company profile - neovibe blog · irrigation pipeline installation. 4. ... dubai, u a e) client :...

28
COMP “Novelt Pro PANY PROFIL ty, Reliability, Responsibility & osperity of its Services” LE

Upload: hoangque

Post on 08-Jun-2018

238 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

COMPANY PROFILE

“Novelty, Reliability, Responsibility

&

Prosperity of its Services”

COMPANY PROFILE

“Novelty, Reliability, Responsibility

&

Prosperity of its Services”

COMPANY PROFILE

“Novelty, Reliability, Responsibility

&

Prosperity of its Services”

Page 2: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

INTRODUCTION

TAURUS GENERAL CONTRACTING L.L.C. is envisaged as a service

provider in Construction Industry, covering Rain water Drainage

Contracting, Sub-Sewage Networks Connections & Homes

Connections Contracting, On-Shore & Off-Shore Oil and Gas field

Services, Sub-Water Networks Contracting works.

TAURUS instituted its office in the capital city of Abu Dhabi in

2010. TAURUS is able to allocate an entire workforce for a specific

project from professionally qualified engineers backed by university

degrees in engineering construction and engineering management

to administrative support staff to field hands. Also, hiring

domestically enables the company to become well integrated into

the community.

Page 3: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

ACTIVITIES

PIPELINE PROJECTS

1. Chilled water pipe line installations.

2. Storm water pipeline installation.

3. Irrigation pipeline installation.

4. Sewerage Works (Relocation, Sewer Diversion including

inflatable stopper installation and over pumping.)

CIVIL WORKS

1. Small building construction works.

2. Minor road works.

3. All kind of surveying works.

4. Excavation and leveling works.

5. Foundations constructions.

Page 4: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

ORGANIZATION CHART

GENERAL MANAGER

ANOJ S. KUMAR

FINANCE

FAISAL

HR

JISHA DIPU

FOREMAN

VINOD, GUNA

HSE ENGINEER

MOHAMED JAVED

SUPERVISOR

NOUFAL

WORK FORCE&

MACHINERY

PROJECT DIRECTOR

C.P.S. KUMAR

PROJECT ENGINEER

AKHIL

SITE ENGINEER

RATHEESHKUMAR

Page 5: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

List of Organization Key Staff

Name Position Phone No.

Anoj S. Kumar General Manager +971-56-1234701

C.P Suresh Kumar Project Director +971-50-6616542

Akhil Project Engineer +971-50-9934281

Ratheesh Kumar Site Engineer +971-55-9947030

Javed Safety +971-56-2376813

Vinod Foreman +971-55-2097577

ABU DHABI OFFICE

P.O. Box:- 36402 – Defense Street – Abu Dhabi – U.A.E

Tel: 02 – 6506023

Fax: 02 - 6506026

Email: [email protected]

Page 6: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

CV OF PROJECT DIRECTOR

C.P. Suresh KumarAddress : Abu DhabiMobile No. : 00971553007016E-mail : [email protected]

Personal Information

Age : 53 years oldDate of Birth : 15 May 1960Nationality : IndianGender : MalePassport No. : 1240409Permanent Residence : IndiaLanguages Known : English, Hindi, Malayalam & Arabic

Qualifications

Diploma in Civil Engineering (3 Years Course)

Professional Experience (27 years in various utility projects)

Project ManagerMay 2012 to March 2013 Client : Todini Costruzioni Generali Spa(Arabtec Eng. Services LLC Project : R881/3A - Comprehensive RoadDubai U.A.E) Improvement-Diversion

Underground ServiceLocation : Dubai U.A.E

Consultant: Parsons International

Project Manager2011 September to 2012February(MACE Contractors L.L.CAbu Dhabi, U A E)

Client : Al Naboodah National ContractingGroup L.L.C

Project : Al Ras Al Akhdar and BaynoonahStreet Improvements Package 1&2

Location : Abu Dhabi, U.A.EConsultant : Parsons International

Page 7: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

Project Manager2010 July to 2011 August

(MACE Contractors L.L. CAbu Dhabi, U A E)

Client : Samsung Saif Bin Darwish JVProject : Upgrading Al Salam Street and Abu

Dhabi City Ring Road - Storm WaterWorks.

Location : Abu Dhabi, U.A.EConsultant : Parsons International

Project Manager2009 June to 2010 June(MACE Contractors L.L.CAbu Dhabi, U A E)

Client : Al Naboodah - MubadallaProject : Sowah Island Sewerage Works &

Potable Water WorksLocation : Abu Dhabi, U.A.EConsultant : Keo International / Tebodin, Middle

East, Abu Dhabi

Project Manager2009 January to 2009 May(MACE Contractors L.L.CAbu Dhabi, U A E)

Client : CAT / TABREEDProject : Yas Island Underground Chilled Water.

Piping Networks – Civil WorksLocation : Abu Dhabi, U.A.EConsultant: M/s Tebodin, Middle East, Abu Dhabi

2008 June to 2008 December(MACE Contractors L.L.CAbu Dhabi, U A E)

Client : Abu Dhabi Distribution CompanyProject : Diversion of 600dia & 250dia Potable

Water Line in Plot no–W45, (1600mts)Khalidiya, Abu Dhabi

Location : Abu Dhabi, U.A.ESupervision: Project Department ADSSC.

Project Manager2007 February to 2008 May(MACE Contractors L.L.CAbu Dhabi, U A E)

Client : Emicool / CAT DubaiProject : Dubai Investment Park Chilled Water

Networks.Consultant: Khatib & Alami & Shankland Cox Ltd.

Page 8: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

Site Engineer2006 June to 2007 January(MACE Contractors L.L.CAbu Dhabi, U A E)

Client : CAT / TABREEDProject : Chilled Water Networks Connections to

Abu Dhabi Government Head Quartersand Potable Water Line Connection toTabreed Chilling Plant.

Consultant: Tebodin Middle East.

Site Engineer2004 June to 2006 May(MACE Contractors L.L.CAbu Dhabi, U A E)

Client : Abu Dhabi MunicipalityProject : C 186/3-Sewer Bypass to Pumping

Stations in Abu DhabiConsultant: M/s Hyder Consultants.

Site Engineer2002 January to 2004 May(MACE Contractors L.L.CAbu Dhabi, U A E)

Client : Abu Dhabi Municipality, SewerageProjects Committee

Project : C142/20 Various Sewerage & DrainageMiscellaneous works in Abu Dhabi

Consultant: M/s Hyder Consultants.Position : Site Engineer.

Site Engineer2000 January to 2001DecemberMACE Contractors L.L.CAbu Dhabi, U A E

Client : Abu Dhabi Municipality, SewerageProjects Committee

Project : C142/16 Various Sewerage & Drainageworks in Abu Dhabi

Consultant: M/s Hyder Consultants.

Site Engineer1998 February to 1999December(MIDFA MACEContractors L.L.CDUBAI, U A E)

Client : Dubai MunicipalityProject : DS 68/1A – Jumeira and Al Saffa

Drainage Miscellaneous and Sewerworks

Consultant: M/s Khatib & Alami.

Site Engineer1996 January to 1998December(MIDFA MACEContractors L.L.CDUBAI, U A E)

Client : Dubai MunicipalityProject : DS 68/4 – Jumeira and Al Saffa

Drainage and Sewerage worksConsultant: M/s Khatib & Alami.

Page 9: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

Site Engineer1993 December to 1996 April(M/s Bartawi Group ofCompaniesDubai, U A E)

Client : Dubai MunicipalityProject : DS 95 – House Connections & Minor

Miscellaneous works in DubaiConsultant: M/s Montgomery Watson.

Junior Engineer1985 to 1992(Al Manartine ConstructionsBahrain )

Projects : Hamad Town Sewerage Works, Phase1, Phase 2, Phase 3.

Consultant: M/s Dar Al Handash, Consultants.

Page 10: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

List of Projects Executed in U.A.E

SerialNo. Client Consultant Project Cost Duration

01 ContractingAnd TradingCompany(CAT) AbuDhabi (SubContract)

ParsonsInternational

Chilled Water PipesInstallation includes all asCivil Works, Trenching,Chamber Construction

AED: 5.2Million

8 Months

02 MACEContractor –Abu Dhabi(Sub Contract)

KEOInternational

Falcon Eye – Abu DhabiTrenching and PipingWorks in Abu Dhabi Cityfor Camera InstallationNet Works.

AED: 1.2Million

6 Months

03 MACEContractor –Abu Dhabi /Samsung / SaifBin Darwish(Sub Contract)

ParsonsInternational

Up gradation of Al SalamStreet1800 mm RC Pipe Stormwater works

A.E.D: 1.5Million

6 Months

04 MACEContractor –Abu Dhabi(Sub Contract)

DorshConsultant

Construction WorksAssociated withRehabilitation andReplacement of ExistingSewer Lines in Abu DhabiIsland Area – Contract 0-2536

A.E.D: 1Million

4 Months

05 Al Salmeen/Advanced PipeLine Services.(Sub Contract)Abu Dhabi

DorshConsultant

Construction WorksAssociated withRehabilitation andReplacement of ExistingSewer Lines in Abu DhabiIsland Area – Contract 0-2535

A.E.D: 1Million

4 Months

Page 11: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

06 EmiratesDistrictCooling L.L.C.(Emicool)Dubai

Khatib & AlamiCivil Works.1200mm Dia preinsulated GRP PipeInsulation.

A.E.D: 1.7Million

8 Months

07 EmiratesDistrictCooling L.L.C.(Emicool)Dubai

Emicool Various MiscellaneousEmergency Works ofChilled Water network.Operations AndMaintenance Contract

A.E.D: 2.8Million

On Perusal

08 MAX BOGL/ADSOAbu Dhabi

Obermeyer Laying of Sewerage,Drainage, Irrigation Linesin FGB MultifunctionalArena Zayed Sports City

A.E.D: 1.3Million

3 Months

Page 12: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

Quality Policy

TAURUS GENERAL CONTRACTING L.L.C. is committed to provide timely

quality service that, as a minimum, conforms to contractual requirements in all

areas of construction and operations and maintenance to achieve customer’s

full satisfaction.

TAURUS GENERAL CONTRACTING L.L.C. Management will provide sufficient

and appropriate resources to implement and achieve quality objectives within

definite programs and schedules to meet regulatory and obligatory

requirements.

TAURUS GENERAL CONTRACTING L.L.C. will continually seek to improve its

quality management system. Effectiveness towards more customer satisfaction

by refining its Project Quality Plan through use of advanced technology, quality

products, training of staff and implementing quality management system that

meets the requirements of ISO 9001:2008

Carry out all operations in a safe and timely manner, to the benefit of the

client, the employees and the company in general.

The management will review the quality policy on annual basis in line with the

company annual quality objectives.

Continually Review

Complete and handover 100% of company projects on time.

Customer complaints to minimum (<1 per year)

Conduct internal audit as per schedule.

Anoj S. Kumar

General Manager

Page 13: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

HEALTH AND SAFETY POLICY

TAURUS GENERAL CONTRACTING L.L.C recognizes the importance of a good

health and safety planning prior to the commencement of project works so as to

avoid any possible injuries or endanger the health and safety of all personnel

involved in the project. To realize our objectives, TAURUS GENERALCONTRACTING L.L.C has prepared the following statements that constitute a

safety plan. Hereby we are going to describe to TAURUS GENERALCONTRACTING L.L.C intends to manage, control and coordinate the works in

order to protect the health, safety and welfare of all personnel engaged in the

project and others who may be affected by the operations.

The following statements aim to provide a plan of TAURUS GENERALCONTRACTING L.L.C (Management and monitoring) systems and measures to

ensure the safe operation of work through the contract period.

TAURUS GENERAL CONTRACTING L.L.C understands the main contractor

has put in great efforts in maintaining good safety and health performance

amongst its projects. TAURUS GENERAL CONTRACTING L.L.C will ensure

that the same scenario is adopted and maintained through the contract period

with the highest priority.

TAURUS GENERAL CONTRACTING L.L.C will try its best to convey the same

message of maintaining high safety and health standards to all subcontractors

and their workers.

TAURUS GENERAL CONTRACTING L.L.C will also ensure that all project

works confirm to the safety standard as required by the main contractors and

relevant statutes and applicable codes and standards.

a. It is the policy of TAURUS GENERAL CONTRACTING L.L.C to provide

safe and healthy working conditions for its employees and to ensure that

the conduct its affairs are not harmful to the safety and health of its

employees and the general community.

Page 14: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

b. Accidents cost time and money and create pain and misery. They are

always caused by unsafe working conditions or unsafe practices.

Accidents can and must be prevented by continuous education,

perseverance and determination.

c. Safety is an important aspect and an integral part of our daily operations

and therefore should not be neglected or compromised for the sake of

progress. TAURUS GENERAL CONTRACTING L.L.C objectives can only

be achieved with the joint and determined effort of both management and

employees.

d. Responsibility rests with each employee who is hereby encouraged to

contribute to the attainment of objectives of this policy. With adequate

safety precautions taken, accidents, human sufferings, loss of time and

damage to property and equipment can be avoided. Safety is everyone’s

concern and its achievement requires everybody’s cooperation and

commitment.

…………………

ANOJ SURESHGENERAL MANAGER

TAURUS GENERAL CONTRACTING L.L.C

Page 15: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required
Page 16: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

ISO CERTIFICATE

Page 17: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

Company Owned Machinery & Tools

An extensive Range of Tools and Equipments includes (but not limited to)

1. Backhoe - 01 No.

2. 6 Wheel Truck - 03 Nos.

3. Roller & Plate Compactor - 03Nos.

4. Air Compactor & Jack Hammer - 01 No.

5. Welding Machines - 03Nos.

6. Generator Set 55 KVA - 01 No.

7. Disk Cutter 14” - 08 Nos.

8. Disk Cutter 16” - 01 Nos.

9. Table Grinder 8” - 1 No.

10.Tool Boxes - 20 Nos.

Page 18: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

GRP LAMINATION SEWER MANHOLES

Page 19: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

WRAPPING WATER STOPPER AROUND GRP PIPES,CONCRETE ENCASEMENT WITH RENDEROC AND HIGHPRESSURE NITOFILL TO STOP LEAKAGE FROMCHILLED WATER PIPES

Page 20: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

CONCRETE ENCASEMENT TO PROTECT THESUSCEPTIBLE AREA OF CHILLED WATER PIPE LEAK

Page 21: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

INSTALLATION OF COUPLERS ON 1200 DIA GRPCHILLED WATER PIPE

Page 22: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

SUSCESSFUL INSTALLATION OF COULER TO STOPWATER LEAKAGE

Page 23: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

JACKETTING WORKS AROUND GRP PIPES

Page 24: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

MUFFLER SYSTEMS INSTALLED IN CHILED WATERLINER TO STOP LEAKAGE WITHOUT SHUTDOWN OFCHILED WATER NETWORK

Page 25: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

CONCRETE ENCASEMENT AROUND STORM WATERLINE

Page 26: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

INSTALLATION OF PIPE LINES FOR DEEP SEWERLINES

Page 27: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

INSTALLATION OF GRP DOUBLE LINER MANHOLE FORSEWER NETWORK

Page 28: COMPANY PROFILE - Neovibe Blog · Irrigation pipeline installation. 4. ... DUBAI, U A E) Client : Dubai Municipality Project : ... works confirm to the safety standard as required

INJECTION WORKS TO STOP WATER LEAKS