Leading Electrical and Instrumentation Construction Company
COMPANYPRESENTATION
Leading Electrical and Instrumentation Construction Company
Leading Electrical and Instrumentation Construction Company
Agenda
1. Company Overview
2. Typical Installations
3. Contract Profiles
4. Typical Projects
5. Experience Schedule
Leading Electrical and Instrumentation Construction Company
Leading Electrical and Instrumentation Construction CompanyLeading Electrical and Instrumentation Construction Company
COMPANYOVERVIEW
Leading Electrical and Instrumentation Construction Company
OverviewB&W have been established in the electrical and instrumentation (E&I) construction industryfor 43 years. B&W are one of the largest specialist E&I contractors in South Africa.
B&W has worked and gained valuable experience in mining, oil & gas, chemical, utilities,renewable energy, power generation, industrial process plants and infrastructure. Thestandard of electrical and instrumentation construction varies from industry to industry andB&W have developed highly qualified teams to cater for the needs of our clients.
B&W hosts numerous complementary services ranging from field engineering, equipmentprocurement, material supply, testing and commissioning and maintenance services.
B&W acquired Pontins in 2009, one of the largest specialist suppliers of earthing andlightning protection services and have been in business for 44 years.
B&W’s commitment to providing a professional service, economically, timeously and withconsistency is the key to our enviable growth record.
B&W are a wholly owned subsidiary of the ELB Group.
Leading Electrical and Instrumentation Construction Company
Company StructureB&W Group
Mozambique
Swaziland
Kenya
Registered Offices
Namibia
South Africa
Company Services
Health, safety andenvironment
Marketing andproposals
Financial Procurement
Quality assurance Planning
HR skills developmentand training
Company Operations
E&I installationsprocess plants
Regions
Maintenance andshutdowns Special services
Pontins
Earthing and LightningProtection Specialists
Conductor Systems
Electrification Systemsfor Mobile Equipment
B&W Instrumentation andElectrical SA (Pty) Ltd
41.94%Equity
Level 4B-BBEE Status
Tanzania
Leading Electrical and Instrumentation Construction Company
Group Structure
ELB EngineeringSolutions (Pty) Ltd
ELB EquipmentHoldings (Pty) Ltd
B&W Instrumentationand Electrical (Pty) Ltd
ELB Group Ltd
ELB EducationalTrust
ELB International(Pty) Ltd
ELB IntelligentSolutions (Pty) Ltd
ELB Engineering(Pty) Ltd
B&W Instrumentation andElectrical Tanzania Ltd B-Quip (Pty) LtdPontins (Pty) Ltd BWIE Properties
(Pty) LtdH&S Training
Academy (Pty) Ltd
B&W Instrumentation andElectrical SA (Pty) Ltd
B&W Instrumentationand Electrical Kenya Ltd
BWIE Instrumentationand Electrical Swaziland
B&W ElectricidadeLda (Mozambique)
B&W Instrumentation andElectrical Namibia (Pty) Ltd
Conductor Systems
Leading Electrical and Instrumentation Construction Company
Manpower ResourcesAdministration & Accounting 29
Construction Management 15
Quality Control 7
Planners 4
Junior Planners 3
HSE Personnel 15
Engineers & Technicians 22
Site Managers & Supervisors 38
Professional Project Managers 10
Foremen 21
Artisans 95
Learners 30
Semi-Skilled 250 – 400
Field Labour 600 - 1800
Leading Electrical and Instrumentation Construction Company
Target Industries
Mining
Renewable Energy
Power Generation
Transmission &Distribution
Industrial & Utilities
Chemical, Oil & Gas
Leading Electrical and Instrumentation Construction Company
Project Footprint
Leading Electrical and Instrumentation Construction Company
End User / Clients
Leading Electrical and Instrumentation Construction Company
Health and Safety
5 Star NOSA graded NOSCAR Award for 5 consecutive years
“Best performance E&I contractor in SA”
Leading Electrical and Instrumentation Construction Company
HSE Statistics
Criteria 2012 2013 2014 2015 Total
Man-hours 1,537,436.00 1,832,534.00 1,812,100.00 2,088,867.00 7,270,937.00
Fatalities 0 0 0 0 0
MTC’s and First Aid Cases Combined 14 18 10 6 48
LTI’s 1 0 0 0 1
LTIFR per 200,000 hours Year to Date 0.13 0.00 0.00 0.000.01
LTIFR per 200,000 hours 12 Month Period 0.13 0.00 0.00 0.00
12 Months to Date – 2014 / 2015
Lost Time Injury Rate (“LTIFR”) – 0.00 per 200,000 hours worked
Recordable Case Rate (“RCR”) – 0.33 per 200,000 hours worked
Leading Electrical and Instrumentation Construction Company
Quality Statement
It is a prime management objective of B&W Instrumentation andElectrical to supply products and services with a high level of qualityand reliability for the realisation of our clients requirements.
It is the objective to effectively complete contracts with the followingcriteria as our primary requirements:
• To minimise all Quality complaints• To maximise client confidence in our competence• The improvement of the profit objectives of the company by
adherence to the above
Leading Electrical and Instrumentation Construction Company
ISO 9001:2008
B&W operates in accordance with proceduresestablished to comply with the strenuous ISO9001:2008 quality requirements.
B&W are currently one of the only ISO9001:2008 accredited electrical andinstrumentation contractors in Sub-SaharanAfrica.
This accreditation not only provides newclients with the comfort that our existingclients have come to expect from us, butaffords us the opportunity of outside auditsby the SABS to ensure that the standards setare not only maintained, but continuallyimproved where possible.
Leading Electrical and Instrumentation Construction Company
BBBEE Status
B&W aims to bring about true broadbased empowerment. An Employee Trustestablished in September 2006 owns a7% stake in the company benefitingemployees with more than four yearsuninterrupted service, with an emphasison black staff (75% of benefits).
B&W is a comfortable ‘Level 4’contributor in terms of the draftDepartment of Trade & Industry’s BBBEECodes of Good Practice. Accordingly100% of client spend can be counted asspend with a BEE company.
Leading Electrical and Instrumentation Construction Company
CIDB Certification
B&W has an 8EP and 8EB grading. This would include major public sectorprojects such as those for Eskom.
Due to new regulations by the CIDB, certificates are no longer issued.
B&W CIDB number: 149138
Leading Electrical and Instrumentation Construction Company
Corporate Social Responsibility
In B&W Southern Africa CorporateSocial Responsibility is an importantbusiness priority and integral to ouroverall business strategy.
Corporate Social Responsibility (CSR)projects are selected on social needand the extent to which they arealigned with our business and canadd value to our clients and ourcommunities.
Our policy is to identify worthySocial Economic Development (SED)projects in the areas in which wework. Our projects have provedhighly successful, making ameaningful difference.
CSR to us is about building relationships with ourcustomers, attracting and retaining talented staff,managing risk and building reputation.
Leading Electrical and Instrumentation Construction Company
Training
In response to the skills shortage in SouthAfrica B&W has invested substantially in thetraining of field labour to increase its skillspool. B&W has its own fully equipped in-housetraining centre based in Alberton and is anaccredited service provider throughConstruction SETA.
B&W has implemented training programmesin line with accredited SAQA unit standards toadvance employee skills and ensure traineesreceive an accredited qualification. Todetermine the appropriate skills developmentrequired B&W provides ongoing on-the-jobassessments. In addition long-term incentivesensure retention of core staff.
Leading Electrical and Instrumentation Construction Company
Typical Training CoursesApproved Unit Standards
• 229998 Explain and perform fall arrest techniques when working at heights
• 9964 Apply health and safety to a work area
• 12484 Perform basic fire fighting
• 120344 Demonstrate knowledge and understanding of relevant currentoccupational health and safety legislation
• 12878 Use and maintain power hand tools on a construction site
• 116999 Apply accurate information about HIV & AIDS to everyday life
Unit Standards Awaiting Approval
• Hazard identification and risk assessment
• First aid (Level 1–3)
• Fire fighting
• Occupational health and safety rep
Leading Electrical and Instrumentation Construction CompanyLeading Electrical and Instrumentation Construction Company
TYPICALINSTALLATIONS
Leading Electrical and Instrumentation Construction Company
Electrical
Leading Electrical and Instrumentation Construction Company
Electrical
Leading Electrical and Instrumentation Construction Company
Instrumentation
Leading Electrical and Instrumentation Construction CompanyLeading Electrical and Instrumentation Construction Company
CONTRACTPROFILES
Leading Electrical and Instrumentation Construction Company
Contract ProfileTemane Pande Development Project
Client: Sasol
Engineer: Foster Wheeler
Location: Temane, Mozambique
Value: R49,6 million
Start Date: January 2003
Completion Date: March 2004
Site Man-hours Used: 256,000
Peak Manpower: 380
Number of Drives: 324
I/O Count: 2800
Field Instruments: 1120
Quantity of Cable: 314,000m
Quantity of Cable Rack: 11,600m
Leading Electrical and Instrumentation Construction Company
Contract ProfileWaste Water Recycle Facility Project
Client: Sasol
Engineer: Foster Wheeler
Location: Secunda
Value: R35,0 million
Start Date: June 2004
Completion Date: November 2005
Site Man-hours Used: 196,000
Peak Manpower: 200
Number of Drives: 158
I/O Count: 1630
Field Instruments: 879
Quantity of Cable: 182,000m
Quantity of Cable Rack: 7,282m
Leading Electrical and Instrumentation Construction Company
Contract ProfileVeolia Water Treatment Plant Project
Client: Sasol
Engineer: Veolia
Location: Secunda
Value: R38,2 million
Start Date: March 2005
Completion Date: April 2006
Site Man-hours Used: 218,000
Peak Manpower: 288
Number of Drives: 330
I/O Count: 2960
Field Instruments: 1230
Quantity of Cable: 233,000m
Quantity of Cable Rack: 9,214m
Leading Electrical and Instrumentation Construction Company
Contract ProfilePprust 600KTPM Concentrator Project
Client: Amplats
Engineer: DRA
Location: Potgietersrust
Value: R179,0 million
Start Date: March 2007
Completion Date: April 2009
Site Man-hours Used: 802,000 (Accident free)
Peak Manpower: 928
Number of Drives: 483
Field Instruments: 3700
Quantity of Cable: 450,000m
Quantity of Cable Rack: 27,000m
Leading Electrical and Instrumentation Construction Company
Contract ProfileShondoni Mining Project
Client: Sasol Mining
Engineer: Worley Parsons
Location: Secunda
Value: R86,0 million
Start Date: May 2013
Completion Date: June 2015
Site Man-hours Used: 230,000
Peak Manpower: 94
Number of Substations: 8
Number of Mini Substations: 10
Number of 11kV Panels: 72
Number of 132kV Circuit Breakers: 4
Number of 20MVA 22kV / 11kV TRF: 2
Number of Street Lights: 54
Quantity of Cable: 32,000m
Leading Electrical and Instrumentation Construction CompanyLeading Electrical and Instrumentation Construction Company
TYPICALPROJECTS
Leading Electrical and Instrumentation Construction Company
Project ReferenceAmbatovy Project Overview
Project Name: Ambatovy (Process Plant)
Location: Tamatave, Madagascar
Project duration: 26 months (July 2009 – September 2011)
B&W contract value: US$ 60 million
• After the successful completion of the Early Works contract on the same project, B&W was appointed as the main Electrical &
Instrumentation installation contractor on one of the largest projects in the world at the time.
• The plant is designed to produce 50t of nickel, 5t of cobalt and 130t of ammonium phosphate. Although the plant is constructed in
Tamatave, near the harbour, the mine is situated near the town of Muramanga, some 450km away.
• The scope of work included the entire electrical and instrumentation installation, including calibration and cold commissioning, on the
plant site, with the exception of the Refinery, Power Generation Plant, Acid Plant and Lime handling sections, which were separate
packages. The enormous scope of work, and limited time for completion, make the project one of, if not the biggest E&I project
undertaken by a South African contractor.
• The scope for included everything from the 11kV and 6.6kV distribution, plant wide, to the lighting and small power, calibration of
instruments, LV and instrumentation installations and cold commissioning, while the Early Works contract included the design, supply
and installation of 11kV overhead lines, distribution and street lighting on the plant site and 6.6kV overhead lines, distribution and
street lighting at the mine site.
Leading Electrical and Instrumentation Construction Company
Project Reference
• 900,000m of electrical cabling
• 490,000m of instrument cabling
• 49,000m of straight cable racking plus 4,950 fittings
• 25,000m of stainless steel instrument tubing
• 395t of sundry steelwork & angle droppers
• 30,000m of single unistrut supports
• 1,100 drives
• 3,455 instruments
• 1,950 luminaries
• 4,880,785 man-hours – all without lost time injury (5,232,096 including the Early Works)
• A peak of 1,656 personnel on site
• The final value of the contract was roughly R430 million and being that the bulk of the materials, including the equipment, cable,
racking, luminaries, instruments and even the cable glands were free-issue by the client; this understates the magnitude of the work
completed.
• On site, B&W had a peak of 628 expatriates (mainly South African) and employed a peak of 1,028 local Malagasy workers. Due to local
content requirements, B&W established the subsidiary, B&W Madagascar SaRl, in Madagascar for the execution of the contract.
Ambatovy Project Statistics
Leading Electrical and Instrumentation Construction Company
Project ReferenceAmbatovy Project Overview & Statistics
Project Name: Ambatovy (Early Works)
Location: Tamatave, Madagascar
Project duration: 8 months (November 2008 – June 2009)
Contract value: US$ 16 million
Project statistics (Early Works, Plant and Mine Site)
• 25km 11kV overhead lines
• 22,5km 6.6kV overhead lines
• 28km fibre optic
• 388 luminaries
• 351,311 man-hours, all without lost time injury
Leading Electrical and Instrumentation Construction Company
Project ReferenceAmbatovy Plant Site
Leading Electrical and Instrumentation Construction Company
Project ReferenceAmbatovy Mine Site
Leading Electrical and Instrumentation Construction Company
Project ReferenceAmbatovy Harbour
Leading Electrical and Instrumentation Construction Company
Project ReferenceAmbatovy Pipeline
Leading Electrical and Instrumentation Construction Company
Coal ProjectSouth Africa
Contracts awarded for two Coal Projects in South Africa, combined value ofR152.0 million
Leading Electrical and Instrumentation Construction Company
InstrumentationMadagascar
Completed Early Works Project and commenced E&I Installation on MainProcess Plant
Main Process Plant was initially delayed for ten months
Leading Electrical and Instrumentation Construction Company
Coal Project
66kV Overhead Line
Remote Northern Mozambique
1.2km span with Lattice Structures
Mozambique
Leading Electrical and Instrumentation Construction Company
Coal Project
Commenced construction on Moatize Coal Project in Northern Mozambique
Further opportunities in the region with other clients now starting withproject implementation
Mozambique
Leading Electrical and Instrumentation Construction Company
Oil & Gas
Awarded E&I Installation Extension to Panda Gas Project
B&W awarded Phase 1 in 2002
Mozambique
Leading Electrical and Instrumentation Construction Company
Sands Project
22kV Supporting Infrastructure
- Substations & H.T cabling
- Back up generators
Process Cabling & Instrumentation for:-
- Wet Concentrator Plant
- Ponds, Pontoons & Dredges
- Mineral Separation Plant
- Starter Ponds
- Product Storage
- Conveyors
Mozambique
Leading Electrical and Instrumentation Construction Company
Solar Photovoltaic
Contract for the 64MWp Solar Photovoltaic ("PV") Project at Postmasburg in theNorthern Cape area of South Africa
The project is a key component of Phase 2 of the South African Department of Energy'sRenewable Energy IPP Procurement Program
Assistance with commissioning of the total plant
South Africa
Leading Electrical and Instrumentation Construction CompanyLeading Electrical and Instrumentation Construction Company
EXPERIENCESCHEDULE
Leading Electrical and Instrumentation Construction Company
Current ProjectsOWNER EPCM
CONTRACTOR PROCESS LOCATION CURRENTVALUE
MONTH OFCOMPLETION
Sibanye Platinum Sibanye Platinum E&I Installation RustenburgRSA R20 million / year Annuity
Sasol Petrochem Sasol E&I Installation SecundaRSA R8 million / year Annuity
Anglo American Venn & Milford Zebulo CollieryUnderground Mining
OgiesRSA R11,2 million June 2016
Vale ABBMoatize Expansion
Electrical Reticulation Network& 220kv Outdoor Switchyards
Mozambique R216 million July 2016
Sasol Mining ELB Impumelelo MineE&I Installation & Material Handling
SecundaRSA R8,3 million Aug 2016
Sasol Mining Worley Parsons Shondoni Mine Phase I & IISub-stations & cabling
SecundaRSA R117 million Aug 2016
Eskom Tenova Kusile Power StationE&I Installation & Material Handling
OgiesRSA R40 million Aug 2016
Swakop Uranium Amec / Bateman Husab Uranium MineE&I Installation Namibia R298 million Sept 2016
Eskom ELB Medupi Power StationE&I Installation & Material Handling
EllisrasRSA R34 million Dec 2019
Leading Electrical and Instrumentation Construction Company
Oil & GasOWNER EPCM
CONTRACTOR PROCESS LOCATION VALUE DURATION
Fina Fluor DanielFina Petroleos Refinery Crude Unit
RevampInstrumentation Installation
Angola R8 million 6 months
Mosgas / Petrosa Foster Wheeler Low Aromatic Distillation UnitE&I Installation
Mossel BayRSA R12,7 million 7 months
Sasol Foster Wheeler Temane Panda Processing FacilityE&I Installation Mozambique R49,6 million 15 months
Sasol Foster Wheeler Waste Water Recycle FacilityE&I Installation
SecundaRSA R35 million 18 months
Sasol Veolia Veolia Water Treatment PlantE&I Installation
SecundaRSA R38,2 million 14 months
Sasol Foster Wheeler Gas Engine Power PlantE&I Installation
SasolburgRSA R22,4 million 7 months
Sasol VGI Consulting Inc. Sasol Wholesale Logistics DepotE&I Installation
AlbertonRSA R60 million 13 months
Sasol Foster Wheeler Sasol Utilities ExpansionE&I Installation
SasolburgRSA R29 million 8 months
Sasol Sastech New Pre-Coat Tank Unit 219E&I Installation
SecundaRSA R6,4 million 6 months
Sasol Thyssenkrupp Uhde Temane ExpansionE&I Installation Mozambique R58 million 19 months
Sasol Sasol Unit 243 UpgradeE&I Installation
SecundaRSA R7,5 million 3 months
Leading Electrical and Instrumentation Construction Company
ChemicalOWNER EPCM
CONTRACTOR PROCESS LOCATION VALUE DURATION
Bayer Chemicals Foster Wheeler Chrome Chemical PlantE&I Installation
NewcastleRSA R23,4 million 9 months
Indian OceanFertilizers
Sulphos(EMS / SNC Lavalin)
IOF Sulphuric & Phosphoric AcidPlant
E&I Installation
Richards BayRSA R22 million 8 months
Lafarge ICER Cement Plant Electrical Upgrade(Labour only)
LichtenbergRSA R10,1 million 5 months
Amplats (ACP) Stein Muller Acid PlantE&I Installation
RustenburgRSA R15,5 million 10 months
PPC Krupp UHDE Slagment PlantElectrical Installation
SaldanhaRSA R14 million 14 months
PPC Kentz / TWP PPC Hercules ExpansionE&I Installation
PretoriaRSA R27 million 8 months
Air Products Air Products G-Oxygen PlantE&I Installation
VanderbijlparkRSA R14,5 Million 6 months
Leading Electrical and Instrumentation Construction Company
Industrial PlantsOWNER EPCM
CONTRACTOR PROCESS LOCATION VALUE DURATION
PFG Glass PFG PFG GlassE&I Installation
SpringsRSA R21,4 million 5 months
Transnet Hatch CoegaInfrastructure
Port ElizabethRSA R68 million 14 months
Transnet Transnet Port Link Line & Salkor YardElectrical Services
SaldanhaRSA R11 million 7 months
Ubombo Sugar BoschUbombo Sugar Mill Factory
ExpansionE&I Installation
Swaziland R44 million 5 months
Sappi AMEC Sappi GoCell UpgradeE&I Installation
NelspruitRSA R58 million 14 months
Nestle ELB Nestle Process PlantE&I Installation
EstcourtRSA R32 million 10 months
Leading Electrical and Instrumentation Construction Company
Renewable EnergyOWNER EPCM
CONTRACTOR PROCESS LOCATION VALUE DURATION
Lesedi Energy Comycento LesediPhotovoltaic Solar
KathuRSA R40 million 10 months
Leading Electrical and Instrumentation Construction Company
MiningOWNER EPCM
CONTRACTOR PROCESS LOCATION VALUE DURATION
Aquarius DRAEverest South Platinum
ConcentratorE&I Installation
LydenburgRSA R13,4 million 3 months
Amplats WatervalSmelter Hatch ACP Stage B
E&I InstallationRustenburg
RSA R16,5 million 7 months
Xstrata J.V DRA Mototolo Concentrator & Spiral PlantE&I Installation
LydenburgRSA R23,1 million 7 months
Nkomati DRA Nkomati ConcentratorE&I Installation
MachadadorpRSA R16,4 million 6 months
De Beers BatemanFinsch Mine Treatment Plant
UpgradeE&I Installation
Lime AcresRSA R46.3 million 20 months
Aflease Bateman Aflease Uranium PlantE&I Installation
KlerksdorpRSA R68 million 9 months
Amplats DRA Pprust 600KTPM ConcentratorE&I Installation
PotgietersrusRSA R179 million 27 months
Amplats Vhumbanani Amandelbult ConcentratorE&I Installation
NorthemRSA R48 million 6 months
ARM / Assmang DRA Iron Ore PlantE&I Installation & Infrastructure
SishenRSA R105 million 14 months
Amplats Vhumbanani Pilanesberg ConcentratorE&I Installation
RustenburgRSA R34 million 7 months
Leading Electrical and Instrumentation Construction Company
MiningOWNER EPCM
CONTRACTOR PROCESS LOCATION VALUE DURATION
Anglo Coal / BHPBilliton DRA Phola Coal
E&I InstallationOgiesRSA R32 million 6 months
BHP Billiton DRA DMO Washing PlantE&I Installation
MiddelburgRSA R88 million 14 months
Amplats Hatch PMR Effluent Treatment PlantE&I Installation
RustenburgRSA R26 million 7 months
BHP Billiton Bateman ET DMO Materials HandlingE&I Installation
MiddelburgRSA R156 million 16 months
Nkomati DRA Nkomati Phase 11BE&I Installation
MachadadorpRSA R26 million 6 months
Sasol RSV 11kV Power Lines Installation SecundaRSA R13 million 7 months
Douglas Colliery Bateman Water PurificationE&I Installation
WitbankRSA R17 million 5 months
Kumba Iron Ore Hatch Sishen SouthE&I Installation
PostmasburgRSA R84 million 16 months
Assmang DRA KEPE&I Installation
KathuRSA R148 million 22 months
AssmangChrome NAC Furnace Process Upgrade
E&I InstallationMachadodorp
RSA R11,5 million 7 months
Sasol RSVThubelisha Mine
Electrical Installation, Terminationfor Plant Wide & OHL
SecundaRSA R34 million 15 months
Leading Electrical and Instrumentation Construction Company
MiningOWNER EPCM
CONTRACTOR PROCESS LOCATION VALUE DURATION
Whims BKM DRA WHIMS Iron Ore UpgradeE&I Installation
SishenRSA R64 million 8 months
Kasese Bateman Kasese CobaltE&I Installation Uganda R14,6 million 5 months
Namdeb Bateman DMS Plant – Elizabeth BayE&I Installation Namibia R28 million 7 months
Kenmare Resources Bateman Moma Mineral SandsOHL and E&I Installation Mozambique R34 million 20 months
LetsengDiamonds Bateman Diamonds Process Plant
E&I Installation Lesotho R16 million 6 months
African Mining Sennet / Logichem Copper MineE&I Installation Botswana R22,4 million 6 months
Albidon Zambia Limited GRC Minproc Munali Process PlantE&I Installation Zambia R16 million 4 months
Equinox Ausenco / Bateman Lumwana Copper MineE&I Installation Zambia R14,9 million 9 months
Dynatec SNC Lavalin AmbatovyOHL & Infrastructure Madagascar R96 million 18 months
Hulletts PGBIXinavane 380 TCH Factory
ExpansionElectrical Installation
Mozambique R33 million 6 months
Amplats Vhumbanani Unki Platinum Mine ConcentratorE&I Installation Zimbabwe R67 million 13 months
Leading Electrical and Instrumentation Construction Company
MiningOWNER EPCM
CONTRACTOR PROCESS LOCATION VALUE DURATION
Vale ABBMoatize Coal
Infrastructure, OHL & SubstationsE&CI Installation
Mozambique R233 million 30 months
Dynatec SNC Lavalin Ambatovy Process PlantE&I Installation Madagascar R414 million 30 months
Rio Tinto Rio Tinto LV & MV Reticulation Mozambique R6,8 million 7 months
Riversdale SedgmanBenga Coal Handling & Preparation
PlantE&I Installation
Mozambique R53 million 12 months
Vale Vale 66kV OHL Repairs Mozambique R5,6 million 2 months
Assmang DRA KOPE&I Installation
KathuRSA R44 million 16 months
Base Minerals Ausenco Kwale Mineral SandsE&I Installation Kenya R94 million 9 months
Rio Tinto Rio Tinto Various E&I Installation Mozambique R12 million 24 months
Kumba ELB Sishen Iron Ore Mine - DMS PlantsE&I Installation
KathuRSA R34,3 million 9 months
Kumba ELBKolomela Iron Ore Mine - DMS
PlantsE&I Installation
PosmasburgRSA R24,7 million 9 months
Leading Electrical and Instrumentation Construction Company
MiningOWNER EPCM
CONTRACTOR PROCESS LOCATION VALUE DURATION
Xtrata DRATweefontein Collieries Coal Mine
InfrastructureE&I Installation & Material Handling
TweefonteinRSA R230 million 16 months
Jindal S&P B&W Plant 33kV Reticulation Mozambique R13,5 million 11 months
Sasol Sasol Coal TweedraaiElectrical Infrastructure
SecundaRSA R15,9 million 4 months
Sasol BET TweedraaiE&I Installation & Material Handling
SecundaRSA R16,5 million 5 months
PPM Worley Parsons RadosE&I Installation & Material Handling
PilanesbergRSA R8,2 million 6 months
Leading Electrical and Instrumentation Construction Company
Dean NevayProject Director
Tel: +27 11 907 1663
Fax: +27 11 907 1957
E-mail: [email protected]
Contact Details
Ken NelBusiness Development Manager
Tel: +27 11 907 1663
Fax: +27 11 907 1957
E-mail: [email protected]