complete pmp exam review cards

Upload: munir-a-sakhani

Post on 04-Apr-2018

229 views

Category:

Documents


1 download

TRANSCRIPT

  • 7/31/2019 Complete Pmp Exam Review Cards

    1/140

  • 7/31/2019 Complete Pmp Exam Review Cards

    2/140

  • 7/31/2019 Complete Pmp Exam Review Cards

    3/140

    Project IntegrationManagement

    Project PlanDevelopment

    Integrated ChangeControl?

    Why is historicalinformation usefulin developing the

    project plan?

    Constraints Project PlanningMethodology?

    Project Plan Work AuthorizationSystem?

    Work Results?

    How is the projectplan used to in

    integrated changecontrol?

  • 7/31/2019 Complete Pmp Exam Review Cards

    4/140

    The processesrequired to ensure

    that various elementsof the project are

    properly coordinated.

    Taking results of otherplanning processes

    and putting them intoa coherent, consistent

    document.

    Coordinatingchanges across the

    entire project.

    Because it helpsverify assumptions

    and assessidentified

    alternatives.

    Factors that limitthe project

    management team'soptions.

    Any structuredapproach to guidethe project team in

    the development of a

    project plan.

    A formal, approveddocument used to

    manage and controlproject execution.

    A formal procedure tosanction project work

    so that it is done atthe proper time and in

    the proper sequence.

    Outcomes ofactivities performedto accomplish the

    project.

    The project planprovides the

    baseline againstwhich all changes

    are controlled.

  • 7/31/2019 Complete Pmp Exam Review Cards

    5/140

    What is required inthe decision

    making process?Llife-Cycle Costing

    Line Manager MatrixOrganization?

    Network Logic? OrganizationPlanning

    ParametricEstimating Pareto Diagram

    Work Package Work BreakdownStructure

  • 7/31/2019 Complete Pmp Exam Review Cards

    6/140

    Analyzing theproblem to identify

    viable solutions andthen making a choice

    from among them.

    The concept ofincluding acquisition,

    operating, and disposalcosts when evaluating

    various alternatives.

    The manager of anygroup that actuallymakes a product orperforms a service.

    Also called a functional

    manager.

    Any organization structure inwhich the project manager

    shares responsibility with thefunctional managers for

    assigning priorities and fordirecting the work of individuals

    assigned to the project.

    Any continuousseries of connectedactivities in a project

    network diagram.

    Identifying,documenting, and

    assigning project roles,responsibilities, and

    reporting relationships.

    An estimating techniquethat uses a statisticalrelationship between

    historical data and othervariables to calculate an

    estimate.

    A histogram, ordered byfrequency of

    occurrence, that showshow many results were

    generate by each

    identified cause.

    A deliverable at thelowest level of the WorkBreakdown Structure. A

    work package may bedivided into activities.

    A task oriented structure thatorganizes and defines total

    work to be accomplished in aproject. Each level represents

    an increasingly detaileddefinition of a project

    component.

  • 7/31/2019 Complete Pmp Exam Review Cards

    7/140

    Float / Slack Critical PathMethod(CPM)

    Backward Pass Corrective Action

    Budgeted Cost ofWork Scheduled

    (BCWS)Baseline

    Arrow DiagrammingMethod (ADM)

    AdministrativeClosure

    Backward Pass Activity

  • 7/31/2019 Complete Pmp Exam Review Cards

    8/140

    The amount of time that an activitymay be delayed from its early start

    date without delaying the projectfinish date. Float is a arithmetic

    calculation and can change as theproject progresses and changes

    are made to the project plan. Also

    called slack.

    A network analysis techniqueused to predict project

    duration by analyzing whichsequence of tasks has theleast amount of scheduling

    flexibility (i.e. the least amount

    of float).

    The calculation of late finishdates and late start dates for

    the uncompleted portions of allnetwork activities. Determinedby working backwards through

    the network logic from the

    project's end date.

    Changes made tobring expected future

    performance of theproject into line with

    the project plan.The sum of the approved cost

    estimates (including anyoverhead allocation) foractivities (or portions of

    activities) scheduled to beperformed during a given period

    (usually project-to-date).

    "The original plan (for a project,a work package, or an activity),

    plus or minus approvedchanges. Usually used with amodifier (e.g., cost baseline,

    schedule baseline, performance

    measurement baseline)."

    A network diagramming technique inwhich activities are represented by

    arrows. The tail of the arrowrepresents the start and the head

    represents the finish of the activity.Activities are connected at points

    called nodes to illustrate the sequencein which the activities are expected to

    be performed.

    "Generating, gathering,and disseminating

    information to formalizeproject completion."

    The calculation of late finish dates andlate start dates for the uncompleted

    portions of all network activities.Determined by working backwardsthrough the network logic from the

    projects end date. The end date maybe calculated in a forward pass or set

    by the customer or sponsor.

    "An element of work performedduring the course of a project.

    An activity normally has anexpected duration, an expected

    cost, and expected resourcerequirements. Activities areoften subdivided into tasks."

  • 7/31/2019 Complete Pmp Exam Review Cards

    9/140

    Activity Definition Activity Description

    Activity DurationEstimating

    Cost of WorkPerformed (ACWP)

    Actual Finish Date Actual Start Date

    AdministractiveClosure Application Area

    Bar Chart Baseline

  • 7/31/2019 Complete Pmp Exam Review Cards

    10/140

    Identifying the specificactivities that must beperformed in order toproduce the various

    project deliverables.

    A short phrase or labelused in a project network

    diagram. The activitydescription normally

    describes the scope of

    work of the activity.

    Estimating thenumber of work

    periods which will beneeded to complete

    individual activities.

    Total costs incurredin accomplishing

    work during a giventime period.

    The point in timethat work actually

    ended on anactivity.

    The point in timethat work actually

    started on anactivity.

    "Generating, gathering,and disseminating

    information to formalizeproject completion."

    A category of projects that havecommon elements not present

    in all projects. Application areasare usually defined in terms of

    either the product of theproject. Application areas often

    overlap.

    "A graphic display of schedule-relatedinformation. In the typical bar chart,

    activities or other project elements arelisted down the left side of the chart,dates are shown across the top, and

    activity durations are shown asdate-placed horizontal bars. Also

    called a Gantt chart."

    "The original plan (for a project,a work package, or an activity),

    plus or minus approvedchanges. Usually used with amodifier (e.g., cost baseline,

    schedule baseline, performancemeasurement baseline)."

  • 7/31/2019 Complete Pmp Exam Review Cards

    11/140

    Work Package Word BreakdownStructure

    Workaround Total QualityManagement (TQM)

    Target Start Date(TS)

    Target Finish Date(TF)

    Time-ScaledNetwork Diagram Team Development

    Target CompletionDate (TC) Successor Activity

  • 7/31/2019 Complete Pmp Exam Review Cards

    12/140

    A deliverable at thelowest level of the workbreakdown structure. Awork package may bedivided into activities.

    A deliverable-orientedgrouping of project

    elements whichorganizes and definesthe total scope of the

    project.

    A response to a negative riskevent. Distinguished fromcontingency plan in that a

    workaround is not planned inadvance of the occurrence of

    the risk event.

    A common approachto implementing a

    quality improvementprogram within an

    organization.

    The date work isplanned (targeted)

    to start on anactivity.

    The date work isplanned (targeted)

    to finish on anactivity.

    Any project network diagramdrawn in such a way that thepositioning and length of the

    activity represents itsduration. Essentially, it is a

    bar chart that includesnetwork logic.

    Developingindividual and group

    skills to enhanceproject performance.

    An imposed datewhich constrains orotherwise modifies

    the network

    analysis.

    (1) In the arrowdiagramming method, theactivity which departs a

    node. (2) In theprecedence diagramming

    method, the to activity.

  • 7/31/2019 Complete Pmp Exam Review Cards

    13/140

    Subnet Statement of Work(SOW)

    Start Date Stakeholder

    Staff Acquisition Source Selection

    SolicitationPlanning

    What is ProjectRisk Management?

    How is Monte Carloanalysis used in

    schedulesimulations?

    What is thedifference between

    a risk and aproblem?

  • 7/31/2019 Complete Pmp Exam Review Cards

    14/140

    A subdivision of aproject networkdiagram usually

    representing some

    form of subproject.

    A narrativedescription of

    products or servicesto be supplied under

    contract.A point in time associated with

    an activitys start, usuallyqualified by one of the

    following: actual, planned,estimated, scheduled, early,

    late, target, baseline, or

    current.

    Individuals andorganizations whoare involved in or

    may be affected by

    project activities.Getting the humanresources neededassigned to andworking on the

    project.

    Choosing fromamong potential

    contractors.

    Documentingproduct

    requirements andidentifying potential

    sources.

    The process concerned withidentifying, analyzing, and

    responding to project risk. Italso includes maximizing the

    results of positive events as wellas minimizing the consequences

    of adverse events to project

    objectives.

    To perform the projectmany times in order to

    provide a statisticaldistribution of thecalculated results.

    A risk is a futureevent; it has not yet

    occurred. A problem,on the other hand,

    currently exists.

  • 7/31/2019 Complete Pmp Exam Review Cards

    15/140

    Solicitation Should-CostEstimates

    Scope Verification Scope Planning

    Scope Definition Scope ChangeControl

    Scope Change Scope

    Scheduled StartDate (SS)

    Scheduled FinishDate (SF)

  • 7/31/2019 Complete Pmp Exam Review Cards

    16/140

    Obtainingquotations, bids,

    offers, or proposalsas appropriate.

    An estimate of the cost ofa product or service usedto provide an assessmentof the reasonableness of a

    prospective contractors

    proposed cost.

    Ensuring that allidentified projectdeliverables havebeen completed

    satisfactorily.

    Developing a writtenscope statement thatincludes the project

    justification, the majordeliverables, and the

    project objectives.Decomposing the major

    deliverables intosmaller, moremanageable

    components to provide

    better control.

    Controllingchanges to project

    scope.

    Any change to theproject scope. A scopechange almost alwaysrequires an adjustment

    to the project cost or

    schedule.

    The sum of theproducts andservices to beprovided as a

    project.The point in time work was

    scheduled to start on anactivity. The scheduled start

    date is normally within therange of dates delimited bythe early start date and the

    late start date.

    The point in time work wasscheduled to finish on an

    activity. The scheduled finishdate is normally within the

    range of dates delimited bythe early finish date and the

    late finish date.

  • 7/31/2019 Complete Pmp Exam Review Cards

    17/140

    Schedule Variance(SV)

    SchedulePerformance Index

    (SPI)

    ScheduleDevelopment Schedule Control

    S-Curve Risk ResponseDevelopment

    Risk ResponseControl

    What type of changeconstitutes one ofthe major areas of

    cost growth?

    What is privity ofcontract?

    What are thecharacteristics of awell-written SOW?

  • 7/31/2019 Complete Pmp Exam Review Cards

    18/140

    (1) Any difference betweenthe scheduled completion

    of an activity and theactual completion of that

    activity. (2) In earned

    value, BCWP less BCWS.

    The ratio of workperformed to work

    scheduled(BCWP/BCWS).

    Analyzing activitysequences, activity

    durations, and resourcerequirements to create

    the project schedule.

    Controllingchanges to the

    project schedule.

    Graphic display of cumulative costs,labor hours, or other quantities,

    plotted against time. The name derivesfrom the S-like shape of the curve(flatter at the beginning and end,

    steeper in the middle) produced on aproject that starts slowly, accelerates,

    and then tails off.

    Definingenhancement steps

    for opportunities andmitigation steps for

    threats.

    Responding tochanges in risk

    over the course ofthe project.

    Change to projectscope.

    A doctrine of law thatrecognizes the

    contractual relationshipexisting between abuyer and its prime

    contractor.

    The SOW shoulbe beclear, complete, and

    concise and include adescription of anycollateral services

    required.

  • 7/31/2019 Complete Pmp Exam Review Cards

    19/140

    Risk Quantification Risk Identification

    Risk Event Retainage

    ResponsibilityAssignment Matrix

    (RAM)Resource Planning

    Resource-LimitedSchedule Resource Leveling

    Reserve Request forQuotation (RFQ)

  • 7/31/2019 Complete Pmp Exam Review Cards

    20/140

    Evaluating theprobability of riskevent occurrence

    and effect.

    Determining whichrisk events are

    likely to affect theproject.

    A discreteoccurrence that mayaffect the project for

    better or worse.

    A portion of a contractpayment that is held

    until contractcompletion in order to

    ensure full performance

    of the contract terms.A structure which relates theproject organization structure

    to the work breakdownstructure to help ensure thateach element of the projects

    scope of work is assigned to a

    responsible individual.

    Determining whatresources (people,

    equipment, materials)are needed in what

    quantities to perform

    project activities.A project schedule whose

    start and finish datesreflect expected resource

    availability. The finalproject schedule should

    always be resource-limited.

    Any form of network analysis inwhich scheduling decisions

    (start and finish dates) are drivenby resource management

    concerns (e.g., limited resourceavailability or difficult-to-manage

    changes in resource levels).

    A provision in the project plan tomitigate cost and/or schedule risk.

    Often used with a modifier (e.g.,management reserve, contingency

    reserve) to provide further detail onwhat types of risk are meant to be

    mitigated. The specific meaning of themodified term varies by application

    area.

    Generally, this term isequivalent to request for

    proposal. However, insome application areas itmay have a narrower or

    more specific meaning.

  • 7/31/2019 Complete Pmp Exam Review Cards

    21/140

    Request forProposal (RFP)

    Remaining Duration(RDU)

    Quality Planning Quality Control(QC)

    Quality Assurance(QA)

    ProjectizedOrganization

    Project TimeManagement

    As a PMP, what laws,regulations, and

    ethical standardsgovern your

    professional practice?

    What is meantwhen someone is

    said to beethnocentric?

    What are the twoways project

    resources areobtained?

  • 7/31/2019 Complete Pmp Exam Review Cards

    22/140

    A type of bid document usedto solicit proposals from

    prospective sellers ofproducts or services. In someapplication areas it may havea narrower or more specific

    meaning.

    The time needed tocomplete an

    activity.

    Identifying whichquality standards arerelevant to the projectand determining how

    to satisfy them.

    (1) The process of monitoring specificproject results to determine if they

    comply with relevant quality standardsand identifying ways to eliminate

    causes of unsatisfactory performance.(2) The organizational unit that isassigned responsibility for quality

    control.

    (1) The process of evaluatingoverall project performance on a

    regular basis to provideconfidence that the project will

    satisfy the relevant qualitystandards. (2) The organizational

    unit that is assigned responsibility

    for quality assurance.

    Any organizational structurein which the project manager

    has full authority to assignpriorities and to direct the

    work of individuals assignedto the project.

    A subset of project management thatincludes the processes required to

    ensure timely completion of theproject. It consists of activity

    definition, activity sequencing, activityduration estimating, schedule

    development, and schedule control.

    Those of the state orprovince and/or

    country where youprovide project

    management services.

    A belief in theinherent superiority

    of one's ownculture.

    Staff acquisitionand procurement.

  • 7/31/2019 Complete Pmp Exam Review Cards

    23/140

    What are the twoways project

    resources areobtained?

    Project TeamMembers

    Project Schedule Project RiskManagement

    Project QualityManagement

    ProjectProcurementManagement

    Project Planning Project PlanExecution

    Project PlanDevelopment Project Plan

  • 7/31/2019 Complete Pmp Exam Review Cards

    24/140

    Staff acquisitionand procurement.

    A subset of project management thatincludes the processes required to

    ensure that the project includes all ofthe work required, and only the work

    required, to complete the projectsuccessfully. It consists of initiation,

    scope planning, scope definition,scope verification, and scope change

    control.

    The planned datesfor performing

    activities and theplanned dates for

    meeting milestones.

    A subset of project managementthat includes the processesconcerned with identifying,

    analyzing, and responding toproject risk. It consists of risk

    identification, risk quantification,risk response development, and

    risk response control.

    A subset of project managementthat includes the processesrequired to ensure that the

    project will satisfy the needs forwhich it was undertaken. It

    consists of quality planning,quality assurance, and quality

    control.

    A subset of project management thatincludes the processes required toacquire goods and services from

    outside the performing organization. Itconsists of procurement planning,solicitation planning, solicitation,

    source selection, contractadministration, and contract close-out.

    The developmentand maintenance of

    the project plan.

    Carrying out theproject plan byperforming the

    activities included

    therein.Taking the results of

    other planningprocesses and puttingthem into a consistent,

    coherent document.

    A formal, approved document used toguide both project execution and

    project control. The primary uses of theproject plan are to document planning

    assumptions and decisions, to facilitatecommunication among stakeholders,

    and to document approved scope, cost,and schedule baselines. A project plan

    may be summary or detailed.

  • 7/31/2019 Complete Pmp Exam Review Cards

    25/140

    Project Phase Project NetworkDiagram

    Project Manager(PM)

    ProjectManagement Team

    ProjectManagement

    Software

    ProjectManagement

    Professional (PMP)

    ProjectManagement Body

    of Knowledge(PMBOK)

    ProjectManagement (PM)

    Project Life Cycle Project IntegrationManagement

  • 7/31/2019 Complete Pmp Exam Review Cards

    26/140

    A collection of logicallyrelated project activities,

    usually culminating inthe completion of amajor deliverable.

    Any schematic display of thelogical relationships of projectactivities. Always drawn fromleft to right to reflect project

    chronology. Often incorrectlyreferred to as a PERT chart.

    The individualresponsible for

    managing a project.

    The members of the project teamwho are directly involved in

    project management activities.On some smaller projects, theproject management team may

    include virtually all of the projectteam members.

    A class of computerapplications specifically

    designed to aid withplanning and controlling

    project costs and

    schedules.

    An individualcertified as such by

    the ProjectManagement

    Institute.An inclusive term that describes the sum ofknowledge within the profession of project

    management. As with other professionssuch as law, medicine, and accounting, the

    body of knowledge rests with thepractitioners and academics who apply andadvance it. The PMBOK includes proven,

    traditional practices which are widelyapplied as well as innovative and advanced

    ones which have seen more limited use.

    The application of knowledge,skills, tools, and techniques

    toproject activities in order tomeet or exceed stakeholder

    needs and expectations froma project.

    A collection of generallysequential project phases

    whose name and number aredetermined by the control

    needs of the organization ororganizations involved in the

    project.

    A subset of project management thatincludes the processesrequired to

    ensure that the various elements ofthe project are properly coordinated.

    It consists of project plandevelopment, project plan execution,

    and overall change control.

  • 7/31/2019 Complete Pmp Exam Review Cards

    27/140

    Project HumanResource

    Management

    Project CostManagement

    ProjectCommunications

    ManagementProject Charter

    ProjectProgram Evaluation

    and ReviewTechnique (PERT)

    Program ProcurementPlanning

    PredecessorActivity

    PrecedenceRelationship

  • 7/31/2019 Complete Pmp Exam Review Cards

    28/140

    A subset of project managementthat includes the processesrequired to make the mosteffective use of the peopleinvolved with the project. Itconsists of organizational

    planning, staff acquisition, and

    team development.

    A subset of project managementthat includes the processesrequired to ensure that the

    project is completed within theapproved budget. It consists of

    resource planning, costestimating, cost budgeting, and

    cost control.

    A subset of project management thatincludes the processes required to

    ensure proper collection anddissemination of project information. Itconsists of communications planning,information distribution, performancereporting, and administrative closure.

    A document issued by seniormanagement that provides

    the project manager with theauthority to apply

    organizational resources toproject activities.

    A temporaryendeavor

    undertaken to createa unique product or

    service.

    An event-oriented network analysistechnique used to estimate project

    duration when there is a high degreeof uncertainty with the individualactivity duration estimates. PERT

    applies the critical path method to aweighted average duration estimate.

    Also given as Program Evaluation and

    Review Technique.

    A group of relatedprojects managed in a

    coordinated way.Programs usually

    include an element of

    ongoing activity.

    Determining whatto procure and

    when.

    (1) In the arrowdiagramming method, the

    activity which enters anode. (2) In the precedencediagramming method, the

    from activity.

    The term used in the precedencediagramming method for a

    logical relationship. In currentusage, however, precedence

    relationship, logical relationship,and dependency are widely used

    interchangeably regardless of

    the diagramming method in use.

  • 7/31/2019 Complete Pmp Exam Review Cards

    29/140

    PrecedenceDiagrammingMethod (PDM)

    PERT Chart

    PerformingOrganization

    PerformanceReporting

    Percent Complete(PC) Path Convergence

    Path Pareto Diagram

    ParametricEstimating

    Overall ChangeControl

  • 7/31/2019 Complete Pmp Exam Review Cards

    30/140

    A network diagrammingtechnique in which activities are

    represented by boxes (ornodes). Activities are linked by

    precedence relationships toshow the sequence in which the

    activities are to be performed.

    A specific type ofproject network

    diagram.

    The enterprisewhose employeesare most directly

    involved in doing the

    work of the project.

    Collecting anddisseminating

    information aboutproject performance to

    help ensure project

    progress.An estimate, expressed

    as a percent, of theamount of work whichhas been completed onan activity or group of

    activities.

    In mathematical analysis,the tendency of parallelpaths of approximately

    equal duration to delay thecompletion of the

    milestone where they meet.

    A set of sequentiallyconnected activitiesin a project network

    diagram.

    A histogram, ordered byfrequency of

    occurrence, that showshow many results were

    generated by each

    identified cause.An estimating technique thatuses a statistical relationshipbetween historical data andother variables (e.g., square

    footage in construction, lines ofcode in software development)

    to calculate an estimate.

    Coordinatingchanges across the

    entire project.

  • 7/31/2019 Complete Pmp Exam Review Cards

    31/140

    OrganizationalPlanning

    OrganizationalBreakdown

    Structure (OBS)

    Node Network Path

    Network Logic Network Analysis

    Near-CriticalActivity

    Monte CarloAnalysis

    Monitoring Modern ProjectManagement (MPM)

  • 7/31/2019 Complete Pmp Exam Review Cards

    32/140

    Identifying,documenting, and

    assigning project roles,responsibilities,and

    reporting relationships.

    A depiction of theproject organization

    arranged so as torelate work packages

    to organizational units.One of the defining points of a

    network; a junction pointjoined to some or all of the

    other dependency lines. Seealso arrow diagrammingmethod and precedence

    diagramming method.

    Any continuousseries of connectedactivities in a project

    network diagram.

    The collection ofactivity

    dependencies thatmake up a project

    network diagram.

    The process ofidentifying early andlate start and finish

    dates for theuncompleted portions of

    project activities.

    An activity that haslow total float.

    A schedule risk assessmenttechnique that performs a

    project simulation many timesin order to calculate a

    distribution of likely results.

    The capture,analysis, and

    reporting of projectperformance, usually

    as compared to plan.

    A term used to distinguish thecurrent broad range of project

    management (scope, cost,time, quality, risk, etc.) from

    narrower, traditional use thatfocused on cost and time.

  • 7/31/2019 Complete Pmp Exam Review Cards

    33/140

    Mitigation Milestone Schedule

    Milestone Matrix Organization

    Master Schedule ManagementReserve

    Loop Start-to-finish

    Start-to-start Finish-to-finish

  • 7/31/2019 Complete Pmp Exam Review Cards

    34/140

    Taking steps to lessenrisk by lowering theprobability of a risk

    events occurrence orreducing its effect

    should it occur.

    A summary-levelschedule which

    identifies the majormilestones. See also

    master schedule.

    A significant event inthe project, usually

    completion of amajor deliverable.

    Any organizational structure inwhich the project manager

    shares responsibility with thefunctional managers for

    assigning priorities and fordirecting the work of individuals

    assigned to the project.

    A summary-levelschedule which

    identifies the majoractivities and key

    milestones.

    A separately planned quantity used toallow for future situations which areimpossible to predict. Management

    reserves may involve cost or schedule.Management reserves are intended to

    reduce the risk of missing cost orschedule objectives. Use of

    management reserve requires a

    change to the projects cost baseline.

    A network path that passesthe same node twice. Loops

    cannot be analyzed usingtraditional network analysis

    techniques such as CPM andPERT. Loops are allowed in

    GERT.

    the from activitymust start before

    the to activity canfinish

    the from activitymust start before

    the to activity canstart

    the from activitymust finish before

    the to activity canfinish

  • 7/31/2019 Complete Pmp Exam Review Cards

    35/140

    Finish-to-startThe four possible

    types of logicalrelationships

    LogicalRelationship Line Manager

    Why is the type oforganizational

    structure importantin project

    management?

    When is the projectteam directory

    developed?

    Which type ofpower should a

    project manageravoid?

    Which type ofpower should a

    project manageruse?

    What are the fivemethods of dealing

    with conflict?

    What is the highestlevel of need's in

    Maslow's hierarchyof needs?

  • 7/31/2019 Complete Pmp Exam Review Cards

    36/140

    the from activitymust finish before

    the to activity canstart

    Finish-to-start,Finish-to-finish,

    Start-to-start,Start-to-finish

    A dependencybetween two projectactivities, or betweena project activity and

    a milestone.

    (1) The manager of anygroup that actuallymakes a product or

    performs a service. (2)A functional manager.

    The structure of theorganization often

    constrains theavailability under which

    resources become

    available to the project.

    As part of the staffacquisition phase

    of the project.

    Avoid usingcoercive power.

    Should try to usereward and expert

    powers.

    Smoothing,Withdrawl,

    Compromise,Forcing and Problem

    Solving

    Self-fulfillment throughthe development of

    powers and skills, anda chance to use

    creativity.

  • 7/31/2019 Complete Pmp Exam Review Cards

    37/140

    SmoothingWhat use does a

    Gantt Chartprovide?

    What is life-cyclecosting?

    What is a variablecost?

    How is the costperformance index

    (CPI) figured?

    Define what apayback period is?

    What is internalrate of return (IRR)?

    What is BCWS orPV?

    How is schedulevariance (SV)

    figured?

    What are directcosts?

  • 7/31/2019 Complete Pmp Exam Review Cards

    38/140

    Deemphasizing theopponents' differencesand emphasizing their

    commonalities over

    the issues in question.

    To identify when aparticular resource

    is (or will be)working on a

    particular task.The concept of

    including acquisition,operating, and disposalcosts when evaluating

    various alternatives.

    Costs that risedirectly with the

    size of the project.

    CPI = BCWP /ACWPor EV / AC

    The number of times periodsup to the point at which

    cumulative revenues exceedcumulative costs and,

    therefore, the project hasturned a profit.

    The percentage ratethat makes the presentvalue of costs equal to

    the present value ofbenefits.

    Budgeted cost ofwork scheduled or

    planned value.

    SV = BCWP - BCWSor EV - PV

    Costs incurreddirectly by a

    specific project.

  • 7/31/2019 Complete Pmp Exam Review Cards

    39/140

    Level of Effort(LOE) Lead

    Late Start Date (LS) Late Finish Date(LF)

    Lag Invitation for Bid(IFB)

    Initiation InformationDistribution

    Hanger Hammer

  • 7/31/2019 Complete Pmp Exam Review Cards

    40/140

    Support-type activity (e.g.,vendor or customer liaison) that

    does not readily lend itself tomeasurement of discrete

    accomplishment. It is generallycharacterized by a uniform rateof activity over a specific period

    of time.

    A modification of a logicalrelationship which allows an

    acceleration of the successortask. For example, in a

    finish-to-start dependency with a10-day lead, the successor

    activity can start 10 days before

    the predecessor has finished.

    In the critical path method, thelatest possible point in timethat an activity may begin

    without delaying a specifiedmilestone (usually the project

    finish date).

    In the critical path method, thelatest possible point in time

    that an activity may becompleted without delaying aspecified milestone (usually

    the project finish date).

    A modification of a logicalrelationship which directs a

    delay in the successor task. Forexample, in a finish-to-start

    dependency with a 10-day lag,the successor activity cannot

    start until 10 days after the

    predecessor has finished.

    Generally, this term isequivalent to request for

    proposal. However, insome application areas itmay have a narrower or

    more specific meaning.

    Committing theorganization tobegin a project

    phase.

    Making neededinformation available

    to projectstakeholders in a

    timely manner.An unintended break ina network path. Hangers

    are usually caused bymissing activities or

    missing logical

    relationships.

    An aggregate or summaryactivity (a group of related

    activities is shown as one andreported at a summary level).A hammock may or may nothave an internal sequence.

  • 7/31/2019 Complete Pmp Exam Review Cards

    41/140

    GraphicalEvaluation and

    Review Technique(GERT)

    Grade

    FunctionalOrganization Functional Manager

    Free Float (FF) Forward Pass

    FloatFixed Price

    Incentive Fee (FPIF)Contract

    Firm Fixed Price(FFP) Contract Finish Date

  • 7/31/2019 Complete Pmp Exam Review Cards

    42/140

    A network analysis techniquethat allows for conditional and

    probabilistic treatment oflogical relationships (i.e.,

    some activities may not beperformed).

    A category or rank used todistinguish items that have the

    same functional use (e.g.,hammer) but do not share thesame requirements for quality(e.g., different hammers mayneed to withstand different

    amounts of force).

    An organization structure inwhich staff are grouped

    hierarchically by specialty (e.g.,production, marketing,

    engineering, and accounting atthe top level; with engineering,further divided into mechanical,

    electrical, and others).

    A manager responsible foractivities in a specializeddepartment or function

    (e.g., engineering,manufacturing,

    marketing).The amount of time anactivity can be delayed

    without delaying theearly start of any

    immediately following

    activities.

    The calculation of theearly start and earlyfinish dates for the

    uncompleted portions ofall network activities.

    The amount of time that an activitymay be delayed from its early startwithout delaying the project finish

    date. Float is a mathematicalcalculation and can change as the

    project progresses and changes aremade to the project plan. Also called

    slack, total float, and path float.

    A type of contract where thebuyer pays the seller a setamount (as defined by the

    contract), and the seller canearn an additional amount if it

    meets defined performancecriteria.

    A type of contract wherethe buyer pays the sellera set amount (as defined

    by the contract)regardless of the sellers

    costs.

    A point in time associated withan activitys completion.

    Usually qualified by one of thefollowing: actual, planned,

    estimated, scheduled, early,late, baseline, target or

    current.

  • 7/31/2019 Complete Pmp Exam Review Cards

    43/140

    Fast Tracking Expected MonetaryValue

    Exception Report Event-on-Node

    Estimate ToComplete (ETC)

    Estimate AtCompletion (EAC)

    Estimate Effort

    Earned Value (EV) Early Start Date(ES)

  • 7/31/2019 Complete Pmp Exam Review Cards

    44/140

    Compressing the projectschedule by overlapping

    activities that would normallybe done in sequence, such as

    design and construction.Sometimes confused with

    concurrent engineering.

    The product of an eventsprobability of occurrence and the

    gain or loss that will result. Forexample, if there is a 50 percent

    probability that it will rain, and rainwill result in a $100 loss, the

    expected monetary value of the

    rain event is $50 (.5 x $100).

    Document thatincludes only majorvariations from plan

    (rather than all

    variations).

    A network diagrammingtechnique in which events are

    represented by boxes (or nodes)connected by arrows to show

    the sequence in which theevents are to occur. Used in theoriginal Program Evaluation and

    Review Technique.

    The expected additional costneeded to complete an activity, agroup of activities, or the project.Most techniques for forecastingETC include some adjustment to

    the original estimate based onproject performance to date.

    The expected total cost of an activity, agroup of activities, or of the project when

    the defined scope of work has beencompleted. Most techniques for

    forecasting EAC include some adjustmentof the original cost estimate based on

    project performance to date. Also shown asestimated at completion. Often shown as

    EAC = Actuals-to-date + ETC.

    An assessment of the likely quantitativeresult. Usually applied to project costs anddurations and should always include someindication of accuracy (e.g., x percent).

    Usually used with a modifier (e.g.,preliminary, conceptual, feasibility). Someapplication areas have specific modifiers

    that imply particular accuracy ranges (e.g.,order-of-magnitude estimate, budget

    estimate, and definitive estimate in

    engineering and construction projects).

    The number of labor unitsrequired to complete anactivity or other project

    element. Usually expressed asstaffhours, staffdays, or

    staffweeks. Should not beconfused with duration.

    (1) A method for measuring projectperformance. It compares the amount of work

    that was planned with what was actuallyaccomplished to determine if cost and scheduleperformance is as planned. See also actual cost

    of work performed, budgeted cost of workscheduled, budgeted cost of work performed,

    cost variance, cost performance index, schedulevariance, and schedule performance index. (2)

    The budgeted cost of work performed for an

    activity or group of activities.

    In the critical path method, the earliestpossible point in time on which the

    uncompleted portions of an activity (orthe project) can start, based on the

    network logic and any scheduleconstraints. Early start dates can

    change as the project progresses andchanges are made to the project plan.

  • 7/31/2019 Complete Pmp Exam Review Cards

    45/140

    Early Finish Date(EF)

    DurationCompression

    Duration Dummy Activity

    Deliverable Data Date

    Current Start Date Current Finish Date

    Critical PathMethod (CPM) Critical Path

  • 7/31/2019 Complete Pmp Exam Review Cards

    46/140

    In the critical path method, the earliestpossible point in time on which the

    uncompleted portions of an activity (orthe project) can finish based on the

    network logic and any scheduleconstraints. Early finish dates can

    change as the project progresses andchanges are made to the project plan.

    Shortening the projectschedule without reducingthe project scope. Durationcompression is not always

    possible and often requires

    an increase in project cost.

    The number of work periods (notincluding holidays or other

    non-working periods) required tocomplete an activity or other project

    element. Usually expressed asworkdays or workweeks. Sometimesincorrectly equated with elapsed time.

    An activity of zero duration used toshow a logical relationship in the

    arrow diagramming method. Dummyactivities are used when logical

    relationships cannot be completely orcorrectly described with regular

    activity arrows. Dummies are showngraphically as a dashed line headed by

    an arrow.

    Any measurable, tangible, verifiableoutcome, result, or item that must be

    produced to complete a project or partof a project. Often used more narrowlyin reference to an external deliverable,which is a deliverable that is subject to

    approval by the project sponsor orcustomer.

    The point in time thatseparates actual

    (historical) data fromfuture (scheduled) data.

    Also called as-of date.

    The current estimateof the point in time

    when an activity willbegin.

    The current estimateof the point in time

    when an activity willbe completed.

    A network analysis technique used topredict project duration by analyzing whichsequence of activities (which path) has theleast amount of scheduling flexibility (the

    least amount of float). Early dates arecalculated by means of a forward pass

    using a specified start date. Late dates arecalculated by means of a backward passstarting from a specified completion date

    (usually the forward passs calculated

    project early finish date).

    In a project network diagram, the series ofactivities which determines the earliest

    completion of the project. The critical path willgenerally change from time to time as activities

    are completed ahead of or behind schedule.Although normally calculated for the entire

    project, the critical path can also be determinedfor a milestone or subproject. The critical path isusually defined as those activities with float less

    than or equal to a specified value, often zero.

  • 7/31/2019 Complete Pmp Exam Review Cards

    47/140

    Critical Activity Crashing

    Cost Variance (CV) Cost Plus IncentiveFee (CPIF) Contract

    Cost Plus Fixed Fee(CPFF) Contract

    Cost PerformanceIndex (CPI)

    Cost of Quality Cost Estimating

    Cost Control Cost Budgeting

  • 7/31/2019 Complete Pmp Exam Review Cards

    48/140

    Any activity on a critical path.Most commonly determined byusing the critical path method.Although some activities are

    critical in the dictionary sensewithout being on the critical path,

    this meaning is seldom used in

    the project context.

    Taking action to decrease thetotal project duration after

    analyzing a number ofalternatives to determine howto get the maximum duration

    compression for the least

    cost.

    (1) Any differencebetween the estimated

    cost of an activity and theactual cost of that

    activity. (2) In earned

    value, BCWP less ACWP.

    A type of contract where thebuyer reimburses the seller

    for the sellers allowable costs(allowable costs are defined

    by the contract), and the sellerearns its profit if it meets

    defined performance criteria.

    A type of contract where thebuyer reimburses the seller

    for the sellers allowablecosts (allowable costs are

    defined by the contract) plus afixed amount of profit (fee).

    The ratio of budgeted costs toactual costs (BCWP/ACWP). CPI

    is often used to predict themagnitude of a possible costoverrun using the following

    formula: original costestimate/CPI = projected cost at

    completion.

    The costs incurred toensure quality. The cost

    of quality includesquality planning, quality

    control, quality

    assurance, and rework.

    Estimating the costof the resources

    needed to completeproject activities.

    Controllingchanges to theproject budget.

    Allocating the costestimates to

    individual projectcomponents.

  • 7/31/2019 Complete Pmp Exam Review Cards

    49/140

    Corrective Action Control Charts

    Control Contract Close-out

    ContractWhat are the 3

    general types ofcontracts?

    Fixed price or lumpsum contracts

    Cost reimbursablecontracts

    Unit price contracts ContingencyReserve

  • 7/31/2019 Complete Pmp Exam Review Cards

    50/140

    Changes made tobring expected

    future performanceof the project into

    line with the plan.

    Control charts are a graphicdisplay of the results, over

    time and against establishedcontrol limits, of a process.

    They are used to determine ifthe process is in control or

    in need of adjustment.

    The process of comparingactual performance with

    planned performance, analyzingvariances, evaluating possible

    alternatives, and takingappropriate corrective action as

    needed.

    Completion andsettlement of the

    contract, includingresolution of all

    outstanding items.A contract is a mutually

    binding agreement whichobligates the seller toprovide the specified

    product and obligates the

    buyer to pay for it.

    Fixed price or lumpsum contracts, Cost

    reimbursablecontracts, Unit price

    contractsThis type of contract involves a

    fixed total price for a well-definedproduct. Fixed price contractsmay also include incentives formeeting or exceeding selected

    project objectives such asschedule targets.

    This type of contract involves payment(reimbursement) to the contractor for its actual costs.

    Costs are usually classified as direct costs (costsincurred directly by the project, such as wages formembers of the project team) and indirect costs(costs allocated to the project by the performing

    organization as a cost of doing business, such assalaries for corporate executives). Indirect costs are

    usually calculated as a percentage of direct costs.Cost reimbursable contracts often include incentivesfor meeting or exceeding selected project objectives

    such as schedule targets or total cost.

    With this type of contract thecontractor is paid a preset amount perunit of service (e.g., $70 per hour for

    professional services or $1.08 percubic yard of earth removed) and the

    total value of the contract is a functionof the quantities needed to complete

    the work.

    A separately plannedquantity used to allow for

    future situations whichmay be planned for onlyin part (sometimes called

    known unknowns).

  • 7/31/2019 Complete Pmp Exam Review Cards

    51/140

    Do you includecontingency

    reservers in theschedule baseline?

    Why would you usecontingency

    reserves?

    Are contingencyreservers only usedwhen dealing with

    costs?

    ContingencyPlanning

    ConcurrentEngineering

    CommunicationsPlanning

    Code of Accounts Chart of Accounts

    Change ControlBoard (CCB) Calendar Unit

  • 7/31/2019 Complete Pmp Exam Review Cards

    52/140

    Yes, contingencyreserves are normally

    included in theprojects cost and

    schedule baselines.

    Contingency reservesare intended to

    reduce the impact ofmissing cost or

    schedule objectives.

    No, contingencyreserves mayinvolve cost,

    schedule, or both.

    The development of amanagement plan thatidentifies alternative

    strategies to be used toensure project success if

    specified risk events occur.

    An approach to projectstaffing that, in its mostgeneral form, calls for

    implementors to be involvedin the design phase.

    Sometimes confused with fast

    tracking.

    Determining theinformation andcommunications

    needs of the project

    stakeholders.Any numberingsystem used to

    uniquely identify eachelement of the work

    breakdown structure.

    Any numbering system used tomonitor project costs by

    category (e.g., labor, supplies,materials). The project chart of

    accounts is usually based uponthe corporate chart of accounts

    of the primary performing

    organization.

    A formally constitutedgroup of stakeholders

    responsible forapproving or rejectingchanges to the project

    baselines.

    The smallest unit of time used inscheduling the project. Calendar

    units are generally in hours,days, or weeks, but can also be

    in shifts or even in minutes. Usedprimarily in relation to project

    management software.

  • 7/31/2019 Complete Pmp Exam Review Cards

    53/140

    Budgeted Cost ofWork Scheduled

    (BCWS)

    Budgeted Cost ofWork Performed

    (BCWP)

    Budget AtCompletion (BAC) Baseline

    Bar Chart Gantt chart

    Backward Pass Arrow DiagrammingMethod (ADM)

    Arrow Application Area

  • 7/31/2019 Complete Pmp Exam Review Cards

    54/140

    The sum of the approved costestimates (including anyoverhead allocation) foractivities (or portions of

    activities) scheduled to beperformed during a given period

    (usually project-to-date).

    The sum of the approved costestimates (including anyoverhead allocation) foractivities (or portions of

    activities) completed during agiven period (usually

    project-to-date).

    The estimated totalcost of the project

    when done.

    The original plan (for a project,a work package, or an activity),

    plus or minus approvedchanges. Usually used with amodifier (e.g., cost baseline,

    schedule baseline, performance

    measurement baseline).

    A graphic display of schedule-relatedinformation. In the typical bar chart,

    activities or other project elements arelisted down the left side of the chart,dates are shown across the top, and

    activity durations are shown asdate-placed horizontal bars. Also

    called a Gantt chart.

    A graphic display of schedule-relatedinformation. In the typical bar chart,

    activities or other project elements arelisted down the left side of the chart,dates are shown across the top, and

    activity durations are shown asdate-placed horizontal bars. Also

    called a Bar chart.

    The calculation of late finish dates andlate start dates for the uncompleted

    portions of all network activities.Determined by working backwardsthrough the network logic from the

    projects end date. The end date maybe calculated in a forward pass or set

    by the customer or sponsor.

    A diagramming technique in whichactivities are represented by arrows.The tail of the arrow represents thestart and the head represents thefinish of the activity. Activities are

    connected at points called nodes toillustrate the sequence in which the

    activities are expected to be

    performed.

    The graphicpresentation of an

    activity.

    A category of projects thathave common elements not

    present in all projects.Application areas are usuallydefined in terms of either theproduct of the project or the

    type of customer.

  • 7/31/2019 Complete Pmp Exam Review Cards

    55/140

    Is stakeholdermanagerment aproactive task?

    What is the tripleconstraint and what

    is it used for?

    What is meant bythe word

    internationalization?

    What isSocial-Econominc

    EnvironmentalSustainability?

    Should youincorporate

    stakeholders'requirements into a

    project?

    What does theinitiating process

    do?

    What is the meantby the planning

    process?

    What is down in theexecuting process?

    What is done in thecontrolling

    process?

    What is done in theclosing process?

  • 7/31/2019 Complete Pmp Exam Review Cards

    56/140

    Yes, stakeholdermanagement is a

    proactive task.

    The triple constraint istime, cost, quality. It is

    used to identify the threemost important factors thata project manager needs to

    consider in a project.

    Consideration oftime-zone differences,national and regional

    holidays. travelrequirements, and other

    logistical issues.

    Being accountablefor impacts resultingfrom a project both

    social and

    economic.Yes, always

    incorporate thestakeholder's

    requirements into

    the project.

    It authorizes theproject of phase.

    This process is usedfor defining and

    refining objectivesand selecting the best

    of the alternatives.

    During this phasepeople are coordinatingwith other resources to

    carry out the projectphase or plan.

    This process is for ensuringthat project objectives are metby monitoring and measuringprogress in order to indetifyvariances from the plan so

    that corrective action can betaken if and when necessary.

    This process is whenformailizing acceptanceof the project or phase

    is completed in thehopes of bringing it to

    an orderly end.

  • 7/31/2019 Complete Pmp Exam Review Cards

    57/140

    What is a tightmatrix?

    In a strong matrixwhat type of

    power/authoritydoes the project

    manager have?

    In a weak matrixdoes the project

    manager have muchauthority?

    Project Coordinator

    Project Expeditor

    What are someadvantages/benefits

    of a functionalorganization?

    What are somedisadvantages of a

    functionalorganization?

    Is scope verificationnecessary when a

    project isterminated?

    Will managementby objectives work

    if managementdoesn't support it.

    Dephi Technique

  • 7/31/2019 Complete Pmp Exam Review Cards

    58/140

    This refers tolocating the officesfor the project team

    in the same

    room/location.

    In this type ofmatrix the power

    rests with theproject manager.

    No, thepower/authority

    rests with thefunctional manager.

    An individual who reports to ahigher-level manager in the

    organization, has the authority toassign work to individuals in

    various functional organizations,and shares authoity and

    resources with the functional

    manager.

    An individual who is a staffassistant to an executive whohas the ultimate responsibilityfor the project. Has authority

    only in his managers departmentbut not over resources from

    other departments.

    1) Easier management ospecialist's, 2) Team

    memebers only report to 1boss, 3) Clearly defined

    careeer paths, 4)

    resources are centralized.1) The project manager

    has NO authority, 2)People place moreemphasis on their

    speciality than to the

    project.

    Yes, scope verifcation isnecessary when a project

    is terminated, italthoughs the

    organization to determine

    the level of completion.

    No, in orer to workproperly, it must be

    supported bymanagement.

    A mthod to obtain opinions onissues. Information sent to

    experts, responses are compiledand the results are sent back forfurther review. Using the delphi

    technique helps reduce bias andundue influence.

  • 7/31/2019 Complete Pmp Exam Review Cards

    59/140

    What type ofdiagram uses

    dummy activities?

    What are the threeuses for dummy

    activites?

    What is theexpectancy theory?

    What is problemsolving/confrontation?

    Give three examplesof hygiene factors inHerzberg's theory ofmotivation. How do

    they affect motivation.

    What is McGregor'sTheory X?

    What is McGregor'stheory Y?

    What is anorganizational

    breakdownstructure (OBS)?

    What is the purposeof a resource Gantt

    chart?

    Does the matrix formof project

    organization facilitateor complicate project

    team development?

  • 7/31/2019 Complete Pmp Exam Review Cards

    60/140

    Activity-On-ArrowNetwork.

    1) logic, 2) timedelay and, 3)uniqueness.

    It holds that people tend to behighly productive and

    motivated if they believe theirefforts will lead to successful

    results and they will berewarded for their success.

    Addressing conflict directly bygetting the parties to work

    together to define theproblem, collect information,

    develop and analyzealternatives, and select the

    most appropriate alternative.

    Pay, attitude of supervisor, andworking conditions.

    y motivation,but improving hygiene factors in not

    likely to increase motivation.Motivators are an opportunity to

    achieve and experienceself-actualization.

    Traditional approach: workersare self-centered, lazy, lackingambition. Managers organize

    the elements of theproductive enterprise in theinterest of economic ends.

    Workers are not by natureresistant to organizationalneeds; they are willing and

    eager to acceptresponsibilities and are

    concerned with self-growthand fulfillment.

    A specific type oforganizational chart

    that shows whichunits are responsible

    for which work items

    It identifies when aparticular resource

    is or will be workingon a particular task.

    It complicates teamdevelopment because

    team members areaccountable to both a

    functional manager and

    a project manager.

  • 7/31/2019 Complete Pmp Exam Review Cards

    61/140

    Name three majorforms of projectorganizational

    structure.

    What is aprojectized

    organization?

    Describe thedifference betweena weak matrix and a

    strong matrix.

    What is a project"war room" and

    what is its benefit?

    What is varianceanalysis?

    What is activelistening?

    What is majorcause of conflictwith functional

    managers?

    What is mostdifficult conflict to

    deal with?

    What is earned valueanalysis and how is

    it used inperformance

    reporting?

    What is the tool forused for

    communicationplanning?

  • 7/31/2019 Complete Pmp Exam Review Cards

    62/140

    Functional, Matrix,and Projectized

    One in which a separate,functional organizationis established for eachproject. Personnel areassigned on a full-time

    basis.

    Weak matrices are similar tofunctional organizations.

    Strong matrices are similar toprojectized organizations

    (with balance of power tippedtoward the project manager)

    A single location for the team toget together for any purpose. Itprovides a repository for project

    artifacts, records, andup-to-date schedules and status

    reports. It gives an identity to

    the project team.

    Comparing actualproject results to

    planned or expectedresults in terms of cost,schedule, scope, quality,

    and risk.

    Listening in which therecipient is attentive

    and asks forclarification of

    ambiguous messages

    SchedulesPersonalityconflicts

    An analysis thatintegrates cost and

    schedule measures. It isused to help the project

    management team assess

    project performance.

    Stakeholderanalysis

  • 7/31/2019 Complete Pmp Exam Review Cards

    63/140

    5 Phases of ProjectManagement Initiation Phase Activities

    Planning Phase CoreProcesses

    Planning PhaseFacilitating Processes

    Activity Activity aspects

    Activity definition Activity description

    Activity DurationEstimating Activity-On-Arrow

  • 7/31/2019 Complete Pmp Exam Review Cards

    64/140

    Initiation - Planning -Execution - Control -

    ClosureInitiation

    Scope Planning - ScopeDefinition - Activity Definition -Activity Sequencing - Activity

    Duration Estimating - ResourcePlanning - Cost Estimating -

    Schedule Development - CostBudgeting - Project Plan

    Development

    Quality Planning -Communicaiton Planning - Risk

    ID - Risk Quantification - RiskResponse Devlp -

    Organizational Planning - Staff Acquisition - Procurement

    Planning - Solicitation Planning

    Element of work on aproject

    Duration - Expected cost- Expected resources

    required

    Identifying specificactivities that must beperformed in order to

    produce a project'sdeliverables.

    The scope of work of theactivity. - Used in project

    diagrams.

    Estimating the number of work periods that will be

    needed to completeindividual activities.

    Part of the ArrowDiagramming Method

  • 7/31/2019 Complete Pmp Exam Review Cards

    65/140

    Activity-On-Node Actual Cost of WorkPerformed

    Actual Finish Date Actual Start Date

    Administrative Closure Application Area

    Arrow Arrow DiagrammingMethod

    As-Of Date Backward Pass

  • 7/31/2019 Complete Pmp Exam Review Cards

    66/140

    Part of the PrecedenceDiagramming Method

    Total costs incurred(direct and indirect) for a

    project.

    When work ends.When work starts.

    Formalized project end.Type of: product, project

    or customer. - There isoften overlap

    Graphic presentation of an activity.

    Graphical representationof a project where

    activities are representedby arrows.

    Same as Data DateCalculating a projectlength based on end-date

  • 7/31/2019 Complete Pmp Exam Review Cards

    67/140

    Bar Chart Baseline

    Baseline Finish Date Baseline Start Date

    Budget at Completion Budget Estimate

    Budget Cost of WorkPerformed

    Budgeted Cost of WorkScheduled

    Calendar Unit Change Control Board

  • 7/31/2019 Complete Pmp Exam Review Cards

    68/140

    Left side = Projectelements Bottom = Date

    range (Also called =GANTT Chart)

    The original plan

    Scheduled Finish DateScheduled Start Date

    The estimated total costof the project when done.Estimate

    Sum of approved costestimates completed.Part of Earned Value

    Sum of approved costestimates not yet

    completed. Part of Earned Value

    Smaller unit (Hours -Days - Weeks - Shifts -

    Minutes)

    Group of stakeholdersresponsible for

    approving or rejectingchanges in the project

    baseline.

  • 7/31/2019 Complete Pmp Exam Review Cards

    69/140

    Change in Scope Chart of Accounts

    Charter Code of Accounts

    CommunicationsPlanning Concurrent Engineering

    Contingency Planning Contingency Reserve

    Contract - 3 Categories Contract Definition

  • 7/31/2019 Complete Pmp Exam Review Cards

    70/140

    Scope ChangeNumbering system usedto monitor project costs

    by category.

    Same as project charter

    Numbering system usedto identify each elementof the work breakdown

    structure.

    Determining thecommunication needs

    and procedures for eachstakeholder.

    Not Fast Tracking - Callsfor project

    implementations to beinvolved in the Design

    Phase.

    Risk mitigation plan

    Known Unknowns. Theyare buffers (cost,

    schedules, resources)built into the project

    baseline.

    1 - Fixed price or lumpsum. 2 - Cost

    reimbursable. 3 - Unitprice

    Mutually bindingagreement.

  • 7/31/2019 Complete Pmp Exam Review Cards

    71/140

    Contract - 2 Parts Contract - Fixedprice/Lump Sum

    Contract - Costreimbursable Contract - Unit Price

    Contract Administration Contract Close-out

    Control Control Chart

    Corrective Action Cost Budgeting

  • 7/31/2019 Complete Pmp Exam Review Cards

    72/140

    Seller - delivers productor service. Buyer -obliged to pay for

    product or service.

    Fixed price for awell-defined product or

    service.

    Time and materials.

    Seller is paid a pre-setprice for unit of productor service (i.e. $70 per

    hour)

    Managing therelationship with the

    seller.

    Completion of thecontract.

    Comparing planned vs.actual performance.

    Graphical display of results.

    Used to get a projectback on track.

    Allocating cost estimatesto the actual project.

  • 7/31/2019 Complete Pmp Exam Review Cards

    73/140

    Cost control. Cost Estimating

    Cost of Quality Cost Performance Index= Formula

    Cost Performance Index Project Cost atCompellation

    Cost Plus Fixed FeeContract

    Cost Plus Inventive FeeContract

    Cost Variance Crashing

  • 7/31/2019 Complete Pmp Exam Review Cards

    74/140

    Controlling changes inthe project budget.Estimating project costs

    Cost incurred to ensurequality.CPI = BCWP / ACWP

    Used to predict themagnitude of a project

    cost overrun.

    PCC = Original Cost Est. /CPI

    Time and Materials + afixed profit level.

    Time and Materials +fixed profit level if all

    goals are met.

    BCWP < ACWPDifference between

    estimated and actualcost.

    Taking action todecrease a project

    timeline.

  • 7/31/2019 Complete Pmp Exam Review Cards

    75/140

    Critical Activity Critical Path Method

    Current Finish Date Current Start Date

    Data Date Deliverable

    Dependency Dummy Activity

    Duration Duration Compressing

  • 7/31/2019 Complete Pmp Exam Review Cards

    76/140

    Critical Path MethodThe path with the leastamount of flexibility.

    Current estimate of project completion

    Current estimate of project initiation.

    As-Of-Date. Point of timethat is between historical

    and future date.

    Tangible and verifiableoutcome.

    Requires another step tobe accomplished.

    Zero length. Place holder activities in a project

    schedule.

    Length of time tocomplete an activity.

    Shorten duration withoutdecreasing project

    scope.

  • 7/31/2019 Complete Pmp Exam Review Cards

    77/140

    Early Finish Date Early Start Date

    Earned Value Effort

    Estimate Estimate at Completion

    Estimate to Complete Event-on-Node

    Exception Report Expected Monetary Value

  • 7/31/2019 Complete Pmp Exam Review Cards

    78/140

    Used in the Critical PathMethod. Earliest date theproject can be completed

    by.

    Used in the Critical PathMethod. Earliest date theproject can be started by.

    1 - Method for measuringproject performance. 2 -

    Budgeted cost. 3 -Compares work plannedvs. actually performed.

    Not Duration. Resourceunits needed to complete

    an activity.

    Prediction of costs,resources needed and

    duration.

    EAC = Actuals-to-date +ETC

    Expected additional costneeded to complete an

    activity.

    Project diagrammingmethod that usesconnected boxes.

    Document which showonly major variations to

    the project plan.

    Monetary gain or losedue to an event.

  • 7/31/2019 Complete Pmp Exam Review Cards

    79/140

    Fast Tracking Finish Date

    Firm Fixed Price Contract Fixed Price Incentive FeeContract

    Float Forecast Final Cost

    Forward Pass Fragnet

    Free Float Functional Manager

  • 7/31/2019 Complete Pmp Exam Review Cards

    80/140

    Compressing a projectschedule by overlapping

    activities. Not =Concurrent Engineering

    Project activitiescompleted date.

    Fixed price, regardless of changes in Time and

    Material costs.

    Fixed price with a bonusfor performance.

    Amount of time anactivity can be delayed

    without affecting theproject schedule.

    EST

    Calculating a projecttime-line based on a

    start-date.Subnet

    Amount of time anactivity can be delayed

    without affecting an earlystart of a project.

    Specialized departmentmanager (i.e. Marketing

    Mgr.)

  • 7/31/2019 Complete Pmp Exam Review Cards

    81/140

    Functional Organization Gantt Chart

    Grade Graphical Evaluation andReview Technique

    Hammock Hanger

    Information Distribution Initiation

    Integrated Cost/ScheduleReporting Invitation for Bid

  • 7/31/2019 Complete Pmp Exam Review Cards

    82/140

  • 7/31/2019 Complete Pmp Exam Review Cards

    83/140

    Key Event Schedule Lag

    Late Finish Date Late Start Date

    Lead Level of Effort

    Life-Cycle Costing Line Manager

    Link Logic Diagram

  • 7/31/2019 Complete Pmp Exam Review Cards

    84/140

    Master Schedule

    A step in the project pathmust wait X days after its

    predecessor iscompleted.

    Latest possible date atask can be completed

    without delaying theschedule.

    Latest possible date atask can begin withoutdelaying the schedule.

    A step in the project pathwhich can start X days

    before its predecessor iscompleted.

    Estimate of resourcesneeded to complete the

    task.

    Acquisition - Operating -Disposal costs.

    Considered whenevaluating alternatives.

    A manager who is alsoworking directly on the

    project.

    Connection of stepsProject Network Diagram

  • 7/31/2019 Complete Pmp Exam Review Cards

    85/140

    Logical Relationships (4Types) Finish-to-Start Activity

    Finish-to-Finish Activity Finish-to-Start Activity

    Finish-to-Start Activity Loop

    Management Reserve Master Schedule

    Matrix Organization Milestone

  • 7/31/2019 Complete Pmp Exam Review Cards

    86/140

    Finish-to-start /Finish-to-finish /

    Start-to-start /Start-to-finish

    The FROM activity mustFINISH before the TOactivity can START.

    The FROM activity mustFINISH before the TOactivity can FINISH.

    The FROM activity mustSTART before the TOactivity can FINISH.

    The FROM activity mustSTART before the TO

    activity can FINSH.

    Cannot be in CPM or PERT. Can be in GERT

    Cost and schedulebuffers planned by

    management for unseenevents that would impact

    the project.

    Summary-level schedulethat identifies key

    milestones.

    Project and Functionalmanagers shareresponsibilities.

    Significant event.

  • 7/31/2019 Complete Pmp Exam Review Cards

    87/140

    Mitigation Modern ProjectManagement

    Monitoring Monte Carlo Analysis

    Near-Critical Activity Network Analysis

    Network Logic Network Path

    Node OrganizationalBreakdown Structure

  • 7/31/2019 Complete Pmp Exam Review Cards

    88/140

    Steps to lessen risk bylowering probability.

    Broad / Not focused oncost and time / Focused

    on: scope, cost, timequality, risk, etc.

    Tracking and reportingproject performance and

    status.

    Simulation of Risk thatoccurs throughout the

    project.

    An activity that has lowtotal float.

    The process of identifying early and late

    finish dates for theuncompleted portions of

    project activities.

    A collection of dependencies that makeup the project network

    diagram.

    Connected activities inthe project network

    diagram.

    A junction point in aproject network diagram.

    A depiction of the projectinto work breakdown

    "packages".

  • 7/31/2019 Complete Pmp Exam Review Cards

    89/140

    Organizational Planning Overall Change Control

    Parametric Estimating Pareto Diagram

    Path Path Convergence

    Percent Complete Performance Reporting

    Performing Organization PrecedenceDiagramming Method

  • 7/31/2019 Complete Pmp Exam Review Cards

    90/140

    Identifying, documentingand assigning projectroles, responsibilities

    and reportingrelationships.

    Coordinating changesacross the entire project.

    Estimates based onstatistics and history.

    Histogram ordered byfrequency of occurrence

    that shows multipleresults relating to one

    cause.

    Sequential activities.

    Parallel paths that lead toone milestone, but may

    singularly delay aproject.

    Percent of work alreadyperformed.

    Collecting anddisseminating

    information about projectperformance to help

    ensure project progress.

    The enterprise whoseemployees are most

    directly involved in doingthe work of the project.

    Activities arerepresented by boxes

    and linked sequentially.A diagramming method.

  • 7/31/2019 Complete Pmp Exam Review Cards

    91/140

    Precedence Relationship Predecessor Activity

    Procurement Planning Program

    Program Evaluation andReview Technique Project

    Project Charter Project CommunicationsManagement

    Project CostManagement

    Project Human ResourceManagement

  • 7/31/2019 Complete Pmp Exam Review Cards

    92/140

    Refers to thediagramming methods.

    1 - Arrow DiagrammingMethod - Activity which

    enters a NODE. / 2 -Precedence Diagramming

    Method - Activity whichgoes "away from" the

    NODE.

    Determining what toprocure and when.

    A group of relatedprojects. Usually

    on-going.

    Event-oriented. Used toestimate project

    duration. Used for projects with uncertainly

    in duration.

    A temporary endeavor undertaken to create a

    unique product or service.

    Sr. Management's writtenauthority given to the PM

    for organizationresources.

    Subset project for collecting and dispersing

    project info.

    Subset project for ensuring a project is

    completed within budget.

    Subset project for effectively using

    personnel in the project.

  • 7/31/2019 Complete Pmp Exam Review Cards

    93/140

    Project IntegrationManagement Project Life Cycle

    Project Management Project ManagementBody of Knowledge

    Project ManagementSoftware

    Project ManagementProfessional

    Project ManagementTeam Project Manager

    Project Network Diagram Project Phase

  • 7/31/2019 Complete Pmp Exam Review Cards

    94/140

    Subset project for integrating subset

    projects into the whole.

    A collection of sequentialproject phases.

    The knowledge, skills,tools and techniques to

    meet and exceed astakeholders

    expectations with aproject.

    Book of proven projectmanagement practices.

    Computer applicationdesigned to plan and

    control a project.Certified PM from PMI

    Members of the projectteam.

    Individual responsible for managing the project.

    PERT or GANTTSchematic display of

    project activities.

    A subset collection of project activities.

  • 7/31/2019 Complete Pmp Exam Review Cards

    95/140

    Project Plan Project Plan - Elements

    Is a Project PlanSummary or Detailed?

    Project PlanDevelopment

    Project Plan Execution Project Planning

    Project ProcurementManagement

    Project QualityManagement

    Project Risk Management Project Schedule

  • 7/31/2019 Complete Pmp Exam Review Cards

    96/140

    Formal document usedto guide the project.

    Plan / Cost Assumptions / Schedule / Decisions /

    Scope

    Can be both

    Taking the results of other planning processes

    and putting them into anew document.

    Carrying out the projectplan details.

    Development andmaintenance of the

    project plan.

    Acquiring goods andservices outside of theproject team for use in

    the project.

    Subset of the projectused to ensure the

    project is up torequirements at delivery.

    Subset of the project for identifying and mitigating

    risks.

    Outlines dates for eachactivity in sequential

    order.

  • 7/31/2019 Complete Pmp Exam Review Cards

    97/140

    Project ScopeManagement Project Team Members

    Project TimeManagement Projectized Organization

    Quality Assurance Quality Control

    Quality Planning Remaining Duration

    Request for Proposal Request for Quotation

  • 7/31/2019 Complete Pmp Exam Review Cards

    98/140

    Subset of the projectused to ensure only the

    pre-defined workrequired is done and no

    more.

    They work for the ProjectManager

    Subset of the project thatmonitors and ensures a

    team meeting allmilestone dates.

    Where PM has 100% over project team. No shared

    authority.

    Evaluating process toensure the project will

    satisfy its qualitystandards.

    Process of evaluatingspecific project steps toverify they meet with the

    project quality standards.

    Identifying which qualitystandards are relevant to

    the project.

    Time needed to completean activity.

    Bid document fromcompany to vendor.

    Bid document from acompany to a vendor for

    pricing information.

  • 7/31/2019 Complete Pmp Exam Review Cards

    99/140

    Reserve Resource Leveling

    Resource-LimitedSchedule Resource Planning

    ResponsibilityAssignment Matrix Retainage

    Risk Event Risk Identification

    Risk Quantification Risk Response Control

  • 7/31/2019 Complete Pmp Exam Review Cards

    100/140

    Provision in the projectplan to mitigate cost

    and/or schedule risks.

    Where schedulingconcerns are addressed

    by resource managementconcerns.

    Project where start andend date are based onresource availability.

    Resource identificationprocess.

    Relates projectorganization structure to

    work breakdownstructure.

    Down payment on acontracted product or

    service.

    An occurrence thataffects the projects

    outcome.

    Identifying which riskswill affect the project.

    Identifying probability of the risk.

    Responding to changesin risk over the course of

    the project.

  • 7/31/2019 Complete Pmp Exam Review Cards

    101/140

    Risk ResponseDevelopment S-Curve

    Schedule Control Schedule Development

    Schedule PerformanceIndex Schedule Variance

    Scheduled Finished Date Scheduled Start Date

    Scope Scope Change

  • 7/31/2019 Complete Pmp Exam Review Cards

    102/140

    Risk mitigation planGraph showing

    cumulative cost andlabor over time.

    Controlling changes tothe project schedule

    Analyzing activitysequences, durations

    and resourcerequirements to create a

    project schedule.

    Work performed / WorkSchedule (BCWP /

    BCWS)

    Difference betweenscheduled and actual

    timeframes.

    Planned activity end datePlanned activity startdate

    The sum of the productsand services to be

    provided as a project.Any change to the scope.

  • 7/31/2019 Complete Pmp Exam Review Cards

    103/140

    Scope Change Control Scope Definition

    Scope Planning Scope Verification

    Should-Cost Estimate Slack

    Solicitation Solicitation Planning

    Source Selection Staff Acquisition

  • 7/31/2019 Complete Pmp Exam Review Cards

    104/140

    Controlling changes inthe scope.

    Decomposing the major deliverables into small

    parts.

    Written scopestatements.

    Auditing each scopeelement at the end of aproject for completion.

    Used to judge thereasonableness of a

    vendors quote.Used in PERT for FLOAT

    Obtaining quotes, bidsand offers.

    Document statingrequirements and

    potential sources to meetthose requirements.

    Choosing a vendor or product.

    Getting human resourcesto work on the project.

  • 7/31/2019 Complete Pmp Exam Review Cards

    105/140

    Stakeholder Start Date

    Statement of Work Subnet

    Successor Activity Target Completion Date

    Team Development Time-Scaled NetworkDiagram

    Target Finish Date Target Start Date

  • 7/31/2019 Complete Pmp Exam Review Cards

    106/140

    People directly or indirectly involved in the

    project.Qualified starting date

    A narrative description of products or services to

    be supplied under contract.

    Subproject

    Activity while "leaves"the node.

    A constraining date inthe project diagram.

    Developing teammembers to enhance the

    project.

    Diagram where thephysical shape of each

    activity object isproportional to the

    duration of that activity.

    The date the work for theactivity is planned to be

    completed by.

    The date the work for theactivity is planned to be

    started by.

  • 7/31/2019 Complete Pmp Exam Review Cards

    107/140

    How is contract closeoutsimilar to administrative

    closeout?

    How is performancereporting used as a tool

    for contractadministration?

    When are paymentrequests an output of

    contract administration?

    Describe thecharacteristics of aunilateral contract?

    What is a unilateralcontract?

    Under what two conditionsmust PMI members refrainfrom offering or accepting

    monetary payments or other forms of compensation or

    tangible benefits?

    What is the most criticalculture for the success of

    a project manager working internationally?

    Who can initiate anethics complaint?

    When is a PMPresponsible for reporting

    to PMI possibleviolations of the PMPCode of Professional

    Conduct?

    What are the twoconditions under which

    PMI member's do not haveto honor and maintain theprivacy and confidentiality

    of client information?

  • 7/31/2019 Complete Pmp Exam Review Cards

    108/140

    Both contract closeout andadministrative closure

    involve product verification.However, the contract terms

    and conditions may prescribespecific procedures for

    contract closeout.

    it provides managementwith information about

    how effectively the seller is achieving the

    contractual objectives.

    When the project is usingan external payment

    system.

    It usually takes the formof a purchase order -- a

    standard form listingroutine items at standard

    prices.

    A contract that has onlyone signature (the

    issuer).

    When payments do notconform with applicablelaws and when they may

    provide an unfair advantage for themselves

    or their business.

    LeadershipAny person, group, or

    organization, includingPMI.

    When reasonable andclear facts exist to verify

    the violation.

    1) if granted permission bythe customer, client, or

    employer, and 2) If maintaining the

    confidentiality is otherwiseunethical or unlawful.

  • 7/31/2019 Complete Pmp Exam Review Cards

    109/140

  • 7/31/2019 Complete Pmp Exam Review Cards

    110/140

  • 7/31/2019 Complete Pmp Exam Review Cards

    111/140

    What is the differencebetween attribute

    sampling and variablesampling?

    In which project phase isquality control

    performed?

    What is the differencebetween a tolerance and

    a control limit?

    What are the three (3) keyoutputs from

    administrative closure?

    Name five barriers toeffective project

    communications.

    Name threecommunications

    channels in anorganization?

    Why is communicationsplanning so tightly linkedto project organizational

    planning?

    What is active listening?

    What is earned valueanalysis and how is itused in performance

    reporting?

    List the four parts of thecommunication model.

  • 7/31/2019 Complete Pmp Exam Review Cards

    112/140

    Attribute sampling determineswhether the result does or does

    not conform to the specifications.In variable sampling, the result israted on a continuous scale that

    measures the degree of conformance within a

    pre-established acceptable range.

    Quality control isperformed throughout allphases of the project life

    cycle.

    A tolerance establishesthe range of acceptable

    results. A control limit iscomputed based on the

    results themselves.

    1) Project archives, 2)Project closure, 3)Lessons learned.

    1) Lack of clear communicationchannels. 2) Physical distance

    between communicator andreceiver, 3) Difficulties withtechnical language, 4)Distracting environmental

    factors, 5) Detrimental attitudes.

    Personal, Organization,Grapevine

    Because the project'sorganizational structurewill have a major effect

    on projectcommunications.

    Listening in which therecipient is attentive andasks for clarification of ambiguous messages.

    An analysis that integratescost and schedule

    measures. It is used t helpthe project management

    team assess projectperformance.

    Communicator, Message,Medium, Recipient

  • 7/31/2019 Complete Pmp Exam Review Cards

    113/140

    What is the differencebetween a risk and a

    problem?

    When should EAC becalculated by AC + BAC -

    EV?

    When should EAC becalculated by AC + (BAC

    - EV) / CPI?

    What does thebenefit-cost ratio not tell

    you?

    if a project is experiencingquality problems, should

    the project manager devote more resources to

    inspection of to

    prevention?

    What are the seven (7)main quality control

    tools, often called the"basic seven" tools?

    does the matrix form of project organization

    facilitate or complicateproject team

    development? Why?

    Project Human ResourceManagement compriseswhich three processes?

    How is simulation usedin activity duration

    estimating and what isthe most common type of

    simulation?

    At which phase(s) in theproject life cycle is

    significant risk thoughtto have the greatest

    impact?

  • 7/31/2019 Complete Pmp Exam Review Cards

    114/140

    A risk is a future event; ithas not yet occurred. A

    problem, on the other hand, currently exists.

    When current variancesare seen as atypical, andthe project management

    team's expectation is thatsimilar variances will not

    occur in the future.

    When the currentvariances are seen as

    typical of futurevariances.

    The absolute value of thebenefit or cost.

    Prevention, becausepreventing a problem is

    far less costly, thanfixing a problem.

    1) Flowcharts, 2)Diagrams, 3) Pareto

    Diagram, 4)Cause-and-Effect Diagram,

    5) Graphs, 6) Control

    Charts, 7) Checklists

    It complicates projectteam development.

    Because team membersare accountable to both afunctional manager and

    the project manager.

    1) Organizationalplanning, 2) Staff

    acquisition, 3) Teamdevelopment

    To calculate multiple durations withdifferent sets of assumptions.

    Monte Carlo Analysis, in which adistribution of probable results is

    defined for each activity and used tocalculate a distribution of probable

    results for the total project.

    Project execution andcloseout.

  • 7/31/2019 Complete Pmp Exam Review Cards

    115/140

    Project Plan Execution- Inputs

    Project PlanDevelopment - Tools

    Project Plan Execution- Tools

    Integrated ChangeControl - Inputs

    Integrated ChangeControl - Tools Initiation - Inputs

    Initiation - Tools Scope Planning - Tools

    Scope Planning -Inputs

    Scope Definition -Tools

  • 7/31/2019 Complete Pmp Exam Review Cards

    116/140

    Project plan,supporting details,

    organizational policies,preventive action,

    corrective action

    Project planningmethodology, stakeholder

    skills & knowledge, projectmanagement information

    system (PMIS), earned

    value management (EVM)

    General management skills,product skills & knowledge,work authorization system,

    project managementinformation system (PMIS),

    and organization procedures

    Project plan,performance reports,

    change requests

    Change control system,configuration