1 Company / Owner Marine Contractor Main Contractors - JV

Upload: mohammed-alharahsheh

Post on 22-Jul-2015

48 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: Compact Aqaba LPGT Presentation-22-1-2015

1

Company / Owner

Marine Contractor

Main Contractors - JV

Page 2: Compact Aqaba LPGT Presentation-22-1-2015

OUTLINE:

.1Introduction

.2Resources

.3Progress Percentage

◦Construction Status

.4Financial Summary

.5Variation Orders

2

Page 3: Compact Aqaba LPGT Presentation-22-1-2015

The project consists mainly of the detailed design and construction of LPG Jetty which includes:

•Access Trestle & Loading Platform

•2 No. Berthing Dolphins & 4 No. Mooring Dolphins & Catwalks

•Marine Loading Arms (x2)

•LPG and vapour return lines & Cathodic Protection System

•Fire fighting system & Electrical power supply and lighting

•Contractual project dates:24-Feb-14 24-Oct-14

•Computed Completion Date :21-feb-15

3

Page 4: Compact Aqaba LPGT Presentation-22-1-2015

4

Manpower 1-Nov-2014 1-Jan-2015

Staff 51 54

Direct Labor 41 64

Equipment Quantity Rented/ Owned

Barge 1 Owned

Flexi float barge 1 Owned

Tug Boat 1 1 Owned

Tug Boat 2 1 Rented

Speed Boat 1 Rented

Vibro Hammer 1 Owned

Diesel Hammer 1 Owned

Crawler Crane 1 Owned

Mobile Crane 3 Rented

Air-Compressor 4 Owned

Welding Machine 20 Owned

Truck Mounted Crane

1 Owned

Page 5: Compact Aqaba LPGT Presentation-22-1-2015

5

Status Expected Completion Date

Trestle 100% Complete

Platform 100% Complete

Loading Arm 100% Complete

Pile Static Load Test 100% Complete

Pipe Line 80% 31-Jan-15

Mooring Dolphins 80% 25-Jan-15

Berthing Dolphins 75% 31-Jan-15

Catwalks 75% 5-Feb-15

Abutement & Access 50% 28-Jan-15

Electrical 30% 10-Feb-15

Marine Furniture (QRH,BAS,Fenders,..) 20% 12-Feb-15

Commissioning 4-Feb to 18-Feb-15

Construction

Page 6: Compact Aqaba LPGT Presentation-22-1-2015

6

Front View

10” FF Pipe4” Vapour Pipe6” LPG Pipe

2.5” Water Pipe

U-Channel Pipe Support

Concrete Pipe Support

Pipe 13-Jan-15

FireFighting 80%

Vapour 80%

LPG 80%

Water 80%

Page 7: Compact Aqaba LPGT Presentation-22-1-2015

7

Invoice No.

Description

Initial Amount (JOD)

Agreed Amount (JOD)

Issue Date Due DateSettlement Date

Overdue Period (days)

Status

001

Advance payment

10%1,723,255.00 1,723,255.00 5-Feb-14 6-Mar-14 8-Jun-14 94 Closed

002 IPC-1 2,356,981.61 1,926,073.33 7-May-14 2-Jul-14 19-Aug-14 48 Closed

003 IPC-2 1,092,297.77 969,456.65 7-Jun-14 2-Aug-14 1-Sep-14 30 Closed

004 IPC-3 1,507,114.54 1,245,493.82 12-Jul-14 6-Sep-14 1-Oct-14 25 Closed

005 IPC-4 1,174,215.32 1,583,941.28 11-Aug-14 6-Oct-14 10-Nov-14 35 Closed

006 IPC-5 1,617,218.84 1,006,200.22 8-Sep-14 3-Nov-14 12-Nov-14 9 Closed

007 IPC-6 2,638,679.75 1,919,859.74 7-Oct-14 2-Dec-14 12-Nov-14 Closed

008 IPC-7 1,571,120.29 1,005,264.70 29-Oct-14 24-Dec-14 30-Nov-14 Closed

009IPC-8

1,864,144.68 993,963.07 2-Dec-14 27-Jan-15 Not Yet Open

010IPC-9

1,366,814.24 1,212,026.19 2-Jan-15 27-Feb-15 Not YetOpen

Issued 14-Jan-2015

Page 8: Compact Aqaba LPGT Presentation-22-1-2015

.1Steel Water Tank to feed the fire fighting system•Issued on Nov. 17th 2014 (202,425.00) JD, Progress : 30%

.2Firefighting Pumps Room•Issued on 17th 2014 (40,700.0) JD, Progress : 95%

.3LPG and Vapour Return Tie-In to Existing Networks•Issued on 17th 2014 (64,509.61) JD, Progress : 100%

.4Design, Supply and Installation of Main Power cable•Issued on Dec. 24th (18,246.99) JD, Progress : 80%

.5Design, Supply and Installation of a Standby Power Generator•Issued on Dec. 24th (18,198.69) JD, Progress : 80%

8

Page 9: Compact Aqaba LPGT Presentation-22-1-2015

9

General Layout

General Layout

Page 10: Compact Aqaba LPGT Presentation-22-1-2015

Trestle Modules

Page 11: Compact Aqaba LPGT Presentation-22-1-2015

Pipe Lines on Trestle

Page 12: Compact Aqaba LPGT Presentation-22-1-2015

Mooring Dolphins

Page 13: Compact Aqaba LPGT Presentation-22-1-2015

13

Firefighting Tank + Pump Room

Page 14: Compact Aqaba LPGT Presentation-22-1-2015

14

Static Load Test

Page 15: Compact Aqaba LPGT Presentation-22-1-2015

15

Loading Arm PrecommissioningLoading Arm Construction

Page 16: Compact Aqaba LPGT Presentation-22-1-2015

16

Firefighting Monitor Towers

Page 17: Compact Aqaba LPGT Presentation-22-1-2015

17

Abutment

Page 18: Compact Aqaba LPGT Presentation-22-1-2015

18

Tie in at Loading Arm

Page 19: Compact Aqaba LPGT Presentation-22-1-2015

19

Tie in Point

Page 20: Compact Aqaba LPGT Presentation-22-1-2015

20

Cable Trays onshore + Trestle

Page 21: Compact Aqaba LPGT Presentation-22-1-2015

Q & A21