1 North Island Hospitals Project Comox Strathcona Regional Hospital District June 13, 2013

Upload: others

Post on 10-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • 1

    North Island Hospitals Project

    Comox Strathcona Regional Hospital District

    June 13, 2013

  • 2

    Agenda

    1. Project Objectives, Guiding Principles, Design Guidelines

    2. Overview of each hospital design and new features

    3. Procurement – PPP (P3 Process)

    4. Comox Valley Site Preparation

    5. Campbell River Site Preparation

    6. Key Issues: Comox Valley and Campbell River

  • 3

    Project Objectives

    • Increase North Vancouver Island acute care capacity to meet the population’s growing and changing needs

    • Enhance safety and quality of care for all patients

    • Improve access to services for all North Vancouver Island communities

    • Maximize staff and physician recruitment and retention potential

    3

  • 4

    1. Healing Environment

    2. Evidence Based Design

    3. LEAN approach

    4. Elderly Friendly

    5. Patient Friendly

    6. Consistency of Design

    Guiding Principals: Design

    7. Use of Wood

    8. Sustainability

    9. Efficient Use of Resources

    10. Alternative Sources of Energy

    11. Carbon Neutrality

  • 5

    Hospital Design and Construction

    • Project and Program Design:

    o Initial design decisions for RFP made with direct consultation from over 20 user groups (300 people) Physicians, nurses, food services, laundry, housekeeping, management

    o Future design decisions with proponent to include: User Champions and Super Users Meeting

    User groups (physicians, nurses, food services, laundry, housekeeping, management, public/patient)

    Evidence Based Planning

    Process Flow Mapping

  • 6

    New Hospital Features

    • Standardization:o Office space, meeting rooms, lounges

    o In Patient rooms, Intensive Care rooms, Operating Rooms

    o Maternity ‐ Labour – Delivery – Recovery – Post‐Partum (LDRP’s)

    • Space saving:o Washrooms – no longer staff and gendered (with exception of 

    bathrooms in staff areas)

  • 7

    Comox Valley Hospital

    o 29,000 m2

    o 153 beds

    o $334 million

    o Comox Strathcona Regional Hospital District 40% = $133.6 million

    o MRI

    o University of British Columbia (UBC) Academic Teaching Space

    o 71% growth

    Campbell River Hospital

    • 22,657 sq m2 

    • 95 beds• $266 million• Comox Strathcona Regional Hospital 

    District 40% = $106.4 million

    o Centre of Excellence in Aboriginal Maternal Care

    o University of British Columbia (UBC) Academic Teaching Space

    o 69% growth

  • 8

    Comox Valley Hospital Proposed Design

    8

  • 9

    Campbell River Hospital Rendering

  • 10

    • 95/153 Acute Care beds• 72/105 In Patient Units• 6/8 Intensive Care Units• 7/9 Telemetry• 7/9 Labour Delivery Recovery Post-

    Partum+ Centre of Excellence• Aboriginal Maternal Health

    • 3/6 Pediatrics• Psychiatry 11, 4 PICU (CVH)

    Campbell River Hospital – Comox Valley Hospital

  • 11

    • 4/6 OR’s, 12/18 Surgical Daycare, 10/13 PARR• 5 procedure rooms• Outpatient clinics• Chemo 7, MDC 7• 29/31 ER• Lab (including autopsy x 2)• Medical Imaging• Rehab• Pharmacy

    Campbell River Hospital – Comox Valley Hospital

  • 12

    Public Private Partnerships (PPP)● Long term, performance‐based contract between 

    government and a private partner to deliver infrastructure and facility management services:

    o Design, build, finance, maintain into one contract

    o Transfers key risks: schedule, cost, lifecycle, design

    o Innovation and competition

    o Enables VIHA to focus on core business ‐ healthcare

  • 13

    Project Procurement – PPP Process

    Business Case & Design

    Concept

    Construction

    IssueRFQ

    Issue RFP Negotiate

    Maintenance~ 4 years

    5 months to 2 years

    Design

    Concept Plan

    Contract Term 30 years

    2 to 4 months

    We are here

    March 2014

  • 14

    Project Proponents

    Team: Arbutus Healthcare Partners

    • Carillion Canada Inc.• Bird Capital Limited• Concert Infrastructure Ltd.• Bird Design‐Build Construction Inc.• Campbell Construction Ltd.• Kasian Architecture Interior Design and Planning Ltd.• NBBJ Architecture

    14

  • 15

    Project Proponents

    Team: Plenary Health

    • Plenary Group (Canada) Ltd.• PCL Constructors Westcoast Inc.• CEI Architecture Planning Interiors• Parkin Architects Western Ltd.• Johnson Controls Inc.

    15

  • 16

    Project Proponents

    Team: Tandem Health Partners

    • Balfour Beatty Capital – Canada Ltd.• Gracorp Capital Advisors Ltd.• Connor Clark & Lunn GVest Traditional Infrastructure LP• Graham Design Builders LP• Farmer Construction Ltd.• Stantec Inc.• Honeywell International Inc.

    16

  • 17

    Project Schedule‘Request for Proposal’ Package Finalized April, 2013

    VIHA Site Preparation WorkComox Valley Site – Leighton Contracting (2009) Ltd.Campbell River Site – Palladian Development

    March – November,2013

    Request for Proposal Phase

    Collaborative Meetings (4)

    April – December, 2013

    Identify Preferred Proponent

    Project Agreement Negotiations

    January – March, 2014

  • 18

    Project ScheduleFinancial Close

    Ground Breaking Ceremony

    March, 2014

    Design and Construction of New Facilities April, 2014 – March, 2017

    Service Commencement – Project Completion March, 2017

    Commissioning and Transition Period April – September, 2017

    Move-In Late Fall, 2017

  • 19

    • Began site preparation for both sites• March to July 1, 2013:

    o 24 public presentation/meetings with community

    • Site ceremony in Campbell River• Two rounds of collaborative meetings (May in CV and June in 

    CR)

    • User group meetings• Community Information Sessions

    Six Month Review: What we’ve done

  • 20

    Six Month Look Ahead: What is going to happen?• Finalize VIHA site preparation – Campbell River and Comox• Collaborative meetings with three proponents• User Groups:

    o Process Flow Mapping

    o Present State – Future State

    o LEAN Process Redesign

    o User Group Team Building

    • Public meetings• Technical Evaluations – October – November, 2013• Financial Evaluations – November – December, 2013

    20

  • 21

    Comox Valley Site Preparation

  • 22

    Comox Valley Site Preparation: Schedule and Update

    • Site preparation activity began end of March 2013

    • Tree removal complete, site hydro seeded 

    • All work to be completed by October 2013

    22

  • 23

    • 2‐4 foot berm being established in selected areas of the buffer zone

    • Over 1000 trees being planted in buffer zones between NIC, hospital and Queneesh

    • Coniferous,  deciduous trees, Garry Oaks, shrubs and other plants

    Comox Valley Site Preparation: Schedule and Update

  • 24

    What We’ve Heard: Landscaping and Walkway

    • The existing paved walkway to Lerwick will be closed as of July 1, 2013• A new walkway is being created around the hospital site to Lerwick and 

    Ryan roads– open as of July 1, 2013

    • As of October 1, 2013 you can access Lerwick from two landscaped walkways: 

    o One route between the hospital site and NIC 

    o One route between the hospital site and Queneesh 

    • Walkway and pedestrian routes on hospital grounds will be built to ensure accessibility for:

    o Individuals with mobility challenges, visually impaired and baby strollers

  • 25

    v

    What We’ve Heard: Landscaping and Walkway

  • 26

    • Fencing around the one soccer field to be installed end of June • Soccer fields on Queneesh property stay the same• Soccer field on hospital property remains open until early 2014• From July 1st through September 2013, the soccer field will be accessible 

    only from Lerwick Rd.

    • October 1 there will be accessibility from Queneesho Working with soccer groups and city to ensure usage

    • Baseball diamonds will be removed at the end of June after ball season ends

    • School District has decided not to place them on Queneesh property

    What We’ve Heard: Soccer Field and Baseball Diamonds

  • 27

    What We’ve Heard: CV – Heliport 

    • Concerns on the impact of the new heliport • Governed by MOT• Indicative Design did demonstrate reasonable flight paths for impacts of residential• final impacts will not be known until MOT approval of final helipad • community information sessions will scheduled to inform residents

  • 28

    Campbell River Site Preparation

  • 29

    Campbell River Site Preparation: Schedule and Update

    • Sunshine Wellness Centre – interior renovations – Jan – May 2013o To make way for new ambulance entrance

    o Demolition of south end by July 2013

    • Site preparation activity began March 2013o Work on gravel parking lot north of Yucalta Lodge to begin – April 2013

    Two temporary gravel parking lots  with 140 public parking stalls

    o Modular Project Management offices on site – June 2013

    o Modular Decanted Healthcare programs on site – Spring 2013

    29

  • 30

    Campbell River Site Preparation: Modular Prep and Installation

    30

  • 31

    Campbell River Site Preparation: Parking and Traffic Management

  • 32

    • Traffic flow changes to existing lot off 2nd – one way ‐ opposite direction – end of September 2013

    • Change to ambulance entrance – end of September 2013

    • Restrictions on left turn (westbound) out of existing parking lot to 2nd.

    • We will provide notification well in advance of any changes

    Campbell River Site Preparation: Parking and Traffic Management

  • 33

    Site Preparation: Changes to Traffic Flow and Ambulance Entrance

    Yucalta Lodge

  • 34

    Key Issues: Comox Valley and Campbell River

  • 35

    What We’ve Heard: Fencing and Site Safety• An 8ft construction fence will be in place for the entire period of 

    time that there is work on the site 

    • An Emergency Management Contact List has been created in conjunction with  both School Advisory Committees (Cedar and Queneesh)

    • WorkSafe BC practices and regulations in place

    • Occupational Health & Safety

  • 36

    What We’ve Heard: Noise and Dust Management

    • During construction dust control practices will be utilized

    • Once the hospitals are in place, carefully designed building ventilation systems will be used to minimize noise and exhaust

    • Noise lessening strategies from Royal Jubilee Project will be applied to areas such as refuse, recycling, loading, and service areas

    • Noise reduction materials will be provided on parking structure walls within 200 metres of residential developments

  • 37

    Comox Valley

    • Currently, SJGH has 438 stalls on site, but those accommodate both acute care and residential care, staff and visitors

    • New CV hospital will have 655 parking stalls including:

    o 425 for physicians and staff

    o 230 for patients and visitors including at least 24 stalls for disabled persons

    Campbell River

    o 408 total parking spots, an increase from the current number of 225 spots

    o 265 stalls for physicians and staff

    o 143 stalls for patients and visitors, including at minimum 24 stalls for disabled ( the number of disabled parking is mandated by the bylaws)

    What We’ve Heard: Parking and Traffic Management

  • 38

    What We’ve Heard: Community Engagement• Quarterly open houses and information sessions• Meetings with:

    o School District and local Queneesh Elementary School 

    o Chambers of Commerce

    o City Councils

    o Aboriginal Working Group

    o Service clubs

    o Construction association, and others

    o Sunshine Wellness Staff Staff BBQ to salvage plants and say good‐bye to garden 

    • Project newsletters, Website, Social Media

    38

  • 39

    • Industry Speed Dating:o May 27, 2013 – Campbell River

    o May 28, 2013 – Comox Valley

    o 140 businesses attended in both communities, with over 225 people: 64 local Campbell River businesses attended

    75 local Comox Valley businesses attended

    • Feedback from proponents overwhelmingly positive – excited about the capacity and level of service of local businesses

    What We’ve Heard: Community Engagement

  • 40

    Aboriginal and First Nations Engagement

    • Aboriginal Working Group:o Kwakiutl District Council

    o Nuu‐chah‐nulth Tribal Council

    o First Nations Health Authority

    o We Wai Kai Nation

    o Wei Wai Kum First Nation

    o K'ómoks First Nation

    o Wachiay Friendship Centre

    o VIHA Aboriginal Employment

    o North Island Métis Nation

    o MIKISW Métis Association

    Photo courtesy of Comox Valley Echo

  • 41

    Community Benefits

    • Employment – direct and indirect• Majority of construction hired locally• Construction services and material procured locally• BC Cancer Agency for the North

    o 90% of trades came from North

    o Majority of local companies hired as part of construction team

    • Royal Jubilee Patient Care Centre:• At the peak of construction, approximately 725 people were employed on the 

    project

    • The majority of them from Greater Victoria

  • 42

    Community Benefits

    Preliminary Employment Numbers – Direct Employment

    2013 2014 2015 2016 2017 Total

    Comox Valley

    50 200 250 350 300 1150

    Campbell River

    30 175 225 325 275 1030

  • 43