safety Zones & Automated Speed Enforcement
Safety Zones
• 1500 prioritized locations across 6 zones
• Infrastructure improvements
• Automated speed enforcement in 10% of zones
1. # all vehicle crashes 2. # fatal/serious injury crashes 3. # youth under 18 crashes (x2) 4. # pedestrian & bicyclist crashes 5. # speed related crashes (x2) 6. High youth population
Speed Camera Priority Model
2012 Pilot Site Selection
Schools Parks
Claremont Academy Garfield
Disney Magnet School Humboldt
Hancock High School Washington
Pickard McKinley
Morgan Park High School Senn
Prosser Vocational High School Major Taylor
Pilot Site Selection Criteria • High Safety Zone Ranking • Geographic/City Region Distribution (2 zones per Region • School Park Balance (6 Schools/Parks • School Type Balance (3 Elementary/3 High School)
2012 Safety Zones 76 High Visibility Crosswalks
12 Pedestrian Countdown Timers
140 Safety Zone Stencils
13 Speed Feedback Signs
6 In-Street Stop for Pedestrian Signs
10 ADA Ramps
1 Lead Pedestrian Interval
1 Median Refuge Island
2013 Safety Zones
•50 sites for speed cameras • Selected based on priority model • Geographic/Region Distribution • “Spot Speed Studies” to identify camera sites within safety zone • 3-Year crash data analyzed for clustering of crashes, further focused camera site selection
2013 Work To Date
• Over 400 Crosswalks striped (or in planning)
• Approximately 100 “Safety Zone” Pavement Markings
• 20 Next Generation, Advanced Functionality Speed Feedback Signs to be installed
• Additional Improvements include In-Street Stop for Pedestrian Signs, Updated Speed Limit/Speed Zone signage at every Zone
2013 Safety Zone Improvements
High Visibility Crosswalk Safety Zone Stencils Speed Feedback Signs
2013 Safety Zone Improvements
Stop for Pedestrian Sign Safety Zone/Speed Signs
28
6 Locations: • Existing Bike Network • Potential Projects • Geographic Equity • Feasibility
Modal Data:
Monthly Bike Count
29
Monthly Bike Count
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec
2012 Ridership Year Trend During Peak Hours
Clark/Lincoln-Wells Milwaukee/Elston Jackson/Halsted Overall
30
Applying Data to Designs
South Chicago Ave. Safety Project CDOT is installing a safety project “road diet” on South Chicago Ave. A road diet removes
unnecessary travel lanes to make the street safer for all users. Road diets on streets with less than 20,000 motorists per day show improved safety and reduced speeding without delaying motor
vehicle travel.
• 12,300 motorists use South Chicago Avenue on an average day
• 80% of motorists observed were traveling faster than the posted speed limit
• 15% of motorists observed were traveling greater than 42mph Chance a person would survive if hit by a vehicle traveling this fast…
South Chicago Ave - Existing South Chicago Ave - Proposed
South Chicago Ave. at East End Ave.
Before
After
Vincennes Ave. Safety Project • 981 Crashes (5-year period)
• 21% resulted in injuries
• 100% of bike/ped crashes resulted in injuries
• 4 fatal crashes
• ‘Before’ Speed Data • 86% of NB & 63% of SB Motorists
speeding
• 41% of NB & 16% of SB motorists exceeding 40MPH
7 - 8AM Preliminary Speed Study
Before - 1/29/13 After - 10/3/13
# of Vehicles 718 681
Average Speed 38MPH 32MPH
# Over 30MPH 624 390
% Over 30MPH 87% 64%
# Over 35MPH 463 187
% Over 35MPH 64% 27%
# Over 40MPH 192 54
% Over 40MPH 27% 8%
Lawrence Ave. Streetscape
Neighborhood Context
Lawrence Avenue Streetscape
Existing Cross Section
Lawrence Avenue
Lawrence Avenue – Existing Conditions
Lawrence Avenue
Proposed Cross Section
Lawrence Avenue – Proposed Conditions
• Road Diet with wider sidewalks and continuous bike lanes
• Signal and Timing Improvements
• Street and Pedestrian Lighting
• New Sidewalks and ADA Ramps
• Decorative Stamped Crosswalks
• Permeable Pavers in Parkway
• Pedestrian Refuge Islands
Streetscape Enhancements
• Increased motorist travel times 3-9 mins (depending on time of day)
• Increased motorist times turning off/onto and crossing road • Queue lengths will increase at traffic signals, with the
heaviest at PM westbound rush hour. • During peak hours, traffic will backup through side streets.
• Increased potential of cut-through traffic by cars and delivery vans.
• Traffic calming elements (speed humps) exist on numerous side streets.
Lawrence Avenue – Driver Impact
Lawrence Ave. Streetscape
• Adjust traffic signal timings for through-traffic • All signals 85 seconds • Ped crossings 3.5 ft/second
• Major intersections maintain 4-lane cross sections • Provide center turn lane • Pedestrian refuge islands at non-signalized intersections • Bump-outs on side streets to reduce cut-through traffic • Buses pull over to allow through-traffic to pass • After presentation of trade offs between longer auto travel
times and complete streets design, overwhelming community support for road diet
Lawrence Avenue – Impact Mitigation
Foster Avenue – Road Diet?
21’ 21’
Existing Conditions
• Peak hour parking restrictions (7-9 AM eastbound, 4-6 PM westbound)
• Allows for 2-travel lanes in each direction
• 42’ pavement width curb-to-curb
• CTA bus stops
• 302 crashes ‘09-’11, including 87 speed, 48 youth, 18 bike/ped, 10 serious/fatal
42
24-Hour Average Daily Traffic (ADT)
NB = 20,600, SB = 22,500
Total = 43,200 vehicles
Lawrence Ave. Streetscape Foster Ave: Field Survey
• Expressway interchange generates heavy traffic
• Vehicles use all lanes
• Traffic backed up
• Data matches the field conditions
Road Diet Will it work here?
Source: A New Foster Avenue Facebook Page
Foster Avenue: Recommendations
• New Pavement and Pavement Markings
• High Visibility Crosswalks
• Pedestrian Signs
• Signal Modernization
• Speed Feedback Signs
• Automated Speed Enforcement
• First location in Chicago
• One month warning period: 53,474 warnings
• Citation qualifying events in first 9 days: 3818
Cycle Tracks-Measuring Results
46
1,509
2,139
0
500
1000
1500
2000
2500
May 2012 May 2013
Elston and Milwaukee
Elston and Milwaukee
198
347
0
50
100
150
200
250
300
350
400
May 2012 May 2013
Lake and Damen
Lake and Damen
Temperature May 2012: 50-55 deg. May 2013: 70-75 deg.
Cyc
le T
rack
Inst
all
Cyc
le T
rack
Inst
all
Pilot People Spots
47th & Greenwood 47th & Champlain
People Spots – Measuring Results
Before and After Ped Counts
Attitude and Behavior
• Sense of Community – 6.9 to 7.7 (scale of 1 to 10)
• Meeting City Green Objectives – Increased 23%
• Mode Share – 7% more walked – 17% more rode bikes – 5% fewer drove
• Activity Mapping – Greatly increased diversity of activities – +24% in sitting, +9% in socializing, +26% in eating and
drinking, +17% phone use
Wants a conclusion here
Dearborn Street Complete Street
Dearborn Street - Before Dearborn Street - After