complete pmp exam review cards
TRANSCRIPT
-
7/31/2019 Complete Pmp Exam Review Cards
1/140
-
7/31/2019 Complete Pmp Exam Review Cards
2/140
-
7/31/2019 Complete Pmp Exam Review Cards
3/140
Project IntegrationManagement
Project PlanDevelopment
Integrated ChangeControl?
Why is historicalinformation usefulin developing the
project plan?
Constraints Project PlanningMethodology?
Project Plan Work AuthorizationSystem?
Work Results?
How is the projectplan used to in
integrated changecontrol?
-
7/31/2019 Complete Pmp Exam Review Cards
4/140
The processesrequired to ensure
that various elementsof the project are
properly coordinated.
Taking results of otherplanning processes
and putting them intoa coherent, consistent
document.
Coordinatingchanges across the
entire project.
Because it helpsverify assumptions
and assessidentified
alternatives.
Factors that limitthe project
management team'soptions.
Any structuredapproach to guidethe project team in
the development of a
project plan.
A formal, approveddocument used to
manage and controlproject execution.
A formal procedure tosanction project work
so that it is done atthe proper time and in
the proper sequence.
Outcomes ofactivities performedto accomplish the
project.
The project planprovides the
baseline againstwhich all changes
are controlled.
-
7/31/2019 Complete Pmp Exam Review Cards
5/140
What is required inthe decision
making process?Llife-Cycle Costing
Line Manager MatrixOrganization?
Network Logic? OrganizationPlanning
ParametricEstimating Pareto Diagram
Work Package Work BreakdownStructure
-
7/31/2019 Complete Pmp Exam Review Cards
6/140
Analyzing theproblem to identify
viable solutions andthen making a choice
from among them.
The concept ofincluding acquisition,
operating, and disposalcosts when evaluating
various alternatives.
The manager of anygroup that actuallymakes a product orperforms a service.
Also called a functional
manager.
Any organization structure inwhich the project manager
shares responsibility with thefunctional managers for
assigning priorities and fordirecting the work of individuals
assigned to the project.
Any continuousseries of connectedactivities in a project
network diagram.
Identifying,documenting, and
assigning project roles,responsibilities, and
reporting relationships.
An estimating techniquethat uses a statisticalrelationship between
historical data and othervariables to calculate an
estimate.
A histogram, ordered byfrequency of
occurrence, that showshow many results were
generate by each
identified cause.
A deliverable at thelowest level of the WorkBreakdown Structure. A
work package may bedivided into activities.
A task oriented structure thatorganizes and defines total
work to be accomplished in aproject. Each level represents
an increasingly detaileddefinition of a project
component.
-
7/31/2019 Complete Pmp Exam Review Cards
7/140
Float / Slack Critical PathMethod(CPM)
Backward Pass Corrective Action
Budgeted Cost ofWork Scheduled
(BCWS)Baseline
Arrow DiagrammingMethod (ADM)
AdministrativeClosure
Backward Pass Activity
-
7/31/2019 Complete Pmp Exam Review Cards
8/140
The amount of time that an activitymay be delayed from its early start
date without delaying the projectfinish date. Float is a arithmetic
calculation and can change as theproject progresses and changes
are made to the project plan. Also
called slack.
A network analysis techniqueused to predict project
duration by analyzing whichsequence of tasks has theleast amount of scheduling
flexibility (i.e. the least amount
of float).
The calculation of late finishdates and late start dates for
the uncompleted portions of allnetwork activities. Determinedby working backwards through
the network logic from the
project's end date.
Changes made tobring expected future
performance of theproject into line with
the project plan.The sum of the approved cost
estimates (including anyoverhead allocation) foractivities (or portions of
activities) scheduled to beperformed during a given period
(usually project-to-date).
"The original plan (for a project,a work package, or an activity),
plus or minus approvedchanges. Usually used with amodifier (e.g., cost baseline,
schedule baseline, performance
measurement baseline)."
A network diagramming technique inwhich activities are represented by
arrows. The tail of the arrowrepresents the start and the head
represents the finish of the activity.Activities are connected at points
called nodes to illustrate the sequencein which the activities are expected to
be performed.
"Generating, gathering,and disseminating
information to formalizeproject completion."
The calculation of late finish dates andlate start dates for the uncompleted
portions of all network activities.Determined by working backwardsthrough the network logic from the
projects end date. The end date maybe calculated in a forward pass or set
by the customer or sponsor.
"An element of work performedduring the course of a project.
An activity normally has anexpected duration, an expected
cost, and expected resourcerequirements. Activities areoften subdivided into tasks."
-
7/31/2019 Complete Pmp Exam Review Cards
9/140
Activity Definition Activity Description
Activity DurationEstimating
Cost of WorkPerformed (ACWP)
Actual Finish Date Actual Start Date
AdministractiveClosure Application Area
Bar Chart Baseline
-
7/31/2019 Complete Pmp Exam Review Cards
10/140
Identifying the specificactivities that must beperformed in order toproduce the various
project deliverables.
A short phrase or labelused in a project network
diagram. The activitydescription normally
describes the scope of
work of the activity.
Estimating thenumber of work
periods which will beneeded to complete
individual activities.
Total costs incurredin accomplishing
work during a giventime period.
The point in timethat work actually
ended on anactivity.
The point in timethat work actually
started on anactivity.
"Generating, gathering,and disseminating
information to formalizeproject completion."
A category of projects that havecommon elements not present
in all projects. Application areasare usually defined in terms of
either the product of theproject. Application areas often
overlap.
"A graphic display of schedule-relatedinformation. In the typical bar chart,
activities or other project elements arelisted down the left side of the chart,dates are shown across the top, and
activity durations are shown asdate-placed horizontal bars. Also
called a Gantt chart."
"The original plan (for a project,a work package, or an activity),
plus or minus approvedchanges. Usually used with amodifier (e.g., cost baseline,
schedule baseline, performancemeasurement baseline)."
-
7/31/2019 Complete Pmp Exam Review Cards
11/140
Work Package Word BreakdownStructure
Workaround Total QualityManagement (TQM)
Target Start Date(TS)
Target Finish Date(TF)
Time-ScaledNetwork Diagram Team Development
Target CompletionDate (TC) Successor Activity
-
7/31/2019 Complete Pmp Exam Review Cards
12/140
A deliverable at thelowest level of the workbreakdown structure. Awork package may bedivided into activities.
A deliverable-orientedgrouping of project
elements whichorganizes and definesthe total scope of the
project.
A response to a negative riskevent. Distinguished fromcontingency plan in that a
workaround is not planned inadvance of the occurrence of
the risk event.
A common approachto implementing a
quality improvementprogram within an
organization.
The date work isplanned (targeted)
to start on anactivity.
The date work isplanned (targeted)
to finish on anactivity.
Any project network diagramdrawn in such a way that thepositioning and length of the
activity represents itsduration. Essentially, it is a
bar chart that includesnetwork logic.
Developingindividual and group
skills to enhanceproject performance.
An imposed datewhich constrains orotherwise modifies
the network
analysis.
(1) In the arrowdiagramming method, theactivity which departs a
node. (2) In theprecedence diagramming
method, the to activity.
-
7/31/2019 Complete Pmp Exam Review Cards
13/140
Subnet Statement of Work(SOW)
Start Date Stakeholder
Staff Acquisition Source Selection
SolicitationPlanning
What is ProjectRisk Management?
How is Monte Carloanalysis used in
schedulesimulations?
What is thedifference between
a risk and aproblem?
-
7/31/2019 Complete Pmp Exam Review Cards
14/140
A subdivision of aproject networkdiagram usually
representing some
form of subproject.
A narrativedescription of
products or servicesto be supplied under
contract.A point in time associated with
an activitys start, usuallyqualified by one of the
following: actual, planned,estimated, scheduled, early,
late, target, baseline, or
current.
Individuals andorganizations whoare involved in or
may be affected by
project activities.Getting the humanresources neededassigned to andworking on the
project.
Choosing fromamong potential
contractors.
Documentingproduct
requirements andidentifying potential
sources.
The process concerned withidentifying, analyzing, and
responding to project risk. Italso includes maximizing the
results of positive events as wellas minimizing the consequences
of adverse events to project
objectives.
To perform the projectmany times in order to
provide a statisticaldistribution of thecalculated results.
A risk is a futureevent; it has not yet
occurred. A problem,on the other hand,
currently exists.
-
7/31/2019 Complete Pmp Exam Review Cards
15/140
Solicitation Should-CostEstimates
Scope Verification Scope Planning
Scope Definition Scope ChangeControl
Scope Change Scope
Scheduled StartDate (SS)
Scheduled FinishDate (SF)
-
7/31/2019 Complete Pmp Exam Review Cards
16/140
Obtainingquotations, bids,
offers, or proposalsas appropriate.
An estimate of the cost ofa product or service usedto provide an assessmentof the reasonableness of a
prospective contractors
proposed cost.
Ensuring that allidentified projectdeliverables havebeen completed
satisfactorily.
Developing a writtenscope statement thatincludes the project
justification, the majordeliverables, and the
project objectives.Decomposing the major
deliverables intosmaller, moremanageable
components to provide
better control.
Controllingchanges to project
scope.
Any change to theproject scope. A scopechange almost alwaysrequires an adjustment
to the project cost or
schedule.
The sum of theproducts andservices to beprovided as a
project.The point in time work was
scheduled to start on anactivity. The scheduled start
date is normally within therange of dates delimited bythe early start date and the
late start date.
The point in time work wasscheduled to finish on an
activity. The scheduled finishdate is normally within the
range of dates delimited bythe early finish date and the
late finish date.
-
7/31/2019 Complete Pmp Exam Review Cards
17/140
Schedule Variance(SV)
SchedulePerformance Index
(SPI)
ScheduleDevelopment Schedule Control
S-Curve Risk ResponseDevelopment
Risk ResponseControl
What type of changeconstitutes one ofthe major areas of
cost growth?
What is privity ofcontract?
What are thecharacteristics of awell-written SOW?
-
7/31/2019 Complete Pmp Exam Review Cards
18/140
(1) Any difference betweenthe scheduled completion
of an activity and theactual completion of that
activity. (2) In earned
value, BCWP less BCWS.
The ratio of workperformed to work
scheduled(BCWP/BCWS).
Analyzing activitysequences, activity
durations, and resourcerequirements to create
the project schedule.
Controllingchanges to the
project schedule.
Graphic display of cumulative costs,labor hours, or other quantities,
plotted against time. The name derivesfrom the S-like shape of the curve(flatter at the beginning and end,
steeper in the middle) produced on aproject that starts slowly, accelerates,
and then tails off.
Definingenhancement steps
for opportunities andmitigation steps for
threats.
Responding tochanges in risk
over the course ofthe project.
Change to projectscope.
A doctrine of law thatrecognizes the
contractual relationshipexisting between abuyer and its prime
contractor.
The SOW shoulbe beclear, complete, and
concise and include adescription of anycollateral services
required.
-
7/31/2019 Complete Pmp Exam Review Cards
19/140
Risk Quantification Risk Identification
Risk Event Retainage
ResponsibilityAssignment Matrix
(RAM)Resource Planning
Resource-LimitedSchedule Resource Leveling
Reserve Request forQuotation (RFQ)
-
7/31/2019 Complete Pmp Exam Review Cards
20/140
Evaluating theprobability of riskevent occurrence
and effect.
Determining whichrisk events are
likely to affect theproject.
A discreteoccurrence that mayaffect the project for
better or worse.
A portion of a contractpayment that is held
until contractcompletion in order to
ensure full performance
of the contract terms.A structure which relates theproject organization structure
to the work breakdownstructure to help ensure thateach element of the projects
scope of work is assigned to a
responsible individual.
Determining whatresources (people,
equipment, materials)are needed in what
quantities to perform
project activities.A project schedule whose
start and finish datesreflect expected resource
availability. The finalproject schedule should
always be resource-limited.
Any form of network analysis inwhich scheduling decisions
(start and finish dates) are drivenby resource management
concerns (e.g., limited resourceavailability or difficult-to-manage
changes in resource levels).
A provision in the project plan tomitigate cost and/or schedule risk.
Often used with a modifier (e.g.,management reserve, contingency
reserve) to provide further detail onwhat types of risk are meant to be
mitigated. The specific meaning of themodified term varies by application
area.
Generally, this term isequivalent to request for
proposal. However, insome application areas itmay have a narrower or
more specific meaning.
-
7/31/2019 Complete Pmp Exam Review Cards
21/140
Request forProposal (RFP)
Remaining Duration(RDU)
Quality Planning Quality Control(QC)
Quality Assurance(QA)
ProjectizedOrganization
Project TimeManagement
As a PMP, what laws,regulations, and
ethical standardsgovern your
professional practice?
What is meantwhen someone is
said to beethnocentric?
What are the twoways project
resources areobtained?
-
7/31/2019 Complete Pmp Exam Review Cards
22/140
A type of bid document usedto solicit proposals from
prospective sellers ofproducts or services. In someapplication areas it may havea narrower or more specific
meaning.
The time needed tocomplete an
activity.
Identifying whichquality standards arerelevant to the projectand determining how
to satisfy them.
(1) The process of monitoring specificproject results to determine if they
comply with relevant quality standardsand identifying ways to eliminate
causes of unsatisfactory performance.(2) The organizational unit that isassigned responsibility for quality
control.
(1) The process of evaluatingoverall project performance on a
regular basis to provideconfidence that the project will
satisfy the relevant qualitystandards. (2) The organizational
unit that is assigned responsibility
for quality assurance.
Any organizational structurein which the project manager
has full authority to assignpriorities and to direct the
work of individuals assignedto the project.
A subset of project management thatincludes the processes required to
ensure timely completion of theproject. It consists of activity
definition, activity sequencing, activityduration estimating, schedule
development, and schedule control.
Those of the state orprovince and/or
country where youprovide project
management services.
A belief in theinherent superiority
of one's ownculture.
Staff acquisitionand procurement.
-
7/31/2019 Complete Pmp Exam Review Cards
23/140
What are the twoways project
resources areobtained?
Project TeamMembers
Project Schedule Project RiskManagement
Project QualityManagement
ProjectProcurementManagement
Project Planning Project PlanExecution
Project PlanDevelopment Project Plan
-
7/31/2019 Complete Pmp Exam Review Cards
24/140
Staff acquisitionand procurement.
A subset of project management thatincludes the processes required to
ensure that the project includes all ofthe work required, and only the work
required, to complete the projectsuccessfully. It consists of initiation,
scope planning, scope definition,scope verification, and scope change
control.
The planned datesfor performing
activities and theplanned dates for
meeting milestones.
A subset of project managementthat includes the processesconcerned with identifying,
analyzing, and responding toproject risk. It consists of risk
identification, risk quantification,risk response development, and
risk response control.
A subset of project managementthat includes the processesrequired to ensure that the
project will satisfy the needs forwhich it was undertaken. It
consists of quality planning,quality assurance, and quality
control.
A subset of project management thatincludes the processes required toacquire goods and services from
outside the performing organization. Itconsists of procurement planning,solicitation planning, solicitation,
source selection, contractadministration, and contract close-out.
The developmentand maintenance of
the project plan.
Carrying out theproject plan byperforming the
activities included
therein.Taking the results of
other planningprocesses and puttingthem into a consistent,
coherent document.
A formal, approved document used toguide both project execution and
project control. The primary uses of theproject plan are to document planning
assumptions and decisions, to facilitatecommunication among stakeholders,
and to document approved scope, cost,and schedule baselines. A project plan
may be summary or detailed.
-
7/31/2019 Complete Pmp Exam Review Cards
25/140
Project Phase Project NetworkDiagram
Project Manager(PM)
ProjectManagement Team
ProjectManagement
Software
ProjectManagement
Professional (PMP)
ProjectManagement Body
of Knowledge(PMBOK)
ProjectManagement (PM)
Project Life Cycle Project IntegrationManagement
-
7/31/2019 Complete Pmp Exam Review Cards
26/140
A collection of logicallyrelated project activities,
usually culminating inthe completion of amajor deliverable.
Any schematic display of thelogical relationships of projectactivities. Always drawn fromleft to right to reflect project
chronology. Often incorrectlyreferred to as a PERT chart.
The individualresponsible for
managing a project.
The members of the project teamwho are directly involved in
project management activities.On some smaller projects, theproject management team may
include virtually all of the projectteam members.
A class of computerapplications specifically
designed to aid withplanning and controlling
project costs and
schedules.
An individualcertified as such by
the ProjectManagement
Institute.An inclusive term that describes the sum ofknowledge within the profession of project
management. As with other professionssuch as law, medicine, and accounting, the
body of knowledge rests with thepractitioners and academics who apply andadvance it. The PMBOK includes proven,
traditional practices which are widelyapplied as well as innovative and advanced
ones which have seen more limited use.
The application of knowledge,skills, tools, and techniques
toproject activities in order tomeet or exceed stakeholder
needs and expectations froma project.
A collection of generallysequential project phases
whose name and number aredetermined by the control
needs of the organization ororganizations involved in the
project.
A subset of project management thatincludes the processesrequired to
ensure that the various elements ofthe project are properly coordinated.
It consists of project plandevelopment, project plan execution,
and overall change control.
-
7/31/2019 Complete Pmp Exam Review Cards
27/140
Project HumanResource
Management
Project CostManagement
ProjectCommunications
ManagementProject Charter
ProjectProgram Evaluation
and ReviewTechnique (PERT)
Program ProcurementPlanning
PredecessorActivity
PrecedenceRelationship
-
7/31/2019 Complete Pmp Exam Review Cards
28/140
A subset of project managementthat includes the processesrequired to make the mosteffective use of the peopleinvolved with the project. Itconsists of organizational
planning, staff acquisition, and
team development.
A subset of project managementthat includes the processesrequired to ensure that the
project is completed within theapproved budget. It consists of
resource planning, costestimating, cost budgeting, and
cost control.
A subset of project management thatincludes the processes required to
ensure proper collection anddissemination of project information. Itconsists of communications planning,information distribution, performancereporting, and administrative closure.
A document issued by seniormanagement that provides
the project manager with theauthority to apply
organizational resources toproject activities.
A temporaryendeavor
undertaken to createa unique product or
service.
An event-oriented network analysistechnique used to estimate project
duration when there is a high degreeof uncertainty with the individualactivity duration estimates. PERT
applies the critical path method to aweighted average duration estimate.
Also given as Program Evaluation and
Review Technique.
A group of relatedprojects managed in a
coordinated way.Programs usually
include an element of
ongoing activity.
Determining whatto procure and
when.
(1) In the arrowdiagramming method, the
activity which enters anode. (2) In the precedencediagramming method, the
from activity.
The term used in the precedencediagramming method for a
logical relationship. In currentusage, however, precedence
relationship, logical relationship,and dependency are widely used
interchangeably regardless of
the diagramming method in use.
-
7/31/2019 Complete Pmp Exam Review Cards
29/140
PrecedenceDiagrammingMethod (PDM)
PERT Chart
PerformingOrganization
PerformanceReporting
Percent Complete(PC) Path Convergence
Path Pareto Diagram
ParametricEstimating
Overall ChangeControl
-
7/31/2019 Complete Pmp Exam Review Cards
30/140
A network diagrammingtechnique in which activities are
represented by boxes (ornodes). Activities are linked by
precedence relationships toshow the sequence in which the
activities are to be performed.
A specific type ofproject network
diagram.
The enterprisewhose employeesare most directly
involved in doing the
work of the project.
Collecting anddisseminating
information aboutproject performance to
help ensure project
progress.An estimate, expressed
as a percent, of theamount of work whichhas been completed onan activity or group of
activities.
In mathematical analysis,the tendency of parallelpaths of approximately
equal duration to delay thecompletion of the
milestone where they meet.
A set of sequentiallyconnected activitiesin a project network
diagram.
A histogram, ordered byfrequency of
occurrence, that showshow many results were
generated by each
identified cause.An estimating technique thatuses a statistical relationshipbetween historical data andother variables (e.g., square
footage in construction, lines ofcode in software development)
to calculate an estimate.
Coordinatingchanges across the
entire project.
-
7/31/2019 Complete Pmp Exam Review Cards
31/140
OrganizationalPlanning
OrganizationalBreakdown
Structure (OBS)
Node Network Path
Network Logic Network Analysis
Near-CriticalActivity
Monte CarloAnalysis
Monitoring Modern ProjectManagement (MPM)
-
7/31/2019 Complete Pmp Exam Review Cards
32/140
Identifying,documenting, and
assigning project roles,responsibilities,and
reporting relationships.
A depiction of theproject organization
arranged so as torelate work packages
to organizational units.One of the defining points of a
network; a junction pointjoined to some or all of the
other dependency lines. Seealso arrow diagrammingmethod and precedence
diagramming method.
Any continuousseries of connectedactivities in a project
network diagram.
The collection ofactivity
dependencies thatmake up a project
network diagram.
The process ofidentifying early andlate start and finish
dates for theuncompleted portions of
project activities.
An activity that haslow total float.
A schedule risk assessmenttechnique that performs a
project simulation many timesin order to calculate a
distribution of likely results.
The capture,analysis, and
reporting of projectperformance, usually
as compared to plan.
A term used to distinguish thecurrent broad range of project
management (scope, cost,time, quality, risk, etc.) from
narrower, traditional use thatfocused on cost and time.
-
7/31/2019 Complete Pmp Exam Review Cards
33/140
Mitigation Milestone Schedule
Milestone Matrix Organization
Master Schedule ManagementReserve
Loop Start-to-finish
Start-to-start Finish-to-finish
-
7/31/2019 Complete Pmp Exam Review Cards
34/140
Taking steps to lessenrisk by lowering theprobability of a risk
events occurrence orreducing its effect
should it occur.
A summary-levelschedule which
identifies the majormilestones. See also
master schedule.
A significant event inthe project, usually
completion of amajor deliverable.
Any organizational structure inwhich the project manager
shares responsibility with thefunctional managers for
assigning priorities and fordirecting the work of individuals
assigned to the project.
A summary-levelschedule which
identifies the majoractivities and key
milestones.
A separately planned quantity used toallow for future situations which areimpossible to predict. Management
reserves may involve cost or schedule.Management reserves are intended to
reduce the risk of missing cost orschedule objectives. Use of
management reserve requires a
change to the projects cost baseline.
A network path that passesthe same node twice. Loops
cannot be analyzed usingtraditional network analysis
techniques such as CPM andPERT. Loops are allowed in
GERT.
the from activitymust start before
the to activity canfinish
the from activitymust start before
the to activity canstart
the from activitymust finish before
the to activity canfinish
-
7/31/2019 Complete Pmp Exam Review Cards
35/140
Finish-to-startThe four possible
types of logicalrelationships
LogicalRelationship Line Manager
Why is the type oforganizational
structure importantin project
management?
When is the projectteam directory
developed?
Which type ofpower should a
project manageravoid?
Which type ofpower should a
project manageruse?
What are the fivemethods of dealing
with conflict?
What is the highestlevel of need's in
Maslow's hierarchyof needs?
-
7/31/2019 Complete Pmp Exam Review Cards
36/140
the from activitymust finish before
the to activity canstart
Finish-to-start,Finish-to-finish,
Start-to-start,Start-to-finish
A dependencybetween two projectactivities, or betweena project activity and
a milestone.
(1) The manager of anygroup that actuallymakes a product or
performs a service. (2)A functional manager.
The structure of theorganization often
constrains theavailability under which
resources become
available to the project.
As part of the staffacquisition phase
of the project.
Avoid usingcoercive power.
Should try to usereward and expert
powers.
Smoothing,Withdrawl,
Compromise,Forcing and Problem
Solving
Self-fulfillment throughthe development of
powers and skills, anda chance to use
creativity.
-
7/31/2019 Complete Pmp Exam Review Cards
37/140
SmoothingWhat use does a
Gantt Chartprovide?
What is life-cyclecosting?
What is a variablecost?
How is the costperformance index
(CPI) figured?
Define what apayback period is?
What is internalrate of return (IRR)?
What is BCWS orPV?
How is schedulevariance (SV)
figured?
What are directcosts?
-
7/31/2019 Complete Pmp Exam Review Cards
38/140
Deemphasizing theopponents' differencesand emphasizing their
commonalities over
the issues in question.
To identify when aparticular resource
is (or will be)working on a
particular task.The concept of
including acquisition,operating, and disposalcosts when evaluating
various alternatives.
Costs that risedirectly with the
size of the project.
CPI = BCWP /ACWPor EV / AC
The number of times periodsup to the point at which
cumulative revenues exceedcumulative costs and,
therefore, the project hasturned a profit.
The percentage ratethat makes the presentvalue of costs equal to
the present value ofbenefits.
Budgeted cost ofwork scheduled or
planned value.
SV = BCWP - BCWSor EV - PV
Costs incurreddirectly by a
specific project.
-
7/31/2019 Complete Pmp Exam Review Cards
39/140
Level of Effort(LOE) Lead
Late Start Date (LS) Late Finish Date(LF)
Lag Invitation for Bid(IFB)
Initiation InformationDistribution
Hanger Hammer
-
7/31/2019 Complete Pmp Exam Review Cards
40/140
Support-type activity (e.g.,vendor or customer liaison) that
does not readily lend itself tomeasurement of discrete
accomplishment. It is generallycharacterized by a uniform rateof activity over a specific period
of time.
A modification of a logicalrelationship which allows an
acceleration of the successortask. For example, in a
finish-to-start dependency with a10-day lead, the successor
activity can start 10 days before
the predecessor has finished.
In the critical path method, thelatest possible point in timethat an activity may begin
without delaying a specifiedmilestone (usually the project
finish date).
In the critical path method, thelatest possible point in time
that an activity may becompleted without delaying aspecified milestone (usually
the project finish date).
A modification of a logicalrelationship which directs a
delay in the successor task. Forexample, in a finish-to-start
dependency with a 10-day lag,the successor activity cannot
start until 10 days after the
predecessor has finished.
Generally, this term isequivalent to request for
proposal. However, insome application areas itmay have a narrower or
more specific meaning.
Committing theorganization tobegin a project
phase.
Making neededinformation available
to projectstakeholders in a
timely manner.An unintended break ina network path. Hangers
are usually caused bymissing activities or
missing logical
relationships.
An aggregate or summaryactivity (a group of related
activities is shown as one andreported at a summary level).A hammock may or may nothave an internal sequence.
-
7/31/2019 Complete Pmp Exam Review Cards
41/140
GraphicalEvaluation and
Review Technique(GERT)
Grade
FunctionalOrganization Functional Manager
Free Float (FF) Forward Pass
FloatFixed Price
Incentive Fee (FPIF)Contract
Firm Fixed Price(FFP) Contract Finish Date
-
7/31/2019 Complete Pmp Exam Review Cards
42/140
A network analysis techniquethat allows for conditional and
probabilistic treatment oflogical relationships (i.e.,
some activities may not beperformed).
A category or rank used todistinguish items that have the
same functional use (e.g.,hammer) but do not share thesame requirements for quality(e.g., different hammers mayneed to withstand different
amounts of force).
An organization structure inwhich staff are grouped
hierarchically by specialty (e.g.,production, marketing,
engineering, and accounting atthe top level; with engineering,further divided into mechanical,
electrical, and others).
A manager responsible foractivities in a specializeddepartment or function
(e.g., engineering,manufacturing,
marketing).The amount of time anactivity can be delayed
without delaying theearly start of any
immediately following
activities.
The calculation of theearly start and earlyfinish dates for the
uncompleted portions ofall network activities.
The amount of time that an activitymay be delayed from its early startwithout delaying the project finish
date. Float is a mathematicalcalculation and can change as the
project progresses and changes aremade to the project plan. Also called
slack, total float, and path float.
A type of contract where thebuyer pays the seller a setamount (as defined by the
contract), and the seller canearn an additional amount if it
meets defined performancecriteria.
A type of contract wherethe buyer pays the sellera set amount (as defined
by the contract)regardless of the sellers
costs.
A point in time associated withan activitys completion.
Usually qualified by one of thefollowing: actual, planned,
estimated, scheduled, early,late, baseline, target or
current.
-
7/31/2019 Complete Pmp Exam Review Cards
43/140
Fast Tracking Expected MonetaryValue
Exception Report Event-on-Node
Estimate ToComplete (ETC)
Estimate AtCompletion (EAC)
Estimate Effort
Earned Value (EV) Early Start Date(ES)
-
7/31/2019 Complete Pmp Exam Review Cards
44/140
Compressing the projectschedule by overlapping
activities that would normallybe done in sequence, such as
design and construction.Sometimes confused with
concurrent engineering.
The product of an eventsprobability of occurrence and the
gain or loss that will result. Forexample, if there is a 50 percent
probability that it will rain, and rainwill result in a $100 loss, the
expected monetary value of the
rain event is $50 (.5 x $100).
Document thatincludes only majorvariations from plan
(rather than all
variations).
A network diagrammingtechnique in which events are
represented by boxes (or nodes)connected by arrows to show
the sequence in which theevents are to occur. Used in theoriginal Program Evaluation and
Review Technique.
The expected additional costneeded to complete an activity, agroup of activities, or the project.Most techniques for forecastingETC include some adjustment to
the original estimate based onproject performance to date.
The expected total cost of an activity, agroup of activities, or of the project when
the defined scope of work has beencompleted. Most techniques for
forecasting EAC include some adjustmentof the original cost estimate based on
project performance to date. Also shown asestimated at completion. Often shown as
EAC = Actuals-to-date + ETC.
An assessment of the likely quantitativeresult. Usually applied to project costs anddurations and should always include someindication of accuracy (e.g., x percent).
Usually used with a modifier (e.g.,preliminary, conceptual, feasibility). Someapplication areas have specific modifiers
that imply particular accuracy ranges (e.g.,order-of-magnitude estimate, budget
estimate, and definitive estimate in
engineering and construction projects).
The number of labor unitsrequired to complete anactivity or other project
element. Usually expressed asstaffhours, staffdays, or
staffweeks. Should not beconfused with duration.
(1) A method for measuring projectperformance. It compares the amount of work
that was planned with what was actuallyaccomplished to determine if cost and scheduleperformance is as planned. See also actual cost
of work performed, budgeted cost of workscheduled, budgeted cost of work performed,
cost variance, cost performance index, schedulevariance, and schedule performance index. (2)
The budgeted cost of work performed for an
activity or group of activities.
In the critical path method, the earliestpossible point in time on which the
uncompleted portions of an activity (orthe project) can start, based on the
network logic and any scheduleconstraints. Early start dates can
change as the project progresses andchanges are made to the project plan.
-
7/31/2019 Complete Pmp Exam Review Cards
45/140
Early Finish Date(EF)
DurationCompression
Duration Dummy Activity
Deliverable Data Date
Current Start Date Current Finish Date
Critical PathMethod (CPM) Critical Path
-
7/31/2019 Complete Pmp Exam Review Cards
46/140
In the critical path method, the earliestpossible point in time on which the
uncompleted portions of an activity (orthe project) can finish based on the
network logic and any scheduleconstraints. Early finish dates can
change as the project progresses andchanges are made to the project plan.
Shortening the projectschedule without reducingthe project scope. Durationcompression is not always
possible and often requires
an increase in project cost.
The number of work periods (notincluding holidays or other
non-working periods) required tocomplete an activity or other project
element. Usually expressed asworkdays or workweeks. Sometimesincorrectly equated with elapsed time.
An activity of zero duration used toshow a logical relationship in the
arrow diagramming method. Dummyactivities are used when logical
relationships cannot be completely orcorrectly described with regular
activity arrows. Dummies are showngraphically as a dashed line headed by
an arrow.
Any measurable, tangible, verifiableoutcome, result, or item that must be
produced to complete a project or partof a project. Often used more narrowlyin reference to an external deliverable,which is a deliverable that is subject to
approval by the project sponsor orcustomer.
The point in time thatseparates actual
(historical) data fromfuture (scheduled) data.
Also called as-of date.
The current estimateof the point in time
when an activity willbegin.
The current estimateof the point in time
when an activity willbe completed.
A network analysis technique used topredict project duration by analyzing whichsequence of activities (which path) has theleast amount of scheduling flexibility (the
least amount of float). Early dates arecalculated by means of a forward pass
using a specified start date. Late dates arecalculated by means of a backward passstarting from a specified completion date
(usually the forward passs calculated
project early finish date).
In a project network diagram, the series ofactivities which determines the earliest
completion of the project. The critical path willgenerally change from time to time as activities
are completed ahead of or behind schedule.Although normally calculated for the entire
project, the critical path can also be determinedfor a milestone or subproject. The critical path isusually defined as those activities with float less
than or equal to a specified value, often zero.
-
7/31/2019 Complete Pmp Exam Review Cards
47/140
Critical Activity Crashing
Cost Variance (CV) Cost Plus IncentiveFee (CPIF) Contract
Cost Plus Fixed Fee(CPFF) Contract
Cost PerformanceIndex (CPI)
Cost of Quality Cost Estimating
Cost Control Cost Budgeting
-
7/31/2019 Complete Pmp Exam Review Cards
48/140
Any activity on a critical path.Most commonly determined byusing the critical path method.Although some activities are
critical in the dictionary sensewithout being on the critical path,
this meaning is seldom used in
the project context.
Taking action to decrease thetotal project duration after
analyzing a number ofalternatives to determine howto get the maximum duration
compression for the least
cost.
(1) Any differencebetween the estimated
cost of an activity and theactual cost of that
activity. (2) In earned
value, BCWP less ACWP.
A type of contract where thebuyer reimburses the seller
for the sellers allowable costs(allowable costs are defined
by the contract), and the sellerearns its profit if it meets
defined performance criteria.
A type of contract where thebuyer reimburses the seller
for the sellers allowablecosts (allowable costs are
defined by the contract) plus afixed amount of profit (fee).
The ratio of budgeted costs toactual costs (BCWP/ACWP). CPI
is often used to predict themagnitude of a possible costoverrun using the following
formula: original costestimate/CPI = projected cost at
completion.
The costs incurred toensure quality. The cost
of quality includesquality planning, quality
control, quality
assurance, and rework.
Estimating the costof the resources
needed to completeproject activities.
Controllingchanges to theproject budget.
Allocating the costestimates to
individual projectcomponents.
-
7/31/2019 Complete Pmp Exam Review Cards
49/140
Corrective Action Control Charts
Control Contract Close-out
ContractWhat are the 3
general types ofcontracts?
Fixed price or lumpsum contracts
Cost reimbursablecontracts
Unit price contracts ContingencyReserve
-
7/31/2019 Complete Pmp Exam Review Cards
50/140
Changes made tobring expected
future performanceof the project into
line with the plan.
Control charts are a graphicdisplay of the results, over
time and against establishedcontrol limits, of a process.
They are used to determine ifthe process is in control or
in need of adjustment.
The process of comparingactual performance with
planned performance, analyzingvariances, evaluating possible
alternatives, and takingappropriate corrective action as
needed.
Completion andsettlement of the
contract, includingresolution of all
outstanding items.A contract is a mutually
binding agreement whichobligates the seller toprovide the specified
product and obligates the
buyer to pay for it.
Fixed price or lumpsum contracts, Cost
reimbursablecontracts, Unit price
contractsThis type of contract involves a
fixed total price for a well-definedproduct. Fixed price contractsmay also include incentives formeeting or exceeding selected
project objectives such asschedule targets.
This type of contract involves payment(reimbursement) to the contractor for its actual costs.
Costs are usually classified as direct costs (costsincurred directly by the project, such as wages formembers of the project team) and indirect costs(costs allocated to the project by the performing
organization as a cost of doing business, such assalaries for corporate executives). Indirect costs are
usually calculated as a percentage of direct costs.Cost reimbursable contracts often include incentivesfor meeting or exceeding selected project objectives
such as schedule targets or total cost.
With this type of contract thecontractor is paid a preset amount perunit of service (e.g., $70 per hour for
professional services or $1.08 percubic yard of earth removed) and the
total value of the contract is a functionof the quantities needed to complete
the work.
A separately plannedquantity used to allow for
future situations whichmay be planned for onlyin part (sometimes called
known unknowns).
-
7/31/2019 Complete Pmp Exam Review Cards
51/140
Do you includecontingency
reservers in theschedule baseline?
Why would you usecontingency
reserves?
Are contingencyreservers only usedwhen dealing with
costs?
ContingencyPlanning
ConcurrentEngineering
CommunicationsPlanning
Code of Accounts Chart of Accounts
Change ControlBoard (CCB) Calendar Unit
-
7/31/2019 Complete Pmp Exam Review Cards
52/140
Yes, contingencyreserves are normally
included in theprojects cost and
schedule baselines.
Contingency reservesare intended to
reduce the impact ofmissing cost or
schedule objectives.
No, contingencyreserves mayinvolve cost,
schedule, or both.
The development of amanagement plan thatidentifies alternative
strategies to be used toensure project success if
specified risk events occur.
An approach to projectstaffing that, in its mostgeneral form, calls for
implementors to be involvedin the design phase.
Sometimes confused with fast
tracking.
Determining theinformation andcommunications
needs of the project
stakeholders.Any numberingsystem used to
uniquely identify eachelement of the work
breakdown structure.
Any numbering system used tomonitor project costs by
category (e.g., labor, supplies,materials). The project chart of
accounts is usually based uponthe corporate chart of accounts
of the primary performing
organization.
A formally constitutedgroup of stakeholders
responsible forapproving or rejectingchanges to the project
baselines.
The smallest unit of time used inscheduling the project. Calendar
units are generally in hours,days, or weeks, but can also be
in shifts or even in minutes. Usedprimarily in relation to project
management software.
-
7/31/2019 Complete Pmp Exam Review Cards
53/140
Budgeted Cost ofWork Scheduled
(BCWS)
Budgeted Cost ofWork Performed
(BCWP)
Budget AtCompletion (BAC) Baseline
Bar Chart Gantt chart
Backward Pass Arrow DiagrammingMethod (ADM)
Arrow Application Area
-
7/31/2019 Complete Pmp Exam Review Cards
54/140
The sum of the approved costestimates (including anyoverhead allocation) foractivities (or portions of
activities) scheduled to beperformed during a given period
(usually project-to-date).
The sum of the approved costestimates (including anyoverhead allocation) foractivities (or portions of
activities) completed during agiven period (usually
project-to-date).
The estimated totalcost of the project
when done.
The original plan (for a project,a work package, or an activity),
plus or minus approvedchanges. Usually used with amodifier (e.g., cost baseline,
schedule baseline, performance
measurement baseline).
A graphic display of schedule-relatedinformation. In the typical bar chart,
activities or other project elements arelisted down the left side of the chart,dates are shown across the top, and
activity durations are shown asdate-placed horizontal bars. Also
called a Gantt chart.
A graphic display of schedule-relatedinformation. In the typical bar chart,
activities or other project elements arelisted down the left side of the chart,dates are shown across the top, and
activity durations are shown asdate-placed horizontal bars. Also
called a Bar chart.
The calculation of late finish dates andlate start dates for the uncompleted
portions of all network activities.Determined by working backwardsthrough the network logic from the
projects end date. The end date maybe calculated in a forward pass or set
by the customer or sponsor.
A diagramming technique in whichactivities are represented by arrows.The tail of the arrow represents thestart and the head represents thefinish of the activity. Activities are
connected at points called nodes toillustrate the sequence in which the
activities are expected to be
performed.
The graphicpresentation of an
activity.
A category of projects thathave common elements not
present in all projects.Application areas are usuallydefined in terms of either theproduct of the project or the
type of customer.
-
7/31/2019 Complete Pmp Exam Review Cards
55/140
Is stakeholdermanagerment aproactive task?
What is the tripleconstraint and what
is it used for?
What is meant bythe word
internationalization?
What isSocial-Econominc
EnvironmentalSustainability?
Should youincorporate
stakeholders'requirements into a
project?
What does theinitiating process
do?
What is the meantby the planning
process?
What is down in theexecuting process?
What is done in thecontrolling
process?
What is done in theclosing process?
-
7/31/2019 Complete Pmp Exam Review Cards
56/140
Yes, stakeholdermanagement is a
proactive task.
The triple constraint istime, cost, quality. It is
used to identify the threemost important factors thata project manager needs to
consider in a project.
Consideration oftime-zone differences,national and regional
holidays. travelrequirements, and other
logistical issues.
Being accountablefor impacts resultingfrom a project both
social and
economic.Yes, always
incorporate thestakeholder's
requirements into
the project.
It authorizes theproject of phase.
This process is usedfor defining and
refining objectivesand selecting the best
of the alternatives.
During this phasepeople are coordinatingwith other resources to
carry out the projectphase or plan.
This process is for ensuringthat project objectives are metby monitoring and measuringprogress in order to indetifyvariances from the plan so
that corrective action can betaken if and when necessary.
This process is whenformailizing acceptanceof the project or phase
is completed in thehopes of bringing it to
an orderly end.
-
7/31/2019 Complete Pmp Exam Review Cards
57/140
What is a tightmatrix?
In a strong matrixwhat type of
power/authoritydoes the project
manager have?
In a weak matrixdoes the project
manager have muchauthority?
Project Coordinator
Project Expeditor
What are someadvantages/benefits
of a functionalorganization?
What are somedisadvantages of a
functionalorganization?
Is scope verificationnecessary when a
project isterminated?
Will managementby objectives work
if managementdoesn't support it.
Dephi Technique
-
7/31/2019 Complete Pmp Exam Review Cards
58/140
This refers tolocating the officesfor the project team
in the same
room/location.
In this type ofmatrix the power
rests with theproject manager.
No, thepower/authority
rests with thefunctional manager.
An individual who reports to ahigher-level manager in the
organization, has the authority toassign work to individuals in
various functional organizations,and shares authoity and
resources with the functional
manager.
An individual who is a staffassistant to an executive whohas the ultimate responsibilityfor the project. Has authority
only in his managers departmentbut not over resources from
other departments.
1) Easier management ospecialist's, 2) Team
memebers only report to 1boss, 3) Clearly defined
careeer paths, 4)
resources are centralized.1) The project manager
has NO authority, 2)People place moreemphasis on their
speciality than to the
project.
Yes, scope verifcation isnecessary when a project
is terminated, italthoughs the
organization to determine
the level of completion.
No, in orer to workproperly, it must be
supported bymanagement.
A mthod to obtain opinions onissues. Information sent to
experts, responses are compiledand the results are sent back forfurther review. Using the delphi
technique helps reduce bias andundue influence.
-
7/31/2019 Complete Pmp Exam Review Cards
59/140
What type ofdiagram uses
dummy activities?
What are the threeuses for dummy
activites?
What is theexpectancy theory?
What is problemsolving/confrontation?
Give three examplesof hygiene factors inHerzberg's theory ofmotivation. How do
they affect motivation.
What is McGregor'sTheory X?
What is McGregor'stheory Y?
What is anorganizational
breakdownstructure (OBS)?
What is the purposeof a resource Gantt
chart?
Does the matrix formof project
organization facilitateor complicate project
team development?
-
7/31/2019 Complete Pmp Exam Review Cards
60/140
Activity-On-ArrowNetwork.
1) logic, 2) timedelay and, 3)uniqueness.
It holds that people tend to behighly productive and
motivated if they believe theirefforts will lead to successful
results and they will berewarded for their success.
Addressing conflict directly bygetting the parties to work
together to define theproblem, collect information,
develop and analyzealternatives, and select the
most appropriate alternative.
Pay, attitude of supervisor, andworking conditions.
y motivation,but improving hygiene factors in not
likely to increase motivation.Motivators are an opportunity to
achieve and experienceself-actualization.
Traditional approach: workersare self-centered, lazy, lackingambition. Managers organize
the elements of theproductive enterprise in theinterest of economic ends.
Workers are not by natureresistant to organizationalneeds; they are willing and
eager to acceptresponsibilities and are
concerned with self-growthand fulfillment.
A specific type oforganizational chart
that shows whichunits are responsible
for which work items
It identifies when aparticular resource
is or will be workingon a particular task.
It complicates teamdevelopment because
team members areaccountable to both a
functional manager and
a project manager.
-
7/31/2019 Complete Pmp Exam Review Cards
61/140
Name three majorforms of projectorganizational
structure.
What is aprojectized
organization?
Describe thedifference betweena weak matrix and a
strong matrix.
What is a project"war room" and
what is its benefit?
What is varianceanalysis?
What is activelistening?
What is majorcause of conflictwith functional
managers?
What is mostdifficult conflict to
deal with?
What is earned valueanalysis and how is
it used inperformance
reporting?
What is the tool forused for
communicationplanning?
-
7/31/2019 Complete Pmp Exam Review Cards
62/140
Functional, Matrix,and Projectized
One in which a separate,functional organizationis established for eachproject. Personnel areassigned on a full-time
basis.
Weak matrices are similar tofunctional organizations.
Strong matrices are similar toprojectized organizations
(with balance of power tippedtoward the project manager)
A single location for the team toget together for any purpose. Itprovides a repository for project
artifacts, records, andup-to-date schedules and status
reports. It gives an identity to
the project team.
Comparing actualproject results to
planned or expectedresults in terms of cost,schedule, scope, quality,
and risk.
Listening in which therecipient is attentive
and asks forclarification of
ambiguous messages
SchedulesPersonalityconflicts
An analysis thatintegrates cost and
schedule measures. It isused to help the project
management team assess
project performance.
Stakeholderanalysis
-
7/31/2019 Complete Pmp Exam Review Cards
63/140
5 Phases of ProjectManagement Initiation Phase Activities
Planning Phase CoreProcesses
Planning PhaseFacilitating Processes
Activity Activity aspects
Activity definition Activity description
Activity DurationEstimating Activity-On-Arrow
-
7/31/2019 Complete Pmp Exam Review Cards
64/140
Initiation - Planning -Execution - Control -
ClosureInitiation
Scope Planning - ScopeDefinition - Activity Definition -Activity Sequencing - Activity
Duration Estimating - ResourcePlanning - Cost Estimating -
Schedule Development - CostBudgeting - Project Plan
Development
Quality Planning -Communicaiton Planning - Risk
ID - Risk Quantification - RiskResponse Devlp -
Organizational Planning - Staff Acquisition - Procurement
Planning - Solicitation Planning
Element of work on aproject
Duration - Expected cost- Expected resources
required
Identifying specificactivities that must beperformed in order to
produce a project'sdeliverables.
The scope of work of theactivity. - Used in project
diagrams.
Estimating the number of work periods that will be
needed to completeindividual activities.
Part of the ArrowDiagramming Method
-
7/31/2019 Complete Pmp Exam Review Cards
65/140
Activity-On-Node Actual Cost of WorkPerformed
Actual Finish Date Actual Start Date
Administrative Closure Application Area
Arrow Arrow DiagrammingMethod
As-Of Date Backward Pass
-
7/31/2019 Complete Pmp Exam Review Cards
66/140
Part of the PrecedenceDiagramming Method
Total costs incurred(direct and indirect) for a
project.
When work ends.When work starts.
Formalized project end.Type of: product, project
or customer. - There isoften overlap
Graphic presentation of an activity.
Graphical representationof a project where
activities are representedby arrows.
Same as Data DateCalculating a projectlength based on end-date
-
7/31/2019 Complete Pmp Exam Review Cards
67/140
Bar Chart Baseline
Baseline Finish Date Baseline Start Date
Budget at Completion Budget Estimate
Budget Cost of WorkPerformed
Budgeted Cost of WorkScheduled
Calendar Unit Change Control Board
-
7/31/2019 Complete Pmp Exam Review Cards
68/140
Left side = Projectelements Bottom = Date
range (Also called =GANTT Chart)
The original plan
Scheduled Finish DateScheduled Start Date
The estimated total costof the project when done.Estimate
Sum of approved costestimates completed.Part of Earned Value
Sum of approved costestimates not yet
completed. Part of Earned Value
Smaller unit (Hours -Days - Weeks - Shifts -
Minutes)
Group of stakeholdersresponsible for
approving or rejectingchanges in the project
baseline.
-
7/31/2019 Complete Pmp Exam Review Cards
69/140
Change in Scope Chart of Accounts
Charter Code of Accounts
CommunicationsPlanning Concurrent Engineering
Contingency Planning Contingency Reserve
Contract - 3 Categories Contract Definition
-
7/31/2019 Complete Pmp Exam Review Cards
70/140
Scope ChangeNumbering system usedto monitor project costs
by category.
Same as project charter
Numbering system usedto identify each elementof the work breakdown
structure.
Determining thecommunication needs
and procedures for eachstakeholder.
Not Fast Tracking - Callsfor project
implementations to beinvolved in the Design
Phase.
Risk mitigation plan
Known Unknowns. Theyare buffers (cost,
schedules, resources)built into the project
baseline.
1 - Fixed price or lumpsum. 2 - Cost
reimbursable. 3 - Unitprice
Mutually bindingagreement.
-
7/31/2019 Complete Pmp Exam Review Cards
71/140
Contract - 2 Parts Contract - Fixedprice/Lump Sum
Contract - Costreimbursable Contract - Unit Price
Contract Administration Contract Close-out
Control Control Chart
Corrective Action Cost Budgeting
-
7/31/2019 Complete Pmp Exam Review Cards
72/140
Seller - delivers productor service. Buyer -obliged to pay for
product or service.
Fixed price for awell-defined product or
service.
Time and materials.
Seller is paid a pre-setprice for unit of productor service (i.e. $70 per
hour)
Managing therelationship with the
seller.
Completion of thecontract.
Comparing planned vs.actual performance.
Graphical display of results.
Used to get a projectback on track.
Allocating cost estimatesto the actual project.
-
7/31/2019 Complete Pmp Exam Review Cards
73/140
Cost control. Cost Estimating
Cost of Quality Cost Performance Index= Formula
Cost Performance Index Project Cost atCompellation
Cost Plus Fixed FeeContract
Cost Plus Inventive FeeContract
Cost Variance Crashing
-
7/31/2019 Complete Pmp Exam Review Cards
74/140
Controlling changes inthe project budget.Estimating project costs
Cost incurred to ensurequality.CPI = BCWP / ACWP
Used to predict themagnitude of a project
cost overrun.
PCC = Original Cost Est. /CPI
Time and Materials + afixed profit level.
Time and Materials +fixed profit level if all
goals are met.
BCWP < ACWPDifference between
estimated and actualcost.
Taking action todecrease a project
timeline.
-
7/31/2019 Complete Pmp Exam Review Cards
75/140
Critical Activity Critical Path Method
Current Finish Date Current Start Date
Data Date Deliverable
Dependency Dummy Activity
Duration Duration Compressing
-
7/31/2019 Complete Pmp Exam Review Cards
76/140
Critical Path MethodThe path with the leastamount of flexibility.
Current estimate of project completion
Current estimate of project initiation.
As-Of-Date. Point of timethat is between historical
and future date.
Tangible and verifiableoutcome.
Requires another step tobe accomplished.
Zero length. Place holder activities in a project
schedule.
Length of time tocomplete an activity.
Shorten duration withoutdecreasing project
scope.
-
7/31/2019 Complete Pmp Exam Review Cards
77/140
Early Finish Date Early Start Date
Earned Value Effort
Estimate Estimate at Completion
Estimate to Complete Event-on-Node
Exception Report Expected Monetary Value
-
7/31/2019 Complete Pmp Exam Review Cards
78/140
Used in the Critical PathMethod. Earliest date theproject can be completed
by.
Used in the Critical PathMethod. Earliest date theproject can be started by.
1 - Method for measuringproject performance. 2 -
Budgeted cost. 3 -Compares work plannedvs. actually performed.
Not Duration. Resourceunits needed to complete
an activity.
Prediction of costs,resources needed and
duration.
EAC = Actuals-to-date +ETC
Expected additional costneeded to complete an
activity.
Project diagrammingmethod that usesconnected boxes.
Document which showonly major variations to
the project plan.
Monetary gain or losedue to an event.
-
7/31/2019 Complete Pmp Exam Review Cards
79/140
Fast Tracking Finish Date
Firm Fixed Price Contract Fixed Price Incentive FeeContract
Float Forecast Final Cost
Forward Pass Fragnet
Free Float Functional Manager
-
7/31/2019 Complete Pmp Exam Review Cards
80/140
Compressing a projectschedule by overlapping
activities. Not =Concurrent Engineering
Project activitiescompleted date.
Fixed price, regardless of changes in Time and
Material costs.
Fixed price with a bonusfor performance.
Amount of time anactivity can be delayed
without affecting theproject schedule.
EST
Calculating a projecttime-line based on a
start-date.Subnet
Amount of time anactivity can be delayed
without affecting an earlystart of a project.
Specialized departmentmanager (i.e. Marketing
Mgr.)
-
7/31/2019 Complete Pmp Exam Review Cards
81/140
Functional Organization Gantt Chart
Grade Graphical Evaluation andReview Technique
Hammock Hanger
Information Distribution Initiation
Integrated Cost/ScheduleReporting Invitation for Bid
-
7/31/2019 Complete Pmp Exam Review Cards
82/140
-
7/31/2019 Complete Pmp Exam Review Cards
83/140
Key Event Schedule Lag
Late Finish Date Late Start Date
Lead Level of Effort
Life-Cycle Costing Line Manager
Link Logic Diagram
-
7/31/2019 Complete Pmp Exam Review Cards
84/140
Master Schedule
A step in the project pathmust wait X days after its
predecessor iscompleted.
Latest possible date atask can be completed
without delaying theschedule.
Latest possible date atask can begin withoutdelaying the schedule.
A step in the project pathwhich can start X days
before its predecessor iscompleted.
Estimate of resourcesneeded to complete the
task.
Acquisition - Operating -Disposal costs.
Considered whenevaluating alternatives.
A manager who is alsoworking directly on the
project.
Connection of stepsProject Network Diagram
-
7/31/2019 Complete Pmp Exam Review Cards
85/140
Logical Relationships (4Types) Finish-to-Start Activity
Finish-to-Finish Activity Finish-to-Start Activity
Finish-to-Start Activity Loop
Management Reserve Master Schedule
Matrix Organization Milestone
-
7/31/2019 Complete Pmp Exam Review Cards
86/140
Finish-to-start /Finish-to-finish /
Start-to-start /Start-to-finish
The FROM activity mustFINISH before the TOactivity can START.
The FROM activity mustFINISH before the TOactivity can FINISH.
The FROM activity mustSTART before the TOactivity can FINISH.
The FROM activity mustSTART before the TO
activity can FINSH.
Cannot be in CPM or PERT. Can be in GERT
Cost and schedulebuffers planned by
management for unseenevents that would impact
the project.
Summary-level schedulethat identifies key
milestones.
Project and Functionalmanagers shareresponsibilities.
Significant event.
-
7/31/2019 Complete Pmp Exam Review Cards
87/140
Mitigation Modern ProjectManagement
Monitoring Monte Carlo Analysis
Near-Critical Activity Network Analysis
Network Logic Network Path
Node OrganizationalBreakdown Structure
-
7/31/2019 Complete Pmp Exam Review Cards
88/140
Steps to lessen risk bylowering probability.
Broad / Not focused oncost and time / Focused
on: scope, cost, timequality, risk, etc.
Tracking and reportingproject performance and
status.
Simulation of Risk thatoccurs throughout the
project.
An activity that has lowtotal float.
The process of identifying early and late
finish dates for theuncompleted portions of
project activities.
A collection of dependencies that makeup the project network
diagram.
Connected activities inthe project network
diagram.
A junction point in aproject network diagram.
A depiction of the projectinto work breakdown
"packages".
-
7/31/2019 Complete Pmp Exam Review Cards
89/140
Organizational Planning Overall Change Control
Parametric Estimating Pareto Diagram
Path Path Convergence
Percent Complete Performance Reporting
Performing Organization PrecedenceDiagramming Method
-
7/31/2019 Complete Pmp Exam Review Cards
90/140
Identifying, documentingand assigning projectroles, responsibilities
and reportingrelationships.
Coordinating changesacross the entire project.
Estimates based onstatistics and history.
Histogram ordered byfrequency of occurrence
that shows multipleresults relating to one
cause.
Sequential activities.
Parallel paths that lead toone milestone, but may
singularly delay aproject.
Percent of work alreadyperformed.
Collecting anddisseminating
information about projectperformance to help
ensure project progress.
The enterprise whoseemployees are most
directly involved in doingthe work of the project.
Activities arerepresented by boxes
and linked sequentially.A diagramming method.
-
7/31/2019 Complete Pmp Exam Review Cards
91/140
Precedence Relationship Predecessor Activity
Procurement Planning Program
Program Evaluation andReview Technique Project
Project Charter Project CommunicationsManagement
Project CostManagement
Project Human ResourceManagement
-
7/31/2019 Complete Pmp Exam Review Cards
92/140
Refers to thediagramming methods.
1 - Arrow DiagrammingMethod - Activity which
enters a NODE. / 2 -Precedence Diagramming
Method - Activity whichgoes "away from" the
NODE.
Determining what toprocure and when.
A group of relatedprojects. Usually
on-going.
Event-oriented. Used toestimate project
duration. Used for projects with uncertainly
in duration.
A temporary endeavor undertaken to create a
unique product or service.
Sr. Management's writtenauthority given to the PM
for organizationresources.
Subset project for collecting and dispersing
project info.
Subset project for ensuring a project is
completed within budget.
Subset project for effectively using
personnel in the project.
-
7/31/2019 Complete Pmp Exam Review Cards
93/140
Project IntegrationManagement Project Life Cycle
Project Management Project ManagementBody of Knowledge
Project ManagementSoftware
Project ManagementProfessional
Project ManagementTeam Project Manager
Project Network Diagram Project Phase
-
7/31/2019 Complete Pmp Exam Review Cards
94/140
Subset project for integrating subset
projects into the whole.
A collection of sequentialproject phases.
The knowledge, skills,tools and techniques to
meet and exceed astakeholders
expectations with aproject.
Book of proven projectmanagement practices.
Computer applicationdesigned to plan and
control a project.Certified PM from PMI
Members of the projectteam.
Individual responsible for managing the project.
PERT or GANTTSchematic display of
project activities.
A subset collection of project activities.
-
7/31/2019 Complete Pmp Exam Review Cards
95/140
Project Plan Project Plan - Elements
Is a Project PlanSummary or Detailed?
Project PlanDevelopment
Project Plan Execution Project Planning
Project ProcurementManagement
Project QualityManagement
Project Risk Management Project Schedule
-
7/31/2019 Complete Pmp Exam Review Cards
96/140
Formal document usedto guide the project.
Plan / Cost Assumptions / Schedule / Decisions /
Scope
Can be both
Taking the results of other planning processes
and putting them into anew document.
Carrying out the projectplan details.
Development andmaintenance of the
project plan.
Acquiring goods andservices outside of theproject team for use in
the project.
Subset of the projectused to ensure the
project is up torequirements at delivery.
Subset of the project for identifying and mitigating
risks.
Outlines dates for eachactivity in sequential
order.
-
7/31/2019 Complete Pmp Exam Review Cards
97/140
Project ScopeManagement Project Team Members
Project TimeManagement Projectized Organization
Quality Assurance Quality Control
Quality Planning Remaining Duration
Request for Proposal Request for Quotation
-
7/31/2019 Complete Pmp Exam Review Cards
98/140
Subset of the projectused to ensure only the
pre-defined workrequired is done and no
more.
They work for the ProjectManager
Subset of the project thatmonitors and ensures a
team meeting allmilestone dates.
Where PM has 100% over project team. No shared
authority.
Evaluating process toensure the project will
satisfy its qualitystandards.
Process of evaluatingspecific project steps toverify they meet with the
project quality standards.
Identifying which qualitystandards are relevant to
the project.
Time needed to completean activity.
Bid document fromcompany to vendor.
Bid document from acompany to a vendor for
pricing information.
-
7/31/2019 Complete Pmp Exam Review Cards
99/140
Reserve Resource Leveling
Resource-LimitedSchedule Resource Planning
ResponsibilityAssignment Matrix Retainage
Risk Event Risk Identification
Risk Quantification Risk Response Control
-
7/31/2019 Complete Pmp Exam Review Cards
100/140
Provision in the projectplan to mitigate cost
and/or schedule risks.
Where schedulingconcerns are addressed
by resource managementconcerns.
Project where start andend date are based onresource availability.
Resource identificationprocess.
Relates projectorganization structure to
work breakdownstructure.
Down payment on acontracted product or
service.
An occurrence thataffects the projects
outcome.
Identifying which riskswill affect the project.
Identifying probability of the risk.
Responding to changesin risk over the course of
the project.
-
7/31/2019 Complete Pmp Exam Review Cards
101/140
Risk ResponseDevelopment S-Curve
Schedule Control Schedule Development
Schedule PerformanceIndex Schedule Variance
Scheduled Finished Date Scheduled Start Date
Scope Scope Change
-
7/31/2019 Complete Pmp Exam Review Cards
102/140
Risk mitigation planGraph showing
cumulative cost andlabor over time.
Controlling changes tothe project schedule
Analyzing activitysequences, durations
and resourcerequirements to create a
project schedule.
Work performed / WorkSchedule (BCWP /
BCWS)
Difference betweenscheduled and actual
timeframes.
Planned activity end datePlanned activity startdate
The sum of the productsand services to be
provided as a project.Any change to the scope.
-
7/31/2019 Complete Pmp Exam Review Cards
103/140
Scope Change Control Scope Definition
Scope Planning Scope Verification
Should-Cost Estimate Slack
Solicitation Solicitation Planning
Source Selection Staff Acquisition
-
7/31/2019 Complete Pmp Exam Review Cards
104/140
Controlling changes inthe scope.
Decomposing the major deliverables into small
parts.
Written scopestatements.
Auditing each scopeelement at the end of aproject for completion.
Used to judge thereasonableness of a
vendors quote.Used in PERT for FLOAT
Obtaining quotes, bidsand offers.
Document statingrequirements and
potential sources to meetthose requirements.
Choosing a vendor or product.
Getting human resourcesto work on the project.
-
7/31/2019 Complete Pmp Exam Review Cards
105/140
Stakeholder Start Date
Statement of Work Subnet
Successor Activity Target Completion Date
Team Development Time-Scaled NetworkDiagram
Target Finish Date Target Start Date
-
7/31/2019 Complete Pmp Exam Review Cards
106/140
People directly or indirectly involved in the
project.Qualified starting date
A narrative description of products or services to
be supplied under contract.
Subproject
Activity while "leaves"the node.
A constraining date inthe project diagram.
Developing teammembers to enhance the
project.
Diagram where thephysical shape of each
activity object isproportional to the
duration of that activity.
The date the work for theactivity is planned to be
completed by.
The date the work for theactivity is planned to be
started by.
-
7/31/2019 Complete Pmp Exam Review Cards
107/140
How is contract closeoutsimilar to administrative
closeout?
How is performancereporting used as a tool
for contractadministration?
When are paymentrequests an output of
contract administration?
Describe thecharacteristics of aunilateral contract?
What is a unilateralcontract?
Under what two conditionsmust PMI members refrainfrom offering or accepting
monetary payments or other forms of compensation or
tangible benefits?
What is the most criticalculture for the success of
a project manager working internationally?
Who can initiate anethics complaint?
When is a PMPresponsible for reporting
to PMI possibleviolations of the PMPCode of Professional
Conduct?
What are the twoconditions under which
PMI member's do not haveto honor and maintain theprivacy and confidentiality
of client information?
-
7/31/2019 Complete Pmp Exam Review Cards
108/140
Both contract closeout andadministrative closure
involve product verification.However, the contract terms
and conditions may prescribespecific procedures for
contract closeout.
it provides managementwith information about
how effectively the seller is achieving the
contractual objectives.
When the project is usingan external payment
system.
It usually takes the formof a purchase order -- a
standard form listingroutine items at standard
prices.
A contract that has onlyone signature (the
issuer).
When payments do notconform with applicablelaws and when they may
provide an unfair advantage for themselves
or their business.
LeadershipAny person, group, or
organization, includingPMI.
When reasonable andclear facts exist to verify
the violation.
1) if granted permission bythe customer, client, or
employer, and 2) If maintaining the
confidentiality is otherwiseunethical or unlawful.
-
7/31/2019 Complete Pmp Exam Review Cards
109/140
-
7/31/2019 Complete Pmp Exam Review Cards
110/140
-
7/31/2019 Complete Pmp Exam Review Cards
111/140
What is the differencebetween attribute
sampling and variablesampling?
In which project phase isquality control
performed?
What is the differencebetween a tolerance and
a control limit?
What are the three (3) keyoutputs from
administrative closure?
Name five barriers toeffective project
communications.
Name threecommunications
channels in anorganization?
Why is communicationsplanning so tightly linkedto project organizational
planning?
What is active listening?
What is earned valueanalysis and how is itused in performance
reporting?
List the four parts of thecommunication model.
-
7/31/2019 Complete Pmp Exam Review Cards
112/140
Attribute sampling determineswhether the result does or does
not conform to the specifications.In variable sampling, the result israted on a continuous scale that
measures the degree of conformance within a
pre-established acceptable range.
Quality control isperformed throughout allphases of the project life
cycle.
A tolerance establishesthe range of acceptable
results. A control limit iscomputed based on the
results themselves.
1) Project archives, 2)Project closure, 3)Lessons learned.
1) Lack of clear communicationchannels. 2) Physical distance
between communicator andreceiver, 3) Difficulties withtechnical language, 4)Distracting environmental
factors, 5) Detrimental attitudes.
Personal, Organization,Grapevine
Because the project'sorganizational structurewill have a major effect
on projectcommunications.
Listening in which therecipient is attentive andasks for clarification of ambiguous messages.
An analysis that integratescost and schedule
measures. It is used t helpthe project management
team assess projectperformance.
Communicator, Message,Medium, Recipient
-
7/31/2019 Complete Pmp Exam Review Cards
113/140
What is the differencebetween a risk and a
problem?
When should EAC becalculated by AC + BAC -
EV?
When should EAC becalculated by AC + (BAC
- EV) / CPI?
What does thebenefit-cost ratio not tell
you?
if a project is experiencingquality problems, should
the project manager devote more resources to
inspection of to
prevention?
What are the seven (7)main quality control
tools, often called the"basic seven" tools?
does the matrix form of project organization
facilitate or complicateproject team
development? Why?
Project Human ResourceManagement compriseswhich three processes?
How is simulation usedin activity duration
estimating and what isthe most common type of
simulation?
At which phase(s) in theproject life cycle is
significant risk thoughtto have the greatest
impact?
-
7/31/2019 Complete Pmp Exam Review Cards
114/140
A risk is a future event; ithas not yet occurred. A
problem, on the other hand, currently exists.
When current variancesare seen as atypical, andthe project management
team's expectation is thatsimilar variances will not
occur in the future.
When the currentvariances are seen as
typical of futurevariances.
The absolute value of thebenefit or cost.
Prevention, becausepreventing a problem is
far less costly, thanfixing a problem.
1) Flowcharts, 2)Diagrams, 3) Pareto
Diagram, 4)Cause-and-Effect Diagram,
5) Graphs, 6) Control
Charts, 7) Checklists
It complicates projectteam development.
Because team membersare accountable to both afunctional manager and
the project manager.
1) Organizationalplanning, 2) Staff
acquisition, 3) Teamdevelopment
To calculate multiple durations withdifferent sets of assumptions.
Monte Carlo Analysis, in which adistribution of probable results is
defined for each activity and used tocalculate a distribution of probable
results for the total project.
Project execution andcloseout.
-
7/31/2019 Complete Pmp Exam Review Cards
115/140
Project Plan Execution- Inputs
Project PlanDevelopment - Tools
Project Plan Execution- Tools
Integrated ChangeControl - Inputs
Integrated ChangeControl - Tools Initiation - Inputs
Initiation - Tools Scope Planning - Tools
Scope Planning -Inputs
Scope Definition -Tools
-
7/31/2019 Complete Pmp Exam Review Cards
116/140
Project plan,supporting details,
organizational policies,preventive action,
corrective action
Project planningmethodology, stakeholder
skills & knowledge, projectmanagement information
system (PMIS), earned
value management (EVM)
General management skills,product skills & knowledge,work authorization system,
project managementinformation system (PMIS),
and organization procedures
Project plan,performance reports,
change requests
Change control system,configuration