Community Energy Efficiency & Conservation Community Energy Efficiency & Conservation Strategy Plan (CEP)Strategy Plan (CEP)

Creating a Globally Competitive Community

© Garforth International llc

May 5th, 2011City of Holland, Michigan

Preliminary Indications

Scope of AssessmentScope of AssessmentCity of HollandCity of Holland

Current CEP ScopeCurrent CEP Scope

© Garforth International llc

Should the Scope be Expanded?Should the Scope be Expanded?

CEP Measures of SuccessCEP Measures of SuccessThree Groups of BenefitsThree Groups of Benefits

CompetitivenessCompetitiveness SecuritySecurity

© Garforth International llcFraming goals need to be set earlyFraming goals need to be set early

EnvironmentEnvironment

Holland at a GlanceHolland at a Glance2010 Baseline and Outlook2010 Baseline and Outlook

� Population� 33,100 growing to 41,100 by 2050

� Employment� 9,767 jobs� No approved growth forecast� Optimistic estimates 6000 to 8,500 in next decade

� Residential � 7,433 Single family detached homes

© Garforth International llc

� 7,433 Single family detached homes� 5,125 Multi-family homes / Row houses / Duplexes� 15.4 M sq ft total

� Non-residential and Industry� 6.7 M sq ft Offices and Retail� 4.5 M sq ft Institutional and Recreation� 12.6 M sq ft Industrial with substantial growth

� Transportation� 280,000,000 vehicle miles travelled� Cars, trucks, SUVs ~ 92%

CEP Goals� Lower cost energy than neighbouring communities� Highly reliable electricity supply from local sources

Holland Community Energy PlanHolland Community Energy Plan2011 to 2050 Candidate Goals2011 to 2050 Candidate Goals

Energy MissionEnhance City attractiveness to investors, businesses and residents

through cost effective, reliable clean energy supply

Energy MissionEnhance City attractiveness to investors, businesses and residents

through cost effective, reliable clean energy supply

© Garforth International llc

� Highly reliable electricity supply from local sources� Industrial Energy Service tailored to investors’ needs� Flexibility to meet changing technologies, legislation, fuel

costs and other market conditions� Meet commitment to the U.S. Conference of Mayors

Climate Protection Agreement� Be a leader in developing regional energy productivity

strategy

� Energy efficiency – If you don’t need it don’t use it

� Heat Recovery – It it’s already there – use it

CEP Framework UsedCEP Framework UsedHolland Loading OrderHolland Loading Order

© Garforth International llc

� Renewable energy – If it makes sense, go carbon free

� Energy distribution – Invest where it makes sense

Integrated Approach Integrated Approach –– Tailored for HollandTailored for Holland

City of Holland BaselineCity of Holland BaselineEnergy Profile ~ estimated $135 MEnergy Profile ~ estimated $135 M

Primary Energy / Fuel 20109,898,000 MMBtue / 2,900,000 MWhe

© Garforth International llc

340 340 MMBtuMMBtu ee / 100 / 100 MWhMWhee for each Residentfor each Resident

by type by sector

City of Holland Base Line City of Holland Base Line Carbon FootprintCarbon Footprint

2010 Greenhouse Gas Emissions792,500 metric tons / 873,600 short tons CO2e

© Garforth International llc

24 metric tons for each Resident24 metric tons for each Resident

by type by sector

Greenhouse Gas EmissionsGreenhouse Gas EmissionsProxy for Energy PerformanceProxy for Energy Performance

� Energy use with fossil fuels is the main source of greenhouse gas emissions

� Greenhouse gas emissions are a widely used metric for overall energy productivity

© Garforth International llc

� GHG emissions reflect both energy efficiency and carbon-content of fuels

� Carbon dioxide-equivalent is the measure and CO2e per capita allows benchmark comparisons

Greenhouse Gas IndicatorsGreenhouse Gas IndicatorsMetric Tons / CapitaMetric Tons / Capita

National Municipal

BaselineGoal

© Garforth International llc

What should be 2050 Framing Goal?What should be 2050 Framing Goal?

2050 2050 -- GHG/Capita Goal SettingGHG/Capita Goal SettingBackgroundBackground

� Base Case� Current trajectory would be approaching 37 mt/capita� Roughly a 50% increase

� Climate Protection Agreement� About 20 to 22 mt/capita by 2012� No Kyoto 2050 target yet

� Draft US Federal legislation� About 4 mt/capita by 2050

© Garforth International llc

� About 4 mt/capita by 2050� About same as UNFCCC guidelines

� Comparable Benchmark City - Mannheim� High industrial component� Mostly coal fired electricity � About 11 mt/capita Baseline with 9 mt target by 2020

� Global Best-Practice Cities – Scandinavia� Comparable climates� Range 3mt to 6 mt/capita (Stockholm,Helsinki,Copenhagen)

Suggested Framing Goal ~ 10 mt/capitaSuggested Framing Goal ~ 10 mt/capita

Greenhouse Gas EvolutionGreenhouse Gas EvolutionMetric Tons / CapitaMetric Tons / Capita

© Garforth International llc

10 mt/capita Goal 10 mt/capita Goal –– Challenging but AchievableChallenging but Achievable

Baseline Energy Demand 2010Baseline Energy Demand 2010

© Garforth International llc

Total Energy Demand – Baseline 2010Total Energy Demand – Baseline 2010

Base Case Base Case Energy Demand 2050Energy Demand 2050

© Garforth International llc

Total Energy Demand – Base Case 2050Total Energy Demand – Base Case 2050

Baseline GHG Emissions 2010Baseline GHG Emissions 2010

© Garforth International llc

GHG-Density – Baseline 2010GHG-Density – Baseline 2010

Base Case GHG Emissions 2050Base Case GHG Emissions 2050

© Garforth International llc

GHG-Density – Base Case 2050GHG-Density – Base Case 2050

Energy Supply OutlookEnergy Supply Outlook2010 to 2050 Base Case2010 to 2050 Base Case

2,000,000

2,500,000

7,000,000

8,000,000

9,000,000

10,000,000

Base Case Energy Supply2010 Through 2050

© Garforth International llc

0

500,000

1,000,000

1,500,000

2,000,000

0

1,000,000

2,000,000

3,000,000

4,000,000

5,000,000

6,000,000

7,000,000

2010 2015 2020 2025 2030 2035 2040 2045 2050

MW

h pe

r ye

ar

MM

Btu

per

yea

r

Transportation Natural Gas Other electricity Electricity for Cooling

Battery Cluster GrowthBattery Cluster Growth

Community Energy Efficiency & Conservation Community Energy Efficiency & Conservation Strategy Plan (CEP)Strategy Plan (CEP)

Creating a Globally Competitive Community

© Garforth International llc

May 4th, 2011City of Holland, Michigan

Future Scenarios

CEP Scenario ACEP Scenario AHome and BuildingsHome and Buildings

� All Buildings� 45% of all energy use in City� Efficient renovation of 2.6% of building stock per year� New construction more efficient - 50% of current code by 2050� Selective densification

� Home and Building Energy Performance Labeling� “Aggressive” voluntary approach from 2011� Use ASHRAE/EU approach

� Single Family Homes

© Garforth International llc

� Single Family Homes� Standardized renovation packages financed by owner & City or HBPW

� 2013 to 2033 – “Moderate” package – 53% efficiency � 2034 to 2050 – “High efficiency” package – 66% efficiency � Facilitated by neighbourhood or other community groups

� AC and Refrigerator exchange programs� Non-residential, Large MFH and Retirement Communities

� Public buildings and churches act as living examples� Early adopters of Energy Performance Labeling� Equal focus on both efficient operation and construction� Energy master planning – clusters; major renovations; large

developments

Systematically Raise EfficiencySystematically Raise Efficiency

Energy Energy Performance Performance LabelingLabeling

� Low-cost performance validation tool

� Available when sold or rented

� Display in public buildings

© Garforth International llc

� Display in public buildings� Independent certification� Access to discount

financing� Voluntary or mandatory

approaches possibleBasis for Market Driven Improvement Basis for Market Driven Improvement

Holland Single Family HomesHolland Single Family HomesStandard Efficiency PackagesStandard Efficiency Packages

60

70

80

90

100

SFH-D - Total energy consumption [kBtu/sf]

60

70

80

90

100

SFH-D - Total energy consumption [kBtu/sf]

© Garforth International llc

0

10

20

30

40

50

North East Average Holland Baseline 2050 Moderate 2050 Passive

IECC 2006

IECC 2009

IECC 2012

0

10

20

30

40

50

North East Average Holland Baseline 2050 Moderate 2050 Passive

IECC 2006

IECC 2009

IECC 2012

Example of “Efficiency” Loading OpportunityExample of “Efficiency” Loading Opportunity

Single Family Homes Single Family Homes –– Status 2030Status 2030Shared Benefits Shared Benefits

� 7.433 SFH ~ 70% of all Residential area� 85% Pre-1980 Code and inefficient� Rate: 200 to 250 homes/year� “Moderate” package ~ $28K

� 53% efficiency gain� Windows-insulation-weatherization-furnace-AC-controls

© Garforth International llc

� Windows-insulation-weatherization-furnace-AC-controls

� By 2030 – 4,500 units renovated ~ $125M max� Benefit for HBPW

� 10 to 15 MWel Peak Demand Reduction� Avoided generation investment

� Benefit for homeowner� Reduced energy costs � Reduced risk from future energy price increases� Probable property value enhancement

Residential Efficiency OpportunityResidential Efficiency OpportunityGaining National FocusGaining National Focus

© Garforth International llc

One Fifth of all US Energy ConsumptionOne Fifth of all US Energy Consumption

CEP Scenario ACEP Scenario AIndustrial and City Energy ServicesIndustrial and City Energy Services

� Tailored Industrial Energy Services� 20MW CHP phased with Battery Cluster growth� District heating services using CHP, existing boilers and waste heat� Environmental services for Battery Cluster for VOC elimination*� Additional utility and efficiency services tailored to investors’ needs � Up to 1.0 % efficiency/year based on corporate programmes

� District Heating

© Garforth International llc

� District Heating � Develop district heating services north from 24th Street� “Anchor tenants” – Hope College / Hospital / Aquatic Center / City� Snow melt services as option in heating service package

� City Energy Supply� Maintain existing solid fuel plant through 2050� Add 55MW CCGT De Young Site in three phases by 2026� Configure CCGT to supply District Heating � “Green Power” sourcing Landfill (10MW)

*Turbine combustion air

Extended Opportunities for HBPWExtended Opportunities for HBPW

District HeatingDistrict Heating

� Operated by HPBW� Serve higher density areas� Buildings and Apartments � Network of insulated pipes

© Garforth International llc

� Network of insulated pipes� Multiple supply sources

� Combined Heat & Power� Boilers/Furnaces� Biomass� Waste heat recovery

Widely deployed Widely deployed -- proven technologyproven technology

Centralized supply and delivery� Heating� Domestic hot water

Centralized supply and delivery� Heating� Domestic hot water

Distric HeatingDistric HeatingInstallation elementsInstallation elements

© Garforth International llc

CEP Scenario ACEP Scenario ATransportation and Enabling StrategiesTransportation and Enabling Strategies

� Transportation� Efficiency gains from market evolution

� Revised Federal CAFÉ Standards� Weight reduction from new materials � Trend to smaller vehicles� Drive-train efficiency increases

� Efficiency gain from urban design and city services� Modest densification combined with mixed use� Snow melt extends use of walkable neighborhoods

© Garforth International llc

� Snow melt extends use of walkable neighborhoods� Opportunity for experimentation

� Biodiesel / Ethanol� Tied with economic development / University

� Training, Education and Outreach� In development

� Economic Development Support� In development

� Incentives, Regulatory, Business Models� In development

CEP Scenarios B and CCEP Scenarios B and C

� Scenario B� CEP Scenario A plus…� 24MW of Solar PV to eliminate summer peak –

start in 2012 complete by 2050� Add 20MW Biomass Generating Block after 2030

using bio-gasification

© Garforth International llc

using bio-gasification� Blend bio-gas/natural gas starting in 2013 and

leveling off at 10% by 2023 for CHP and CCGT� Add 37 MWnom Wind by 2020

� Scenario C� CEP Scenario B with …� Add 70 MW Solid Fuel with 30% biomass by 2050� CCGT not implemented

All Scenarios Focus on EfficiencyAll Scenarios Focus on Efficiency

Scenario CScenario CBiomass/Coal Biomass/Coal FFuel Mixuel Mix

� Biomass Content� Woodchips for about 21MWel (30% of 70MW)� Energy content 7 MBtu/lb (4.5 kWhe/kg)� Assume 33% efficiency and 7,500 hours/year

� Fuel Needs

© Garforth International llc

� Fuel Needs� 15.5 US tons (14 metric tons)/hour� 116,000 US tons/year (106,000 metric tons)/year

Scale ProjectsScale ProjectsJump Starts ImplementationJump Starts Implementation

© Garforth International llc

Scale ProjectsScale ProjectsSelection CriteriaSelection Criteria

� High probability of being implemented

� Manageable number of participants

� Large enough for integrated energy solutions � New business models possible� Efficiency levels� Distribution – heating, cooling, power, other..

© Garforth International llc

� Distribution – heating, cooling, power, other..� Distributed clean and renewable supplies� Smart micro-grids…

� Economically, socially, environmentally and operationally attractive

� Future linkage to other Scale Projects

JumpJump--start the implementation processstart the implementation process

Scale Project 3 : Hope College Campus

Scale Project 2 : Historic District Single Family

Neighborhood

Scale Project 4 : High School / Hospital / Aquatic Center

© Garforth International llc

Scale Project 1 : Industrial Park Integrated Energy Services

Hospital / Aquatic Center

Recommended Scale Projects

32

Single Family Homes RenovationSingle Family Homes RenovationPossible Approach Possible Approach –– Scale Project 2Scale Project 2

� Evaluate implementation approach with SP� Historic District Single Family Neighborhood

� Historic neighborhood with about 150 homes

� Approach� Develop neighborhood energy plan with

neighborhood association, City and HBPW

© Garforth International llc

neighborhood association, City and HBPW� Renovation at least to “moderate” package level� Evaluate near-passive/aggressive renovation level� Develop standardized financing options� Evaluate low-temp District Heating (“geothermal”)� Implement and adjust based on experience� Parallel education of wider community

� Roll out to other neighborhoods

Scale Project 5: Initial District HeatingScale Project 5: Initial District HeatingNodes for Downtown SystemNodes for Downtown System

City Hall

Freedom Village

© Garforth International llc

Hospital

Aquatic Center

High SchoolHigh

School

Heinz Plant

Library

Hydro Automotive Structures

Hope CollegeBoiler House

DH-Pipe Central Ave renewalDH Main connectionsDH Connection Scale project 4 DH optional connectionCurrent snowmelt

Impact of Impact of ScenariosScenariosTotal City Fuel Mix Total City Fuel Mix -- 2010 to 20502010 to 2050

© Garforth International llc

Impact of ScenariosImpact of ScenariosElectricity Fuel Mix Electricity Fuel Mix -- 2010 to 20502010 to 2050

4,000,000

5,000,000

6,000,000

Fuel Mix Electricity Generation City of Holland

© Garforth International llc

0

1,000,000

2,000,000

3,000,000

Baseline 2010 Base Case 2050

Scenario A 2050

Scenario B 2050

Scenario C 2050

Fue

l MW

h pe

r y

ear

Solid Biomass

Biogas/Landfill gas

Fuel Oil

Natural Gas

Coal

20102010--2050 Results2050 ResultsGHG Emissions TotalGHG Emissions Total

© Garforth International llc

20102010--2050 Results2050 ResultsGHG Emissions per CapitaGHG Emissions per Capita

© Garforth International llc

CEP CEP ScenariosScenariosBenefits for HBPWBenefits for HBPW

� Increased fuel flexibility� Coal, gas, bio-gas, bio-mass ….� Decrease of fuel price risk � Reduced carbon cost risk

� Additional revenues� Heating, domestic hot water, snow melt� Environmental services� Potential industrial energy management services

© Garforth International llc

� Potential industrial energy management services� Capacity for sale outside Holland � Configured for PV peak reduction

� Reduced infrastructure and operating cost� Decision timed based on markets costs� Actively seek incentives

� Future sales of municipal energy service skills to other municipalities

� Higher returns

CEP CEP ScenariosScenariosBenefits Benefits for City of for City of HollandHolland

� High-quality industrial jobs� Local labor opportunity

� SFH upgrade programme� Ongoing energy and environmental services� PV Installation� Refrigerator and AC buyback

© Garforth International llc

� Higher property values and sales taxes � Improved “dividends” from HBPW

� Added value businesses in Holland� Future added-value businesses outside Holland� Reduced cost of capital

� Reduction of GHG emissions� Increased attractiveness for all residents

Benefits of Winning!Benefits of Winning!CompetitiveCompetitive--SustainableSustainable--FlexibleFlexible

ResidentResidentResidentResident

•Lower utility costs•Improve resale value•Enhance employment•Improve quality of life

•Lower utility costs•Improve resale value•Enhance employment•Improve quality of life

•Environmental impact•Community growth•Attractive development•Competitive energy services

•Environmental impact•Community growth•Attractive development•Competitive energy services

•Tailored energy•Lower costs•Sell waste energy•Reduced CO2 risks

•Tailored energy•Lower costs•Sell waste energy•Reduced CO2 risks

IndustryIndustryIndustryIndustry

© Garforth International llc

CommercialCommercialCommercialCommercial

•Reduced costs•Rental values•Low vacancy•Productivity

•Reduced costs•Rental values•Low vacancy•Productivity

BanksBanksBanksBanks

•Collateral Value•Credit worthiness•Collateral Value•Credit worthiness

•Improve quality of life•Improve quality of life

DeveloperDeveloperDeveloperDeveloper

•Premium prices•Low carrying time•Reduced investment

•Premium prices•Low carrying time•Reduced investment

•Competitive energy services•New business opportunities•Competitive energy services•New business opportunities

UtilitiesUtilitiesUtilitiesUtilities

•Higher returns•Emissions reduction•Customer intimacy•Diversification

•Higher returns•Emissions reduction•Customer intimacy•Diversification

•Reduced CO2 risks•Reduced CO2 risks

AcademicAcademicAcademicAcademic

•Sustainable curriculum•Lower costs•Student magnet•Global network

•Sustainable curriculum•Lower costs•Student magnet•Global network

Community Process to Refine PlanCommunity Process to Refine PlanKey MilestonesKey Milestones

Milestone / Activity Dec Jan Feb Mar Apr May Jun Jul AugContract AwardTask Force & Community - Kick off meetingsData Gathering – City/UtilityEnergy and Carbon BaselineNeighborhood Scale Projects short listDevelop Initial RecommendationsTask Force – Initial Recommendations

© Garforth International llc

City Council – Initial RecommendationsTown Hall Meeting – Initial RecommendationsIntegrate feedback and adjust scenariosFull EECSPT team – Preliminary RecommendationsDrafting Final ReportTask Force – Draft Final ReportCity Council – Draft Final ReportIntegrate feedbackFinal Report voted on by City CouncilCommunity Town Hall Meeting – Next StepsLaunch EECSP Action Plan