community meeting – construction update presentation december 16, 2015

17
Construction Update Meeting December 16, 2015

Upload: derekc1990

Post on 08-Feb-2017

306 views

Category:

Services


1 download

TRANSCRIPT

Page 1: Community Meeting – Construction Update Presentation December 16, 2015

Construction Update Meeting

December 16, 2015

Page 2: Community Meeting – Construction Update Presentation December 16, 2015

2

• Doug Nelson – Executive Director of Development & Construction, UCSF Benioff Children’s Hospital Oakland

• Richard West and Tony Solano – JLL

• Darrel Graef – Project Superintendent, Turner Construction Company

• Ed Walsh and Abhishek Gupta – Turner Construction Company

Welcome

Page 3: Community Meeting – Construction Update Presentation December 16, 2015

3

UCSF Benioff Children’s Hospital / Turner – General Discussion

Project Communication

Upcoming Construction Activities

Local Business Utilization

Pre-Apprenticeship Programs

Agenda

Page 4: Community Meeting – Construction Update Presentation December 16, 2015

4

• Project Communication

• Project Communication– Darrel Graef (Turner Supt) 510-764-3059– Flyers and Project Website

• notifications of change to site conditions as it pertains to the neighborhood

• http://chonext100.org

• Concerns/Issue Reporting—Contact information are posted on Site Signage and Project

Website

Communication & Reporting

Page 5: Community Meeting – Construction Update Presentation December 16, 2015

5

• Finalize west elevation work at MLK garage entrance (Painting, Signage)

• Start constructing temporary barrier walls in OPC 1.• Middle of December is anticipated start for excavation of the OPC2 site

and start working on foundations/drill piers.

Upcoming Major Construction Activities

Page 6: Community Meeting – Construction Update Presentation December 16, 2015

6

• Garage entrance and exit is now on MLK, old garage entrance for vehicles and pedestrians is closed.

• Waiting for city approval to install new crosswalk from temp ramp to main hospital.

• MLK will be the truck route for off-hauling the excavated dirt.• Interior work inside OPC1 to proceed during off hours.

Construction Logistics

Page 7: Community Meeting – Construction Update Presentation December 16, 2015

Overall Site Plan

Page 8: Community Meeting – Construction Update Presentation December 16, 2015

New Garage Logistics

Page 9: Community Meeting – Construction Update Presentation December 16, 2015

Construction Sequencing

MLK JR Way(Sidewalk Closed)

Phase 2A OPC2 Earthwork/FoundationConstruction Status• Site Excavation• 100% Foundation

Logistics ItemsA. Potential Temporary Bus Stop

Location B. Temporary FenceC. Entrance GateD. Pedestrian Travel RedirectionE. Parking Structure New

EntranceF. Trailer/Laydown

B

C

B

D

A

C

E

F

Page 10: Community Meeting – Construction Update Presentation December 16, 2015

10

Projected Business Participation*Local Goal = 35% Projected = 44%

Oakland Contractors = 13%Small Contractors = 37%

Minority Contractors = 8%Women Contractors = 1%

*based on actual and expected contract awards to 31 prime subcontractors through September 2015

Page 11: Community Meeting – Construction Update Presentation December 16, 2015

11

Local Business UtilizationTurner attained a 44% Local business utilization far exceeding the 35% minimum goal as directed by CHO. This was a direct outcome of our extensive outreach efforts which resulted in a total of 247 contractors responding to our outreach efforts (123 submitted bids and 124 declined to submit a bid).

Of the 123 submitted bids:• 45 are Local firms (25 are from Oakland) • 12 are Minority owned firms • 6 are Women owned firms • 12 are Small business firms

Page 12: Community Meeting – Construction Update Presentation December 16, 2015

12

Questions/Discussion?

Page 13: Community Meeting – Construction Update Presentation December 16, 2015

13

13Proposed RPP Boundary

RPP Boundary Map

Page 14: Community Meeting – Construction Update Presentation December 16, 2015

Oakland Children’s Hospital

Page 15: Community Meeting – Construction Update Presentation December 16, 2015

Oakland Children’s Hospital

Page 16: Community Meeting – Construction Update Presentation December 16, 2015

Oakland Children’s Hospital

Page 17: Community Meeting – Construction Update Presentation December 16, 2015

Oakland Children’s Hospital